+ All Categories
Home > Documents > P19 - Critical Path Method0

P19 - Critical Path Method0

Date post: 07-Apr-2018
Category:
Upload: wasakc
View: 230 times
Download: 0 times
Share this document with a friend

of 23

Transcript
  • 8/6/2019 P19 - Critical Path Method0

    1/23

    Critical Path Method (CPM)

  • 8/6/2019 P19 - Critical Path Method0

    2/23

    2

    Critical Path Method (CPM)

    CPM is a network diagramming technique used to

    predict total project duration.

    A critical path for a project is the series ofactivities that

    determines the earliest time by which the project can becompleted.

    The critical path is the longest path through the network

    diagram and has the least amount ofslack orfloat.

    Slackorfloat is the amount oftime an activity can be

    delayed without delaying a succeeding activity or the

    project finish date.

  • 8/6/2019 P19 - Critical Path Method0

    3/23

    3

    Calculating the Critical Path

    Develop a good network diagram.

    Add the duration estimates for all activities on

    each path through the network diagram.

    The longest path is the critical path.

    Ifone or more ofthe activities on the critical path

    takes longer than planned, the whole project

    schedule will slip unless the project manager takes

    corrective action.

  • 8/6/2019 P19 - Critical Path Method0

    4/23

    4

    More on the Critical Path

    The critical path does notnecessarily contain all the criticalactivities; it only accounts for time.

    There canbe more than one critical path ifthe lengths oftwo or

    more paths are the same.

    The critical path can change as the project progresses.

  • 8/6/2019 P19 - Critical Path Method0

    5/23

    Network Representation

  • 8/6/2019 P19 - Critical Path Method0

    6/23

    The Network

    Consider the following list ofactivities

  • 8/6/2019 P19 - Critical Path Method0

    7/23

    Which one is the correct network representation

  • 8/6/2019 P19 - Critical Path Method0

    8/23

    CPM Computations

    We define the followings

  • 8/6/2019 P19 - Critical Path Method0

    9/23

    Forward Pass

    A forward pass through the network diagramdetermines the early start and finish dates.

    We visit all nodes from node 1 to the last one to

    determine the earliest occurrence time

  • 8/6/2019 P19 - Critical Path Method0

    10/23

    Backward Pass

    A backward pass determines the late start and finishdates.

    We visit all nodes again, but backward to

    determine the latest occurrence time

  • 8/6/2019 P19 - Critical Path Method0

    11/23

    Example

  • 8/6/2019 P19 - Critical Path Method0

    12/23

    Forward Pass

  • 8/6/2019 P19 - Critical Path Method0

    13/23

    Backward Pass

  • 8/6/2019 P19 - Critical Path Method0

    14/23

    Example 1. Find the critical path for the following

    project

    Activity Description Estimated

    Duration (Days)

    Predecessor

    A Evaluate current technology

    platform

    2 None

    B Define user requirements 5 AC Design Web page layouts 4 B

    D Set-up Server 3 B

    E Estimate Web traffic 1 B

    F Test Web pages and links 4 C,D

    G Move web pages to production

    environment

    3 D,E

    H Write announcement of intranet

    for corp. newsletter

    2 F,G

    I Train users 5 G

    J Write report to management 1 H,I

  • 8/6/2019 P19 - Critical Path Method0

    15/23

    15

    Example 2: Determining the Critical Path for Project X

  • 8/6/2019 P19 - Critical Path Method0

    16/23

    Example 6-5.2: Critical activities

  • 8/6/2019 P19 - Critical Path Method0

    17/23

    Extra

  • 8/6/2019 P19 - Critical Path Method0

    18/23

    18

    Construction ofthe Time Schedule

    Critical Vs Non critical activities

  • 8/6/2019 P19 - Critical Path Method0

    19/23

    19

    Construction ofthe Time Schedule

    Free float is the amount oftime an activity can be

    delayed without delaying the early start ofany

    immediatelyfollowing activities.

    Total float is the amount oftime an activity canbe

    delay

    edfrom its earl

    ystart without dela

    ying theplanned project finish date.

  • 8/6/2019 P19 - Critical Path Method0

    20/23

    Example 6.5

  • 8/6/2019 P19 - Critical Path Method0

    21/23

    Red Flagging rule.

  • 8/6/2019 P19 - Critical Path Method0

    22/23

    22

    Buffers and Critical Chain

    A buffer is additional time to complete a task.

    Critical chain scheduling removes buffers from individualtasks and instead creates:

    A project buffer or additional time added before the projectsdue date.

    Feeding buffers or additional time addedbefore tasks on thecritical path.

  • 8/6/2019 P19 - Critical Path Method0

    23/23

    23

    Importance ofUpdating Critical Path Data

    It is important to update project schedule

    information to meet time goals for a project.

    The critical path may change as you enter actual

    start and finish dates.

    Ifyou know the project completion date will slip,negotiate with the project sponsor.


Recommended