NHAI – PIU (Rohtak)
(Package No. IE/BOT-II/NH-10/HRY/004)
Intercontinental Consultants and Technocrats Pvt. Ltd. Ho.No.354/29,Sky Hawk Banquet Hall, Tilak Nagar, Rohtak,Haryana-124001
Ph. 01262-655291,655292, Fax.No. 01262-295902, E-mail:[email protected]
in
association
with
ICT/IC/NHAI/IND/NH-10/TL-8321 6th April 2015
Independent Engineering Service for 4/6 Laning of NH-10 from Delhi/Haryana Border to RohtakIn the state of Haryana On BOT basis Under NHDP PhaseIII(A)
Project No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015
in
association
with
CHAPTER TABLE OF CONTENTS Page No.
1.0 EXECUTIVE SUMMARY 1-7
1.1 PROGRESS SUMMARY 1
1.2 CONCESSIONAIRE’S WORK PROGRAMME 1
1.3 HANDING OVER OF SITE 1
1.4 SHIFTING OF UTILITIES 1
1.5 FOREST CLEARANCE AND REMOVAL OF TREES 1
1.6 DESIGN REVIEW CARRIED OUT BY TL/IE DURING THE MONTH 1
1.7 QUALITY CONTROL 2
1.8 MAINTENANCE OF EXISTING ROAD 2
1.9 SAFETY MEASURES 3-4
1.10 FORCE MAJEURE EVENT DURING THE MONTH 5
1.11 ISSUE OF DELAYED COMPLETION 5
1.12 ISSUES OF CONCERN 5-7
2.0 PROJECT DETAILS 8-9
2.1 PROJECT BACKGROUND 8
2.2 STRETCHES OF PROJECT HIGHWAY 8
2.3 MAIN SCOPE OF WORK 9
2.4 LOCATION MAP 10
3.0 CONTRACT DETAILS 11
4.0 ROLE OF INDEPENDENT ENGINEER 12-14
4.1 DESIGN REVIEW STAGE 12
4.2 CONSTRUCTION STAGE 12-13
4.3 OPERATION AND MAINTENANCE STAGE 14
4.4 ORGANIZATION CHART OF IE 15
5.0 WORK PROGRESS 16-28
5.1 OVERALL PHYSICAL PROGRESS 16
5.2 DETAILS OF WORK CARRIED OUT DURING THE MONTH 16-28
6.0 HANDING OVER OF SITE 29
7.0 SHIFTING OF UTILITIES 29
8.0 FOREST CLEARANE AND REMOVAL OF TREES 29
9.0 DESIGN REVIEW 30-31
10.0 MAINTENANCE OF EXISTING ROAD 32
11.0 SAFETY MEASURES 33-34
12.0 WEATHER REPORT 35
13.0 QUALITY REVIEW REPORT 36-46
13.1 QUALITY ASSURANCE/MATERIALS TESTING REPORT 36
13.2 Details of Non-Conforming Product Notifications 37-46
14.0 CORRESPONDENCE BETWEEN I. E. & THE CONCESSIONAIRE 47
15.0 FORCE MAJEURE EVENT 48
16.0 REDRESSAL OF GRIEVANCES 49
17.0 APPENDIX
17.1 DETAILS OF MOBILIZATION OF IE’S STAFF 50
17.2 DETAILS OF THE CONCESSIONAIRE’S SITE STAFF (SPV) 51
17.3 QUALITY ASSURANCE RECORD 52-54
Independent Engineering Services for 4/6 Laning of Delhi/Haryana Border to Rohtak
In the state of Haryana On BOT basis Under NHDP Phase III (A) Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015
1
in association
with
1.0 EXECUTIVE SUMMARY
1.1 PROGRESS SUMMARY
Description Up to Previous Month This Month
Cumulative
As per Concessionaire’s Programme 100% - -
As per actual 94.33% 0.00% 94.33%
The Concessionaire has started the construction of balance works of the project. The works of balance service roads in Bahadurgarh Bypass are being carried out including some other works such as fixation of sign boards, etc. The works of fixation of bearings and launching of steel girders in the track span of ROB at Ch. 86+177 have been completed by the Concessionaire. Presently, the works of erection of intermediate cross girders and cross bracing are being carried out by the Concessionaire. The Concessionaire has been requested to also carry out works related to safety and maintenance of project highway including to take actions to prevent encroachment of NHAI land. The progress of works need to be expedited by the Concessionaire to complete the project without any more further delays. The project can be completed within a period of 3-4 months if the Concessionaire executes the works with proper planning and by providing adequate resources.
1.2 CONCESSIONAIRE’S WORK PROGRAMME:
The Concessionaire had committed during meeting held at RO Office, Chandigarh on 16th January 2015 under the Chairmanship of Mr. B. S. Singla, CGM (T), that the balance works including ROB at Ch. 86+177 will be completed by 31st March 2015. The Concessionaire has been asked to submit the work programme to complete the entire project. The Concessionaire has also been asked to the expedite the completion of the balance works of entire project from Km. 29+650 to Km. 85+372 such as balance service road, slip roads, truck lay byes, road signages & safety appurtenances, road markings, balance works of structures, balance toll plaza works, highway lighting works, MBCB, drainage works, bus bays, ROB at Rohtak bypass to make the Rohtak bypass operational. The Concessionaire had also been advised to submit the consolidated case for extension of time of project at the earliest but the same has not been received up till now.
1.3 HANDING OVER OF SITE:
Land in the total length of the project has been handed over.
1.4 SHIFTING OF UTILITIES:
Completed.
1.5 FOREST CLEARANCE AND REMOVAL OF TREES:
Completed
1.6 DESIGN REVIEW CARRIED OUT BY TL/IE DURING THE MONTH:
Design of roads and structures had already been completed.
Independent Engineering Services for 4/6 Laning of Delhi/Haryana Border to Rohtak
In the state of Haryana On BOT basis Under NHDP Phase III (A) Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015
2
in association
with
1.7 QUALITY CONTROL:
The fixation of bearings for ROB at Ch. 86+177 (in track span) has been completed by the Concessionaire. These works were checked by Railway Authorities as well as by the representatives of Independent Engineer and PIU-NHAI/Rohtak. The service road works were also inspected regularly by the representatives of the Independent Engineer and necessary directions to ensure the proper levels and for quality of materials were issued to the Concessionaire and subsequently follow ups are being made at site to ensure compliance of these observations.
1.8 MAINTENANCE OF PROJECT HIGHWAY:
1.8.1 Status of Maintenance: The works have been started by the Concessionaire, however, the maintenance and repair is yet
to be carried out by the Concessionaire.
1.8.2 Maintenance measures required to be taken by the Concessionaire:
Following Maintenance measures are still required to be taken by the Concessionaire.
i. The slip roads at every grade separators & VUPs require extensive repairs.
ii. Proper drainage measures are required to be taken at slip roads & in the stretch where water is accumulated on account of reverse slope.
iii. Rain cuts at two three places up to Km 85+000 are require to be attended on priority basis.
iv. Restoration of pavement affected due to rain cuts in Rohtak Bypass at the approaches of
(a) Minor Bridge at Ch. 88+393 (both sides)
(b) VUP at Ch. 91+131 (both sides)
v. Restoration of pavement due to rain cuts in scattered reaches from Ch. 86+700 to Ch. 93+140.
vi. Slope protection work is yet to be taken up where height of embankment is more than 3.0m. particularly at the approaches of structures.
vii. The repair of strip seal expansion joints of various locations. The list of damaged strip seal expansion joints has been forwarded already to the Concessionaire.
viii. Rectification of defects noted in the structures and for which the list of the same has already been submitted to the Concessionaire.
ix. The sealing of gaps in the RCC crash barrier panels at the grade separator at Ch. 33+445, Ch. 35+643, Ch. 38+440, Ch. 40+107, etc.
Independent Engineering Services for 4/6 Laning of Delhi/Haryana Border to Rohtak
In the state of Haryana On BOT basis Under NHDP Phase III (A) Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015
3
in association
with
1.9 SAFETY MEASURES:
The Concessionaire must address required safety measures by deploying safety teams to look after
the work of safety measures on the project highway. The cleaning of chocked/non-functioning pipe &
box culverts is required to be carried out by the Concessionaire for which immediate efforts are
required to be made by the Concessionaire. The main points of concern are as follows.
(a) Unauthorized median cuts:
Existing Illegal cuts in median indicated in previous reports have not been closed and as such
present status remains same as given below:
(i) Km 31+500 (Sector – 9)
(ii) Km 50+950 (Rohad Village)
(iii) Km 52+190 (Near Toll plaza diversion)
(iv) Km 69+540
(v) Km 77+800 (Petrol Pump)
(vi) Km 83+450
(vii) Km 85+100
The above mentioned median cuts are on the stretch which has been opened to traffic (i.e. from
Ch. 29+650 to Ch. 85+372). These median openings are required to be closed immediately to
avoid accidents. Similar action in the further stretch from Km 85+372 to Km. 93+140 should also
be taken accordingly.
(b) Fixing of Road Signs
Since the stretch from Km. 29.650 to Km. 85.372 has been opened to traffic so it has become
very necessary to fix the sign boards particularly at the junctions. Following are the junctions
which need immediate attention of the Concessionaire:
(i) Junction at Km. 68+400
(ii) VUP at Km. 69+600
(iii) Clover leaf at Km. 76+076
(iv) VUP at Km. 79+207
(v) Grade Separator at Km. 85+372
Independent Engineering Services for 4/6 Laning of Delhi/Haryana Border to Rohtak
In the state of Haryana On BOT basis Under NHDP Phase III (A) Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015
4
in association
with
(c) Black Spots
Though the project highway has been constructed as per required specification & design but the
following spots except the illegal cuts are still existing at present which may also prove as
accident prone areas in future in the absence of further improvement .
(i) At grade junction at Km 35+350
Junction has been developed but the provision of a CUP of 4.5 m height will minimize the
accidents in view of height of embankment at this location.
(ii) At grade junction at Km 36+500
Provision of VUP at this location in place of at grade junction will bring the complete safety in
view of Bahadurgarh-Badli traffic and close vicinity of village Nayagaon.
(iii) At grade junction at Km 56+600
Provision of VUP is required at this location in place of at grade junction to make this junction completely safe in view of Sampla-Beri cross road at curvature of MCW and nearby adjacent Tehsil building Rest house and Girls College.
(d) Recommendations of Independent Engineer which have not been acted upon by the Concessionaire:
The Construction of balance works has been taken up by the Concessionaire but the following observations made by the IE are yet to be complied with by the Concessionaire.
(i) Shifting of electric lines crossing project highway on bamboos erected in median and shoulder areas in the stretches from Km. 67+500 to Km. 67+875 (median), Km. 68+100 to Km. 68+350 (RHS), Km. 89+720 to Km. 90+150 (RHS).
(ii) Protection of slopes at the approaches of structures on Rohtak Bypass and high embankment stretches.
(iii) Protection of site from encroachment, etc is required to be addressed as per clause 10.5 of the agreement. The Concessionaire has been directed several times through written and verbal directions however concrete steps are required to be taken by the Concessionaire in this regard.
(iv) Land plan which is a basic record to be maintained has not been submitted by the Concessionaire despite of asking him so many times.
Independent Engineering Services for 4/6 Laning of Delhi/Haryana Border to Rohtak
In the state of Haryana On BOT basis Under NHDP Phase III (A) Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015
5
in association
with
1.10 FORCE MAJEURE EVENT DURING THE MONTH:
None
1.11 ISSUE OF DELAYED COMPLETION:
The cure period notice was issued to the Concessionaire by the NHAI vide letter No.
NHAI/RO/CHD/11011/PD-RTK/DLH-RTK/NH-10/2232, dated 12th December 2013 in view of various
issues of slow progress to complete the works timely and failure on the part of the Concessionaire
towards other issues such as safety, maintenance & protection of site from encroachment, etc. The
Concessionaire vide their letter No. WHHPPL/NHAI/2014/102/HN002/CMO/D/230, dated 06th February
2014 has given detailed reply on the cure period notice and assured that they will complete the work
and as such no further action was taken.
1.12 ISSUES OF CONCERN:
(i.) ROB at Km 86+177
The factors contributing to the delay in this ROB and status of work are described in detail as
below.
a) The launching of girders and deck slab casting in the obligatory span of ROB at Ch. 86+177
could not be carried out due to dispute in which Railway were demanding 30% capitalized
cost as maintenance charges before approval of traffic block. The Concessionaire refused
to deposit the capitalized maintenances cost to Railway because the maintenance has to be
carried out by the Concessionaire as per Concession Agreement. This issue was resolved
on 20th September 2013 after intervention of MORTH and NHAI. The Railway Authority
confirmed on 17th February 2014 for depositing of only supervision charges on the
capitalized cost of maintenance of this ROB.
b) The Railway Department asked the Concessionaire on 3rd September 2013 to comply the
observations regarding quality of steel girders for the track span before getting the traffic
block for execution of launching of steel girders and the compliance of these observations
could not be made by the Concessionaire in time. The Railway Department again asked on
14th December 2013 to comply with the observations regarding quality of fabrication of
girders and concrete, proper stacking of girders, etc.
The Concessionaire submitted on 23rd December 2013 that the observations on quality of
concrete shall be complied by 31st December 2013. Regarding additional butt welds, the
Concessionaire pointed out that the butt welding is permitted for joining two plates as per
Independent Engineering Services for 4/6 Laning of Delhi/Haryana Border to Rohtak
In the state of Haryana On BOT basis Under NHDP Phase III (A) Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015
6
in association
with
codal provisions of IRS Welded Bridge and IRC: 24-2001.The Concessionaire has also
informed that they had to do butt welding because of non-availability of 12.5m plate lengths
at the time of fabrication and the appropriate NDT testing was performed and inspection
clearance for obligatory Span was taken from the concerned representative of NW Railway.
c) The Railway Department further intimated on 8th January 2014 that none of the items of
inspection note sent vide their letter dated 5th September 2013 has been complied during
last 4 months. Regarding butt welding of girders, it was pointed out by the Railway that the
Concessionaire has provided additional butt weld in the web plate using shorter plates
which is not as per approved drawing and therefore, the plea of the Concessionaire for non-
availability of longer plates is not acceptable. The NWR asked that the Concessionaire
should be directed to fabricate the end portion of these girders as per approved drawings
and to submit the programme of fabrication of girders. The Railway also asked to submit the
QAP and WPSS for fabrication of girders as well as for bearings. Subsequently, this issue
was resolved during meetings held with Railway Authorities at NWR Jaipur.
d) The Railway Authority further asked the Concessionaire on 18th September 2014 to provide
and install the bearings before issuance of traffic block. The Concessionaire procured the
bearings on 20th November 2014 but the installation of the same is yet to be done by the
Concessionaire.
e) The Concessionaire had submitted the traffic working order including activity schedule of inspection & fixation of bearings on 22nd November 2014 for processing and sanctioning of the case for issuance of traffic block for launching girders in obligatory span of said ROB and the same was forwarded to North Western Railway by the Project Director on 25 th November 2014.
f) The North Western Railway on 16th December 2014 has again informed that the bearings have not been fixed at site although bearings were received almost one month back. The Railway has further once again intimated that the fixing of bearing and all other prerequisite like arranging of cranes, securing arrangement for cross frame etc. are must before processing the papers for sanction of Traffic Working Order and the bearings are to be fixed under supervision of the Railway Officials.
g) The period of CRS sanction was up to 31st January 2015 and the Concessionaire could not complete the fixation of bearings to get the traffic block from Railways to launch the steel girders within available period of CRS sanction up to 31st January 2015. The Project Director has requested the Railway Authorities to further extend the CRS extension up to 30th April 2015 which has been accorded by the Railway.
h) Status of work:
The fixation of bearings in track span has been completed by the Concessionaire in block
period from 21st March 2015 to 25th March 2015 and presently the work of erection of
intermediate cross girder & bracing is being carried out by the Concessionaire.
Independent Engineering Services for 4/6 Laning of Delhi/Haryana Border to Rohtak
In the state of Haryana On BOT basis Under NHDP Phase III (A) Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015
7
in association
with
(ii.) Compliance of Railway observations on ROBs at Ch. 71+580, Ch. 59+868 and Ch.
70+002:
The Concessionaire has yet to complete the balance works of these ROBs which are
requested to be carried out to comply with the observations raised by the Railway Department
for these ROBs. The Railway Department has further pointed out that these works have not
been completed by the Concessionaire yet. The Concessionaire has again been reminded to
complete the works and to submit the completion plan.
(iii.) Elevated Corridor for Metro Rail
The initial stretch of length 1.4 Km from Chainage 29+650 (start of the project) to Chainage
31+050 (start of Bahadurgarh Bypass) has been taken up by the DMRC for construction of
Elevated Corridor for Metro Rail. The stretch is having heavy traffic conditions and therefore
remains congested due to undergoing construction of Metro line. The NHAI, DMRC, HUDA,
Concessionaire are deciding to construct an underpass at junction at Ch. 31+050 to decongest
the traffic and also a four party agreement is being prepared for DMRC, NHAI, Concessionaire
& HUDA departments for this issue. The Draft agreement for this has being prepared and
being finalized by NHAI with DMRC/HUDA departments.
Iindependent Engineering Services for 4/6 Laning of NH-10 from Delhi/Haryana Border to Rohtak In the state of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
8 Monthly Progress Report: March 2015
in
association
with
2.0 PROJECT DETAILS
2.1 PROJECT BACKGROUND
The Ministry of Road Transport and Highways (MORT&H), Govt. of India has decided to take up the
development of various National Highway Corridors where the traffic intensity has increased significantly
thereby necessitating capacity fragmentation for safe and efficient movement of traffic. National Highway
No.10, (NH-10) is part of North – South Corridor. The Ministry of Road Transport and Highways
(MOSRT&H) has entrusted to the National Highways Authority of India (NHAI) the development,
maintenance and management of the National Highway No.10 including section from Km. 29.700 to Km.
87.000. The NHAI had resolved to augment the existing road from Km 29.700 to Km 87.000 on the
Bahadurgarh- Rohtak in the State of Haryana by 4/6 laning on Build, Operate and Transfer (BOT) Basis.
The Project starts at Delhi / Haryana border at Ch. 29.650 and ends at Ch. 93.140 (design chainage). The total length of the project including the two (2) Bypasses is 63.49km.
For the realization of the above-mentioned project, a Concession Agreement between the NHAI and M/s. West Haryana Highways Project Pvt. Ltd. was signed on 6th November 2007.
The commencement date of the project is 3rd May 2008 with total project duration of 24 months. The project completion date is 2nd May 2010.
Intercontinental Consultants and Technocrats (ICT) Pvt. Ltd. has been appointed as the Independent Engineer for the project. An Independent Consultancy Contract was signed on 17 th January 2008 between the NHAI and ICT.
2.2 Stretches of Project Highway
Description of stretch Chainage
Length (Km) From To
Existing Road 29+650 31+050 1.400
Bahadurgarh Bypass 31.050 44+400 13.350
Existing Road 44+400 68+400 24.000
Rohtak Bypass 68+400 93+140 24.740
Total length of Project Highway 63.490
Iindependent Engineering Services for 4/6 Laning of NH-10 from Delhi/Haryana Border to Rohtak In the state of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
9 Monthly Progress Report: March 2015
in
association
with
2.3 Main scope of work
The project highway includes the following items of work
Roadwork
Bridges
Grade Separators / Interchanges
Railway Over Bridges (ROBs)
Slab/Box Culverts
Pipe Culverts
Vehicular Underpasses
Toll Plaza
Roadside Furniture
Street Lighting
Pedestrian Facilities
Landscaping and Tree plantation
Rent Areas
Truck lay-Bys, Bus-Bays, and Bus shelters
Cattle crossing
Development of Site for Wayside Amenities
Traffic Aid Posts
Medical Aid posts
Vehicle Rescue posts
Telecom system
Highway Traffic Management System
2.4 LOCATION MAP: The Location Map is given in Fig.1 (Page-8)
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A),
Package No.IE/BOT/II/NH-10/HRY/004
Figure-1
LOCATION MAP 10 Monthly Progress Report: March 2015
in
association
with
Rohtak
Delhi/Haryana Border
Independent Engineering Services for 4/6 Laning of NH-10 from Delhi/Haryana Border to Rohtak In the state of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004)
11
Monthly Progress Report: March 2015
in
association
with
3.0 CONTRACT DETAILS
I. Name of the Project : Design, Construction, Development, Operation, Finance and Maintenance of Delhi/Haryana Border (Km29.700) to Rohtak (Km87.000) on NH-10 in the State of Haryana, under (NHDP Phase-III (A) on BOT Basis.
II. Package No : IE/BOT-II/NH-10/HRY/004
III. Name of the Concessionaire : M/s West Haryana Highways Projects Pvt. Ltd. (WHHPPL)
IV. Name of EPC : M/s Era Infra Engineering Ltd.
V. Project Cost : Rs. 486 Crores
VI. Project Limit : Ch. Km 29.650 to Ch. 93.140
VII. Signing of Concession agreement : 6th November 2007
VIII. Financial Close : 3rd May 2008 (180 days)
IX. Appointed Date : 3rd May 2008. (180 days from date of agreement)
X. Development Period : 6th Nov.2007 to 2nd May 2008
XI. Construction Period : 3rd May 2008 to 2nd May 2010. (2 Years)
XII. a) Date of Project Completion (original): 2nd May 2010.
b) Revised Project Completion Date (1st revision): 01st May 2011 (due to 365 days EOT as recommended by the Independent Engineer)
C) Revised Project Completion Date (2nd revision): 31st December 2011 (due to 240 days EOT as recommended by Independent Engineer). EOT upto 30th June 2013 was submitted by Concessionaire, however, it was advised to submit the EOT covering the period upto COD.
XIII. Concession period : 03rd May 2008 to 3rd May 2033. (25 Years)
XIV. End date of Concession period : 3rd May 2033.
The Project involves the widening and strengthening of existing 2-lane dual carriageway into 6-lane divided carriageway from start of project at design Ch.29+650 to the beginning of Bahadurgarh Bypass at Ch.31+050 with a length of 1.40 km, new construction of 4-lane Bahadurgarh Bypass from Ch.30+050 to Ch. 44+400; eccentric widening of the existing 2-lane to 6-lane divided carriageway from Ch.44+400 to Ch. 68+400, new construction of 4-lane Rohtak Bypass from Ch. 68+400 to Ch. 93+140 which skips to urban center of Rohtak; 2 Major Bridges;9 Minor Bridges; 64 nos. Slab/Box Culverts; 5 Nos. Grade Separators/Interchanges; 4Nos. Vehicular Underpasses; 67 Nos. Pipe Culverts; and Project Facilities such as Toll Plaza, Roadside Furniture, Street lighting, Pedestrian Facilities, Landscaping and Tree Plantation, Rest areas, Truck lay-Bys, Bus-Bays and Bus Shelters, cattle Crossings, Development of Site for Wayside Amentias, Traffic Aid Posts, Medical Aid Posts, Vehicle Rescue Posts, Telecom System and Highway Traffic Management system.
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
12 Monthly Progress Report: March 2015
in
association
with
4.0 ROLE OF INDEPENDENT ENGINEER
4.1 Design Review Stage
Undertake a detailed review of Drawings to be furnished by the
Concessionaire along with supporting data including the geo-technical and
hydrological investigations; characteristics of materials from borrow areas
and query sites, topographical surveys and traffic surveys.
Review any modified Drawings or supporting documents sent to it by the
Concessionaire.
Review the detailed design, construction methodology, quality assurance
procedures and the procurement, engineering and construction time
schedule sent to it by the Concessionaire.
Review and make comment on the EPC Contract or any other contract for
construction, operation and maintenance of the Project Highway.
4.2 Construction Stage
Review and make comment in respect of the Drawings, Documents and
Safety Report received by the Independent Consultant during the
Construction Period.
Review Monthly Progress Report furnished by the Concessionaire and
send comments thereon to the authority and Concessionaire.
Inspect the Construction Works and the Project Highway once every
month, and make out a report of such inspection (the “Inspection
Report”) setting forth an overview of the status, progress, quality and
safety of construction, including work methodology adopted, the materials
used and the sources.
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
13 Monthly Progress Report: March 2015
in
association
with
Require the Concessionaire to carry out tests on sample basis to be
specified by the Independent Engineer in accordance with Good Industry
Practice for quality assurance. The Independent Engineer shall issue
necessary directions to the Concessionaire for ensuring that the tests are
conducted in a fair and efficient manner, and shall monitor and review
the results thereof.
Undertake review of the progress of constructions and identify potential
delays, of any.
To make recommendation to the Authority for the suspension of
Construction Works if the Concessionaire fails to make adequate
arrangements for the safety of the workers and Users in the zone of
construction.
Issue a Completion Certificate or Provisional Certificates, as the case
may be.
Make a fair and reasonable assessment of the costs of providing
information, works and services and certify the reasonableness of such
costs for payment by the Authority to the Concessionaire.
Aid and advise the Concessionaire in preparing the Maintenance Manual.
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
14 Monthly Progress Report: March 2015
in
association
with
4.3 Operation and Maintenance Stage:
Review and make comments in respect of the Designs, Documents and safety
report.
Review the Maintenance Program furnished by the Concessionaire and send
comments to the authority and the Concessionaire.
Review the monthly status report furnished by the Concessionaire and send
comments to the authority and the Concessionaire.
Inspect the Project Highway once every month and make an O & M Inspection
Report.
Examine the request of Concessionaire for closure of any Lane (s) of the
carriageway for undertaking maintenance/repair works thereof.
Monitor and review the curing of defects and deficiencies by the Concessionaire.
Review and send comments on modifications that the Concessionaire proposes to
make on the Project Highway,
Undertake traffic sampling, as and where required by the Authority.
4.4 Organization Chart of Independent Engineer (Page – 15)
Monthly Progress Report: March 2015
15
in
association
with
NHAI
Eleazar S. Regondola
Team Leader-ICT / Sr. Highway Engineer
Brajendu Ku.
Mohanty,
Accountant
Sushil Kumar
Computer
Operator
Sharad Pratap Singh,
Steno
Chhabi Lal Sharma,
Office Boy
Manish Deshpande,
HTMS/Tolling
System Expert
James Cooper,
Road Safety Expert
P. K. Nanda,
Sr. Pavement
Specialist
Rajiv Kumar,
Sr. Quality cum Material
Expert
Sr. Bridge Design
Engineer
Prashant Dixit, Asst.
Quality & Material
Engineer
Shailendra B Singh,
Asst.Bridge Engineer Vijay Setia Asst.
Highway Engineer
Sujeet Kumar,
Environmental Engineer
Chinmaya Ku Mallick
CADD Expert
Independent Engineering Services for 4/6 Laning of Delhi/Haryana Border to Rohtak, Section of NH-10, in the state of Haryana, On NHDP Phase –III (A),
Package No. IE/BOT-II/NH-10/HRY-004
Figure -2
B. S. Chhikara, Highway
Engineer
Mehmood Sardar,
Survey Engineer
Rajeev Ku.
Makhija, Traffic
& Transportation
Expert
Adhir Ku. Pani
Electrical Engineer
Financial Expert
Mr. Vikas Goel,
Legal Expert
Chandan SIngh
Guard-1
Bhim Bahadur,
Guard-2
Bridge/ Structural Engineer
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015 16
in
association
with
la
5.0 WORK PROGRESS
5.1 Overall Physical Progress:
Description During the Month Cumulative
As per schedule - -
Actual 0.00% 94.33%
The construction of balance works is being carried out by the Concessionaire, however, the progress of balance works is required to be expedited by providing adequate resources for which the Concessionaire has been advised accordingly.
5.2 Details of Road Works carried out during the month:
Status of Road Works (Main Carriageway) as of 31st March 2015
(Length of Main Carriageway 63.490km.)
Description
Completed Length (Km.) During this month Cumulative
(LHS) (RHS) (LHS) (RHS) Average Percentage
Earthwork nil nil 62.966 62.906 62.936 99.127
Sub grade nil nil 62.966 62.729 62.848 98.988
G.S. B. nil nil 62.889 62.729 62.809 98.927
WMM 1st nil nil 62.856 62.639 62.748 98.831
WMM 2nd nil nil 62.797 62.626 62.712 98.774
DBM 1st nil nil 62.776 62.587 62.682 98.727
DBM 2nd nil nil 62.775 62.577 62.676 98.718
B. C. nil nil 61.111 60.908 61.010 96.093
Status of Road Works (Service Road) as of 31st March 2015
(Length of Service Road 14.750km.)
Description
Completed Length (Km.) During this month Cumulative
(LHS) (RHS) (LHS) (RHS) Average Percentage
Earthwork nil nil 13.460 13.230 13.345 90.475
Sub grade nil nil 12.030 12.080 12.055 81.729
G.S. B. nil nil 10.950 11.660 11.305 76.644
WMM 1st nil nil 10.880 11.510 11.195 75.898
WMM 2nd nil nil 10.410 11.110 10.760 72.949
DBM 1st nil nil 9.940 10.870 10.405 70.542
B. C. nil nil 9.090 9.260 9.175 62.203
Note: Service road works are being carried out by the Concessionaire.
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015 17
in
association
with
Physical Progress of Road Works as of 31st March 2015:
Sl.
No.
Types of
work
Existing Road
Section
Bahadurgarh
Bypass
Existing
Road
Section
Rohtak
Bypass
Overall
Progress
Km.29+650 to km. 31.050 (1.400 km)
Km. 31.050 to km. 44.400 (13.350 km)
Km. 44.400 to km. 68.400 (24.000 km)
Km.68+400 to km 93+140 (24.740 km)
Km 29+650 to km 93.140
(63.490 km)
1 Earthworks 1.400 13.350 24.000 24.186 62.936
2 Subgrade 1.400 13.350 24.000 24.098 62.848
3 GSB 1.400 13.350 24.000 24.059 62.809
4 WMM 1st Layer 1.400 13.350 24.000 23.998 62.748
5 WMM 2nd
Layer 1.400 13.350 24.000 23.962 62.712
6 DBM 1st Layer 1.400 13.350 24.000 23.932 62.682
7 DBM 2nd
Layer 1.400 13.350 24.000 23.926 62.676
8 B.C. 1.400 13.350 24.000 22.260 61.010
B. Structures:
Status of balance works on structures has been shown on next page.
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015 18
in
association
with
A. Status of Structures as on 31st March 2015
Sl. No.
Location Type of
Structure Date
started
Span Configuration
(mtr)
Progress during the
month Present status Balance work as on 31st March2015
1 78+549 MJBR 20.03.09 (32.550+27.054+
27.054) No activity
All pile, pile cap, Abutment, pier abutment cap, pier cap completed. Approach slab A1 & A2 both sides completed. All deck slab completed. RE Wall work under progress
Fixing of Seismic restrainer (20 Nos. out of 40 Nos.)
Protection coping beam cum barriers in 52m wide sections.
Painting of steel girder & other structure
V-type neoprene seal to be extended in crash barrier
Tightening of bearing bolts
Rectification of expansion joint (P2 LHS)
Installation of utility pipe railing on top of crash barrier (both sides)
2 82+617 MJBR 04.12.08 (30+30+30) -do-
All pile, pile cap, Abutment, pier abutment cap, pier cap completed. 24 Nos. PSC girder launching completed. Deck slab both sides completed.
Fixing of Seismic restrainer (2 Nos. out of 56 Nos.)
V-type neoprene seal (RHS)
Installation of utility pipe railing on top of crash barrier (both sides)
3 31+171 MNBR 21.3.11 (10.00+10.00) No activity to complete the balance work.
Service road bridge on both sides completed.
Wing wall both sides final lift (service road bridges both sides)
Floor protection work (service road bridges both sides)
Installation of Filler board in expansion gap (Service road bridges both sides)
Curtain wall and floor apron (service road bridges both sides)
4 37+390 MNBR 16.02.09 (1 x 16.00) No activity Deck slab on both side completed.
Finishing of retaining wall top after cutting the projected steel bars
Rectification of settled approach slab and crash barrier & expansion joint (A2 RHS)
5 43+013 MNBR 20.04.09 (1 x 11.40) -do-
Deck slab on both side in Main carriageway completed. Service road bridge on both side completed.
Lifting of deck slab both sides Service road.
Bearing and pedestal (Service road bridge) (12 Nos. out of 12 Nos.)
Approach slab (service road, both sides)
Seismic restrainer (25 Nos. out of 44 Nos.)
Rectification of expansion joint (A2 RHS)
Drainage spout (service road)
V-type neoprene seal (service road)
6 44+194 MNBR 31.05.09 (1 x 37.00) -do-
Deck slab both sides completed. Service road bridge piling, pile cap, Abutment cap completed. PSC girder completed.
Approach slab (service road)
Seismic restrainer Pad (10 Nos. out of 34 Nos.)
Expansion joint 1 No. (NCPN)
Crash barrier (Service Road Bridge)
Service road bridge at RHS deck slab
Rain water pipe & Drainage spout
V-type neoprene seal
Bearing and pedestal 6 Nos. out of 6 Nos.)
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015 19
in
association
with
Sl. No.
Location Type of
Structure Date
started
Span Configuration
(mtr)
Progress during the
month Present status Balance work as on 31st March2015
7 47+117 MNBR 28.05.09 (1 x 21.00) No activity Deck slab on both sides completed.
Seismic restrainer pad (7 Nos. out of 24 Nos.)
Rectification of expansion joint (A1 RHS)
8 70+782 MNBR 30.04.09 (1 x 14.00) -do- Deck slab on both sides completed.
B. C. at RHS on deck slab (only mastic has been laid)
9 76+550 MNBR 16.09.08 (1 x 21.00) -do- Deck slab on both side completed.
Installation of rain water pipe (10Nos) with interconnections
10 88+393 MNBR 06.01.09 (1 x 21.00)
Retaining wall excavation at A1 & A2 LHS in progress
Deck slab on both sides completed
MS railing on top of crash barrier both sides
Seismic restrainer (24 Nos. out of 24 Nos.)
B.C. & Mastic asphalt on deck slab
Rain water pipe & Drainage spout
V-type neoprene seal
Load testing of deck slab
11 92+762 MNBR 20.11.09 (7.50+7.50) No activity Deck slab both sides completed.
Approach slab (both sides)
Wing/return wall (all 4 sides)
B.C. & mastic over deck slab(both sides)
Rain water pipe and Drainage spout
Curtain wall and floor apron
12 48+503 MNBR 05.08.09 (3.250+3.250+3.
250) -do-
Structure completed, balance works yet to be completed
Crash barrier LHS
13 40+107 VUP 20.12.08 (1 x 10.00) -do- Structure completed, balance works yet to be completed
PCC top in median gap
Installation of filler board in expansion gap (all 4 sides)
Sealing of crash barrier gaps & rain water pipe in crash barrier
14 69+723 VUP 07.12.08 (1 x 10.00) -do- Structure completed, balance works yet to be completed
Rain water pipe & Drainage spout (4 nos.)
PCC top in median gap
Installation of filler board in expansion gap (all 4 sides)
Protection coping beam cum barriers and drainage arrangement in 52m wide sections.
15 79+207 VUP 22.10.08 (1 x 10.00) -do- Structure completed, balance works yet to be completed
Installation of filler board in expansion gap (all 4 sides)
PCC top in median
Rain water pipe (4 Nos. out of 4 Nos.)
16 91+131 VUP 15.02.09 (1 x 10.00) -do- Deck slab both side completed.
Rectification of damaged reinforcement and casting of RCC crash barrier (both sides)
Approach slab (both sides)
RE/Retaining walls need to be carried out to restrict the embankment toe width up to 52m.
B.C. on deck slab.
Wearing course under VUP both sides
Rain water pipe & Drainage spout (both sides)
PCC on top of median
Installation of filler board in expansion gap
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015 20
in
association
with
Sl. No.
Location Type of
Structure Date
started
Span Configuration
(mtr)
Progress during the
month Present status Balance work as on 31st March2015
17 33+445 GSP 10.11.09 (21.00+40.00+ 21.00)
No activity Completed Sealing of crash barrier gaps &
installation rain water pipes in crash barrier.
18 38+440 GSP 31.12.08 (21.00+40.00+
21.00)
-do-
All deck slab on both side completed.
RE/retaining walls (Toe wall A1 & A2 RHS)
Rectification of expansion joints (A1 LHS and A2 RHS)
Rain water pipe & Drainage spout (5 Nos. out of 32 Nos. and their interconnections).
Sealing of crash barrier gaps & rain water pipe in crash barrier.
19 55+643 GSP 20.02.09 (21.00+40.00+
21.00)
-do- All deck slab on both side completed.
Installation of drainage pipes in RE wall
20 76+076 GSP 03.09.08 (21.00+40.0+
21.00) -do- All deck slab completed.
Rain water pipe & drainage spout 4 Nos. and rain water pipe to be connected
21 85+372 GSP 03.02.09 (21.00+40.0+
21.00) -do-
All deck slab on both sides completed. RE Wall work under progress
V-Type Neoprene seal both sides.
RE work in median gap B/S
Construction of balance RE walls at the location of CUP (A2 side approach).
Mastic asphalt on deck slab (both sides).
Drainage spouts.
Rectification of expansion joint A2 RHS (NCPN)
22 59+868 ROB 08.08.09 (28.217+32.420+
19.579) -do-
All pile, pile cap, Abutment, Pier, Abutment cap and pier cap completed. All girder launching completed. Deck slab span (A2-P2) & (A1-P1) and (P1-P2) at RHS completed.
Height of RE walls (A1 side) in 52m sections is to be increased yet & drainage works.
Railing on footpath sides is not proper.
V-Type Neoprene seal to be extended up to end of crash barrier.
Painting of steel girder (track portion).
Extra shuttering to be removed. (Partly done)
Rain water pipes to be provided. (A2-P2 side 1 No. drainage spout and rain water to be connected and out let not properly.
Concreting of PSC girders end to protect PSC cable.
Repair work of anti-crash barrier concrete work and making proper expansion joints in anti-crash barrier. (Brick wall instead of RCC crash barrier)
Integrity test of RCC girder, since these were honey-combed
Completion plan.
Anti-smoke painting under side of deck slab.
Tightening of bearing bolts
Rectification of expansion joints A2 & P2 RHS
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015 21
in
association
with
Sl. No.
Location Type of
Structure Date
started
Span Configuration
(mtr)
Progress during the
month Present status Balance work as on 31st March2015
23 70+002 ROB 01.08.09 (24.159+35.613+
44.500) No activity
All pile, pile cap, Abutment, Pier and Abutment cap at A1& A2 both sides & pier cap P1 at both sides & pier cap P2 both sides completed. Deck slab on both sides completed. RE wall work under progress.
Protection coping beam cum barriers and drainage arrangement in 52m wide sections.
Integrity test of RCC girder, since these were honey-combed
Anti-smoke painting under side of deck slab (P1-P2 both sides cantilever portion
Stoppers to be casted.
Proper bolting and seating of bearings
Bolting of some cross bracings
Painting of steel girder. (A2-P2) both sides and P1-P2 track portion
Incomplete cross-bracing & bottom plate of cross girder (A2-P2) of steel girder
Tightening of bolts
Extra shuttering to be removed. (partly done)
Completion plan
Rainwater pipes to be fixed. [Partly done, span (A1-P1) P1 side 1 no. drainage spout and rain water pipe to be connected. (P1 P2) side half portion both sides balance. (A2-P2) half portion A2 both sides.]
Railing on footpath sides is not proper.
Proper restoration of approaches of bridge No. 98A.
24 71+580 ROB (New)
31.01.11 (1 x 30) -do-
4 Nos. pile cap completed & Abutment A1 & A2 both sides completed. Abutment cap A1 & A2 at both sides completed. Steel girder launching completed. Deck slab both sides completed.
Rectification works of RE walls as per NCPNs and balance RE works in A2 (RHS) as per Change of Scope.
Incomplete bolting of bearing
V-Type Neoprene seal to be extended up to end of crash barrier
RCC wall along Railway boundary (30m) constructed to prevent trespassing in progress.
Site cleaning within railway boundary
Completion plan
Railing on footpath sides is not proper.
Anti-smoke painting under side of deck slab and painting of steel structures to be done. (Track portion)
Rain water pipe to be fixed. (6 Nos. out of 12 Nos. with interconnections)
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015 22
in
association
with
Sl. No.
Location Type of
Structure Date
started
Span Configuration
(mtr)
Progress during the
month Present status Balance work as on 31st March2015
25 86+188 ROB 23.03.09 (30.90+30.90)
Bearing fixing and pedestal casting and
launching steel girder track
span (A1 - P1) completed. Fixation of
cross girders & bracing is being
done.
All abutment and pier completed & pier cap P1 both sides and abutment cap A2 at both sides and abutment cap A1 at both sides completed. Deck slab span (A2-P1) both sides completed.
Bearing fixing and pedestal casting span (A1-P1)
Seismic restrained pad 30 Nos. out of 30)
Deck slabs 2 Nos. (Track span)
RE Wall work (A1 side in progress.
Crash barrier (8 sides)
Approach slab
Expansion joint (6 Nos. out of 6)
B.C. on deck slab.
Mastic asphalt
Railing on footpath sides as per drawing.
Load testing of deck slab
Painting of steel girder & other structure
Rain water pipe & Drainage spouts
26 41+300 CUP
(Change of Scope)
19.02.11 (1 x 7.00) No activity Deck slab at both sides completed.
Wearing course (Under CUP).
Rain water pipe & Drainage spouts (4 Nos.)
Installation of filler board in expansion gap (all 4 sides)
PCC on top of median.
27 44+014 CUP
(Change of Scope)
24.01.13 (1 x 7.00) -do- Deck slab B/s completed
Wearing course under CUP.
Rain water pipe & Drainage spouts (4 Nos.)
Installation of filler board in expansion gap (all 4 sides)
PCC on top of median.
28 60+600 CUP
(Change of Scope)
28.03.11 (1 x 7.00) -do- Deck slab both sides completed.
Wearing course under CUP
Retaining wall LHS
PCC top in median gap
Installation of filler board in expansion gap (All four sides).
29 66+500 CUP
(Change of Scope)
13.06.11 (1 x 7.00) -do- Deck slab at both sides
completed.
Wearing course under CUP
Rain water pipe & drainage spout (4 Nos.)
PCC top in median gap
Installation of filler board in expansion gap (All four sides).
30 71+650 CUP
(Change of Scope)
19.10.11 (1 x 7.00) -do- Deck slab both sides
completed. Wearing course under CUP.
31 85+728 CUP
(Change of Scope)
28.02.13 (1 x 7.00) Deck slab at
LHS completed Deck slab both sides completed
Approach slab (both sides)
Wearing course under CUP.
PCC on top of median.
Installation of filler board in expansion gap (All four sides).
32 86+500 CUP
(Change of Scope)
18.10.11 (1 x 7.00) Retaining wall at A1 both side
PCC done
Deck slab both sides completed
Approach slab both side
Retaining wall (both sides)
Wearing course under CUP both sides
Rain water pipe & Drainage spouts (4 Nos.)
Installation of filler board in Expansion gap
PCC on top of median
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015 23
in
association
with
B. Status of Box Culvert as of 31st
March 2015
Sl. No.
Location Type of Structure Date
started Present status Remarks
1 31+675 Box Culvert 28.09.2009 Completed
2 32+195 Box Culvert 25.09.2009 Completed
3 34+892 Box Culvert 04.08.08 Completed
4 35+390 Box Culvert 05.09.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
5 36+983 Box Culvert Not constructed.
6 40+307 Box Culvert 01.06.11 Completed
7 45+079
(R). Box Culvert Considered under COS
8 46+549(R). Box Culvert Deck slab both sides completed except wing wall Yet to start the construction of balance works.
9 47+098(R). Box Culvert Completed
10 48+363(R). Box Culvert Not constructed
11 48+368(R). Box Culvert 28.11.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
12 48+485(R). Box Culvert Deck slab both sides completed except wing wall
-do-
13 53+914(R). Box Culvert 13.03.08 Deck slab both sides completed except wing wall
-do-
14 54+770(R). Box Culvert Completed
15 57+214(R). Box Culvert 01.03.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
16 57+538(R). Box Culvert 03.12.08 Deck slab both sides completed except wing wall
-do-
17 58+233(R). Box Culvert 16.03.08 Deck slab both sides completed except wing wall
-do-
18 62+505(W) Box Culvert Deck slab both sides completed except wing wall
-do-
19 63+588(R). Box Culvert 20.04.09 Deck slab both sides completed except wing wall
-do-
20 63+978(R). Box Culvert 05.05.09 Completed
21 64+394(R). Box Culvert Deck slab both sides completed except wing wall Yet to start the construction of balance works.
22 66+189(R). Box Culvert Deck slab both sides completed except wing wall
-do-
23 68+822 Box Culvert Deck slab both sides completed except wing wall
-do-
24 69+346 Box Culvert 05.09.09 Deck slab both sides completed except wing wall
-do-
25 69+565 Box Culvert Completed
Completed
26 70+513 Box Culvert 15.12.09 Completed
27 70+850 Box Culvert Deck slab both sides completed except wing wall Yet to start the construction of balance works.
28 71+186 Box Culvert 18.12.09 Deck slab both sides completed except wing wall -do-
29 72+196 Box Culvert 11.11.09 Deck slab both sides completed except wing wall -do-
30 72+366 Box Culvert Not constructed
31 72+530 Box Culvert 26.10.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
32 72+986 Box Culvert Not constructed
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015 24
in
association
with
Sl. No.
Location Type of Structure Date
started Present status Remarks
33 73+870 Box Culvert 08.08.09 Completed
34 74+139 Box Culvert 10.07.09 Completed
35 74+389 Box Culvert Not constructed
36 74+876 Box Culvert 02.07.09 Completed
37 75+091 Box Culvert 07.07.09 Completed
38 75+949 Box Culvert 18.12.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
39 77+096 Box Culvert 07.12.08 Completed
40 77+519 Box Culvert 10.01.09 Completed
41 77+722 Box Culvert 05.12.08 Completed
42 78+109 Box Culvert 07.12.08 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
43 78+703 Box Culvert 15.05.10 Deck slab both sides completed except wing wall
-do-
44 79+055 Box Culvert 15.05.10 Deck slab both sides completed except wing wall
-do-
45 79+340 Box Culvert Deck slab both sides completed except wing wall
-do-
46 79+710 Box Culvert 10.07.10 Completed
47 80+070 Box Culvert 22.07.09 Completed
48 80+665 Box Culvert 18.08.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
49 81+021 Box Culvert 19.11.08 Completed
50 81+243 Box Culvert Not constructed
51 81+419 Box Culvert 27.08.08 Completed
52 81+806 Box Culvert 16.09.08 Completed
53 82+064 Box Culvert 30.11.08 Completed
54 82+222 Box Culvert 04.12.08 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
55 83+194 Box Culvert 20.07.09 Completed
56 83+348 Box Culvert Completed
57 83+803 Box Culvert 13.05.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
58 84+568 Box Culvert 24.11.08 Completed
59 84+800 Box Culvert 05.05.09 Completed
60 85+620 Box Culvert 16.05.10 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
61 86+287 Box Culvert 01.10.11 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
62 86+770 Box Culvert Not Started Yet to start the construction of balance works.
63 87+091 Box Culvert 18.04.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
64 87+265 Box Culvert 02.05.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
65 87+476 Box Culvert 22.05.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
66 87+774 Box Culvert 31.05.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
67 87+946 Box Culvert 27.05.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015 25
in
association
with
Sl. No.
Location Type of Structure Date
started Present status Remarks
68 88+485 Box Culvert 10.12.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
69 89+158 Box Culvert 20.11.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
70 89+481 Box Culvert 22.08.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
71 89+730 Box Culvert 19.11.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
72 89+898 Box Culvert 25.06.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
73 90+131 Box Culvert 18.08.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
74 90+412 Box Culvert 25.08.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
75 90+692 Box Culvert 09.09.09 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
76 91+462 Box Culvert 08.05.10 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
77 91+845 Box Culvert Deck slab both sides completed except wing wall Yet to start the construction of balance works.
78 92+037 Box Culvert Deck slab both sides completed except wing wall Yet to start the construction of balance works.
79 92+257 Box Culvert 24.04.10 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
80 92+630 Box Culvert 25.04.10 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
81 33+463 Box Culvert
(Change of Scope) Deck slab both sides completed except wing wall Yet to start the construction of balance works.
82 40+470 Box Culvert
(Change of Scope) Completed
83 45+092 Box Culvert
(Change of Scope) 24.07.09 Completed
84 58+080 Box Culvert
(Change of Scope) 03.12.08 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
85 62+479 Box Culvert
(Change of Scope) Completed
86 85+850 Box Culvert
(Change of Scope) 12.04.11 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
87 87+650 Box Culvert
(Change of Scope) 11.01.10 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
88 88+000 Box Culvert
(Change of Scope) 17.01.10 Deck slab both sides completed except wing wall Yet to start the construction of balance works.
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015 26
in
association
with
C. Status of Pipe Culvert as of 31st
March 2015
Sl. No.
Location Type of Structure Date started Present status Remarks
1 30+950 HPC Completed both sides except headwall Yet to start the construction of balance works.
2 33+883 HPC 01.09.08 Completed both sides except headwall -do-
3 33+979 HPC Not Constructed
4 35+750 HPC 20.11.08 Completed both sides except headwall Yet to start the construction of balance works.
5 36+002 HPC Completed both sides except headwall -do-
6 36+750 HPC (A) Completed both sides except headwall -do-
7 37+700 HPC 03.09.09 Completed both sides except headwall -do-
8 37+900 HPC 18.11.08 Completed both sides except headwall -do-
9 38+800 HPC 26.10.08 Completed both sides except headwall -do-
10 39+302 HPC 19.11.08 Completed both sides except headwall -do-
11 39+684 HPC Not constructed
12 41+214 HPC 19.11.08 Completed both sides except headwall Yet to start the construction of balance works.
13 41+500 HPC 08.12.08 Completed both sides except headwall -do-
14 42+717 HPC 20.12.08 Completed both sides except headwall -do-
15 43+306. HPC 26.12.08 Completed both sides except headwall -do-
16 43+739 HPC 12.01.09 Completed both sides except headwall -do-
17 44+500 HPC 23.05.09 Completed both sides except headwall -do-
18 46+437 HPC (A) 12.05.11 Completed both sides except headwall -do-
19 47+547 HPC (A) Completed both sides except headwall -do-
20 49+880 (W) HPC 04.02.11 Completed both sides except headwall
-do-
21 50+015 (W) HPC 13.08.09 Completed both sides except headwall
-do-
22 50+857 (W) HPC Completed both sides except headwall -do-
23 51+118 HPC (A) 24.10.09 Completed both sides except headwall -do-
24 51+876 (W) HPC 22.11.08 Completed both sides except headwall -do-
25 52+012 (W) HPC 22.11.08 Completed
26 52+857 (W) HPC
Completed both sides except headwall Yet to start the construction of balance works.
27 54+975 (W) HPC 28.11.08 Completed both sides except headwall Yet to start the construction of balance works.
28 55+324 (W) HPC 25.04.09 Completed both sides except headwall -do-
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015 27
in
association
with
Sl. No.
Location Type of Structure Date started Present status Remarks
29 55+573 (W) HPC 25.04.09 Completed both sides except headwall -do-
30 56+134 (W) HPC Completed both sides except headwall -do-
31 59+141 (W) HPC 25.04.09 Completed both sides except headwall -do-
32 59+770 HPC (A) 10.05.10 completed both sides except headwall -do-
33 60+683 (W) HPC 20.04.09 Completed both sides except headwall -do-
34 60+835 (W) HPC 20.04.09 Completed both sides except headwall -do-
35 61+061 (W) HPC 20.04.09 Completed both sides except headwall -do-
36 61+736 (W) HPC 20.04.09 Completed both sides except headwall -do-
37 61+961 (W) HPC 20.04.09 Completed both sides except headwall -do-
38 62+114 HPC (A) Completed both sides except headwall -do-
39 62+538 HPC (A) Completed both sides except headwall -do-
40 62+650 HPC (A) Completed both sides except headwall -do-
41 62+838 HPC (A) Completed both sides except headwall -do-
42 64+689 (W) HPC 24.04.09 Completed both sides except headwall -do-
43 65+189 (R) HPC 24.04.09 Completed both sides except headwall -do-
44 65+892 (W) HPC 24.04.09 Completed both sides except headwall -do-
45 65+916 (W) HPC 24.04.09 Completed both sides except headwall -do-
46 66+272 (W) HPC 24.04.09 Completed both sides except headwall -do-
47 67+081 (W) HPC 24.04.09 Completed both sides except headwall
48 67+892 HPC (A)
Completed both sides except headwall Yet to start the construction of balance works.
49 70+298 HPC 25.11.09 Completed both sides except headwall -do-
50 71+596 HPC Completed both sides except headwall
51 71+650 HPC 23.02.10 Completed both sides except headwall Yet to start the construction of balance works.
52 71+793 HPC 17.11.09 Completed both sides except headwall -do-
53 73+129 HPC 09.08.09 Completed both sides except headwall -do-
54 73+535 HPC 07.08.09 Completed
55 74+341 HPC 13.08.09 Completed both sides except headwall Yet to start the construction of balance works.
56 78+282 HPC 23.04.09 Completed both sides except headwall -do-
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
Monthly Progress Report: March 2015 28
in
association
with
57 80+290 HPC (A) 05.09.09 Completed both sides except headwall -do-
Sl. No.
Location Type of Structure Date started Present status Remarks
58 82+498 HPC 13.09.08 Completed both sides except headwall -do-
59 82+890 HPC 19.11.08 Completed both sides except headwall -do-
60 84+186 HPC 05.02.09 Completed both sides except headwall -do-
61 84+416 HPC 13.12.08 Completed both sides except headwall -do-
62 85+260 HPC 18.02.09 Completed both sides except headwall -do-
63 86+078 HPC
Completed both sides except headwall -do-
64 88+275 HPC 09.03.09 Completed both sides except headwall -do-
65 88+729 HPC 21.02.09 Completed both sides except headwall -do-
66 91+060 HPC 01.03.09 Completed both sides except headwall -do-
67 32+865 HPC
(Change of Scope) 12.10.09 Completed both sides except headwall
-do-
68 39+627 HPC
(Change of Scope) 10.11.11 Completed both sides except headwall
-do-
69 40+882 HPC
(Change of Scope) 04.02.09 Completed both sides except headwall
-do-
70 42+003 HPC
(Change of Scope) 11.12.08 Completed both sides except headwall
-do-
71 45+985 HPC
(Change of Scope) 10.02.11 Completed both sides except headwall
-do-
72 47+384 HPC
(Change of Scope) 08.10.10 Completed both sides except headwall
-do-
73 49+134 HPC
(Change of Scope) 20.05.10 Completed both sides except headwall
-do-
74 53+150 HPC
(Change of Scope) 05.12.10 Completed both sides except headwall
-do-
75 56+785 HPC
(Change of Scope) 13.03.08 Completed both sides except headwall
-do-
76 60+547 HPC
(Change of Scope) 21.02.11 Completed both sides except headwall
-do-
77 65+595 HPC
(Change of Scope) 24.04.09 Completed both sides except headwall
Yet to start the construction of balance works.
78 66+795 HPC
(Change of Scope) 24.04.09 Completed both sides except headwall
-do-
79 73+278 HPC
(Change of Scope) 18.02.10 Completed
80 85+740 HPC
(Change of Scope) 08.03.11 Completed both sides except headwall Yet to start the construction of balance works.
81 86+520 HPC
(Change of Scope)
Not Started
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A) Package No. IE/BOT-
II/NH-10/HRY/004
Monthly Progress Report: March 2015 29
in
association
with
6.0 Handing over of site:
Land in the total length of the project highway has been handed over.
}
7.0 Shifting of utilities:
Completed
7.1 Status of shifting of utilities:
Utility to be shifted by Electrical Authority:
Completed
7.2 Problem encountered:
None.
8.0 Forest clearance and removal of trees:
Removal of trees had already been completed.
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
30 Monthly Progress Report March 2015
in
association
with
9.0 DESIGN REVIEW
9.1 Designs/Drawings reviewed:
9.1.1 Highway Drawing Status:
Status of Highway drawings is given as below:
Sl. No.
Description Ref No. of
Concessionaire
Reviewed
vide IE’s
Ref. No
Status of the Drawing
Remarks
1
Typical cross-
sections of drawing & Flaring
details
256/14.02.09 635/20.02.09 Concurred
Final X-sections
drawings are yet to be submitted by
Concessionaire
2
Plan & Profile
drawings from Km 29+650 to 93+140
034/13.08.08
158/09.12.08 193/02.01.09
203/08.01.09 255/12.02.09
266/14.02.09 267/14.02.09
635/20.02.09
The drawings
concurred with some comments
Final drawings are
yet to be
submitted by Concessionaire
3
Typical details of
Kilometer stone and Hectometer
stone
237/31.01.09 673/03.03.09 Concurred _
4 Location of utility
ducts 303/25.03.09 754/30.03.09 Approved _
5
Details of Road
crossing / Junctions
All drawing
submitted on different Nos. &
date
Reviewed vide
different Nos. & date
Reviewed _
6
Drainage Plan and
Profile of drains/
median drain at super elevation
398/11.06.09 1038/23.06.09 Return with
comments
Reply of comments
yet to be received
7
Technical Proposal
for slope protection
464/05.08.09 1191/12.08.09 approved _
8
Revised Plan and Profile drawing
from Km 31+00 to 34+00
591/3.12.09 1584/15.12.09 Concurred _
9
Location of Toll Plaza, Truck Lay
byes and wayside amenities
647/02.02.10 1750/05.02.10 Location accepted ---
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
31 Monthly Progress Report March 2015
in
association
with
Sl. No.
Description Ref No. of
Concessionaire
Reviewed vide IE’s Ref.
No
Status of the Drawing
Remarks
10 Revised location of Truck Lay by
765/20.05.2010 672/22.05.10
2129/27.05.10 Revised location accepted.
----
11 Location of Bus
bays 936/07.10.2010
2637 dated
18.10.2010
Revised proposal
received and accepted.
Layout drawings
approved.
12
Plan & Profile of
Service road from Km 35+00 to
44+200
652/11.02.10 1906/22.03.10 2676/21.10.10
Approved
13 Median openings
on existing road
1897/15.01.10
936/07.10.10.10
1695/19.01.10
2637/18.10.10 Locations accepted _
14 Drawings of crash
barrier 692/10.03.10 1900/19.03.10 Approved Approved
15
Drainage arrangement of
existing road from km. 44.00 to km.
68.00
723/14.04.10 2021/21.04.10 Concurred with
comments
Chainage-wise
proposal is yet to be submitted.
16 Arboriculture and landscaping
693/10.03.10 1942/03.04.10 Reviewed and found in order.
-
17 Design of overlay for existing
Pavement
752/07.05.2010 2079/13.05.10 Reviewed and found in order.
-----
9.2 Design/drawing pending with Independent Engineer:
None.
9.3 Design/drawing still required to be submitted by the Concessionaire for works
required to be taken up shortly:
9.3.1 Highway drawings:
o Strip plan and land plan showing ROW at each chainage.
o Drainage plan and profile drawings of median drains from Ch. 44+400 to Ch.
68+800
o Details of slip roads under change of scope.
o Entry & exit drawing of each slip road on Grade Separators & VUPs
The Concessionaire is being reminded for submission of pending drawing.
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
32 Monthly Progress Report: March 2015
in
association
with
10.0 MAINTENANCE OF EXISTING ROAD:
10.1 Status of Maintenance:
The maintenance and repair work have been completed by the Concessionaire in most of stretches up to Km. 85+000. Some repair of rain cuts beyond Km. 85+000 still remains to be attended on Rohtak Bypass.
10.2 Maintenance measures required to be taken by the Concessionaire:
No maintenance measures were taken by the Concessionaire during the month and status is as follows:
I. Restoration of pavement affected due to rain cuts in Rohtak Bypass at the approaches of
(a) Minor Bridge at Ch. 88+393 (both sides)
(b) VUP at Ch. 91+131 (both sides)
II. Restoration of pavement due to rain cuts in scattered reaches from Ch. 86+700 to Ch. 93+140.
III. Slope protection work is yet to be taken up where height of embankment is more than 3.0m. particularly at the approaches of structures.
IV. The repair of strip seal expansion joints of various locations. The list of damaged strip seal expansion joints has been forwarded already to the Concessionaire.
V. Rectification of defects noted in the structures and for which the list of the same has already been submitted to the Concessionaire.
VI. The sealing of gaps in the RCC crash barrier panels at the grade separator at Ch. 33+445, Ch. 35+643, Ch. 38+440, Ch. 40+107, etc.
VII. Lot of bushes/wild growth have come up in the median & slopes of embankment obstructing the movement of traffic which are required to be attended by Concessionaire.
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
33 Monthly Progress Report-March 2015
in
association
with
11.0 SAFETY MEASURES:
The Concessionaire must address required safety measures by deploying safety teams to look after the
work of safety measures on the project highway. The cleaning of chocked/non-functioning pipe & box
culverts is required to be carried out by the Concessionaire for which immediate efforts are required to
be made by the Concessionaire. The main points of concern are as follows.
(a) Unauthorized median cuts:
Existing Illegal cuts in median indicated in previous reports have not been closed and as such
present status remains same as given below:
(i) Km 31+500 (Sector – 9)
(ii) Km 50+950 (Rohad Village)
(iii) Km 52+190 (Near Toll plaza diversion)
(iv) Km 69+540
(v) Km 77+800 (Petrol Pump)
(vi) Km 83+450
(vii) Km 85+100
The above mentioned median cuts are on the stretch which has been opened to traffic (i.e. from
Ch. 29+650 to Ch. 85+372). These median openings are required to be closed immediately to
avoid accidents. Similar action in the further stretch from Km 85+372 to Km. 93+140 should also
be taken accordingly.
The illegal cut at CH. 50+950 has become an accidental spot. It should be either closed or this
crossing be developed as at grade junction.
(b) Fixing of Road Signs
Since the stretch from Km. 29.650 to Km. 85.372 has been opened to traffic so it has become very
necessary to fix the sign boards particularly at the junctions. Following are the junctions which
need immediate attention of the Concessionaire:
(i) Junction at Km. 68+400
(ii) VUP at Km. 69+600
(iii) Clover leaf at Km. 76+076
(iv) VUP at Km. 79+207
(v) Grade Separator at Km. 85+372
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
34 Monthly Progress Report-March 2015
in
association
with
However work of fixing of sign boards has been completely stopped for the last six months.
Concessionaire should take up the work and fix sign boards which are essential for safety of road
users.
(c) Black Spots
Though the project highway has been constructed as per required specification & design but the
following spots except the illegal cuts are still existing at present which may also prove as
accident prone areas in future in the absence of further improvement .
(i) At grade junction at Km 35+350
Junction has been developed but the provision of a CUP of 4.5 m height will minimize the
accidents in view of height of embankment at this location.
(ii) At grade junction at Km 36+500
Provision of VUP at this location in place of at grade junction will bring the complete safety in
view of Bahadurgarh-Badli traffic and close vicinity of village Nayagaon.
(iii) At grade junction at Km 56+600
Provision of VUP is required at this location in place of at grade junction to make this junction completely safe in view of Sampla-Beri cross road at curvature of MCW and nearby adjacent Tehsil building Rest house and Girls College.
(d) Recommendations of Independent Engineer which have not been acted upon by the Concessionaire:
The Construction of balance works has been taken up by the Concessionaire but the following
observations made by the IE are yet to be complied with by the Concessionaire.
i. Shifting of electric lines crossing project highway on bamboos erected in median and shoulder areas in the stretches from Km. 67+500 to Km. 67+875 (median), Km. 68+100 to Km. 68+350 (RHS), Km. 89+720 to Km. 90+150 (RHS).
ii. Protection of slopes at the approaches of structures on Rohtak Bypass and high embankment stretches.
iii. Protection of site from encroachment, etc is required to be addressed as per clause 10.5 of the agreement. The Concessionaire has been directed several times through written and verbal directions however concrete steps are required to be taken by the Concessionaire in this regard.
iv. Land plan which is a basic record to be maintained has not been submitted by the Concessionaire despite of asking him so many times.
v. The Concessionaire should develop a dedicated team for monitoring the safety works as well as for protection of site which has been neglected completely by Concessionaire.
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
35
Monthly Progress Report: March 2015
in
association
with
12.0 Weather Report:
Detail of Weather report for the month of March 2015
S.N. Date Time
Temperature
Weather
Rain Fall in
(mm)
Cumulative Rain fall
Remarks Maximum
0 C Minimum
0 C
1 1-Mar-15 8.00AM 28.0 11.0 Rainy 33.0 33.0
2 2-Mar-15 8.00AM 28.0 12.0 Rainy 39.0 72.0
3 3-Mar-15 8.00AM 28.0 12.0 Sunny Nil 72.0
4 4-Mar-15 8.00AM 28.0 12.0 Sunny Nil 72.0
5 5-Mar-15 8.00AM 29.0 12.0 Sunny Nil 72.0
6 6-Mar-15 8.00AM 29.0 12.0 Cloudy Nil 72.0
7 7-Mar-15 8.00AM 29.0 12.0 Rainy 9.0 81.0
8 8-Mar-15 8.00AM 29.0 13.0 Rainy 2.0 83.0
9 9-Mar-15 8.00AM 30.0 13.0 Sunny Nil 83.0
10 10-Mar-15 8.00AM 30.0 13.0 Sunny Nil 83.0
11 11-Mar-15 8.00AM 30.0 13.0 Sunny Nil 83.0
12 12-Mar-15 8.00AM 30.0 13.0 Sunny Nil 83.0
13 13-Mar-15 8.00AM 30.0 13.0 Sunny Nil 83.0
14 14-Mar-15 8.00AM 31.0 14.0 Cloudy Nil 83.0
15 15-Mar-15 8.00AM 31.0 14.0 Rainy 4.0 87.0
16 16-Mar-15 8.00AM 31.0 14.0 Sunny Nil 87.0
17 17-Mar-15 8.00AM 31.0 14.0 Sunny Nil 87.0
18 18-Mar-15 8.00AM 31.0 14.0 Sunny Nil 87.0
19 19-Mar-15 8.00AM 32.0 15.0 Sunny Nil 87.0
20 20-Mar-15 8.00AM 32.0 15.0 Sunny Nil 87.0
21 21-Mar-15 8.00AM 32.0 15.0 Sunny Nil 87.0
22 22-Mar-15 8.00AM 32.0 15.0 Sunny Nil 87.0
23 23-Mar-15 8.00AM 32.0 15.0 Sunny Nil 87.0
24 24-Mar-15 8.00AM 32.0 16.0 Cloudy Nil 87.0
25 25-Mar-15 8.00AM 32.0 16.0 Cloudy Nil 87.0
26 26-Mar-15 8.00AM 33.0 16.0 Sunny Nil 87.0
27 27-Mar-15 8.00AM 33.0 16.0 Sunny Nil 87.0
28 28-Mar-15 8.00AM 33.0 16.0 Sunny Nil 87.0
29 29-Mar-15 8.00AM 33.0 17.0 Sunny Nil 87.0
30 30-Mar-15 8.00AM 33.0 17.0 Rainy 11.0 98.0
31 31-Mar-15 8.00AM 33.0 17.0 Sunny Nil 98.0
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A))
Package No. IE/BOT-II/NH-10/HRY/004
36 Monthly Progress Report: March 2015
in
association
with
13.0 QUALITY REVIEW REPORT:
13.1 QUALITY ASSURANCE/MATERIALS TESTING REPORT:
The site inspection were carried out diligently and regularly by the representations of the Independent
Engineer and written/verbal directions were given to the Concessionaire regarding quality of workmanships,
rectification of non-conformities noted in some works as per issued NCRs, safety of project highway,
documentation of activities, etc. The directions issued on the activities which transpired during the reporting
month are as following.
(i) The Concessionaire was advised to take proper measures immediately in order to drain out the water on permanent basis to avoid any inconvenience to road users at grade separator at Km 33+400. The Concessionaire was further advised to take proper drainage measures in such a way that the water in drained out in shortest period of time after occurrence of rains in order to avoid the damage to the road crust. It was admonished that the road already damaged be repaired immediately particularly the repair of damaged slip roads at grade separators.
(ii) The Concessionaire was advised to use locally available sandy soil (tibba sand) materials in service road works and for balance earth works of the Project Highway to ensure good quality of earth works.
(iii) The Concessionaire was requested to take action for the compliance of safety observations at the earliest and submit the compliance report to this office accordingly.
(iv) The Concessionaire was advised to take actions for the safety of workers and of completed works because some discrepancies were noted during site inspection in the removal of shuttering materials/bars in superstructure of the non-track span of ROB at Ch. 86+177 (Rohtak-Bhiwani Line).
(v) The Concessionaire was advised to rectify the discrepancies in service road works to ensure that the FRL levels are not lowered at any location.
(vi) The Concessionaire was advised to take up the rectification work of trenches made at the slip roads at VUP at Km 79+207 and to report the compliance at the earliest for further submission of compliance report to the Project Director.
(vii) The Concessionaire was once again reminded to take action against illegal access/encroachments by serving the time bound notice to the encroachers for vacating the ROW.
(viii) The Concessionaire was requested to take immediate action to improve the quality of materials & workmanship of on going works.
Independent Engineering Services for 4/6 Laning of NH-10 from Delhi/Haryana Border to Rohtak In the state of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
37
Monthly Progress Report: March 2015
in
association
with
E
13.2 Details of Non-Conforming Product Notifications:
NCPN
No.
Issued Ref./
Date
Type of
NCPN
Mile
Stone Description
Corrective Action
Accepted
YES/NO
Closed
Date
01 55/23.07.08 Embankment MS-1 Construction of Embankment from Ch. 61+000 to Ch.
61+630 RHS (5th & 6th Layer) Yes 13.09.08
02 63/25.07.08 Embankment MS-1 Construction of Embankment from Ch. 61+630 to Ch.
61+80 0 RHS (1st Layer) Yes 05.08.08
03 123/21.08.08 Embankment MS-1 Construction of Embankment from Ch. 75+400 to Ch.
75+600 (RHS) Yes 15.06.09
04 131/26.08.08 Reinforcement MS-1 Improper storage of reinforcements Yes 07.10.08
05 135/29.08.08 Embankment MS-1 Construction of embankment at Ch. 50+640 to
Ch.50+890, RHS (4th & 5th layer) Yes 25.09.08
06 136/29.08.08 Embankment MS-1 Construction of embankment from Ch. 57+750 to
Ch.58+600, LHS (12th & 13th layer) Yes 25.09.08
07 186/17.09.08 Embankment MS-1 Construction of embankment at Ch. 85+600 to
Ch.85+800 Yes 22.10.08
08 235/03.10.08 Embankment MS-1
Construction of embankment at Ch. 76+650 to
Ch.76+800(5th layer),Ch. 76+800 to Ch. 76+900 (6th
Layer), Ch. 76+900 to Ch. 77+000(7th layer), Ch. 77+000
to Ch. 77+080(6th layer), Ch. 77+100 to Ch. 77+200(9th
layer),
Yes 22.10.08
09 237/04.10.08 Embankment MS-1 Construction of embankment from Ch.51+600 to
Ch.51+870 (RHS) 1st layer Yes 04.02.09
10 299/27.10.08 Embankment MS-1 Construction of embankment from Ch.41+000 to
Ch.41+300 (7th layer) andCh.41+300 to Ch. 41+400 (3rd
layer)
Yes 26.12.08
11 369/21.11.08 Box Culvert MS-1 Backfilling in Box Culvert at Ch. 81+419
Yes 23.01.09
12 398/02.12.08 H P Culvert MS-1 Back filling in Hume Pipe Culvert at Ch. 82+498 Yes 23.01.09
13 414/10.12.08 Embankment MS-1 Earthwork from km. 37+410 to km. 37+500, 19th layer Yes 04.02.09
14 415/10.12.08 Embankment MS-1 Earthwork from km. 56+140 to km. 56+250, 4th layer Yes 20.01.09
15 418/12.12.08 Reinforcement MS-1 Defects/deficiencies on reinforcement and mud on top
the PCC of Box Culvert at Km. 34+892 Yes 22.12.08
16 445/23.12.08 Embankment MS-1
Embankment construction from Ch. 53+600 to
Ch.53+900 (RHS) & Ch. 56+250 to Ch 56+400 (LHS) 1st
layer without clearing & grubbing and removal of
unsuitable materials & shrubs
Yes 09.02.09
18 477/01.01.09 Vehicular
Underpass MS-1 Shuttering forms in Vehicular Underpass at km. 79+207 Yes 21.01.09
Independent Engineering Services for 4/6 Laning of NH-10 from Delhi/Haryana Border to Rohtak In the state of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
38
Monthly Progress Report: March 2015
in
association
with
NCPN
No.
Issued Ref./
Date
Type of
NCPN
Mile
Stone Description
Corrective Action
Accepted
YES/NO
Closed
Date
19 491/05.01.09 Embankment MS-1
Earthwork done without clearing and grubbing on
account of which there is bumping at Ch.48+040 to Ch.
48+180 (4th layer)
Yes 28.02.09
20 520/15.01.09 Embankment MS-1 Spreading of earth in embankment was in depth of 1.0
meter instead of 25cms at Ch. 39+500 to Ch. 39+600 Yes 28.02.09
21 589/07.02.09 Embankment MS-1 Earthwork in embankment was spread in thickness of 800
mm instead of 250 mm loose at Ch. 39+900 to Ch.
40+050 (10th layer)
yes 12.10.10
23 605/12.02.09 Embankment MS-1 Earthwork in embankment was spread in thickness of
1000 mm instead of 250 mm loose at Ch. 59+000 to Ch.
59+120 (1st layer)
Yes 15.04.09
24 606/12.02.09 Embankment MS-1 Subgrade material was laid/compacted in one layer of
500mm instead of three layers at Ch. 38+000 to Ch.
38+200
Yes 22.02.10
25 607/12.02.09 Embankment MS-1 Earthwork in embankment was spread in thickness of
500mm instead of 250mm loose at Ch. 89+200 to Ch.
89+350(8th layer)
Yes 27.03.09
26 615/14.02.09 Embankment MS-1 Earthwork in embankment was being done without C&G
at Ch. 47+500 to Ch. 47+550 Yes 23.07.14
27 626/18.02.09 Embankment MS-1 Earthwork in embankment 4th layer was being done in
thickness of 1000mm instead of required 250mm (loose)
at Ch. 58+600 to Ch. 58+800
Yes 15.04.09
28 640/23.02.09 Pipe Culvert MS-1 Structure works in pipe culverts at Ch. 82+890, Ch.
84+416 and Ch. 85+260 Yes 17.11.14
29 654/27.02.09 Embankment MS-1 Earthwork in Embankment at Ch. 38+000 to Ch. 38+200 Yes 08.03.10
30 665/02.03.09 Embankment MS-1 Earthwork in Embankment at Ch. 79+300 to Ch. 79+700 Yes 08.03.10
31 677/04.03.09 Box Culvert MS-1 Structure work in top slab of Box Culvert at Ch. 58+080
(LHS) yes 19.12.09
32 708/13.03.09 Embankment MS-1 Earthwork in Embankment at Ch. 66+350 to Ch. 66+500
(RHS) 8th layer Yes 20.04.09
33 712/14.03.09 Embankment MS-1 Earthwork in Embankment at Ch. 66+040 to Ch. 66+185
(RHS) 10th layer Yes 20.04.09
34 713/14.03.09 Embankment MS-1 Earthwork in Embankment at Ch. 66+195 to Ch. 66+350
(RHS) 8th layer Yes 20.04.09
35 724/18.03.09 Grade
Separator MS-1
Compressive strength of concrete cubes for Grade
Separator at Ch.38+436, R.C.C. Piles: A2-LHS-pile No. P6
and A1-LHS-pile No.-P6
Yes 19.06.09
36 745/27.03.09 Embankment MS-1 Thickness of sub grade material at Ch. 72+390 to Ch. 72+500, sub grade 2nd layer. The thickness was 500mm instead of 200 mm (loose)
Yes 27.07.09
Independent Engineering Services for 4/6 Laning of NH-10 from Delhi/Haryana Border to Rohtak In the state of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
39
Monthly Progress Report: March 2015
in
association
with
NCPN
No.
Issued Ref./
Date
Type of
NCPN
Mile
Stone Description
Corrective Action
Accepted
YES/NO
Closed
Date
37 746/27.03.09 Embankment MS-1 Laying/grading of G.S.B. material at Ch. 74+400 to Ch.
74+800. Laying was being done on loose surface in part
width of embankment.
Yes 15.06.09
38 751/28.03.09 Vehicular
Underpass MS-1
Reinforcement of top slab bracket portion rings/strips and
spacing of reinforcement are not as per drawing and bar
bending schedule.
yes 29.10.14
39 767/02.04.09 Embankment MS-1 Earthwork in embankment at Ch. 42+400 to Ch. 42+520
(both side) 11th layer Yes 28.06.14
40 771/03.04.09 GSB MS-1 Thickness of GSB at Ch. 81+440 to Ch. 81+500 (both
side) G.S.B. top layer Yes 15.06.09
41 800/10.04.09 Embankment MS-1 The earth dumped in thickness of 500mm instead of
250mm and was not graded/watered/rolled at Ch.
66+530 to Ch. 66+900 (RHS) 7th layer
Yes 25.05.09
42 834/20.04.09 Hume Pipe
Culvert MS-1 Structures works for Hume Pipe Culvert at Ch. 60+835
(LHS)
Yes 3.12.14
43 864/29.04.09 Minor Bridge MS-1 Structure works for Minor Bridge at Ch. 76+550 Yes 18.11.14
44 868/29.04.09 Major Bridge MS-1 Structure works for Major Bridge at Ch. 82+637 of
abutment A1 and A2
- -
45 877/01.05.09 Box Culvert MS-1 Structure works for box Culvert at Ch. 57+214.378 Yes 22.09.14
46 892/06.05.09 WMM MS-2 WMM top layer from Km. 51+890 to km. 52+200 and km.
51+630 to km. 51+850 Yes 02.07.09
47 927/19.05.09 Embankment MS-2 Earth works in embankment at Ch. 45+900 to Ch.
46+020 4th layer (RHS) Yes 14.09.09
48 934/20.05.09 Box Culvert MS-2 Structure works in Box Culvert at Ch. 77+096 yes 29.10.14
49 958/27.05.09 Embankment MS-2 Earth works in Embankment at Ch. 60+450 to Ch.
60+580 Yes 27.05.14
50 959/27.05.09 Embankment MS-2 Earth work in embankment at Ch. 70+520 to Ch. 70+700 Yes 06.06.09
51 976/03.06.09 Embankment MS-2 Earth work at Ch.46+900 to Ch. 46+950 (RHS) Yes 03.10.09
52 977/03.06.09 Embankment MS-2 FDD of sub grade top at Ch. 64+250 to Ch. 64+500 Yes 07.09.09
53 985/06.06.09 Box Culvert MS-2 Structure works in Box Culvert (top slab and walls, RHS)
at km. 77+096 yes 17.11.14
Independent Engineering Services for 4/6 Laning of NH-10 from Delhi/Haryana Border to Rohtak In the state of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
40
Monthly Progress Report: March 2015
in
association
with
NCPN
No.
Issued Ref./
Date
Type of
NCPN
Mile
Stone Description
Corrective Action
Accepted
YES/NO
Closed
Date
54 986/06.06.09 Box Culvert
MS-2
Structure works in Box Culvert (Wall 2nd lift and top slab,
RHS) Yes 17.07.14
55 998/10.06.09 Minor Bridge MS-2 The width of approaches to Minor Bridge at Ch.
37+390.356 from Ch. 37+075 to 37+675 Yes 30.03.12
56 1017/16.06.09 Embankment MS-2 Spread in thickness of embankment top at Ch. 66+800 to
Ch. 66+900 & Ch. 67+500 to Ch. 67+600, RHS Yes 01.02.10
57 1049/26.06.09 GSB MS-2 Segregated and surface irregularities at Ch. 33+920 to
Ch. 34+030, GSB top layer Yes 2.07.14
58 1056/29.06.09 Kerbs MS-2 Laying of kerbs at Ch. 61+300 to Ch. 61+400 yes 17.05.12
59 1057/29.06.09 Prime coat MS-2 Laying of prime coat at Ch. 52+880 to Ch. 53+100 Yes 09.07.09
60 1076/06.07.09 G.S.B. MS-2 Laying of G.S.B. at Ch. 35+400 to Ch. 35+650 Yes 21.07.14
61 1078/07.07.09 Sub grade MS-2 Dumping of earth at Ch. 68+130 to Ch. 68+350 (LHS) Yes 04.04.12
62 1103/14.07.09 G. S. B. MS-2 G. S. B. layer at Ch. 30+640 to Ch. 30+740 Yes 23.02.10
63 1128/24.07.09 Embankment MS-2 Earthwork in Embankment 1st layer at Ch. 44+400 to Ch. 44+500 (RHS), Ch. 45+100 to Ch. 45+250 (RHS) and Ch. 48+730 to Ch. 48+820 (RHS)
Yes 24.08.09
64 1147/31.07.09 G. S. B. MS-2 Laying of G.S. B. as per four lane instead of six lane at
Ch.38+670 to Ch. 38+800 Yes 22.02.10
65 1204/18.08.09 Hume Pipe
Culvert MS-2 Casting of cradle and backfilling on Hume Pipe Culvert at
km. 49+134 (LHS)
Yes 23.9.14
66 1206/19.08.09 Major Bridge MS-2 Concreting and casting on Abutment A2 (RHS) pile cap of
Major Bridge at km. 82+617 - -
67 1213/20.08.09 G.S.B. MS-2 G. S. B. material laid at Ch.90+400 to Ch. 90+500 Yes 17.02.10
68 1218/21.08.09 W.M.M. MS-2 Laying of W.M.M. (top layer) at Ch. 79+700 to Ch.
80+000. Yes 30.03.12
69 1219/21.08.09 G.S.B. MS-2 Laying of G.S.B. at Ch. 90+400 to Ch. 90+700 Yes 03.03.10
70 1224/22.08.09 W.M.M. MS-2 Laying of W.M.M. at Ch. 48+550 to Ch. 48+750, LHS (1st layer).
Yes 07.09.09
71 1230/24.08.09 G.S.B. MS-2 Laying of G.S.B. materials at Ch.38+670 to Ch. 38+800
and Ch. 38+000 to Ch. 38+200 Yes 23.02.10
72 1265/05.09.09 G.S.B. MS-2 Laying of G.S.B. materials at Ch.58+850 to Ch. 59+000
(LHS) Yes 25.11.09
Independent Engineering Services for 4/6 Laning of NH-10 from Delhi/Haryana Border to Rohtak In the state of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
41
Monthly Progress Report: March 2015
in
association
with
NCPN
No.
Issued Ref./
Date
Type of
NCPN
Mile
Stone Description
Corrective Action
Accepted
YES/NO
Closed
Date
73 1266/05.09.09 G.S.B. MS-2 Laying of G.S.B. materials at Ch.63+520 to Ch. 63+590 (RHS)
Yes 25.11.09
74 1329/23.09.09 G.S.B. MS-2 Laying of G.S.B. materials at Ch.91+560 to Ch. 92+000 Yes 17.11.09
75 1345/01.10.09 G.S.B.
MS-2
Laying of G.S.B. materials at Ch.43+000 to Ch. 43+400 (both side)
Yes 17.11.09
76 1349/03.10.09 G.S.B. MS-2 Laying of G.S.B. materials at Ch.87+000 to Ch. 87+100 (both side)
Yes 5.07.14
77 1428/26.10.09 G.S.B. MS-2 Laying of G. S. B. material at Ch. 43+720 to Ch. 43+950
(both side). Yes 18.11.09
78 1467/09.11.09 D.B.M. MS-2 D. B. M. was laid without applying the tack coat over the
primed surface at Ch. 33+810 to Ch. 34+260 (1st layer) Yes 11.07.14
79 1518/23.11.09 Earthwork MS-2 Earthwork at Ch. Ch. 71+600 to Ch. 71+800
Yes 22.03.10
80 1551/04.12.09 Earthwork MS-2
Restoration of raincuts extending into pavement crust
layers at Ch. 80+740 to Ch. 80+980 (both sides) and at
ch81+060 to Ch.81+280 (both sides)
yes 30.10.14
81 1558/08.12.09 Earthworks MS-2
Embankment works at Ch. 70+100 to Ch.70+350 (both
sides)
yes 31.10.14
82 1563/09.12.09 Earthworks MS-2 Earthworks in widening of existing carriageway at Ch.51+550 to Ch. 52+100, LHS and at Ch. 52+220 to Ch.52+840, LHS and at Ch. 52+900 to Ch.53+100, LHS
Yes 18.07.14
83 1571/10.12.09 Earthworks MS-2 Earthworks in widening of existing carriageway at
Ch.53+750 to Ch. 54+100, LHS Yes 26.05.14
84 1625/31.12.09 WMM MS-2 WMM 2nd layer at Ch. 66+300 to Ch.66+470 (RHS) Yes 24.07.12
85 1628/01.01.10 DBM MS-2 DBM 1st layer at Ch. 30+630 to Ch. 30+700, LHS Yes 24.06.14
86 1635/04.01.10 DBM MS-2 DBM 2nd layer at Ch. 64+900 to Ch.65+000, RHS in part
width of 8m towards kerb side.
Yes 19.07.14
87 1684/18.01.10 Grade
Separator MS-2 Non-conforming product at Abutment A1, LHS of Grade
Separator at Ch.55+643 Yes 23.9.14
88 1685/18.01.10 Grade
Separator MS-2 Non-conforming product at pier P1, LHS of Grade
Separator at Ch.55+643 Yes 16.02.10
89 1699/21.01.10 DBM MS-2 Non-conforming DBM works at Ch. 31+220 to Ch.
31+400 on both sides of drain on RHS
Yes 02.08.14
90 1714/27.01.10 Embankment MS-2 Non-conforming embankment works at Ch. 78+290 to
Ch. 78+450 Yes 17.02.10
91 1772/10.02.10 DBM MS-2 DBM 1st layer at Ch. 29+680 to Ch. 29+830 (RHS) yes 20.08.10
92 1976/13.04.10 Earthwork MS-2 Earth Work in shoulder at Ch. 51+440 to Ch. 51+770,
LHS Yes 21.05.14
Independent Engineering Services for 4/6 Laning of NH-10 from Delhi/Haryana Border to Rohtak In the state of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
42
Monthly Progress Report: March 2015
in
association
with
NCPN
No.
Issued Ref./
Date
Type of
NCPN
Mile
Stone Description
Corrective Action
Accepted
YES/NO
Closed
Date
93 1983/14.04.10 DBM MS-2 DBM 1st layer with Grade-I material at Ch. 86+860 to Ch.
87+000, LHS Yes 05.04.12
94 1986/15.04.10 DBM MS-2 DBM 1st layer with Grade-I material at Ch. 86+850 to Ch.
87+140, RHS yes 31.08.10
95 1987/15.04.10 DBM MS-2 Thickness of DMB 1st layer at Ch. 31+700 to Ch. 31+720 Yes 21.07.14
96 2002/20.04.10 Earthwork MS-2 Earth work from Ch. 60+920 to Ch. 61+200 Yes 19.07.14
97 2060/08.05.10 Sub grade MS-2 Dismantling of existing bituminous layers for laying sub
grade/non-bituminous layers on existing road surface at
Ch. 61+850 to Ch. 62+190, LHS
yes 7.10.14
98 2061/08.05.10 BM MS-2 Laying of profile corrective course with BM material at Ch.
63+350 to Ch. 63+400, LHS and Ch 63+750 to Ch.
63+900, LHS.
yes 8.10.14
99 2062/08.05.10 DBM MS-2 Laying of DBM at Ch. 48+450 to Ch. 48+550, KHS Yes 25.06.14
100 2100/19.05.10 DBM MS-2 Laying of DBM 1st layer at Ch. 61+000 to Ch. 61+900,
LHS. Yes 01.08.14
101 2128/27.05.10 RE wall MS-2 Construction of RE wall at Ch 33+445 (toward
Bahadurgarh) - -
102 2166/05.06.10 BM MS-2 Back filling with excavated bituminous materials at Ch 63+590(Box culvert) LHS and Ch 64+395 (Box culvert) LHS
yes 20.06.14
103 2170/08.06.10 A. R. Bridge MS-2 Sand filling without checking excavation bottom levels at Ch 48+503 (AR Bridge) RHS Portion
yes 7.10.14
104 2189/15.06.10 Shoulder MS-2 Preparation of shoulder at Ch. 63+840 to Ch. 64+000,
LHS yes 09.05.12
105 2190/15.06.10 Sub grade MS-2 Dumping of GSB material on loose layer of sub grade at Ch. 58+800 to Ch. 59+000, RHS.
Yes 26.05.14
106 2206/19.06.10 MS-2 Strengthening and widening of existing carriageway at Ch. 57+600 to Ch. 58+280, RHS.
- -
107 2218/24.06.10 Minor Bridge MS-2 Concrete works at minor bridge at Ch. 88+393, RHS - -
108 2219/24.06.10 HPC MS-2 Laying of pipes and collar joints at Hume Pipe Culvert at
Ch. 78+282 Yes 26.07.10
109 2237/29.06.10 DBM MS-2 Laying of DBM 1st layer at Ch. 57+300 to Ch. 57+460,
LHS Yes 25.07.14
110 2238/29.06.10 Embankment
and sub grade
MS-2 Embankment and sub grade works at Ch. 60+020 to Ch.
60+230, RHS yes 11.10.10
111 2296/16.07.10 DBM
MS-2 Deficient thickness and surface level of DBM 2nd layer
from km. 31+000 to km. 31+230, LHS - -
112 2364/02.08.10 Grade Separator
MS-2 Compressive strength of concrete samples taken during
casting of girder for Grade Separator at Ch. 85+372 on
29th June 2010
yes 19.11.10
113 2379/07.08.10 DBM
MS-2 DBM 1st layer at Ch. 49+180 to Ch. 49+260, RHS. Yes 22.07.14
Independent Engineering Services for 4/6 Laning of NH-10 from Delhi/Haryana Border to Rohtak In the state of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
43
Monthly Progress Report: March 2015
in
association
with
NCPN
No.
Issued Ref./
Date
Type of
NCPN
Mile
Stone Description
Corrective Action
Accepted
YES/NO
Closed
Date
114 2399/13.08.10 GSB
MS-2 Thickness of GSB layer at Ch. 72+180 to Ch. 72+230,
both sides and Ch. 74 + 800 to Ch. 74+900, LHS. Yes 20.04.12
115 2408/14.08.10 DBM
MS-2 Laying of DBM 2nd layer at Ch. 48+820 to Ch. 48+900,
RHS
Yes 12.10.10
116 2409/14.08.10 RES works
MS-2 Reinforced fill material at Ch. 38+300 (LHS) - RES works
at the approaches of grade separator at Ch. 38+436
(Bahadurgarh side)
- -
117 2421/17.08.10 Embankment
MS-2 Earth work in Embankment at Ch.42+850 to Ch. 42+980,
Both sides Yes 22.07.14
118 2675/30.10.10 Pavement
MS-2 DBM 1st layer at Ch. 52+000 to Ch. 52+300, LHS Yes 04.04.12
119 2708/12.11.10 WMM
MS-2 Laying of WMM 1st layer from km. 52+210 to km.
52+340, LHS Yes 04.04.12
120 2753/30.11.10 Bituminous
Concrete MS-2
Use of aggregates from unapproved source for
bituminous course (BC) from km. 62+720 to km.63+210,
LHS
Yes 16.07.14
121 2754/30.11.10 Bituminous
Concrete MS-2
Use of aggregates from unapproved source for
bituminous course (BC) from km. 62+440 to km.62+720,
LHS
Yes 11.07.14
122 2793/11.12.10 Bituminous Concrete
MS-2 Non-conforming BC works from Ch. 75+100 to Ch.
75+640, RHS Yes 04.08.14
123 2831/22.12.10 Bituminous Concrete
MS-2 Laying of BC at CH. 31+950 to Ch. 32+800, RHS without
fixing of censor wires to achieve desired lines and grades - -
124 2841/27.12.10 Bituminous Concrete
MS-2 Laying of BC works at Ch.79+800 to Ch. 82+486, LHS at
low temperatures, poor workmanship and use of
arrangement from unapproved source.
- -
125 2843/28.12.10 DBM
MS-2
Laying of DBM 1st layer at Ch. 45+600 to Ch. 45+800,
RHS (widening portion) where prime coat was applied in
uncleaned surface and simultaneously work of laying
DBM 1st layer was being done.
Yes 28.06.14
126 2875/08.01.11 Embankment
MS-2 Application of prime coat and DBM 1st layer from km. 70+650 to km. 70+750, LHS carried out simultaneously.
Yes 04.02.11
127 2877/08.01.11 Embankment
MS-2 Execution of earthwork from km. 45+925 to km. 46+000,
LHS without carrying out clearing and grubbing. - -
128 2921/20.01.11 RES
MS-2 Reinforced earth fill materials from Ch. 33+510 to Ch.
33+820 (Rohtak side) and Ch. 33+100 to Ch. 33+400
(Bahadurgarh side)
- -
129 2923/20.01.11 RES
MS-2 Reinforced earth fill materials from Ch. 38+100 to Ch.
38+400 (Bahadurgarh side) and Ch. 38+480 to Ch.
38+800 (Rohtak side)
- -
130 2925/21.01.11 Bituminous Concrete
MS-2 Bituminous concrete works from Ch. 83+000 to Ch.
84+000 (both sides) Yes 07.04.12
131 3004/14.02.11 DBM
MS-2
Level difference was found much more than the
tolerances allowed as per table 900-1 as the work was
carried out during night and without using sensor wire
from Ch. 44+870 to Ch. 45+010, RHS (DBM top layer)
Yes 28.06.14
Independent Engineering Services for 4/6 Laning of NH-10 from Delhi/Haryana Border to Rohtak In the state of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
44
Monthly Progress Report: March 2015
in
association
with
NCPN
No.
Issued Ref./
Date
Type of
NCPN
Mile
Stone Description
Corrective Action
Accepted
YES/NO
Closed
Date
132 3470/09.07.11 PSC girder of Major Bridge
MS-2 Compressive strength of PSC girder of Major Bridge at
Ch. 82+617 was found non-conforming to specification
and specified strength of grade M-50
yes 30.04.12
133 3483/13.07.11 WMM
MS-2 The top levels of WMM surface at Ch. 42+000, LHS of
service road were not meeting the specified tolerance
criteria of MORT&H Section 900.
- -
134 3537/28.07.11 BC
MS-2
The top levels of Bituminous Concrete (BC) layer at Ch.
68+240 to Ch. 68+350 (RHS) were not meeting the
specified tolerance limits as per Clause 902.3 of
MORT&H.
- -
135 3621/25.08.11 PQC
MS-2 Finished Level of Pavement Quality Concrete from Ch.
52+560 (offset of 4m to 87m - 2nd lane from median) - -
136 4098/30.12.2011 RES
MS-2
Horizontal and vertical alignment of RES panels at Grade
Separator at Ch 55+643 (from Ch. 55+360 to Ch.
55+590) is not as per approved cross-sectional drawings
and submitted methodology of RES woks
- -
137 4099/30.12.2011 RES
MS-2 Non-conforming reinforced fill material used in the
approaches of Grade Separator at Ch. 55+643 - -
138 4158/12.01.12 DBM
MS-2
DBM 1st layer was done after WMM on the same day.
Prime coat was sprayed simultaneously with completion
of WMM on wet surface and primed surface was not
allowed to cure for at least 24 hours at Ch. 48+360 to
Ch. 48+490, LHS
Yes 24.07.14
139 4159/12.01.12 B.C.
MS-2
Surface of BC layer was not as per specification due to
faulty workmanship. The mix of BC was also appeared
faulty needing testing verification at Ch. 60+160 to Ch.
60+600, LHS
Yes 29.05.14
140 4162/13.01.12 Box culvert
MS-2 Box culvert constructed partly with pipe at the left hand
side and constructed wing wall parapet wall over pipe at
Ch. 48+485.
yes 28.03.12
141 4231/02.02.12 Embankment
MS-2 Use of unsuitable earth work materials at entry and exit
loops at Ch. 69+540, LHS. yes 30.05.12
142 4264/11.02.12 B. C.
MS-2 Laying of bituminous concrete layer from Ch. 66+500 to
Ch. 66+720, LHS Yes 28.05.14
143 4287/17.02.12 B. C.
MS-2 Laying of bituminous concrete at Ch. 55+610 to Ch.
55+671, LHS
Yes 24.07.14
144 4308/23.02.12 Minor Bridge
MS-2 Non-conforming works at minor bridge at Ch. 44+194 - -
145 4343/02.03.12 RES MS-2
Non-conforming reinforced earth fill materials in RES works at approaches of ROBs at Ch. 59+868 (RHS), Ch. 70+002 (both sides), Ch. 71+580 (both sides) Bahadurgarh side, Grade Separators at Ch. 76+076 (both sides) and Ch. 85+372(both sides) and Major Bridge at Ch. 78+549 (both sides).
yes 27.06.13
146 4411/19.03.12 W.M.M
MS-2 Non-conforming WMM materials dumped in 4 stretches between km. 76+140 to km. 79+430 and likewise regarding improper mixing of the material at Sunaria Camp site on 19th March 2012.
yes 22.05.12
Independent Engineering Services for 4/6 Laning of NH-10 from Delhi/Haryana Border to Rohtak In the state of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
45
Monthly Progress Report: March 2015
in
association
with
NCP
N
No.
Issued Ref./
Date
Type of
NCPN
Mile
Stone Description
Corrective Action
Accepted
YES/NO
Closed
Date
147 4412/19.03.12 Grade Separator
MS-2 Non-conforming alignment of RE wall and locking block
for Grade Separator at km. 76+076. - -
148 4835/10.07.12 WMM
MS-2 Use of non-conforming WMM materials from Ch. 70+120
to Ch. 70+200, RHS Yes 04.08.14
149 4890/23.07.12 RES
MS-2 Non-conforming RES works in the approaches of ROB at
Ch. 59+868 - -
150 4916/27.07.12 RES
MS-2 Non-conforming RES works in the approaches of ROB at
Ch. 59+868 (Bahadurgarh side) - -
151 5048/27.08.12 WMM
MS-2
Non-conforming WMM works in the approaches of ROB at
Ch. 59+868 (A1 side), approaches to minor bridge at Ch.
44+250 (A2 side) and junction.
- -
152 5061/30.08.12 GSP
MS-2 Defective fixing of expansion joint for Grade Separator at
Ch. 85+372, Abutment A-2 right hand side carriageway. - -
153 5097/07.09.12 RE Panel
MS-2
Bulging of RE wall panels of VUP at Ch. 69+723 in
Bahadurgarh side (LHS) approach Panel No.
13,14,15,16,17 from abutment (A-1) (1st & 2nd layer of
panel from top) due to poor workmanship in execution of
works and lack of proper supervision.
- -
154 5319/02.11.12 GSP
MS-2 Non-conforming level of PCC for cast-in-situ RCC friction
slab and RCC crash barrier at the approaches of Grade
Separator at km. 85+372
yes 19.04.13
155 5577/14.01.13 ROB
MS-2 Non-conforming reinforced earth wall works at the
approaches of ROB at Ch. 71+580 yes 12.07.13
156 5603/18.01.13 Subgrade/GSB
MS-2 Non-conforming level of subgrade/laying of GSB from
km. 36+200 to km. 36+500 - -
157 5694/08.02.13 WMM
MS-2 Non-conforming WMM works at Ch. 71+460 to
Ch. 71+560, LHS. Yes 27.06.13
158 5720/14.02.13 DBM
MS-2 Non-conforming DBM 1st layer at Ch. 71+380 to
Ch. 71+520, LHS (approaches of ROB at Ch. 71+580) Yes 06.11.14
159 5956/17.04.13 GSB
MS-2 Non-conforming GSB works at Ch. 71+620 to Ch. 71+860
(LHS) and Ch. 71+670 to Ch. 71+720 (RHS) Yes 25.06.14
160 5957/17.04.13 RE work
MS-2 Non-conforming reinforced earth works in the approaches
of ROB at Ch. 71+580 - -
Independent Engineering Services for 4/6 Laning of NH-10 from Delhi/Haryana Border to Rohtak In the state of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
46
Monthly Progress Report: March 2015
in
association
with
NCP
N
No.
Issued Ref./
Date
Type of
NCPN
Mile
Stone Description
Corrective Action
Accepted
YES/NO
Closed
Date
161 5990/26.04.13 Kerb
MS-2 Non-conforming horizontal alignment of kerbs laid from
Ch. 71+680 to Ch. 71+800, LHS Yes 30.07.13
162 6005/30.04.13 GSB
MS-2
Deficiencies on thickness of GSB and level of GSB top
where it is observed that the actual level was reduced
from 0.534m to 0.752m w.r.t. to the approved plan and
profile from km. 34+440 to km. 34+520, RHS Service
Road.
- -
163 6011/01.05.13 Overhead sign boards, gantry
structures
MS-2 Non-conforming overhead sign boards, gantry structures
and foundations along with photographs - -
164 6098/ 24.5.13 DBM layer
MS-2 Regarding non-conforming DBM layer in the stretch from
Km 35+750 to Km 36+500. Yes 27.06.13
165 6107/27.5.13 Levels of
bituminous concrete layer
MS-2
Regarding non-conforming levels of bituminous concrete
layer in the stretch from Km 71+600 to Km 71+900
(RHS).
- -
166 6868/19.12.13 Installation of Guard Posts.
MS-2 The guard posts being cast in situ are not as per
approved drawing and without providing reinforcement
stirrups (Ch. 70+000 to Ch. 82+000)
- -
167 6891/26.12.13 Laying of GSB and WMM materials
MS-2 The thickness and quality of WMM and GSB materials was
not conforming to specification requirements. Yes 28.05.14
Summary of NCPN as of 31st
March 2015:
Total number of NCPN issued : 167
Total number of NCPN closed : 137
Total number of NCPN outstanding : 30
Independent Engineering Services for 4/6 Laning of NH-10 from Delhi/Haryana Border to RohtakIn the state of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
47
in
associatio
n
14. CORRESPONDENCE BETWEEN INDEPENDENT ENGINEER AND THE CONCESSIONAIRE:
SL No.
Ref. Letter No./Date Directions given to the
Concessionaire Action taken by the Concessionaire
1 ICT/IC/NHAI/IND/NH-10/TL-
8273, 02nd March 2015
Drainage arrangement at grade
separator at Km. 33+400. Action is yet to be taken.
2 ICT/IC/NHAI/IND/NH-10/TL-
8280, 09th March 2015 Drainage/Maintenance Measures. Action has not been taken yet on
these works.
3 ICT/IC/NHAI/IND/NH-10/TL-
8281, 10th March 2015
Software Factory Acceptance Test
(FAT) in Techsture Technologies at
Ahmedabad-Reg.
Factory inspection has been conducted jointly by Independent Engineer/Concessionaire from 25th March 2015 to 28th March 2015.
4 ICT/IC/NHAI/IND/NH-10/TL-
8286, 12th March 2015
Construction of ROB over
Southern Bypass at L-xing No. A-
37 at Km. 71+580 on Rohtak-
Rewari Line (Deposit work)-Reg.
The Concessionaire is complying with the observation raised by the Project Director however revised estimate is yet to be submitted.
5 ICT/IC/NHAI/IND/NH-10/TL-
8287,12th March 2015 Quality of Earthwork materials.
The report is awaited.
6 ICT/IC/NHAI/IND/NH-10/TL-
8288, 12th March 2015
Meeting regarding safety
measures.
Action not taken yet. The Concessionaire is required to take action at the earliest.
7 ICT/IC/NHAI/IND/NH-10/TL-
8289, 12th March 2015
Monthly Progress Report February
2015. The MPR observations are yet to be complied with by the Concessionaire.
8 ICT/IC/NHAI/IND/NH-10/TL-
8290, 12th March 2015
Construction of ROB at Ch.
86+177 (Rohtak-Bhiwani Line).
The girder launching in track span has been completed. The cross bracings and intermediate cross girders are being fixed.
9 ICT/IC/NHAI/IND/NH-10/TL-
8294,14th March 2015
Construction of Service road in
Km. 35.000 (LHS).
No action has been taken yet by the Concessionaire to rectify the level deficiencies noted in the works of GSB.
10
ICT/IC/NHAI/IND/NH-10/TL-
8295, 14th March 2015 &
ICT/IC/NHAI/IND/NH-10/TL-
8312, 25th March 2015
Chief Minister Grievances Redress
and Monitoring System Haryana
(Complaint regarding repair of
road).
Temporary filling back of the trenches at slip road junctions has been done however permanent repair is yet to be carried out.
11 ICT/IC/NHAI/IND/NH-10/TL-
8299, 19th March 2015
Web Portal INAM- PRO- Platform
for Infrastructure and Material
Providers.
The Concessionaire has been advised to take necessary & appropriate actions.
Independent Engineering Services for 4/6 Laning of NH-10 from Delhi/Haryana Border to RohtakIn the state of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
48
in
associatio
n
SL No.
Ref. Letter No./Date Directions given to the
Concessionaire Action taken by the Concessionaire
12 ICT/IC/NHAI/IND/NH-10/TL-
8301, 21st March 2015
Timelines for ETC Implementation-
Reg.
The Change of Scope estimate for the implementation & ETC in 2 lanes in each direction is yet to submitted after complying with of the observations raised by the Toll Expert.
13 ICT/IC/NHAI/IND/NH-10/TL-
8305, 23rd March 2015 Illegal access on Rohtak Bypass. Adequate action is yet to be taken by
the Concessionaire.
14 ICT/IC/NHAI/IND/NH-10/TL-
8306, 24th March 2015
Sub-standard quality of WMM
materials. The compliance report is yet to be submitted by the Concessionaire.
15 ICT/IC/NHAI/IND/NH-10/TL-
8308, 24th March 2015
Shifting of Gantry pole on Jakhoda
mor to Assauda mor (44.450)
Chainage in Jhajjar Distt.
The Concessionaire has inspected the site at their own level and has informed this office verbally to take action at the earliest.
16 ICT/IC/NHAI/IND/NH-10/TL-
8309, 24th March 2015 Updation of PMIS Status-Reg.
The Concessionaire is required to take actions regularly for online updation of the status of PMIS.
15. Force Majeure Event:
No such event occurred this month.
Independent Engineering Services for 4/6 Laning of NH-10 from Delhi/Haryana Border to RohtakIn the state of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT-II/NH-10/HRY/004
49
Monthly Progress Report: March 2015
in
associatio
n
16. REDRESSAL OF GRIEVANCES
Sl. No. Public Grievance Redressal Action
1.
Residents of village Ismaila requested to Project Director for completing the balance work at CUP at Km. 60+600 and this office was intimated vide his letter No. NHAI/PIU-RTK/B-H/14-15/272 dated 02 May 2014
Work taken in hand but stopped in incomplete condition
2.
Application from Sarpanch of village Bhambhewa regarding construction of service road from CUP at Km. 71+650 to Km. 71+875 (Pehrawar Bhambhewa road) and extension of retaining wall received vide Project Director letter No.681, dated 11th June 2014.
Concessionaire has been asked to complete LHS service road and extend the retaining walls at the earliest and Sarpanch of village Bhambhewa has been informed accordingly vide Project Director letter No. 815, dated 26th June 2014.
The Concessionaire has not taken up the work on A1 side for construction of retaining walls on both sides.
3
Repair of slip roads trenches at the grade separator at Ch. 79+207 (Both sides) under Chief Minister Grievances Redress and monitoring system Haryana.
Temporary measures have been done by filling the trenches by GSB materials however permanent repairs are yet to be done by the Concessionaire.
Sl.
No.Name Position
Date of
MobilizationAssigned Package Remarks
1 Mr. Eleazar S. RegondolaTeam Leader-cum-Senior Highway
Engineer19.06.08 Whole contract Package On leave
2 Mr. James Cooper Road Safety Expert29.12.09
Whole contract Package
1 Mr. Balbir Singh Jayas Sr.Bridge Design Engineer 19.06.08 Whole contract Package Resigned
2 Mr.Rajeev Kumar Makhija Trafic & Transport Expert06.09.10 Whole contract Package
3 Dr. P. K. Nanda Sr. Pavement Specialist 24.09.09 Whole contract Package
4 Mr. Rajiv Kumar Sr. Quality / Material Expert 14.07.08 Whole contract Package
5 Mr. Amitava Basu Financial Expert Whole contract Package
6 Mr. Vikas Goel Legalal Expert Whole contract Package
1 Mr. Mehmood Sardar Survey Engineer 18.08.08 Whole contract Package
2 Mr. Balbir Singh Chhikara Highway Engineer-1 19.06.08 Whole contract Package
3 Mr. R. N. Bansal Highway Engineer-2 19.06.08 Whole contract PackageDemobilized on
31.03.2011
4 Mr. Vijay Setia Asst. Highway Engineer-1 04.05.09 Whole contract Package
5 Mr. Anil Kumar Asst. Highway Engineer-2 22.07.08 Whole contract PackageDemobilized on
31.03.2011
6 Mr. Jagan Mohan Pattnaik Bridge/ Structural Engineer 04.09.08 Whole contract PackageDemobilized on
05.09.2012
7Mr. Dharmendra Kumar/Mr.
Chinmaya Kumar MallickCAD Expert 08.03.10 Whole contract Package
Replacement of Mr.
Dharmendra Kumar
8Mr. Shambhu Nath Singh/Mr.
Sujeet KumarEnvirnmental Engineer 06.10.09 Whole contract Package
9 Mr. Rakesh Kumar Ass. Bridge Engineer -1 26.08.10 Whole contract Package Resigned
10 Mr. Shailendra B. Singh Ass. Bridge Engineer -2 07.06.10 Whole contract Package
11 Mr. Tarkeshwar Nath Asst. Quality cum Material Engineer 25.07.08 Whole contract Package Resigned
12 Mr. Prashant Dixit Asst. Quality cum Material Engineer 06.10.10 Whole contract Package
13 Mr. Adhir Kumar Pani Electrical Engineer 11.05.09 Whole contract Package
14 Mr. Manish Deshpande HTMS/Tolling Expert 28.03.11 Whole contract Package
1Mr. Sandeep Sharma/Mr.
Himanshu Singh SajwanOffice Manager 01.04.09 Site Office
Demobilized on
31.07.2013
2Mr. Bhabani Sankar Rana/Mr.
B. K. MohantyAccountant 01.07.08 Site Office
Replacement of Mr. B. S.
Rana
3Mr. Deepak Kumar/Brajendu
Kumar MohantyCashier 01.04.09 Site Office
Demobilized on
31.07.2013
4 Mr. Sharad Pratap Singh Steno 20.06.08 Site Office
5
Mr. Brajendu Ku. Mohanty/
Jagdeep / Mr. Brajendu Ku.
Mohanty/Sushil Kumar
Computer Operator 01.08.13 Site OfficeReplacement of Mr. B.K.
Mohanty
6 Mr. Chhabi Lal Sharma Photocopy Machine Operator 20.06.08 Site OfficeDemobilized on
31.07.2013
7Mr. Pradeep Ku. Rana /
Mr. Chhabi Lal SharmaOffice Boy 01.08.13 Site Office
Replacement of Mr.
Pradeep Ku. Rana
8
Mr. Suresh Chand /
Mr. Rabindra Deonath/Mr.
Chandan Singh
Guard-1 20.06.08 Site OfficeReplacement of Mr.
Rabindra Deonath
9 Mr.Bhim Bahadur Guard-2 01.08.09 Site Office
Independent Engineering Services for 4/6 laning of NH-10 of Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase - III (A)
Package No. IE/BOT-II/NH-10/HRY/004
Details of mobilization of Independent Engineer's Staff
50 Monthly Progress Report: March 2015
(a) Expatriate:
(d) Support Staff:
( c) Sub Professional:
(b) Key Professional:
31st March2015
in association
with
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III (A)
Package No. IE/BOT/-II/NH-10/HRY/004
51 Monthly Progress Report: March 2015
in
association
with
DETAILS Of THE CONCESSIONAIRE’S SITE STAFF (SPV)
SL.
NO.
NAME DESIGNATION
1 MR. Sanjay Kumar Sharma PROJECT DIRECTOR
2 MR. G. K. SINGH MATERIAL ENGINEER
3 MR. SANDEEP ARYA AUTO CAD OPERATOR
4 MR. NAVAL KUMAR TOLL OPERATIONS
DETAILS Of THE CONCESSIONAIRE’S SITE STAFF (EPC)
SL.
NO.
NAME DESIGNATION
1 Alok Asthana Project Manager
2 Pawan Sharma Highway Engineer
3 MR. RAJEEV KUMAR JHA SAFETY ENGINEER
4 MR. SURENDRA SINGH PROJECT ENGINEER-HIGHWAY
5 MR. BHUPENDRA SINGH SUPERVISOR
6 MR. MD.NAZIM SUPERVISOR
7 MR. AMARJEET YADAV FOREMAN
8 MR. KULBIR SINGH SODHI FOREMAN
9 MR. KRISHNA SINGH SR SUPERVISOR
10 MR. KAUSHAL KUMAR SITE ENGINEER
11 MR. SATYENDRA KUMAR JR.SUPERVISOR
12 MR. RAM KUMAR SRIVASTAV LAB TECHNICIAN
13 MR. MANISH KUMAR MATERIAL RECEIVER
14 MR. RAJESH KUMAR MATERIAL RECIEVER
15 MR. KR.MANOJ KUMAR SR.FOREMAN-ELECTRICAL
16 MR. MANAS KUMAR SAMAL MECHANIC
17 MR. BED PRAKASH DY..SUPERVISOR
18 MR. LAXMAN KUSHWAHA WELDER
19 MR. PANKAJ CHATURVEDI OFFICER ACCOUNT
20 MR. BIJENDRA KUMAR SURVEYOR
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III(A)
Package No IE/BOT-II/NH-10/HRY-004
Tested Passed Failed Remarks
1.1 No. of Borrow Areas 1 1 0
1.2 Sample Collection 3 3 0
1.3 Gradation IS:2720 (Part - 4) As Required 3 3 0
1.4 Plasticity Index Test IS:2720 (Part - 5) As Required 3 3 0
1.5 Free Swell Index Test IS:2720 (Part-40) As Required 1 1 0
1.6 Proctor Density Test IS:2720 (Part - 8) As Required 3 3 0
1.7 Deleterious Content Test IS:2720 (Part -27) As Required 0 0 0
1.8 CBR IS:2720 (Part - 16) As Required 1 1 0
2.1 Sample Collection 0 0 0
2.2 Gradation IS:2720 (Part - 4) As Required 0 0 0
2.3 Plasticity Index Test IS:2720 (Part - 5) As Required 0 0 0
2.4 Free Swell Index Test IS:2720 (Part-40) As Required 0 0 0
2.5 Proctor Density Test IS:2720 (Part - 8) As Required 0 0 0
2.6 Deleterious Content Test IS:2720 (Part -27) As Required 0 0 0
2.7 Field density Test IS:2720 (Part -28) As Required 0 0 0
2.8 CBR IS:2720 (Part -16) As Required 0 0 0
3.1 Gradation IS:2720 (Part - 4) 1 test / 1500 M3 3 3 0
3.2 Plasticity Index Test IS:2720 (Part - 5) 1 test / 1500 M3 3 3 0
3.3 Free Swell Index Test IS:2720 (Part-40) As Required 1 1 0
3.4 Proctor Density Test IS:2720 (Part - 8) 1 test / 1500 M3 3 3 0
3.5 Deleterious Content Test IS:2720 (Part -27) As Required 0 0 0
3.6 Field density Test IS:2720 (Part -28) 1 test / 1000 M2 18 18 0
4.0 Sub Grade (MORTH : 305)
4.1 Gradation IS:2720 (Part - 4) 1 test / 1500 M3
2 2 0
4.2 Plasticity Index Test IS:2720 (Part - 5) 1 test / 1500 M3 2 2 0
4.3 Free Swell Index Test IS:2720 (Part-40) As Required 1 1 0
4.4 Proctor Density Test IS:2720 (Part - 8) 1 test / 1500 M3 2 2 0
4.5 Deleterious Content Test IS:2720 (Part -27) As Required 0 0 0
4.6 CBR IS:2720 (Part -16) 1 test / 3000 M3 1 1 0
4.7 Field density Test IS:2720 (Part -28) 1 test / 500 M2 12 12 0
5.1 Gradation IS:2720 (Part - 4) 1 test / 200 M3 5 5 0
5.2 Plasticity Index Test IS:2720 (Part - 5) 1 test / 200 M3 5 5 0
5.3 Proctor Density Test IS:2720 (Part - 8) As Required 0 0 0
5.4 Water Absorption IS:2386 (Part - 3) As Required 0 0 0
5.5 10 % Fine Value BS - 812 (Part - 3) As Required 0 0 0
5.6 CBR IS:2720 (Part -16) As Required 0 0 0
5.7 Field density Test IS:2720 (Part -28) 1 test / 500 M2 8 8 0
6.1 Gradation IS:2720 (Part - 4) 1 test / 100 M3 6 6 0
6.2 Plasticity Index Test IS:2720 (Part - 5) 1 test / 100 M3 6 6 0
6.3 Proctor Density Test IS:2720 (Part - 8) As Required 0 0 0
6.4 Aggregate Impact Value IS:2386 (Part - 4) 1 test / 200 M3 3 3 0
6.5 Flakiness & Elongation Index IS:2386 (Part - 1) 1 test / 200 M3 3 3 0
6.6 Water Absorption IS:2386 (Part - 3) As Required 0 0 0
6.7 Soundness Value IS:2386 (Part - 5) As Required 0 0 0
6.8 Field density Test IS:2720 (Part -28) 1 test / 500 M2 10 10 0
7.1 Gradation IS:383 1 Test / 15 Days 5 5 0
7.1 Silt Content IS:383 1 Test / 15 Days 2 2 0
7.3 Specific Gravity Water Absorption IS:2386 (Part - 3) As Required 0 0 0
8.1 Gradation IS:383 1 Test / 15 Days 5 5 0
8.2 Aggregate Impact Value IS:2386 (Part - 4) 1 Test / 15 Days 5 5 0
8.3 Flakiness Index IS:2386 (Part - 1) 1 Test / 15 Days 5 5 0
8.4 Specific Gravity & Water Absorption IS:2386 (Part - 3) As Required 0 0 0
9.1 Fineness Value IS :4031 (Part-1) Every Batch 1 1 0
9.2 Consistency IS :4031 (Part-4) Every Batch 1 1 0
9.3 Setting Time (Initial & Final) IS :4031 (Part-5) Every Batch 1 1 0
9.4 Soundness IS :4031 (Part-3) Every Batch 0 0 0
9.5 Compressive Strength (3 Days) IS :4031 (Part-6) Every Batch 3 3 0
9.6 Compressive Strength (7 Days) IS :4031 (Part-6) Every Batch 3 3 0
9.7 Compressive Strength (28 Days) IS :4031 (Part-6) Every Batch 3 3 0
8.0 Coarse Aggregate (MORTH : 1008)
9.0 Cement (MORTH : 1006)
1.0 Test on Borrow Areas (MORTH 305)
2.0 Test on OGL Sample (MORTH : 305)
3.0 Embankment (MORTH : 305)
5.0 Granular Sub Base (MORTH : 401)
6.0 Wet Mix Macadam (MORTH : 406)
7.0 Fine Aggregate (MORTH : 1008)
QUALITY ASSURANCE TEST RECORDS FOR THE MONTH OF March 2015
Sl. No. DescriptionIS / Project Spec.
ClauseFrequency of Tests
Total Test for the Month of March 2015
Monthly Progress Report : March 2015
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III(A)
Package No IE/BOT-II/NH-10/HRY-004
Tested Passed Failed RemarksSl. No. Description
IS / Project Spec.
ClauseFrequency of Tests
Total Test for the Month of March 2015
10.1 Mix Design IS: 10262 MORTH 1700 0 0 0
10.2 Cube Test (7Days) IS: 516 MORTH 1700 9 9 0
10.3 Cube Test (28Days) IS: 516 MORTH 1700 15 15 0
11.1 Rate of Spray MORTH - 500 2 Test /Day0 0 0
11.2 Viscosity IS: 8887 Every Batch 0 0 0
11.3 Residue by evaporation IS: 8887 Every Batch 0 0 0
11.4 Penetration of Residue IS:1203 Every Batch 0 0 0
11.5 Ductility of Residue IS:1208 Every Batch 0 0 0
11.6 Residue on 600 micron IS: 8887 Every Batch 0 0 0
11.7 Miscibility of water IS: 8887 Every Batch 0 0 0
12.1 Rate of Spray MORTH - 500 2 Test /Day 0 0 0
12.2 Viscosity IS: 8887 Every Batch 0 0 0
12.3 Residue by evaporation IS: 8887 Every Batch 0 0 0
12.4 Penetration of Residue IS:1203 Every Batch 0 0 0
12.5 Ductility of Residue IS:1208 Every Batch 0 0 0
12.6 Residue on 600 micron IS: 8887 Every Batch 0 0 0
12.7 Miscibility of water IS: 8887 Every Batch 0 0 0
13.1 Penetration Test IS:1203 Every Batch 2 2 0
13.2 Softening Point Test IS:1205 Every Batch 2 2 0
13.3 Ductility Test IS:1208 Every Batch 2 2 0
13.4 Flash Point Test IS:1209 Every Batch 0 0 0
13.5 Specific Gravity IS:1202 Every Batch 0 0 0
13.6 Absolute Viscosity IS:1206 Every Lot 0 0 0
13.7 Kinematic Viscosity IS:1206 Every Lot 0 0 0
14.1 Penetration Test IS:1203 Every Batch 0 0 0
14.2 Softening Point Test IS:1205 Every Batch 0 0 0
14.3 Ductility Test IS:1208 Every Batch 0 0 0
14.4 Flash Point Test IS:1209 Every Batch 0 0 0
14.5 Specific Gravity IS:1202 Every Batch 0 0 0
14.6 Elastic Recovery of half tread IRC:SP:53 Every Batch 0 0 0
15.1 Mix Grading Table : 500-41 Test/400 ton min 2
sets/day0 0 0
15.2 Hot Bin Aggregate Table : 500-4 1test/each fraction 0 0 0
15.3 Mix Density Table : 500-41 sets/400 ton min 2
sets/day0 0 0
15.4 Bitumen Extraction Grading Table : 500-41 sets/400 ton min 2
test/day0 0 0
15.5 Water Sensitivity Test AASHTO: T-283 As Required 0 0 0
15.6 Core Test Table : 900-4 1 test / 250 M2 0 0 0
15.7 Aggregate Impact Value IS:2386 (Part - 4) 1 test / 50 M3 0 0 0
15.8 Flakiness & Elongation Index IS:2386 (Part - 1) 1 test / 50 M3 0 0 0
15.9 Specific Gravity & water absorption IS:2386 (Part - 3) As Required 0 0 0
15.10 Soundness Test IS:2386 (Part - 5) As Required 0 0 0
15.11 Sand Equivalent Value IS:2720 (Part -37) As Required 0 0 0
15.12 Plasticity Index Test IS:2720 (Part -5) As Required 0 0 0
15.13 % of Fractured Faces MORTH - 500.2.2 As Required 0 0 0
15.14 Stripping Value IS:6241 As Required 0 0 0
16.0 Semi Dense Bituminous Concrete (MORTH : 508)
16.1 Mix Grading Table : 500-151 Test/400 ton min 2
sets/day0 0 0
16.2 Hot Bin Aggregate Table : 500-15 1test/each fraction 0 0 0
16.3 Marshall Density, Stability & Flow Table : 500-16
1 Test/400 ton min 2
sets/day0 0 0
16.4 VIM, VMA, VFB Table : 500-162 Test/400 ton min 2
test/day0 0 0
16.5 Bitumen Extraction Grading Table : 5001 Test/400 ton min 2
sets/day0 0 0
16.6 Water Sensitivity Test AASHTO: T-283 As Required 0 0 0
16.7 Core Test Table : 500 1 test / 250 M2 0 0 0
16.8 Aggregate Impact Value IS:2386 (Part - 4) 1 test / 50 M2 0 0 0
16.9 Flakiness & Elongation Index IS:2386 (Part - 1) 1 test / 50 M2 0 0 0
16.10 Specific Gravity & water absorption IS:2386 (Part - 3) As Required 0 0 0
16.11 Soundness Test IS:2386 (Part - 5) As Required 0 0 0
16.12 Sand Equivalent Value IS:2720 (Part -37) As Required 0 0 0
16.13 Plasticity Index Test IS:2720 (Part -5) As Required 0 0 0
16.14 % of Fractured Faces MoRTH - 500.2.2 As Required 0 0 0
16.15 Stripping Value IS:6241 As Required 0 0 0
14.0 Modified Bitumen (IRC: 53)
15.0 Bituminous Macadam (MORTH : 500)
10.0 Concrete (MORTH : 1700)
11.0 Prime Coat:
12.0 Tack Coat :
13.0 Bitumen (MORTH : 500)
Monthly Progress Report : March 2015
Independent Engineering Services for 4/6 laning of NH-10 from Delhi/Haryana Border to Rohtak
In the State of Haryana on BOT basis Under NHDP Phase III(A)
Package No IE/BOT-II/NH-10/HRY-004
Tested Passed Failed RemarksSl. No. Description
IS / Project Spec.
ClauseFrequency of Tests
Total Test for the Month of March 2015
17.1 Mix Grading Table : 500-10
1 Test/400 ton min 2
sets/day0 0 0
17.2 Hot Bin Aggregate Table : 500-10 1test/each fraction 0 0 0
17.3 Marshall Density, Stability & Flow Table : 500-111 Test/400 ton min 2
sets/day0 0 0
17.4 VIM, VMA, VFB Table : 500-122 Test/400 ton min 2
sets/day0 0 0
17.5 Bitumen Extraction Grading Table : 500-101 Test/400 ton min 2
sets/day0 0 0
17.6 Water Sensitivity Test AASHTO: T-283 As Required 0 0 0
17.7 Core Test Table : 900-4 1 test / 250 M2 0 0 0
17.8 Aggregate Impact Value IS:2386 (Part - 4) 1 test / 50 M3 0 0 0
17.9 Flakiness & Elongation Index IS:2386 (Part - 1) 1 test / 50 M3 0 0 0
17.10 Specific Gravity & water absorption IS:2386 (Part - 3) As Required 0 0 0
17.11 Soundness Test IS:2386 (Part - 5) As Required 0 0 0
17.12 Sand Equivalent Value IS:2720 (Part -37) As Required 0 0 0
17.13 Plasticity Index Test IS:2720 (Part -5) As Required 0 0 0
17.14 % of Fractured Faces MoRTH - 500.2.2 As Required 0 0 0
17.15 Stripping Value IS:6241 As Required 0 0 0
18.1 Mix Grading Table : 500-181 Test/400 ton min 2
test/day0 0 0
18.2 Hot Bin Aggregate Table : 500-18 1test/each fraction 0 0 0
18.3 Marshall Density, Stability & Flow Table : 500-191 Test/400 ton min 2
test/day0 0 0
18.4 VIM, VMA, VFB Table : 500-192 Test/400 ton min 2
test/day0 0 0
18.5 Bitumen Extraction Grading Table : 500-181 Test/400 ton min 2
test/day0 0 0
18.6 Water Sensitivity Test AASHTO: T-283 As Required 0 0 0
18.7 Core Test Table : 900-4 1 test / 250 M2 0 0 0
18.8 Aggregate Impact Value IS:2386 (Part - 4) 1 test / 50 M2 0 0 0
18.9 Flakiness & Elongation Index IS:2386 (Part - 1) 1 test / 50 M2 0 0 0
18.10 Specific Gravity & water absorption IS:2386 (Part - 3) As Required 0 0 0
18.11 Soundness Test IS:2386 (Part - 5) As Required 0 0 0
18.12 Sand Equivalent Value IS:2720 (Part -37) As Required 0 0 0
18.13 Plasticity Index Test IS:2720 (Part -5) As Required 0 0 0
18.14 % of Fractured Faces MoRTH - 500.2.2 As Required 0 0 0
18.15 Stripping Value IS:6241 As Required 0 0 0
19.1 No. of Pipes test 0 0 0
19.2 Physical Test IS: 458 As per IS : 458 0 0 0
19.3 Three edge bearing test IS: 458 As per IS : 458 0 0 0
19.4 Water Absorption test IS: 458 As per IS : 458 0 0 0
20.0 Manufacturing Test reports / Third Party Test reports
20.1 Cement IS : 4031 Every Batch 1 1 0
20.2 Steel IS : 1786 Every Batch 0 0 0
20.3 Bitumen IS : 1200 - 1220 Every Batch 2 2 0
20.4 Admixture IS : 9103 Every Batch 0 0 0
20.5 Stand Wire IS : 14268 Every Batch 0 0 0
20.6 Emulsion SS IS : 8887 Every Batch 0 0 0
20.7 Emulsion RS IS : 8887 Every Batch 0 0 0
21.1 Cube Test (7Days) IS: 516 MORTH 900 0 0 0
22.1 Mix Design IS: 10262 MORTH 1700 0 0 0
22.2 Cube Test (7Days) IS: 516 MORTH 1700 0 0 0
22.3 Cube Test (28Days) IS: 516 MORTH 1700 0 0 0
22.4 Flexural Test (7days) IS: 516 MORTH 900 0 0 0
22.5 Flexural Test (28days) IS: 516 MORTH 900 0 0 0
23.1 Dimension IS: 1077 MORTH 1000 0 0 0
23.2 Water Absorption test IS: 3495 MORTH 1000 0 0 0
23.3 Compressive Strength IS: 3495 MORTH 1000 0 0 0
23.4 Efflorescence IS :3495 MORTH 1000 0 0 0
24.1 Hardness Number Table : 515.3 As Required 0 0 0
24.2 Bitumen Extraction Grading Table : 500-18 Periodic, 2test/day 0 0 0
24.3 Water Sensitivity Test AASHTO: T-283 As Required 0 0 0
24.4 Aggregate Impact Value IS:2386 (Part - 4) 1 test / 50 M2 0 0 0
24.5 Flakiness & Elongation Index IS:2386 (Part - 1) 1 test / 50 M2 0 0 0
24.6 Specific Gravity & water absorption IS:2386 (Part - 3) As Required 0 0 0
24.7 Soundness Test IS:2386 (Part - 5) As Required 0 0 0
24.8 Sand Equivalent Value IS:2720 (Part -37) As Required 0 0 0
24.9 Plasticity Index Test IS:2720 (Part -5) As Required 0 0 0
24.1 % of Fractured Faces MoRTH - 500.2.2 As Required 0 0 0
24.11 Stripping Value IS:6241 As Required 0 0 0
22.0 Pavement Quality Concrete for toll plaza area
23.0 Brick Work (MORTH : 1000)
24.0 Mastic Asphalt (MORTH: 515)
17.0 Dense Bituminous Macadam (MORTH : 507)
18.0 Bituminous Concrete (MORTH : 509)
19.0 Hume Pipes (MORTH : 2100)
21.0 Dry Lean Concrete for toll plaza area
Monthly Progress Report : March 2015