+ All Categories
Home > Documents > Page 44 • May 4, 2019 • …archive.constructionequipmentguide.com/web_edit...May 04, 2019  ·...

Page 44 • May 4, 2019 • …archive.constructionequipmentguide.com/web_edit...May 04, 2019  ·...

Date post: 03-Oct-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
1
Page 44 • May 4, 2019 • www.constructionequipmentguide.com • CONSTRUCTION EQUIPMENT GUIDE As Spring Arrives, Highway Repair Proceeds in Phases MnDOT prepare residents for the upcoming work, which will see one half of the east- west highway closed to give crews a safe work zone. The plan is based on staged detours of Route 59 overpass bridges and ramps, various lane closures and a lane crossover on Route 2. PCi began the work last October and completed the temporary crossovers just before Thanksgiving. Bill Hines, PCi’s proj- ect manager, is assisted by Rachel Wedig, the onsite construction manager. “With our spring load restrictions, PCi wants to start in early May or as soon as they can,” Groven said. “The work on the crossovers was done rapidly. They brought in some grading and base materials. We were hit with early snow in October and they had to wait until we got some warmer weather to melt it off and be able to pave it in.” No major construction challenges are expected, although nothing is being taken for granted in case there are problems with gravel and clay subbases. “Some of these concerns were alleviated when they decided to do a concrete overlay,” said Groven, who added that there are no utility issues. “The contract was awarded last spring with the idea that they could start con- struction in the summer and continue into this year. PCi chose to develop a plan to do everything at once. They have had plenty of time to plan the schedule. Communication with PCi has been good, and we’ve worked well as a team to create a project team — MnDOT, PCi, and Alliant.” The general contractor is looking to rent some properties to set up a concrete batch plant and laydown yards. There is a good possibility that an MnDOT right of way can be secured, as well as an MnDOT truck station half a mile from the project, or spaces in Erskine. “If they can start in May, it should take a few months to repair one side of the road,” said Groven. “The work will be done in sec- tions. We can only allow them to close cer- tain direction ramps for a certain amount of time and they can only close the Highway 59 portion for a certain period. There’s also the weigh station on the east end of the project for which access has to be maintained.” The two bridges are located at the Route 59 interchange, with one crossing Route 2 and the other spanning a railway. Work on the bridges will be done simultaneously with the road work. “Once they close Highway 59, they’ll do all the bridge work in one time slot,” said Groven. “The bridge over Highway 2 is a concrete girder one, so it’s mainly just deck repairs and the approach panels on both sides. The bridge over the railroad is a steel beam one, so for that we are repainting it, and repairing the deck and approach panels. We’ve had PCi perform work on other bridge rehabilitation projects and they’ve done really well. It’s a well-oiled machine when it comes to their work. They come in and get her done.” For the replacement of curb, gutter, storm sewer and culverts along Route 2, the plan is to have crews replace the infrastructure on the side of the road being repaired, with the possibility that some underground work could also be done on the other side. Concrete pipe may be ordered, and orders may also include prefabricated catch basins and manholes. Peak days in spring will have close to 65 workers on site. Subcontractors include Hoffman Construction Company for removals, grading, base, and underground; Knife River Materials for bituminous paving; Subsurface Inc. for manhole rehabil- itation; H&R Construction for guardrails and signage; Sherbrooke Turf for landscap- ing and erosion control; NECI for surveying; and Warning Lites for traffic control. Removals from the existing road are expected to yield concrete and asphalt to be recycled on site and reused as aggregate base material. New materials should include 30,000 cu. yds. of concrete,7500 tons of asphalt, and 10,000 tons of aggregate base. Equipment to be used on the proj- ect includes lifts, concrete and bitu- minous pavers, a concrete batch plant, milling machines, grinding machines, and crushing machines. PCi uses Guntert Zimmerman slip- form pavers, Rexcon concrete plants, a substantial number of Caterpillar products, Wirtgen milling machines and Bidwell paving machines. “We’ve encountered some weath- er-related factors,” said Hines, noting that the repairs are done based on the severity of the problem, “We have several onsite mechanics with the paving crews and grading crews. We refurbish and restore equipment dur- ing the off season, and we do regular seasonal maintenance to keep the fleet in an efficient state.” Hines expects that some rented equipment will be used on the proj- ect. PCi purchases equipment from regional and local dealerships. Hines said he is looking forward to the start of work in the spring and pointed out that all projects provide opportunities to pro- mote employees and improve skills. “We train in the areas of safety quality, and environmental compliance to all employees and stakeholders,” he said. CEG HIGHWAY from page 1 PCi Roads photo PCi uses Guntert Zimmerman slipform pavers, as well as Rexcon concrete plants. MnDOT photo With proper construction techniques and dowel alignments with the joints, a concrete pavement can last a long time, said MnDOT project manager Shawn Groven. PCi Roads photo Materials used in the project are expected to include 30,000 cu. yds. of concrete.
Transcript
Page 1: Page 44 • May 4, 2019 • …archive.constructionequipmentguide.com/web_edit...May 04, 2019  · possibility that some underground work could also be done on the other side. Concrete

Page 44 • May 4, 2019 • www.constructionequipmentguide.com • CONSTRUCTION EQUIPMENT GUIDE

As Spring Arrives, Highway Repair Proceeds in Phases MnDOT prepare residents for the upcomingwork, which will see one half of the east-west highway closed to give crews a safework zone. The plan is based on stageddetours of Route 59 overpass bridges andramps, various lane closures and a lanecrossover on Route 2. PCi began the work last October and

completed the temporary crossovers justbefore Thanksgiving. Bill Hines, PCi’s proj-ect manager, is assisted by Rachel Wedig,the onsite construction manager.“With our spring load restrictions, PCi

wants to start in early May or as soon as theycan,” Groven said. “The work on thecrossovers was done rapidly. They broughtin some grading and base materials. Wewere hit with early snow in October and theyhad to wait until we got some warmerweather to melt it off and be able to pave itin.”No major construction challenges are

expected, although nothing is being takenfor granted in case there are problems withgravel and clay subbases.

“Some of these concerns were alleviatedwhen they decided to do a concrete overlay,”said Groven, who added that there are noutility issues. “The contract was awarded lastspring with the idea that they could start con-struction in the summer and continue intothis year. PCi chose to develop a plan to doeverything at once. They have had plenty oftime to plan the schedule. Communicationwith PCi has been good, and we’ve workedwell as a team to create a project team —MnDOT, PCi, and Alliant.”The general contractor is looking to rent

some properties to set up a concrete batchplant and laydown yards. There is a good

possibility that anMnDOT right of way canbe secured, as well as anMnDOT truck station halfa mile from the project, or spaces in Erskine.“If they can start in May, it should take a

few months to repair one side of the road,”said Groven. “The work will be done in sec-tions. We can only allow them to close cer-tain direction ramps for a certain amount oftime and they can only close the Highway 59portion for a certain period. There’s also theweigh station on the east end of the projectfor which access has to be maintained.”The two bridges are located at the Route

59 interchange, with one crossing Route 2and the other spanning a railway. Work onthe bridges will be done simultaneously withthe road work.“Once they close Highway 59, they’ll do

all the bridge work in one time slot,” saidGroven. “The bridge over Highway 2 is aconcrete girder one, so it’s mainly just deckrepairs and the approach panels on bothsides. The bridge over the railroad is a steelbeam one, so for that we are repainting it,

and repairing the deck and approach panels.We’ve had PCi perform work on otherbridge rehabilitation projects and they’vedone really well. It’s a well-oiled machinewhen it comes to their work. They come inand get her done.”For the replacement of curb, gutter, storm

sewer and culverts along Route 2, the plan isto have crews replace the infrastructure onthe side of the road being repaired, with thepossibility that some underground workcould also be done on the other side.Concrete pipe may be ordered, and ordersmay also include prefabricated catch basinsand manholes.Peak days in spring will have close to 65

workers on site. Subcontractors includeHoffman Construction Company forremovals, grading, base, and underground;Knife River Materials for bituminouspaving; Subsurface Inc. for manhole rehabil-itation; H&R Construction for guardrailsand signage; Sherbrooke Turf for landscap-ing and erosion control; NECI for surveying;and Warning Lites for traffic control.Removals from the existing road are

expected to yield concrete and asphalt to berecycled on site and reused as aggregate basematerial.New materials should include 30,000 cu.

yds. of concrete,7500 tons of asphalt, and10,000 tons of aggregate base.Equipment to be used on the proj-

ect includes lifts, concrete and bitu-minous pavers, a concrete batchplant, milling machines, grindingmachines, and crushing machines.PCi uses Guntert Zimmerman slip-form pavers, Rexcon concrete plants,a substantial number of Caterpillarproducts, Wirtgen milling machinesand Bidwell paving machines.“We’ve encountered some weath-

er-related factors,” said Hines, notingthat the repairs are done based on theseverity of the problem, “We haveseveral onsite mechanics with thepaving crews and grading crews. Werefurbish and restore equipment dur-ing the off season, and we do regularseasonal maintenance to keep thefleet in an efficient state.”Hines expects that some rented

equipment will be used on the proj-ect.PCi purchases equipment from regional

and local dealerships.Hines said he is looking forward to the

start of work in the spring and pointed outthat all projects provide opportunities to pro-mote employees and improve skills.“We train in the areas of safety quality,

and environmental compliance to allemployees and stakeholders,” he said. CEG

HIGHWAY from page 1

PCi Roads photoPCi uses Guntert Zimmerman slipform pavers, as well asRexcon concrete plants.

MnDOT photo With proper construction techniques and dowel alignments withthe joints, a concrete pavement can last a long time, said MnDOTproject manager Shawn Groven.

PCi Roads photoMaterials used in the project are expected to include 30,000 cu.yds. of concrete.

Recommended