Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations
Transcript
Page 1: Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.

Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005

LHCb

Install Meeting 20/04/05

TS / CV / Detector Cooling Installations

Page 2: Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.

Detector Cooling activities for the

LHCb experiment

Project Leader: Paolo Guglielmini

Inner Tracker cooling unit

IT-3314 Tracker Trigger cooling unit

RICH 1 & 2 cooling unit

Outer Tracker cooling unit

Primary cooling system modifications

Backup chiller for IT, TT and VELO stations

SPD/PS detectors air cooling

Others Muon on-detector air cooling

Gas compressors cooling

Cooling systems from mixed water network

IT-3307

Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005

Page 3: Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.

IT-3314: Inner TrackerTracker Trigger

DESCRIPTION Both cooling systems at fluorocarbon C6F14 in liquid state are based on a water condensed chiller connected to CERN mixed water network. They shall remove respectively some 2 kW and

1.65 kW heat power at -15°C from IT and TT detectors.

BUDGET CODE T757000

SCHEDULE Contract signature April 2005Installation at Contractor’s premises July 2005Installation of pipelines

and manifolds in the UX85 October 2005Installation of the unit in the UX85 End 2005Performance tests in the UX85 February 2006Commissioning March 2006

Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005

Page 4: Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.

DESCRIPTION The cooling system running fluorocarbon C6F14 in liquid state is based on a heat exchanger connected to CERN chilled water network and shall remove some 4 kW heat power at 10°C from both detectors.

BUDGET CODE T753000 (70%) and 32551 (30%)

SCHEDULE Contract signature April 2005Installation at Contractor’s premises July 2005Installation of pipelines

and manifolds in the UX85 October 2005Installation of the unit in the UX85 End 2005Performance tests in the UX85 February 2006Commissioning March 2006

IT-3314: RICH 1 & 2

Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005

Page 5: Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.

1

2

1. Location of the cooling stations

Metallic platform on the protected area of the RB84 side.

2. Transfer lines path along the cavern

Grouped supply/return pipelines around the shielding wall, across the vault, down to detector zone.

IT-3314

Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005

Page 6: Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.

IT-3314

3

4

3. TT distribution manifolds

Inner cooling circuits fed by ten independent lines with different flows.

4. IT distribution manifolds

Inner cooling circuits fed by twelve independent lines with equal flow.

No distribution manifolds provided for RICHes lines.

Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005

Page 7: Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.

IT3307: Outer Tracker

DESCRIPTION The cooling system running demineralised water is based on a heat exchanger connected to CERN mixed water network and shall remove some 23 kW heat power at 19°C from the detector.

BUDGET CODE T229900

SCHEDULE Contract signature April 2005Installation of pipelines

and manifolds in the UX85 June – July 2005Installation at Contractor’s premises September 2005Installation of the unit in the UX85 End 2005

Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005

Page 8: Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.

IT3307: Primary cooling system modifications

DESCRIPTION The already existing pipelines for chilled and mixed water (on RB86 side), compressed air (on both sides) and demineralised water (on RB84 side) shall be prolonged. The counting houses cooling lines shall be installed and equipped. Metallic supports for the transfer lines of detector cooling units shall be constructed on the RB84 side of the UX85.

BUDGET CODE 32560

SCHEDULE Contract signature April 2005Installation of the pipelines for primary

networks in the UX85, including installation and electrical tests on related equipments June – July 2005

Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005

Page 9: Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.

IT-3307

RB84

RB86

2

1

RB86

RB84

1. Compressed air (in white)

Demineralised water (in light blue)

2. Chilled water (in light blue)

Mixed water (in green)

RB84

2

Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005

Page 10: Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.

IT-3307

1

2 3

Connections to:

1. barracks D1 and D2

2. barracks D3/A and D3/B

3. detector cooling systems

Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005

Page 11: Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.

Others (1/5): Backup chiller for IT, TT and

VELO cooling stations

DESCRIPTION An air chilled fridge unit (32 kW cooling capacity) shall be provided as a backup for the IT, TT and VELO cooling systems, in order to supply mixed water at 13°C in case of breakdown or maintenance of the standard network. The chiller will be located on top of the barracks and equipped with automatic valves.

BUDGET CODE 32560

SCHEDULEInstallation and commissioning of unit

and related pipeworksJuly 2005

Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005

Page 12: Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.

Others (2/5): SPD/PS detectors air cooling

DESCRIPTION The electronic acquisition cards for the SPD and PS, dissipating a total heat power of about 4.4 kW shall be cooled down with a

dried and filtered air flow at 6 bar pressure. All components of the cooling system shall be positioned into a zone of the protected area still to be defined according to technical

and integration matters.

SCHEDULE Cooling system tested and

commissionedFebruary 2006

PSSPD

Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005

Page 13: Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.

Others (3/5): Muon on-detector air cooling

DESCRIPTION The on-detector electronic, fitted with the Muon chambers in stations M1-M5 shall be cooled by means of a forced air circulation. The air will be taken form the bulk by a fan, and exhausted to the bulk, the cooling capacity being assured by the cavern ventilation system.

The heat dissipated by on-detector electronic is 3.5 kW for station M1, 3 kW for stations M2 and M3 and 2 kW for stations M4 and M5.

SCHEDULE Cooling system tested and

commissionedFebruary 2006

Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005

Page 14: Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.

Others (4/5): Gas compressor cooling

DESCRIPTION Two gas compressors located in building 2870/R-004 release during normal functioning a heat power of about 8 kW each. An independent cooling unit shall be connected to both compressors in order to dissipate such heat power.

SCHEDULE Cooling system tested and

commissionedFebruary 2006

Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005

Page 15: Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.

Balcony racks

LVPS on bunker

Gas racksIT/TT

service boxes

Muon racks

Calorimeter racks

VELO vacuum pump

Total heat dissipated

[kW]40 96

8 (RB86)

4 (RB84)

4 (IT)

4.5 (TT)24 30 3

Others (5/5): Cooling systems from mixed

water network

DESCRIPTION Different heat sources in the UX85 shall be cooled down with systems running mixed water coming from CERN network.

SCHEDULE Cooling systems (pipeworks and supply/return equipped manifolds) installed, tested and commissioned

February 2006

Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005

Page 16: Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.

Others (5/5): Cooling systems from mixed

water network

Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005

Page 17: Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005 LHCb Install Meeting 20/04/05 TS / CV / Detector Cooling Installations.

Paolo Guglielmini - TS / CV LHCb Install Meeting - 20/04/2005

IT3307 – Installation matters

JUNE – JULY 05

1. cooling pipes integration in the detector area (RB84 side): to be finished and approved for the 6th of May

2. work sequence: primary system RB86 side barracks lines

supports RB84 side OT transfer lines3. storage area for Contractor’s material to be reserved (SG8 2870?)4. cable trays around the new pipelines for chilled water, mixed water

and compressed air to be dismounted (RB86)5. metallic platform on left side of the vault area to be dismounted, all

RB84 side to be prepared for installation6. new metallic structure behind counting houses:

to be finished in three weeks7. positioning of the OT unit on the platform (autumn):

dimensional constraints, to be studied how to lift it up