13
Summary of the Centralized Parks Maintenance Facility Study COG General Forum Meeting, 27 Aug 2012 Ronald J. Woodhead, Director Alan Popovich, APArchitects LLC 1
Transcript
Page 1: Parks Mtn. PRESENTATION: COG General Forum 27 Aug 2012

Summary of the

CentralizedParks Maintenance Facility Study

COG General Forum Meeting, 27 Aug 2012

Ronald J. Woodhead, Director

Alan Popovich, APArchitects LLC

1

Page 2: Parks Mtn. PRESENTATION: COG General Forum 27 Aug 2012

About

• Prepared by APArchitects LLC for the Recreation Authority

• Draft version presented to the Authority in July

• Final version (dated 13 Aug 2012) presented to the COG Parks Capital Committee and the Authority at their August joint meeting.

• Full report is posted at: http://issuu.com/crpr

2

Page 3: Parks Mtn. PRESENTATION: COG General Forum 27 Aug 2012

Why?

• A redesign of the Borough Public Works Facility

• Growth of Park Operations with increased park facilities (prior and future).

• Inadequate size of building and grounds for equipment service, staff and storage.

• Lack of water and sewer service.3

Page 4: Parks Mtn. PRESENTATION: COG General Forum 27 Aug 2012

Study Tasks

1. Review current & future Storage & Maintenance needs.

2. Evaluate 3 specific sites:Current site; Tudek Park; Whitehall Road Reg. Pk.

3. Provide a recommendation on the preferred site and prepare a Concept Plan to replace the current Osmond Street Facility.

4

Page 5: Parks Mtn. PRESENTATION: COG General Forum 27 Aug 2012

State College Borough – Public Works Facility

5

Current CRPR Parks Shop Area (in yellow) since 1978

2. Tom Tudek Memorial Park 3. Whitehall Road Reg. Park

Page 6: Parks Mtn. PRESENTATION: COG General Forum 27 Aug 2012

The Central Facility and the Park-Specific Maintenance Buildings

6

OSMOND STREET SHOP

Hess Complex

21 A.Spring Creek34 A.

Circleville Park 38 A.

Millbrook Marsh62 A.

Tudek Park87 A.

Fogleman Complex

15 A.

48 Other Sites 390 Acres

Page 7: Parks Mtn. PRESENTATION: COG General Forum 27 Aug 2012

CurrentConditions

Parks Maintenance Staff:

Equipment & Materials (at Osmond St.):

7

To Operate 908 acres at 54 sites

● 14 Trucks● 14 Tractors / Mowers / Groomers● 10 Equipment Trailers

● 17 Tractor Attachments● Park supplies, spares, power

equipment & hand tools.

● YEAR-ROUND: 9 positions(all at Osmond Street)

● SEASONAL: Up to 16 positions(12 at Osmond Street + 4reporting to specific parks).

One Building w/ 1,920 sf

Page 8: Parks Mtn. PRESENTATION: COG General Forum 27 Aug 2012

The Concept Plan

Equip. Service Areas: 1,800 sf

3 Service Bays (+ 1 Outdoor Wash Bay)

Park Staff Areas: 1,800 sf

Offices, 2 restrooms, lunch / locker room, work room, mechanical room, circulation

Warehouse Storage Area: 4,400 sf

For both park items and rec. program supplies

Vehicle Storage Sheds: 8,000 sf

8

16,000 sf of buildings on a 1.5 acre site

Page 9: Parks Mtn. PRESENTATION: COG General Forum 27 Aug 2012

The Concept Plan

9

Warehouse & Storage AreaEquipment Service BaysBulk Storage Bins

Staff & Office AreasVehicle Storage Sheds

Staff Parking Areas

Page 10: Parks Mtn. PRESENTATION: COG General Forum 27 Aug 2012

The Concept Plan - Cost Estimate

• Buildings & Shed Construction $1,329,700.

• Site Development Costs $ 501,750.

Earthwork, utilities, fencing, access drives,service yard, stormwater mgmt.

• Contingency (10%) $ 183,145.

SUBTOTAL $2,014,595.

• Design, Permitting & Approvals (10%) $ 201,460.

TOTAL PROJECT COST $2,216,055.

10

The Maintenance Building originally proposed solely for the maintenance of Whitehall Road Regional Park will not be built ($305,000). Those services would work directly from the Centralized Facility.

Page 11: Parks Mtn. PRESENTATION: COG General Forum 27 Aug 2012

The Recommended Site:Whitehall Road Regional Park

11

Recommended Location for Region-wide Parks Maintenance Facility

Page 12: Parks Mtn. PRESENTATION: COG General Forum 27 Aug 2012

The Timeframe – Whitehall Road Regional Park

• JUNE 2013 Phase 1 Park Construction begins (using temporary access easement).

• BY SEPT. 2013CRPR vacates the Borough Public Works Facility to allow their project to proceed. CRPR rents an interim facility pending the construction schedule for a new CRPR facility.

• BY AUG. 2014 Schedule not confirmed.

Toll Bros. provides utilities and the Blue Course DriveExtension to the park boundary.

• LATE-SPRING 2015Phase 1 Park Opens. 12

Page 13: Parks Mtn. PRESENTATION: COG General Forum 27 Aug 2012

Moving Forward

• Seek input from the 5 Participating Municipalities.

• Refine the Concept Plan to reduce estimated costs.

• Evaluate a Phasing Plan.

• Research the costs associated with revising the Master Site Plan for Whitehall Road Regional Park.

• Explore commercial site options and costs – for both interim and permanent uses.

13


Recommended