Florida Keys Aqueduct Authority
Stock Island - Tank 3
Section 01010
Summary of Work
TEAM 13-0612 TS - 1
SECTION 01010
SUMMARY OF WORK
PART 1 – GENERAL
1.01 DESCRIPTION
A. The scope of this section defines the work and materials included in each bid item in
the specifications for the repair of the Stock Island Pumping Station Tank 3 for the
Florida Keys Aqueduct Authority, Key West, Florida (hereinafter "Owner").
B. This tank is a 5-million gallon, welded, steel, flat bottom, cone roof tank. The
following information was observed:
Diameter: 140 ft.
Height: 42 ft.
Material: A36 Steel
C. The overall project consists of providing all labor, materials, supervision, power,
equipment and supplies for repairing the damaged roof and floor. The
CONTRACTOR is being presented two options for this repair and is requested to
bid on one or both:
1. OPTION 1 - Replace Damaged Steel and Entire Floor:
a) Damaged roof support members and rim angle sections will be
removed and replaced in-kind.
b) The entire floor will be cut out and replaced with a new, lap welded,
carbon steel floor.
c) Following repairs, the entire tank interior and exterior will be
abrasive blasted and recoated.
d) Install a new 24” diameter roof vent on Tanks 1, 2 and 3, including
repair of damaged exterior coatings around vent area of Tanks 1 and
2.
2. OPTION 2 - Geodesic Dome and Floor Repair:
a) Install an API-650 designed windgirder on the tank shell.
b) Remove entire existing roof, support structure, and support columns.
c) Install an aluminum geodesic dome roof.
d) Replace a 24” wide ring of floor plates around the perimeter of the
floor (annular ring), including under the tank shell.
e) Apply the specified thick film liner over the entire floor and 36” up
the tank shell interior.
f) Install a new 24” diameter roof vent on Tanks 1 and 2, including
repair of damaged exterior coatings around vent area.
1.02 RELATED DRAWINGS
A. S100 – Wind Girder Plan
B. S101 – Wind Girder Section Detail
C. S102 – Wind Girder Ladder Opening
D. S103 – Wind Girder Penetration
Section 01010
Summary of Work Florida Keys Aqueduct Authority
Stock Island - Tank 3
TEAM 13-0612 TS - 2
E. S104 – Annular Ring Detials
1.03 SITE CONDITIONS
A. Equipment and material required for daily work may be stored at the tank but cannot
unreasonably encumber the job site with material or equipment. Storage will be at
the risk of the CONTRACTOR. No responsibility will be assumed by the OWNER
or the ENGINEER for the security of stored material and equipment. All hazardous
material must be stored in locked containers.
B. Coordination of access to the tank must be arranged with the OWNER prior to
accessing the construction area.
C. All waste material, including scrap metal and spent abrasives, shall be contained
within the designated work area, and disposed of according to the submitted plan.
D. The CONTRACTOR shall take a video of the tank site prior to beginning work to
document the condition and placement of equipment and structures.
E. At the completion of this project, the areas surrounding the tank shall be restored to
a condition equal to or better than conditions prior to this project. Any grass,
shrubbery, trees, etc., damaged by CONTRACTOR personnel or equipment, or as a
result of work performed shall be replaced at the CONTRACTOR's expense. All
damaged grass shall be replaced with sod of the same type as the existing grass.
F. The CONTRACTOR shall be responsible for any damage to any surrounding
structures such as buildings, cars, landscaping, sidewalks, etc., as a result of paint
spatter, blast abrasive, mechanical damage, etc. All damage shall be repaired to the
satisfaction of the property owner making the claim at no additional cost to the
OWNER or ENGINEER.
1.04 GENERAL DESCRIPTION OF WORK TO BE PERFORMED
A. All fabrication, installation, welding, abrasive blasting, and coating or lining
application shall be done by experienced personnel. The awarded contractor shall
be able to provide proof of five successful projects as prime contractor on projects
of similar size, completed in the last five years. Similar projects shall be a minimum
of 1,000,000-gallon tank size in potable water service.
B. The CONTRACTOR shall furnish all labor, materials, equipment, tools, services
and incidentals to complete all work required by these specifications and as shown
on the drawings.
C. The CONTRACTOR shall perform the work complete, in place, and ready for
continuous service, and shall include, repairs, testing, permits, cleanup,
replacements, and restoration required as a result of damages caused during this
construction.
D. All materials, equipment, skills, tools and labor which are reasonably and properly
inferable and necessary for the proper completion of the work in a substantial
manner and in compliance with the requirements stated or implied by these
Specifications or Drawings shall be furnished and installed by the CONTRACTOR
without additional compensation, whether specifically indicated in the Contract
Documents or not.
E. The CONTRACTOR shall comply with all Municipal, County, State, Federal, and
other codes which are applicable to the proposed construction work.
Florida Keys Aqueduct Authority
Stock Island - Tank 3
Section 01010
Summary of Work
TEAM 13-0612 TS - 3
1.05 WORK SEQUENCE
A. All work to be done under these specifications shall be done with minimum
interference to the existing utility service and water systems operation and adjacent
land uses. The CONTRACTOR shall coordinate his work with the OWNER such
that the facilities are maintained to the maximum extent possible.
B. Construct work in stages to accommodate the OWNER use of the premises during
the construction period; coordinate the construction schedule and operations with
the OWNER representative.
1.06 CONSTRUCTION AREAS
A. CONTRACTOR shall limit his use of the construction areas for work and storage,
to allow for:
1. Work by other Contractors
2. OWNER use
B. Contractor shall coordinate use of work site under direction of ENGINEER.
C. CONTRACTOR shall assume full responsibility for the protection and safekeeping
of all materials and equipment under this contract, stored on site.
D. CONTRACTOR shall move and store products under CONTRACTOR‟S control,
which interfere with operations of the OWNER or separate CONTRACTORS.
E. CONTRACTOR shall obtain and pay for the use of additional storage or work areas
needed for operations.
1.07 OWNER OCCUPANCY
A. The OWNER will have full access to and use of all existing utilities during the
entire period of construction for the conduct of its normal operations.
CONTRACTOR shall cooperate with the OWNER representative in all
construction operations to minimize conflict, and facilitate OWNER usage.
B. CONTRACTOR shall at all times conduct his operations as to insure the least
inconvenience to the facility.
1.08 PLANS AND SPECIFICATIONS
A. SPECIFICATIONS
1. Each section consists of three (3) parts: PART 1, GENERAL; PART 2,
PRODUCTS; and PART 3, EXECUTION. The General part contains
general requirements, which govern the work. Products and Execution
modify and supplement these by detailed requirements of the work and shall
always govern whenever there appears to be a conflict.
1.09 INTENT
A. All work called for in the specifications applicable to this Contract, but not shown
on the Plans in their present form, or vice versa, shall be of like affect as if shown or
mentioned in both. Work not specified in either the plans or in the Specifications,
but involved in carrying out their intent or in the complete and proper execution of
the work, is required and shall be performed by the CONTRACTOR as though it
were specifically delineated or described.
B. The apparent silence of the specifications as to any detail, or the apparent omission
from them of a detailed description concerning any work to be done and materials to
Section 01010
Summary of Work Florida Keys Aqueduct Authority
Stock Island - Tank 3
TEAM 13-0612 TS - 4
be furnished, shall be regarded as meaning that only the best general practice is to
prevail and that only material and workmanship of the best quality is to be used, and
interpretation of these specifications shall be made upon that basis.
C. The inclusion of the General Requirements (or work specified elsewhere), in the
General part of the specifications is only for the convenience of the
CONTRACTOR, and shall not be interpreted as a complete list of related
specification sections.
1.10 DISCREPANCY BETWEEN DRAWINGS AND SPECIFICATIONS
A. In case of any discrepancy between the drawings and specifications, the more
stringent requirement shall apply. The CONTRACTOR will not be held responsible
for the discovery of such discrepancy, but any work done on the item involved after
such discovery, and prior to authorization by the ENGINEER, will be done at the
CONTRACTOR'S risk and expense.
PART 2 - PRODUCTS (NOT USED)
PART 3 - EXECUTION (NOT USED)
- END OF SECTION 01010 –
Florida Keys Aqueduct Authority
Stock Island - Tank 3
Section 05050
Welding
TEAM 13-0612 TS - 5
SECTION 05050 - WELDING
PART 1 - GENERAL
1.01 DESCRIPTION
A The purpose of this section is to provide guidelines for various welding procedures
required for the repair of this tank. This section is not intended to replace industry
standards.
B The requirements of this specification apply to atmospheric storage tank welding
(including welding of temporary and permanent attachments) during fabrication and
erection. This specification is applicable to water storage tanks being provided in
accordance with AWWA D100. It also covers tank repairs in accordance with API-
653.
C All welding within the scope of this specification shall be in accordance with the
requirements of API-653 and the additional requirements stated herein.
D The CONTRACTOR is responsible for all testing, as required by the referenced
standards and this specification.
1.02 QUALITY ASSURANCE
A Welding Procedures
(1) Shall be qualified in accordance with the requirements of ASME Section IX
and API-653.
B Welder Qualifications
(1) Welders and tackers shall be qualified in accordance with the requirements
of ASME Section IX,(Latest Edition).
(2) The OWNER may require re-qualification of any welder where there is a
question regarding his ability to make welds meeting the requirements of
this specification.
(3) The CONTRACTOR shall have a system in place which ensures that
welders have been properly qualified, and that their qualification has been
maintained as required in ASME Section IX. Records of welder
qualification and qualification maintenance shall be available for Review by
the OWNER at the work site.
C Destructive Testing
(1) For Impact Toughness Testing, a welding procedure qualification coupon
shall be tested. Charpy V notch impact test specimen, taken from the weld
metal, heat affected zone (HAZ), and unaffected base metal (three from each
area), shall be tested as required in ASTM A-370 and the following:
(a) The thickness of the procedure qualification coupon shall be at least
90% of the thickness of the thickest material (requiring testing) to be
used in the product.
(b) The long axis of the weld shall be parallel to the principal direction
of rolling or forging in the base material.
Section 05050
Welding Florida Keys Aqueduct Authority
Stock Island - Tank 3
TEAM 13-0612 TS - 6
(c) The long axis of all charpy specimens shall be perpendicular to the
weld axis and the principal direction of rolling or forging of the base
material.
(d) The notches, in all specimens, shall be cut such that their long axis is
approximately perpendicular to the surface of the material.
(2) Weld Metal Specimens;
(a) The center axis of the specimen shall be at least ¼”, and where
thickness permits, not less than 3/8” from the weld surface.
(b) The area of the notch and resulting fracture shall be located totally
within the deposited weld metal.
(3) HAZ Specimens;
(a) The center axis of the specimens shall be as near as practicable to a
depth midway between the surface and center thickness.
(b) Specimens shall be etched to define the HAZ before locating the
notch.
(c) The notch shall be cut in such a manner as to include as much HAZ
as possible in the resulting fracture surface.
(4) Base Metal Specimens;
(a) Shall be taken from the same depth as and shall be parallel to the
HAZ Specimens.
(b) The area of the notch and resulting fracture shall be located totally
within unaffected base metal.
(c) Sub-sized impact specimens may only be used with the approval of
the OWNER.
(d) The test temperature and acceptance criteria shall be the same as
required, by contract specification, for the base metal. The test
results for the HAZ specimens (average value as defined in ASTM
A-370) shall equal or exceed those of the base metal specimens.
(e) The welding procedure qualification coupon shall be exposed to the
same heat treatment cycles, both before and after welding, as the
product will experience.
(f) After initial testing, additional heats of filler material of the same
AWS Classification, produced by the same manufacturer, need not
be impact tested provided the minimum impact properties required
by the applicable filler material specification meet or exceed those
required by contract specification for the base material.
D Non Destructive Examination Requirements (NDE)
(1) General
(a) NDE examiners shall be qualified in accordance with the
requirements of SNT-TC-1A. Only individuals qualified for NDT
LEVEL II or III may perform and evaluate the results of
nondestructive examination.
(2) Visual Examination (VT)
(a) All welds, including temporary attachment removal sites, shall be
visually examined by a qualified examiner, other than the welder
who made the weld.
Florida Keys Aqueduct Authority
Stock Island - Tank 3
Section 05050
Welding
TEAM 13-0612 TS - 7
(b) The following discontinuities are unacceptable:
(i) Cracks.
(ii) Undercut depth exceeding 1/32" for horizontal butt joints.
Undercut depth exceeding 1/64" for vertical butt joints.
(iii) Incomplete penetration.
(iv) Lack of fusion.
(v) Excess groove weld reinforcement
(3) Magnetic Particle(MT) or Liquid Penetrant (PT) Examination
(a) Where the applicable Codes require sectional, gouging, or chipping
inspection Magnetic Particle (MT) or Liquid Penetrant (PT)
Examination of fillet welds, MT or PT (for stainless only)
examination of the root pass and final layer shall be performed in
lieu of the required inspection.
(b) The first pass of the new shell-to-bottom weld shall be PT tested
prior to additional welding on either side. All indications shall be
repaired prior to additional welding.
(4) Radiographic Examination
(a) Radiography shall be conducted in accordance with ASME, Section
V, Article 4. The CONTRACTOR shall report to the OWNER.
(5) Vacuum Box Testing
(a) All new floor seams and bottom to shell corner welds shall be
vacuum box tested.
(b) The vacuum box test shall be conducted in accordance with ASME
Section V, Article 10.
(6) Marking and Recordkeeping
(a) After completion of the work, a nameplate shall be prepared in
accordance with Section 11 of API-653. The nameplate shall be not
less than 4” H x 6” W, constructed of corrosion resistant material.
1.03 REFERENCE DOCUMENTS
A Standard (Latest Edition)
(1) ASME Boiler and Pressure Vessel Code, Section IX, Welding and Brazing
Qualifications, latest edition.
(2) ASME Boiler and Pressure Vessel Code, Section V, Non-Destructive
Examination, latest edition.
(3) ASNT Recommended Practice No. SNT-TC-1A.
(4) ASTM A-370
(5) AWWA D100 Welded Steel Tanks for Water Storage.
(6) API-653 Tank Inspection, Repair, Alteration and Reconstruction.
B In the event of a conflict between a referenced document and this document, this
document shall take precedence.
Section 05050
Welding Florida Keys Aqueduct Authority
Stock Island - Tank 3
TEAM 13-0612 TS - 8
PART 2 - PRODUCTS
2.01 MATERIALS
A Materials are to be supplied as specified herein the enclosed drawings and
specifications.
B Welding Material Storage and Use
(1) All filler material must be kept in a clean, dry, warm area.
(2) Immediately after removal from sealed containers, carbon and low alloy
steel, low hydrogen electrodes and stainless steel electrodes shall be placed
in hot holding ovens and maintained at 250F to 300F, issued for use in
hot portable ovens maintained at the same temperature range or issued in
small quantities which will be used within the appropriate exposure limit.
(3) Where the holding oven will contain only carbon and low alloy steel
electrodes, the temperature range may be expanded to 250F to 350F.
Additional, E7024 electrodes shall be heated at 150F to 175F and E6010
electrodes shall not be heated above 100F (ambient temps).
(4) Electrodes shall not be used after they have been exposed to the atmosphere
longer than the exposure time limit shown in the following table.
Electrode Type Exposure Time Limit
Stainless steel 8 hours
E7018-X 4 hours
E8018-X 2 hours
E7024 8 hours
E6010 None
(5) If electrodes are issued in portable electrode ovens (same temperature
requirements for holding ovens), the exposure time doesn‟t start until
electrodes are removed from the portable oven.
(6) Once exposed to the atmosphere, carbon and low alloy steel low hydrogen
electrodes shall be used, within the time limit or discarded. They shall not
be returned to a portable or holding oven. Stainless electrodes and E7024
may be returned to the holding oven for a minimum of 8 hours and then re-
issued.
(7) Portable electrode ovens shall remain plugged in with the tell-tale light
energized and visible except while in transit.
(8) Welders should remove, from the portable oven, only the amount they
believe will be consumed before the next break in welding.
(9) Covered electrodes which have become wet shall be discarded.
(10) SAW flux shall be purchased in triple layer bags or better, which prevent
moisture pick-up. Once removed from the bag, SAW flux shall be used
immediately or stored in a holding oven maintained at 250F and 350F.
Opened, but only partially used bags shall be similarly stored.
Florida Keys Aqueduct Authority
Stock Island - Tank 3
Section 05050
Welding
TEAM 13-0612 TS - 9
(11) A program shall be implemented to ensure that the above requirements for
control of filler materials are observed. The program shall be described in a
written procedure which shall be available for Review by THE OWNER at
the work site.
(12) Filler material used shall be that specified in the WPS.
(13) All welding filler materials shall meet the requirements of the applicable
AWS filler material specification.
(14) Covered electrodes for SMAW welding shall not exceed 5/32” diameter for
vertical and overhead welding and 3/16” diameter for flat and horizontal
welding.
(15) Covered electrodes for carbon and alloy steel welding shall be low hydrogen
type (EXX18) and shall have been purchased in hermetically sealed metal
containers. For materials with a minimum tensile strength between 80 and
85 quips, E8018-CS covered electrodes shall be used. Non-low hydrogen,
D7024 or E6010 type, electrodes may be used for welding on carbon steel
floor and roof plates. E6010 may be used on carbon steel roof and floor
plates with thickness of 1/2” or less. This does not include any welds
involving the tank shell plates.
(16) Bare rod filler materials for GTAW shall be ID tagged to preclude loss of
identification.
(17) Filler materials shall be used in accordance with the Manufacturer‟s
Recommended Practices. For FCAW welding, the shielding gas used must
be the same as that used by the Manufacturer during product qualification
testing.
PART 3 - EXECUTION
3.01 GENERAL WELDING PROCESSES
A The Following welding processes are allowed with the noted restrictions.
Welding Processes Restrictions
GTAW (Gas Tungsten Arc) Addition of filler material required
SMAW (Shielded Metal Arc) None
FCAW (Flux Cored Arc) a) Externally shielded only75/25 A/CO2
(All positions) CO2 (Flat & Horizontal
Only)
b) Short Circuit Transfer Mode
prohibited
c) Wind protection required at site
SAW (Submerged Arc) No alloy in the flux
B Other welding processes may not be used without written approval of the OWNER.
When requesting the use of other processes, the following additional information
must be submitted:
(1) Proposed application and limitations of those applications.
(2) In-Progress Inspections to ensure that process remains under control.
Section 05050
Welding Florida Keys Aqueduct Authority
Stock Island - Tank 3
TEAM 13-0612 TS - 10
(3) NDE required for completed welds. If less than 100% a detailed description
of the sampling plan to be employed.
(4) Any special welder qualification requirements.
(5) Historical evidence supporting quality of welds.
C Joint Design and Preparation
(1) The actual joint designs to be employed (on this contract only) shall be
detailed on the applicable OWNER approved WPS or another document
which has been submitted along with WPS.
(2) Note: Groove weld symbols, without a number representing bevel depth or
effective throat, require full penetration welds.
(3) Butt joint alignment shall not result in a centerline offset exceeding 10% of
the thickness of the thinner part or 1/16,” whichever is less, except
misalignment of the tank shell shall meet the criteria specified in API-650
Sections 5.2.3.1 and 5.2.3.2.
(4) The transition of thickness at butt joints of parts having different thickness
shall not exceed a 4 to 1 slope. The addition of weld metal beyond the edge
of the groove may be employed to achieve the slope.
(5) Parts to be joined by fillet welds, shall be brought into as close contact as
practicable. In no case shall the root opening exceed 3/16” and, where there
is any root opening, the size of the fillet shall be increased by the amount of
the opening.
(6) The gap between a backing bar and the bottom surface of the joint and the
gap between feting surfaces of a lap joint shall not exceed 1/16.”
(7) For single welded pipe or tube joints, inside diameters shall match within
1/16” and the maximum point mismatch, due to out-of-roundness, shall not
exceed 3/32.”
(8) Socket weld fit up shall meet the requirements of ANSI B31.1, Paragraph
127.3.3.
(9) Backing rings and bars, when used, shall be of a material which is
compatible with the base metal.
(10) Where a weld prep has been made with a thermal process, such as oxy-
acetylene cutting of air-arc gouging, the surface shall be ground as necessary
to remove any slag or scale and provide a relatively smooth surface on
which to weld.
(11) Prior to welding, surfaces to be welded and adjacent surfaces for at least
1/2” shall be clean and free of any scale, rust, oil, grease, paint or other
extraneous material. Tools such as, grinders and wire brushes, which have
been used on carbon steels, shall not be used on stainless steel.
D GTAW Shielding and Purge Gas
(1) For GTAW welding, the torch shield gas shall be argon. Purge Gas,
required only during deposit of the first 3/16” of weld thickness in stainless
butt joints, shall be Argon.
E Preheat and Interpass Temperatures
(1) For carbon steel, material over 1-1/2” in thickness, the minimum preheat
temperature shall be 200F. In all other cases, the minimum preheat
temperature shall be 50F.
Florida Keys Aqueduct Authority
Stock Island - Tank 3
Section 05050
Welding
TEAM 13-0612 TS - 11
(2) Minimum preheat temperatures also apply to tack welding and temporary
attachment welding.
(3) When determining required preheat temperature, the material thickness is
the thickness of the thicker member being joined.
(4) Elevated preheat (temperatures above 50F), when required in paragraph
10.1 and 10.2 above, shall be by electric resistance or induction heaters.
Exceptions to this requirement are:
(a) Manually applied flame heat may be used for welds with a throat
3/4” on P1 materials up to 2” thick. In such cases, care must be
exercised to heat the entire area uniformly, avoiding any localized
hot or cold spots.
(b) Manually applied flame heating may be used for tack welds.
(5) In lieu of using electric heaters as required above, a procedure for applying
flame heat by mechanical means, which ensures a uniform controlled heat
throughout the welding operations, may be submitted to the OWNER for
approval.
(6) Where there is a specified maximum inter-pass temperature, the joint shall
be below that temperature immediately prior to beginning any weld bead.
(7) Where there is a specified maximum inter-pass temperature, the joint shall
be below that temperature immediately prior to beginning any weld bead.
(8) Surface temperature measurements, using thermocouple, contact pyrometers
or temperature indicating crayons, shall be used to verify that the joint to be
welded and adjacent surfaces in all directions, for a distance equal to at least
the thickness of the material but not less than 3", are at or above the
specified minimum preheat temperature before and during all welding.
F Miscellaneous Welding Requirements
(1) Welding shall be performed in accordance with the specific requirements of
the applicable, OWNER approved, WPS.
(2) Tack welds shall be examined to ensure that they are defect free and
properly prepared for incorporation into the final welds.
(3) For single welded open root joints, as a minimum, the first two passes shall
be deposited using the GTAW process. The resulting deposit thickness shall
be at least 1/8".
(4) Double welded full penetration joints require back gouging of the root to
sound metal, followed by MT/PT examination, before depositing metal on
the second side unless the joint is 100% radiographed, then MT/PT testing is
optional.
(5) For SMAW welding, individual bead thickness shall not exceed 3/16".
Deposited bead width shall not exceed 6 times the electrode core wire
diameter except that, when welding the cap pass on groove welds, the
maximum deposited bead width may be increased to 8 times the electrode
core wire diameter.
(6) For FCAW welding, individual bead thickness shall not exceed 1/4", except
for groove root passes, which are not limited in thickness. The bead width
shall not exceed 1/2", except in the vertical position where the maximum
bead width is 1".
Section 05050
Welding Florida Keys Aqueduct Authority
Stock Island - Tank 3
TEAM 13-0612 TS - 12
(7) For single wire SAW welding, individual bead thickness shall not exceed
1/4" except for groove root passes, which are not limited in thickness. The
bead width shall not exceed 5/8". In the horizontal position, only fillet
welding is permitted and the maximum single pass, horizontal fillet size is
5/16".
(8) All slag or other foreign material shall be removed prior to depositing
succeeding weld passes.
(9) After cleaning, each weld pass shall be examined to ensure that it is defect
free prior to depositing the subsequent pass.
(10) Temporary attachments may be removed by grinding or thermal methods,
however, if thermal methods are used, approximately 1/8" of material shall
be left for final removal by grinding. Temporary attachments may not be
removed by hammer blows or by bending back and forth.
(11) For vertical welding, the direction of travel shall be "up".
G Post Weld Heat Treatment (PWHT)
(1) PWHT of storage tank weld joints shall be performed when and as required
in AWWA D100.
(2) Furnace, electric resistance or induction heaters shall be used for all PWHT.
Other methods may not be used without written approval of the OWNER.
(3) A strip chart record of the thermal history is required for all PWHT.
- END OF SECTION -
Florida Keys Aqueduct Authority
Stock Island - Tank 3
Section 07710
Aluminum Geodesic Dome Roof
TEAM 13-0612 TS - 13
SECTION 07710
ALUMINUM GEODESIC DOME ROOF
PART 1 - GENERAL
1.01 DESCRIPTION
A. This section defines the design requirements for the aluminum dome structure as
described in the contract drawings and documents.
1.02 SUBMITTALS
A. Before executing any of the work in this section, prints or drawings shall be
submitted to the engineer showing dimensions, sizes, thickness, gauges, materials,
finishes, joint attachment and erection procedure.
B. A complete set of design calculations for the dome(s) shall also be submitted.
These calculations shall be signed by a Florida registered professional engineer. All
work shall be fabricated and erected in accordance with the approved drawings.
C. Certification that the specified material alloys, sizes and quantities have been
furnished shall be submitted upon completion of the project.
1.03 REFERENCES
A. The following codes and standards form a part of this section to the extent specified
herein:
1. ASTM C509 Standard Specifications for Elastomeric Cellular Preformed
Gasket and Sealing Material
2. ASTM C1115-00 Standard Specification for Dense Elastomeric Silicone Rubber
Gaskets
3. ASTM C920 Standard Specification for Elastomeric Joint Sealants
4. Aluminum Association Specifications for Aluminum Structures
5. Aluminum Association Aluminum Design Manual; Specifications and
Guidelines for Aluminum Structures
6. ASCE 8-02 Specification for the Design of Cold-Formed Stainless Steel
Structural Members
7. ASTM F593 Standard Specification for Stainless Steel Bolts, Hex Cap Screws,
and Studs
8. AASHTO Division 2 Section 25 Elastomeric Bearings
9. Federal Specification TT-S-00230C
10. Federal Specification A-A-59588
PART 2 - PRODUCTS
2.01 DESCRIPTION
A. The dome roof shall be clear-span and self-supporting from the peripheral structure
with primary horizontal forces contained by an integral aluminum tension ring
(unless otherwise specified). The frame shall consist of aluminum structural
members with the joints arrayed on the surface of a sphere. The arrangement of
Section 07710
Aluminum Geodesic Dome Roof
Florida Keys Aqueduct Authority
Stock Island - Tank 3
TEAM 13-0612 TS - 14
members shall result in a pattern of triangular spaces. These spaces shall be closed
with light gauge aluminum panels. The members shall be joined by means of
bolting their flanges to aluminum gusset plates.
B. The design shall include a walkway and/or access to all vents for maintenance.
C. An exterior, hinged access hatch, minimum 30” x 30” shall be provided near the
top of the tank ladder.
D. All metal components of the aluminum dome structure shall be aluminum or 300
series stainless steel. No galvanized, aluminized, painted, or plated steel shall be
used anywhere in the dome above the mounting bracket base plates. Dissimilar
materials in the supporting structure shall be isolated from the aluminum dome by
means of a compatible elastomeric gasket.
E. The entire structure shall be designed as a watertight system under all design load
and temperature conditions.
F. The aluminum closure panels shall be attached continuously along their edges to the
structural members by means of batten bars which engage the panels in an
interlocking joint. This batten bar shall also secure an elastomeric weatherseal
gasket that shall form a continuous watertight seal along the panel edges. Designs
that incorporate overlapping panels and/or designs that incorporate fasteners which
penetrate panels and attach to structural members are expressly prohibited.
G. Connection forces shall be transferred through gusset plates connected to the top
and bottom flanges of the beam struts. The connections shall be designed as
moment connections; a minimum of four bolts shall be used to connect the gusset
plate to each strut flange.
F. The structural analysis shall be performed using stiffness analysis models. The
structural computer models shall include the effect of geometry irregularities such as
dormer openings and perimeter support members. Full provisions shall be made to
allow for thermal expansion.
G. Fasteners shall be designed with a factor of safety of 2.34 on ultimate strength and
1.65 on yield strength.
2.02 EXPERIENCE/QUALIFICATIONS
A. No equipment shall be supplied by any manufacturer not regularly engaged in the
manufacturing and production of domes in the size and character herein specified.
The manufacturer must have designed, manufactured and installed at least three (3)
domes of the same type and size as unit(s) specified herein. These domes must be in
satisfactory use for a period not less than ten (10) years.
B. The cover manufacturer must own and operate its own US-based manufacturing
facility, and the use of a fabrication facility that is not US-based and/or owned and
operated by the cover manufacturer is expressly prohibited. Manufactures that do
not meet these qualifications will not be considered.
C. The cover manufacturer must be ISO 9001 certified.
D. Contractor to submit resumes of key personnel for Owner review and approval.
Florida Keys Aqueduct Authority
Stock Island - Tank 3
Section 07710
Aluminum Geodesic Dome Roof
TEAM 13-0612 TS - 15
2.03 MATERIALS
A. The following is a summary of approved materials and/or material specifications:
1. All aluminum alloys shall be as defined by the Aluminum Association and
published in the ALUMINUM STANDARDS AND DATA.
2. Bolts and Fasteners - Bolts shall be 300 series stainless steel per ASTM
F593, Alloy Group 1. Lockbolts shall be 7075-T73 aluminum or 305
stainless steel. Screws shall be aluminum or 300 series stainless steel.
3. Plates and Sheets - Plate and sheet material shall be aluminum alloy 3003-
H16, 3105-H154, 6061-T6, 5052-H32 or 5052-H36; mill finish AA - M10
as fabricated. Tension ring gussets shall be 0.375 inch minimum thickness.
Sheet materials shall be 0.05” minimum thickness.
4. Structural Shapes - Aluminum structural shapes shall be alloy 6061-T6. The
aluminum structural members shall be a minimum of 4 ½ inches deep.
5. Tension Ring - Tension ring structural shapes shall be 6061-T6 aluminum.
Design of the tension ring shall be based on the net cross section of the
members and shall not include top flange protrusions used for panel
attachment, bolt holes, or outstanding legs that are not connected through the
joints.
6. Miscellaneous Shapes - Miscellaneous aluminum shapes shall be alloy
6061-T6 or 6063-T5.
7. Gaskets - All gaskets shall be ozone resistant Silicone or Neoprene only. If
Neoprene gaskets are utilized they must be shielded from exposure to
ultraviolet light. The gaskets must have a ¼” minimum thickness.
8. Sealant - All sealants shall be silicone and resistant to ozone and ultraviolet
light and conform to Federal Specification TT-S-00230C.
9. Miscellaneous Penetration Seals- All other penetration seals shall be
weatherproof rubber seals.
10. Support Bearings - Bearings at the supports shall conform to AASHTO
Division 2, Section 25. Acceptable bearing surfaces for sliding bearing are
Teflon to stainless steel only. In order to avoid damage to the Teflon and to
reduce the coefficient of bearing friction, Teflon shall not bear on aluminum
surfaces.
2.04 DESIGN LOADS
A. The entire dome structure shall be designed to sustain the loads specified herein,
with the stress limitations of the Aluminum Association SPECIFICATIONS FOR
ALUMINUM STRUCTURES. For members subjected to axial forces and bending
moments due to load eccentricity or lateral loads, the combined member stresses
shall be determined by adding the stress component due to axial load to the stress
components due to bending in both the major and minor axis. In no case shall the
dome be designed for any loads less than those specified by the local building code
and/or local amendments.
Section 07710
Aluminum Geodesic Dome Roof
Florida Keys Aqueduct Authority
Stock Island - Tank 3
TEAM 13-0612 TS - 16
B. The load cases to be considered shall be those described below unless more severe
loads are specified by the purchaser.
1. Dead Load – The dead load shall be defined as the weight of the structure
and all permanently attached to and supported by the structure.
2. Live Load – As required per ASCE 7-05 Section 4.9.1.
3. Snow Load – As required per ASCE 7-05 but not less than required by local
building codes and/or local amendments.
a) Importance Factor (I) = 1.0 or greater per ASCE 7-05 Table 1-1.
b) Exposure Factor (Ce) = 1.0 or greater per ASCE 7-05 Table 7-2.
c) Thermal Factor (Ct) = 1.2.
4. Unbalanced Snow Load – As required per ASCE 7-05 Section 7.6.4 and
Figure 7-3 but not less than required by local building codes and/or
amendments.
5. Wind Load – As required per ASCE 7-05 Figure 6-7 but not less than
required by local building codes and/or amendments.
a) Importance Factor (I) = 1.0 or greater per ASCE 7-05 Table 6-1.
b) Exposure Factor = C minimum or D where required.
c) Internal wind pressure coefficient shall not be less than 0.
6. Load Combinations – As required per ASCE 7-05 Section 2.4.1.
7. Temperature - The load combinations listed above shall be considered for a
temperature change of 100 degrees F below the installation temperature and
100 degrees F above the installation temperature and for a material
temperature range of 40 degrees F below 0 to 160 degrees F above zero.
8. Panel Design Load - In addition to the above mentioned loads and load
combinations, the aluminum panels shall be designed for a 250 pound load
distributed over one square foot at any location and a plus or minus 60 psf
load distributed over the entire area of any given panel. These loads are to
be taken as acting separately from one another and not simultaneously with
other design loads.
C. Snap-Through Buckling (General Shell Buckling) shall be determined in accordance
with the following formula:
Where:
w = Allowable load [pressure psf].
Ix = Moment of inertia of strut about the strong axis [in4].
A = Cross sectional area of strut [in2].
R = Spherical radius of dome [in].
L = Average member length [in].
SF = Safety factor (1.65).
1. The allowable buckling pressure shall be compared to the maximum
intensities of symmetrical and nonsymmetrical load conditions.
w =2258x10 I A
(SF) R L
6x
2
Florida Keys Aqueduct Authority
Stock Island - Tank 3
Section 07710
Aluminum Geodesic Dome Roof
TEAM 13-0612 TS - 17
2. In lieu of the above formula, non-linear analysis modeling may also be
performed to verify that the stiffness is adequate to prevent snap-through
buckling for all load cases include live, snow and wind loads. To account for
modeling variations and/or user assumptions in the analysis, a minimum
safety factor of 1.95 shall be used.
2.05 MANUFACTURERS
A. The aluminum dome cover shall be as manufactured by CST Covers - Gardena,
California (310) 353-5100 or Conroe, Texas (936) 539-1747.
PART 3 - EXECUTION
3.01 INSTALLATION
A. The dome shall be installed by the manufacturer‟s installation crews.
B. All work shall be executed by skilled mechanics with a supervisor experienced in
the erection of domes. The dome shall be erected plumb and level and in proper
alignment.
C. Due to space constraints, the dome must be assembled on the tank. No lay down
area is available.
D. Field re-fabrication of structural components or panels will not be accepted. Forcing
of the structure to achieve fit-up during construction is expressly forbidden and not
acceptable.
E. All sealant joints shall be tooled slightly concave after sealant is installed. Care
shall be taken to keep sealant confined to joint area, and any outside of the joint
shall be removed so that the panels will be free from misplaced sealant. All gasket
materials shall be continuous; splices will not be allowed. All sealants shall be
placed only in a manner as recommended by the sealant manufacturer.
3.02 WARRANTY
A. The dome manufacturer shall warrant that the work described herein shall be free
from defects, workmanship and material. The dome manufacturer shall replace or
repair only faulty workmanship or defective material furnished by it that is reported
to it within one (1) year from the date of completion of this scope of work.
B. The dome manufacturer shall warrant that the work described herein shall be leak
tight for a minimum of five years from the date of approved installation completion.
END OF SECTION 07710
Section 09900
Painting Florida Keys Aqueduct Authority
Stock Island - Tank 3
TEAM 13-0612 TS - 18
SECTION - 09900
PAINTING
PART 1 - GENERAL
1.01 DESCRIPTION
A. This section pertains to the interior and exterior painting of Tank 3, including the
thick-film liner specified in Option 2 (See Section 01010).
B. All surfaces encompassed by this specification shall be cleaned, prepared and coated
with the designated paint system as specified herein. All coating shall be applied in
strict accordance with the manufacturer's instructions.
1.02 RELATED SECTIONS
A. 01010 Summary of Work
1.03 REFERENCED STANDARDS
A. SSPC Society for Protective Coatings
1.04 QUALITY ASSURANCE
A. INSPECTION PROGRAM
1. Throughout the duration of the work, a formalized inspection program will be
developed and maintained by the OWNER/ENGINEER. The CONTRACTOR
will be familiarized with the inspection program and the Project line of authority
at the Pre-Construction Conference.
2. It shall be the CONTRACTOR'S responsibility to provide the OWNER, through
the ENGINEER, with clear, accurate information necessary for the required
inspection reports.
3. The CONTRACTOR shall fill out a daily inspection report form. This form
will be furnished by the ENGINEER. No request for payment will be processed
unless accompanied by completed inspection report forms. Inspections will be
performed by the ENGINEER or his designee. It is expected that information
furnished on the CONTRACTOR‟S inspection reports shall coincide with the
information recorded during the ENGINEER'S inspections.
4. The CONTRACTOR shall notify the INSPECTOR when an area is ready for
inspection. No work will be approved until the INSPECTOR has performed all
required tests and inspections.
5. The CONTRACTOR shall provide for the INSPECTOR all necessary rigging
required to complete the inspection and testing operations. The CONTRACTOR
shall assist the INSPECTOR in making all required tests and inspections.
Deficient areas such as pinholes, holidays, embedded contamination, sags, dry
spray, mechanical damage, high / low mils, shall be repaired to meet the
requirements of this specification.
6. The OWNER will provide part-time coating inspection for the duration of the
project. The INSPECTOR shall be on site at critical points in the operation
including holiday tests and touch-up work.
Florida Keys Aqueduct Authority
Stock Island - Tank 3
Section 09900
Painting
TEAM 13-0612 TS - 19
B. INSPECTION AUTHORITY
1. The OWNER has ultimate responsibility for Contract administration and
inspection for this project. Field inspection responsibilities will be assigned to
the INSPECTOR.
2. The INSPECTOR can stop the job if the CONTRACTOR is deviating from the
specifications. The CONTRACTOR'S field supervisor shall be advised verbally
to stop work. Work can resume after the deviation is corrected to the
satisfaction of the OWNER and INSPECTOR.
3. Each step of the construction is subject to approval by the INSPECTOR prior to
proceeding with a subsequent step.
4. During the progress of the work and up to the date of final acceptance, the
CONTRACTOR shall at all times afford representatives of the OWNER,
County, State, and Federal agencies having jurisdiction, every reasonable, safe,
and proper access for observation of the work done or being done at the site and
also at the place of manufacture or preparation.
C. TEST EQUIPMENT FURNISHED BY CONTRACTOR
1. The CONTRACTOR shall have the following test equipment available for use
by the INSPECTOR at the job site at all times during the progress of the work:
a) Sling Psychrometer
b) Surface Temperature Gauge
c) Wet Film Thickness Gauge
d) Dry Film Thickness Gauge (Properly Calibrated)
e) National Bureau of Standards thickness plates.
f) SSPC VIS-1- Pictorial Surface Preparation Standard
g) Holiday Detector. Low voltage type such as Tinker & Rasor Model M-1,
Series 9533
h) Keane-Tator Surface Comparator Number 372 or equal
D. CONTRACTOR FURNISHED INFORMATION
1. The following information will be part of the information required for the
inspection reports:
a) Compressor: Size, Manufacturer, Moisture and Water separators, Air Drier,
Cleanliness of Air, Number of Blast Nozzles.
b) Safety Equipment: Protective Cloths, Respirators, and Breathing Equipment.
c) Paint Equipment: Paint Pump, Spray Gun, and other essential items deemed
necessary.
d) Materials: Abrasive: (Size, Type, Source, Cleanliness)
e) Paints: Type, Manufacturer, Batch No., other information deemed necessary.
f) Thinners: Type, Manufacturer, Batch No., and other information deemed
necessary.
g) Inhibitors: Type, Manufacturer, Batch No., and other information deemed
necessary.
h) Grouts: Type, Manufacturer, and other information deemed necessary.
i) Contractor Personnel: Name, Address, and Phone Number of Supervisor.
Name, Address, and Phone Number of Foreman. Name of each
Crewmember or Laborer.
j) Caulking: Type, Manufacturer, and other information deemed necessary.
Section 09900
Painting Florida Keys Aqueduct Authority
Stock Island - Tank 3
TEAM 13-0612 TS - 20
E. CONTRACTOR REQUEST FOR INSPECTION
1. The CONTRACTOR shall notify the INSPECTOR 24 hours in advance that
portions of the work are ready for inspection and will assist the INSPECTOR in
making all necessary tests and inspections.
2. No rigging and/or staging shall be removed before required inspection and
approval is made. The CONTRACTOR shall assist the INSPECTOR in the use
and operation of all equipment for access to the surfaces to be tested.
3. The CONTRACTOR shall make all necessary rigging available to the
INSPECTOR, and assist in the operation of rigging during any and all testing
operations.
4. Approval by the INSPECTOR of an area does not release the CONTRACTOR
from providing the quality and workmanship provided by this Specification.
F. COATING THICKNESS AND CONTINUITY:
1. The specified coverage rates of the coatings are minimums. The first coat on
metal surfaces refers to the first paint coat and not to conditioning or other
pretreatment applications. Coating shall be applied to the thickness specified,
and in accordance with these specifications. The minimum dry film thickness at
any spot measurement shall not be less than 80% of the specified thickness.
Unless otherwise specified, not less than two (2) coats shall be applied. The
CONTRACTOR shall furnish a wet film thickness gauge, a dry film thickness
gauge, and certified thickness calibration standards for the INSPECTOR use.
Dry film thickness gauges shall be Mikrotest III, Elcometer Inspector III,
Positest, or Positector.
2. After each coat has been allowed to dry, the dry film thickness will be measured
by the INSPECTOR. The CONTRACTOR shall not apply a successive coat
until the dry film thickness of the preceding coat or coats has been approved by
the INSPECTOR.
3. Coating system thickness is the total thickness of all the required coats of paint,
and does not include passivators or sealers.
4. Measurement of dry paint thickness over steel surfaces will be done in
accordance with SSPC-PA 2.
1.05 PRODUCT HANDLING
A. STORAGE
1. All coating materials shall be protected from direct sunlight and stored in a
separate structure provided by the CONTRACTOR. The structure shall be
constructed of non-combustible materials. It shall have sufficient ventilation to
prevent the concentration of fumes and vapors.
2. Coating storage environmental conditions shall conform to the coating
manufacturer's recommendations. The CONTRACTOR shall be solely
responsible for the protection of all the material stored by him at the job site.
3. Coating materials shall be delivered to the job site in the original and unopened
containers, with legible labels, marked with the proper designation of the
product, as well as the manufacturer.
4. All coating materials at the job site shall be subject to inspection.
5. An approved environmental paint spill kit and container shall be located near the
paint storage area.
Florida Keys Aqueduct Authority
Stock Island - Tank 3
Section 09900
Painting
TEAM 13-0612 TS - 21
6. All coating components will be delivered in unopened containers. They will be
protected from freezing and over heating during shipment.
7. All coating components must be stored at temperatures above freezing and out
of the weather. The containers must remain unopened until they are ready to be
used.
B. MIXING
1. Mechanical mixers or shakers shall be used to mix the coating after properly
measuring the required components. Catalysts, thinners, and other components
shall only be added in exact quantities and at the times specified by the coating
manufacturer. Containers used for mixing shall be clean and dry. Mixed
materials that are not used prior to expiration of the pot life shall be discarded.
2. All coatings materials shall be mixed and thinned in the presence of the
INSPECTOR. Plural component materials will not be approved for application
unless the INSPECTOR can verify the proper proportions were mixed, and they
had proper Induction time after mixing.
3. An approved environmental paint spill kit and container shall be located near the
paint mixing area.
4. An appropriate type of fire extinguisher shall be kept nearby.
1.06 SUBMITTALS
A. The following information shall be provided in accordance with these
specifications. Information on each coating system shall be delivered to the
ENGINEER two (2) weeks before applying that coating system. A list of materials
proposed to be used under this section shall be provided within ten (10) days of the
Notice to Proceed.
B. For each primer, intermediate, and finish coating the CONTRACTOR shall provide
the Manufacturer's Application Instructions and the data listed below:
1. Surface preparation recommendations.
2. Primer, intermediate, and finish coating, pot life and specific mixing
instructions.
3. Induction time after mixing.
4. Minimum and maximum dry and wet film thickness per coat.
5. Minimum and maximum curing time between coats including atmospheric
conditions for each.
6. Curing time before submergence in liquid.
7. Thinner and thinning ratios to be used with each paint.
8. Ventilation requirements.
9. Allowable atmospheric conditions during which the paint may be applied,
including ambient temperature, relative humidity and surface temperature.
10. Allowable applications methods.
11. Maximum allowable moisture content of surface to be painted.
12. Maximum storage life.
13. Manufacturer's certification that painting materials are in accordance with the
appropriate reference standards.
14. Material Safety Data Sheets and cautions concerning health hazards.
1.07 COLOR SELECTION
Section 09900
Painting Florida Keys Aqueduct Authority
Stock Island - Tank 3
TEAM 13-0612 TS - 22
A. All colors are as specified by the OWNER‟s color schedule after submittal of the
manufacturers color charts.
B. The CONTRACTOR shall submit a color chart, from the specified coating
manufacturer, to the OWNER to select a color for the exterior tank and logo. The
OWNER shall submit their choice to the CONTRACTOR in writing before
application of coatings.
1.08 DAMAGE CLAIMS
A. The CONTRACTOR shall be responsible for all damages that may be
caused by this painting operation to surrounding property.
PART 2 - PRODUCTS
2.01 MATERIALS
A. The products referenced in this section are presented as a standard of comparison.
Products manufactured by other manufacturers may be substituted upon request.
Requests for substitution shall be in accordance with PART 1.06 above. Only
products of one manufacturer shall be used in a particular coating system.
B. Materials, supplies and articles provided shall be the standard products of
manufacturers. Paints in a particular coating system shall be the products of a single
manufacturer unless otherwise specified.
C. No lead containing coatings shall be used.
2.02 COATING MATERIALS
A. Each of the following manufacturers is capable of supplying the industrial coating
thin film materials specified in this specification. Where manufacturers and paint
numbers are listed, it is to show the type and quality of coatings that are required.
Proposed substitute materials for the paint numbers shown must be proven to satisfy
the material descriptions and to equal or exceed the properties of the listed
materials.
1. Tnemec Co., Inc.
2. Induron Protective Coatings, Inc.
B. The thick film liner in Option 2 shall be provided by Industrial Maintenance Group,
Plant City, Florida. No substitutions will be permitted.
C. Standard products of manufacturers other than those specified in 2.02.A will be
accepted when it is demonstrated to the Engineer that they are equal in composition,
durability, usefulness and convenience for the purpose intended. The written
acceptance by the OWNER shall be obtained before any such alternate products are
ordered by the CONTRACTOR. Request for substitution will be considered
provided the following minimum conditions are met:
1. The proposed coating system shall use an equal or greater number of separate
coats to achieve the required dry film thickness.
2. The proposed coating system shall use coatings of the same generic type.
3. Request for substitution shall have the directions for application and description
literature, which includes generic type, nonvolatile content by volume, and
information confirming that the substitution is equal to the specified coating
system.
Florida Keys Aqueduct Authority
Stock Island - Tank 3
Section 09900
Painting
TEAM 13-0612 TS - 23
4. The contractor shall provide certified laboratory data sheets showing the results
of complete spectrographic and durability tests performed on the proposed
substitute. A laboratory which conforms to the provisions of ASTM E329 and
which is a member of the American council of Independent Laboratories shall
perform tests. Costs incurred in the testing program shall be borne by the
contractor.
D. No extra contract time for tank out of service will be granted for evaluation of
substitute materials.
PART 3 - EXECUTION
3.02 GENERAL
A. All work shall be accomplished by skilled workmen in a professional manner.
B. All abrasive blasting, coating or lining application shall be done by experienced
personnel. The awarded CONTRACTOR shall be able to provide proof of five
successful projects as prime contractor on projects of similar size, completed in the
last five years.
C. All work shall comply with Local, County, State, and Federal regulations
concerning abrasive blasting and pollution control.
D. All rigging shall meet OSHA requirements, and shall be operated in a safe manner,
and will conform to industry standards. All rods and other tank appurtenances that
are used for rigging purposes shall be carefully checked for structural integrity
before use in climbing or rigging. Deficiencies shall be reported and corrected
before use.
E. The CONTRACTOR shall test all coating to be removed to assure that the coating
will meet environmental requirements for removal and disposal.
F. Prior to abrasive blasting, the CONTRACTOR shall demonstrate that the fill and
drain piping is plugged sufficiently as to not fill or clog the piping with abrasives.
G. The close proximity of OWNER property shall require containment of blast
abrasives, paint over-spray, and spatter.
H. All waste material, including spent abrasives and chemicals, shall be disposed of in
accordance with the CONTRACTOR submitted Waste Disposal Plan.
I. Surfaces to be coated shall be cleaned in accordance with SSPC-SP1 (Solvent
Cleaning). Before applying coating or surface treatments, oil, grease, dirt, rust,
loose mill scale, old weathering coatings, and other foreign substances shall be
removed, except as specified. Oil and grease shall be removed before mechanical
cleaning is started. Where mechanical cleaning is accomplished by blast cleaning,
the abrasive used shall be washed, graded and free of contaminants, which might
interfere with the adhesion and performance of the coatings. Blast abrasive shall be
"Black Beauty" or approved equal, capable of achieving a surface profile of 1 to 3
mils (unless otherwise recommended by the paint manufacturer). The
CONTRACTOR shall furnish for the INSPECTOR's use, a Keane-Tator Surface
Comparator Number 372 or equal.
J. Clean cloths and clean fluids shall be used in solvent cleaning. Cleaning and
painting shall be scheduled so that dust and spray from the cleaning process does not
fall on wet, newly painted surfaces.
Section 09900
Painting Florida Keys Aqueduct Authority
Stock Island - Tank 3
TEAM 13-0612 TS - 24
K. Preparation of metallic surfaces shall be based upon comparison with SSPC-VIS 1
(ASTM D2200), and as described herein. The CONTRACTOR shall furnish the
photographic standards. To facilitate inspection, the CONTRACTOR shall, on the
first day of abrasive blasting operations, abrasive blast metal panels to the standards
specified. Plates shall measure a minimum of 8.5 inches by 11 inches. Panels
meeting the requirements of the Specifications shall be initialed by the
CONTRACTOR and OWNERS Representative and coated with a clear
non-yellowing finish. One of these panels shall be prepared for each type of
abrasive blasting and shall be used as a comparison standard throughout the project.
L. Compressed air for blast cleaning shall be clean, dry, and oil free as confirmed by a
blotter test each day prior to beginning blasting. Test air quality by directing the air
stream from the blast nozzle without abrasive onto a clean piece of blotter paper for
1 minute. Inspect the blotter for contamination.
M. All abrasive and dust from the blasting operation shall be removed from the surfaces
before the painting application has begun.
N. Abrasive blasted surfaces shall be coated the same day that blasting was done, and
before any rust bloom occurs.
O. All painting equipment shall be maintained in good working order and shall be
comparable to that described in the coating manufacturer's most recent application
instructions. It shall be thoroughly cleaned and inspected daily.
P. Worn nozzles, tips, etc., shall be replaced regularly. Effective oil and water
separators shall be used and serviced on all air lines.
3.03 SAFETY
A. The CONTRACTOR shall be responsible for fall protection and confined space
entry on this project.
B. All applicable OSHA requirements shall be followed.
C. All personnel entering the tank shall be certified for confined space entry.
3.04 PROTECTION OF AREAS NOT TO BE COATED
A. All areas that are not specified to be coated or repaired shall be adequately protected
to avoid any damage or overspray during all repairs, washing, blasting, and painting
operations. The CONTRACTOR shall confer with the OWNER before conducting
any work, to clarify these areas.
B. The areas NOT to be coated include:
1. All conduit and instrumentation.
2. All stainless steel and any unpainted piping.
3. Concrete foundation and containment area.
C. Tank surfaces under items that are not to be coated shall be coated. Items not to be
coated shall be temporarily relocated while the area is coated. After coating has
cured, the relocated equipment shall be returned to its original location.
D. Any damage shall be repaired at the CONTRACTOR's expense.
3.05 APPLICATION
A. Unless otherwise specified, the application of paint shall be in accordance with
SSPC-PA-1 latest edition and the paint manufacturer's printed instructions for
Florida Keys Aqueduct Authority
Stock Island - Tank 3
Section 09900
Painting
TEAM 13-0612 TS - 25
surface preparation, mixing, thinning, and paint application unless otherwise
specified herein. The CONTRACTOR shall fully comply with all recommendations
and instructions set forth by the paint manufacturer. All coatings shall be applied
before the shelf life of the coating expires.
B. Paint shall only be applied over thoroughly dry surfaces, with a surface temperature
that conforms to the manufactures minimum - maximum limits, and the relative
humidity shall not exceed 85%. The surface temperature must be at least 5 degrees
above the dew point. Paint shall not be applied to a condensing surface. Paint shall
not be applied when freshly painted surfaces may be damaged by rain, fog, dust or
condensation and/or when it can be anticipated that these conditions will prevail
during the drying period.
C. Except where otherwise specified, thinning shall only be done when necessary for
the workability of the coating material and then only in accordance with the coating
manufacturer‟s most recent printed application instructions. Use only approved
manufacturer's thinner. Thinner shall only be added in the exact quantities as
recommended by the manufacturer.
D. Paint shall be applied in a uniform layer, with a 50% over-lap pattern. All runs and
sags shall be brushed out immediately or the paint will be removed and surface
recoated.
E. All fasteners, welded seams, edges, holes, etc. shall have special care taken in
applying the prime and topcoat. These areas shall be brush coated before applying
the coating to remaining surfaces. This is to insure proper dry film thickness on
these areas.
F. Areas inaccessible to spray shall be brushed. If inaccessible by brush, daubs or
sheepskins may be used if approved by the manufacturer. Top quality, properly
styled brushes and rollers shall be used. The brushing or rolling shall be done so
that a smooth coat as nearly uniform in thickness as possible is obtained. Brush or
roller strokes shall be made to smooth the film without leaving deep or detrimental
marks.
G. Drying time between coats shall adhere to the coating manufacturer's
recommendation with conditions of temperature and humidity taken into account.
All paint and coating materials shall be stored prior to application under cover and
at temperature within 10 degrees F. of the anticipated application temperature.
H. The dry film thickness of each coat and the entire system shall follow the coating
manufacturer's recommendations and this specification. The number of coats
specified shall be a minimum to achieve the specified film thickness.
I. All paint damaged areas, which shall be touch-up painted, shall be feathered after
surface preparation to provide a smooth, even surface before priming. Touch-up
systems will be the same as the original specification. Manufacturer's complete
touch-up recommendations shall be followed.
3.06 VENTILATION
A. The CONTRACTOR shall provide forced air ventilation while work is being done
inside the tank, after each coat is applied and continue after completion of painting
for a minimum period of seven days to insure proper cure of the coating. Air shall
be exhausted from the lowest portions of the tank with the top openings kept open
and clear. Ventilation requirements will be in strict accordance with the
Section 09900
Painting Florida Keys Aqueduct Authority
Stock Island - Tank 3
TEAM 13-0612 TS - 26
manufacturer's recommendations, this Specification and all OSHA requirements as
applicable.
3.07 SURFACE PREPARATION
A. EXTERIOR
1. The CONTRACTOR shall remove all chalk, loose paint, deposits, or other
surface contamination by High Pressure Water Wash (min. 4000 psi) of the
entire exterior immediately prior to any additional cleaning or coating
application.
2. All new steel and all rusted and abraded spots shall be abrasive blast cleaned in
accordance with SSPC-SP6 “Commercial Blast”.
3. NEW ROOF VENTS – The new vents shall be abrasive blasted and primed, in
accordance with the “Exterior” portions of this specification, prior to
installation. All coatings damaged from the installation of the new roof vents
shall be power tool cleaned in accordance with SSPC-SP11 “Power Tool Clean
to Bare Metal”.
4. The CONTRACTOR shall take every precaution necessary to contain dust from
the abrasive blasting operation blowing towards the surrounding buildings and
passing traffic.
B. INTERIOR
1. The CONTRACTOR shall remove all dirt, loose paint, deposits, oils, grease, or
other surface contamination by High Pressure Water Wash (min. 4000 psi) of
the entire interior immediately prior to any additional cleaning or coating
application.
2. The entire interior shall be abrasive blast cleaned in accordance with SSPC-
SP10 “Near White Metal” immediately prior to coating application.
3.08 COATING SYSTEMS
A. INTERIOR – THIN FILM COATING
1. All interior coatings, caulking materials, and linings of potable water tank shall
be approved for application in accordance with NSF-61 for use in potable water
systems.
2. All interior surfaces shall be cleaned as applicable in Section 3.06.B
„SURFACE PREPARATION, INTERIOR‟.
3. Each coat shall be of a contrasting color to facilitate application and inspection.
4. Interior Coating System:
a) PRE-COAT: Apply by brush, one (1) coat of the specified first coat to all
weld seams, roof lap joints, structural members, manholes, edges, lugs and
brackets. Drying time at this point is not critical and application of first coat
may proceed as soon as brushed areas are coated.
b) PRIME COAT: Apply by brush, roller, or spray to all bare metal, prepared
interior surfaces, Tnemec Company's Series N140 PotaPox Plus at a dry film
thickness of 3 mils to 5 mils.
c) TOP COAT: Apply by brush to all interior surfaces, Tnemec Company
Series N140 PotaPox Plus at a dry film thickness of 3 mils to 5 mils.
Florida Keys Aqueduct Authority
Stock Island - Tank 3
Section 09900
Painting
TEAM 13-0612 TS - 27
d) COVERAGE RATES: Maximum coverage rates shall not exceed
manufacturer's recommendations per coat. The total dry film thickness of the
interior system shall be no less than 6.0 mils at any location.
e) CAULKING: After the finish coat has cured per the manufacturer's
recommendations, all of the roof lap joints, angles, and brackets that cannot
be removed and other areas as indicated by the inspector shall be caulked
using a one component polyurethane sealant as manufactured by Sika
Corporation, Sika-flex 1a. The sealant shall be applied per the
manufacturer's data sheets.
B. EXTERIOR
1. The CONTRACTOR shall submit coating manufacturer's color charts to the
ENGINEER within ten (10) days after Contract Award. Finish colors will be
selected by the OWNER.
2. Each coat shall be of a contrasting color to facilitate application and inspection.
3. A one-gallon kit of the finish coat of paint shall be supplied to the OWNER as
touch-up paint. This kit shall be "fresh" at the time of final acceptance of the
tank. The touch-up kit shall have a minimum shelf life of one (1) year.
4. The CONTRACTOR shall be responsible for all damages that may be caused by
this painting operation to surrounding property and to vehicles traveling on and
parked on adjacent properties and roadways.
5. The CONTRACTOR shall clean all exterior surfaces as applicable in Section
3.07.A „SURFACE PREPARATION, EXTERIOR‟.
6. The CONTRACTOR shall apply the following Exterior Coating System,
including the entire exterior of Tank 3 and the roof vent areas of Tanks 1 and 2:
a) PRIME COAT: Apply by brush, roller, or spray, to all bare metal surfaces
Tnemec Company's Series 135 Chembuild at a dry film thickness of 3.0 mils
to 5.0 mils.
b) INTERMEDIATE COAT: Apply by brush or roller, to all exterior surfaces
Tnemec Company's Series 1028 Enduratone at a dry film thickness of 2.0
mils to 3.0 mils.
c) TOP COAT: Apply by brush or roller to all exterior surfaces, one coat of
Tnemec Company's Series 1028 Enduratone at a dry film thickness of 2.0
mils to 3.0 mils.
7. COVERAGE RATES: Maximum coverage rates shall not exceed
manufacturer's recommendations per coat. The total dry film thickness of the
exterior system shall be no less than 7.0 mils.
8. The CONTRACTOR shall take every precaution necessary to avoid paint
splatter blowing toward the street or any surrounding structures, including the
parking area and buildings. This also includes vehicles driving near the tank.
C. INTERIOR – THICK FILM LINER – OPTION 2
1. The CONTRACTOR shall prepare all interior surfaces as applicable in Section
3.06.B „SURFACE PREPARATION, INTERIOR‟.
2. The CONTRACTOR shall apply the following liner to the floor and 36” up the
tank shell:
Section 09900
Painting Florida Keys Aqueduct Authority
Stock Island - Tank 3
TEAM 13-0612 TS - 28
a) Geotextile: Cut and fit one layer of geotextile specified in Section
13200.2.01.F to the entire tank floor only. Geotextile does not extend up the
tank shell.
3. Apply one application of IMG Watersafe-UB™ at 100-120 mils DFT over
the entire floor and 36” up the tank shell.
- END OF SECTION 09900 –
Florida Keys Aqueduct Authority
Stock Island - Tank 3
Section 13200
Repairs and Renovations
TEAM 13-0612 TS - 29
SECTION 13200
REPAIRS & RENOVATIONS
PART 1 - GENERAL
1.08 DESCRIPTION
A. A specific description of all repairs and renovations to be performed are as listed
herein.
B. Two options are presented for performing this project. Both options, and the parts
thereof, are detailed in this section.
1.09 RELATED SECTIONS
A. 01010 Scope of Work
B. 05050 Welding
C. 07710 Aluminum Geodesic Dome Roof
D. 09900 Painting
1.10 REFERENCED STANDARDS
A. API American Petroleum Institute
B. AWWA American Water Works Assocation
C. AWS D1.1 American Welding Society
D. SSPC Society for Protective Coatings
E. NACE National Association of Corrosion Engineers
1.11 SUBMITTALS – The CONTRACTOR shall include in the submittals the following:
A. Structural: Submit detailed fabrication and erection drawings. Indicate all
dimensions, method of assembly, connections and bill of materials.
B. Should more than one submittal be required, later submittals should clearly identify
all changes.
C. Indicate all shop and erection dimensions and details, including cuts, copes,
connections, holes, threaded fasteners and welds.
D. Indicate all shop and field welds by AWS A2.0 "Welding Symbols".
E. Revise original approved shop and erection drawings to correspond with changes
made in the field.
F. Submit Product data, (manufacturer's literature), Specifications and installation
instructions for manufactured items.
G. Upon completion of all work, “as built” drawings shall be submitted. These
drawings shall be marked up to show all changes or modifications made that deviate
from the approved submittal drawings. Final payment will not be processed until the
“as built” drawings are submitted.
Section 13200
Repairs & Renovations
Florida Keys Aqueduct Authority
Stock Island - Tank 3
TEAM 13-0612 TS - 30
1.12 TANK REPAIR REQUIREMENTS
A. OPTION 1 – Steel Replacement
1. Roof Structure: Remove the damaged structural roof members as described below.
Replace damaged roof support structure including columns, rafters, bracing, etc, as
needed to restore the structural integrity of the roof. All new structural shapes and
bolts shall be the same material, size, and dimensions as the original tank design.
All joints and connections shall use the same design as the original tank design
(bolted, welded, etc.). All welding shall be performed in accordance with API-653
Standards.
The basis of the Bid for this Option is to replace, at a minimum, the following:
a) 12” I-Beam – Qty 20
b) Vertical Column – Qty 2
c) 2” x 2” x 3/8” – As needed
Photo of Roof Structure
2. Rim Angle: Damaged sections of the rim angle shall be cut out and replaced. New
angle shall be the same material and size as the original tank design. All new angle
sections shall be rolled to a 70‟-0” radius prior to installation. Joints between new
12” I-Beam
Vertical Column
Florida Keys Aqueduct Authority
Stock Island - Tank 3
Section 13200
Repairs and Renovations
TEAM 13-0612 TS - 31
and existing angle sections shall be full penetration butt welds only. Testing of
welds shall be in accordance with Section 05050.
3. Roof Plates: All damaged roof plates shall be straightened or replaced as necessary
to restore a water tight seal and to properly install new structural members. New
roof plates shall be A36 steel, 3/16” nominal thickness. Any weld between the roof
plates and the rim angle shall be 3/16” fillet weld and serve as a “frangible joint” as
specified in API-650.
4. Roof Vent – Tanks 1, 2, and 3: Install a new 24” diameter tank mounting flange and
new mushroom-style vent assembly. The new vent/screen assembly shall have a
capacity to pass air so that at the maximum possible rate of water, either entering or
leaving the tank, excessive pressure will not be developed. The vent screen shall be
designed and so constructed as to prevent the entrance of birds, insects or animals
and ensure fail-safe operation in the event that the insect screens frost over or
become blocked. Vent design shall be in accordance with AWWA D100. The neck
and mounting flange shall be welded carbon steel with a bolted flange to attach the
vent. The vent body and hood shall be constructed of aluminum and shall be bolted
to the mounting flange. The screen shall be non-corrosive material.
5. Floor Replacement: The entire floor of this tank shall be replaced in accordance
with API-653 Standards. The tank shell shall be cut ½” above the existing shell-to-
bottom weld to remove the old floor. The new floor shall be A36 steel, lap welded.
The floor plates attached to the shell (“sketch plates”) shall be 5/16” thick. The
remainder of the floor shall be ¼” thick. Testing of welds shall be in accordance
with Section 05050.
6. Foundation: After removing the old floor and prior to installation of the new floor,
remove the top 6” of existing soil and replace it with 6” of clean, dry sand with
50,000 ohm/cm resistivity. The new sand shall be compacted and leveled.
7. Coatings: After all repairs are complete, abrasive blast the entire interior and apply
the “Thin Film” coating system specified in Section 09900. The exteriors of all
three tanks shall be prepared and coated in accordance with Section 09900.
B. OPTION 2 – Geodesic Dome Roof
1. Windgirder: Install a new steel windgirder as shown on drawings S100 through
S103.
2. Geodesic Dome Roof: Install a new geodesic dome roof as specified in Section
07710 of this specification
3. Floor Section Replacement: A 24” wide, perimeter section of this floor shall be
replaced with a new “annular ring”. The annular ring shall be A36 steel, 5/16”
thick. Joints between ring sections shall be full penetration butt welds using back-
up bars. The existing floor plates shall be lap-welded on top of the new annular
ring.
4. Floor Patch Plates: All through holes in the floor shall be covered with a ¼”-thick,
lap welded patch plate in accordance with API-653 standards.
5. Soil Replacement: As the existing floor plates are removed, all discovered voids in
the soil under the tank floor shall be filled with clean, dry, structural sand having a
minimum resistivity of 50,000 ohm/cm.
Section 13200
Repairs & Renovations
Florida Keys Aqueduct Authority
Stock Island - Tank 3
TEAM 13-0612 TS - 32
6. Thick-Film Liner: After all repairs are complete on the floor and the entire floor and
shell are abrasive blast cleaned, cover the entire floor with geotextile specified in
Section 13200.2.01.F and apply 100-120 mils of IMG Watersafe-UB™ over the
entire floor and 36” up the tank shell.
7. Coatings: The remainder of the interior shall be prepared and coated in accordance
with the “Thin Film” coating system specified in Section 09900. The tank exterior
shall be prepared and coated in accordance with Section 09900.
8. Roof Vent – Tank 1 and 2: Install a new 24” diameter tank mounting flange and
new mushroom-style vent assembly. The new vent/screen assembly shall have a
capacity to pass air so that at the maximum possible rate of water, either entering or
leaving the tank, excessive pressure will not be developed. The vent screen shall be
designed and so constructed as to prevent the entrance of birds, insects or animals
and ensure fail-safe operation in the event that the insect screens frost over or
become blocked. Vent design shall be in accordance with AWWA D100. The neck
and mounting flange shall be welded carbon steel with a bolted flange to attach the
vent. The vent body and hood shall be constructed of aluminum and shall be bolted
to the mounting flange. The screen shall be non-corrosive material.
1.13 QUALITY ASSURANCE – The CONTRACTOR shall use the following standards for
construction and personnel:
A. Design Criteria: API-653 (current edition)
B. Qualifications of Suppliers and Personnel:
1. Steel Fabricator: Not less than 5 years continuous experience in the fabrication
of structural steel.
2. Steel Erector: Not less than 5 years continuous experience in the erection of
tanks or similar structures.
3. Welding: All welding shall be performed by welders who are currently qualified
by tests as prescribed in AWS D1.1 "Qualification Procedure".
4. A current and accurate Weld Procedure Specification (WPS) and Procedure
Qualification Report (PQR) shall be submitted to the Owner for approval for all
welds performed on this tank.
5. Use experienced riggers to erect steel. Carefully plan and lay out work so that a
minimum of cutting and removal of undamaged material will be necessary.
1.14 EXTRA WORK
A. Any potential work items that are found after the work has begun shall be brought to
the attention of the ENGINEER in writing via formal RFI. Submittal by e-mail is
acceptable. These out of scope items shall be approved by Owner‟s directive only.
PART 2 - PRODUCTS
2.01 MATERIALS
A. All materials shall be new and shall be in conformance with API-653 Standards.
B. Structural steel shapes, plates and bars: ASTM A36.
C. Machine bolts: Use ASTM A307 machine bolts at all connections not indicated on
Drawings as high-strength or stainless steel.
Florida Keys Aqueduct Authority
Stock Island - Tank 3
Section 13200
Repairs and Renovations
TEAM 13-0612 TS - 33
D. Pipe Flanges: ANSI B16.5 standard flanges.
E. Welding electrodes:
1. Mild steel-covered arc welding electrodes for A36 steels: AWS A5.1, E70XX
Series, low hydrogen, having a minimum yield point of 60,000 psi.
F. Geotextile: TenCate Mirafi® 135N, or approved equal. A needle punched, nonwoven geotextile composed of polypropylene fibers.
2.02 MATERIAL HANDLING
A. Storage of Materials
1. Store steel to be incorporated into this project above ground on platforms, skids
or other approved supports.
2. Protect steel from corrosion.
3. Store welding electrodes in accordance with AWS D12.1.
PART 3 - EXECUTION
3.02 FABRICATION
A. All fabrication shall be done by manufacturers who are regularly engaged in the
manufacture of the type of work herein specified.
3.03 SCHEDULE
A. All repair and renovation work shall be accomplished prior to start of any painting
operations.
3.04 ERECTION
A. All work shall be accomplished by skilled workmen in a workmanlike manner.
B. All welders shall hold current AWS certification and shall submit all credentials
to the Engineer prior to starting work.
C. All welding will be subject to testing in accordance with ASME Section V.
- END OF SECTION 13200 -
Cover01 Contents.pdf