INSTALLATION INSTRUCTIONS V00029KP_01 © Panduit Corp. 2017 FOR TECHNICAL SUPPORT www.panduit.com/resources/install_maintain.asp Dual Single PEV12 PEV1296 PEVF12 PEVF1296 PED12B1 PED1296B1 PEV10 PEV1096 (Sold Separately) PEVF10 PEVF1096 PED10B1 PED1096B1 PEV8 PEV896 PEVF8 PEVF896 PED8B1 PED896B1 PEV6 PEV696 PEVF6 PEVF696 PED6B1 PED696B1 [6.0] (8.0) *10.0* 12.0 20.31” = 19” RACK 24.31” = 23” RACK TYP 1.25 TYP 4.75 TYP 3.00 16.00” = 19” RACK 20.00” = 23” RACK TYP [10.25] (12.25) *14.25* 16.25 10.75 TYP 6.00 7.8” STD. MOUNTING 12.6” FULLY EXTENDED 10.7” FULLY EXTENDED 15.5” STD. MOUNTING 40% of Capacity* 60% of Capacity* 7.75 TYP 4.75 TYP 7.8” STD. MOUNTING 12.6” FULLY EXTENDED 10.7” FULLY EXTENDED 15.5” STD. MOUNTING [24.8] 31.8 (37.8) *43.8* 1.07 TYP 16.00” TYP 23.2” to Inside Panel of Manager [6.0] (8.0) *10.0* 12.0 [25.9] 32.9 (38.9) *44.9* 7.8” STD. MOUNTING 12.6” FULLY EXTENDED 1.75 TYP 15.5” STD. MOUNTING 10.7” FULLY EXTENDED 40% of Capacity* 60% of Capacity* (1) P ATCHRUNNER High Capacity Vertical Cable Manager (6) 1/2-13 Hex Nuts (6) 1/2-13x1.0” Bolts (12) Washers for 1/2-13 bolts P ATCHRUNNER High Capacity Vertical Cable Manager PART NUMBERS LOCATION GUIDE: Standard and 6-inch Racks CONTENTS 6” Vertical Manager dimension shown in brackets [...] 8” Vertical Manager dimensions shown in parenthesis (...) 10” Vertical Manager dimensions shown in asterisk *...* 3” Standard CEA Rack 6” Rack For horizontal dimensions: 6” Vertical Manager dimension shown in brackets [...] 8” Vertical Manager dimensions shown in parenthesis (...) 10” Vertical Manager dimensions shown in asterisk *...* For vertical dimensions: 23” Deep 4-Post Rack dimension shown in brackets [...] 36” Deep 4-Post Rack dimensions shown in parenthesis (...) 42” Deep 4-Post Rack dimensions shown in asterisk *...* LOCATION GUIDE: 4-post Racks *Reversible Total capacity of dual sided manager is split 60% and 40%. Note: Single-sided managers have equivalent dimensions to the 60% capacity side of a Dual-sided manager. *Reversible Total capacity of dual sided manager is split 60% and 40%. Page 1 of 5
Transcript
Page 1: PATCH RUNNER High Capacity Vertical Cable Manager

INSTALLATION INSTRUCTIONS V00029KP_01© Panduit Corp. 2017

FOR TECHNICAL SUPPORT www.panduit.com/resources/install_maintain.asp

Dual Single

PEV12

PEV1296

PEVF12

PEVF1296

PED12B1

PED1296B1

PEV10

PEV1096

(Sold Separately)

PEVF10

PEVF1096

PED10B1

PED1096B1PEV8

PEV896

PEVF8

PEVF896

PED8B1

PED896B1PEV6

PEV696

PEVF6

PEVF696

PED6B1

PED696B1

[6.0]

(8.0)

*10.0*

12.0

20.31” = 19” RACK

24.31” = 23” RACK

TYP

1.25

TYP

4.75

TYP

3.00

16.00” = 19” RACK

20.00” = 23” RACK

TYP

[10.25]

(12.25)

*14.25*

16.25

10.75

TYP6.00

7.8” STD. MOUNTING

12.6” FULLY EXTENDED

10.7” FULLY EXTENDED

15.5” STD. MOUNTING

40% of

Capacity*

60% of

Capacity*

7.75

TYP

4.75

TYP 7.8” STD. MOUNTING

12.6” FULLY EXTENDED

10.7” FULLY EXTENDED

15.5” STD. MOUNTING

[24.8]

31.8

(37.8)

*43.8*

1.07

TYP

16.00”

TYP

23.2” to Inside Panel

of Manager[6.0]

(8.0)

*10.0*

12.0

[25.9]

32.9

(38.9)

*44.9*

7.8” STD. MOUNTING

12.6” FULLY EXTENDED

1.75 TYP

15.5” STD. MOUNTING

10.7” FULLY EXTENDED

40% of

Capacity*

60% of

Capacity*

(1) PATCHRUNNER High Capacity Vertical Cable Manager(6) 1/2-13 Hex Nuts (6) 1/2-13x1.0” Bolts(12) Washers for 1/2-13 bolts

PATCHRUNNER High Capacity Vertical Cable Manager

PART NUMBERS

LOCATION GUIDE: Standard and 6-inch Racks

CONTENTS

6” Vertical Manager dimension shown in brackets [...]8” Vertical Manager dimensions shown in parenthesis (...)10” Vertical Manager dimensions shown in asterisk *...*3” Standard

CEA Rack

6” Rack

For horizontal dimensions:6” Vertical Manager dimension shown in brackets [...]8” Vertical Manager dimensions shown in parenthesis (...)10” Vertical Manager dimensions shown in asterisk *...*

For vertical dimensions:23” Deep 4-Post Rack dimension shown in brackets [...]36” Deep 4-Post Rack dimensions shown in parenthesis (...)42” Deep 4-Post Rack dimensions shown in asterisk *...*

LOCATION GUIDE: 4-post Racks

*Reversible Total capacity of dual sided manager is split 60% and 40%.

Note: Single-sided managers have equivalent dimensions to the 60% capacity side of a Dual-sided manager.

*Reversible Total capacity of dual sided manager is split 60% and 40%.

Page 1 of 5

Page 2: PATCH RUNNER High Capacity Vertical Cable Manager

INSTALLATION INSTRUCTIONS V00029KP_01

FOR TECHNICAL SUPPORT www.panduit.com/resources/install_maintain.asp Page 2 of 5

Door Bracket Base Installation

Install Door Bracket Base into cutout features on side panels using (2) #12-24 X 1/2" Screws.

Top of part

Bottom of part

#12-24 X 1/2" Screws

If material from Door Bracket Base cannot be touched or seen protruding through cutouts on inside of panel, then the Door Bracket is not properly engaged.

Note: When properly installed, Door Bracket Base will protrude through cutouts on inside of panel.

Panduit recommended mounting locations

Mounting of a PATCHRUNNER High Capacity Vertical Manager

Panduit recommends that the PATCHRUNNER High Capacity Vertical Manager be mounted such that the front face of the manager’s panels are 1.25” forward of the front face of the rack it is attached to. However, other holes on the side panel of the manager and the channels of the rack are available so that the manager may be moved forward to accommodate applications which require a larger bend radius requirement.

Other available holes for mounting

Standard Rack

6” Deep Steel Rack 4-Post Rack

Other available holes for mounting

Panduit recommended mounting locations

Door Bracket

Material visibleBrackets Engaged

Material not visibleBrackets not engaged

Door Bracket Base

Page 3: PATCH RUNNER High Capacity Vertical Cable Manager

INSTALLATION INSTRUCTIONS V00029KP_01

FOR TECHNICAL SUPPORT www.panduit.com/resources/install_maintain.asp

Page 3 of 5

After the first rack is mounted to the floor with the appropriate hardware, Use Three 1/2-13x1.0” bolts (supplied with the vertical cable manager panels) to fasten the PATCHRUNNER High Capacity Vertical Cable Manager to the rack. Next, mount the second rack to the other side of the PATCHRUNNER High Capacity Vertical Cable Manager using the remaining 1/2-13x1.0” bolts. Then mount the second rack to the floor using the appropriate hardware.Note: Design is only intended to have PED*B1 doors to mount in front of the manager.

Mounting of a PATCHRUNNER High Capacity Vertical Manager on a 7 Ft. Tall 4-Post Rack

Bottom Mounting LocationDetail View

Mounting Locations(Near top, Near center, Near bottom)

NutWashers

Bolt

Note:Tighten bolts to 120 in-lbs.

Bottom Mounting LocationDetail View

(6” Steel Rack)

Mounting Locations(Near top, Near center,

Near bottom)

Nut Washers Bolt

After the first rack is mounted to the floor with the appropriate hardware, Use Three 1/2-13x1.0” bolts (supplied with the vertical cable manager panels) to fasten the PATCHRUNNER High Capacity Vertical Cable Manager to the rack. Next, mount the second rack to the other side of the PATCHRUNNER High Capacity Vertical Cable Manager using the remaining 1/2-13x1.0” bolts. Then mount the second rack to the floor using the appropriate hardware.

Center Mounting of a PATCHRUNNER 7Ft. Tall High Capacity Vertical Manager on Standard 7 Ft. Tall CEA Rack or 6”- 7Ft. Tall Steel Rack

Bottom Mounting LocationDetail View

(Standard CEA Rack)

Mounting Locations(Near top, Near center,

Near bottom)

Nut Washers Bolt

Page 4: PATCH RUNNER High Capacity Vertical Cable Manager

INSTALLATION INSTRUCTIONS V00029KP_01

FOR TECHNICAL SUPPORT www.panduit.com/resources/install_maintain.asp

Washers

After the first 8 ft. tall rack is mounted to the floor with the appropriate hardware, Use Three 1/2-13x1.0” bolts (supplied with the vertical cable manager panels) to fasten the PATCHRUNNER High Capacity 8 Ft. Tall Vertical Cable Manager to the rack. Next, mount the second 8 ft. tall rack to the other side of the PATCHRUNNER High Capacity 8 Ft. Tall Vertical Cable Manager using the remaining 1/2-13x1.0” bolts. Then mount the second 8 ft. tall rack to the floor using the appropriate hardware.

Mounting of a PATCHRUNNER High Capacity Vertical Manager on a 8 Ft. Tall 4-Post Rack

Bottom Mounting LocationDetail View

Mounting Locations(Near top, Near center, Near bottom)

Nut Washers Bolt

Note:Tighten bolts to 120 in-lbs.

Bottom Mounting LocationDetail View

(6"- 8Ft Tall Steel Rack)

Mounting Locations(Near top, Near center,

Near bottom)

Nut Washers Bolt

After the first 8 ft. tall rack is mounted to the floor with the appropriate hardware, Use Three 1/2-13x1.0” bolts (supplied with the vertical cable manager panels) to fasten the PATCHRUNNER High Capacity 8 Ft. Tall Vertical Cable Manager to the rack. Next, mount the second 8 ft. tall rack to the other side of the PATCHRUNNER High Capacity 8 Ft. Tall Vertical Cable Manager using the remaining 1/2-13x1.0” bolts. Then mount the second 8 ft. tall rack to the floor using the appropriate hardware.

Center Mounting of a PATCHRUNNER 8 Ft. Tall High Capacity Vertical Manager on Standard 8 Ft. Tall CEA Rack or 6"- 8 Ft. Tall Steel Rack

Bottom Mounting LocationDetail View

(Standard 8 Ft. Tall CEA Rack)

Mounting Locations(Near top, Near center,

Near bottom)

Nut Bolt

Page 4 of 5

Page 5: PATCH RUNNER High Capacity Vertical Cable Manager

INSTALLATION INSTRUCTIONS V00029KP_01

For instuctions in Local Languagesand Technical Support:

www.panduit.com/resources/install_maintain.asp

E-mail:[email protected]

Fax:(708)444-6448www.panduit.com

Page 5 of 5

Equipment Mounting Instructions1. Mount appropriate cage nuts to cage nut holes provided in center mounting brackets. Mounting to the cage nut holes on the bottom of a center mounting bracket to the holes on the top of the center mounting bracket directly below will meet the correct mounting requirement for CEA equipment.2. Secure equipment using appropriate screws

Screws

Screws

Cage Nuts

Cage Nuts

Detail ViewCenter Mouning Bracket Multi-Layer Strain

Relief BarQuick Net Patch Panel

Note: For cleaning PANDUIT recommends using ‘SIMPLE GREEN’ all purpose cleaner (or local equivalent) and a lint free cloth

FINGER REMOVAL

Score Groove

Step 1:Starting with bottom fingers, align tabs on base of finger with keyholes on side panel of manager. The cable retainers on the finger will be pointed upward,

Finger flags

Apply outward pressure (from inside of manager) until plastic finger clicks into place.

Step 2:

Step 3:

Repeat Steps 1 and 2 on remaining fingers.

Outwardpressure

Removal/Replacement:Use a flat-head screwdriver to release snaps at locations shown and apply inward pres-sure until finger is removed.

Apply inward pressure at finger ends to remove finger.

Finger Installation

Snap locations


Recommended