+ All Categories
Home > Documents > Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC –...

Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC –...

Date post: 16-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
98
SRC Operations Pty Ltd ABN: 36 612 974 366 Patons Lane Resource Recovery Centre Quarry Operation Management Plan June 2019 R.W. CORKERY & CO. PTY. LIMITED Prepared by:
Transcript
Page 1: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC Operations Pty Ltd ABN: 36 612 974 366

Patons Lane

Resource

Recovery Centre

Quarry Operation

Management Plan

June 2019

R.W. CORKERY & CO. PTY. LIMITED Prepared by:

Page 2: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

This page has intentionally been left blank

Page 3: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC Operations Pty Ltd ABN: 36 612 974 366

Patons Lane Resource

Recovery Centre

Quarry Operation

Management Plan

Prepared for:

SRC Operations Pty Ltd ABN: 36 612 974 366 PO Box 7 ENFIELD NSW 2136

Telephone: 1300 424 646 Email: [email protected]

Prepared by:

R.W. Corkery & Co. Pty. Limited Geological & Environmental Consultants ABN: 31 002 033 712

Brooklyn Office: 1st Floor, 12 Dangar Road PO Box 239 BROOKLYN NSW 2083

Orange Office: 62 Hill Street ORANGE NSW 2800

Brisbane Office: Suite 5, Building 3 Pine Rivers Office Park 205 Leitchs Road BRENDALE QLD 4500

Telephone: (02) 9985 8511 Email: [email protected]

Telephone: (02) 6362 5411 Email: [email protected]

Telephone: (07) 3205 5400 Email: [email protected]

Ref No. 582/20 June 2019

Page 4: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

ii

This Copyright is included for the protection of this document

COPYRIGHT

© R.W. Corkery & Co. Pty Limited 2019 and

© SRC Operations Pty Ltd 2019

All intellectual property and copyright reserved.

Apart from any fair dealing for the purpose of private study, research, criticism or review, as permitted under the Copyright Act, 1968, no part of this report may be reproduced, transmitted, stored in a retrieval system or adapted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without written permission. Enquiries should be addressed to R.W. Corkery & Co. Pty Limited.

Document Control Until Finalised for Approval Document Title Quarry Operation Management Plan Document No. 582/20 Version Issued by – Date Distributed to Comments Rec’d from – Date Version 1 RWC – 24 February 2016 SRC – D. White/L. Smith D. White – 29 February 2016 Version 2 RWC – 2 March 2016 SRC – D. White/L. Smith D. White - 25 May 2016 Version 3 RWC – 30 May 2016 SRC – D. White/L. Smith DPE – 21 November 2016 Version 4 RWC – 24 Nov. 2016 SRC – D. White/L. Smith DPE – 29 November 2016 Version 5 RWC – 2 Dec 2016 SRC – D. White/L. Smith DPE – 7 December 2016 Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor Bingo – 19 June 2019 Final Approved by: D. Taylor Date: 24/06/19 Final Document Distribution

Hard Copy to: Not required No. of Copies: - USBs to: Not required No. of USBs - Email to: [email protected]

Page 5: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

CONTENTS Page

iii

ACRONYMS AND KEY TERMS ............................................................................................................... VI

1. INTRODUCTION AND OBJECTIVES ............................................................................................. 1

1.1 INTRODUCTION ................................................................................................................... 1

1.2 OBJECTIVES ......................................................................................................................... 1

1.3 QUARRY OPERATION MANAGEMENT PLAN APPROVAL REQUIREMENTS ................. 3

1.4 DOCUMENT PREPARATION ............................................................................................... 5

2. PROJECT DESCRIPTION ............................................................................................................... 6

2.1 OVERVIEW ............................................................................................................................ 6

2.2 MANAGEMENT PLAN FRAMEWORK .................................................................................. 6

2.3 DESCRIPTION OF OPERATIONS AND WORKS ................................................................ 8

2.3.1 Staging ...................................................................................................................... 8

2.3.2 Site Establishment and Construction of the RRA ..................................................... 9

2.3.3 Operation ................................................................................................................ 13

3. CONSULTATION – SCHEDULE 5 CONDITION (4)(B) ................................................................ 16

3.1 CONSULTATION REQUIRED BY THE APPROVAL .......................................................... 16

3.2 COMMUNITY CONSULTATION.......................................................................................... 16

4. APPROVED SITE LAYOUT AND ACTIVITIES ............................................................................ 17

4.1 APPROVED SITE LAYOUT ................................................................................................. 17

4.2 APPROVED ACTIVITIES .................................................................................................... 17

4.2.1 Clay/Shale Extraction and Stockpiling .................................................................... 17

4.2.2 Recycling and Re-processing Operations............................................................... 19

4.2.3 Landfilling ................................................................................................................ 19

4.2.4 Off-site Clay/Shale Transportation .......................................................................... 21

4.3 EXTRACTION AREA AND STOCKPILING LAYOUT.......................................................... 21

5. RESOURCES ................................................................................................................................. 23

5.1 GEOLOGICAL SETTING ..................................................................................................... 23

5.2 RESOURCE TYPES ............................................................................................................ 23

5.3 RESOURCE QUANTITIES .................................................................................................. 24

6. EXTRACTION PLAN ..................................................................................................................... 27

6.1 OVERALL EXTRACTION PLAN .......................................................................................... 27

6.2 CELL 1 EXTRACTION PLAN .............................................................................................. 27

7. EXTRACTION OPERATIONS ....................................................................................................... 33

7.1 QUALITY CONTROL ........................................................................................................... 33

7.2 EXTRACTION METHODS AND EQUIPMENT .................................................................... 33

7.3 SEPARATION FROM LANDFILL OPERATIONS – SCHEDULE 5 CONDITION 5(4)(E) ... 34

7.4 EXTRACTION SEQUENCE ................................................................................................. 34

7.5 EXTRACTION RATES ......................................................................................................... 34

Page 6: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

CONTENTS Page

iv

8. STOCKPILE MANAGEMENT ........................................................................................................ 37

8.1 STRATEGY .......................................................................................................................... 37

8.2 STOCKPILE LAYOUT .......................................................................................................... 37

8.3 STOCKPILE CONSTRUCTION – SCHEDULE 5 CONDITION (4)(D)(I/IV) AND (K) .......... 43

8.4 STOCKPILE MANAGEMENT – SCHEDULE 5 CONDITION (4)(G) ................................... 45

8.5 STOCKPILE SURVEYS – SCHEDULE 5 CONDITION (4) (I/II) AND (J) ............................ 45

9. PERSONNEL MANAGEMENT ...................................................................................................... 46

9.1 INTRODUCTION .................................................................................................................. 46

9.2 ROLES AND RESPONSIBILITIES ...................................................................................... 46

9.3 TRAINING – SCHEDULE 5 CONDITION (4), (H), (I,II) ....................................................... 46

10. DOCUMENTATION........................................................................................................................ 47

10.1 EXTRACTION RECORDS ................................................................................................... 47

10.2 QUARTERLY SURVEY RECORDS .................................................................................... 47

10.3 OFF-SITE CLAY/SHALE TRANSPORTATION – SCHEDULE 5, CONDITIONS (4), (I/II) AND (I/VIII).................................................................................................................... 47

10.4 PUBLICATION ..................................................................................................................... 47

11. REFERENCES ............................................................................................................................... 48

APPENDICES Appendix 1 Correspondence from Government Agencies ..................................................................... 51

Appendix 2 Curricula Vitae ..................................................................................................................... 85

FIGURES Figure 1 Site Location........................................................................................................................... 2

Figure 2 Management Plan Framework ............................................................................................... 7

Figure 3 Management Plan Approval Process ..................................................................................... 7

Figure 4 Site Establishment Works .................................................................................................... 11

Figure 5 Layout Of Recycling and Reprocessing Area ...................................................................... 12

Figure 6 Cell 1 General Arrangement ................................................................................................ 14

Figure 7 Approved Site Layout ........................................................................................................... 18

Figure 8 Extraction and Stockpiling Layout ........................................................................................ 22

Figure 9 Entire Extraction Area Layout .............................................................................................. 28

Figure 10 Cell 1 Extracted Layout ........................................................................................................ 29

Figure 11 Cell 1 Extraction Sequence .................................................................................................. 31

Figure 12 Cell 1 Extraction / Waste Separation ................................................................................... 35

Figure 13 Indicative Stockpile Layout - North Ramp and Cells 1A and 1B .......................................... 40

Figure 14 Indicative Stockpile Layout - Cells 1C (Upper Level) ........................................................... 41

Figure 15 Indicative Stockpile Layout - Cell 1C (Lower Level)............................................................. 42

Page 7: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

CONTENTS Page

v

TABLES Table 1 Quarry Operation Management Plan Requirements ............................................................. 3

Table 2 Clay Quantities Required for Liner in Cell 1 ......................................................................... 20

Table 3 Daily and Intermediate Cover Requirements ....................................................................... 20

Table 4 Volume of Materials for Final Capping ................................................................................. 20

Table 5 Material Types and Intended Uses ...................................................................................... 24

Table 6 Estimated Resources in Cell 1 ............................................................................................. 25

Table 7 Use and Stockpiling of Materials Extracted from the Northern Ramp and Cells 1A and 1B .................................................................................................................................. 38

Table 8 Use and Stockpiling of Materials Extracted from Northern Ramp and Cells 1C (Upper Level) ....................................................................................................................... 39

Table 9 Use and Stockpiling of Materials Extracted from Northern Ramp and Cells 1C (Lower Level) ....................................................................................................................... 43

Table 10 Clay/Shale Requirements during Cell 1 Extraction Operations ........................................... 43

Page 8: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

vi

ACRONYMS AND KEY TERMS ACRONYMS

bcm bank cubic metres

C&D construction and demolition

C&I commercial and industrial

CLC Community Liaison Committee

DP&E Department of Planning and Environment

EMS environmental management system

EPA Environment Protection Authority

FMPPR Further Modified Preferred Project Report

lcm Loose cubic metres

QOMP Quarry Operation Management Plan

RRA recycling and reprocessing area

RWC RW Corkery & Co. Pty Limited

KEY TERMS

Cells Discrete areas within the Site for the extraction of clay/shale. Three main cells have been defined each with three sub-cells.

Clay/Shale A general term referring to clay, weathered and fresh shale.

Test kiln A ceramic kiln typically less than 1m3 internal volume used to fire small samples of clay/shale recovered from the active extraction area on a daily basis.

Stockpiles An accumulation of materials with the same general quality placed in an orderly manner for subsequent use / retrieval.

Fired-Colour The colour achieved through the firing / burning of clay/shale within a test kiln typically at approximately at 1 000ᵒC to 1 050ᵒC.

Clay Highly weathered rock which displays a plastic characteristic.

Shale A fine grained sedimentary rock comprising compressed/consolidated clay particles – often displays bedding.

Laminite A fine to medium grained sedimentary rock with alternating thin layers (lamellae) of shale and siltstone / sandstone.

Claystone A fine grained sedimentary rock comprising compressed/consolidated clay particles – typically massive and without bedding.

Siltstone A fine grained sedimentary rock comprising compressed/consolidated silt particles.

Extraction A term used to describe the recovery of extractive materials, e.g. clay/shale through the use of a range of earthmoving equipment.

Page 9: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

1

1. I N T RO D U C TI ON AN D O BJ E CT I VES

1.1 INTRODUCTION

The preparation of this Quarry Operation Management Plan (“QOMP”) has been co-ordinated for SRC Operations Pty Ltd by RW Corkery & Co. Pty Limited (RWC) to document the manner in which the approved extraction operations within the Patons Lane Resource Recovery Centre (“the Project”) will be undertaken throughout its operational life. Emphasis is placed in the QOMP upon the planned extraction operations and the management of the stockpiles of material extracted from the cells that will ultimately be backfilled with waste.

This document has been prepared focusing upon the extraction activities in the first cell (Cell 1) and the stockpiling of materials extracted from this cell. This approach has been adopted in accordance with Schedule 3, Condition 32 of Project Approval MP09_0074 (“the Project Approval”) which provides for the staged submission of Management Plans for the Project with the approval of the Secretary of the Department of Planning and Environment (DP&E). Correspondence with the Secretary of DP&E confirming approval for the submission of staged plans for the QOMP is attached in Appendix 1.

Considerable care has been taken to ensure that the quarry operations and the construction of Cell 1 remains entirely consistent with the Further Modified Preferred Project Report (FMPPR) and the other plans specified in the project approval. The cell design was developed with reference to all relevant plans in the project approval. A review of the cell design and compliance with the project approval was conducted during a teleconference with representatives of the client, Douglas Partners, Lead Auditor Trevor Brown and independent subject matter expert Ian Swane (Practice Leader Jacobs Practice Leader – Contaminated Land Management; Principal Engineer, Site Auditor) on 14 May 2015.

Accordingly, the volumes of material to be extracted remain the same as set out in the project approval. Extraction operations for Stage 1 are designed around Cell 1 and involve the removal of an estimated 769 000 tonnes of material. Details of the materials and volumes to be extracted are set out in Section 5.3. These activities are entirely consistent with the project approval. The FMPPR shows a total of 733 815 tonnes of material to be extracted from Cell 1 (Source Table 2.3). The small increase of 35 185 tonnes is due to the excavation of an access ramp on the northern boundary which is constructed in the area of Cell 2 (estimated at 37 600 tonnes as set out in Table 5).

Figure 1 displays the location of the Patons Lane RRC, within a 60ha area of land located west of Luddenham Road, Orchard Hills, referred to throughout this document as “the Site”.

1.2 OBJECTIVES

The key objectives of the QOMP are to:

i) satisfy the requirements of Schedule 5 Condition 4 of Project Approval MP09_0074.

ii) provide an overview of the overall extraction plan for the entire site for the life of Patons Lane RRC;

provide a level of detail for the extraction operations in Cell 1;

Page 10: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

2

Source: Arcadis

Figure 1 SITE LOCATION

Page 11: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

3

i) provide for the separation of the extraction operations and waste placementactivities; and

ii) provide a level of detail for the stockpiling activities for materials extracted fromCell 1.

1.3 QUARRY OPERATION MANAGEMENT PLAN APPROVAL REQUIREMENTS

The QOMP has been prepared to satisfy Schedule 5, Condition 4 of Project Approval MP09_0074 which was issued by the NSW Land and Environment Court on 13 July 2012. Table 1 lists where each of the individual requirements of this condition are addressed in this document.

Table 1 Quarry Operation Management Plan Requirements

Page 1 of 3 Cond. No.

Requirement Document Reference

How Addressed?

Schedule 5, Condition 4 – Project Approval MP09_0074 Quarry Operation Management Plan 4. The Proponent shall prepare and implement a

Quarry Operation Management Plan for the Project. This plan must:

a) be prepared by a suitably qualified team of experts;

Section 1 / Appendix 2

Curriculum Vitae are provided for Mr Corkery (Geological Consultant) and Mr Hoare (Quarry Designer)

b) be prepared in consultation with the EPA and Council;

Section 3.1 / Appendix 1

Both EPA and Council were consulted – see documentation in Appendix 1

c) be approved by the Director-General prior to the commencement of site establishment;

Section 1 – QOMP is hereby submitted to DP&E for approval

d) include stockpile construction methods that minimise the visibility and acoustic impact of the use of equipment during the placement or removal of materials from any part of the stockpile, in particular where any part of the equipment will be above RL 54m AHD;

Section 8.3 The method of stockpile construction has been compiled in order to achieve each of the nominated requirements.

e) show the active land fill cell separate from all extraction activities at all times;

Section 7.3 Figure 12 displays the separation between the operational extraction area and the placed wastes.

f) include a protocol to ensure stockpiles of clay/shale materials for use by the brick industry are kept separate from material to be used for cell construction, daily waste covering and capping;

Section 7.1 and 8.2

Section 7 outlines the components of the required protocol whilst Section 8 addresses the manner in which the clay/shale is stockpiled for the various uses.

Page 12: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

4

Table 1 (Cont’d) Quarry Operation Management Plan Requirements

Page 2 of 3 Cond. No.

Requirement Document Reference

How Addressed?

Schedule 5, Condition 4 – Project Approval MP09_0074 (Cont’d) Quarry Operation Management Plan (Cont’d) g) include provision for all clay/shale stockpiles for

brick industry to be sign posted with a description of the material to ensure there is no contamination, and that plant operators know where to place the different materials;

Section 8.4 The signposting of stockpiles will be an important component of the stockpile management.

h) include provision for regular staff or contractor training is to be undertaken to reinforce the importance of keeping the clay types separate;

Section 9.3 All relevant staff and contractors will be trained through the site induction process and through reference to relevant on-site procedures.

i) specify management practices so that stockpiles are constructed, accessed and managed as follows:

i. The clay material to be sold to the brick manufacturing industry will be kept separated from the material to be used during the cell, construction, daily waste covering and capping of the finished areas.

Section 7.1, 8.2 The layout of the stockpiles has been designed with the clear separation of clay/shale raw materials for the brick industry.

ii. The light-firing shale stockpiles will be located so as not to interfere with the construction of the cells or the emplacement of waste and all stockpiles will be sign posted with a description of the material to ensure there is no contamination. The sign posting will also ensure that the plant operators and the Stockpile Management Supervisor know where to place the different materials and regular training will take place to reinforce the importance of keeping the clay types separated.

Sections 7.1, 8. and 9.2

The method of stockpile management together with a comprehensive quality control system will ensure that all clay/shale materials are correctly stockpiled for subsequent use / despatch.

iii. There will be several stockpiles on site at any one time based on the type of material, i.e. cream-firing clay, light pink-firing clay and red-firing clay.

Section 7.1 and 8

As above.

Stockpile Construction iv. The construction will use scrapers for

placement of the first 5 to 6 metres and then dump trucks and a dozer for the final 2 to 3 metres.

Section 8.3 The method of construction in Section 8.3 reflects this requirement.

Management of Stockpiled Materials v. Once an area on the site has been designated

as a stockpile location, signs will be erected describing the material to be deposited within that location. The plant operator responsible for preparing the stockpile will have responsibility for ensuring that only the designated clay is deposited there.

Section 8.2 The use of signs is an integral part of stockpile management.

Page 13: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

5

Table 1 (Cont’d) Quarry Operation Management Plan Requirements

Page 3 of 3 Cond. No.

Requirement Document Reference

How Addressed?

Schedule 5, Condition 4 – Project Approval MP09_0074 (Cont’d) Quarry Operation Management Plan (Cont’d) vi The Site Manager will arrange for quarterly

surveys to be carried out on the stockpiles. The survey results will be correlated against the surveys undertaken on the site as a whole and the information provided in the original geological report undertaken on the site.

Section 8.5 Section 8.5 outlines the plans for quarterly stockpile surveys.

vii All vehicles exporting material from the site will be required to do so via the weighbridge. A record will be maintained of the type, quantity and destination of the material exported on each vehicle.

Section 10.3 All heavy vehicles transporting clay/shale from the site would pass over the weighbridge which would generate electronic records for auditing purposes.

viii Monthly reports detailing the type of material exported from the site will be prepared for l&l NSW and the EPA, if required.

Section 10.3 As above.

j) Includes a protocol that requires surveys of the stockpiles once every three months, with the first survey being on or before the date that operations commence.

Section 8.5 Section 8.5 outlines the plans for quarterly stockpile surveys.

k) The batter slopes of stockpiles must be no more than 1:3 (Vertical: Horizontal), unless otherwise approved by the EPA.

Section 8.3 / Appendix 1

The nominated batter slopes have been adjusted in consultation with the EPA to 1:1 (V:H) – see EPA Correspondence in Appendix 1.

1.4 DOCUMENT PREPARATION

This document has been prepared by Mr Robert W. Corkery, Principal of RW Corkery & Co. Pty Limited. Mr Corkery is a qualified geologist with in excess of 40 years’ experience working with the Brick Industry in the Sydney region. A copy of Mr Corkery’s brief curriculum vitae is presented in Appendix 2. He has managed a number of resource investigations on the Site, the most recent being in 2004. The 2004 resource report is referred to throughout this document as RWC (2004). During the preparation of the QOMP, Mr Corkery worked closely with RPM Global Pty Ltd, a specialist mining engineering company to assist in the development of a computerised geological model and a series of extraction plans which have been relied upon during the preparation of this QOMP. A copy of a curriculum vitae for RPM Global’s senior Mining Engineer (Mr Matthew Hoare) is also included in Appendix 2. Mr Corkery also consulted with Mulgoa Quarries Pty Ltd and PGH Bricks during the preparation for the QOMP to ensure a practical plan is developed to maximise the recovery of suitable brick manufacturing raw materials.

Page 14: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

6

2. P R OJ E C T DE SC R I P T I O N

2.1 OVERVIEW

The Patons Lane Resource Recovery Centre (‘the Project’), located in Orchard Hills, NSW is a resource management facility located within Lot 40, DP 738126, i.e. the former Erskine Park Quarry owned by SRC Operations Pty Ltd (‘the Principal’). Project Approval MP09_0074 was granted by the NSW Land and Environment Court for the establishment and operation of the resource recovery centre in August 2012 and approved for the landfilling of commercial and industrial (C&I) and construction and demolition (C&D) waste types (general solid (non-putrescible) waste).

The objectives of the Patons Lane Resource Recovery Centre (RRC) are to:

• provide a facility to assist the NSW Government to meet the recycling targets forC&I and C&D waste;

• recover a high proportion of clay/shale resources for the brick and constructionindustry;

• receive and emplace wastes and residuals from the on-site recycling; and

• progressively rehabilitate a disused quarry to re-instate the agriculturallyproductive land consistent with the surrounding lands.

2.2 MANAGEMENT PLAN FRAMEWORK

Approval was obtained from the Department of Planning and Environment (DP&E) pursuant to Condition 32 of Schedule 3 of the Project Approval to submit all but two plans (the Site Establishment Noise Management Plan and the Construction Traffic Management Plan) in stages. Stage 1 is defined as being works and activities up to the completion of the extraction of Cell 1, and is estimated to take five to seven years. Stage 1 plans, apart from those outlined above, will need to be updated prior to undertaking subsequent Stages 2 and 3.

In accordance with the requirements of the Project Approval, this plan and other plans of management relevant to Site Establishment for the Project were approved by the DP&E and verified via a Pre-Site Establishment Audit process, prior to the commencement of the Site Establishment works and activities (i.e. construction works). Prior to the commencement of operations (i.e. the receipt of any waste materials) additional plans must be prepared and approved by DP&E (in accordance with the Project Approval) and verified via a separate Pre-Operational Compliance Audit.

All site establishment and operations management plans are designed to work in conjunction with the Landfill Environmental Management Plan (LEMP) which provides the overarching environmental management framework for the Project. An outline of the management plan framework is shown in Figure 2.

The management plan approval process is outlined in Figure 3.

Page 15: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

7

Figure 2 MANAGEMENT PLAN FRAMEWORK

Figure 3 MANAGEMENT PLAN APPROVAL PROCESS

Page 16: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

8

2.3 DESCRIPTION OF OPERATIONS AND WORKS

2.3.1 Staging

The Project will operate in accordance with three key stages. Stage 1 is defined as being up to the completion of excavation of Cell 1 which includes all site establishment works and Cells 1A, 1B and 1C. Management plans will be updated in future prior to additional works being commenced (such as Cells 2 and 3) as part of Stages 2 and 3.

Stage 1 works and activities are made up of the following components:

• Site establishment works and activities

• Construction of the recycling and reprocessing area (RRA)

• Operation of the landfill and the RRA and cell construction up to the completionof the excavation of Cell 1 (made up of Cells 1A, 1B and 1C).

Stage 1 is expected to take 5-7 years to complete.

Plans for Stage 1 have been prepared based on the impacts of the above activities being carried out at full operational level i.e. up to the maximum permitted tonnages and vehicle movements as permitted by the Project Approval. General construction and operating parameters are summarised in the following sections.

• Hours of construction:

1. Monday to Friday, 7am to 6pm

2. Saturday, 8am to 1pm

3. Sunday, no work

• Total input: up to 450,000 tonnes per annum (tpa)

• Waste recycled: up to 350,000 tpa

• Waste landfilled: up to 205,000 tpa

• Heavy vehicles: up to 250 heavy vehicle movements per day

• Maximum resource export rate: 160,000 tpa

• Maximum stockpile height: 54 m AHD

• Construction: 10 to 15 people

• Operation: 20 people full time, plus up to 10 part-time contractors

• Hours of operation:

1. Monday to Friday 7am to 5pm

2. Saturday 8am to 2pm.

Page 17: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

9

2.3.2 Site Establishment and Construction of the RRA

The details of these works and activities which have been included in the assessment undertaken to develop the Construction Traffic Management Plan and the Site Establishment Noise Management Plan (SENMP) are set out below.

These construction activities are expected to take 18 months to complete and will be carried out within the following parameters:

• Hours of Construction:

1. Monday to Friday 7am to 6pm

2. Saturday 8am to 1pm

3. Sunday, no work

• Personnel:

1. Construction: 10 to 15 people.

Site Establishment

The site establishment works and activities are as follows:

• Construction/shaping of the northern face and much of the eastern face to theirfinal rehabilitated landform and landscaping of those faces. Construction of thenorthern face will be achieved through the following:

1. Reshaping the existing north eastern and north western bund walls, byreducing their height in some areas, raising their height in other areas tocreate an even northern face with a maximum elevation of 53 m AHD, and amore gentle northerly slope than currently exists. The new northern face andacoustic mound will provide acoustic protection for earthmoving andlandfilling equipment/vehicles operating within Cells 1 and 2. The acousticmound will be removed at the conclusion of capping in Cell 2 when it is nolonger needed for acoustic protection.

2. Areas to the north of the acoustic mound will be regraded to their finalrehabilitated landform with slopes of approximately 5%. Final landscapingof these areas will occur during site establishment.

• Partial rehabilitation of the existing southern and southwestern bund walls throughthe reduction in the elevation to an approximate elevation of between 57 m AHDand 58 m AHD such that they will not be visible from any residence within TheVines Estate. Once re-shaped, the surface and adjoining batter slopes will berevegetated.

• Upgrading and sealing of Patons Lane and upgrading the entrance to the site(from Patons Lane) together with the installation of three weighbridges andupgrade of associated office building.

Page 18: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

10

• Site preparatory works within the recycling and re-processing area to create the required landform and create a suitable pad for the materials recycling facility warehouse and mobile recycling equipment.

• Construction and commissioning of the on-site wheel wash facility.

• Upgrading and sealing the internal road network beyond the proposed wheel wash facility to the exit point from the recycling and re-processing area.

• Building and construction works and infrastructure works as shown in Figure 4.

These works and activities will be undertaken generally in the order set out below (and referenced on Figure 4) noting that the scheduling of specific works will be dependent on factors such as weather, commercial factors including contractor availability, specific logistical requirements and many other issues and will vary accordingly. In addition, many of the works and activities will need to be undertaken simultaneously. The works and activities associated with site establishment are as follows:

1. Construct surface water controls (integrate dams as required)

2. Excavation of stockpiled clay/shale and construct northern face (external and Internal slopes)

3. Regrading/shaping areas north of the northern face

4. Dewatering of quarry void

5. Landscaping northern face

6. Construct track for Transgrid access

7. Construct raw material stockpiles

8. Excavate recycling and re-processing area to 48 m AHD to 49 m AHD. Extraction of clay to form required landform

9. Clay/shale extraction in Cell 1A, then 1B and 1C

10. Install leachate riser and drainage layer in Cell 1A and then 1B

11. Construct Initial Leachate Evaporation Pond

12. Construction of recycling and re-processing area infrastructure (see Figure 5 for details)

13. Maintain height of the eastern face of 57 m to 58 m AHD (outer slope reduced for landscaping)

14. Construct/re-establish Dam 3 (3A&B)

15. Construct/re-establish Dam 4 (4A)

16. Construct/re-establish Dam 5(5A)

17. Construct Dam 6

18. Establish contingency stockpile area

19. Establish contingency stockpile area

20. Upgrade internal road network [sealed]

Page 19: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

11

Figure 4

SITE ESTABLISHMENT WORKS Source: Arcadis

Page 20: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

12

Figure 5 LAYOUT OF RECYCLING AND

REPROCESSING AREA Source: Arcadis

Page 21: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

13

21. Upgrade internal road network [unsealed]

22. Construct wheel wash facility Pro

23. Upgrade site entrance

24. Install weighbridges

25. Construct car park

26. Construct site office

27. Reduction in height from southwestern face

28. Establish workshop area

29. Construct acoustic mound.

Construction of the RRA The management plans have been based on the impacts of the construction of the entire RRA. The layout of the RRA is set out below in Figure 5. These items are largely buildings and structures that will be subject to Construction Certificates, BCA regulations and Occupation Certificates certified by an approved certifying authority.

The infrastructure permitted to be constructed as part of the RRA will be undertaken generally in the order set out below (and referenced on Figure 5) noting that the scheduling of specific works will be dependent on factors such as weather, commercial factors including contractor availability, specific logistical requirements and other issues and will vary accordingly. In addition, many of the following works and activities will need to be undertaken simultaneously:

1. Drainage works 2. C&D / C&I Recycling Building 3. Product Bays 4. Delivery Area 5. Road network 6. Crushing and Screening Area 7. Recycling Facility Warehouse 8. Amenities building 9. Car Park.

2.3.3 Operation

The specific works and activities associated with Stage 1 operations are the: • emplacement of wastes into Cell 1A; • construction of Cell 1B and 1C including the selective extractive operations to

extract the clay/shale resource and related stockpiling activities; and • receipt and processing of wastes in the RRA with residuals being compacted,

baled, and emplaced in Cell 1A and 1B.

Figure 6 shows the general arrangement of Cell 1.

Page 22: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

14

Source: Arcadis

Figure 6 CELL 1 GENERAL ARRANGEMENT

Page 23: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

15

Compacted and baled residual waste will be transported from the RRA to the landfill cell via a dedicated on-site heavy vehicle fitted with a walking floor trailer.

Mobile plant and equipment to be used for the placement of waste into the cells include an excavator with a detachable grab attachment for handling the baled waste, and a bucket attachment for movement of daily cover. A compactor will also be used to provide further compaction of residual waste.

Bulldozers, dump trucks and excavators will be used for the excavation of Cells 1B and 1C.

Page 24: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

16

3. C O N S U LTAT I O N – S c he d ul e 5 C on di t i o n (4 ) ( B )

3.1 CONSULTATION REQUIRED BY THE APPROVAL

The project approval requires that the QOMP must

“b) be prepared in consultation with the EPA and Council”

Accordingly, thorough consultation was undertaken with these agencies as well as the DP&E during the preparation of this document as required by the project approval. Chronological details of the consultation and all relevant correspondence in contained in Appendix 1.

Consultation with government agencies undertaken during the preparation of this document is summarised as follows:

1. Discussions with, and correspondence to, DP&E seeking approval to prepare a Quarry Operation Management Plan (QOMP) in stages with the first stage focusing on the extraction and stockpiling activities for Cell 1. This correspondence was sent to the DP&E in accordance with Schedule 3, Condition 32 on 27 November 2015. The correspondence to the DP&E also sought to obtain support to modify the nominated (and impractical) method of stockpile construction and provided in Schedule 5, Condition 4(i). A copy of the DP&E’s written response dated 18 May 2016 is presented in Appendix 1.

2. Discussions with, and correspondence to the Environment Protection Authority (EPA) and Penrith City Council seeking their input to the issues to be addressed in this document. This correspondence was sent to both agencies in response to the requirement of Schedule 5, Condition 4(b). The correspondence to the EPA also sought to approve a variation to the batter slopes of stockpiles of materials extracted and stockpiled on site (i.e. in response to the requirement in Schedule 5, Condition 4k).

Discussions were held with the EPA on 7 March 2016 and correspondence was provided by the EPA on 11 April 2016. The EPA approved the draft QOMP on 27 May 2016 (see Appendix 1).

A meeting was held with Penrith City Council on 25 February 2016 and correspondence was provided by Council on 22 April 2016. PCC indicated on 11 April 2016 that the “QOMP appears to satisfy the requirements of the relevant condition of consent” and further advised on 22 April 2016 that they had no objections to the staged approach (see Appendix 1).

3.2 COMMUNITY CONSULTATION

There is no formal requirement within the Project Approval for specific consultation with the community regarding the QOMP. However, general community consultation for the Project has been undertaken by SRC with respect to the overall Project. SRC has undertaken a letter box drop with follow-up one-to-one discussions held with interested neighbours. A component of these discussions has related to SRC's overall program for the submission of a range of management plans, including this document. It is noted that all management plans including the QOMP are required to be available on the Patons Lane RRC website (patonslanerrc.com.au).

Additionally, the community will be kept informed of the development of various plans via the Community Liaison Committee (CLC).

Page 25: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

17

4. AP P R O V E D S I T E L AY O U T AN D AC T I V I T I ES 4.1 APPROVED SITE LAYOUT

Figure 7 displays the site layout approved by the NSW Land and Environment Court. This figure is shown as Schedule 8 of the Project Approval being Appeal No. 10928 of 2010 and is identified as GHD DRG No. 21-10649-Y00. The layout comprises of the following key components.

1. An extraction area, part of which has previously been extracted covering a total area of 24.5ha. The extraction area comprises three cells, namely Cells 1, 2 and 3 each of which has been subdivided into three sub-cells namely: Cell 1A, 1B and 1C; Cell 2A, 2B and 2C; and Cell 3A, 3B and 3C. The three extraction cells are proposed as the repositories for approved wastes.

2. A waste recycling and re-processing facility located within the southwestern corner of the Site in an area surrounded by an existing perimeter bund wall and a new internal bund wall. The footprint of the waste recycling and re-processing facility is approximately 5.6ha.

3. On-site infrastructure comprising site offices and amenities, weighbridges, workshop and internal roads.

4. On-site water and leachate management structures. Some of the dams within the Site are already constructed whilst other dams are proposed to be constructed. In some cases, the locations of the dams will be temporary as they will need to be relocated throughout the life of Patons Lane RRC.

5. Parts of the existing northern perimeter bund walls will be upgraded to provide the level of visual and acoustic protection for Patons Lane RRC to operate with an acceptable impact upon the amenity of surrounding landholders and occupiers.

4.2 APPROVED ACTIVITIES 4.2.1 Clay/Shale Extraction and Stockpiling

The extraction of clay/shale within the total approved extraction area will serve three purposes, namely:

i) the provision of approximately 3.15 million tonnes of clay/shale raw materials for brick manufacture;

ii) the provision of approximately 2.05 million tonnes of clay/shale for uses within the landfill component of Patons Lane RRC, i.e. for lining the floor of the waste cells, daily or intermediate cover and capping materials; and

creation of a void (within its related air space) that will provide sufficient volume for the emplacement of 4.3 million tonnes of waste.

Page 26: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

18

Figure 7 Approved Site Layout

A4 / Colour

Figure dated 04/04/19 inserted on 04/04/19

Page 27: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

19

For the purposes of the development application for Patons Lane RRC, Cell 1 was subdivided into three areas, referred to as Cells 1A, 1B and 1C (see configuration in Figure 7). For the purposes of this document, the boundaries of Cells 1A, 1B and 1C have been slightly modified to accommodate the results of the mining engineering design and design of the waste cells within Cell 1. The modified cell boundaries are relied upon throughout this QOMP.

The extraction of clay/shale materials to create the void for waste emplacement will require the various materials to be stockpiled until they are transported off site for brick manufacture or used on site for the uses outlined in (ii) above.

4.2.2 Recycling and Re-processing Operations

The recycling and re-processing operations will be undertaken within a dedicated area covering approximately 5.6ha (see Figure 7). The waste recycling and re-processing area will be surrounded by an acoustic earth mound which will restrict its visibility and noise propagation.

The recycling and reprocessing area will incorporate both commercial and industrial (C&I) recycling as well as the construction and demolition (C&D) re-processing. A series of bays will be constructed on the eastern side of the area for the storage of products produced in both of the above facilities.

Residual wastes from both the C&I and C&D re-processing operations will be placed in the on-site landfill.

4.2.3 Landfilling

The landfill cells created within Patons Lane RRC will be developed as a state-of-the-art landfill for the emplacement of the residual wastes generated by the on-site re-processing operations and other wastes delivered from external sources which cannot be re-processed or recycled.

The landfill will be developed as three cells, each with their own leachate collection system. The cells will vary in elevation from approximately 17m AHD to 30m AHD (Cell 1), 28m AHD to 31m AHD (Cell 2) and 28m AHD to 31m AHD (Cell 3). Each landfill cell will be developed progressively following the extraction of the clay/shale present to the depth nominated in Figure 9. Each Cell will be lined with 1m of compacted clay extracted on site and 0.3m of drainage material. Table 2 lists the quantities of clay required for the liner within each Cell.

Page 28: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

20

Table 2

Clay Quantities Required for Liner in Cell 11

All wastes placed within the landfill cells will be covered on a daily basis with at least 150mm of cover material, principally general purpose shale recovered on site. Intermediate cover will also be applied to those sections of the landfill not required for operational purposes for in excess of three months. For the purposes of planning, the quantity of daily and intermediate cover, will equate to approximately 5% of the waste volume within each section of the landfill. Table 3 lists the quantities of cover material required for the wastes placed within Cells 1A, 1B and 1C.

Table 3

Daily and Intermediate Cover Requirements1

Once the final landform level has been reached within the active landfill area, the final landform will be capped with a combination of materials comprising subsoil (0.75m of on-site clay), a sealing layer (0.6m of on-site clay) and seal-bearing layer (0.3m of on-site general purpose shale). Table 4 lists the quantity of clay and general purpose shale required for the capping of the final landform created during the extraction of Cell 1 and the related landfilling activities.

Table 4 Volume of Materials for Final Capping1

Layer2 Material Type Area (m2)

Thickness of Layer (m)

Volume of Material for Final Cap (bcm)

Subsoil Layer Clay 25 000 0.75 18 800 Sealing Layer Clay 25 000 0.6 15 000 Seal-bearing Layer GP Shale 25 000 0.3 7 500 Total 1.65 41 300 Notes: 1 Source: Douglas Partners 2 Source: Figure 2.20 within Further Modified Preferred Project.

Cell 11 Area (m2)2

Volume of Clay for Liner (bcm)3

Cell 1A 26 900 26 900 Cell 1B 18 300 18 300 Cell 1C 22 000 22 000 Total 67 200 67 200 Notes: 1 Source: Douglas Partners 2 Cell base as shown on Figure 8 3 Area includes the area under the clay barrier but doesn’t include the cell walls. 4 Based on a 1.0m thick clay liner across the base and assumed to be bank cubic

metres (bcm) (for 100% comparison).

Cell Waste Volume (m3)

Daily/Intermediate cover bcm lcm

Cell 1A 680 000 27 200 34 000 Cell 1B 360 000 14 400 18 000 Cell 1C 520 000 20 800 26 000 Total 1 560 000 62 400 78 000 Notes: 1 Source: Douglas Partners

Page 29: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

21

4.2.4 Off-site Clay/Shale Transportation

Schedule 3 Condition 23 limits the transportation of clay/shale off site for brick manufacture to 160 000tpa throughout the operational years of Patons Lane RRC. This quantity of clay/shale will be removed at an average of approximately 22 laden trucks per day. The approved maximum daily number of heavy vehicle movements is 250 per day.

4.3 EXTRACTION AREA AND STOCKPILING LAYOUT

For the purposes of this QOMP, Figure 8 presents the key extraction areas, i.e. within Cells 1, 2 and 3 and the three principal stockpiling areas, namely the northern, central and southern (contingency) stockpile areas. Other project components have been removed from this figure to enable a focus on the extraction and stockpiling operations.

Within the extraction area, two internal haul roads will be developed, both of which will be unsealed.

i) An internal road for waste trucks delivering waste to be active waste cell. Figure 8 shows this road will be aligned around the eastern side of Cell 3 and the eastern and north sides of Cell 2. This road will retreat as the waste cells are filled.

ii) An internal road for earthmoving equipment to travel to and from Cell 1 and for the removal of clay/shale from Cell 1 by scrapers and off-road haul trucks for placement within the stockpile areas. The road is strategically positioned between the northern and central stockpile areas.

Page 30: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

22

Figure 8 Extraction and Stockpiling Layout

Dated 04/04/19. Inserted 04/04/19

Page 31: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

23

5. R E SO U R C ES

5.1 GEOLOGICAL SETTING

The Site is underlain by a sequence of rocks within a geological unit referred to as the “Bringelly Shale”, a formation the Wianamatta Group that crops out over most of the Sydney’s western suburbs.

The Wianamatta Group is the main source of raw materials for the production of structural bricks in the Sydney region (Herbert, 1979). The Bringelly Shale generally comprises a sequence of consolidated sediments including claystone, siltstone, laminite, sandstone, tuff and coal. This unit is preferred for brick production due to its favourable plasticity characteristics and ability to produce a range of different fired colours including light-fired colours recovered from selectively extractable units.

In the vicinity of the Site, the Bringelly Shale dips gently to the southwest at approximately 5o and has been interpreted to be approximately 50m to 55m thick. The sediments show strong lateral facies variation, especially in the coarser grained sandstone beds, resulting in difficult lithological correlation of between drill holes. Minor faulting is evident within the existing extraction area but is not thought to significantly constrain the geological interpretation between drill holes.

Weathering of the sequence of rocks beneath the Site is generally intense in the top 3m to 4m from the surface. Weathering intensity decreases rapidly with depth below the zone of intense weathering with relatively fresh rock generally encountered within 4m to 8m below the natural surface.

5.2 RESOURCE TYPES

The resource types within the Site are categorised firstly upon the material type and secondly upon fired colour. For the purposes of this document, the key material types are:

i) clay;

ii) weathered shale;

iii) shale

iv) shale and laminite; and

v) sandstone.

The term “shale” embraces both claystone and siltstone rock types.

The materials to be extracted exhibit a wide range of fired colours generally reflecting the proportion of iron oxides in the clay and weathered shale and iron carbonate (siderite) in the unweathered shale and laminite.

Given the range of material types and fired colours, a total of seven groups of materials have been defined within the Site. For the purposes of this document, the materials on site and their intended uses are set out in Table 5. The nominated material types in Table 5 are generally consistent with terms used by the brick industry.

Page 32: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

24

Table 5

Material Types and Intended Uses

Material Type Intended Use Red clay On-site activities, e.g. lining waste cells

and capping White/pink clay Brick manufacture Brown shale Brick manufacture Cream shale Brick manufacture Apricot shale Brick manufacture Terracotta / Apricot-firing shale and laminite Brick manufacture (limited)

Daily cover and capping Sandstone Brick manufacture (limited)

Daily cover and capping

5.3 RESOURCE QUANTITIES

The resources to be extracted from Cell 1 have been quantified by RPM Global based upon the geological model compiled from data assembled in RWC (2004) and the consideration within four distinct areas within the extraction area, namely:

1. Northern ramp; 2. Cells 1A and 1B; 3. Cell 1C (upper level) and part of the southern ramp; and 4. Cell 1C (lower level) and part of the southern ramp.

The resources within Cells 1A and 1B are combined given the proposed extraction floor within that area of Cell 1 is similar to the existing extraction floor and the materials within that area will need to be extracted prior to the commencement of the liner construction in Cell 1A.

The resources within Cell 1C (upper level) and Cell 1C (lower level) have been reported separately given it is the clay materials and weathered shale within the upper level that will be required for use as the clay liner in Cell 1A.

Table 6 lists the estimated quantity of each type of material within each of the defined areas within Cell 1. It is noted that the quantities of resources were estimated through calculations of material volumes from the geological model and the conversion to tonnes assuming the following material specific gravities.

• 1m3 of clay = 1.8 tonnes/m3 • 1m3 of weathered shale = 2.0 tonnes/m3 • 1m3 of shale, siltstone, etc. = 2.2 tonnes/m3 • 1m3 of sandstone = 2.4 tonnes/m3

The quantities in Table 6 are strictly indicative as a range of variables influence the exact quantity of each material type extracted.

Table 6 also includes a quantity of fill materials that is currently located within a section of the existing perimeter bund wall whose footprint is located above the southwestern corner of Cell 1C.

Page 33: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QU

AR

RY O

PERA

TION

MA

NA

GEM

ENT PLA

N

SRC

Operations PTY LTD

P

ato

ns L

an

e R

eso

urc

e R

eco

ve

ry C

entre

R

ep

ort N

o. 5

82

/20

25

Table 6

Estimated Resources in Cell 1

Northern Ramp Cell 1A and Cell 1B Cell 1C (upper level) Cell 1C (lower level) Totals Material SG1 kbcm2 klcm3 kt4 kbcm2 klcm3 kt4 kbcm2 klcm3 kt4 kbcm2 klcm3 kt4 kbcm2 klcm3 kt4 Red Clay 1.8 13.4 16.75 24.1 1.1 1.4 2.0 28.8 36.0 51.8 8.8 11.0 15.8 52.1 65.1 93.8 White/Pink Clay 1.8 3.6 4.50 6.5 0.7 0.9 1.3 20.3 25.4 36.5 14.5 18.1 26.1 39.1 48.9 70.4 Brown Shale 2.0 0.2 0.25 0.4 0.5 0.6 1.0 30.1 37.6 60.2 0.6 0.8 1.2 31.4 39.2 62.8 Cream Shale 2.2 0.2 0.25 0.4 9.9 12.4 21.8 24.9 31.1 54.8 35.0 43.8 77.0 Apricot Shale 2.2 0.2 0.25 0.4 12.5 15.6 27.5 43.1 53.9 94.8 55.8 69.8 122.8 GP Shale5 2.2 2.4 3.00 5.3 20.1 25.1 44.2 69.3 86.6 152.5 91.8 114.8 202.0 Sandstone 2.4 0.2 0.25 0.5 11.2 14.0 26.9 9.9 12.4 23.8 21.3 26.6 51.1 Fill6 2.0 45.0 56.3 90.0 45.0 56.3 90.0

Totals 16.6 20.2 25.25 37.6 56.0 70.0 124.7 124.2 155.3 238.5 171.1 213.9 368.9 371.5 464.4 769.9 1: SG = Specific Gravity 2: kbcm = thousand bank cubic metres. 3: klcm = thousand loose cubic metres. 4: kt = thousand tonnes 5: GP Shale = General purpose shale comprising red-firing shale and laminite. 6: The nominated fill materials are currently located within section of the existing perimeter bund wall whose footprint is located above the southwestern corner of Cell 1C.

Page 34: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

26

Table 6 presents the resources within Cell 1 in terms of the following.

• Bank cubic metres (bcm), i.e. the in situ volume of materials calculated from the Cell 1 model.

• Loose cubic metres (lcm), i.e. the expanded volume of material calculated by increasing the bcm quantity by a conservative factor of 25%.

• Tonnes (t), i.e. the weight of the material calculated by multiplying the bcm by the nominated specific gravity.

Page 35: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

27

6. E X T R AC T I O N P L AN

Figure 8 displays the approved extraction area within the Site. Overall, the extraction area covers approximately 24.5ha of which approximately 5.4ha has already been disturbed by extraction activities. A small quantity of resources remains within the area previously extracted.

The extraction plan comprises three cells, namely, Cells 1, 2 and 3 with a total of nine sub-cells.

6.1 OVERALL EXTRACTION PLAN

Figure 9 displays the layout of the entire extraction area at the end of the extraction operations. The floor of the extraction area will be profiled to create the required basal topography for the waste cells. Elevations of the floor level within Cell 1A will vary from approximately 31m AHD to 17m AHD with the deepest area reflecting the existing extraction floor in that section of the cell. Elevations of the floor levels within Cells 1B and 1C will vary from approximately 28m AHD to 31m AHD. In the event cream-firing shale is exposed on the extraction floor, SRC will determine whether it is appropriate to remove the resource and replace it with lesser value clay/shale.

Figure 9 shows that Cells 1, 2 and 3 will be separated by a retained section of clay/shale (or compacted clay) up to 10m wide to assist in the long-term management of leachate within each cell by separating leachate capture into three distinct catchments and collection systems.

6.2 CELL 1 EXTRACTION PLAN

Figure 10 displays the layout of Cell 1 at the end of the extraction operations and Figure 11 displays the sequence of extraction through four distinct areas within Cell 1, i.e. those used for the definition of clay/shale resources (see Section 5.3).

1. Northern ramp

2. Cells 1A and 1B

3. Cell 1C (upper level) and part of the southern ramp

4. Cell 1C (lower level) and part of the southern ramp

Northern Ramp

The northern ramp will be excavated largely within the footprint of Cell 2 to provide for the long-term access for trucks delivering waste to the active waste placement area in Cell 1. The ramp will vary in grade from 1:10 (V:H) to 1:12 (V:H) and will extend from an elevation of approximately 44m AHD to approximately 31m AHD at the northeastern corner of Cell 1. Figure 11A displays the area and configuration of extraction to create the northern ramp.

The material extracted from within the northern ramp will be largely red clay and white/pink clay which will be transferred to the floor of Cell 1 and stockpiled within the floor of Cell 1B. The remainder of the material will be effectively blended and placed within the GP Shale stockpile area (see Section 8.2).

Page 36: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

28

Figure 9 Entire Extraction Area Layout

Dated 04/04/19. Inserted 04/04/19

Page 37: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

29

Figure 10 Cell 1 Extracted Layout

Dated 04/04/19. Inserted 04/04/19

Page 38: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

30

Cells 1A and 1B

Where practicable, the material within Cells 1A and 1B will be extracted in a manner that will remove the individual clay/shale and sandstone units. Figure 11B displays the area and configuration of extraction within Cells 1A and 1B. It is recognized that selective extraction of the individual units may be difficult, if not impossible, particularly in the area centered on the existing floor of Cell 1A.

It is noted that it may be preferable to extract sections of the floor in Cell 1B prior to the excavation of the northern ramp so that the clay from the ramp (and perhaps the relocated Dam 4) can be stockpiled in that area for use in lining Cell 1A.

All materials extracted from Cell 1A and 1B will be transported to the clay/shale stockpile areas via the northern ramp.

Cell 1C (Upper Level)

The upper level of Cell 1C (i.e. to approximately 40m AHD) will be extracted principally to provide the remainder of red clay required for the lining of Cells 1A, 1B and 1C. Figure 11C displays the internal layout for extraction within Cell 1C whereby an internal ramp will be constructed to provide access from the upper level of Cell 1C to the floor of Cell 1 to enable the clay to be stockpiled within Cells 1B and 1C. The proposed internal ramp will follow the general alignment of a former internal road within the former extraction area. Extraction will cease within the upper cell once all clay required is transported to the floor of Cell 1.

Cell 1C (Lower Level)

Following the delivery of all the required red clay to the floor of Cell 1, the remainder of the clay/shale within Cell 1C will be extracted and transported to the defined stockpile areas to the east of Cell 1. Figure 11D displays the proposed southern ramp that will be constructed progressively from Cell 1C to the internal road for earthmoving equipment between the northern and central stockpile areas. Extraction will continue in Cell 1C until all clay/shale is extracted to defined floor, as displayed in Figure 11D.

Page 39: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

31

Figure 11 Cell 1 Extraction Sequence

Dated 04/04/19. Inserted 04/04/19

Page 40: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

This page has intentionally been left blank

This page has intentionally been left blank

Page 41: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

33

7. E X T R AC T I O N O PE R AT I O NS

7.1 QUALITY CONTROL

An important activity in the extraction operations will be the daily quality control procedure to establish the fired colour of the material(s) to be extracted during the following day(s). This will underpin a protocol to ensure stockpiles of clay/shale materials for use by the brick industry are kept separate from material to be used for cell construction, daily waste covering and capping. Quality control within the extraction area will involve the following procedure.

The protocol is designed to maximise the volume of extracted materials quarantined for use by the brickmaking industry. Prior to the cessation of activities at the end of each day during each extraction campaign, the bulldozer will rip a series of lines across the active extraction floor which will bring to the surface a range of materials from approximately 0.6m to 1m below the extraction floor.

Representative samples of the ripped material will be sampled, numbered using a manganese dioxide solution and placed in a test kiln overnight at approximately 1020°C. The location of each numbered sample will be spray painted onto the extraction floor.

The fired samples will be examined the following morning and assessed for their fired colour and a record made for discussions/directions to the on-site extraction supervisor and equipment operations. The fired colour assessment will be based on an agreed colour board assembled from previously fired samples. Stockpiles of brick making materials will be delineated based on these predetermined colour characteristics. Extracted materials will be directed to the appropriate stockpile following this daily assessment.

7.2 EXTRACTION METHODS AND EQUIPMENT

Extraction of clay/shale materials within the three sub-cells will be undertaken typically on a campaign basis to ensure sufficient volume is available for the projected landfilling requirements. Extraction will typically involve the following.

i) Any recoverable topsoil and/or subsoil will be recovered using a scraper and either stockpiled for use in future rehabilitation or directly transferred to an area being rehabilitated.

ii) Where red clay is present, it will be recovered using a scraper and placed on the floor of the cell adjacent to Cell 1A.

iii) Any white/pink clay recovered and not required for cell lining will be transported to the active stockpile area for the later despatch for brick manufacture.

iv) The weathered shale, fresh or unweathered, laminite and sandstone units will be ripped (and possibly cross-ripped) with a bulldozer after which it will either be: – recovered by a scraper and placed in the active stockpile area; or – pushed into a stockpile on the extraction floor and loaded by excavator into an

on-site haul truck (for transfer to the active stockpile area) or a road registered truck for despatch off site.

It is noted that the proposed extraction area layout reflects the use of scrapers which invariably require a greater area for access and manoeuvring.

Page 42: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

34

7.3 SEPARATION FROM LANDFILL OPERATIONS – Schedule 5 Condition 5(4)(e)

Figure 12 displays the extraction sequence in Cell 1 and the proposed locations of the internal intercell bund to be constructed to separate the area of waste placement (and leachate generation) and area of clay/shale extraction/stockpiling. Apart from separating leachate from sediment laden runoff, the intercell bund will provide a physical barrier between the ongoing extraction and waste placement operations. The intercell bunds are generally consistent with those displayed in Schedule 10 of Project Approval MP09_0074.

The intercell bunds shown on Figure 12 are displayed at their minimum width of 10m as the opportunity may arise to effectively increase the width and height of the barrier to effectively store red clay for its subsequent use in the construction of the cell liners within Cells 1B and 1C.

7.4 EXTRACTION SEQUENCE

Extraction will commence in Cell 1A and 1B and progress in accordance with the staged emplacement cells, namely 1A 1B 1C 2A 2B 3A 3B 3C.

7.5 EXTRACTION RATES

Extraction rates will be tailored in any one year to ensure:

i) sufficient void volume is available for landfilling purposes;

ii) the full quantity of brick manufacturing raw materials (160 000tpa) are extracted for despatch from site; and

iii) the required quantity of cover and capping materials are available.

Extraction rates within Cell 1 will reflect the requirement for:

• the on-site requirement for clay to line Cell 1;

• the expectation for the supply of 160 000 of materials annually for brick manufacture.

Page 43: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

35

Figure 12 Cell 1 Extraction / Waste Separation

Dated 04/04/19. Inserted 04/04/19

Page 44: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

This page has intentionally been left blank

This page has intentionally been left blank

Page 45: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

37

8. S TO C KPI L E M AN AG E M E N T

8.1 STRATEGY

The quantity of clay/shale that needs to be stockpiled throughout the life of the Patons Lane RRC will be dictated by the following factors.

i) The need to ensure sufficient clay/shale is extracted to provide the void space required for the progressive waste placement and backfilling operation.

ii) The quantity of materials used on site or transported off site for brick manufacture.

Based upon the planning for this document, it will be necessary at all times throughout the life of the facility to maintain a range of stockpiles on site. Emphasis will be placed upon separating the stockpiles of materials to be used on site from those to be transported off site.

This section presents the protocol to be adopted that will enable SRC to manage the location, construction and progressive removal of the materials stockpiled for on-site use or for despatch off site.

8.2 STOCKPILE LAYOUT

Figure 8 displays the three principal clay/shale stockpile areas, namely:

i) the Northern Stockpile Area;

ii) the Central Stockpile Area; and

iii) the Southern (Contingency) Stockpile Area.

Northern Stockpile Area

The northern stockpile area is located wholly within the footprint of Cell 2 covering an area of approximately 5.4ha. The land within this area slopes from the southeast to the northwest at a grade of approximately 1.5%. The northwestern corner of the northern stockpile area has been designated as the location of the relocated Dam 4 to collect runoff from the northern stockpile area and the unsealed internal road to be used by waste trucks travelling to and from the active waste emplacement area.

Central Stockpile Area

The central stockpile area is located wholly within the eastern side of the footprint of Cell 3 covering an area of approximately 4.0ha. The area slopes from the south (at 50m AHD) to the northwest (at 47m AHD) also at a grade of approximately 1.5%. Runoff from the central stockpile area will be directed to Dam 5 to the northwest of the area.

Page 46: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

38

Southern (Contingency) Stockpile Area The southern (contingency) stockpile area is located within the southeastern corner of the Site and covers an area of approximately 2.6ha. The area slopes from the north to the south at a grade of approximately 2%. Runoff from the southern (contingency) stockpile area will be directed to the south towards Dam 6. The eastern side of this area is currently occupied by the southern section of the existing eastern bund wall. The materials within this bund wall will be progressively removed throughout the early years of the operation to make the full footprint of the stockpile area available for stockpiling clay/shale and sandstone extracted from Cells 1, 2 and 3. The eastern side of the existing eastern bund wall will be retained as displayed on Figure 7.

Schedule 4 Condition 24 restricts the upper surface of all stockpiles of materials extract on site to 54m AHD.

These limitations will result in the stockpile heights within each stockpile area being limited as follows.

– Northern Stockpile Area - 7m to 11m – Central Stockpile Area - 4m to 7m – Southern (Contingency) Stockpile Area - 6m to 10m

The designation of individual stockpile areas within the three stockpile areas will need to be dynamic to reflect the quality control results discussed in Section 7.1. As such, the area(s) for the stockpile(s) of each material type will need to be reviewed and adjusted throughout the life of Patons Lane RRC.

Tables 7, 8 and 9 list the indicative quantity of materials to be extracted from each of the four areas nominated in Figure 11. Distinction is made between the materials to be:

a) used either directly without long term stockpiling; b) stockpiled for use through the life of Cell 1; and c) stockpiled for use by the brick industry.

For planning purposes, the materials extracted during the construction of the northern ramp and Cell 1A and 1B are considered together.

Table 7 Use and Stockpiling of Materials Extracted from the Northern Ramp and Cells 1A and 1B

Material Quantity Extracted Quantity Used without long-term Stockpiling

Quantity Stockpiled for use within Cell 1

Quantity Stockpiled for Brick Industry

kbcm klcm kt kbcm klcm kbcm klcm klcm kt Red Clay 14.5 18.1 26.1 14.5 18.1 - - - - White/Pink Clay 4.3 5.4 7.7 4.3 5.4 - - Brown Shale 0.7 0.9 1.4 - - - - 0.9 1.4 Cream Shale 10.1 12.5 22.2 - - - - 12.5 22.2 Apricot Shale 12.7 15.9 27.9 - - - - 15.9 27.9 GP Shale 22.5 28.1 50.0 - - - - - - Sandstone 11.4 14.3 27.4 - - - - 14.3 27.4 Fill - - - - - - - - - kbcm = x 1000 bank cubic metres klcm = x 1000 loose cubic metres kt = x 1000 tonnes

Page 47: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

39

Figure 13 displays the indicative layout of the stockpile areas for the materials extracted from within the northern ramp and Cells 1A and 1B. Not all stockpile areas would be used during this period of extraction. The type of material stockpiled with the stockpile areas is nominated on Figure 13. It is assumed that the quantity of clay required for lining Cell 1A will be recovered from the northern ramp and Cells 1A and 1B from the excavation of Dam 4.

Figure 13 displays an indicative arrangement of the stockpiles within the Site. Three stockpiles sizes are displayed, namely:

• 100m long x 50m wide (approximately 22 000lcm / 40 000t capacity);

• 80m long x 50m wide (approximately 18 000lcm / 30 000t capacity); or

• 100m long x 75m wide (approximately 32 000lcm / 52 000t capacity.

Each of the stockpile areas are numbered N – Northern / C – Central / S – Southern. Whilst the stockpile areas displayed on Figure 13 show the footprint of the stockpiles the area may not be constructed to the full height or cover the full area of the stockpile area. The full height of some of the stockpiles would be achieved during the extraction in Cell 1C (upper level).

Figures 14 and 15 display indicative layouts for the stockpiles containing the materials extracted from within Cell 1C (upper level) and Cell 1C (lower level). The types of material stockpiled within each stockpile area are nominated on both figures.

Table 8 Use and Stockpiling of Materials Extracted from Northern Ramp and Cells 1C (Upper Level)

Material Quantity Extracted Quantity Used without long-term Stockpiling

Quantity Stockpiled for use within Cell 1

Quantity Stockpiled for Brick Manufacture

kbcm klcm kt kbcm klcm kbcm klcm klcm kt Red Clay 28.8 36.0 51.8 28.8 36.0 - - - -

White/Pink Clay 20.3 25.4 36.5 20.3 25.4 - - - -

Brown Shale 30.1 37.6 60.2 - - - - 37.6 60.2 Cream Shale - - - - - - - - -

Apricot Shale - - - - - - - - -

GP Shale - - - - - - - - -

Sandstone - - - - - - - - -

Fill 45.0 56.3 90.0 - - 45.0 56.3 - - kbcm = x 1000 bank cubic metres klcm = x 1000 loose cubic metres kt = x 1000 tonnes

Table 10 presents the quantity of clay/shale to be used on site which is drawn from Tables 7, 8 and 9, i.e. for use in the construction of the clay liner, as daily/intermediate cover and capping the completed landform. The quantities of clay are provided in bank cubic metres (bcm) given the clay will be compacted to 100%.

Page 48: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

40

Figure 13 Indicative Stockpile Layout - North Ramp and Cells 1A and 1B

Dated 04/04/19. Inserted 04/04/19

Page 49: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

41

Figure 14 Indicative Stockpile Layout - Cells 1C (Upper Level)

Dated 04/04/19. Inserted by 04/04/19

Page 50: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

42

Figure 15 Indicative Stockpile Layout - Cell 1C (Lower Level)

Dated 2/3/16. Inserted 05/09/16

Page 51: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

43

Table 9 Use and Stockpiling of Materials Extracted from Northern Ramp and Cells 1C (Lower Level)

Material Quantity Extracted Quantity Used without long-term Stockpiling

Quantity Stockpiled for use within Cell 1

Quantity Stockpiled for Brick Manufacture

kbcm klcm kt kbcm klcm kbcm klcm klcm kt Red Clay 8.8 11.0 15.8 - - 8.8 11.0 - -

White/Pink Clay 14.5 18.1 26.1 - - 14.5 18.1 - -

Brown Shale 0.6 0.8 1.2 - - - - 0.8 1.2 Cream Shale 24.9 31.1 54.8 - - - - 31.1 54.8 Apricot Shale 43.1 53.9 94.8 - - - - 53.9 94.8 GP Shale 69.3 86.6 152.5 - - - - 86.6 152.5 Sandstone 9.9 12.4 23.8 - - - - 12.4 23.8 Fill - - - - - - - - - kbcm = x 1000 bank cubic metres klcm = x 1000 loose cubic metres kt = x 1000 tonnes

Table 10

Clay/Shale Requirements (bcm) during Cell 1 Extraction Operations1

Material Cell Lining Daily/Intermediate Cover Final Capping Total Cell 1A Cell 1B Cell 1C Cell 1A Cell 1B Cell 1C Cell 1A2 Cell 1B Cell 1C

Red Clay 26.9 18.3 20.0 - - - 33.8 - - 99.0 GP Shale - - - 27.2 14.4 20.8 7.5 - - 69.9 Notes: 1 Source: Accumulated from Tables 1, 2 and 3. 2 The nominated amount relates to the final landform completed above Cells 1A and 1C.

From an operational perspective, it is proposed to construct the stockpiles within the northern and central stockpile areas typically with a height of approximately 4m to 6m and each with a capacity of approximately 18 000lcm and 22 000lcm) other than stockpile area C1. Stockpiles of this capacity typically vary from 80m long x 50m wide to 100m long x 50m wide1. Stockpiles of this size can be constructed over a reasonable period of time and provide sufficient height and volume required to achieve the preferred level of blending for the brick manufacturing raw materials.

8.3 STOCKPILE CONSTRUCTION – Schedule 5 Condition (4)(d)(i/iv) and (k)

Stockpiles will be constructed to minimise visual and acoustic impacts. Measures taken to achieve this outcome include:

• Shielding of stockpiling operations behind the northern bund to be constructed during site establishment. This will form a visual and acoustic barrier between operations and the residential precinct to the north of the site.

• Height markers will be constructed to indicate the maximum stockpile height of 54m AHD.

1 Numerous variables exist for stockpile lengths and widths.

Page 52: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

44

• Use of late model plant with appropriate noise suppression. Specific plant items that have a lower sound rating will be utilised if works are required on stockpiles above 54m AHD. Additionally, works in such areas shall be avoided during morning periods where possible to further mitigate potential impacts on neighbours.

• Location of stockpiles close to the northern bund to maximise noise attenuation. The stockpiles/windrows will preferentially orientated east-west to provide additional noise attenuation to the residents north of the site.

• Stockpiling operations will be minimised in unfavourable weather conditions particularly southerlies.

The construction of stockpiles of brick manufacturing materials will enable blending of the similar types of materials to occur given the various materials are extracted at the various times and from different locations from within the extraction area. The recovery of materials from a stockpile will assist in maintaining a more consistent quality of the raw materials.

Stockpiles of materials will be constructed using scrapers for the first 5m to 6m. Haul trucks and dozers will be used for stockpile construction above the levels completed by the scraper (5m to 6m) up to an additional 2m to 3m with the maximum elevation of all stockpiles being no greater than 54m AHD.

In most cases, the stockpiles will be at least 50m wide to enable the scrapers to turn around within the stockpile footprint rather than traverse the full length of the stockpile. The scrapers will place materials in layers approximately 0.5m thick which will enable the full area of the stockpile to be built up evenly. Care will be taken when the stockpile rises above 2m in height to ensure the edges of the stockpiles are elevated to prevent any rollovers. The stockpiles would have longitudinal slopes of between 7° or 1:8 (V:H) and 14° or 1:4 (V:H) and side slopes typically at the angle of response, i.e. approximately 37° or 1:1.33 (V:H) or slightly greater. It may be necessary at times to remove the approach ramp(s) constructed by scrapers for each stockpile to improve access between stockpiles.

Each stockpile will have height markers to show the 6m level to delineate the limit of the extent of scraper stockpiling permitted. Additionally, markers will be installed to identify the maximum stockpile elevation of 54m AHD.

It is noted that the project approval states at Schedule 5 condition 4 (k) that :

“The batter slopes of all stockpiles must be no more than 1:3 vertical:horizontal, unless otherwise approved by the EPA”

The EPA in correspondence of 11 April 2016 approved the proposed revised batter slopes of stockpiles to 1:1 (V:H) and these slopes have been factored into the stockpile design.

Page 53: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

45

8.4 STOCKPILE MANAGEMENT – Schedule 5 Condition (4)(g)

Management of the stockpiles of brick manufacturing raw materials and material required for on-site activities will involve the following.

1. Marking the nominated footprint for the respective stockpiles. The corners of each stockpile area would be marked with a painted 205 litre drum and post together with a sign designating the stockpile number and material type.

2. Materials to be transported off site for brick manufacture will be stockpiled in locations close to the internal road network, whilst those required for on-site uses will be located close to the northern and southern ramps to enable them to be transported to the active operational area, when required.

3. Where practical, it is proposed that for most materials, at least two stockpile areas will be used so that one area can be constructed whilst the other stockpile is being removed.

As discussed in Section 8.3, the boundaries of each stockpile area will be reviewed on a regular basis (e.g. quarterly) to ensure that the areas(s) set aside for each type of materials is consistent with the quantities and material types being extracted. This review would also reflect the extent to which certain types of brick manufacturing materials are being removed from site.

8.5 STOCKPILE SURVEYS – Schedule 5 Condition (4) (i/ii) and (j)

Each stockpile will be surveyed on a quarterly basis to record the quantity and type of materials within each stockpile. The survey will establish the volume of materials expressed in loose cubic metres (lcm). The results of the quarterly survey would be tabulated and a summary presented in each Annual Environmental Management Review.

The results of each quarterly survey will be reconciled against the indicative quantities of materials presented in Table 6. It is noted that the proposed methodology for quality control (see Section 7.1) will dictate the actual quantities of each type of materials stockpiled. Hence, there is likely to be some variance between the actual quantities of materials stockpiled and that listed in Table 6.

Page 54: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

46

9. P E RS O N NE L M AN AG EM E N T

9.1 INTRODUCTION

The Project Approval states that the QOMP must "include provision for regular staff or contractor training which is required to be undertaken to reinforce the importance of keeping the types of clay/shale separate". This section of the QOMP deals with this specific requirement as well as other general personnel matters.

9.2 ROLES AND RESPONSIBILITIES

SRC Operations will enter into a commercial contract to supply materials to brick manufacturing companies such as CSR/PGH Bricks and Austral Bricks.

Such arrangements include the appointment of a specialised extraction contractor who will be responsible for the selective mining of each of the specified material types. It is likely that the extraction operations will be deemed to be mining operations for the purposes of the Mining Act 1992. Accordingly, the extraction contractor will also provide a Mine Manager who will be responsible for dealing with all legislative and operational matters relating to extraction operations.

Patons Lane RRC General Manager Operations and Compliance will liaise directly with the appointed Mine Manager in respect of day to day operations and compliance with all relevant aspects of the project Approval.

The contractual agreements appointing the Mine Manager and extractive industry contractor will specifically outline the responsibility of the Mine Manager to comply with the specific requirements of the project approval in relation to:

• stockpile management; and

• maximising the yields of brick manufacturing materials.

9.3 TRAINING – Schedule 5 Condition (4), (h), (i,ii)

Patons Land RRC will be operated in accordance with the Landfill Environmental Management Plan (LEMP) and the Project Environmental Management System (EMS) which has been developed in accordance with relevant Australian Standards.

All staff and contractors will be trained via a site induction process upon engagement and prior to commencement of any work in accordance with the training procedures outlined within the EMS. This training will include details on the importance of keeping clay/shale types separate in accordance with the CoC. The EMS will be updated periodically, as required, based on outcomes of the Annual Environmental Management Review and Independent Environmental Audits.

Page 55: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

47

10. D O C UM EN TAT I ON

10.1 EXTRACTION RECORDS

SRC will require the earthmoving contractor to maintain a daily record of the type of materials extracted, the number of loads (in a scraper and/or haul truck) and its destination. This will enable the quantity of materials extracted and stockpiled to be compiled on a daily basis.

10.2 QUARTERLY SURVEY RECORDS

SRC will commission a survey of the Site at the end of March, June, September and December each year to record:

i) the volume of the extraction void beneath a defined level;

ii) the volume of the landfill component;

iii) the volume of all stockpiles of clay and GP Shale retained within the floor of Cell 1; and

iv) the volume of all stockpiles of materials within the northern, central and southern (contingency) stockpiling areas.

This information will be reviewed and compared with the results of the previous quarterly survey and the weighbridge records for the clay/shale materials despatched from Patons Lane RRC.

10.3 OFF-SITE CLAY/SHALE TRANSPORTATION – Schedule 5, Conditions (4), (i/ii) and (i/viii)

The number of trucks departing Patons Lane RRC on a daily basis and the weight of the clay/shale materials transported from the Site for brick manufacturing, or other purposes, will be recorded using the on-site weighbridges. This data will be complied in monthly survey sheets and forwarded to the Department of Planning & Environment (Resources and Geoscience) and the Environment Protection Authority, if and when required.

It is noted that the Division of Resources and Energy will separately require an annual return for the materials extracted on site, i.e. for both the materials to be used on site and transported off site.

10.4 PUBLICATION

A summary of all of the above records will be provided in each Annual Review prepared for Patons Lane RRC in accordance with Schedule 5 Condition 5.

Page 56: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

48

11. R E F E RE N C ES

RW Corkery & Co, 2004. Resource Report, prepared on behalf of Dellara Pty Ltd.

.

Page 57: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

49

Appendices

(Total No. of pages including blank pages = 14)

Appendix 1 Correspondence from Government Agencies

Appendix 2 Curriculum Vitae - RW Corkery of RW Corkery & Co - M. Hoare of RPM Global

Page 58: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

50

This page has intentionally been left blank

Page 59: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

51

Appendix 1

Correspondence from Government Agencies

- Department of Planning & Environment

- Environment Protection Authority

- Penrith City Council

(Total No. of pages including blank pages = 6)

Page 60: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

52

This page has intentionally been left blank

Page 61: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

53

Page 62: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

54

Page 63: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

55

Page 64: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

56

Consultation Required by the Project Approval

The project approval requires that the QOMP must “b) be prepared in consultation with the EPA and Council”

Accordingly, detailed consultation was undertaken with these agencies as well as the DP&E during the preparation of this document as required by the project approval with all relevant correspondence contained in Appendix 1 as Attachments as per the numbering below. Patons Lane has provided a summary of the consultation undertaken which is set out below. Department of Planning and Environment

1. 27 November 2015 – Correspondence to DP&E from RW Corkery (Attachment 1) seeking approval to prepare a Quarry Operation Management Plan (QOMP) and Engineering Plans in stages with the first stage focusing on the extraction and stockpiling activities for Cell 1 in accordance with the Project Approval Schedule 3, Condition 32 which specifically provided for the submission of any plans as follows :

“STAGED SUBMISSION OF PLANS OR PROGRAMS

32. The Proponent may submit any plan or program required by this approval on a progressive basis with the approval of the Director-General.”

2. 8 February 2016 – Correspondence (Attachment 2) to DP&E again requesting approval to prepare a Quarry Operation Management Plan (QOMP) and Engineering Plans in stages commencing with Cell 1.

3. Further submission to DP&E on 6 May 2016 which requested approval for the progressive lodgement of the Engineering plans, the QOMP and all related plans on the staged basis set out in the document “2016‐3‐7 Letter and Draft QOMP for PCC” reviewed and referenced by Penrith City Council in their written advice confirming that they have no objections to this approach.

4. On 16th May 2016, DP&E provided approval to submit the QOMP and the Detailed Engineering Plans on a progressive basis pursuant to Schedule 3, Condition 32 of the Project Approval. This approval is attached (Attachment 3).

Page 65: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

57

Penrith City Council (PCC) 5. 27 November 2015 – Correspondence sent to PCC by RW Corkery and Co. (Attachment

4) asking if PCC wanted to review a copy of the draft QOMP.

6. 8 February 2016 – Meeting at Penrith City Council offices. PCC attendees Peter Wood (Manager Assessments), Rob Craig (Principal Planner), Carlie Fulton (Senior Environmental Health Officer) Anthony Price (Environmental Health Co-ordinator), Patons Lane Attendees David White (Compliance and Operations) Lee Smith (Business Development) Rob Corkery (Quarry Consultant RW Corkery and Co.) Rob Corkery provided an overview of the concepts included in the Draft QOMP.

7. 11 February 2016 – Robert Craig Principal Planner emailed a request for copy of Draft QOMP to review (Attachment 5).

8. 7 March 2016 – Draft QOMP emailed to PCC with covering letter discussing outcomes of the meeting on 25 February 2016. Covering letter attached which includes a specific request for PCC to comment on the staged approach proposed in the QOMP. Covering letter provided as Attachment 6.

9. 17 March 2016 – Email from Carlie Fulton PCC confirming site inspection.

10. 15 March 2016 – David White meets briefly with Peter Wood Manager Assessments PCC and provides 4 extra hard copies of the Draft QOMP and the covering letter to PCC.

11. 22 March 2016 – Site inspection carried out with Ms Carlie Fulton, Senior Environmental Health Officer, Mr Jeremy Stacy, Senior Biodiversity Officer, Mr Mitch Nobbs, Trainee Environmental Health Officer. Patons Lane Representative – David White

12. 11 April 2016 – Response from Rob Craig – Principal Planner PCC stating that QOMP “appeared to comply with all consent conditions” (Attachment 7)

13. 12 April 2016 – Email from David White to Rob Craig requesting that PCC provide a specific response to the staging and scope of works set out in the QOMP.

14. 22 April 2016 – Email from Rob Craig Principal Planner PCC confirming that PCC was comfortable that the proposed staging and scope of works set out in the QOMP was consistent with the project approval (Attachment 8).

Page 66: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

58

Environmental Protection Authority (EPA)

15. 27 November 2015 – Rob Corkery writes to EPA re direction on slopes of stockpiles (Attachment 9).

16. 7 March 2016 - First consultation with EPA –. 2 hour meeting at EPA offices Goulburn St. EPA attendees Chris McElwain (Senior Manager Waste Compliance), Ruth Owler (Unit Head Waste Compliance), Katherine Falconer (Senior Compliance Officer), Damien Rose (Senior Compliance Officer). Patons Lane Attendees Jason Walter, (Director), Lee Smith (Business Development & Communications), David White(Operations & Compliance), Craig Bagnall (Niche Consulting) Mark Wainwright (Niche Consulting), Ryan Jacka (Sydney Environmental Soil Laboratories – SESL)

17. 15 March 2016 – Email sent inviting EPA to a site meeting to specifically discuss QOMP. 16 March 2016 – Ruth Owler (Unit Head Waste Compliance) sent email confirming site meeting.

18. 21 March 2016 – meeting on site attended by EPA officers Ruth Owler and Michaela Burgess. Patons Lane representatives David White and Lee Smith. David White provided 4 hardcopies of the Draft QOMP and a covering letter.

19. 21 March 2016 – Follow up email sent to Ruth Owler containing electronic copies of the Draft QOMP and covering letter. Email also requested feedback on the EPA re QOMP (Attachment 10).

20. April 11 2016 – EPA sends email and letter confirming batter slopes included in stockpile management proposed in the QOMP are approved by the EPA (Attached). Specifically, EPA has approved a variation to the batter slopes of stockpiles of materials extracted and stockpiled on site as required pursuant to Schedule 5, Condition 4k of the project approval (Attachment 11).

21. 25 April 2016 – Email sent to EPA requesting feedback on QOMP. Email included including PCC response for EPA reference (Attachment 12).

22. 17 May 2016 – Kathy Falconer contacted David White to advise that EPA had no immediate issues to raise in relation to the QOMP.

23. 27 May 2017 – EPA provide approval of QOMP (Attachment 13).

Page 67: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

59

Attachment 1

Page 68: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

60

Attachment 2

Page 69: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

61

Attachment 3

Page 70: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

62

Attachment 4

Page 71: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

63

Attachment 5

Page 72: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

64

Page 73: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

65

Attachment 6

Page 74: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

66

Page 75: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

67

Page 76: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

68

Page 77: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

69

Page 78: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

70

Page 79: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

71

Attachment 7

Page 80: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

72

Page 81: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

73

Attachment 8

Page 82: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

74

Page 83: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

75

Attachment 9

Page 84: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

76

Attachment 10

Page 85: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

77

Page 86: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

78

Attachment 11

Page 87: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

79

Page 88: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

80

Attachment 12

Page 89: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

81

Page 90: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

82

Page 91: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

83

Page 92: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

84

Attachment 13

Page 93: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

85

Appendix 2

Curricula Vitae

- RW Corkery

- M. Hoare

(Total No. of pages including blank pages = 6)

Page 94: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

86

This page has intentionally been left blank

Page 95: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

87

Page 96: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

88

Page 97: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

QUARRY OPERATION MANAGEMENT PLAN SRC OPERATIONS PTY LTD Report No. 582/20 Patons Lane Resource Recovery Centre

89

Page 98: Patons Lane Resource Recovery Centre Quarry Operation ... · Version 6 RWC – 16 Dec 2016 SRC – D. White Bingo – 29 March 2019 Version 7 RWC – 4 April 2019 Bingo – D. Taylor

SRC OPERATIONS PTY LTD QUARRY OPERATION MANAGEMENT PLAN Patons Lane Resource Recovery Centre Report No. 582/20

90

This page has intentionally been left blank


Recommended