Date post: | 02-Aug-2015 |
Category: |
Business |
Upload: | informa-australia |
View: | 199 times |
Download: | 6 times |
Presentation by Captain Paul Toussaint-Jackson12th Annual Bulk Materials & Handling Conference 2015
Perth1
FLOATING DECK SOLUTIONS DEVELOPMENTS IN DAMPIER AND BEYOND
AFD provides innovative maritime logistics solutions based on flexible, lightweight
and rapidly constructed infrastructure that is safe, robust and can be used for the
long-term. Our solutions are highly competitive in terms of both construction time
and cost compared to traditional infrastructure. Each solution is carefully tailored
for the client to complement core client business objectives. Our solutions are
systems that can be readily extended into landside logistics.
AFD can assist with the development of complete deal structures for the
establishment of the installations including regulatory approval, contract design,
contractor management, operations design, site management and financing. AFD
is uniquely placed to design deal structures that provide excellent return for
private proponents yet complement public policy objectives.
AFD concept designs have attracted major investment from some of Australia’s
largest companies.
Australian Floating Decks
• Easily and rapidly scalar to suit developing trade;
• Uses shallow bathymetry (for the FDTS) as an asset rather than an obstacle: no
dredging is required. These facilities have minimal environmental impact;
• Rapidly constructed in a far shorter timeframe than conventional infrastructure;
• Far lower capital cost than conventional infrastructure of equivalent capability;
• Highly robust, safe and flexible and be highly suitable for use in cyclone prone areas;
• Readily handled by existing port services and operations;
• Completely privately funded but provide good revenue returns to the State, legacy
assets for the State and retain key controls for the State over the land or seabed
through lease/license instruments;
• Open access for general custom and have Customs and quarantine approved
facilities.
• All types of project cargo handled including multi-thousand tonne pre-assembled
modules. General, bulk, livestock and vehicular.
AFD Floating Deck System Design Elements
• It has been estimated that between $700 - $800 billion is required to close Australia’s
infrastructure gap over the next decade – this is a sum equal to about half of the nation’s
current annual GDP;
• Many governments are unwilling to increase debt levels including debt funding of
infrastructure;
• Conventional infrastructure projects can be very expensive and may have significant
lead times due to required approvals. It may also result in significant long-term
maintenance cost and environmental impact;
• Insufficient infrastructure has a core impact on a nation’s productivity and its production.
AFD believes its models are a case of ‘working smarter and not harder’.
• AFD believes that floating deck infrastructure can provide in many cases the same
functionality as conventional maritime infrastructure but with a wide range of
advantages. In developed economies such as Australia this can mean significantly lower
costs. In nations with lower unit costs the cost differential may be less but there are still
many advantages with the alternative infrastructure model.
Challenging the infrastructure gap
Floating Deck Systems – applications
Coastal topography, meteorological and environmental conditions need to be carefully
assessed for each new development;
The real solution for each site is not as infrastructure alone but as a logistics system if
the full value of the installation is to be realised.
The many attributes of these systems including lower capital cost make them attractive
to the private sector.
The systems are designed to be complementary to traditional infrastructure and can be
applied to developed ports or greenfield sites.
Low environmental impact makes the systems ideal for environmentally sensitive sites.
Floating Decks – stability, flexibility, strength
The floating decks are very stable allowing structure of very large weight and weight to
be located on an otherwise very shallow draught platform. This can include loaders and
conveyors in various forms, stockpiles, workshops and berth space;
The floating decks can be easily modularised to create greater working area;
Floating decks allow shallow bathymetry to be used as an opportunity rather than as a
problem – they can be used to bridge to deeper water either as a static or moving
installation;
The simplicity of floating deck installations makes them easy to work within the normal
colour and movement of a port;
Floating decks can be easily fit to simple shore-side construction to provide the option of
legacy (shore land) assets that may be important in achieving permission from the State.
The Floating decks can be readily transferred to other sites or sold.
7
Floating decks can work with high point loads, shear forces and
bending moments
Giant floating deck under construction
Plow section
to be fitted
forward to
deflect
debris
Model RTP - Estuarine Projects
Crawler crane in stowed position
2000 tonne bulk fuel inventory in mid-ship tanks
3 high rota box stacks – to 10000 tonne concentrate inventory
FD self-installs piles
Hydraulic brackets
RTP FD rides up and down piles with changing water
levels
Size of FD to suit site
Optimum dimensions
Length: 100m
Beam: 30m
Working deck: 3000 m2
Cargo dwt: 12-13 kt
40 tonne bollardsFender points
Optional
Portable w/shop
Cone sockets on deck
River level
River current flow
Land side area – RTP would be located far enough out to ensure flotation at low water levels
Berthing side
Shore
access
Debris field
deflector
Floating deck under construction for Australian service
11
Floating decks are readily handled by standard port services
Floating deck undergoing installation at Dampier
DFD undergoing installation at Dampier, December 2014
Floating decks self-install and bring all elements for installation to the site
FDTS Floating Deck Cargo Area Capacity
Sample cargo area capacity (theoretical tight stow only) based on 110m x 38m floating
deck (4180 m2 of useable area).
CAT 797 Mining Haul Trucks Largest
mechanical haul trucks in the world
(400 tonne payload)
CAT D9 Tractors
48.8 tonnes
TEU Sea Containers triple stacked or
560 double stackedHammersley Iron Ore Rail Wagons
OR
OR
28 114
144 700+
DFD3500 m2
25 tonnes/m2
2 x 100m berths
Drilling mud
Fuel
Fresh water
All hydraulic
Lateral movement <100mm
Demobilisation < 1 hour
FDTS: the ‘shock absorber’Trans-shipment in sheltered port anchorage
RORO or LOLO exchange
Deep water allows port access by large cargo liners
At Dampier floating deck will take 1.5 hours to shore
FDTS3500 m2 floating decks
15000 tonne cargo dwt
Land-backed terminal
AQIS wash-down
Customs licensed
• The DFD (Dampier Floating Deck) and FDTS (Floating Deck Trans-shipment System)
are two projects that I have designed and developed at the Port of Dampier to improve
critical supply chain constraints affecting both the Port and the Pilbara region in general.
• These projects are intended have the maximum trade facilitation impact at a fraction of
the cost of conventional infrastructure and with much shorter development times.
• The DFD I conceived as a forward floating supply base function to directly assist the
logistics of supplying offshore oil and gas platforms out of Dampier.
• The FDTS I designed as a land-backed facility with a moving floating deck that will allow
genuine international liner cargo shipping services to call at Dampier for the first time.
• Both the FDTS and DFD are designed as logistics systems rather than simple
infrastructure solutions and are highly adaptable including inwards supply for mine and
port construction and as platforms for conveyors and export facilities.
• These projects are game changers for logistics into the Northwest and are expected to
do much to fundamentally address some of the core logistics productivity issues we
have in that very important region for the Australian economy.
Case Study: New Floating Deck Projects for Dampier
Current logistics constraints• The Port of Dampier is one of the world’s largest bulk export ports and has excellent
private facilities for the export of LNG, condensate, iron ore and salt. These facilities are
profit-driven and fit for purpose.
• The principal import facility however, the Dampier Cargo Wharf (DCW), requires
expanded capacity to cope with the growth in trade. Congestion causes delays and
demurrage costs for project vessels, additional costs to projects and reinforces the use
of inefficient long-distance road-haul services to our region for large oversize and out of
gauge project cargo.
• In 2011 I undertook a study to find a solution to not only the constraints of the DCW
facility but also the wider logistics productivity issue for the Pilbara.
• From this study I identified two critical supply chains that conflict at Dampier:
- Critical Supply Chain 1 – The high cycle marine services supply to offshore oil and
gas installations; and,
- Critical Supply Chain 2 – The inwards industrial supply chain including mine supply.
• Both of these supply chains rely heavily on access to the DCW.
• Finally I recognised the advantages of enabling direct call international liner services.
20
Dreams into reality
21
First cargo handled 6 months after major
construction commenced
Floating deck self-
installing at the
Dampier
23
Floating decks de-mobilised to sheltered cyclone moorings
24
DFD and FDTS for Dampier 2015
Legend
Current rail haul
Current road haul
East Coast liner route
Optional road haul
New West Coast liner options
5
4
4
12
3
4
5
2
3
Currently China to Pilbara
supply chain takes 31 days
(red route)
5
6
4
FDTS supports China to
Pilbara supply chain of just
9 days 2
FDTS provides a general cargo
terminal function at Dampier
supporting the development of
new liner services.
Floating Deck Systems:
further innovation
27
• Model RTP is for ore concentrate handling and is a fully self-contained floating base with
an optional stockpile capability of 10000 tonnes or more. It contains bulk fuel supply,
maintenance workshops and amenities with berth space for up to 4 x 5000 tonne ore
barges. Rota-box or bulk ship loader fit-out is optional as is aviation facility and auxiliary
vessel berths and support;
• Model RTP is ‘Pack away’ – can be demobilised in under an hour;
• Model RTP can operate in bathymetry as shallow as 4 metres;
• Construction in 18 months from approvals;
• Minimal environmental impact – site restoration easily achieved
• A new modular design provides for extended facilities of 300 metres or more with a
deadweight capacity of 30,000 tonnes on the floating deck and berthing of bulk vessels in
excess of 100,000 tonnes
Model RTP
Model MFD
28
FDTS first stage development –
Dampier, WA
Thank you