+ All Categories
Home > Documents > Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland...

Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland...

Date post: 15-Dec-2015
Category:
Upload: lilly-cobleigh
View: 214 times
Download: 0 times
Share this document with a friend
Popular Tags:
34
Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD Presented by Bob Long American Concrete Pavement Association Mid-Atlantic Chapter
Transcript
Page 1: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Pavement Type Selection(Designs, Costs & Bidding)

9th Annual Concrete Conference for the Maryland Transportation Industry

March 24, 2009

Timonium, MD

Presented by Bob Long

American Concrete Pavement Association

Mid-Atlantic Chapter

Page 2: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Pavement Type Selection Evolution of the Process

Good old days More responsible More structured Let the market dictate

Page 3: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Pavement Type Selection Typical Basic Components

Equivalent designs Cost estimates Life Cycle Cost Analysis (LCCA) Innovative Contracting (e.g., alternate bids)

Page 4: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

What are equivalent sections?

•Traffic•Reliability •Subgrade•Terminal Condition

•Traffic•Reliability •Subgrade •Terminal Condition

=

• Provide reasonably similar level of service• Designed with the same procedure

• Same structural capacity

• Similar traffic-carrying capacity over the analysis period

Equivalent Designs

Page 5: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Different Pavement Types

Subbase

Subgrade Subbase

Subgrade

Base

Asphalt Layer

Concrete Section Asphalt Section

Page 6: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

How Pavements Carry Loads3000 kg.3000 kg.

pressure < 0.2 MPa

pressure 2.0 MPa

Concrete’s Rigidness spreads the load over a large areaand keeps pressures on the subgrade low.

Page 7: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Costs

Accurate estimates are essential Take into account volume, production, and

availability of materials Update regularly

Page 8: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Costs

Liquid AC index jumped from $340 to $842 per ton in just over 4 months (April—August 2009) – that’s a $25 per ton increase for in-place asphalt pavement

Availability of liquid AC was becoming a concern Over the last 2 years, the price of asphalt pavement

has jumped from about $55 to over $75 and as high as $130 per ton

Although cement prices did rise for a while before the big AC increases, prices are lower and stable

Page 9: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Materials Costs

Page 10: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Economic procedure

– That uses Engineering inputs

Compares competing alternates over their life

– by considering all significant costs (and benefits) Construction, Maintenance, Rehabilitation User Performance

Expressed in equivalent dollars

What is it ?

Life-Cycle Cost Analysis

Page 11: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

A Magical Black Box

– There is no concrete LCCA or asphalt LCCA

Complicated

– Does not need a computer program

What it is Not

Life-Cycle Cost Analysis

Pavement A

Pavement A - Rehabilitation Schedule

Pavement A - Present Worth Calculation

Discount Rate =

Yr Cost (1+i)^n PWInitial Const.. 0 1.000Rehab 1.Rehab 2.Rehab 3.Rehab 4.Rehab 5.Rehab 6.Rehab7.Rehab 8.Rehab 9.Rehab 10.Salvage

Total Cost Total NPV

Determine the stream of flow for expenditures. The cash flow diagram (below) shows the inflow and outflow of cash due to construction and rehabilitation. Arrows indicate a major cash expenditure (construction, rehabilitation, etc.). An up arrow indicates the outflow of cash. Down arrows show inflows. With pavements the inflow of cash only occurs at the end of the analysis period to show either continued-use or salvage value. The height of the arrow indicates the magnitude of the expenditure.

2 6 84 10 12 14 2016 18 22 24 3026 28 32 34 4036 38 42 44 5046 480

Using the the expenditure stream above, calculate the Present Worth (PW) for each rehabilitation activity (PW for the initial cost is the initial cost).

PW is calculated using the following formula:

PW = Rehab Cost / (1+i)n

Where i = discount rate n = year rehab takes place

Page 12: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Present Worth Analysis (PW) Equivalent Uniform Annual Cost

Analysis (EUAC)

How it is done:

Life-Cycle Cost Analysis

Page 13: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Present Worth Analysis: Discounts all future costs (benefits) to the present

Co

sts

Initial Cost

Rehabilitation CostMaintenance

Cost

Salvage Value

Years

Co

sts

Present Worth

Years

Life-Cycle Cost Analysis

Page 14: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Economic Factors– Discount rate

– Analysis Period

Engineering Factors– Comparable sections

– Rehabilitation selection

– Agency Costs

– User costs

Basic Factors:

Life-Cycle Cost Analysis

Page 15: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Normally equal for each alternative– Highway: 30-50 years– Street: 20-30 years

– Airport: 30 years

Include at least one rehabilitation– Needed to capture the true economic benefit of each alternate

Analysis Period:

Life-Cycle Cost Analysis

Page 16: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Delay-of-use – Time delays - New construction & Rehabilitation– Fuel consumption

– Driver discomfort

Roadway deterioration– Cargo damage– Vehicle wear

Accidents

User Costs:

Life-Cycle Cost Analysis

Page 17: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Some basic insights:

Initial Costs – Account for about 65-90% of Life Cycle Cost. – Selection of features plays an important role – Need to account for added features on the pavement

performance.

Timing of Activities. – After initial costs and discount rate, the next most important

factor. – The longer an activity is delayed, the greater it is discounted

and the less impact it has on present worth.

Life-Cycle Cost Analysis

Page 18: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Pavement Type SelectionOverview of Maryland Process

Policy on application of process

Three tiered approach– Life cycle cost comparison– Component analysis– Innovative contracting

Probabilistic approach to LCC

Weighting of component factors based on project priorities

Project team formed to make final decision

Page 19: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Application Policy All projects developed through the Project

Planning Division ready for design, and

Any projects with a construction estimate > $15 million (with at least $5 million dedicated to pavement/MOT items)

Estimated to be 6 to 8 projects per year. (Staff resource levels were a limiting factor in the number of projects that could be identified.)

Page 20: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Three Tiered Approach

1st Tier – LCC Analysis within 20%• Initial Cost• Future Rehab Costs over 40 Years• User Delay Costs

2nd Tier – Component Analysis • Cost Factors• Construction Factors• Design & Environment Factors• Form Team and Consider Industry Input

3rd Tier – Innovative Contracting • Alternate Bidding• Warranty Contract • Design/Build Contact

Page 21: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Life Cycle Cost Factors

Based on historical data and expert opinion– Material unit costs– Pavement service life– Construction sequencing– Construction duration– General analysis inputs

Variability represented by average and standard deviation

Page 22: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Example Input – Service Life

Page 23: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Component Analysis Cost Factors

– Present worth Agency Costs – Initial & Future– Present worth User Delay Costs

Construction Factors– Duration of Construction– Maintenance of Traffic– Maintenance of Access – (utilities & future maint, material sources, reliability of construction)

Design and Environment Factors– Traffic and Geometry– Adjacent Pavement and Structures– Environmental Impact – (community concerns, future planning)

Page 24: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Project Level PTST

Chief Engineer for MDSHA Operations. Chief Engineer for MDSHA Operations. District Engineer of MDSHA District that project District Engineer of MDSHA District that project

resides.resides. Director of Highway Development (OHD) for Director of Highway Development (OHD) for

MDSHA.MDSHA. Director of Materials & Technology (OMT) for Director of Materials & Technology (OMT) for

MDSHA.MDSHA. Pavement Division Chief of OMT for MDSHA.Pavement Division Chief of OMT for MDSHA.

Page 25: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Example Component Score

Page 26: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Component Matrix

Page 27: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Alternate Pavement Bidding

Alternate pavement bidding involves the bidding of two equivalent pavement designs in order to determine the most economical solution to the owner.

Page 28: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Use of Alternate Bidding FHWA traditionally discouraged use of alternate

bids for pavements FHWA approved a Special Experimental Project for

use of alternate bids in Missouri 1996. AASHTO recognizes Alternate Bids as a contracting

technique that will be utilized in the 21st century Recommended when more than one alternate is

judged “equal” by an agency and that the least costly design approach will result from a competitive bid.

Alternate bidding should be used when there is no clear cut choice between two alternates and have similar life cycle costs

Page 29: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Use of Alternate Bidding

Federal Aid policy suggests that alternative designs are considered for large projects

A life cycle cost economic analysis should be conducted to compare the total cost of each alternate.

If the alternates do not provide equivalent designs then an adjustment must be made to the bid to equate the alternates.

Pavements should be bid in the same units and materials costs escalators should not be used.

Page 30: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Use of Alternate Bidding

The following States/Provinces have experience with alternative bidding:– Alabama– Kansas– Kentucky– Louisiana– Maryland– Michigan– Missouri– Ohio– Pennsylvania– West Virginia

Page 31: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Alternate Pavement Bidding Account for Bid Adjustment Method A + B A + B + C C is usually a product of the following

example:

C = User Delay Cost + (periodic) Rehab Cost + Annual Maintenance Cost

C is added to the actual bid amount

Page 32: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

West Virginia’s Alternate Bids

Three projects so far with 3 more coming this year

No C factor so far First project went asphalt Next two went concrete with the concrete bid

10% less than asphalt WV is getting the lowest unit prices for

asphalt they seen in years

Page 33: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

Available Software

AASHTO DARWIN design WinPAS (ACPA’s Windows version of

DARWIN) Mechanistic Empirical Pavement Design

Guide (MEPGD – coming soon) RealCosts (LCCA) Concrete Pavement Analyst (NRMCA

parking lot design and cost analysis program)

Page 34: Pavement Type Selection (Designs, Costs & Bidding) 9 th Annual Concrete Conference for the Maryland Transportation Industry March 24, 2009 Timonium, MD.

THANK YOU!

www.midatlantic.pavement.com

www.pavement.com


Recommended