Date post: | 15-Dec-2015 |
Category: |
Documents |
Upload: | lilly-cobleigh |
View: | 214 times |
Download: | 0 times |
Pavement Type Selection(Designs, Costs & Bidding)
9th Annual Concrete Conference for the Maryland Transportation Industry
March 24, 2009
Timonium, MD
Presented by Bob Long
American Concrete Pavement Association
Mid-Atlantic Chapter
Pavement Type Selection Evolution of the Process
Good old days More responsible More structured Let the market dictate
Pavement Type Selection Typical Basic Components
Equivalent designs Cost estimates Life Cycle Cost Analysis (LCCA) Innovative Contracting (e.g., alternate bids)
What are equivalent sections?
•Traffic•Reliability •Subgrade•Terminal Condition
•Traffic•Reliability •Subgrade •Terminal Condition
=
• Provide reasonably similar level of service• Designed with the same procedure
• Same structural capacity
• Similar traffic-carrying capacity over the analysis period
Equivalent Designs
Different Pavement Types
Subbase
Subgrade Subbase
Subgrade
Base
Asphalt Layer
Concrete Section Asphalt Section
How Pavements Carry Loads3000 kg.3000 kg.
pressure < 0.2 MPa
pressure 2.0 MPa
Concrete’s Rigidness spreads the load over a large areaand keeps pressures on the subgrade low.
Costs
Accurate estimates are essential Take into account volume, production, and
availability of materials Update regularly
Costs
Liquid AC index jumped from $340 to $842 per ton in just over 4 months (April—August 2009) – that’s a $25 per ton increase for in-place asphalt pavement
Availability of liquid AC was becoming a concern Over the last 2 years, the price of asphalt pavement
has jumped from about $55 to over $75 and as high as $130 per ton
Although cement prices did rise for a while before the big AC increases, prices are lower and stable
Materials Costs
Economic procedure
– That uses Engineering inputs
Compares competing alternates over their life
– by considering all significant costs (and benefits) Construction, Maintenance, Rehabilitation User Performance
Expressed in equivalent dollars
What is it ?
Life-Cycle Cost Analysis
A Magical Black Box
– There is no concrete LCCA or asphalt LCCA
Complicated
– Does not need a computer program
What it is Not
Life-Cycle Cost Analysis
Pavement A
Pavement A - Rehabilitation Schedule
Pavement A - Present Worth Calculation
Discount Rate =
Yr Cost (1+i)^n PWInitial Const.. 0 1.000Rehab 1.Rehab 2.Rehab 3.Rehab 4.Rehab 5.Rehab 6.Rehab7.Rehab 8.Rehab 9.Rehab 10.Salvage
Total Cost Total NPV
Determine the stream of flow for expenditures. The cash flow diagram (below) shows the inflow and outflow of cash due to construction and rehabilitation. Arrows indicate a major cash expenditure (construction, rehabilitation, etc.). An up arrow indicates the outflow of cash. Down arrows show inflows. With pavements the inflow of cash only occurs at the end of the analysis period to show either continued-use or salvage value. The height of the arrow indicates the magnitude of the expenditure.
2 6 84 10 12 14 2016 18 22 24 3026 28 32 34 4036 38 42 44 5046 480
Using the the expenditure stream above, calculate the Present Worth (PW) for each rehabilitation activity (PW for the initial cost is the initial cost).
PW is calculated using the following formula:
PW = Rehab Cost / (1+i)n
Where i = discount rate n = year rehab takes place
Present Worth Analysis (PW) Equivalent Uniform Annual Cost
Analysis (EUAC)
How it is done:
Life-Cycle Cost Analysis
Present Worth Analysis: Discounts all future costs (benefits) to the present
Co
sts
Initial Cost
Rehabilitation CostMaintenance
Cost
Salvage Value
Years
Co
sts
Present Worth
Years
Life-Cycle Cost Analysis
Economic Factors– Discount rate
– Analysis Period
Engineering Factors– Comparable sections
– Rehabilitation selection
– Agency Costs
– User costs
Basic Factors:
Life-Cycle Cost Analysis
Normally equal for each alternative– Highway: 30-50 years– Street: 20-30 years
– Airport: 30 years
Include at least one rehabilitation– Needed to capture the true economic benefit of each alternate
Analysis Period:
Life-Cycle Cost Analysis
Delay-of-use – Time delays - New construction & Rehabilitation– Fuel consumption
– Driver discomfort
Roadway deterioration– Cargo damage– Vehicle wear
Accidents
User Costs:
Life-Cycle Cost Analysis
Some basic insights:
Initial Costs – Account for about 65-90% of Life Cycle Cost. – Selection of features plays an important role – Need to account for added features on the pavement
performance.
Timing of Activities. – After initial costs and discount rate, the next most important
factor. – The longer an activity is delayed, the greater it is discounted
and the less impact it has on present worth.
Life-Cycle Cost Analysis
Pavement Type SelectionOverview of Maryland Process
Policy on application of process
Three tiered approach– Life cycle cost comparison– Component analysis– Innovative contracting
Probabilistic approach to LCC
Weighting of component factors based on project priorities
Project team formed to make final decision
Application Policy All projects developed through the Project
Planning Division ready for design, and
Any projects with a construction estimate > $15 million (with at least $5 million dedicated to pavement/MOT items)
Estimated to be 6 to 8 projects per year. (Staff resource levels were a limiting factor in the number of projects that could be identified.)
Three Tiered Approach
1st Tier – LCC Analysis within 20%• Initial Cost• Future Rehab Costs over 40 Years• User Delay Costs
2nd Tier – Component Analysis • Cost Factors• Construction Factors• Design & Environment Factors• Form Team and Consider Industry Input
3rd Tier – Innovative Contracting • Alternate Bidding• Warranty Contract • Design/Build Contact
Life Cycle Cost Factors
Based on historical data and expert opinion– Material unit costs– Pavement service life– Construction sequencing– Construction duration– General analysis inputs
Variability represented by average and standard deviation
Example Input – Service Life
Component Analysis Cost Factors
– Present worth Agency Costs – Initial & Future– Present worth User Delay Costs
Construction Factors– Duration of Construction– Maintenance of Traffic– Maintenance of Access – (utilities & future maint, material sources, reliability of construction)
Design and Environment Factors– Traffic and Geometry– Adjacent Pavement and Structures– Environmental Impact – (community concerns, future planning)
Project Level PTST
Chief Engineer for MDSHA Operations. Chief Engineer for MDSHA Operations. District Engineer of MDSHA District that project District Engineer of MDSHA District that project
resides.resides. Director of Highway Development (OHD) for Director of Highway Development (OHD) for
MDSHA.MDSHA. Director of Materials & Technology (OMT) for Director of Materials & Technology (OMT) for
MDSHA.MDSHA. Pavement Division Chief of OMT for MDSHA.Pavement Division Chief of OMT for MDSHA.
Example Component Score
Component Matrix
Alternate Pavement Bidding
Alternate pavement bidding involves the bidding of two equivalent pavement designs in order to determine the most economical solution to the owner.
Use of Alternate Bidding FHWA traditionally discouraged use of alternate
bids for pavements FHWA approved a Special Experimental Project for
use of alternate bids in Missouri 1996. AASHTO recognizes Alternate Bids as a contracting
technique that will be utilized in the 21st century Recommended when more than one alternate is
judged “equal” by an agency and that the least costly design approach will result from a competitive bid.
Alternate bidding should be used when there is no clear cut choice between two alternates and have similar life cycle costs
Use of Alternate Bidding
Federal Aid policy suggests that alternative designs are considered for large projects
A life cycle cost economic analysis should be conducted to compare the total cost of each alternate.
If the alternates do not provide equivalent designs then an adjustment must be made to the bid to equate the alternates.
Pavements should be bid in the same units and materials costs escalators should not be used.
Use of Alternate Bidding
The following States/Provinces have experience with alternative bidding:– Alabama– Kansas– Kentucky– Louisiana– Maryland– Michigan– Missouri– Ohio– Pennsylvania– West Virginia
Alternate Pavement Bidding Account for Bid Adjustment Method A + B A + B + C C is usually a product of the following
example:
C = User Delay Cost + (periodic) Rehab Cost + Annual Maintenance Cost
C is added to the actual bid amount
West Virginia’s Alternate Bids
Three projects so far with 3 more coming this year
No C factor so far First project went asphalt Next two went concrete with the concrete bid
10% less than asphalt WV is getting the lowest unit prices for
asphalt they seen in years
Available Software
AASHTO DARWIN design WinPAS (ACPA’s Windows version of
DARWIN) Mechanistic Empirical Pavement Design
Guide (MEPGD – coming soon) RealCosts (LCCA) Concrete Pavement Analyst (NRMCA
parking lot design and cost analysis program)
THANK YOU!
www.midatlantic.pavement.com
www.pavement.com