+ All Categories
Home > Documents > PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

Date post: 17-Jan-2018
Category:
Upload: claribel-foster
View: 218 times
Download: 0 times
Share this document with a friend
Description:
PC19 High DG WECC Study Requestor: SPSC Changes from 2024CC: – Increased DG generation throughout all of the Western Interconnection. Noting impacts on west-wide energy dispatch and indicators of stress on the supply system; Increase in capacity by 22,648 MW * Note in this study analysis DG refers to small scale solar PV or “rooftop solar” for individual retail customers Key Questions: – How does the system respond to the additional DG? (i.e. over- generation, dump energy) – How does the DG “injection” impact transmission flow and path utilization throughout the region and on the interties? *No changes were made to transmission or load 3 W ESTERN E LECTRICITY C OORDINATING C OUNCIL
63
PC19 High DG - WECC Study Results July 23, 2015 W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L
Transcript
Page 1: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

PC19 High DG - WECC Study Results

July 23, 2015

Page 2: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

2

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

Overview

Scope

• Scope• Key Questions

Assumptions

• E3 Assumptions• Geographic

Variations• Capacity Added

for Study

Results

• Generation Change

• Dump Energy• Path Flows

Production Cost Model

Page 3: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

3

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

PC19 High DG WECC• Study Requestor: SPSC

• Changes from 2024CC:– Increased DG generation throughout all of the Western Interconnection.

Noting impacts on west-wide energy dispatch and indicators of stress on the supply system; Increase in capacity by 22,648 MW

*Note in this study analysis DG refers to small scale solar PV or “rooftop solar” for individual retail customers

• Key Questions:– How does the system respond to the additional DG? (i.e. over-generation,

dump energy)– How does the DG “injection” impact transmission flow and path utilization

throughout the region and on the interties?

*No changes were made to transmission or load

Page 4: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

4

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

DG Starting Point (E3)*

• E3 analysis focuses on small scale solar PV installations by retail customers

– Does not include “wholesale DG” that a utility might procure to meet state DG targets

• Market-Driven DG Model Key Drivers:• Solar PV capital cost• Customer bill savings• Federal investment tax credit• State-specific incentive programs• State net energy metering caps• Utility system interconnection potential

Affect customer decisionto invest in solar PV

Limit total penetrationOn a utility’s system

*Source: E3

Page 5: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

5

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

DG Assumtions (E3)*

• Assumption Overview:• High DG projections are developed by relaxing existing Net Energy Metering

(NEM) caps and assuming achievement of aspirational solar PV cost reductions

• Key Assumptions:• Assumes Net Energy Metering (NEM) caps are removed, allowing installations

of DG in each utility’s service territory up to its “Interconnection Potential• No change in retail rate design

– California Exception: After 2017 exports are assumed to be compensated at avoided cost

• Retail rates escalate at 0.5% per year in real terms• Federal ITC sunsets in 2017

– Credit reduces to 10% of capital costs thereafter• Current state inventive programs sunset after current NEM cap is exceeded

*Source: E3

Page 6: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

6

2024 High DG Projections

Total capacity: 22,648 MW

Load Area

Distributed PV Capacity

(MW)Peak Load

(MW)Capacity

(% of Peak)AESO - 16,370 0.0%APS 1,548 8,512 18.2%AVA 129 2,571 5.0%BCHA - 11,603 0.0%BPA 394 12,023 3.3%CFE - 2,753 0.0%CHPD 18 803 2.3%DOPD 13 500 2.6%EPE 70 2,346 3.0%FAR EAST 34 420 8.2%GCPD 14 1,029 1.4%IID 74 1,198 6.2%LDWP 1,032 5,826 17.7%MAGIC VLY 75 884 8.5%NEVP 747 4,937 15.1%NWMT 207 2,324 8.9%PACE_ID 49 878 5.5%PACE_UT 576 5,642 10.2%PACE_WY 141 1,829 7.7%PACW 263 4,387 6.0%

Load Area

Distributed PV Capacity

(MW)Peak Load

(MW)Capacity

(% of Peak)PG&E_BAY 2,234 12,792 17.5%PG&E_VLY 2,813 12,517 22.5%PGN 441 4,828 9.1%PNM 490 3,472 14.1%PSC 1,645 7,235 22.7%PSE 204 5,222 3.9%SCE 4,534 23,779 19.1%SCL 57 2,709 2.1%SDGE 933 4,520 20.6%SMUD 495 3,206 15.4%SPP 322 3,603 8.9%SRP 1,240 8,484 14.6%TEP 434 4,151 10.5%TIDC 117 603 19.5%TPWR 19 1,137 1.7%TREAS VLY 153 1,924 7.9%WACM 821 5,529 14.8%WALC 294 2,460 12.0%WAUW 19 152 12.2%

Page 7: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

7

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

Generation Change

Conventional Hydro

Energy Storage

Steam - Coal

Steam - Other

Nuclear

Combined Cycle

Combustion Turbine

IC

Other

DG/DR/EE - Incremental

Biomass RPS

Geothermal

Small Hydro RPS

Solar

Wind

0 50,000,000 100,000,000 150,000,000 200,000,000 250,000,000 300,000,000

Annual Generation by Category (MWh)2024 PC19 High DG WECC 2024 PC1 v1.5

Page 8: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

8

Production Cost and CO2Category 2024 PC1 15-01-19 2024 PC 19 High DG WECC Difference

Conventional Hydro 238,955,786 238,935,910 -19,876Energy Storage 3,592,412 3,344,337 -248,076Steam 230,393,384 212,095,530 -18,298,043Nuclear 56,254,786 56,206,670 -48,116Combined Cycle 278,957,656 254,970,479 -23,987,178Combustion Turbine 51,794,128 48,872,363 -2,921,765IC 818,909 655,300 -163,609DG/DR/EE - Incremental 17,916,707 65,404,109 47,487,402Biomass RPS 19,581,287 19,034,598 -546,689Geothermal 31,937,139 31,523,705 -413,434Small Hydro RPS 4,360,054 4,351,069 -8,985Solar 38,182,163 35,734,009 -2,448,153Wind 74,232,546 73,783,251 -449,295== Total == 1,050,342,237 1,048,276,420 -2,065,817

Cost (M$) 22,843 21,477 (1,366)CO2 Cost (M$) 1,730 1,613 (116)CO2 Amount (MMetrTn) 363 336 (26)Dump Energy (MWh) 357,799 3,499,883 3,142,084 Pumping (PL+PS) (MWh) 15,426,008 15,104,430 (321,579)

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C O U N C I L

Page 9: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

9

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

Changes in Total Annual Generation

Conventional Hydro

Energy Storage

Steam - Coal

Steam - Other

Nuclear

Combined Cycle

Combustion Turbine

IC

Other

DG/DR/EE - Incremental

Biomass RPS

Geothermal

Small Hydro RPS

Solar

Wind

(30,000,000) (20,000,000) (10,000,000) 0 10,000,000 20,000,000 30,000,000 40,000,000 50,000,000 60,000,000

Annual Energy Difference (MWh): 2024 PC1 v1.5 vs 2024 PC19 High DG WECC

Page 10: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

10

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

Generation Change By State

AB AZ BC CA CO ID MT MX NE NM NV OR SD TX UT WA WY-10,000,000

-5,000,000

0

5,000,000

10,000,000

15,000,000

20,000,000

25,000,000

30,000,000

Annual Gen Change (GWh) 2024 PC1 v1.5 vs 2024 PC19 High DG WECC

Conventional HydroEnergy StorageSteam - CoalSteam - OtherNuclearCombined CycleCombustion TurbineICOtherBiomass RPSDG/DR/EE - IncrementalGeothermalSmall Hydro RPSSolarWind

IGS as-signed to

UT

Page 11: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

11

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

Generation Change by Subregion

Alberta

British Columbia

Basin

California

Desert Southwest

Northwest

Rocky Mountain

-10,000,000 -5,000,000 0 5,000,000 10,000,000 15,000,000 20,000,000 25,000,000 30,000,000

Change (GWh) by Subregion - 2024 PC1 v1.5 vs. 2024 PC19 High DG WECC

WindSolarSmall Hydro RPSGeothermalDG/DR/EE - IncrementalBiomass RPSOtherICCombustion TurbineCombined CycleNuclearSteam - OtherSteam - CoalEnergy StorageConventional Hydro

IGS assigned to CA

Page 12: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

12

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

Dump Energy

0 AB AZ BC CA CO ID MT MX NE NM NV OR SD TX UT WA WY (blank)

-500000

0

500000

1000000

1500000

2000000

2500000

171,852

2,185,696

0 228 090,328

0 0 0

Biomass RPS Combined Cycle Combustion Turbine Conventional Hydro DG/DR/EE - IncrementalEnergy Storage Geothermal IC Nuclear OtherPumping Load Small Hydro RPS Solar Steam - Coal Steam - Otherunknown Wind (blank)

Page 13: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

13

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

Modeling Constraints

Constraints Name TypeCosts (K$)

Duration(Hrs) CC

Duration (Hrs) PC19 FromBusName FromBusID ToBusName ToBusID

MAGUNDEN-OMAR 230 kV line #1 Branch 26,238 5,741 4,418 MAGUNDEN 24087 OMAR 24101

MAMMOTH-BIG CRK3 230 kV line #1 Branch 8,515 106 1,476 MAMMOTH 24316 BIG CRK3 24303

REDBUTTE-UTAH-NEV 345 kV line #1 Branch 7,706 965 2,500 REDBUTTE 66280 UTAH-NEV 67657

CAL SUB 120/120 kV transformer #1 Branch 2,181 964 1,072 CAL SUB 64025 CAL S PS 64023

BLKGLADW 115/115 kV transformer #1 Branch 2,083 2,252 2,807 BLKGLADW 72771 BLKDPSW 72773

P60 Inyo-Control 115 kV Tie Interface 1,111 2,602 1,019

PG&E Bay 25% LocalMinGen Nomogram 0 511 1,043

LDWP 25% LocalMinGen Nomogram 0 3,859 5,079

SCE 25% LocalMinGen Nomogram 30,401 5,127 5,566

Page 14: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

14

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

Nomograms• Nomogram: – Constraint (inequality) enforced by GV– When “at limit”, additional thermal generation is

dispatched to balance the inequality• 4 new nomograms to 2024 CC:– LDWP 25% LocalMinGen– PG&E Bay 25% LocalMinGen– SCE 25% LocalMinGen– SDGE 25% LocalMinGen

Page 15: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

15

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

Nomogram Constraint PC19 vs CC

9 369 729 1089 1449 1809 2169 2529 2889 3249 3609 3969 4329 4689 5049 5409 5769 6129 6489 6849 7209 7569 7929 8289 8649

-4000

-3500

-3000

-2500

-2000

-1500

-1000

-500

0

500

1000

PG&E Bay 25% LocalMinGenPG&E Bay 25% CCLDWP 25% LocalMinGenLDWP 25% CCSCE 25% LocalMinGenSCE 25% CC

Page 16: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

16

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

Difference in Duration (Hrs)Br

anch

Bran

ch

Bran

ch

Bran

ch

Bran

ch

Inte

rfac

e

Nom

ogra

m

Nom

ogra

m

Nom

ogra

m

MAGUNDEN-OMAR 230 kV

line #1

MAMMOTH-BIG CRK3 230 kV

line #1

REDBUTTE-UTAH-NEV 345

kV line #1

CAL SUB 120/120 kV

transformer #1

BLKGLADW 115/115 kV

transformer #1

P60 Inyo-Con-trol 115 kV Tie

PG&E Bay 25% LocalMinGen

LDWP 25% LocalMinGen

SCE 25% LocalMin-

Gen

-1500

-1000

-500

0

500

1000

1500

2000

Difference in Modeling Constraints PC19 vs CommonCase

Dura

tion

(Hrs

)

Page 17: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

17

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

Results – Most Heavily Utilized Paths• Congestion vs Utilization– Some lines are designed to be congested

• “Most Heavily Utilized” = A path that meets any one of the following criterion (10-year plan utilization screening):– U75 > 50%– U90 > 20%– U99 > 5%

• Uxx = % of year that flow is greater than xx% of the path limit

Page 18: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

18

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

Results – Changes in Transmission Utilization

P45 SDG&E-CFE

P83 Montana Alberta Tie Line

Most Heavily Utilized Paths

P08 Montana to Northwest

P60 Inyo-Control

P10 West of Colstrip

P01 Alberta-British Columbia

Most Heavily Utilized Paths U75 U90 U99

P10 West of Colstrip 50.50% 0% 0%

P45 SDG&E-CFE 13.31% 10.70% 9.3%

P83 Montana Alberta Tie Line 16.09% 8.67% 5.48%

Page 19: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

19

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

Results Common Case

0%

10%

20%

30%

40%

50%

60%

70%

80%

Most Heavily Utilized Paths - PC1_1_5 U75 U90 U99

Perc

ent o

f Hou

rs

Page 20: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

20

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

Results PC19

-P60 Inyo

-Control 1

15 kV Tie

-P52 Silve

r Peak-

Control 5

5 kV

-P45 SDG&E-C

FE

-P83 Montan

a Alberta

Tie Lin

e

xy WA-BC Ea

st

P26 Northern-So

uthern California

P32 Pavant-G

onder InterM

tn-Gonder 230 kV

-P61 Lugo

-Victorvi

lle 500 kV

Line

P66 COI

P18 Montan

a-Idah

o

P15 Midway-

LosBanos

P31 TOT 2

A

P48 Northern New M

exico (N

M2)

-P28 Interm

ountain-M

ona 345 kV

-xy AB-M

T0%

10%

20%

30%

40%

50%

60%

Most Heavily Utilized Paths - PC19 High DG - WECCU75 U90 U99

Perc

ent o

f Hou

rs

Page 21: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

21

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

Path Flows

-1000

-800

-600

-400

-200

0

200

400

600

WECC P45 SDG&E-CFE

2024CC-V1.5 2024-PC19 High DG 2012 2024 Max 2024 Min

Meg

awatt

s

N -> S

-3000

-2000

-1000

0

1000

2000

3000

WECC P10 West of Colstrip

2024CC-V1.5 2024 PC19 High DG 2012 2024 Max 2024 Min

Meg

awatt

s

N -> S

Page 22: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

22

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

Path Flows

-400-300-200-100

0100200300400500600

WECC P83 Montana Alberta Tie Line

2024CC-V1.5 2024 PC19 High DG 2012 2024 Max 2024 Min

Meg

awatt

s

N -> S

-6000

-4000

-2000

0

2000

4000

6000

WECC P66 COI

2024CC-V1.5 2024-PC19 High DG 2012 2024 Max 2024 Min

Meg

awatt

s

N -> S

Page 23: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

23

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

Findings• Generation and Energy Changes:– Increased DG availability results in a reduction in Coal (steam)

and Combined Cycle generation – Increased levels of dump energy (likely due to modeling

constraints – nomograms, transfer capacity)

• Transmission Changes:– Increased path over-utilization in Southern CA and in the

North-East regions

• Production Cost Changes:– Decrease in production cost– Decrease in CO2 production

Page 24: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

24

W E S T E R N E L E C T R I C I T Y C O O R D I N A T I N G C OU N C I L

Contact Info

Tyson [email protected]

Dan [email protected]

801-819-7657

Page 25: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

Distributed Generation Projections for High DG Case

October 10, 2014

Arne Olson, PartnerNick Schlag, Sr. Consultant

Page 26: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

26

Background

In a number of past efforts, E3 has worked with LBNL and WECC to establish input assumptions regarding distributed generation in study cycles:• In 2011-12, E3 worked with LBNL and WECC to develop estimates of DG

potential for the SPSC’s 2022 and 2032 High DG/DSM cases• In 2014, E3 & LBNL developed an approach to project “market-driven”

distributed generation in the WECC, which was used to inform the 2024 Common Case

WECC has requested projections of distributed generation consistent with High DG futures for the Western Interconnection to use in the SPSC’s 2024 and 2034 High DG/DSM casesTo develop these projections, E3 has used logic from both prior efforts to assess future DG installations

Page 27: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

27

Defining “Distributed Generation”

“Distributed” generation means different things to different people:• Behind-the-meter, e.g., customer-owned resource• Small utility or IPP owned resource that is connected at the distribution system and serves

load downstream• Small resource that is connected at the distribution system and does not serve load

downstream• Small resource that is connected to the sub-transmission system (i.e., low-voltage

transmission) near load• Small resource that is located remote from load• Large resource that is located in load pocket and helps defer or avoid transmission

investmentsThis analysis focuses on small scale solar PV installations that individual retail customers would install to avoid purchasing electricity from an electric utility

• Does not include “wholesale DG” that a utility might procure to meet state DG targets

Page 28: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

28

Approaches to Developing High DG Assumptions

2022/2032 High DG Case assumptions developed in two steps:• Estimate interconnection potential for each state• Make state-specific adjustments to interconnection potential

to reflect differences in economic drivers of DG2024/2034 High DG Case assumptions derived by modeling customer decisions under a scenario favorable to distributed generation adoption• Use E3’s Market Driven DG Model to develop projections

of adoption• Rely on estimates of interconnection potential as an upper

bound

Page 29: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

MODELING MARKET-DRIVEN DG

Page 30: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

30

Channels for Distributed Solar PV Adoption

Background

In prior transmission planning study cycles, WECC has incorporated distributed solar PV assumptions consistent with state policy goalsThis framework ignores the potential for market-driven DG• With low PV costs, this could become a large amount of capacity

E3 and LBNL have developed a framework to incorporate market-driven DG into transmission planning studies

Program Goals(e.g. California Solar Initiative)

RPS Set-Asides(e.g. 30% DG set-aside in Arizona)

Market-Driven Adoption

Policy-driven DG, modeled in past WECC studies

New to WECC studies

Page 31: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

31

E3’s Market Driven DG Model

To provide inputs for WECC’s transmission planning studies, E3 has developed a model of DG deployment throughout the WECC footprint between present day and 2040• Joint funding from WECC and LBNL through DOE’s ARRA grants

Input assumptions capture geographic variations in PV cost-effectiveness and state policy• State-specific PV costs• State-specific net metering policy• Capacity factors at a BA level• Utility-specific retail rates (and incentives where applicable)

The model also captures the changing cost-effectiveness of PV:• Continued declines in PV capital costs• Expiration of incentives & tax credits (e.g. ITC in 2017)• Escalation of retail rates• Expected changes to state net metering policies (e.g. California AB 327)

Page 32: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

32

2024 Common Case Recommendations

The Market-Driven DG Model used to develop preliminary recommendations for customer-sited solar for the 2024 Common Case

2024Market Peak Market

Driven DG Load Driven DGState (MW) (MW) (% of Peak)

Arizona 1,751 23,227 7.5%California 5,742 68,908 8.3%Colorado 742 11,789 6.3%Idaho 51 5,664 0.9%Montana 35 2,483 1.4%New Mexico 170 5,139 3.3%Nevada 241 9,951 2.4%Oregon 191 10,392 1.8%Utah 106 5,537 1.9%Washington 90 20,950 0.4%Wyoming 47 3,464 1.4%

Total 9,166 167,505 5.5%

For the 2024 Common Case, TAS adjusted the recommended

values (shown at left) downward by 20%

Page 33: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

HIGH DG CASE RECOMMENDATIONS

Page 34: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

34

Key Drivers of Market Driven DG Model

The main drivers of the modeled customer adoption of solar PV are:

1. Solar PV capital cost2. Customer bill savings3. Federal investment tax credit4. State-specific incentive programs5. State net energy metering caps6. Utility system interconnection potential

Changing the assumptions for each of these parameters provides the basis for exploring alternative projections

Affect customer decision to invest in solar PV

Limit total penetration on a utility’s system

Page 35: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

35

High DG projections are developed by relaxing existing NEM caps and assuming achievement of aspirational solar PV cost reductions

Overview of Assumptions

Assumption Reference Case High DG Case

Net Metering CapsCurrent Policy• Current NEM caps remain in

place• California cap lifted after 2016

NEM Caps Removed• All NEM caps lifted• Limits associated with

interconnection potential enforced

Solar PV Cost TrendsModerate Reductions• Cost trajectory derived by E3

for TEPPC planning studies

Aspirational Reductions• Sunshot goals achieved by

2020

Page 36: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

36

Treatment of NEM Caps

In the Reference Case, each state’s NEM cap was enforced according to current policy

High DG case assumes current NEM caps are removed, allowing installations of DG in each utility’s service territory up to its ‘Interconnection Potential’

State Current NEM CapArizona n/a

CaliforniaLimits under current NEM rate design established by AB327 (approximately 5% of non-coincident peak); beyond 2017, alternative rate designs will be considered with no associated cap

Colorado n/aIdaho n/aNew Mexico n/aNevada 3% of utility peakOregon 0.5% of peak for munis, coops, & PUDs; no cap for IOUsUtah 0.1% of peak for munis; 20% of peak for IOUsWashington 0.5% of peakWyoming n/a

Page 37: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

37

6,638

11,668

15,336

0

5,000

10,000

15,000

20,000

Rule 21 30% Rule Max w/oCurtailment

Incr

emen

tal P

V Po

tenti

al (M

W)

Residential Rooftop Commercial Rooftop

Ground Mounted

Interconnection Potential Background

To estimate interconnection potential across the WECC, E3 leveraged results from a 2012 analysis, Technical Potential for Local Distributed Photovoltaics in California

Study produced estimates of the amount of “local” distributed PV (LDPV) potential under different interconnection standards in California:

1. Rule 21 (Current Policy): sum of rated capacity of interconnections on a feeder may not exceed 15% of the feeder’s peak load

2. 30% Rule: same as (1), but with constraint relaxed to 30%

3. Max w/o Curtailment: the maximum capacity that can be installed on a feeder for which all generation will serve load on that feeder (e.g. no required backflow or curtailment)

In 2012 study cycle, E3 generalized these results to the WECC BAs; the same method is used to determine limits in this study cycle

• 30% Rule for 2024 High DG projections• Max w/o Curtailment for 2034 High DG

projections

Page 38: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

38

Capital Cost Trajectories

Reference case cost reduction trajectory derived through application of learning curve approach• 20% learning rate on

modules; 15% on BOS• IEA medium-term

renewable energy outlook• Adopted by TEPPC

Aspirational case cost reduction trajectory assumes achievement of Sunshot goals by 2020• $1.50/W residential• $1.25/W commercial

$4.11$3.23 $2.83

$1.50 $1.50$0

$2

$4

$6

$8

2010 2014 2018 2022 2026 2030 2034

Residential Costs (2013 $/W-dc)

Reference

Aspirational

$3.54$2.80 $2.45

$1.25 $1.25$0

$2

$4

$6

$8

2010 2014 2018 2022 2026 2030 2034

Commercial Costs (2013 $/W-dc)

Reference

Aspirational

Page 39: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

39

Other Key Assumptions

No changes in retail rate design• Surplus NEM generation is compensated at full retail rate• EXCEPTION: in California, after 2017, exports are assumed to be

compensated at avoided cost (see Slide 30)Retail rates escalate at 0.5% per year in real termsFederal ITC sunsets in 2017• Credit reduces to 10% of capital costs thereafter

Current state incentive programs sunset after current NEM cap is exceeded• e.g. Washington & Oregon (see Slide 31)

Page 40: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

40

High DG Case projections

2024 Projections

Reference Case projections

0

5,000

10,000

15,000

20,000

25,000

2012 2014 2016 2018 2020 2022 2024

Inst

alle

d Ca

paci

ty (M

W)

WECC-US2012 - 2024

2024Market Peak Market

Driven DG Load Driven DGState (MW) (MW) (% of Peak)

Arizona 3,533 23,227 15.2%California 12,305 68,908 17.9%Colorado 2,301 11,789 19.5%Idaho 351 5,664 6.2%Montana 249 2,483 10.0%New Mexico 613 5,139 11.9%Nevada 1,023 9,951 10.3%Oregon 812 10,392 7.8%Utah 574 5,537 10.4%Washington 639 20,950 3.1%Wyoming 248 3,464 7.2%

Total 22,648 167,505 13.5%

0

5,000

10,000

15,000

20,000

25,000

2012 2014 2016 2018 2020 2022 2024

Inst

alle

d Ca

paci

ty (M

W)

WECC-US2012 - 2024

2024Market Peak Market

Driven DG Load Driven DGState (MW) (MW) (% of Peak)

Arizona 1,751 23,227 7.5%California 5,742 68,908 8.3%Colorado 742 11,789 6.3%Idaho 51 5,664 0.9%Montana 35 2,483 1.4%New Mexico 170 5,139 3.3%Nevada 241 9,951 2.4%Oregon 191 10,392 1.8%Utah 106 5,537 1.9%Washington 90 20,950 0.4%Wyoming 47 3,464 1.4%

Total 9,166 167,505 5.5%

Incremental Additions

Incremental Additions

Page 41: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

41

Comparison to 2022 High DG Recommendations

2022 and 2024 High DG projections have similar quantities of distributed generation capacity, but show a regional shift• Relative increases in California, Colorado• Slight decreases in states in the Pacific Northwest

2022 2024High DG High DG Change

State (MW) (MW) (MW)Arizona 3,650 3,533 (117) California 11,670 12,305 635 Colorado 1,410 2,301 891 Idaho 550 351 (199) Montana 160 249 89 New Mexico 600 613 13 Nevada 1,090 1,023 (67) Oregon 1,240 812 (428) Utah 690 574 (116) Washington 1,090 639 (451) Wyoming 510 248 (262)

Total 22,660 22,648 (12)

Notable decreases from 2022

Notable increases from 2022

Page 42: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

42

2034Market Peak Market

Driven DG Load Driven DGState (MW) (MW) (% of Peak)

Arizona 4,495 27,833 16.1%California 17,852 78,325 22.8%Colorado 3,426 12,749 26.9%Idaho 493 6,312 7.8%Montana 345 2,763 12.5%New Mexico 773 5,954 13.0%Nevada 1,274 11,489 11.1%Oregon 1,067 11,794 9.0%Utah 739 5,481 13.5%Washington 852 23,560 3.6%Wyoming 333 3,955 8.4%

Total 31,650 190,215 16.6%

2034Market Peak Market

Driven DG Load Driven DGState (MW) (MW) (% of Peak)

Arizona 2,314 27,833 8.3%California 6,816 78,325 8.7%Colorado 1,133 12,749 8.9%Idaho 93 6,312 1.5%Montana 65 2,763 2.3%New Mexico 251 5,954 4.2%Nevada 307 11,489 2.7%Oregon 234 11,794 2.0%Utah 181 5,481 3.3%Washington 95 23,560 0.4%Wyoming 82 3,955 2.1%

Total 11,570 190,215 6.1%0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

2012 2014 2016 2018 2020 2022 2024 2026 2028 2030 2032 2034

Inst

alle

d Ca

paci

ty (M

W)

WECC-US2012 - 2034

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

2012 2014 2016 2018 2020 2022 2024 2026 2028 2030 2032 2034

Inst

alle

d Ca

paci

ty (M

W)

WECC-US2012 - 2034

High DG Case projections

2034 Projections

Reference Case projections

Page 43: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

DETAILED PROJECTIONS BY LOAD AREA

Page 44: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

44

2024 High DG Projections

Total capacity: 22,648 MW

Load Area

Distributed PV Capacity

(MW)Peak Load

(MW)Capacity

(% of Peak)AESO - 16,370 0.0%APS 1,548 8,512 18.2%AVA 129 2,571 5.0%BCHA - 11,603 0.0%BPA 394 12,023 3.3%CFE - 2,753 0.0%CHPD 18 803 2.3%DOPD 13 500 2.6%EPE 70 2,346 3.0%FAR EAST 34 420 8.2%GCPD 14 1,029 1.4%IID 74 1,198 6.2%LDWP 1,032 5,826 17.7%MAGIC VLY 75 884 8.5%NEVP 747 4,937 15.1%NWMT 207 2,324 8.9%PACE_ID 49 878 5.5%PACE_UT 576 5,642 10.2%PACE_WY 141 1,829 7.7%PACW 263 4,387 6.0%

Load Area

Distributed PV Capacity

(MW)Peak Load

(MW)Capacity

(% of Peak)PG&E_BAY 2,234 12,792 17.5%PG&E_VLY 2,813 12,517 22.5%PGN 441 4,828 9.1%PNM 490 3,472 14.1%PSC 1,645 7,235 22.7%PSE 204 5,222 3.9%SCE 4,534 23,779 19.1%SCL 57 2,709 2.1%SDGE 933 4,520 20.6%SMUD 495 3,206 15.4%SPP 322 3,603 8.9%SRP 1,240 8,484 14.6%TEP 434 4,151 10.5%TIDC 117 603 19.5%TPWR 19 1,137 1.7%TREAS VLY 153 1,924 7.9%WACM 821 5,529 14.8%WALC 294 2,460 12.0%WAUW 19 152 12.2%

Page 45: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

45

2034 High DG Projections

Total capacity: 31,650 MW

Load Area

Distributed PV Capacity

(MW)Peak Load

(MW)Capacity

(% of Peak)AESO - 22,683 0.0%APS 1,990 9,715 20.5%AVA 177 2,920 6.1%BCHA - 12,948 0.0%BPA 553 13,930 4.0%CFE - 3,513 0.0%CHPD 27 990 2.7%DOPD 18 638 2.8%EPE 87 2,891 3.0%FAR EAST 49 500 9.7%GCPD 20 1,199 1.6%IID 91 1,449 6.3%LDWP 1,327 6,550 20.3%MAGIC VLY 103 889 11.6%NEVP 925 5,548 16.7%NWMT 282 2,541 11.1%PACE_ID 67 988 6.8%PACE_UT 740 5,523 13.4%PACE_WY 181 1,891 9.5%PACW 347 4,633 7.5%

Load Area

Distributed PV Capacity

(MW)Peak Load

(MW)Capacity

(% of Peak)PG&E_BAY 3,237 14,225 22.8%PG&E_VLY 4,247 14,478 29.3%PGN 571 5,644 10.1%PNM 607 3,679 16.5%PSC 1,965 7,105 27.7%PSE 262 5,602 4.7%SCE 6,605 26,716 24.7%SCL 75 2,852 2.6%SDGE 1,437 5,331 27.0%SMUD 620 3,480 17.8%SPP 422 4,487 9.4%SRP 1,509 10,321 14.6%TEP 513 4,693 10.9%TIDC 174 710 24.5%TPWR 26 1,252 2.1%TREAS VLY 206 2,171 9.5%WACM 1,108 7,136 15.5%WALC 470 3,910 12.0%WAUW 26 172 15.4%

Page 46: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

Thank You!Energy and Environmental Economics, Inc. (E3)101 Montgomery Street, Suite 1600San Francisco, CA 94104Tel 415-391-5100Web http://www.ethree.com

Page 47: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

MARKET-DRIVEN DG: METHODOLOGY AND ASSUMPTIONS

Page 48: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

48

General Model Logic

E3’s Market-Driven DG model combines a customer decision model with policy targets and NEM caps to provide a comprehensive assessment of behind-the-meter solar PV in the Western InterconnectModeling steps:1. Assess potential size of distributed solar PV market based

on economics2. Adjust forecast upward to meet any policy targets3. Limit total installations based on state net metering caps

Page 49: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

49

Step 1: Market-Driven Adoption

1. Determine payback period

Payback

-$4,000

-$3,000

-$2,000

-$1,000

$0

$1,000

$2,000

$3,000

$4,000

0 5 10 15

Cum

ulati

ve N

et C

ost (

$)

Years Since Installation

2. Determine max market share

3. Fit logistic curve

t-1t

0%1%2%3%4%5%6%7%8%

0 5 10 15 20 25

Mar

ket P

enet

ratio

n (%

)

Years

4. Apply to technical potential

7%

0%

20%

40%

60%

80%

100%

0 5 10 15 20 25 30 35

Max

imum

Mar

ket S

hare

(%)

Payback Period

Technical potenial MW

x Market penetration at t %

= Installed capacity at t MW

Page 50: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

50

Calculating the Payback Period

The payback period is the first year in which a customer who choose to install solar PV will have a net positive cash flowTo determine the payback period, E3 considers:• System capital costs: costs of purchasing & installing a PV system• Operating & maintenance costs: costs of year-to-year maintenance,

including inverter replacement• Federal tax credits: investment tax credit (30% until 2017; 10% thereafter)• State & local incentives: up-front & performance-based incentives, vary by

utility & state• Bill savings: reductions monthly energy bills, vary by utility• Green premium: a non-financial value that a customer derives from having

invested in solar PV (assumed to be 1 cent/kWh)

Page 51: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

51

Solar PV Capital Costs by Installation Vintage

Installed PV cost assumptions based on draft recommendations for PV capital costs developed by E3• Presented to TAS on December 19

Future cost reductions primarily reflect lower balance-of-systems costs

Historical

$4.8

$3.6$4.0

$3.0

$0

$1

$2

$3

$4

$5

$6

$7

$8

$9

$10

2010 2012 2014 2016 2018 2020 2022 2024

Inst

alle

d Co

st (2

014

$/W

-dc)

Residential

Commercial

Page 52: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

52

Solar PV Costs by State

System average costs are adjusted for each state to capture regional variations in costs• Regional adjustments based on LBNL’s Tracking the Sun VI

$5.1$4.8 $4.6

$4.3 $4.3

$3.7$3.5

$4.2$4.0 $3.9

$3.6 $3.6

$3.1$2.9

$4.8 $4.6 $4.6 $4.6 $4.5

$3.9 $3.8 $3.8 $3.8 $3.7

$0

$1

$2

$3

$4

$5

$6

CA NM WA OR MT ID UT WY NV AZ CO TX

2013

Inst

alle

d Co

sts (

2014

$/W

-dc)

Residential

Commercial

Where Tracking the Sun VI did not report PV costs, costs were interpolated based on the Army Corps of Engineer’s Construction Works Cost Index

Page 53: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

53

All WECC states currently allow net metering, under which a customer is compensated for PV output based on its retail rate

• This is the primary economic benefit to a customer who chooses to install distributed PVMarket adoption model includes utility-specific rate information for 30 large utilities in the West (a subset are shown below)

• For other smaller utilities, a state-specific average retail rate is used

$0.00

$0.05

$0.10

$0.15

$0.20

$0.25

$0.30

$0.35

2013

Res

iden

tial R

etai

l Rat

e ($

/kW

h)

Avoided Energy Cost

California: IOUs’ high tiered rates provide strong incentive to

customers

Northwest: Low-cost hydropower keeps

rates lowSouthwest Rocky Mountains

General trend in retail rates

Page 54: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

54

Changes to Avoided Energy Cost over Time

E3 assumes that utilities continue to compensate customers at their full retail rate throughout the analysis horizon with one exception• Real escalation of 0.5% per year is assumed

California’s AB 327 directs the CPUC to implement a standard NEM tariff beginning in July 2017As this tariff has not yet been defined, E3 has chosen to model it in the following manner:• All generation consumed on-site is compensated at the customer’s

retail rate• 50% for residential systems, 70% for commercial systems (based on

CPUC NEM study)• All generation exported to the grid is compensated at the utility’s

long-run avoided cost (based on a CCGT)

Page 55: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

55

State-Specific Incentives

Payback period is also heavily influenced by state incentive programsE3’s model captures the impact of two large incentive programs:• Renewable Energy Cost Recovery Program (WA)

• Performance-based incentive capped at $5,000 per year• Program ends in 2020

• Residential Energy Tax Credit (OR)• Incentive of $2.1/W-dc, capped at $6,000• Program ends in 2018

Note: incentives linked to specific policy targets (e.g. set-asides, program goals) are not modeled explicitly and are instead accounted for by adjusting market-driven forecast upward to meet policy goals

Page 56: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

56

Sample Payback Period Results, 2013 Residential Systems

Payback periods vary widely across the WECC geography as a function of:• System costs• Incentives

• Retail rates• Capacity factors

Utility StateCost

($/W-ac)ITC (%)

Incentive ($/W-ac)

Incentive ($/kWh)

Retail Rate ($/kWh)

Capacity Factor (%)

Payback(yrs)

Arizona Public Service Co AZ 5.06$ 30% -$ -$ 0.13$ 22% 12Pacific Gas & Electric Co CA 6.02$ 30% -$ -$ 0.31$ 20% 7Public Service Co of Colorado CO 4.39$ 30% -$ -$ 0.12$ 20% 13Idaho Power Co ID 5.39$ 30% -$ -$ 0.09$ 19% 20NorthWestern Energy LLC - (MT) MT 5.43$ 30% -$ -$ 0.11$ 17% 19Public Service Co of NM NM 5.66$ 30% -$ -$ 0.13$ 23% 13Nevada Power Co NV 5.06$ 30% -$ -$ 0.12$ 22% 13Portland General Electric Co OR 5.46$ 30% 1.25$ -$ 0.10$ 15% 17PacifiCorp UT 5.39$ 30% -$ -$ 0.11$ 19% 17Puget Sound Energy Inc WA 5.60$ 30% -$ 0.15$ 0.10$ 14% 11

Page 57: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

57

Modeling Solar PV Adoption

NREL’s Solar Deployment System (SolarDS) model provides one of the more transparent forecasts of PV adoption:

• “…a geospatially rich, bottom-up, market-penetration model that simulates the potential adoption of photovoltaics (PV) on residential and commercial rooftops in the continental United States through 2030”

Much of the logic used in the Adoption Module has been adapted from SolarDS:

• Maximum market share as a function of payback period• Logistic curves for adoption

Documentation for SolarDS model: http://www.nrel.gov/docs/fy10osti/45832.pdf(Figures taken from this document)

Page 58: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

58

Assumed Payback Curves

Payback curves are based on functional forms documented in SolarDS model

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

0 5 10 15 20 25 30

Max

imum

Mar

ket S

hare

(% o

f tec

hnic

al

pote

ntial

)

Payback Period

Res ExistingRes NewCom ExistingCom New

Utility StatePayback

(yrs)

Maximum Market

Share (%)Arizona Public Service Co AZ 12 2.7%Pacific Gas & Electric Co CA 7 12.2%Public Service Co of Colorado CO 13 2.0%Idaho Power Co ID 20 0.2%NorthWestern Energy LLC - (MT) MT 19 0.3%Public Service Co of NM NM 13 2.0%Nevada Power Co NV 13 2.0%Portland General Electric Co OR 15 1.1%PacifiCorp UT 17 0.6%Puget Sound Energy Inc WA 11 3.7%

Page 59: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

59

Assumed Technical Potential

E3 calculates technical potential by specifying:1. The percentage of total customers that could feasibly install solar PV (50%

for residential and commercial)2. The representative system size for a typical install (4 kW for residential; 50

kW for commercial)Resulting assumed technical potential aligns well with NREL’s assessment of rooftop PV technical potential on a state level:

Total technical potential is approximately 150 GW in 20100

10

20

30

40

50

60

70

80

AZ CA CO ID MT NM NV OR UT WA WY

Rooft

op P

V Te

chni

cal P

oten

tial

(GW

)

E3 Assumed Technical Potential

NREL Modeled Technical Potential

Source: U.S. Renewable Energy

Technical Potentials: A GIS-

Based Analysis (NREL)

Page 60: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

60

Step 2: Policy Adjustments

A large number of states have enacted policies to encourage the deployment of distributed solar PVIn cases where the market-based adoption forecast falls short of state policy targets, upward adjustments are made to reflect achievement of current policy• Assumes utilities will fund programs to reach targets

State PolicyArizona RPS DG Set-Aside (4.5% of IOU/coop retail sales by 2025)California California Solar Initiative (2,300 MW for IOUs; 700 MW for publics)

Colorado RPS DG set-aside (3% of IOU 2020 retail sales; 1% of public utility 2020 retail sales)

New Mexico RPS DG set-aside (0.6% of 2020 retail sales)Nevada Nevada Solar Incentives Program (36 MW among NVE and SPP)

Oregon Energy Trust (124 MW among PGE and PacifiCorp)Solar Volumetric Incentive and Payments Program (27.5 MW among PGE, PacifiCorp, and IPC)

Page 61: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

61

Policy Adjustments

For each utility, initial market-driven DG forecast is adjusted upward in each year it is short of policy targetsIllustrative example shown for APS

0

100

200

300

400

500

600

700

800

900

2010 2012 2014 2016 2018 2020 2022 2024

Inst

alle

d Ca

paci

ty (M

W)

Market-Driven DG Policy Target

Page 62: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

62

Step 3: Adjust for Net Metering Policy

Common Case projections assume all current NEM caps remain in place• Arizona, Colorado, Montana, New Mexico, Wyoming: no cap• Oregon & Washington: 0.5% of utility peak• Idaho: 0.1% of utility peak• Nevada: 3% of utility peak• California: 5% of noncoincident peak (currently)

Common Case projections assume these caps remain in place throughout the analysis• Exception: California’s AB 327 lifts the existing NEM cap beginning

in 2017 with the implementation of a standard NEM tariff

Page 63: PC19 High DG - WECC Study Results July 23, 2015 W ESTERN E LECTRICITY C OORDINATING C OUNCIL.

63

NEM Adjustments

For each utility whose installed capacity would be constrained by a NEM cap, installation forecast is adjusted downward to the limitIllustrative example shown for Puget Sound

0

50

100

150

200

250

300

2010 2012 2014 2016 2018 2020 2022 2024

Inst

alle

d Ca

paci

ty (M

W)

Market-Driven DG Policy Target


Recommended