Date post: | 08-Mar-2018 |
Category: |
Documents |
Upload: | nguyenliem |
View: | 219 times |
Download: | 3 times |
Case Study & Initiatives
SO2 & NOx Control
G.VenuGM (Project Engineering)NTPC Ltd
- Overview - NTPC Perspective- Technology Scan- Environmental Action Plan
SOxNOx Conference 21/09/2017 New Delhi
Case Study & Initiatives
SO2 & NOx Control
Overview
Pollution is the introduction of contaminants into the natural environment that causeadverse change. Pollution can take the form of chemical substances or energy, such asnoise, heat or light.
India: Emission % by sourceEmission (%) Power Industry Residential/Others Transport
SO2 46 41 6 7
NOx 20 20 10 40
PM 17 9 47* 17
CO - 10 11 75* Wood Burning/Brick Kiln/Generator/Construction/Waste Burning etc.
Nitrogen dioxide and nitric oxide are referred to together as oxides of nitrogen
(NOx). NOx gases react to form smog and acid rain as well as being central to
the formation of fine particles (PM) and ground level ozone, both of which areassociated with adverse health effects..
Sulphur dioxide (SO2) is one of a group of highly reactive gases known as
“oxides of sulphur”. SO2 is linked with a number of adverse effects on the
respiratory system and other environmental issues. It is an important
industrial emission gas which causes several difficulties in the environmentlike acid rain.
Indian Power Scenario: 2016-17India: 329 GW
NTPC : 51,410 MW Capacity (16%)
NTPC Generation: 250 BU (22%)
NTPC Coal PLF 78.6%
India 329 GW
Thermal 12th PlanTarget- 88 GW
Addition- 99 GW
Renewable 2016-17Target-17 GW
Addition-11 GWShortage-6 GW in Solar
Coal- 546 MMT
Sector Wise (GW & BU) 2016-17
Sector GW % BU %
Central 80 25% 433 38%
State 104 32% 351 30%
Private 143 43% 370 32%
Capacity Type (GW): Total 329 GW
Thermal 220 67%
Nuclear 6 2%
Hydro 45 14%
Renewable 57 17%India Generation (BU)
@ PLF 60% (Th)
Total 1154 2016-17
Thermal 931 81%
Hydro + Nu 141 12%
Renewable 82 7%
Coal: Capacity Sector Wise (GW)
(4.8 BU/GW)
Total 194 100%
Central 55 28%
State 65 34%
Private 74 38%
Renewable Energy 2016-17 (1.4 BU/GW)
Description Capacity, GW Generation, BU
Total 57 GW 100% 82 BU 100%
Wind 32 56% 46 56%
Solar 12 21% 14 17%
Bio 8 14% 14 17%
Small Hydro 5 9% 8 10%
Peak Demand 2016-17
Demand Met Deficit %
159.6 GW 157 GW (-) 2.6 (-) 1.6
1142 MU 1135 MU (-) 7 (-) 0.7
Private Utility Capacity (MW)
Tata Power 10,496
Adani Power 10,440
DVC 9,445
Reliance Power 6,000
GMR 4,400
Lanco Infratech 3,460
CLP 3,000
Torrent Power 1,647
PSU Utility Capacity (MW)
NTPC 51,410
NHPC 9,847
DVC 9,298
NPCIL 4,500
NLC 4,298
SJVN 1,959
Renewable: Capacity Sector Wise (GW)
(1.4 BU/GW)
Total 57 100%
Central 2 4%
State 0 0%
Private 55 96%
Generation (BU) All India
Period 2017 Conventional Renewable
Total Generation
(BU)
April 103.16 6.93 110.09
May 107.29 8.66 115.95
June 97.52 10.22 107.74
July 97.91 11.9 109.81
Total 405.88 37.71 443.59% 91.5 8.5 100
Thermal Plant: April to August 2017 Generation Data: Sector-wise
S.No Sector Installed
Capacity (MW)
Generation
(BU)
PLF (%)
1 Central 63,190 144 71.73
2 State 71,228 129 54.46
3 Private 85,015 151 56.01
Total 219,435 424 58.96
The emissions per unit of electricity from Thermal Plants are estimated to be in therange of 6.94 to 7.20 g/kWh for SO2, and 4.22 to 4.38 g/kWh for NOx
Coal will be mainstay for Energy needs…
2014-15:SO2 Levels 2014-15:NOx Levels
2009--2015-SO2 Levels 2009-15:NOx Levels Delhi
Cape Town
UN Framework Convention for Climate Change (UNFCCC)
India notified revised Environmental Norms on 7th December 2015 (before COP-21)Since RE is not available 24x7, India has to look for adequate balancing power from coal as India does not have enough gas and oil resources.
The twenty-first session of the Conference of the Parties (COP) and the eleventh session of the Conference of the Parties serving as the meeting of the Parties to the Kyoto Protocol (CMP) took place from 30 November to 11 December 2015, in Paris, France.
India: Renewable Generation expected by 2022 (20%)
Description Sulphur Dioxide (SO2) Oxides of
Nitrogen (NOx)
Mercury
(Hg)
Installation Period (mg/Nm3)
(For < 500 MW
size)
(mg/Nm3)
(For > 500 MW
size)
(mg/Nm3) (mg/Nm3)
Installed before December
31, 2003
600 200 600 0.03
Installed after 2003 and up to
Dec, 2016
600 200 300 0.03
Installed after December,
2016
100 100 100 0.03
Suspended Particulate Matter
(SPM)
New Norms
(mg/Nm3)
Installation Period
Installed before December 31, 2003 100
Installed after 2003 and up to 31
Dec, 2016
50
Installed after 31 December, 2016 30
New Environmental Norms for Particulate emissions, SO2, Nox & Mercury (07/12/2015)
Mercury Emission Control:
No matured or commercial technology
is available for mercury emission
control now. However, the limits of
Mercury emission shall be met
through above methods like ESP/ESP
R&M and future FGD in all units.
National Ambient Air Quality Standards
(2009)
Pollutant Time weighted Average
Concentration in Ambient Air
(microgram/cum)
SO2 Annual24 hours
5080
NOx Annual24 hours
4080
Case Study & Initiatives
SO2 & NOx Control
NTPC Perspective
NTPC Operating Plants NO. OF PLANTS
CAPACITY (MW)
NTPC Owned
Coal 20 38,755
Gas/Liquid Fuel 7 4,017
Hydro 1 800
Renewable(Solar + Wind)
12 910
Sub-Total 40 44,482
Owned By JVs/Subsidiaries
Coal & Gas 9 7,216
Operating Plants Total 49 51,698
Ongoing Projects as on 14.07.2017 Capacity (MW)I. NTPC owned:
A. Coal Based Projects
1. Bongaigaon, Assam 250
2. Barh-I, Bihar 1,980
3. Lara-I, Chattisgarh 1,600
4. North Karanpura, Jharkhand 1,980
5. Kudgi-I, Karnataka 800
6. Gadarwara-I, Madhya Pradesh 1,600
7. Solapur, Maharashtra 660
8. Darlipalli-I, Odisha 1,600
9. Tanda-II, Uttar Pradesh 1,320
10. Khargone, Madhya Pradesh 1,320
11. Telangana Phase-I, Telangana 1,600
Sub Total (A) 14,710B. Hydro Electric Power Projects (HEPP)
12. Tapovan Vishnugad, Uttarakhand 520
13. Lata Tapovan, Uttarakhand@ 171
14. Rammam Hydro, West Bengal 120
Sub Total (B) 811C. Renewable Projects (Solar/Small Hydro)
15.Singrauli Small Hydro 8
16. Rojmal Wind 10
Sub Total (C) 18
Total I: (A)+(B)+(C) 15,539
II Projects under JVs & Subsidiaries
Coal Based Projects
18. Nabinagar- JV with Railways, Bihar 500
19. Nabinagar, JV with BSPGCL, Bihar 1,980
20. Meja, JV with UPRVUNL, Uttar Pradesh 1,320
21.Rourkela NSPCL 250
22. Durgapur NSPCL 40
Total II 4,090
III Total On-Going Projects as on 14.07.2017 (I)+(II) 19,654 MW
Operating Plants: 51,698 MWPlants Under Implementation: 19,654 MW
Plants under Tendering: 4,996 MW (Thermal: 3720 + RE : 1276)
Total Capacity: 76,348 MW
NTPC Portfolio
Super Critical is Central to NTPC’s Clean Power Focus
Thermal Efficiency development of NTPC units
NTPC Initiatives & Future PlansCoal will be mainstay for India. Accordingly, NTPC is working towards a balance of Technology Mix & Portfolio Mix havingdiversified fuel mix with 600 BU Generation by 2032 for reduction of emissions and resulting Environmental Protection.
Tenders for all new coal plants like Patratu (3 X 800 MW)/Talcher TPP (2 X 660 MW)/Singrauli-III (2 X 660 MW) include FGD &SCR Systems for limiting SO2 & NOx emissions.
Technology Mix Portfolio Mix
- Higher Efficiency- Lower Aux Power
- Higher Parameters- R&M of units
- SC/Ultra Super Critical units- IGCC/Oxyfuel
- Advanced Ultra SC (R&D)- Retrofit of Pollution Control Systems
- (FGD/CM/SCR/SNCR)
- Renewable EnergySolar PV Plants
Roof Top Solar PV PlantsSolar Thermal PlantWind Power PlantGeo Thermal Plant
Small Hydro- Hydro Projects
- Nuclear Projects
Other areas:- Wind + Solar Hybrid Plant @ Kudgi- Waste to Energy Plants- Biomass Co-firing
Portfolio by 2032 GW %
Coal 85 65.4
Gas 6 4.6
Hydro 5 3.8
Solar + Other RE 32 24.7
Nuclear 2 1.5
• During early 2016, NTPC Team visited USA, Europe & Japan to get feedback on varioustechnologies for SO2 &NOx controls. Apart from Manufacturers, NTPC Team also visited12 Coal fired Power Stations abroad wherein Emission Control Systems like FGD, SCR,SNCR, REACT etc. were installed.
• NTPC Team collected feedback on Technologies and Performance feedback along withO&M issues. NTPC Team also gathered data about the Environmental Normsimplementation period, schedule as well as shut down of unit required etc.
• The above visits, discussions with various Technology providers and internal technicalanalysis had confirmed the need for installation of suitable technologies likeFGD/SCR/SNCR/CM for control of SO2 &NOx from the Coal fired Power Plants of NTPC.
• Based on the above, NTPC has selected the appropriate technology and also taken up inFebruary 2016 various Policy Advocacy issues on implementation of NewEnvironmental Norms with MOEF &CC, MOP, CEA & CERC. A number of meetings in thisregard was also attended by NTPC and discussed all implementation issues.
NTPC Efforts & Policy Advocacy
Major issues taken up by NTPC (February 2016)
• Exemption of norms for SO2 & NOx Emission limits for units commissioned prior to 2003.
For existing units, serious concerns exist with regard to space availability for retrofit of FGD andDe-Nox Systems as no provision was required to be kept as per Environmental Clearances forthese units.
• Proven Technology for NOx limit of 100 mg/Nm3.
Provenness of SCR Technology for high ash Indian coals are yet to be established. Further,without SCR/SNCR Technology, the limit to be relaxed to 450 mg/Nm
3for unit installed after
2003.• Staggering of implementation period and consideration of 5-10 years for implementation as
per practice in some countries like South Africa.
• Allowing fixed charge recovery for extended shut down for retrofitting FGD/SCR/ChimneyLining for about 6 months per unit.
• Compliance to be considered on Station Level and not on Unit level for emission limits.
• With stringent limits of PM, SO2 & NOx Emission limits, Chimney height norms to be relaxed.
• Issues related to additional costs involved and impact on tariff and request for Fund support.
Case Study on
SO2 & NOx Emission Control Technologies
The IEA’s June 27–released World
Energy Outlook 2016 special report,
“Energy and Air Pollution,” says that
between 2005 and 2015, coal-fired power
generation worldwide expanded 34%, but
total power sector emissions over the
same period plunged: SO2 by 55%,
NOx by 34% and PM2.5 by 32%.
The World’s Power Sector emitted a third of global sulphur dioxide (SO2) emissions,14% of nitrogen oxides (NOx), and 5% of total particulate emissions (PM2.5), but thoseemission values have fallen drastically over the last decade even though coal powergeneration has seen a surge, the International Energy Agency (IEA) said in a newreport.IEA attributes the reduction in emissions principally due to the “Introduction ofEmission Standards for Coal-fired Power Plants, which led either to the use of coal witha lower sulphur content or to the installation of Pollution Control Technologies” overthe last 10 years.
Spray Dryer Absorber (SDA)Circulating Dry Scrubber (CDS)Novel Integrated Desulfurization (NID)
Sulphur Dioxide (SO2) Emission Control Technologies
Beside above there are other technologies such as Sorbent Injection, Multi-pollutant Control Technology.
Parameters WET Limestone FGD DRY FGD (SDA/CDS/NID)
Commercially Available Range ~ 1,100 MWe~ 300-400 MW single absorber. For higher
size units multiple absorbers.
SO2 removal efficiency Up to 99 % up to 99 % (90-95 % for SDA)
Installation Cost (Considering ZLD & Chimney lining cost)
High Low
Operating Cost Moderate High
Sorbent consumptionCaCO3 (limestone)
SR 1.05CaO / Ca(OH)2
SR 1.3 – 1.5
Sorbent costs (Rs/ton) ~2000 ~6000
Water consumption1.0 with GGH
1.4 without GGH0.7
Auxiliary Power ConsumptionHigh with GGH
Moderate without GGH Moderate
Flue gas temperature at FGD outletSaturation temperature
50 – 60 °C (Without GGH)75 – 85 °C
SO3 removal < 40 % > 98 %
Condition of existingstack
Existing stack has to be modified . Long outage for retrofit
Existing stack can be usedwithout modification
Brief comparison of De-SOx Technology
21
Sea Water FGD
Preferred option for Coastal Plants except in Japan
METRIC UNIT
SO2 Emissions ≤ 35 mg/Nm3
Particulate Matter Emissions ≤ 5 mg/Nm3
Ammonia Slip ≤ 3 mg/Nm3
Ammonia Recovery Rate
≥ 99%
Ammonia based FGD System
LIMESTONE PROCESS AMMONIA PROCESS
Absorbent Limestone Ammonia
By-Product GypsumAmmonia Sulfate
Fertilizer
SO2 Removal Efficiency
≥ 95% ≥ 99%
Waste Water 25 kg/hr /MW None
CO2 Emissions 0.7 t/t SO2 Removed None
Comparison Between Limestone & Ammonia Process
Multi-Pollutant Control (MPC) Systems
MPC Systems*
Wet Scrubbing Dry TechnologiesNon-Thermal Plasma
TechnologiesGas Phase Oxidation
Technologies
Air borne ProcessNeuStream
ProcessSkymine Process(High Water Consumption)
ReACTSNOX
EBFGTECO
(High Power Consumption)
EPS SystemLextranLotoX
(High Power Consumption)
Multi-Pollutant Control system remove two or more of the principal regulated pollutants (SO2, NOx, PM, Hg and CO2) in a single reactor or a single system designed for the purpose
*Source: IEA Report
NTPC’s Plan for implementation of SO2 Emission Control Technology
Based on meetings/discussions with various SO2 emission control technology supplier and visit to various
installations worldwide it has been concluded that Wet FGD may be most suitable technology for Indian
conditions.
De-SOx technologies
For Indian conditions wet FGD will be more suitable Sea water FGD will be suitable in case of coastal plant
As NTPC is already installing Wet FGD in two of its projects i.e. Bongaigaon (3 X 250 MW) & Vindhyachal (1 X 500 MW).
Based on experience of the design of two projects, planning for FGD at various NTPC stations are on with respect to following issues:
Availability of Space for installation of various FGD system components.
Availability of Lime stone.
Disposal of by-product.
Modification in the existing duct layout.
Modification in the Chimney lining.
Technologies to limit Nitrogen Oxide (NOx) emission
There are mainly three NOx control technology namely,
Combustion Modification(CM)
Selective Non-Catalytic Reduction(SNCR)
Selective Catalytic Reduction(SCR)
These technologies can be implemented individually/ combined as per the requirement
Description In Combustion Post Combustion
Technology Combustion Modification SNCR SCR
NOx Emission Control Measures
Low NOx Burner
Staged combustion throughvarious type of over fire airdampers
NOx reduction through reagentinjection:Aqueous ammonia or Ureasolution
NOx reduction through reagentinjection in presence of catalyst:Catalyst type:Plate/ Honeycomb/CorrugatedReagent:Anhydrous/ Aqueous or Ureaderived ammonia
Reduction Efficiency 20 – 60 % 25-40 % 90 % & Above
Installation Cost Low Moderate High
Operational CostNone
High (mainly reagent cost)High (Aux power, reagent
cost & catalyst replacement)
Operating Temperature Range
N/A 870° to 1100°C 300° to 400°C
Brief comparison of Technologies to limit Nitrogen Oxide (NOx) emission
The suitability of SCR/SNCR technology for Indian Coal with high ash and abrasive ash is not proven
Case Study on SO2 & NOx Emission Control
Action Plan
SO2
Emission Control
Worldwide Plant Visit
& Feedback
Analysis & Policy
Advocacy
Technology, Phasing Plan &
Strategy
Action Plan &
Approval
Tendering & Implementation
NOx
Emission Control
Worldwide Plant Visit
& Feedback
Analysis & Policy
Advocacy
Technology, Pilot Testing & Strategy
Tendering & Implementation(after Pilot Test)
EOI forLimestone Supply &
Gypsum Sale
Boiler OEM support for Combustion Modification
CM Pilot Test
300/100 mg/Nm3
600 mg/Nm3
Wet Limestone FGDLot-1: UC & up to 5 years
Lot-2: 5 to 15 yearsLot-3: >15 years
USAEurope
UKJapan
SCR/SNCR
Compliance Target progressively
as per RPC guidelines byDecember 2022
NTPC Plant
Operating Data
Collection
NTPCPlant
Operating Data
Collection
NTPC48 GW Coal fired Plants(Additional 14 GW after CERC clearance)
MOEFCERCCEAMOPRPC
S.No Description Capacity(MW)
NIT Remarks
FGD under operation/implementation/tendering 5,250 Done VSTPP-V FGD Commissioned
Summary of FGD Tendering Plan
1 Lot-1A (ICB Mode)(Units Under Construction & Less than 5 years in operation)
17,440 30/06/2017
2 Separate Tenders (ICB Mode)(Khargone & North Karanpura)
3,300 17/07/2017
3 Lot-1B (DCB Mode)(Units less than 5 years in operation)
7,210 31/07/2017
4 Lot-2 (DCB Mode)(Units between 5 to 15 years in operation)
14,670 Oct-Dec 2017(Plan)
5 Lot-3 (DCB Mode)(Units more than 15 years in operation)
14,580 - (NIT after CERCclearance)
Total 62,540 MW
Wet Limestone based FGD System Plan: NTPCAfter detailed deliberations and meetings with CEA, CERC, RPCs and Ministries, NTPC formulated an ActionPlan for control of SO2 & NOx which was cleared by NTPC Board in March 2017 and subsequently developedan implementation plan.
S.No Activity detail Expected Time Schedule Remarks
1 Distribution of common test procedure to EOI Applicants after
approval of procedure and investment note sheet15.10.16 Distributed on 17.10.16
2 Publishing of Notice for interesting applicants other than EOI for
pilot test20.10.16 Published on 20.10.16
3 Agreement signing with Various willing applicants and allocation
of stationDec 2016 Discussions completed. 11 Applicants
selected
4 Engineering of Pilot test Sept 2017 Approximately 6 months required.
Start of Test expected by September 20175 Supply of material
6 Erection of Pilot plant
7 Integration with the unit (Depend on shut down of unit)*
8 Collection of test data and Analysis of the test result March 2018 6-12 months continuous test is required.
9 Declaration of outcome of the test June 2018 Final Results by June 2018 & then Action
Plan
De Nox Action Plan:
In order to check the suitability of SCR technology for high ash and abrasive ash, SCR pilot test studies is beingundertaken at NTPC running stations to check the suitability of SCR system for High ash Indian Coal and resultsof same are expected to come by March 2018. Planning/strategies shall be decided after the SCR pilot testresult.
De Nox Pilot plant Testing Schedule:-
NOX Emissions Control
SCR/ SNCR system allocated to NTPC station for carrying out pilot test of SCR/ SNCR
system
Total- 11 SCR tests and 3 SNCR tests
S No Name of Applicant SCR/SNCR Test Allocated NTPC Station
1 BHEL 2 nos. SCR test Simhadri (U#1)
2 GE- Alstom 1 no. SCR & 1 no. SNCR Vindhyachal (U#13)
3 MHPS 1 no. SCR test Sipat (U#4)
4 Termokimik Italy 1 no. SCR Singrauli (U#6/7)
5 Shanghai 1 no. SCR Talcher (U#6)
6 Andritz 1 no. SCR Korba (U#7)
7 ERC 1 no. SNCR Korba (U#7)
8 Yara Norway 1 no. SCR & 1 no. SNCR Rihand (U#4)
9 Thermax B&W 1 no. SCR Ramagundam (U#7)
10 Doosan 1 no. SCR Kahalgaon (U#7)
NOx emission control: Tentative Plan (after Pilot Test results)
De-NOx Plan-NTPC131 Units
60 GW
Limit: 600 mg/Nm3
Combustion Modification (CM)for units installed Before 2003
52 units/17 GW
Limit: 100 mg/Nm3
SCR/Hybrid system for units installed after Jan 2017
(planned after successful SCR pilot test)
35 Units/22 GW
Limit: 300 mg/Nm3
CM + SNCR for units installed Between 2004 to Dec 2016
(planned after successful SNCR testing)
44 Units/21 GW
SCR De-NOx system in Patratu (3 X 800 MW) will be ordered under EPC for compliance of New Norm.SCR included in future tenders of TTPS-III (2 X 660 MW) & SSTPP-III (2 X 660 MW)
Total 159 Units of 65 GWPhasing out 25 Units of 2.4 GW
SCR Tendering done in Patratu (3 X 800 MW)
Coal
• USC/AUSC Units
• CCS & Utilisation
• Flexibilization
• Pollution Control
• Ash Utilization
Renewable
• Wind & Solar
• Battery Storage
• Bio-Mass
• Geo-Thermal
Hydro & Nuclear
• Hydro
• Pumped Storage
• Nuclear• Electric Vehicles
• Charging Stations
• Storage Solutions
• Manufacturing
• EPC Solutions
EV
Storage
Renewable
EPC
• WtE Plants
• Energy Conservation
• Green Buildings
WtE
EC
GB
Future Business Areas