+ All Categories
Home > Documents > PE Welding • Electro Fusion • Pressure Testing Steve Gordon · PE Welding • Electro Fusion...

PE Welding • Electro Fusion • Pressure Testing Steve Gordon · PE Welding • Electro Fusion...

Date post: 26-Aug-2018
Category:
Upload: trandieu
View: 232 times
Download: 7 times
Share this document with a friend
32
Utilities - Continual Improvement PE Welding Electro Fusion Pressure Testing Steve Gordon
Transcript

Utilities - Continual Improvement

PE Welding

• Electro Fusion

• Pressure Testing

Steve Gordon

PE Jointing Fusion Welding

Electrofusion Welding of PE

Ideally, this System Should perform like this:

Service Failures of Electrofusion Joints

And not this:

Electrofusion Fitting Failures

• Majority of problems seen are:

• Unsatisfactory training• Poor welding practices: Clamping (Misalignment),

Scraping, Moisture and Contamination• Poor or unsuitable equipment• Excessive pipe ovality

Training perception of trench welding?

Reality

…. in Summer

Understanding Electro Fusion Welding Principles

• Prepare

• Align

• Cook

• Cool

Why do we scrape pe pipes?

Pigmentation

UV Stabiliser Packages

Oxidisation 1,2,3

SCRAPING

What type is suitable?

PREFERRED METHOD

Mechanical scrapers provide a uniformed removal of between 0.2 to 0.4mm during pipe end preparation

Hand Scraping

CONTAMINATION

CONTAMINATION

When contamination is present on the pipe or coupler, fusion becomes increasing more difficult to achieve!

WIS 4 32 08

>75% Ductile and K > 1.7 Pass Satisfactory

<75% Ductile and K > 1.7 Technical failure Problems very unlikely

<75% Ductile and 1.2<K<1.7 Non-critical failure Problems unlikely

<75% ductile and K < 1.2 Critical failure Problems likely

CONTAMINATION

The use of protective shelters prevents additional contamination entering the

jointing area!

ALIGNMENT - OVALITY

Suitable alignment clamps can assist with re-rounding of

pipe

MISALIGNMENT

MISALIGNMENT

5

Pipe misaligned into EF fitting

During fusion heat & pressure create movement of wires

MISALIGNMENT

6,7,8

Clamping/ Misalignment• Misalignment• Wire movement• Overheating

Why Audit – what do we find?

Improving Site Quality

• Site PE Audits, Testing and coaching• Giving clients and partners an understanding of the quality being installed. • Highlights any potential failures

ENERGY GRAPH: DUCTILE JOINT

Elongation (mm)

Forc

e (N

)

16,17,18,19

ENERGY GRAPH: BRITTLE JOINT

Elongation (mm)

Forc

e (N

)

20,21,22

Lab UKAS Schedule –Failure Investigation

Pressure Testing

Type 2 Test Analysis

n< 0.04

0.04 < n < 0.050.05 < n < 0.080.08 < n < 0.10

n > 0.10

AssessmentAir Indicated

Pass Compacted GroundPass Intermediate Ground

Pass Exposed PipeLeakage Indicated

Expected PE Decay Curves

Decay Time/ Pressurisation Time = Regression Time

HPPE (PE100) SDR 11 (16 bar)

16

17

18

19

20

21

22

23

24

0 2 4 6 8 10 12 14 16

Pres

sure

(bar

)

Leak Suspected

Air Suspected

Compacted

Intermediate

Without constraint

0.04

0.05

0.08

0.10

Slipline/ PIM

Backfilled

DecaySlopes

Type 2 Test: Analysis

0

5

10

15

20

0 20 40 60 80 100 120 140 160Elapsed Test Time (min)

Pres

sure

(bar

)

RampTime

1 x 8 x 20 x

n1 n2

Pressure Test Equipment: Loggers

GPS Data Log Technology (ANT Hire)•No more down time for operator as test is remotely accessed•Remote dialling access allows instant results for critical tests •Validation of test data and location is confirmed•Individual web access (paper-less trail) Professional analysis at lower costs (Exova)

Pressure Test

Thank you

Questions?


Recommended