PEMBROKE STUDIOS

PROGRESS REPORT

AUGUST 2016

Page 2: Pembroke Studios Progress Report August 2016

Internal stripping and removal of asbestos

Page 3: Pembroke Studios Progress Report August 2016
Page 4: Pembroke Studios Progress Report August 2016

Removal of all timber stud and plasterboard ,

including all ceilings

All debris to be removed from the premises in preparation for ground works.

Page 5: Pembroke Studios Progress Report August 2016

Trial excavations to prove solid bedrock , suitable to

cast concrete bases accommodating steel uprights

All excavations have been inspected by Emile Sanan, the Structural Engineer appointed by YPG Developments Ltd

Page 6: Pembroke Studios Progress Report August 2016