Prepared by:
ARMEL S. ALVAREZOfficer In-Charge
Recommending Approval:
ALBERTO E. MAÑUSVISMIN OpCen Head
Approved by:
MARIO C. MONSALVECOG 1 - HEAD
DAN M. ABANDOMDC - PRESIDENT
OUTLINE OF PRESENTATION
INTEGRATION PROJECT CHARTER LOCATION MAP
SCOPE PROJECT BRIEF
16 ELEMENTS OF EXECUTION PLANNING PROGRAMMING & PLANNING PROJECT TABLE OF ORGANIZATION SAFETY PROCEDURES AND INSPECTIONS QA/QC & INSPECTION PROCEDURES DESIGN REVIEW, COORDINATION AND DETAILING BUILDING SERVICES ENGINEERING/ COORDINATION BUILDING INFORMATION MODELING & COORDINATED SERVICES DRAWINGS BUILDABILITY, VALUE ENGINEERING AND INNOVATION CONSTRUCTION METHODS & TEMPORARY WORKS CONSTRUCTION PHASING AND SITE LOGISTICS PROCUREMENT WORKS PACKAGING AND PROCUREMENT MANAGEMENT COMMERCIAL INPUT ON SUBCONTRACT / SUPPLY CONDITIONS
PROJECT OPERATING BUDGET SUSTAINABILITY, CSR AND ENVIRONMENT RISK MANAGEMENT
PROJECT CHARTER
PROJECT TITLE : CENTRIO TOWERPROJECT OWNER : CDO GATEWAY CORP.
DESIGNERS/CONSULTANTS:
Architectural : G&W Architects,
Engineers & Consultants
Structural : Sy^2 + Associates
Mechanical/Fire Protection : RD Aguilos
Plumbing/Sanitary : CL Madriaga Engineers
Electrical Consultant : IRAIDO Tech. Leader, Inc
GENERAL CONTRACTOR : Makati Development Corp.
ESTIMATED PROJECT COST : Php 702 065 382.85 (3 flrs Podium + 21 flrs Residential)
CENTRIO TOWER PROJECT
AVIDA TOWER ASPIRA
CORRALES A
VENUE
CORRALES A
VENUE
RAMON CHAVEZ STREET
RAMON CHAVEZ STREET
THIS SITE
GEN LUNASTREETGEN LUNASTREET
J. EBARLE STREET
J. EBARLE STREET
J RIVERA STREET
J RIVERA STREET
LOCATION MAP
CENTRIO MALL
PROJECT BRIEF
Lot Area : 3,936.14 m2
Gross Floor Area (GFA) : 20,641.53 m2
Covered Floor Area (CFA) : 25,450.83 m2
Net Saleable Area (NSA) : 15,881.98 m2
Gross Leasable Area (GLA) : 133.34 m2
Gross Parking Area (GPA) : 4,809.30 m2
Residential Gross Floor Area (RGFA)
: 20,304.16 m2
Building Efficiency : 62.93 % (NSA+GLA/CFA)
Residential Footprint Efficiency
: 78.22% (NSA / RGFA)
No. of Floors : 24 Floors (Ground floor to Roof Deck)
Parking :2 Floors ( Ground Floor to Second
Floor)
Amenities / Residential : 1 Floor (3rd floor)
Residential Floors :3rd Floor to 23rd Floor (21 floors)
Residential Units
Studio : 292 Units (55.94%)
1 Bedroom : 188 Units (36.02%)
2 Bedrooms : 42 Units (8.05%)
TOTAL : 522 Units
PROGRAMMING AND PLANNING
DESIGN UPDATES
MILESTONES
PROJECT SCHEDULE
1/16 PROGRAMMING AND PLANNING1/16 PROGRAMMING AND PLANNING
1/16 DESIGN UPDATES
ACTIVITYMILESTONE DATES STATUS /
REMARKSTARGET ACTUAL
GROUND BREAKING Feb. 19, 2013 DONE
BORED PILE July 19, 2013 July 11, 2013 DONE
COMPLETION OF EXCAVATION June 4, 2014
NTP AWARD OF SUPERSTRUCTURE July 30, 2013 Dec. 12, 2013 DONE
FIRST CONCRETE POURING April 7, 2014
TOPPING OFF May 14, 2015
WATER TIGHTNESS July. 22, 2015
TESTING AND COMMISIONING Dec 15, 2015
ENERGIZATION OF PERMANENT POWER
Dec 20, 2015
PERMANENT WATER CONNECTION Nov 15, 2015
ELEVATOR OPERATION November 15, 2015
1/16 MILESTONES
1/16 MILESTONES
ACTIVITY
MILESTONE DATES STATUS / REMARKS
TARGET ACTUAL
START OF HANDOVER TO OWNER & CRU March 15, 2016
FIRE SAFETY AND INSPECTION CERTIFICATE (FSIC)June 10, 2016
OCCUPANCY PERMIT January 15, 2016
PROJECT COMPLETION / HANDOVER TO AVIDA December 20, 2016
PROJECT TECHNICAL CLOSE-OUT March 20, 2017
PROJECT FINANCIAL CLOSE-OUT May 20, 2017
2/16 PROJECT SCHEDULE
BID RESULT
MDC BUDGET MOMENTUM ACTUATE ARN BUILDERS
62,252,141.05 106,257,047.64 131,642,032.30 337,964,330.13
2/16 PROJECT TABLE OF ORGANIZATION
TABLE OF ORGANIZATION
MANPOWER SCHEDULE
2/16 CENTRIO TOWER TABLE OF ORGANIZATION
CONCRETE ENGRLITO BITANTOS
CONCRETE ENGRLITO BITANTOS
FORMWORKS ENGRRYAN E. ILOGON
FORMWORKS ENGRRYAN E. ILOGON
UTILITYR. R. BOYLES
UTILITYR. R. BOYLES
DRIVERC.O. MANDAL
DRIVERC.O. MANDAL
WAREHOUSEMANAL C. MAGHANOYWAREHOUSEMANAL C. MAGHANOY
DOCS CONTROLLERDM MASLA
DOCS CONTROLLERDM MASLA
TIMEKEEPERTBA
TIMEKEEPERTBA
COG 1 HEADM. C. MONSALVE
COG 1 HEADM. C. MONSALVE
VISMIN OPCEN HEADA. E. MAÑUS
VISMIN OPCEN HEADA. E. MAÑUS
EQUIPMENT ENGR.EQUIPMENT ENGR.
QUANTITY SURVEYORL. D. NACALABAN
QUANTITY SURVEYORL. D. NACALABAN
CG VISMIN OPCENMA. FE TRACES
CG VISMIN OPCENMA. FE TRACES
ASS. QUANTITY SURVEYORE.B. AMORES
ASS. QUANTITY SURVEYORE.B. AMORES
Q.S. DEPT.Q.S. DEPT.
PLANNING HEADI.S. SUERTE
PLANNING HEADI.S. SUERTE
ARCHITECTURALJETHRO VILLAROJO
ARCHITECTURALJETHRO VILLAROJO
CADD OPERATORC.A. GASATAYA
CADD OPERATORC.A. GASATAYA
MEPF TBA
MEPF TBA
CADD OPERATORCARL ALABA
CADD OPERATORCARL ALABA
DOCTORTBH
DOCTORTBH
IT SPECIALISTTBA
IT SPECIALISTTBA
ASST.ADMIN. OFFICER IRISH P. LOMO
ASST.ADMIN. OFFICER IRISH P. LOMO
GEOGRAPHICAL / SUPPORT TEAM
LEGEND:
ADMIN DEPT.ADMIN DEPT.
TSD - COORDINATORRALPH LAO
TSD - COORDINATORRALPH LAO
MAINTENANCE TEAM MAINTENANCE TEAM
ACCOUNTING DEPT.ACCOUNTING DEPT.
PROJECT CONTROLLER(CONCURRENT)C.T. INDIANO
PROJECT CONTROLLER(CONCURRENT)C.T. INDIANO
VISMIN CRFGC.T. INDIANOVISMIN CRFGC.T. INDIANO
OPCEN BASED (SHARED)
CDO BASED (SHARED)
PROJECT BASED
For Hiring/Replacement
Hired
PURCHASING SPECIALISTTBA
PURCHASING SPECIALISTTBA
T.S.D. DEPT. EHS DEPT.
EHS SUPERVISORS. A. TORRES
EHS SUPERVISORS. A. TORRES
PROJECT NURSEJ. D. TAPPOL
PROJECT NURSEJ. D. TAPPOL
SAFETY OFFICERTBH
SAFETY OFFICERTBH
SAFETY OFFICERTBA
SAFETY OFFICERTBA
EQUIPMENT / MAINTENANCE HEAD
EQUIPMENT / MAINTENANCE HEAD
CQC SURVEY TEAM M.E.F.P.
PURCHASING
BY THIRD PARTYBY THIRD PARTY SURVEY HEADE. SINGAYAN
SURVEY HEADE. SINGAYAN
SURVEY AIDEA.B. BLANILASURVEY AIDEA.B. BLANILA
SURVEY AIDEA.C. AJAN
SURVEY AIDEA.C. AJAN
MEFP HEADTBH
MEFP HEADTBH
ELECTRICAL/AUX.TBH
ELECTRICAL/AUX.TBH
PROJECT SUPERINTENDENTTBN
PROJECT SUPERINTENDENTTBN
REBAR ENGRTBH
REBAR ENGRTBH
CONCRETE ENGRTBH
CONCRETE ENGRTBH
E.C.P.D.
PROJECT MANAGERTBH
PROJECT MANAGERTBH
PROJECT IN CHARGEA. S. ALVAREZ
PROJECT IN CHARGEA. S. ALVAREZ
QA DEPT.
QUANTITY ASSURANCER. G. RODRIGUEZ
QUANTITY ASSURANCER. G. RODRIGUEZ
ASST. QUALITY ASSURANCETBH
ASST. QUALITY ASSURANCETBH
VISMIN COSGBENJAMIN JOSEVISMIN COSG
BENJAMIN JOSE
WAREHOUSE AIDER. Q. MABAGAL
WAREHOUSE AIDER. Q. MABAGAL
GENERAL FOREMANLIBRANDO REPUELAGENERAL FOREMANLIBRANDO REPUELA
FOREMANANGELITO SALIGUMBA
FOREMANANGELITO SALIGUMBA
FOREMAN ARTHUR ANJAO
FOREMAN ARTHUR ANJAO
Required - 41 Hired - 24 Balance - 17
As of April 28, 2014
2/16 MANPOWER SCHEDULE
2014 2015 2016
2/16 MANPOWER SCHEDULE2014 2015 2016
3/16 SAFETY PROCEDURES AND INSPECTION
SAFETY PROCEDURES AND INSPECTION
FIRE SAFETY SECURITY MEASURES DELIVERY PROCEDURES EXISTING EXTERIOR BOARD UP/ FENCE SAFETY NET SEQUENCE
SAFETY PROCEDURES AND INSPECTION
FIRE SAFETY SECURITY MEASURES DELIVERY PROCEDURES EXISTING EXTERIOR BOARD UP/ FENCE SAFETY NET SEQUENCE
SAFETY MEASURES
The following Safety measures shall be strictly implemented:
Provide standard road signs where heavy equipment and trucks will be crossing.
Material Safety Data Sheet (MSDS) shall be submitted by the subcontractors for approval prior to work execution.
The subcontractors shall be responsible for providing the necessary personal protective equipment (PPE) as deemed required by their work scope.
The subcontractors shall observed the safety rules and regulations being implemented by MDC while inside the project site.
3/16 SAFETY PROCEDURES AND INSPECTION
FIRE SAFETY
2 x 5-kg capacity dry chemical (multi-purpose) fire extinguisher shall be provided whenever necessary within the construction site. One (1) fire extinguisher for every equipment (i.e., generators, welding machine, gas cutting, etc.) shall be provided.
A fire watch/safety enforcer shall be provided in areas where welding and gas cutting activities are being performed. Water supply and distribution facilities for fire fighting purposes shall be provided at construction site.
Smoking shall be prohibited within the construction premises except at the designated smoking area.
3/16 SAFETY PROCEDURES AND INSPECTION
SECURITY MEASURESThe following Security Measures shall be strictly implemented:
• Workers will be required to wear Identification cards and color coded uniforms before entering and while inside the construction site.
• All contractors shall assign skeletal forces during holiday seasons.
• Workers are prohibited from loitering inside and within the periphery of the project site.
• Dayshift and nightshift guards shall be posted in strategic locations inside the premises to:o Check and report any person seen loitering during and after
working hourso Check and report any unauthorized usage of equipmento Conduct regular inspection within the project premises and
report any violation of the house rules and regulations.• In addition, all security guards are required to frisk all
employees & workers entering and leaving the project site for security reasons.
3/16 SAFETY PROCEDURES AND INSPECTION
3/16 SAFETY PROCEDURES AND INSPECTION
DELIVERY PROCEDURES
All delivery vehicles shall be allowed access only through
the construction gate along Corrales Avenue.
Security Guard at the gate shall log the delivery details and
communicate with MDC for proper unloading, hauling and
warehousing.
EXISTING EXTERIOR BOARD UP/FENCE
CENTRIO MALL
SEDA
Residential area made of light
weight materialsCENTRIO TOWER
CORRALES AVENUE
VIEW FROM CENTRIO STP
VIEW FROM CORRALES AVE.
VIEW FROM CORNER CORRALES AVE. & CENTRIO
PARKING ENTRANCE
VIEW FROM CENTRIO PARKING ENTRANCE
3/16 SAFETY PROCEDURES AND INSPECTION
SAFETY NET 3/16
SAFETY NET
4/16 QA/QC & INSPECTION PROCEDURES
INITIAL PHASE (1ST CONTROL)
INTERMEDIATE PHASE (2ND CONTROL)
FINAL PHASE (3RD CONTROL)
CURING TANK
QA/QC & INSPECTION PROCEDURESQA/QC & INSPECTION PROCEDURES
INITIAL PHASE (1st CONTROL)
startstart
SUB –CONTRACTOR TO PREPARE SUBMITTAL REVIEW FORM:1.Material Samples2.Testing Certificates3.Installation Methodology4.Tolerances5.Equipment Requirement6.Hazard Analysis7.Forms8.Schedules
SUB –CONTRACTOR TO PREPARE SUBMITTAL REVIEW FORM:1.Material Samples2.Testing Certificates3.Installation Methodology4.Tolerances5.Equipment Requirement6.Hazard Analysis7.Forms8.Schedules
DOCUMENT CONTROLLER to
receive submittals and logs.
DOCUMENT CONTROLLER to
receive submittals and logs.
QA / QC to review, verify and
comment if submittal is as per approved plans
and specifications.
QA / QC to review, verify and
comment if submittal is as per approved plans
and specifications.
PROJECT MANAGER / PIC
to review and forwards to CONSULTANT for
APPROVAL.
PROJECT MANAGER / PIC
to review and forwards to CONSULTANT for
APPROVAL.
APPROVED?APPROVED?
SUBCONTRACTOR may proceed to
work
SUBCONTRACTOR may proceed to
work
QA / QC to verify comments and forward to SUB CONTRACTOR
QA / QC to verify comments and forward to SUB CONTRACTOR
YES
NO
endend
PM / PIC reviews and evaluates comments
PM / PIC reviews and evaluates comments
4/16 QA/QC & INSPECTION PROCEDURES
4/16 QA/QC & INSPECTION PROCEDURES
INTERMEDIATE PHASE (2nd CONTROL)
startstart SUB –CONTRACTOR TO PREPARE WORK REQUEST / WORK INSPECTION REQUEST1.Structural / Civil Works2.Others
SUB –CONTRACTOR TO PREPARE WORK REQUEST / WORK INSPECTION REQUEST1.Structural / Civil Works2.Others
DOCUMENT CONTROLLER to receive and logs.
DOCUMENT CONTROLLER to receive and logs.
FIELD OPERATION GROUP (FOG/MDC) to check and verify
FIELD OPERATION GROUP (FOG/MDC) to check and verify
QA / QC to check and verify if work is done as per approved plan and specifications.
QA / QC to check and verify if work is done as per approved plan and specifications.
APPROVED?APPROVED?
YES
NO
FOG to check and verify if rectifications works is done as per plan and specification
FOG to check and verify if rectifications works is done as per plan and specification
SUB CONTRACTOR to rectify and repair comments
SUB CONTRACTOR to rectify and repair comments
SUB-CONTRACTOR TO PROCEED WORKSUB-CONTRACTOR TO PROCEED WORK
endend
PROJECT MANAGER / PIC to review and verifyPROJECT MANAGER / PIC to review and verify
4/16 QA/QC & INSPECTION PROCEDURES
FINAL PHASE (3rd CONTROL)
startstart
SUB –CONTRACTOR to submit WORK ACTIVITY COMPLETION REPORT
SUB –CONTRACTOR to submit WORK ACTIVITY COMPLETION REPORT
APPROVED?APPROVED?
YES
NO
FIELD OPERATION GROUP (MDC) to check and verify
FIELD OPERATION GROUP (MDC) to check and verify
DOCUMENT CONTROLLER to receive submittals and logs.
DOCUMENT CONTROLLER to receive submittals and logs.
QA / QC to check and verify if work is done as per approved plan and specifications.
QA / QC to check and verify if work is done as per approved plan and specifications.
QA / QC to issue PUNCHLIST or
DEFECT list
QA / QC to issue PUNCHLIST or
DEFECT list
PROJECT MANAGER / PIC approves and forward PUNCHLIST to Sub-Contractor for rectification.
PROJECT MANAGER / PIC approves and forward PUNCHLIST to Sub-Contractor for rectification.
SUB-CONTRACTOR to rectify items in the PUNCHLIST / DEFECT list.
SUB-CONTRACTOR to rectify items in the PUNCHLIST / DEFECT list.
FOG checks and verify if work is rectified and forward to QA/QC
FOG checks and verify if work is rectified and forward to QA/QC
PROJECT MANAGER / PIC issues Work Activity Completion
PROJECT MANAGER / PIC issues Work Activity Completion
endend
2.5m
3.0m
4.0mEXISTING WALL
6MM Ǿ - 50X50 WIREMESH WALL
1.0m
3.0m CURING TANK
4/16 PROPOSED SAMPLE ROOM FOR CURING TANK
1.0m
3.0m
4/16 PROPOSED CURING TANK
1.2m
3.0m 2.0m
4/16 PROPOSED FORMS ACCESSORIES STOCKING PER FLOOR
5/16 DESIGN REVIEW, COORDINATION & DETAILING
Continue review of plans and coordination of approved
construction drawings and detailing prior to implementation at site.
DESIGN REVIEW, COORDINATION & DETAILING DESIGN REVIEW, COORDINATION & DETAILING
6/16 DESIGN REVIEW, COORDINATION AND DETAILING
Conflicts,Clashes &
Incomplete Details
Conflicts,Clashes &
Incomplete Details
MDC/SubcontractorsTo Formulate Solutions and Shop drawings
MDC/SubcontractorsTo Formulate Solutions and Shop drawings
Approval By MDC
Engineering, Consultants
& APMC
Approval By MDC
Engineering, Consultants
& APMC
YES
Seek alternative Solutions
& IncorporateComments of MDC Eng’g. & Consultants
Seek alternative Solutions
& IncorporateComments of MDC Eng’g. & Consultants
ImplementationImplementation
YES
NO
NO
Approved Resolution
& Drawings should
be signed by
MDC Eng’g., Consultants
& APMC
Approved Resolution
& Drawings should
be signed by
MDC Eng’g., Consultants
& APMC
Review FCD Plans/Drawings(by MDC Operation &
Subcontractors)
Review FCD Plans/Drawings(by MDC Operation &
Subcontractors)
7/16 ELEMENTS OF EXECUTION PLANNING
COG1 will coordinate with the planning and design team by
providing information relevant to architectural and engineering
works that need to be incorporated into the design (e.g. existing
location of tapping points for water supply, sewers, power
supply, actual survey data).
COG1 will also provide the planning and design team with local
regulatory requirements such as those of local utility providers
and local government unit (LGU) that will affect the building
services design.
BUILDING SERVICES ENGINEERING / COORDINATIONBUILDING SERVICES ENGINEERING / COORDINATION
7/16 ELEMENTS OF EXECUTION PLANNING
BUILDING INFORMATION MODELLING• Bored piles, pile caps, mat footings and columns will
be modelled using BIM software to eliminate conflicts and
ensure correct calumniation.
• MEPFS will be modelled also using BIM software to
eliminate conflicts/clashes such as Electrical
pipes, Plumbing/Sanitary pipes and Mechanical ducting.
BUILDING INFORMATION MODELLING & COORDINATED SERVICES DRAWINGSBUILDING INFORMATION MODELLING & COORDINATED SERVICES DRAWINGS
8/16 ELEMENTS OF EXECUTION PLANNING
BUILDABILITY, VALUE ENGINEERING & INNOVATIONBUILDABILITY, VALUE ENGINEERING & INNOVATIONReview of the design as to buildability and efficiency, with
careful analysis on the compatibility of the design with
structural, architectural and building services.
Apply value engineering with innovative construction
methodologies not just to lessen cost but to expedite
completion of the project
9/16 ELEMENTS OF EXECUTION PLANNING
FORMWORKS CONCRETING SEQUENCE
STRUCTURAL EXCAVATION SEQUENCE
FOUNDATION POURING SEQUENCE
CONCRETING OF GOUND FLOOR
EXTERIOR PC WALLS
STRUCTURAL CONCRETING SEQUENCE
CONSTRUCTION METHODS AND TEMPORARY WORKSCONSTRUCTION METHODS AND TEMPORARY WORKS
9/16 STRUCTURAL EXCAVATION SEQUENCE
9/16 FOUNDATION POURING SEQUENCE
RETAINING WALLVOL = 76.36m3April 20, 2014
RETAINING WALLVOL = 76.36m3April 20, 2014
9/16 FORMWORKS & CONCRETING SEQUENCE
Total Translab Area = 20,065.50 m2
PODIUM (GND & 3fr FLRS) 2 FLOORSTotal Floor Area = 5,684.94 m2
Slab Concrete Total Volume = 5,402.68 m3Slab Concrete Total Volume/floor = 234.89 m3Pouring Cycle = 2 floors/month
Total Contact Formworks Area = 61,173.73 m2Total Formworks Equipment to be provided= 3164 m2
9/16 CONCRETING OF GROUND FLOOR
CRANE FOUNDATIONINITIAL JACKUP: 7DAYS
GF: APRIL 11, 2014
2ND :JUNE 10, 2014
4TH JACKUP: 2DAYS
3RD JACKUP: 2DAYS
1ST JACKUP: 2 DAYS
`
```
4TH : AUG. 1, 2014
8TH : SEPT 18, 2014
6TH : SEPT 6, 2014
``
2ND JACKUP: 2 DAYS
TOPPING OFF(MARCH 14,
2015)
3RD : JULY 20, 2014
12TH : NOV. 5, 2014
10TH : OCT. 12, 2014
15TH : NOV. 29, 2014
17TH : DEC. 23, 2014
21ST :FEB 9, 2015
19TH : JAN 16, 2015
`
23rd: March 5, 2015
GF: NOV 8, 2014
2ND: NOV 20, 2014
4TH : DEC 26, 2014
8TH : FEB 21, 2015
6TH : JAN 24, 2015
3RD : DEC 10, 2014
17TH : JUNE 20, 2015
10TH : MAR 24, 2015
19TH : JULY 21, 2015
21ST : AUG 15, 2015
24TH : OCT 1, 2015
23RD :SEP 16, 2015
15TH : MAY 23, 2015
12TH : APRIL 22, 2015
GF2ND
3RD 4TH 5TH 6TH 7TH 8TH 9TH 10TH 11TH 12TH 14TH 15TH 16TH 17TH 18TH 19TH 20TH
23RD 22TH 21TH
RD RD : March 14, 2015
RD : OCT 15, 2015
STRUCTURALARCHITECTURAL
PRECAST AND
CONCRETE CYCLE: 15
DAYS/FLOOR
10/16 STRUCTURAL CONCRETING SEQUENCE
``
``
``
9/16 EXTERIOR PC WALL PANELSL PANELS
10/16 ELEMENTS OF EXECUTION PLANNING
LOGISTIC & TOWER CRANE LAYOUT PLAN
VEHICULAR TRAFFIC FLOW
FORMS, REBAR AND CONCRETE USAGE
EQUIPMENT SCHEDULE
CONSTRUCTION PHASING, TOWER CRANES & SITE LOGISTICS
CONSTRUCTION PHASING, TOWER CRANES & SITE LOGISTICS
10/16 LOGISTIC AND TOWER CRANE LAYOUT
CORR
ALES
AVE
NU
E
AREA
(5.0) P. 1 of 2
GUARD HOUSEGUARD HOUSE
POWER HOUSEPOWER HOUSE
REBAR REBAR FABRICATIONFABRICATION
Residential Area made of Light weight materials
Existing CHB Fence
WAITING AREAWAITING AREA
CLINICCLINICTEMFACILTEMFACIL
PEDESTRIANPEDESTRIAN
ENTRANCE / EXITENTRANCE / EXIT
REBAR FABRICATIONREBAR FABRICATION
TOW
ERAREA Internal Climbing TOWER CRANE (Luffing-Type)
50M JIB (Max. load 10T & Tip load 3T)
4m
9.3m
4m
24mPRECAST CASTING BEDPRECAST CASTING BED
5/16 CONSTRUCTION PHASING AND SITE LOGISTICS
CAPITOL ROAD
Residential Area made of Light weight materials
Res
iden
tial
Are
a
CO
RR
AL
ES
AV
EN
UE
(5.0) P. 2 of 2
VEHICULAR TRAFFIC FLOW OF DELIVERIES OF MATERIALS ON SITE
TOW
ERAREA
10/16 CONSTRUCTION PHASING AND SITE LOGISTICS
REBARS AND CONCRETE USAGE
10/16 CONSTRUCTION PHASING AND SITE LOGISTICS
Item Equipment Qty Start Finish Remarks/Usage
A Luffing Tower Crane 1 March 30, 2014 Coming from Davao Project
B Mobile Crane 25T 1 March 15, 2014 Material Lifting
C Construction Elevator 1 Nov. 2, 2014 Material lifting and
workers
E Service Vehicle 1 Feb. 1, 2013 Day to day transportation requirement
F Generator 300kva 1 June 1, 2014 For emergency brown-out
G Transformer 100kva 3 Feb. 14, 2014 For construction use
EQUIPMENT SCHEDULE
11/16 ELEMENTS OF EXECUTION PLANNING
PROCUREMENT PROCESS FLOW
PROCUREMENTPROCUREMENT
11/16 PROCUREMENT PROCESS FLOW
PROCUREMENT STRATEGY
PROCUREMENT STRATEGY & SCHEDULE
12/16 ELEMENTS OF EXECUTION PLANNING
WORKS PACKAGING & PROCUREMENT MANAGEMENTWORKS PACKAGING & PROCUREMENT MANAGEMENT
ITEMS EXCAVATIONCIVIL /
STRUCTURALARCHITECTURAL MEPF
STATUS DONE SELF PERFORMSELF
PERFORM/SUBCON
AWAITING AWARD FROM AVIDA
MDC CONTRACT
EXCAVATION WORKS
SOIL TREATMENTARCHITECTURAL
WORKSMEPF WORKS
ARN BULIDERSACTUATEAV PAMATONGMomentumSelf Perform
PAPER BID PAPER BID PAPER BID PAPER BID PAPER BID
CIVIL/STRUCTURAL WORKS
MECHANICAL
ELECTRICAL
PLUMBING AND FIRE PROTECTION
12/16 PROCUREMENT STRATEGY
Energy & Building App. Powerline Controls Elec.Energy Factors, Inc.Electrolyte Engineering
Marguad Trading Alpa Plumbing Works Inc.Universal MacrotechTriplewell Construction
Triplewell Con. Corp.CDM
HNHKEVLARNOVICEJS ASSOCIATE
13/16 PROCUREMENT STRATEGY & SCHEDULE
PROJECT :AVIDA CENTRIO TOWERLOCATION :CORRALES AVENUE, CAGAYAN DE ORO CITY
SUBJECT :WORK PROCUREMENT PACKAGES - CIVIL/STRUCTURAL WORKSas of :3/8/2014
CONTRACT PACKAGE WORK PACKAGES CONTRACTORS/SUPPLIERS PROCUREMENT
STRATEGYTARGET DATE
OF AWARD STATUS
FIXED LUM SUM (FLS)
CP-FLS-1 Construction of TemfacilHNH BUILDERS
PAPER BID 1/26/2014 AWARDEDNOVICE CORPORATIONJS ASSOCIATES
CP-FLS-2 Construction of Crane FoundationHNH BUILDERS
PAPER BID 1/26/2014 AWARDEDNOVICE CORPORATIONJS ASSOCIATES
CP-FLS-3
Excavation and Disposal
Pile Hacking and Disposal
HNH BUILDERS
PAPER BID 1/26/2014 AWARDED NOVICE CORPORATION
JS ASSOCIATES
CP-FLS-4
Clearing and Grubbing Backfilling and Compaction of
Imported Materials Base Course -
Imported Materials - filling to beds Formworks
Installation Fabrication and Installation of Rebars Polythelene Sheet Cast in Place Concrete
STP AND CISTERN TANK CIVIL WORKS EXCL. ELECROMECH Concrete Accessories Pre-cast Wheel Stops
Cementitous Deck and underlament, Concrete Toppings STRAIGHT TO FINISH WITH HARDENER
APPLICATION AND DUSTPROOFING Rubbed
Concrete with Skim Coat
ADMIN WORKERS ADMIN 1/26/2014 ON-GOING HIRING
LEGEND: Regular Vendor
Not seen in Vendor Search
Prospective New/Reactivate Vendor
Admin
13/16 PROCUREMENT STRATEGY & SCHEDULE
CP-FLS-5 SOIL TREATMENT WORKS
GEN PEST MANAGEMENT SERVICES
PARTNERING 4/23/2014
CP-FLS-5
THERMAL & MOISTURE PROTECTION Damproofing
Polyethelene Sheet, min. 6mil thickness; To Slab on Grade
JAN OWEN MARTIN CONSTRUCTION CORPORATION
PAPER BID 3/30/2014
THI ENGINEERING SERVICESRICH-FREE TRADING &
DEVELOPMENTSHASTA
MULTI DEVELOPMENTDORON BUILDERS & CONSTRUCTION
SUPPLIESGLOSCORE PHILIPPINES CONSTRUCTION, INC.
AC TROJAN INDUSTRIES, INC.EC STRUCTURAL COMPOSITES, INC.GREEN BAY INDUSTRIAL TRADING
COMPANY
CP-FLS-6SUPPLY & DELIVERY OF READY MIXED CONCRETE
8,000 psi, 6,000 psi, 5,000 psi, 3,000 psi
GEO-TRANSPORT AND CONSTRUCTION, INC.
PAPER BID 1/26/2014 AWARDED HORIZON CONCRETE PRODUCTS,
CORP.AV PAMATONG
OMMIX
PROJECT :AVIDA CENTRIO TOWERLOCATION :CORRALES AVENUE, CAGAYAN DE ORO CITY
SUBJECT :WORK PROCUREMENT PACKAGES - CIVIL/STRUCTURAL WORKSas of :3/8/2014
CONTRACT PACKAGE WORK PACKAGES CONTRACTORS/SUPPLIERS PROCUREMENT
STRATEGYTARGET DATE
OF AWARD STATUS
FIXED LUM SUM (FLS)
LEGEND: Regular Vendor
Not seen in Vendor Search
Prospective New/Reactivate Vendor
Admin
13/16 PROCUREMENT STRATEGY & SCHEDULE
PROJECT :AVIDA CENTRIO TOWERLOCATION :CORRALES AVENUE, CAGAYAN DE ORO CITY
SUBJECT :WORK PROCUREMENT PACKAGES - CIVIL/STRUCTURAL WORKSas of :3/8/2014
CONTRACT PACKAGE WORK PACKAGES CONTRACTORS/SUPPLIERS PROCUREMENT
STRATEGYTARGET DATE
OF AWARD STATUS
FIXED LUM SUM (FLS)
LEGEND: Regular Vendor
Not seen in Vendor Search
Prospective New/Reactivate Vendor
Admin
CP-FLS-7
Cementitious Deck Supply of Hardener
JAN OWEN MARTIN CONSTRUCTION
CORPORATION
PAPER BID 5/10/2014
RICH-FREE TRADING & DEVELOPMENT
TRADETEK RESOURCES, INC.
REBTRADE INTERNATIONAL CORP.
CP-FLS-8 Supply of Skim Coat (Rubbed Concrete)
TECHNORESINS INDUSTRIAL INC.
PAPER BID 8/2/2014 MGS BESSER BLOCK, INC.NOVTEK CORPORATION
ERN CORPORATIONTECHNOTRUST CORP.
CP-FLS-9 Pre-cast Concrete Precast wheel stops ADMIN WORKERS ADMIN 5/31/2014
13/16 PROCUREMENT STRATEGY & SCHEDULE
PROJECT :AVIDA CENTRIO TOWERLOCATION :CORRALES AVENUE, CAGAYAN DE ORO CITY
SUBJECT :WORK PROCUREMENT PACKAGES - CIVIL/STRUCTURAL WORKSas of :3/8/2014
CONTRACT PACKAGE WORK PACKAGES CONTRACTORS/SUPPLIERS PROCUREMENT
STRATEGYTARGET DATE
OF AWARD STATUS
FIXED LUM SUM (FLS)
LEGEND: Regular Vendor
Not seen in Vendor Search
Prospective New/Reactivate Vendor
Admin
CP-FLS-10
Masonry Finishes-Plastering
INSTALLATION OF TILES INSTALLATION OF STEEL DOORS
Installation of Steel Doors with louvers
INSTALLATION OF WOOD DOORS INSTALLATION OF PVC DOORS
HNHKEVLAR
ADMIN WORKERSNOVICE
PAPER BID 05/9/2014
CP-FLS-11
METAL WORKS Structural Metal
Framing - Elevator Hoisting Beam Metal Fabrications Steel Grating - recommended manufacturer
WEBFORGE - Arch Specs pg 16
E.C. DAUGHSON, INC.
PAPER BID 05/30/2014
POWERBRIGHT ENTERPRISESPHILGLOBAL ASIA INDUSTRIAL
CORPORATIONSSI METAL
LRC TRADING & ENGINEERING SERVICES
DO ALL METAL INDUSTRIESGOMECO METAL
JEFF JAMESNORBENJAR ENTERPRISESMETRO STONERICH CORP.WEBFORGE PHILIPPINES
AMSTEELAVECS CORP.
CABRERA CONCEPT
13/16 PROCUREMENT STRATEGY & SCHEDULE
PROJECT :AVIDA CENTRIO TOWERLOCATION :CORRALES AVENUE, CAGAYAN DE ORO CITY
SUBJECT :WORK PROCUREMENT PACKAGES - CIVIL/STRUCTURAL WORKSas of :3/8/2014
CONTRACT PACKAGE WORK PACKAGES CONTRACTORS/SUPPLIERS PROCUREMENT
STRATEGYTARGET DATE
OF AWARD BIDDING
FIXED LUM SUM (FLS)
LEGEND: Regular Vendor
Not seen in Vendor Search
Prospective New/Reactivate Vendor
Admin
CP-FLS-12 SUPPLY AND INSTALLATION OF ALUMINUM SPANDREL
DN STEEL MARKETING ALI
Recommended Manufacturer/contractor Arch. Specs
page 48 PAPER BID 05/30/2014
UNION GALVASTEEL
PHILMETAL
CP-FLS-13
SUPPLY AND INSTALLATION OF GYPSUM BOARD - CEILING WORKS
12mm Thk Gypsum Board
12mm Thk Moisture Resistant Gypsum Board DRYWALL
WORKS Brand for Gypsum Board: BORAL
Arch. Specs page 85
REMACRIS BUILDERS
PAPER BID 05/30/2014
PZL CONSTRUCTION, INC.NOVELL STEEL
MAKATI COVER-ALL AND INTERIORS, INC.
ONEL BUILDERS RESOURCES, INC. (OBRI) (Needs to Update)
INSUPHIL INDUSTRIALLORETA RIGID URETHANE
INSULATIONKENT INTERNATIONAL
CK BUILDERS
CP-FLS-14
SUPPLY & INSTALLATION OF WALL COVERINGS EIFS
Dryvit Systems, Inc. or BASF Wall Systems Arch Specs pg 43
PIONEER
PAPER BID 05/30/2014 IRVINE
13/16 PROCUREMENT STRATEGY & SCHEDULE
PROJECT :AVIDA CENTRIO TOWERLOCATION :CORRALES AVENUE, CAGAYAN DE ORO CITY
SUBJECT :WORK PROCUREMENT PACKAGES - CIVIL/STRUCTURAL WORKSas of :3/8/2014
CONTRACT PACKAGE WORK PACKAGES CONTRACTORS/SUPPLIERS PROCUREMENT
STRATEGYTARGET DATE OF
AWARD STATUS
FIXED LUM SUM (FLS)
LEGEND: Regular Vendor
Not seen in Vendor Search
Prospective New/Reactivate Vendor
Admin
CP-FLS-15 SUPPLY AND INSTALLATION OF DIVIDERS AND PARTITIONS Urinal Partitions
JEBSEN International Trading Corp. ALI
Recommended Manufacturer/contractor
Arch. Specs page 99
FORMAL CANVASSING 05/30/2014
MULTI RICH HOME
CP-FLS-16 INSTALLATION OF T&B ACCESSORIES ADMIN WORKERS ADMIN 05/30/2014 CP-FLS-17 STP ELECTROMECHANICAL ECOSYSTEMS PARTNERING 05/30/2014
14/16 ELEMENTS OF EXECUTION PLANNING
PROJECT BUDGET
OPERATING PROJECT BUDGETOPERATING PROJECT BUDGET
14/16 OPERATING PROJECT BUDGET (AWARDED)
Proposed Contract Amount (FLS ONLY) 221,079,737.53
Proposed Contract Amount (VAT Exclusive) 197,392,622.79
Proposed OPB 172,576,169.61
Gross Operating Income (12.57%) 24,816,453.19
Indirect Cost (GAE 4.0%) 7,895,704.91
Net Income Before Tax (NIBT) 30% 16,920,748.28
Allowance for Corporate Taxes 5,076,224.48
Net Income After Tax (NIAT) 11,844,523.79
NIAT 6.0%
14/16 OPERATING PROJECT BUDGET (AWARDED)
15/16 ELEMENTS OF EXECUTION PLANNING
Continue review on possible application of green building features in the project
SUSTAINABILITY NOISE LEVEL DUST CONTROL ROADS/ SIDEWALKS/COMMON AREAS
SUSTAINABILITY, CSR (Corporate Social Responsibility) AND ENVIRONMENT
SUSTAINABILITY, CSR (Corporate Social Responsibility) AND ENVIRONMENT
14/16 SUSTAINABILITY, CSR & ENVIRONMENT
SUSTAINABILITY
A material recovery area will be provided to sort rebar cutting for ease of reuse.
Surplus ready-mix concrete (RMC) will be poured onto the dirt road, potholes and other muddy areas within the construction site.
All equipment will be required to pass emission testing standards
to prevent air pollution.
NOISE LEVEL
Noise level during construction operations or use of equipment, tools, and any sound source which would result in the emission of noise above the ambient noise level standards will be limited to:
Period Maximum Noise Level Daytime ( 7AM – 10PM ) 75 dbNight ( 10PM onwards ) 65 db
Noise generating activities shall be prohibited during Sundays.
.
DUST CONTROL
To maintain cleanliness right outside the construction perimeter
area, housekeeping crew will be deployed on a regular basis to
address the dust and dirt on the road (Corrales Avenue) where the
equipment passes through.
The following measures will also be implemented:- Regular wetting of dirt at the work area.
- Wash bay area shall be provided at entrance/exit gate to clean vehicles coming out of the project site.
-Truck access ways and roadways shall be sprinkled with water to confine dust particles.
- Dump truck haulers of excess excavated soil and construction debris shall be covered to prevent spillage.
- Regular hauling of excess excavated soil and construction debris shall be done at specified times.
- Catch pan for cleaning equipment tires, fuel, oil and lubricant - Catch pan for cleaning equipment tires, fuel, oil and lubricant spillage shall be provided.spillage shall be provided.
14/16 SUSTAINABILITY, CSR & ENVIRONMENT
15/16 SUSTAINABILITY, CSR & ENVIRONMENT
ROADS / SIDEWALKS / COMMON AREAS
- Sidewalks, roads & other common areas surrounding the Sidewalks, roads & other common areas surrounding the project site shall not be obstructed by construction project site shall not be obstructed by construction materials or equipment.materials or equipment.
- Roads and sidewalks shall not be used as staging areas, Roads and sidewalks shall not be used as staging areas, for mixing cement or fabrication, or temporary storage of for mixing cement or fabrication, or temporary storage of materials and supplies.materials and supplies.
- Heavy equipment w/ track shoes shall not be allowed Heavy equipment w/ track shoes shall not be allowed passage to and from the construction site unless they are passage to and from the construction site unless they are carried on flat bed trailers. carried on flat bed trailers.
15/16 SUSTAINABILITY, CSR & ENVIRONMENT
Incorporate the potential wage increase in the unit price.
Incorporate in the Terms & Conditions of the package that the
rebars supplied by the owner shall be under Gross Maximum
Quantity (GMQ ).
16/16 ELEMENTS OF EXECUTION PLANNING
RISK MANAGEMENTRISK MANAGEMENT
16/16 ELEMENTS OF EXECUTION PLANNING
16/16 ELEMENTS OF EXECUTION PLANNING
16/16 ELEMENTS OF EXECUTION PLANNING
16/16 ELEMENTS OF EXECUTION PLANNING
16/16 ELEMENTS OF EXECUTION PLANNING
The End...