PERFORMANCE AND FINANCIAL REPORT (01 APRIL TO 30 JUNE 2014). DR. PHIL MJWARA PORTFOLIO COMMITTE 27 AUGUST 2014. OUTLINE OF THE PRESENTATION. DST Overview. Achievements for the Quarter 1. Remedial Actions. Reasons for Delays in Achieving Targets. Summary of Outcomes Progress. - PowerPoint PPT Presentation
Popular Tags:
40
PERFORMANCE AND FINANCIAL REPORT (01 APRIL TO 30 JUNE 2014) DR. PHIL MJWARA PORTFOLIO COMMITTE 27 AUGUST 2014 1
Transcript
Page 1: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

PERFORMANCE AND FINANCIAL REPORT (01 APRIL TO 30 JUNE 2014)

DR. PHIL MJWARAPORTFOLIO COMMITTE 27 AUGUST 2014

1

Page 2: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

DST Overview

Conclusion

Financial Performance

Achievements for the Quarter 1

Reasons for Delays in Achieving Targets

OUTLINE OF THE PRESENTATION

Summary of Outcomes Progress

2

Remedial Actions

Challenges on Specific Indicators

Achievement per Programme

04/20/23

Page 3: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

THE MANDATE OF THE DEPARTMENT (1)

3

DST OVERVIEW

04/20/23

Page 4: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

THE MANDATE OF THE DEPARTMENT (2)

4

DST OVERVIEW

04/20/23

Page 5: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

.

5

DST VISION.

04/20/23

Page 6: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

.

6

DST MISSION STATEMENT.

04/20/23

Page 7: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

7

KEY OBJECTIVES OF THE DEPARTMENT

04/20/23

Page 8: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

The Department contributes to and reports on the following government outcomes:

8

DST OVERVIEW

04/20/23

Page 9: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

DST PROGRAMMES

DST OVERVIEW

Technology Innovation

Research Development and Support

International Cooperation and

Resources

Administration

White Paper on

S&T, National Research &

Development Strategy, Ten-Year

Innovation Plan

Socio-Economic Innovation

Partnerships904/20/23

Page 10: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

PURPOSE OF THE PROGRAMMES (1)

Programme 1: Administration To conduct the overall management and administration of

the department.

10

DST OVERVIEW

04/20/23

Page 11: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

PURPOSE OF THE PROGRAMMES (2)

Programme 2: Technology Innovation To enable research and development in strategic and

emerging focus areas to promote the realisation of commercial products, processes and services from R&D outputs; through the implementation of enabling policy instruments.

11

DST OVERVIEW

04/20/23

Page 12: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

PURPOSE OF THE PROGRAMMES (3)

Programme 3: International Cooperation and Resources

This Programme aims to strategically develop, promote and manage international relationships, opportunities and S&T agreements that strengthen the NSI and enable an exchange of knowledge, capacity and resources between South Africa and its regional and international partners.

12

DST OVERVIEW

04/20/23

Page 13: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

PURPOSE OF THE PROGRAMMES (4) Programme 4: Research development and support Provide an enabling environment for research and

knowledge production that promotes strategic development of basic sciences and priority science areas, through science promotion, human capital development, the provision research infrastructure and relevant research support in pursuit of South Africa’s transition to a knowledge economy.

13

DST OVERVIEW

04/20/23

Page 14: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

PURPOSE OF THE PROGRAMMES (5) Programme 5: Socio-Economic Innovation

Partnerships This Programme enhances the growth and development

priorities of government through targeted S&T-based innovation interventions and the development of strategic partnerships with other government departments, industry, research institutions and communities.

14

DST OVERVIEW

04/20/23

Page 15: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

DST PERFROMANCE OEVERVIEW (5)

• The DST’s overall performance (total number of output targets n=65). Of the 65 targets set for the 2014/15 financial year, the Department is on course with a total of 44 (68%). Figure 1 below shows that only 19 (29%) were at moderate risk with three percent achieved.

15

DST OVERVIEW (1)

04/20/23

Page 16: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

DST OVERALL PERFROMANCE FOR Q1 PERFORMANCE FOR 2014/15

16

DST OVERVIEW (2)

04/20/23

Page 17: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

MAJOR REASONS FOR DELAYS IN ACHIEVING TARGETS

Administrative delays Changes in the scope of work. For example; The research community requested further consultation

before the finalisation of the first draft of the Marine and Antarctic Research Strategy

Process delays Inputs that could not be solicited from other major stakeholders e.g. Progress on the Cabinet memo is contingent on a response from the

DTI

Targeting process The target commences in the second/ third or fourth quarter. For example; Total number of graduates and students placed in DST-

funded work preparation programmes in SETI institutions.

17

REASONS FOR DELAYS IN ACHIEVING THE SET TARGETS

04/20/23

Page 18: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

IMPROVEMENT PLAN

EXCO- led process to address the issues that relate to administrative delays. The DDGs are expected to indicate the tentative performance status; i.e.

how programmes will ensure that targets on course, at moderate risk and certainty will be achieved.

Workshops have been conducted to solicit inputs from the marine research community

Improved planning processes. With the intervention of the DDG for the programme implicated: discussion

meeting has been scheduled with the DTI

18

REMEDIAL ACTIONS

04/20/23

Page 19: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

SOME CHALLENGES THIS REPORTING QUARTER PER INDICATOR (1)

Quarter One Target

Quarter One Progress

Status Reason for variance

Action

First draft of the Marine and Antarctic Research Strategy completed by 30 June 2014

The first draft could not finalised; however the Stakeholder inputs are being incorporated into the document by the NRF

Moderate Risk

The research community requested further consultation

A workshop was held on 20 May 2014 to solicit more inputs from the marine research community

19

CHALLENGES ON SPECIFIC INDICATORS

04/20/23

Page 20: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

SOME CHALLENGES THIS REPORTING QUARTER PER INDICATOR (2)

Quarter one Target

Quarter one Progress

Status Reason for variance

Action

100 interns fully funded or co-funded in R&D of design, manufacturing and product development by 30 June 2014

43 interns supported through Mintek (Phase 3) by 31 June 2014.

Moderate Risk

60 interns are actually being supported through TIA; however, this figure was not included in the TIA quarter 1 report as funding had not been transferred from DST

Contract finalisation will be expedited and this number will be included in the TIA quarter 2 report

20

CHALLENGES ON SPECIFIC INDICATORS

04/20/23

Page 21: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

QUARTER ONE HIGHLIGHTS: ADMINISTRATION- (1)

21

ACHIEVEMENTS PER PROGRAMME

Annual Target Quarter One Target

Quarter One Progress

Status

One DST 2013/14 annual report approved by DST EXCO and signed by the DG by 31 May 2014

One DST 2013/14 annual report approved by DST EXCO and signed by the DG by 31 May 2014

One DST 2013/14 annual report was approved by DST EXCO and signed by the DG by 31 May 2014

Achieved

Vacancy rate reduced to six percent by 31 March 2015

No target Currently the average vacancy rate is seven percent for the first quarter

On Course

04/20/23

Page 22: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

QUARTER THREE HIGHLIGHTS: TECHNOLOGY INNOVATION (TI) – (1)

The Innovation Priorties and Instruments Chief Directorate championed the hosting of the South Africa-Taiwan Innovation and Commercialisation Workshop that was held in Taiwan, and formed part of the South African delegation that attended the South Africa-Taiwan Joint Committee (JC) Meeting on Science and Technology (S&T) Cooperation.

The three Hydrogen South Africa (HySA) centres of competence (CoCs) were financially supported through two streams of funding (human resources funding for salaries and project funding). This support resulted in eight publications in peer reviewed journals being produced, and two patent applications being filed. The first patent involves a metal hydride (MH) storage container and the second involves an MH storage unit, integrated with a fuel cell power pack.

22

ACHIEVEMENTS PER PROGRAMME

04/20/23

Page 23: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

QUARTER THREE HIGHLIGHTS: TECHNOLOGY INNOVATION (TI) – (2)

Annual Target Quarter One Target Quarter One Progress Status

352 postgraduate students (MSc, PhD) financially supported in key strategic areas by 31 March 2015

No target 79 postgraduate students (MSc, PhD) financially supported in key strategic areas by 30 June 2014

On course

340 trainees supported in key strategic areas by 31 March 2015

60 trainees supported in key strategic areas 30 June 2014

67 trainees supported in key strategic areas 30 June 2014

On Course

ACHIEVEMENTS PER PROGRAMME

04/20/23 23

Page 24: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

QUARTER THREE HIGHLIGHTS: INTERNATIONAL COOPERATION AND RESOURCES (ICR) – (1)

The Programme continued to expand South Africa’s already extensive portfolio of

bilateral STI partnerships with the conclusion of the first formalised STI cooperation

framework (a Memorandum of Understanding) with Malaysia in April 2014.

Innovation partnerships strengthened with Asia (Taiwan). The programme included a

major innovation and commercialisation workshop, which provided a platform for

sharing experiences with regard to enterprise development, intellectual property

management and innovation funding.

24

ACHIEVEMENTS PER PROGRAMME

04/20/23

Page 25: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

QUARTER THREE HIGHLIGHTS: INTERNATIONAL COOPERATION AND RESOURCES (ICR) – (2)

Delegation led by the Minister who was a speaker in several sessions, South Africa

was by the far the most prominent non-European country participating in the

European Open Science Forum (ESOF-2014) conference held in Copenhagen in

June 2014.

Within the broader multilateral area, the Minister participated in the prestigious

Carnegie Group meeting, bringing together the Science Ministers and Advisors of the

G8, the European Commission, Brazil, China, India, Mexico and South Africa. The

Minister had the invaluable opportunity to exchange perspectives with her

counterparts on strategies to enhance global STI cooperation in areas such as anti-

biotic resistance, energy security and research infrastructure.

25

ACHIEVEMENTS PER PROGRAMME

04/20/23

Page 26: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

QUARTER THREE HIGHLIGHTS: INTERNATIONAL COOPERATION AND RESOURCES (ICR) – (3)

Annual Target

Quarter One target

Quarter One Progress Status

R354.6m foreign STI funds secured from international partners through agreed instruments for knowledge production, technology transfer, enhanced innovation, and STI human capital development by 31 march 2015

R22m foreign STI funds secured from international partners through agreed instruments for knowledge production, technology transfer, enhanced innovation, and STI human capital development by 30 June 2014

R 70,830,601 foreign STI funds secured from international partners through agreed instruments for knowledge production, technology transfer, enhanced innovation, and STI human capital development by 30 June 2014

On Course

26

ACHIEVEMENTS PER PROGRAMME

04/20/23

Page 27: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

QUARTER THREE HIGHLIGHTS: RESEARCH DEVELOPMENT AND SUPPORT(RDS) (1)

• In June 2014 the Department of Arts and Culture (DAC) requested to collaborate with DST in the areas of heritage, indigenous knowledge and palaeontology to present a joint project that highlights South Africa’s heritage and scientific convergence. The two departments agreed to participate jointly during the South Africa Year in China and Cultural Season to take place in September and October 2014, in China.

The Department of Science and Technology held public launch events at various host institutions for the four new Centres of Excellence that were awarded in December 2013, namely: Food Security CoE (University of Western Cape), Human Development CoE (University of the Witwatersrand), Integrated the Mineral Resources and Analyses CoE (University of Johannesburg), and Maths and Statistics CoE (University of the Witwatersrand).

27

ACHIEVEMENTS PER PROGRAMME

04/20/23

Page 28: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

QUARTER THREE HIGHLIGHTS: RESEARCH DEVELOPMENT AND SUPPORT (RDS) (2)

• Several workshops were held with respect to the commercialisation of the Reconfigurable Open Architecture Computing Hardware (ROACH) – the first to discuss the general approach and the second to determine the IP arrangements. The investigations for the IP arrangements were concluded and an application was made to the Technology Localisation Implementation Unit within the CSIR for financial support to develop the local manufacturing capability. The SKA Project Office also issued a tender for the development of ROACH-3.

28

ACHIEVEMENTS PER PROGRAMME

04/20/23

Page 29: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

QUARTER THREE HIGHLIGHTS: RESEARCH DEVELOPMENT AND SUPPORT (RDS)– (3)

Annual Target Quarter One target

Quarter One Progress Status

60 research infrastructure grants awarded as per award letters 31 March 2015

No target The funding contract for implementation and management of the National Equipment Programme (NEP), National Nanotechnology Equipment Programme (NNEP) and the National Facilities (NF) has been approvedThe NRF has issued a call for proposals for the 2014/15 financial year

On Course

3 876 researchers awarded research grants through NRF-managed programmes as reflected in the NRF project reports by 31 march 2015

1 000 researchers awarded research grants through NRF-managed programmes as reflected in the NRF project reports by 30 June 2014

2 453 researchers were awarded research grants through NRF- managed programmes as reflected in the NRF project report

On Course

29

ACHIEVEMENTS PER PROGRAMME

04/20/23

Page 30: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

QUARTER THREE HIGHLIGHTS: RESEARCH DEVELOPMENT AND SUPPORT (RDS)– (4)

Annual Target Quarter One Target

Quarter One Progress Status

Multi-wavelength astronomy strategy approved by DST EXCO by 31 December 2014

Draft multi-wavelength Astronomy strategy finalised by 30 June 2014

Multiwavelength astronomy strategy draft finalised

On Course

942 160 participants in science awareness and engagement programmes by 31 March 2015

Grant funding awarded to organisations implementing the initiatives by 30 June 2014

Grants were awarded to organisations conducting science festivals and the National Science Week by 30 June 2014

On Course

30

ACHIEVEMENTS PER PROGRAMME

04/20/23

Page 31: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

QUARTER THREE HIGHLIGHTS: SOCIO-ECONOMIC INNOVATION PARTNERSHIP (SEIP) – (1)

• The selection of innovative sanitation technologies through the DST and Bill and Melinda Gates Foundation agreement has been concluded. These innovative sanitation technology solutions will be piloted in selected rural schools of the Nciba Circuit of the Eastern Cape.

• An Imagine Cup Local final was held on 28 April 2014. This competition challenges the countries’ best student programmers to develop solutions to real-world problems being experienced within their respective communities. The South African winning team, Super Sea Dragons, developed a 2D action-adventure planet plat-former, which also won the global Skype award worth $5000

31

ACHIEVEMENTS PER PROGRAMMES

04/20/23

Page 32: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

QUARTER THREE HIGHLIGHTS: SOCIO- ECONOMIC PARTNERSHIP (SEP) – (2)

Annual Target Quarter One Target

Quarter One Progress Status

Two knowledge products on technology-led opportunities for sustainable livelihoods published on DST website by 31 March 2015

Through consultation and review, identity the topics and format of the two new knowledge products by 30 June 2014

The topics and format were identified for two knowledge products by 30 June 2014. These are on stimulating agro-processing in a rural economy (Nkowankowa Demonstration Centre) and on using a school as a catalyst for local economic development

On Course

20 knowledge and innovation products (patents, prototypes, technology transfer packages) added to the IP portfolio by 31 March 2015

Monitoring of signed contracts with implementing agencies and take timeous corrective action by 30 June 2014

Monitoring of signed contracts ongoing. The CSIR Meraka filed one patent on 27 May 2014 on "Switching between Video Streams".

On Course

32

ACHIEVEMENTS PER PROGRAMMES

04/20/23

Page 33: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

DST Financial Performance

FINANCIAL PERFORMANCE REPORT

33

BUDGET SPLIT – BY PROGRAMME

04/20/23

Page 34: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

BUDGET SPLIT – BY ECONOMIC CLASSIFICATION

34

FINANCIAL PERFORMANCE REPORT

04/20/23

Page 35: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

FINANCIAL PERFORMANCE - SUMMARY

35

DST Financial Performance ReportDST Financial Performance ReportDST Financial Performance Report

FINANCIAL PERFORMANCE REPORT

04/20/23

Page 36: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

Donor Funds

36

ANALYSIS OF DONOR FUNDS

04/20/23

Page 37: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

EXPENDITURE BY PROGRAMME – 30 JUNE 2014

37

Amount % of total

budget Amount

% of total

budget Amount

% of expenditure

plan

Administration 290,960 57,598 19.8% 58,623 20.1% -1,025 -1.8%

Research Development & Innovation 991,623 353,744 35.7% 351,803 35.5% 1,941 0.5%

International Cooperation & Resources 119,699 17,675 14.8% 18,713 15.6% -1,038 -5.9%

Human Capital & Knowledge Systems 3,503,762 617,486 17.6% 615,541 17.6% 1,945 0.3%

Socio-economic Partnerships 1,564,146 355,371 22.7% 354,928 22.7% 443 0.1%

Total 6,470,190 1,401,874 21.7% 1,399,608 21.6% 2,266 0.2%

Planned expenditure Actual spending Deviation from

expenditure plan Programme R'thousands

Budget

04/20/23

Page 38: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

EXPENDITURE TRENDS AS AT 30 JUNE 2014

3804/20/23

Page 39: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

39

Currently 71% of the annual 2014/15 targets are on course including the achieved. EXCO put processes in place to ensure that all targets on course will be

achieved as planned.

Human capital development, knowledge generation and exploitation, infrastructure and Africa collaboration will remain key focus areas and are central in the 2014/15 Annual Performance Plan.

• The Department commits itself to continuous improvement in the policies, processes, structures and instruments that have been put in place in pursuit of an effective NSI whose contribution to national development is being optimised. Also in continuous pursuit of addressing the triple challenges ( poverty, unemployment and inequality) facing the country.

CONCLUSION

04/20/23

Page 40: PERFORMANCE AND FINANCIAL REPORT   (01 APRIL TO 30 JUNE 2014)

40

THANK YOU