Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version PERFORMANCE-BASED CONTRACTS - INTERNATIONAL EXPERIENCES FINNISH ROAD ADMINISTRATION PEKKA PAKKALA TRB Executive Workshop - April 27 2005
Transcript

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

PERFORMANCE-BASED CONTRACTS -INTERNATIONAL EXPERIENCES

FINNISH ROAD ADMINISTRATION

PEKKA PAKKALA

TRB Executive Workshop - April 27 2005

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

PRESENTATION OVERVIEW

DRIVERS & GOALSBRIEF HISTORY & DEVELOPMENTBASIC MAINTENANCE MODELSCONTRACT ISSUESINTERNATIONAL DIFFERENCESPERFORMANCE MEASURESRESULTS & TRENDSKEY ISSUES & SUMMARY CONCLUSIONS

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

DRIVERS & GOALS

Reduction in Prices 10-40%Usually Decided at High Gov't LevelsStaying In Core Business - Road ManagementCommit to Maintenance & Pavement PreservationCrisis - Governmental Costs & Taxes Demonstrate Efficiency & PerformanceBetter Service Levels in Most ScenariosEfficiency & Customer Based Focus

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

Development Steps of Finnra

Present Client/Producer Model

OWN WORK

BALANCINGWORK LOAD

COSTEFFICIENCY

COMPETITION STUDIES

TO OPEN COMPETITION

Authority Org.DesignConstructionMaintenanceInternal Services

RWA CLIENT-AUTHORITYORGANIZATION

STATE OWNEDPRODUCTIONENTERPRISE

OTHER PRODUCERS

RWAMinor worksby privatecontractors,Balancing own workload by private contractorsMinor purchaseson open market

RWAComparing own prices tocontractorprices, search for effectiveoperations

Increasing purchases on open market

RWASubmitting own work to competition in minor scale Tendering own work to external market.Increasing purchases on open market

RWAInternal Separation of Client & Production.

Negotiated Contracts & Selective Open competition

1960-decade1950-decade 1970-decade 1980-decade 1990-decade Jan. 2001(4 Year Phased In Period to Jan. 2005)

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

HISTORY & DEVELOPMENT

1960s - 80s - Some attributes ordered via contractsScandinavia - Mainly Winter MaintenanceEarly 1990s - Increased purchases via contracts1990s - 3 Year Routine Maintenance ContractsLater 1990s - Long-Term Performance BasedTerminology

Performance Specified Maintenance ContractsAsset Management ContractsLong-Term Maintenance ContractsArea Maintenance ContractsPerformance-Based ContractsTerm Network Contracts (Down Under)

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

DIFFERING MODELS

Routine Maintenance

Routine, Periodic & Rehabilitation

Routine Maintenance-PLUSWinter MaintenanceSummer MaintenanceDrainageCracks, PotholesCleaningRoutine Gravel Road UpkeepVegetation & TrashShoulder RepairBridge Cleaning

Resurfacing & Line MarkingIncluding Small Capital ProjectsSigns & Traffic SignalsPavement RehabilitationEmergency ResponseAsset/corridor management Guard Rail Repair/ReplaceLighting

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

CONTRACT ISSUES

Contract Types:Lump SumUnit PricesHybrid or CombinationBeginning to look at risk sharing

Selection Criteria Not Low Bid (Sweden & Norway - maybe Ontario 90%?)Best Value - England, Australia, New Zealand, Finland, USA, British Columbia, Holland & EstoniaIssues;

Competency & Quality Control Plans (Contractor Led)Measuring Resources & Ability to Perform

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

INTERNATIONAL DIFFERENCES

Budget Priority

Scandinavia & Some EU Countries & Down UnderWinter Maintenance First (Safety Issue)Routine MaintenancePreventative MaintenanceLeft Over - Capital Projects

Cultural DifferencesAll Services or Routine MaintenanceUsing a Consultant Adviser to Direct Contractor?

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

Comparison of Maintenance Contracts

Mostly all except Resurfacing & Rehabilitation

98% Price2% Other

New Winter Maintenance

Payment

3-6 YearsOutput & Performance

Based

Sweden

Mostly all except Resurfacing & Rehabilitation

100% PriceLump Sum(Some Unit

Prices)

4-6 YearsOutput & Performance

Based

Norway

Mostly all except Resurfacing & Rehabilitation

75% Price25% Other

Lump Sum(Some Unit

Prices)

3, 5 & 7Years

Output & Performance

Based

Finland

Mostly all exceptResurfacing & Rehabilitation

70-80% Price20-30% Other

Lump Sum(Some Unit

Prices)

5Years

Output & Performance

Based

Estonia

Mostly all exceptResurfacing & Rehabilitation

90% Price10% Other

Lump Sum9 Years(New – 7+2)

Output & Performance

Based

Ontario, Canada

Mostly all exceptResurfacing & Rehabilitation

40% Price60% Other

Lump Sum8 YearsOutput & Performance

Based

British Columbia, Canada

Mostly all exceptResurfacing & Rehabilitation

78% Price22% Other

Unit Price5 YearsOutputBased

Alberta, Canada

ActivitiesIncluded

Contractor Selection Criteria

Contract Method

Contract Duration

Type of Contract

Source: Pekka Pakkala - Finnra

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

Comparison of Maintenance Contracts

ALL exceptResurfacing & Rehabilitation

50% Price50% Other &(Negotiated)

Lump Sum7 Years(7+7)

Performance Based

USA(FL)

ALL exceptRehabilitation

50% Price50% Other &(Negotiated)

Lump Sum5 Years(5+5)

Performance Based

USA(VA)

ALLQuality Price Trade Off (QPTO)

Lump Sum10 YearsPerformance Based

New Zealand

ALL30-40% Price60-70% Other

Lump Sum7 YearsPerformance Based

(eMAC)

England

ALL50% Price50% Other (Varies with

Territory)

Lump Sum10 YearsPerformance Based

AustraliaSydney, WA & Tasmania

ActivitiesIncluded

Contractor Selection Criteria

Contract Method

Contract Duration

Type of Contract

Source: Pekka Pakkala - Finnra

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

PERFORMANCE - BASED MEASURES

PAVEMENTSRoughness (IRI)Skid Resistance (Never a Problem In Summer - Due to Studded tires)Rutting (Biggest problems in Finland on paved roads)Deflection (Structural Condition/Residual Pavement Life)Texture & Cracking

OTHERSLevel of Service (Via Pictures) ==> Guard Rail, Trash, Drainage, & etc. Some Illumination criteria developing for Signs & Road Markings

WINTER MAINTENANCEActive plowing 2 hours after snow fall (Max 4 cm of snow) Less than 1 cm after snow stops and # of hours (1st Class Roads)Skid resistance greater than 0.3

Usually Time & Response Criteria at Output Level

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

WINTER ROAD PERFORMANCE - BASED MEASURES

II

Ib

IIs

III

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

PERFORMANCE - BASED MEASURES

GOOD VERY GOOD

SATISFACTORY

PASSABLEPOOR

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

PERFORMANCE - BASED MEASURES

GOOD VERY GOOD

SATISFACTORY

PASSABLEPOOR

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

MEASURING PERFORMANCE

(Visual)

Pavements

(PMS) (Visual)

Winter MaintenanceGuard Rail

Line Marking

Lighting, Signs & Signals

Bridges(BMS) (Visual) (Visual)

Tunnels(TMS) (Visual) (Visual)(TMS) (Visual)

CleaningTunnels Drainage

Gravel Road

(Visual)

Vegetation & Trash (Visual)

Cracks & Potholes(Visual)

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

International Lessons Learned

InputDriven

OutputDriven

OutcomeDriven

Own Forces

PSMC Alliancing

Financing

Separate Consulting &Physical WorksContracts“Conventionalcontracts”

Hybrid

• Innovation• Contract Duration• Flexibility• Contractor Risks• Productivity• Cost Savings

Source: Opus Int.

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

TRENDS

More Outsourcing By Countries - Recently Norway (Baltic Countries; Switzerland, & Other European Countries Interested)Beginning With 3 Year Contracts Rumors that British Columbia - 10 Years Contracts?Pavement Preservation Technology & Modeling (Finland is using more "Road Doctor" Technology)Contracts are moving to 7 year duration & Performance-BasedHolding - No new 10 year, Fully Integrated Contracts (eMACshave been the closest - England)

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

KEY ISSUES - 5Cs

COMPETENCECOMPETITIONCOST SAVINGSCOMMUNICATION & TRUSTCORRECT BALANCE of RISKS

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

KEY REQUIREMENTS

Robust & good data of existing road network assets and what are the present costs at existing levels of serviceGood funding stream for maintenance - if funding continues to decline then the costs for repair tend to escalate Requires expertise, good tendering practices, and clear & concise contract language. It is difficult to write all conditions in the contract Having common standards & performance measures Champions among the client and service providersPartnering or partnering board Head to head competition among service providersGood communications & sharing knowledge with all parties

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

CONCLUSIONS

Performance-based maintenance contracts is a good road management practice & is aligned with good Pavement Preservation practicesMaintenance contracting provides savingsCannot fix a major capital investment via maintenance contractingIt may be wise to have a deliberate process and progression to long-term performance based contracts - is there an appetite for maintenance in the private sector.May start with routine maintenance contracts - it is not that complicated

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

FINLAND MODEL & STRATEGY

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

PRESENT SITUATION - 2006

DESIGN &PLANNING

100% OUTSOURCED

CONSTRUCTION AND REHABILITATION IN 2001-2002

100% OUTSOURCED

MAINTENANCE(3,5 & 7 YEAR DURATION -75% Price - 25% Technical)

100% OUTSOURCED

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

FINNISH MODEL

Separate Contracts(Periodic Maintenance)

Routine Maintenance3, 5 & 7 Years

Winter MaintenanceSummer MaintenanceDrainageCracks, PotholesCleaningGravel Road CareVegetation & TrashShoulder RepairBridge CleaningGraffiti CleaningGuard Rail Repair/ReplaceEmergency ResponseNew - Including Small Capital Projects

Resurfacing & OverlaysMajor Bridge RehabilitationLine MarkingsLighting

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

FINLAND COMPETITION RESULTS

Rakennusliike Karjaluoto Oy

Skanska Asphalt Oy

YIT Construction Oy

NCC InterAsphalt Oy

Tractor Construction Määttä Brothers Oy

Savon Kuljutus Oy

Finnish Road Enterprise

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

FINNISH RESULTS

Cost Savings ~ over 30% (40-50% based on Cost/km)78% Of Contracts Won By Finnish Road EnterpriseQuite Close Competition3-6 Proposals Per Contract AreaTransition from to Client - Producer Model was SuccessfulMarket is beginning to Mature Stipends to the Non-WinnersWhat's NEW!

Gravel Road Performance Specifications Being TestedCombinations of 3-5-7 Year AgreementsBonus - Reduced Salt Usage & Better Customer Service Pilot Stages - Separate Long-term Contracts for Line Markings, Bridges, & Pavement Resurfacing/Overlays

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

PRESENT CONTRACT DURATION

0

5

10

15

20

25

30

35

3 Years 5 Years 7 Years

Contract Duration

Quantity

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

MAINTENANCE CONTRACT DEVELOPMENT

Small Investments

Area RoutineMaintenance

Contracts

Increase Contract Length Integrated Performance Contracts

ving to Integrated Contracts

MoOther Periodic Maintenance & Improvements

Separate Maintenance Contracts

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

MAINTENANCE CONTRACT DEVELOPMENT

Area Contracts Integrated Performance Contracts

• 7-8 Years• (500) 1000-2000 km• Fully Integrated Client Services• Lump Sum • Outcome Based Criteria

• 3 Years• 500-1500 km• Broad Range of tasks• Hybrid - Lump Sum &

Unit Prices• Technical Criteria

Pekka Pakkala TRB Executive Workshop - April 27 2005 – Edited Version

Frost damage(Pilot tests)

3-5-7 yearswith 2 year optionsFrost damagerepairsRoad marking(Pilot tests)

3-5-7 years

Consolidating into larger areas

Include Road Markings?

3-5-7 yearsUnited largerareas ContentexpansionRoad markings ?

7-year contractsContend expands& includes small capital investment tasks

CURRENTAREA CONTRACTS

LONG-TERM PERFORMANCEMAINTENANCE CONTRACTS

DEVELOPMENTAL STAGES FOR AREA MAINTENANCE CONTRACTS

2002 2003 2004 2005 2006


Recommended