+ All Categories
Home > Documents > Performance of Driven Displacement Pile–Improved Ground in Controlled Blasting...

Performance of Driven Displacement Pile–Improved Ground in Controlled Blasting...

Date post: 21-Mar-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
13
Performance of Driven Displacement PileImproved Ground in Controlled Blasting Field Tests Tygh N. Gianella, A.M.ASCE 1 ; and Armin W. Stuedlein, M.ASCE 2 Abstract: Full-scale, controlled blasting field tests on driven displacement pileimproved ground were conducted to study the response of densified and reinforced ground to blast-induced excess pore pressures. In order to make appropriate comparisons to the baseline response of the native, unimproved ground, explosive charges sufficient to induce liquefaction were detonated in a control zone and the resulting post- liquefaction settlements were measured. Excess pore pressures generated in the improved ground were observed to be significantly smaller than that in the unimproved ground, and resulted in settlements that were generally one-sixth to one-third of that measured in the unimproved ground. Piles tipped into a dense bearing layer settled significantly less than the surrounding soil and piles that were floated above the bearing layer. Importantly, measured excess pore pressures pointed to a change in soil response from contractive to dilative during blasting, indicating that the improved ground mobilized significant strength during blasting, similar to the response expected from cyclic mobility of dense soils. The energy of scaled ground motions developed from velocity measurements are used to relate the observed soil response to blasting to that expected from earthquake-induced ground motions. The paper concludes with a comparison of shear strains expected from shear strain compatibility (SSC) between the improved ground and the displacement piles to those implied by the measured pore pressures. The com- parison indicated that some portions of the improved ground responded in an incompatible manner during the blast-induced ground motions and that the assumption of SSC may not be appropriate for design of some reinforcement-type ground improvements. DOI: 10.1061/(ASCE) GT.1943-5606.0001731. © 2017 American Society of Civil Engineers. Introduction Numerous and careful observations of the effects of earthquakes have pointed to the potential for liquefaction of relatively loose, saturated granular soils and resulting damage to civil infrastructure. However, cyclic stress-induced excess pore pressure magnitudes equal to the effective overburden pressures (i.e., liquefaction) are not required within a particular soil layer to initiate damaging mag- nitudes of settlement (Tokimatsu and Seed 1987; Ishihara and Yoshimine 1992). Based on the results of laboratory investigations, Lee and Albaisa (1974) determined that the primary factor gov- erning postshaking volumetric strains (and therefore settlements) was the magnitude of the excess pore pressure ratio, r u , defined in their study as the ratio of cyclically-induced excess pore pressure to the isotropic consolidation stress. Among other factors, the pre- shaking relative density of the soil contributed to variations in the resulting magnitude of volumetric strains or postshaking compress- ibility, with increases in relative density leading to reductions in deformation for a given r u . Later, Seed et al. (1975) synthesized these observations using an analytical model that captured the gen- eral changes in compressibility, assessed using the modulus of vol- ume compressibility, m v . Fig. 1 summarizes the measurements by Lee and Albaisa (1974) and analytical model by Seed et al. (1975). Tokimatsu and Seed (1987) and Ishihara and Yoshimine (1992) ex- tended the previous findings to determine that the magnitude of cyclic shear strain imposed on liquefiable soils also governed the magnitude of postshaking volumetric strain, or settlement. The aforementioned findings, among others, have led to ac- cepted design protocols for the mitigation of liquefaction and its effects, such as setting a limiting maximum r u to 5060% or less (Schaefer et al. 1997). These protocols seem most appropriate for ground improvement techniques that reinforce loose soils in be- tween stiffened elements, such as deep soil mix columns or panels, or jet grouted columns. However, densification-based ground im- provement techniques increase the relative density of the soil, and subsequently lead to reduced settlements following the generation and dissipation of excess pore pressure (Fig. 1). Methods that both densify and reinforce, such as displacement piling, may offer re- dundancies that may provide optimal cyclic performance. Raising the maximum allowable r u possible with such redundant methods may lead to improved cost-efficiency of ground treatment if good performance can be demonstrated to rightfully cautious engineers. Controlled blasting may be used to evaluate the in situ reduction in postshaking deformations that is possible with ground improve- ment (Ashford et al. 2000a, b). This paper describes the use of con- trolled blasting to compare the full-scale performance, including the generation of blast-induced excess pore pressures and sub- sequent deformations, of driven timber displacement pileimproved ground to that of the native, unimproved ground. First, the subsur- face of the test site and program selected to evaluate the effect of various pile spacings and time elapsed since driving on densification of potentially liquefiable soils is summarized. Experiments con- ducted to evaluate the baseline response of unimproved ground to controlled blasting are described, and the blast-induced excess pore pressure response and postliquefaction ground settlements are presented. The pore pressure response and postblasting settlements in the improved ground resulting from the same blast pattern are then presented, and comparisons to the unimproved ground are made. Although peak residual excess pore pressures in excess of 60% of the effective overburden stress were observed in the 1 Staff Engineer, GeoEngineers, Inc., 1200 NW Naito Pkwy. #180, Portland, OR 97209. 2 Associate Professor, Oregon State Univ., 101 Kearney Hall, Corvallis, OR 97331 (corresponding author). E-mail: armin.stuedlein@oregonstate .edu Note. This manuscript was submitted on February 5, 2016; approved on February 23, 2017; published online on May 15, 2017. Discussion period open until October 15, 2017; separate discussions must be submitted for individual papers. This paper is part of the Journal of Geotechnical and Geoenvironmental Engineering, © ASCE, ISSN 1090-0241. © ASCE 04017047-1 J. Geotech. Geoenviron. Eng. J. Geotech. Geoenviron. Eng., 2017, 143(9): -1--1 Downloaded from ascelibrary.org by OREGON STATE UNIVERSITY on 05/15/17. Copyright ASCE. For personal use only; all rights reserved.
Transcript
Page 1: Performance of Driven Displacement Pile–Improved Ground in Controlled Blasting …timberpilingcouncil.com/wp-content/uploads/2017/08/... · 2017-08-07 · Performance of Driven

Performance of Driven Displacement Pile–ImprovedGround in Controlled Blasting Field Tests

Tygh N. Gianella, A.M.ASCE1; and Armin W. Stuedlein, M.ASCE2

Abstract: Full-scale, controlled blasting field tests on driven displacement pile–improved ground were conducted to study the response ofdensified and reinforced ground to blast-induced excess pore pressures. In order to make appropriate comparisons to the baseline response ofthe native, unimproved ground, explosive charges sufficient to induce liquefaction were detonated in a control zone and the resulting post-liquefaction settlements were measured. Excess pore pressures generated in the improved ground were observed to be significantly smallerthan that in the unimproved ground, and resulted in settlements that were generally one-sixth to one-third of that measured in the unimprovedground. Piles tipped into a dense bearing layer settled significantly less than the surrounding soil and piles that were floated above the bearinglayer. Importantly, measured excess pore pressures pointed to a change in soil response from contractive to dilative during blasting, indicatingthat the improved ground mobilized significant strength during blasting, similar to the response expected from cyclic mobility of dense soils.The energy of scaled ground motions developed from velocity measurements are used to relate the observed soil response to blasting to thatexpected from earthquake-induced ground motions. The paper concludes with a comparison of shear strains expected from shear straincompatibility (SSC) between the improved ground and the displacement piles to those implied by the measured pore pressures. The com-parison indicated that some portions of the improved ground responded in an incompatible manner during the blast-induced ground motionsand that the assumption of SSC may not be appropriate for design of some reinforcement-type ground improvements. DOI: 10.1061/(ASCE)GT.1943-5606.0001731. © 2017 American Society of Civil Engineers.

Introduction

Numerous and careful observations of the effects of earthquakeshave pointed to the potential for liquefaction of relatively loose,saturated granular soils and resulting damage to civil infrastructure.However, cyclic stress-induced excess pore pressure magnitudesequal to the effective overburden pressures (i.e., liquefaction) arenot required within a particular soil layer to initiate damaging mag-nitudes of settlement (Tokimatsu and Seed 1987; Ishihara andYoshimine 1992). Based on the results of laboratory investigations,Lee and Albaisa (1974) determined that the primary factor gov-erning postshaking volumetric strains (and therefore settlements)was the magnitude of the excess pore pressure ratio, ru, definedin their study as the ratio of cyclically-induced excess pore pressureto the isotropic consolidation stress. Among other factors, the pre-shaking relative density of the soil contributed to variations in theresulting magnitude of volumetric strains or postshaking compress-ibility, with increases in relative density leading to reductions indeformation for a given ru. Later, Seed et al. (1975) synthesizedthese observations using an analytical model that captured the gen-eral changes in compressibility, assessed using the modulus of vol-ume compressibility, mv. Fig. 1 summarizes the measurements byLee and Albaisa (1974) and analytical model by Seed et al. (1975).Tokimatsu and Seed (1987) and Ishihara and Yoshimine (1992) ex-tended the previous findings to determine that the magnitude of

cyclic shear strain imposed on liquefiable soils also governedthe magnitude of postshaking volumetric strain, or settlement.

The aforementioned findings, among others, have led to ac-cepted design protocols for the mitigation of liquefaction and itseffects, such as setting a limiting maximum ru to 50–60% or less(Schaefer et al. 1997). These protocols seem most appropriate forground improvement techniques that reinforce loose soils in be-tween stiffened elements, such as deep soil mix columns or panels,or jet grouted columns. However, densification-based ground im-provement techniques increase the relative density of the soil, andsubsequently lead to reduced settlements following the generationand dissipation of excess pore pressure (Fig. 1). Methods that bothdensify and reinforce, such as displacement piling, may offer re-dundancies that may provide optimal cyclic performance. Raisingthe maximum allowable ru possible with such redundant methodsmay lead to improved cost-efficiency of ground treatment if goodperformance can be demonstrated to rightfully cautious engineers.

Controlled blasting may be used to evaluate the in situ reductionin postshaking deformations that is possible with ground improve-ment (Ashford et al. 2000a, b). This paper describes the use of con-trolled blasting to compare the full-scale performance, includingthe generation of blast-induced excess pore pressures and sub-sequent deformations, of driven timber displacement pile–improvedground to that of the native, unimproved ground. First, the subsur-face of the test site and program selected to evaluate the effect ofvarious pile spacings and time elapsed since driving on densificationof potentially liquefiable soils is summarized. Experiments con-ducted to evaluate the baseline response of unimproved groundto controlled blasting are described, and the blast-induced excesspore pressure response and postliquefaction ground settlements arepresented. The pore pressure response and postblasting settlementsin the improved ground resulting from the same blast pattern arethen presented, and comparisons to the unimproved ground aremade. Although peak residual excess pore pressures in excess of60% of the effective overburden stress were observed in the

1Staff Engineer, GeoEngineers, Inc., 1200 NW Naito Pkwy. #180,Portland, OR 97209.

2Associate Professor, Oregon State Univ., 101 Kearney Hall, Corvallis,OR 97331 (corresponding author). E-mail: [email protected]

Note. This manuscript was submitted on February 5, 2016; approved onFebruary 23, 2017; published online on May 15, 2017. Discussion periodopen until October 15, 2017; separate discussions must be submitted forindividual papers. This paper is part of the Journal of Geotechnicaland Geoenvironmental Engineering, © ASCE, ISSN 1090-0241.

© ASCE 04017047-1 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2017, 143(9): -1--1

Dow

nloa

ded

from

asc

elib

rary

.org

by

OR

EG

ON

ST

AT

E U

NIV

ER

SIT

Y o

n 05

/15/

17. C

opyr

ight

ASC

E. F

or p

erso

nal u

se o

nly;

all

righ

ts r

eser

ved.

Page 2: Performance of Driven Displacement Pile–Improved Ground in Controlled Blasting …timberpilingcouncil.com/wp-content/uploads/2017/08/... · 2017-08-07 · Performance of Driven

improved ground, the blast pulses forced the pore pressure responsefrom contractive to dilative, and indicated that the strength and stiff-ness of the densified ground was effectively mobilized, serving tolimit the subsequent deformations. The site-specific attenuation

characteristics of the blast-induced ground motions are presented,and used to estimate the free surface ground motions at the center ofthe displacement pile–treated area and are shown to correlate to themeasured pore pressure responses. The paper concludes with com-parisons of the observed and estimated performance to that ex-pected assuming shear strain compatibility of the pile-reinforcedsoils. Comparisons indicate that the measured excess pore pres-sures and implied shear strains are inconsistent with shear straincompatible deformation for some portions of the pile-improved soilduring the blasting-induced ground motions.

Subsurface Conditions and Test Pile Program

The investigation of soil response to controlled blasting was con-ducted at two separate areas separated 15 m apart, and included theunimproved or control zone and the pile-improved or treated zone.Gianella et al. (2015) and Stuedlein et al. (2016) describes thedisplacement pile ground improvement test program and postim-provement in situ tests in detail; a brief summary follows to providean appropriate context for interpretation of the blast experiments.Fig. 2 presents the site and exploration plan along with the pilegroups constructed to evaluate the magnitude of ground improve-ment possible with conventional and drained timber piles. Fig. 3shows the subsurface profile and preimprovement and postim-provement in cone penetration test (CPT) corrected cone tip resis-tance, qt. Treated Zones 1 and 2 consisted of timber piles fitted withprefabricated vertical drain (PVD) elements, and were installed in

Fig. 1. Variation of the modulus of volume compressibility, mv, withpeak excess pore pressure ratio, ru, deduced from experiments andtheoretical considerations

LEGEND

CPTCPT W/ SHEAR WAVEBORINGB-# EXPLORATORY BORINGB-#E EXPLOSIVES BORING

TIMBER PILE

0.61 m

B-5 B-9

B-6

B-1E1

B-11

B-4 B-8

1.22 m

P2-6

P3-6

P3-8

P4-9P2-8

P3-1

P4-7

P4-8

0.76 m

P3-9

P4-1

B-13

P2-1 B-10

P3-7

P4-6

B-12E1

7.62 m

Zone 5 - 2D & 4D

B-17E1

B-13E1

B-14E1

DRIVEN DISPLACEMENT PILE-TREATED ZONES

B-15E1

Zone 3 - 5D

B-16E1

Zone 4 - 3D

B-18E1

3.05 m

P2-9

P2-7

B-11E1

B-7

1.52 m 1.52 m

B-1E2

B-2E1

B-9E1

B-5E2

1.52 m

CONTROL ZONE

B-8E1

B-1E1

7.62 m

B-3E2

P-1

B-3

P1-1

B-1

0.76 m

B-7E1

B-2E2

Zone 1 - 5DPVD

B-2

Zone 2 - 3DPVD

B-4E2

B-10E1

B-6E1

B-5E1

P1-6

B-3E1

P1-9

B-4E1

3.05 m

P1-7

P1-8

7.62 m

B-6E2

Fig. 2. Site and exploration plan including pile locations, initial in situ tests, and blast casing locations; note that the control zone was located morethan 15 m northeast of Zone 5

© ASCE 04017047-2 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2017, 143(9): -1--1

Dow

nloa

ded

from

asc

elib

rary

.org

by

OR

EG

ON

ST

AT

E U

NIV

ER

SIT

Y o

n 05

/15/

17. C

opyr

ight

ASC

E. F

or p

erso

nal u

se o

nly;

all

righ

ts r

eser

ved.

Page 3: Performance of Driven Displacement Pile–Improved Ground in Controlled Blasting …timberpilingcouncil.com/wp-content/uploads/2017/08/... · 2017-08-07 · Performance of Driven

five-by-five pile groups spaced at five and three pile head diameters(D, equal to 310 mm, on average), respectively. Pile groups intreated Zones 3, 4, 5A, and 5B were installed at 5D, 3D, 2D, and4D, respectively.

The piles were installed through a 2–2.5 m thick layer of looseto medium dense, clayey and silty sand fill (SM and SC), soil thatincluded residential housing debris (e.g., brick, wood, roofingshingles, etc.) generated following Hurricane Hugo in 1989. Pre-drilling and spudding of pile locations to depths of 2–3 m was re-quired to allow the piles to penetrate the fill layer. Underlying thefill was a 8.5–9 m thick layer of loose to medium dense (prior toimprovement), potentially liquefiable clean to silty sand (SP andSM), overlying a 1–1.5 m thick stratum of sandy clay (CH), andfollowed by a deposit of dense to very dense sand (SP). The base-line qt shown in Fig. 3, corresponds to the conditions at the centerof each treated zone prior to improvement (Fig. 2). The stratigraphyacross the site was relatively uniform; prior to improvement, qtand energy-corrected standard penetration testing (SPT) blowcount, N60 ranged between approximately 1 and 10 MPa and 1 to10 blows per 0.3 m, respectively, within the potentially liquefiablesoil layer. The groundwater table was approximately 2.13 m belowthe ground surface during the first blast event, and 2.15 m duringthe second blast event (described subsequently).

In general, qt measured 10 days following pile installation(Fig. 3) indicated that the improvement increased with reductionsin pile spacing (Stuedlein et al. 2016). Approximately 8 monthsfollowing installation, qt reduced across the test zones, with thegreatest reductions associated with the greatest pile spacing. Zone2, with drained piles spaced at 3D, yielded the largest magnitudesof qt 255 days following installation; however, it is not clear ifthis observation resulted from the presence of PVDs or the pile

installation sequence (Stuedlein et al. 2016). In general, the relativedensity of the subsurface increased from 40–55% to 60–90% asmeasured 255 days following pile installation, depending on thepile head spacing and depth.

Use and Limitations of Controlled Blasting

Controlled blasting was conducted to compare the effectiveness ofthe driven displacement pile–improved ground to reduce excesspore pressures and deformations to that of the unimproved controlzone. Although explosives cannot replicate the ground motions as-sociated with earthquakes, they can be used to evaluate effects as-sociated with earthquakes, such as liquefaction and the subsequentdeformations (settlements). Hence, the use of controlled blasting ingeotechnical experimentation has gained wide acceptance over thelast 15 years. Experiments ranging from the performance of stonecolumns (Ashford et al. 2000a, b), axial (Rollins and Strand 2006)and lateral response of deep foundations (Ashford et al. 2004;Rollins et al. 2005, 2006; Weaver et al. 2005), and earthquakedrains (Rollins et al. 2004) have been successfully conducted. Gohlet al. (2001) describe an experiment conducted to relate measuredblast–induced shear strains to ru, and showed that their blast patternreplicated the shear strain-pore pressure triggering curves devel-oped in laboratory tests described by Dobry et al. (1982).

Nevertheless, significant differences in the characteristics ofblast-induced and seismic ground motions exist, and a brief discus-sion of these differences is helpful for the interpretation of the re-sults described in this study. Generally, earthquake-induced groundmotions in a near-surface free-field produce vertically-propagatinghorizontal shear stresses as the dominant loading type (Seed 1979).

0306090

0 10 20 30

Zone 5B: 4D

0306090

0 10 20 30

Zone 5A: 2D

255-daysPost-installation

0306090

0 10 20 30

Zone 4: 3D

10-daysPost-installation

0306090

0 10 20 30

Zone 2: 3DPVD

Fines Content

0306090

0

5

10

15

0 10 20 30

Dep

th (m

)

Zone 1: 5DPVD

0306090

0 10 20 30

Zone 3: 5D

Baseline

Corrected Cone Tip Resistance, qt (MPa)

Fines Content, FC (%)

SM and SC [FILL]

SP with lenses of SM

SP

CH

SP

Fig. 3. Preimprovement and postmprovement cone tip resistance profiles observed for pile groups spaced at two pile head diameters to five pile headdiameters and with and without PVDS (adapted from Gianella et al. 2015)

© ASCE 04017047-3 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2017, 143(9): -1--1

Dow

nloa

ded

from

asc

elib

rary

.org

by

OR

EG

ON

ST

AT

E U

NIV

ER

SIT

Y o

n 05

/15/

17. C

opyr

ight

ASC

E. F

or p

erso

nal u

se o

nly;

all

righ

ts r

eser

ved.

Page 4: Performance of Driven Displacement Pile–Improved Ground in Controlled Blasting …timberpilingcouncil.com/wp-content/uploads/2017/08/... · 2017-08-07 · Performance of Driven

Conversely, detonation of explosives results in the generation of ashock wave that propagates radially from the charge (Dowding andHryciw 1986). The resulting ground motions reflect the passageof the shock wave that is characterized by initial compressivefollowed by tensile hoop stresses (Narin van Court and Mitchell1994), which upon unloading, induce shear stresses owing tothe expanding conical shock wave geometry (Hryciw 1986). Thesestresses travel at the P wave velocity of the soil, as opposed to the Swave velocity associated with earthquake-induced cyclic shearstresses. The peak amplitude and frequency content of near-fieldacceleration time histories associated with blasting is significantlyhigher than those of earthquake time histories, and are character-ized with high amplitude shear strain pulses (Gohl et al. 2001), im-plying higher shear strain rates than those of earthquakes. However,Gohl et al. (2001) noted that the ground velocity and displacementamplitudes developed from blasting over the test volume arecomparable to those generated by earthquake motions; this devel-opment is attributed to the high frequency nature of the accelera-tions (Kramer 1996; Dowding and Duplaine 2004). Pore pressuresthat are generated from blasting result from a combination ofchanges in total mean stress during the blast pulse, transient meaneffective stresses imposed on the soil skeleton, and unloading-typeshear strains; of these, the major contributor to residual excess porepressures is from the shear strains (Gohl et al. 2010). Thus, corre-lation of the development of liquefaction and subsequent effectsfrom blasting to that from earthquake motions is possible.

Controlled Blasting Experiments

Instrumentation

Various instruments were used to observe the effectiveness of thedriven displacement pile–improved zones and the control zone suchas pore pressure transducers and ground surface settlement moni-toring points for optical leveling. Additionally, regulations in SouthCarolina required that ground vibrations associated with the deto-nation of explosives be monitored given the proximity of severalprivately-owned structures. Velocity time histories of each blastevent were monitored at the ground surface of five structures ad-jacent to the test site using Minimate Plus seismographs manufac-tured with a standard triaxial geophone. Velocity amplitudes of0.5 mm=s triggered the seismographs, which then initiated sam-pling at 333 Hz. Unfortunately, geophones were not set above eachof the blasted zones, and therefore no measurements of the groundmotions at these areas are available. However, measurements ateach of the five structure locations allowed the development ofsite-specific attenuation relationships that can be used to estimateground motions at the ground surface at the center of the controland treated zones, as described subsequently.

Pore pressure transducers (PPTs) were installed within bore-holes drilled in the center of the control zone (B-1) and treatedzones (B-3, B-5, B-7, and B-9) in order to observe the excess porepressures developed as a result of the detonation of explosivecharges. Druck model UNIK 5000 PPTs capable of measuringpressures of up to 5.2 MPa, and withstanding blast pressures ofup to 20.7 MPa were used. A sampling rate of 5 Hz was used be-cause the focus of this investigation was on the peak residual excesspore pressures (i.e., those generated following passage of the shockwave); accordingly, peak blasting pressures may not have been cap-tured. The PPTs were individually calibrated prior to insertionwithin weighted, protective acrylic housings fabricated similar tothat described by Cox et al. (2009) and grouted within the bore-holes at nominal target depths of 4.6, 6.1, 7.6, and 9.1 m. The actual

depth of PPT installation varied from borehole to borehole, as de-scribed subsequently. A low-strength cement-bentonite grout wasused to seal the PPTs and replace excavated soil over the entirelength of the borehole and prevent communication of pore pres-sures within the borehole.

Control Zone: Blast Program and Excess PorePressures

The blasting program for the unimproved control zone consisted offour separate blasts, of which the first two consisted of small chargeweights to check the responsiveness of the PPTs and data acquis-ition system (termed BE1 and BE2; Mahvelati et al. 2016). Thethird and fourth blast events form the focus of the investigation de-scribed in this paper. Explosive charges were constructed of penta-erythritol tetranitrate (PETN), sized to an equivalent of 0.91 kg oftrinitrotoluene (TNT) each. The experimental setup for the thirdblasting event (termed BE3) at the control zone consisted of sixblast casings designated B-1E2 through B-6E2 installed within acircular arrangement (with radius of 3.81 m) as shown in Fig. 2,with four decks of charges in each casing. The decks were locatedat depths of 3.7, 5.3, 7.2, and 8.8 m below the ground surface, re-sulting in a total charge weight of 21.8 kg. This charge weight wasselected based on the subsurface conditions from in situ tests at thetest site and nearby blast-induced liquefaction studies reported byCamp et al. (2008). The intention was to verify that the chargeweight necessary to induce liquefaction in the unimproved groundat the control zone was sufficient prior to blasting the displacementpile treated zone.

The blast sequence comprising BE3 was designed so that thecenter of the control zone would experience blast pulses fromopposing directions in an effort to push and pull the ground as de-scribed by Gohl et al. (2001) and others (e.g., Rollins and Strand2006; Ashford et al. 2004; Rollins et al. 2005, 2006; Weaver et al.2005). The blast sequence started at the bottom deck, with chargesdetonated in approximate diametrically-opposed locations with det-onations of one and one, then two and two charges (i.e., four det-onations per deck for a total 16 detonations over 9 s) with a 600 msdelay between blasts. The blast sequence started at the bottom deckand worked upward toward the surface where the sequence wasrepeated. See Gianella (2015) for further details of the blast se-quence. Unfortunately, BE3 was unable to be executed as intended,and the 24 charges were detonated over a relatively short timeframe (i.e., approximately 1 s). New blast casings were installedin the control zone six months later, and the intended blastingsequence in the control zone, Blast Event 4 (i.e., BE4) wasperformed.

Fig. 4 presents the excess pore pressure ratio time history foreach of the PPTs measured at the control zone during BE3 andBE4. The PPTs at elevations of 6.35, 7.39, and 8.60 m reachedpeak ru of 126, 140, and 152%, respectively, and peak residualru ranged between 75 and 100% during BE3. Complete liquefac-tion was achieved at the deepest elevation (i.e., ru ¼ 95–100%),and that near-complete liquefaction was achieved for the depthof 7.39 m. Fig. 4(b) presents the excess pore pressures measuredfollowing BE4. Each of the 16 individual detonations resulted in aslightly delayed peak in ru, with the last peak in ru ending at ap-proximately 9.5 s. The shallowest PPT responded slower to theblasting as a result of the charges being detonated in the deepestdecks first. All of the PPTs demonstrated a contractive soil responsewith increases in ru following each blast, indicating that soil in thecontrol zone consisted loose to medium dense, liquefiable sand.The PPTs at elevations of 5.25, 6.35, 7.39, and 8.60 m reached peakru values of 105, 147, 133, and 148%, respectively, for BE4. The

© ASCE 04017047-4 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2017, 143(9): -1--1

Dow

nloa

ded

from

asc

elib

rary

.org

by

OR

EG

ON

ST

AT

E U

NIV

ER

SIT

Y o

n 05

/15/

17. C

opyr

ight

ASC

E. F

or p

erso

nal u

se o

nly;

all

righ

ts r

eser

ved.

Page 5: Performance of Driven Displacement Pile–Improved Ground in Controlled Blasting …timberpilingcouncil.com/wp-content/uploads/2017/08/... · 2017-08-07 · Performance of Driven

two deepest PPTs sustained complete liquefaction with peakresidual ru ranging from 95 to 105%, whereas the two shallowPPTs showed ru ranging from 75 to 85%. Sand boils were not ob-served in the control zone after blasting, likely because of the stiff-ness and relatively impermeability of the fill overlying theliquefiable layer.

Postliquefaction Settlements at the Control Zone

Optical level measurements of the ground surface were conductedto observe the settlement resulting from postliquefaction consoli-dation. A baseline survey was performed prior to blasting at 29individual points, distributed along three lines as shown in Fig. 5.Each line was spaced 60 degrees apart with the survey pointsspaced at 1.52 m intervals from the center of the control zone. Pro-tocols were set to ensure that the points could be re-establishedfollowing each blast event. Ground surface elevations were sur-veyed approximately 3 and 20 h after BE3; after 3 h, ru ranged

from 2% in the shallow PPTs to 4% in the deeper PPTs. The el-evations were surveyed again the following morning to determine iffurther settlement occurred, and on average, approximately 8 mmof additional settlement occurred between the 3 h and 20 h settle-ment surveys. Fig. 5 presents the ground surface settlements for thethree survey lines 20 h after BE3, and indicates that the maximumsettlement, equal to approximately 160 mm, occurred in the centerof the control zone and decreased with increasing distance from thecenter of the control zone.

Another survey was performed along the A, B, and C lines 24 hafter BE4. The ground surface settlements measured along theselines indicate the differences in settlement between events with sig-nificantly different shaking durations. The settlements observedfollowing BE4 were approximately 25 mm larger, on average, thanthose measured from BE3, and a maximum settlement of approx-imately 200 mmwas observed near the center. An additional surveywas performed 48 h following BE4, but little to no additional set-tlement occurred. The cumulative maximum settlement for both

0

25

50

75

100

125

150

3 6 9 12 15 18 21

r u(%

)

Time (minutes)

z = 5.25 m z = 6.35 m

z = 7.39 m z = 8.60 m

0

25

50

75

100

125

150

0 5 10 15

Time (s)

0

25

50

75

100

125

150

5 10 15 20 25

r u(%

)

Time (minutes)

z = 5.25 m z = 6.35 m

z = 7.39 m z = 8.60 m

0

50

100

150

0 5 10 15

Time (s)

0

2

4

6

8

10

12

0 10 20

Dep

th (

m)

qt (MPa) and NSPT (bpf)

PPT

P-1 (CPT)

B-1 (SPT)

(a)

(b) (c)

Fig. 4. Characterization, instrumentation, and blast performance at the unimproved control zone: (a) excess pore pressure generation and dissipationtime histories for Blast Event 3; (b) excess pore pressure generation and dissipation time histories for Blast Event 4; (c) in situ tests and PPT locations

© ASCE 04017047-5 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2017, 143(9): -1--1

Dow

nloa

ded

from

asc

elib

rary

.org

by

OR

EG

ON

ST

AT

E U

NIV

ER

SIT

Y o

n 05

/15/

17. C

opyr

ight

ASC

E. F

or p

erso

nal u

se o

nly;

all

righ

ts r

eser

ved.

Page 6: Performance of Driven Displacement Pile–Improved Ground in Controlled Blasting …timberpilingcouncil.com/wp-content/uploads/2017/08/... · 2017-08-07 · Performance of Driven

blasting events equaled approximately 350 mm (14 in.) in thecenter of the control zone.

Improved Ground: Blast Program and Excess PorePressures

The same charge weight and blasting sequence previously de-scribed for BE4 in the control zone was applied to the treated zones

in order to make one-to-one comparisons of ru and settlement. Thisevent is designated Blast Event 5 (i.e., BE5). Fig. 2 shows the lo-cation of the 18 blast casings with four decks per casing, set at thesame elevations as those for the control zone. Each of the 72 ex-plosive charges contained an equivalent of 0.91 kg of TNT resultingin a total charge weight of 65.5 kg. Owing to the presumed diffi-culty in interpreting the pore pressure and deformation response forZones 5A and 5B, and due to the poor control of pile head spacingfor the 2D piles detailed by Stuedlein et al. (2016), Zone 5 was notconsidered during the blast program.

Fig. 6 compares the generation of excess pore pressures in thetreated zones at the nominal target PPT depths of 4.6, 6.1, 7.6, and9.1 m (variations in depths developed during installation). In gen-eral, contractive pore pressures resulted from detonation of the ex-plosive charges in the beginning of the blast sequence. However,continued detonation of charges result in the change in response ofthe improved ground. For example, the comparison of ru responsefor the shallowest PPTs in the control zone and Zone 3 is illustratedin Fig. 7. The seventh charge in the treated Zone 3 caused a tran-sition from the contractive, positive pore pressure response-to-detonation to a dilative response, where pore pressures reduced inresponse to subsequent detonations. In between blasts and after ap-proximately 3.7 s, ru equaled approximately 75%; the ru dropped aconsistent (and absolute) 15 to 20% in response to subsequentblasts. In terms of cyclic stress paths, such a response indicates thatthe stress state has effectively crossed the phase transformation lineand dilated (e.g., Ishihara et al. 1975; Zhang et al. 1997), and thatsignificant soil strength had been mobilized in response to detona-tion of the charges.

In general, the excess pore pressure response was relativelysimilar between the various arrangements of displacement pile–improved ground. The drained piles, installed to investigate theimprovement in densification due to draining driving–induced con-tractive pressures, not cyclic stress–induced pore pressures, did notperform noticeably better than the conventional piles. The shallow-est PPTs exhibited the strongest dilative responses, owing to thedevelopment of the larger relative densities at these depths follow-ing pile installation (Fig. 3). In some instances (e.g., at a depth of∼7.5 m in Zones 3 and 4), the response changed from contractive todilative repeatedly. Table 1 summarizes the peak residual ru ob-served at 12 s for all of the PPTs for ease of comparison. Peakresidual ru in the treated zones were up to 22% (absolute) smallerthan those measured in the control zone at similar depths. In gen-eral, the reductions in ru were approximately 2 to 10% (absolute)lower for piles spaced at 3D (i.e., Zones 2 and 4) than those at 5D(i.e., Zones 1 and 3). Although peak residual ru appeared to behigh, liquefaction, as commonly defined (with residual ru > 95 to100%) did not occur.

Excess pore pressures could have been elevated in the treatedzone as compared to the control zone because of the overlappingenergies associated with four shared blast rings. Therefore, the blastenergy experienced by the treated zones was probably larger thanthat experienced in the control zone, and therefore the measure-ments of pore pressure in the treated zone could have been higherthan if a single treated zone was blasted with a single blast ring.However, the magnitude of residual pore pressure is of less concernthan the consequences; these are described subsequently.

Postblasting Settlements of Improved Groundand Piles

A ground surface survey set using a square grid spaced at 1.52 mwas conducted prior to and following blasting of the treated zones.Pile head elevations for piles that were tipped, as well as those that

Fig. 5. Postblast ground surface settlements measured at the controlzone: (a) survey points along Lines A, B, and C; (b) settlements mea-sured along Line A; (c) Line B; (d) Line C

© ASCE 04017047-6 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2017, 143(9): -1--1

Dow

nloa

ded

from

asc

elib

rary

.org

by

OR

EG

ON

ST

AT

E U

NIV

ER

SIT

Y o

n 05

/15/

17. C

opyr

ight

ASC

E. F

or p

erso

nal u

se o

nly;

all

righ

ts r

eser

ved.

Page 7: Performance of Driven Displacement Pile–Improved Ground in Controlled Blasting …timberpilingcouncil.com/wp-content/uploads/2017/08/... · 2017-08-07 · Performance of Driven

were not tipped into the dense bearing layer (approximately 12.5–13 m below grade) were surveyed so as to understand the differ-ences in settlement between the two toe bearing conditions.Following blasting, the settlement of the soil in the treated zonesranged from a minimum of about 15 mm to a maximum of 95 mmas shown in Fig. 8. The majority of observed settlements rangedbetween one-sixth to one-third of those observed at the controlzone. Greater settlements were observed at the northern andsouthern ends of the test area, whereas smaller settlements wereobserved in the middle (Fig. 8). The variation in settlements cor-relates to the spatial distribution of the magnitude of silty finesthroughout the test site, measured using split-spoon samples andestimated using kriging of fines content with calibrated variograms(Bong and Stuedlein 2017). Because the compressibility of siltysands increases with fines content (Bandini and Sathiskumar2009), greater settlements are expected where the concentrationof silty fines are larger.

The settlement response confirms the experimental observationsby Lee and Albaisa (1974) and corresponding analytical modelproposed by Seed et al. (1975; Fig. 1). Soils with relative density

in the range of 70 to 80% such as those densified using drivendisplacement piles experience smaller increase in compressibilityas a result of shaking-induced pore pressures, and therefore smallerpostshaking reconsolidation settlement. Therefore, designers ofdensification-based ground improvement could allow larger peakmagnitudes of ru than those associated with ground improvementmethodologies that do not result in significant densification(e.g., deep soil mixing, jet grouting).

Optical level surveys showed that piles that were not tipped intothe dense sand layer exhibited similar settlements as those of thesurrounding soils. The magnitudes of pile head settlements forrepresentative floating piles ranged from about 55 to 95 mm(Table 2). Adjacent piles that were embedded in dense bearing layerexhibited much lower settlements, ranging from about 0 to 45 mm.Pile compression following dissipation of excess pore pressureoccurs as the downward soil movement relative to the pile shaft(i.e., downdrag) transfers load to the pile (i.e., dragload), and themovement that occurs is commensurate with the magnitude of piletoe resistance to downward movement (Fellenius and Siegel 2008;Wang and Brandenberg 2013). Some piles appeared to heave

0

25

50

75

100

125

150

5 10 15 20 25

r u(%

)

Time (minutes)

z = 8.60 m z = 7.39 m z = 6.34 m z = 5.06 m

0

25

50

75

100

125

0 5 10 15Time (s)

0

25

50

75

100

125

150

5 10 15 20 25

r u(%

)

Time (minutes)

z = 8.99 m z = 7.53 m z = 6.16 m z = 4.95 m

0

25

50

75

100

125

0 5 10 15Time (s)

0

25

50

75

100

125

150

5 10 15 20 25

r u(%

)

Time (minutes)

z = 7.64 m

z = 6.08 m

z = 4.83 m

0

25

50

75

100

125

0 5 10 15Time (s)

0

25

50

75

100

125

150

5 10 15 20 25

r u(%

)

Time (minutes)

z = 8.98 m z = 7.44 m z = 6.07 m z = 5.39 m

0

25

50

75

100

125

0 5 10 15Time (s)

(a) (b)

(c) (d)

Fig. 6. Excess pore pressure generation and dissipation time histories for the improved ground at (a) Zone 1, 5DPVD; (b) Zone 2, 3DPVD; (c) Zone3, 5D; (d) Zone 4, 3D

© ASCE 04017047-7 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2017, 143(9): -1--1

Dow

nloa

ded

from

asc

elib

rary

.org

by

OR

EG

ON

ST

AT

E U

NIV

ER

SIT

Y o

n 05

/15/

17. C

opyr

ight

ASC

E. F

or p

erso

nal u

se o

nly;

all

righ

ts r

eser

ved.

Page 8: Performance of Driven Displacement Pile–Improved Ground in Controlled Blasting …timberpilingcouncil.com/wp-content/uploads/2017/08/... · 2017-08-07 · Performance of Driven

(maximum heave of 25 mm), but this response likely represents anoutcome of the blast program, and would not occur during an earth-quake if supporting embankment, bridge abutment, or struc-tural loads.

Assessment of Blast-Induced Ground Motions

The effects of blasting on excess pore pressures and deformationshave been quantified in the previous discussion, but have not beencorrelated to the ground motions triggered. On the free surface fol-lowing detonation, a wave train consisting of a P wave, an S wave,and a Rayleigh wave are produced and spread out radially from the

epicenter. Nearest to the epicenter, the body wave amplitudes aregreatest and most distinguishable, but decay with distance sothat the ground motions become dominated by Rayleigh waves.The displacement amplitude of body waves decay with the inverseof the radial distance squared, whereas surface waves decay in cor-respondence to the inverse of the square root of radial distance(Richart et al. 1970). Triaxial geophones used to observe theground motions during blasting were positioned at epicentral dis-tances ranging from 24 to 120 m from the center of the blastedareas, and allowed observation of longitudinal (P wave dominant),transverse (S wave dominant) and vertical motions. Comparison ofthe attenuation of displacement amplitudes determined by integrat-ing velocity time histories to the epicentral distances from thecenter of the blast locations showed that the body wave–dominatedground motions transitioned to surface wave–dominated groundmotions between approximately 25 and 38 m, similar to that re-ported by Dowding and Duplaine (2004). The measured near-field(e.g., 25 m) particle motions confirmed that the blast-inducedground motions were dominated by body waves, and thereforecould be used to scale the measured velocity time histories to es-timate those at the center of each blast area.

Scaling of ground motions is possible upon determination of thesite-specific attenuation characteristics. Fig. 9 shows the attenua-tion of the peak vector sum of particle velocity (PPV) for the threeorthogonal velocity components (vertical, longitudinal, and trans-verse) with scaled distance for BE4 and BE5. Scaled distanceis defined as the ratio of hypocentral distance between the pointsof detonation and observation and the square root of the mass of theexplosive charge (Wiss 1981). The peak particle velocities wereconsistently generated by the fourth blast, which consisted of anequivalent of 1.82 kg of TNT at a depth of 8.8 m. The attenuationcharacteristics followed both the general form suggested by Wiss(1981) as well as that reported by Gohl et al. (2001) for liquefactionexperiments in alluvial silty sands. No significant differences be-tween the attenuation characteristics of PPV and individual motioncomponents were noted. Considering the shared attenuation char-acteristics, the near-field ground surface motions can be estimatedreliably using measured near-field velocity time histories andscaled in accordance with the site-specific attenuation relationship.For example, the PPV estimated above the treated zone for BE5using the site-specific attenuation curve in Fig. 9 is 0.44 m=s, rep-resenting a scale factor of approximately 4 for the nearest measuredvelocity time history, observed at an epicentral distance of 24 m and

0

20

40

60

80

100

0 5 10 15

r u(%

)

Time (s)

Zone 3: 4.83 m

Control Zone: 5.25 m

Transition to dilative response

Fig. 7. Example comparison of excess pore pressure response mea-sured for the unimproved control zone to that of improved ground(the transition to a dilative response at approximately 3.7 s for thePPT in the treated Zone 3)

Table 1. Comparison of Peak Residual ru across the Control and TreatedZones (Corresponding to 12 s)

Nominal PPTdepth (m)

Excess pore pressure ratio, ru (%)

Control zone Zone 1 Zone 2 Zone 3 Zone 4

4.6 73 60 61 70 566.1 82 84 77 82 787.6 93 84 80 82 819.1 104 87 82 —a 85aNo PPT at this location.

Fig. 8. Postblasting ground surface settlement (mm) measured at the treated zones

© ASCE 04017047-8 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2017, 143(9): -1--1

Dow

nloa

ded

from

asc

elib

rary

.org

by

OR

EG

ON

ST

AT

E U

NIV

ER

SIT

Y o

n 05

/15/

17. C

opyr

ight

ASC

E. F

or p

erso

nal u

se o

nly;

all

righ

ts r

eser

ved.

Page 9: Performance of Driven Displacement Pile–Improved Ground in Controlled Blasting …timberpilingcouncil.com/wp-content/uploads/2017/08/... · 2017-08-07 · Performance of Driven

dominated by body waves. The scaled ground motion can be com-pared to the development of excess pore pressures to relate theblast-induced motions to those experienced in earthquakes.

Fig. 10 compares the baseline corrected, scaled longitudinal andtransverse acceleration time histories estimated for the groundsurface above the center of treated zones, along with the Arias in-tensity (Arias 1970; Kayen and Mitchell 1997) and excess porepressure ratios for Zone 2. The motions are characterized by coinci-dent (i.e., in-phase) longitudinal and transverse pulses that corre-spond to each detonation. The peak longitudinal and transverseaccelerations are estimated equal to 1.80 and 1.10 g, and occurredduring the fourth and second blasts, respectively. The Arias inten-sity, commonly correlated to the development of excess porepressure in liquefiable deposits, is equal to 17.3 and 3.8 m=s forthe longitudinal and transverse motions, respectively. To relatethe blast-induced ground motions to seismically-induced groundmotions, the sum of azimuthal contributions to Arias intensity(i.e., 21.1 m=s) is equivalent to that expected for rupture of anearby (within 10 km) fault with moment magnitude, M, equalto 7, or M ¼ 8.5 and distance of approximately 100 km (Kayenand Mitchell 1997). Each pulse produces a significant increase

in Arias Intensity to approximately 5 s (or eight blasts); thereafter,the increase in intensity diminishes with reduced acceleration am-plitude, likely because of the damping of energy associated with theonset of large shear strains implied by the measured excess porepressures. The mean period for these motions is approximately0.125 s (or 8 Hz), lower than typical crustal or subduction zoneground motions, which typically range between 0.2 and 1.0 s(Rathje et al. 1998). Peak velocity pulses were similar to crustalearthquake motions (e.g., 1989 Loma Prieta [CDMG Station47381], 1994 Northridge [CDMG Station 24278]; Ancheta et al.2013), ranging from 15 to 41 cm=s and 6 to 20 cm=s for the lon-gitudinal and transverse ground motions, respectively.

Assessment of the Cyclic Stress Reduction DesignApproach

Shear Strain Compatible Design Approach

Baez (1995) proposed a design approach for use with stone column(or aggregate pier) reinforcement with or without the effect ofdensification, whereby a portion of the earthquake-induced cyclicshear stresses within potentially liquefiable soils could be assumedto be diverted to the stiffer reinforcing elements. This designapproach required the assumption of shear strain compatibility(SSC) between the reinforcement and the surrounding soil, imply-ing that the element would not exhibit flexure during strong groundmotion. The designer estimates the cyclic stress ratio using the cur-rent formulation of the simplified method (Seed and Idriss 1971),then sizes the stone column spacing or the area replacement ratio,Ar, until the shear stress reduction factor is low enough to reducethe cyclic stress ratio, CSR, to limit ru to acceptable levels (e.g., 50to 60%; Baez 1995). In this approach the CSR of the unimprovedground, CSRU, at each depth of interest is multiplied by the shearstress reduction factor, KG, given by

KG ¼ 1

Gr½Ar þ 1Grð1 − ArÞ�

ð1Þ

where Gr ¼ Gsc=Gs is the shear modulus ratio; Gsc = shear modu-lus of stone column; and Gs = shear modulus of the soil duringshaking (i.e., accounting for modulus reduction). Stone columnsare generally characterized with Gr between 2 and 7 (Baez andMartin 1993), as a function of the gradation of the stone columnand the stiffness of the surrounding soil.

Since this design approach was developed in 1995, it has beenapplied to a variety of ground improvement techniques. For exam-ple, design guidance for transportation infrastructure in the SecondStrategic Highway Research Program (SHRP2 2015) point to theuse of Eq. (1) for much stiffer reinforcement elements such as deepsoil mixing columns, jet grouted columns, drilled displacementpiles, continuous flight auger piles, and other ground reinforcementtechniques. However, questions regarding the applicability of theSSC assumption have developed as a result of numerical and ana-lytical studies by Olgun and Martin (2008), Gueguin et al. (2013),and Rayamajhi et al. (2014), and centrifuge tests by Rayamajhi et al.(2015). These studies have suggested that flexure of reinforcingelements decreases the magnitude of cyclic shear stresses reduc-tion; however, these findings have not been confirmed at full-scale.The results of the full-scale field trial described in this paper can beused to investigate the appropriateness of the SSC design approachfor very stiff elements.

Table 2. Comparison of Pile Head Settlement of Adjacent Piles with andwithout Embedment into the Dense Sand Layer Following Dissipation ofExcess Pore Pressure

Pile #

Pileembedment

(m)Settlement

(mm)Comparable

pile #

Pileembedment

(m)Settlement

(mm)

1–3 11.3 92 1–7 12.7 181–4 11.5 86 1–5 12.6 62–3 7.0 77 2–19 12.6 342–6 11.6 73 2–16 12.6 463–1 9.1 56 3–3 13.0 153–2 10.1 54 3–15 12.6 93–4 11.4 70 3–25 12.8 344–3 10.7 94 4–20 12.8 214–6 9.5 83 4–14 12.6 04–8 8.5 97 4–20 12.8 214–9 10.0 73 4–4 12.9 12

Fig. 9. Attenuation of peak particle velocity with scaled distancemeasured at the test site for BE4 and BE5, and comparison with thosemeasured by Gohl et al. (2001) in alluvial silty sands

© ASCE 04017047-9 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2017, 143(9): -1--1

Dow

nloa

ded

from

asc

elib

rary

.org

by

OR

EG

ON

ST

AT

E U

NIV

ER

SIT

Y o

n 05

/15/

17. C

opyr

ight

ASC

E. F

or p

erso

nal u

se o

nly;

all

righ

ts r

eser

ved.

Page 10: Performance of Driven Displacement Pile–Improved Ground in Controlled Blasting …timberpilingcouncil.com/wp-content/uploads/2017/08/... · 2017-08-07 · Performance of Driven

Assessment of Cyclic Stress Reduction and ShearStrain Compatibility

The simplified method for liquefaction triggering (Seed and Idriss1971) can be rearranged in terms of shear strains, γcomp, of anyreinforced or composite mass under the assumption of SSC(Baez 1995)

γcomp ¼0.65 · amax · σvo · rd · KG

g · Gcompð2Þ

where amax = peak acceleration; σvo = total vertical stress at a depthof interest; rd = shear stress reduction coefficient; g = gravitationacceleration; and Gcomp = shear modulus of the composite mass.The depth-varying shear stress reduction factor was computedfor Zones 1 and 2 using the assumed invariant shear modulus ofthe timber pile (870 MPa), the depth-varying maximum shearmodulus of the improved soil [estimated using the shear wavevelocity reported by Stuedlein et al. (2016)], Gmax, and thedepth-varying Ar. Owing to modulus reduction during cyclic strain-ing, the shear modulus of the soil used to computeKG was assumedequal to one-third of Gmax at the moment of peak residual excesspore pressure (consistent with the measured excess pore pressuresand modulus reduction described subsequently).

An estimate of amax is required to compute γcomp using Eq. (2)and to illustrate the range in shear strains possible under SSC.Fig. 10 indicates the peak transverse (S wave dominated) groundaccelerations, amax;T , estimated from the measured site-specific at-tenuation characteristics and scaled measurements of velocity timehistories. Accordingly, this intensity measure was used in Eq. (2)for purposes of comparison to the generated excess pore pressure–estimated shear strain curves described subsequently. Because thismagnitude of amax is generally higher than those associated withtypical seismically-induced strong ground motions, hypotheticalshear strains are computed for the case of amax;EQ ¼ 0.40 g to pro-vide an appropriate context for applicability under earthquake load-ing (n.b., this assumes M ¼ 7.5). Separately, a simplified approachto map measured ru to a first order estimate of shear strain is illus-trated in Fig. S1 as described in Supplemental Appendix S1, andthis approach is used to make a direct comparison of estimated insitu shear strains induced in the displacement pile-improved groundto those calculated under SSC. This approach relies on the modulusreduction curves for South Carolina soils by Zhang et al. (2005),the PPT measurements of peak residual ru presented previously,and interpolation of ru for locations in between the PPTs.

Fig. 11 presents the amax-varying and depth-varying shearstrains computed under SSC along with the range in ru-shear straincurves reported by Dobry et al. (1982) for Monterey 0 sand with

0

20

40

60

80

100

120

r u(%

) an

d A

rias

Inte

sity

(%

)

z = 4.95 m

z = 6.16 m

z = 7.53 m

z = 8.99 m

0

25

50

75

100

-2

-1

0

1

2

Ari

as In

ten

sity

(%

)

Lo

ng

itu

din

al A

ccel

erat

ion

(g

)

Longitudinal ground motion

Arias Intensity,

1.80

100% = 17.3 m/sec -2.0

-1.5

-1.0

-0.5

0.0

0.5

1.0

1.5

2.0

-100

-75

-50

-25

0

25

50

75

100

1st Last

r u

z = 4.95 m

0

25

50

75

100

-2

-1

0

1

2

0 1 2 3 4 5 6 7 8 9 10 11 12

Ari

as In

ten

sity

(%

)

Tran

sver

se A

ccel

erat

ion

(g

)

Time (seconds)

Transverse ground motion

Arias Intensity,

1.10

100% = 3.84 m/sec -1.0

-0.8

-0.6

-0.4

-0.2

0.0

0.2

0.4

0.6

0.8

1.0

-100

-75

-50

-25

0

25

50

75

100

1st Last

r u

z = 8.99 m

Transverse

Longitudinal(a)

(b)

(c)

Fig. 10. Comparison of ground motion characteristics to generation of excess pore pressure for treated Zone 2: (a) comparison of normalized Ariasintensity to excess pore pressure time history; (b) comparison of scaled longitudinal ground motion with normalized Arias intensity; (c) comparison ofscaled transverse ground motion with normalized Arias intensity; insets show the first and last acceleration pulse with measured excess pore pressure

© ASCE 04017047-10 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2017, 143(9): -1--1

Dow

nloa

ded

from

asc

elib

rary

.org

by

OR

EG

ON

ST

AT

E U

NIV

ER

SIT

Y o

n 05

/15/

17. C

opyr

ight

ASC

E. F

or p

erso

nal u

se o

nly;

all

righ

ts r

eser

ved.

Page 11: Performance of Driven Displacement Pile–Improved Ground in Controlled Blasting …timberpilingcouncil.com/wp-content/uploads/2017/08/... · 2017-08-07 · Performance of Driven

isotropic consolidation pressures ranging from 25 to 100 kPa andDr ranging from 45 to 80% for comparison. Fig. 11 shows that thedepth-varying shear strains estimated under SSC can vary overseveral orders of magnitude depending on the magnitude of shak-ing intensity and area replacement ratios considered. For example,the range in shear strains computed under SSC for Zone 1,with a pilehead spacing of 5D, and for amax;T is consistent with those inferredfrom the excess pore pressure measurements (Appendix S1). Con-versely, the excess pore pressures associated with strains computedunder SSC are significantly lower than those measured for pilesspaced at 3D (i.e., Zone 2, with Ar ¼ 8.7% at the ground surfaceand 3.6% at the bearing layer). The range in ru and correspondingshear strain reported by Dobry et al. (1982) shows that the mea-sured excess pore pressures cannot be associated with the magni-tude of strains under SSC for Zone 2 with pile head spacing of 3D.Rather, the estimated shear strain associated with the measured ru,also shown in Fig. 11, is consistent with the data reported by Dobryet al. (1982), NRC (1985), and blast-induced liquefaction experi-ments of unreinforced ground reported by Gohl et al. (2001).Conversely, if one considers the lower intensity of shaking morecommonly associated with earthquake-induced ground motions(i.e., amax;EQ ¼ 0.40 g and M ¼ 7.5), one would conclude thatno excess pore pressures would have been generated in Zone 2.

The observations regarding SSC can be explained by the flexurethat the timber piles likely exhibited during the blast-inducedground motions, which limits diversion of shear stresses to thestiffer pile element (Rayamajhi et al. 2014). Fresh cracking aroundthe soil-pile interface was noted in the field following blasting, andthis pointed to possible cyclic gapping between the soil and thepile during the blast-induced ground motions, which would havelimited a composite or strain-compatible response. Based onnumerical and analytical models (Olgun and Martin 2008;

Gueguin et al. 2013; Rayamajhi et al. 2014), centrifuge model tests(Rayamajhi et al. 2015), and the field tests described in this paper,the use of the shear strain compatibility assumption and corre-sponding design approach for relatively stiff reinforcement lique-faction mitigation ground improvement may not be appropriate.

Summary and Conclusions

Full-scale, controlled blasting field tests on driven displacementpile-improved ground were conducted to study the response of den-sified and reinforced ground to blast-induced excess pore pressures.This paper described controlled blasting of unimproved ground us-ing sufficient explosive charges to induce liquefaction and the re-sulting postliquefaction settlements measured to provide a baselinefor comparison against the improved ground. Excess pore pressuresgenerated in the improved ground were observed to be smaller thanthat in the unimproved ground, and resulted in settlements that weregenerally one-sixth to one-third of that measured in the unimprovedground. Piles tipped into a dense bearing layer settled significantlyless than those in the surrounding soil. Importantly, measured ex-cess pore pressures pointed to a change in response from contrac-tive to dilative during execution of the cyclic detonation pattern,indicating that the improved ground mobilized significant strengthduring blasting, representative of soils densified by the installationof the displacement piling.

In order to help compare this work to and place it within thecontext of earthquake-induced ground motions, a site-specific at-tenuation relationship was generated from measured ground veloc-ity time histories. The attenuation characteristics were similar tothose reported for other liquefiable sites and suggested that groundmotions could be confidently estimated above the center of the

2

4

6

8

10

(a) (b)

0.001% 0.010% 0.100% 1.000%

Dep

th (

m)

Shear Strain

Estimated Strains Strains under SSCwith Estimated Strain Range in (Dobry 1985)

0.00

0.25

0.50

0.75

1.000.01% 0.10% 1.00%

Exc

ess

Po

re

Pre

ssu

re R

atio

, ru

Shear Strain

ru

amax,T = 1.10g

ru

amax,EQ = 0.40g

Fig. 11. Comparison of shear strains estimated using the SSC design approach for the transverse and selected peak ground accelerations to thoseestimated using measured excess pore pressures and shear modulus reduction curves: (a) piles in Zone 1 and spaced at 5D, with Ar ¼ 3.1% at theground surface and reducing to 1.4% at the bearing layer; (b) piles in Zone 2, spaced at 3D, with Ar ¼ 8.7% at the ground surface and 3.6% at thebearing layer

© ASCE 04017047-11 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2017, 143(9): -1--1

Dow

nloa

ded

from

asc

elib

rary

.org

by

OR

EG

ON

ST

AT

E U

NIV

ER

SIT

Y o

n 05

/15/

17. C

opyr

ight

ASC

E. F

or p

erso

nal u

se o

nly;

all

righ

ts r

eser

ved.

Page 12: Performance of Driven Displacement Pile–Improved Ground in Controlled Blasting …timberpilingcouncil.com/wp-content/uploads/2017/08/... · 2017-08-07 · Performance of Driven

blasted areas. Peak ground accelerations thus estimated rangedfrom 1.1 to 1.8 g for transverse and longitudinal components, withmean periods of about 8 Hz, consistent with previously reportedcharacteristics of blast-induced ground motions. The correspondingArias intensity suggested that the blast program produced similarintensity as a moment magnitude 7.0 earthquake within a 10 kmfault-rupture distance.

An assessment of the commonly-used shear strain compatibilityassumption for use with reinforcement-based ground improvementmethods was conducted by inferring shear strains from excesspore pressure measurements. Shear strains computed assuming acomposite, compatible reinforced mass were inconsistent withthose estimated in the improved ground, as well as inconsistentwith the measured excess pore pressures for the case of pile headspacing at three diameters (with a range in area replacement ratio of8.7–3.6%). Moreover, the estimated shear strain-excess pore pres-sure response of the improved soils at the test site compared favor-ably to the shear strain–excess pore pressure response of sandysoils reported in the literature. These comparisons, as well as thoserecently reported and based on numerical and centrifuge studies,suggest that the assumption of shear strain–compatible deformationfor use with reinforcement-based liquefaction mitigation groundimprovement design methodologies may not be appropriate.

Acknowledgments

The authors wish to thank the sponsors of this research, whichincludes the IDEA Program of the National Cooperative HighwayResearch Program, National Academy of Science, under GrantNCHRP-180, and the South Carolina chapter of the Pile DrivingContractors Association (PDCA). The authors gratefully acknowl-edge the significant effort by Van Hogan, formerly of the PDCA, aswell as the member firms that have contributed materials, labor, andequipment: Pile Drivers, Inc., S&ME, Inc., Soil Consultants, Inc.,Chuck Dawley Surveying, Cox Wood Industries, and HaywardBaker, Inc. The authors also thank the anonymous reviewers fortheir comments and suggestions.

Supplemental Data

Fig. S1 and other material are available online in the ASCE Library(www.ascelibrary.org).

References

Ancheta, T. D., et al. (2013). “PEER NGA-West2 database.” PEER Rep.2013/03, Pacific Earthquake Engineering Research Center, UCBerkeley, Berkeley, CA.

Arias, A. (1970). “A measure of earthquake intensity.” Seismic design fornuclear power plants, R. J. Hansen, ed., MIT Press, Cambridge, MA.

Ashford, S. A., Rollins, K. M., and Baez, J. I. (2000a). “Comparison ofdeep foundation performance in improved and non-improved groundusing blast-induced liquefaction.” Soil dynamics and liquefaction,ASCE, Reston, VA, 20–34.

Ashford, S. A., Rollins, K. M., Bradford, V. S. C., Weaver, T. J., and Baez,J. I. (2000b). “Liquefaction mitigation using stone columns arounddeep foundations: Full-scale test results.” Transp. Res. Rec., 1736(1),110–118.

Ashford, S. A., Rollins, K. M., and Lane, J. D. (2004). “Blast-inducedliquefaction for full-scale foundation testing.” J. Geotech. Geoenviron.Eng., 10.1061/(ASCE)1090-0241(2004)130:8(798), 798–806.

Baez, J. I. (1995). “A design model for the reduction of soil liquefactionby vibro-stone columns.” Ph.D. thesis, Univ. Southern California,Los Angeles, 222.

Baez, J. I., and Martin, G. R. (1993). “Advances in the design of vibrosystems for the improvement of liquefaction resistance.” Proc., Symp.on Ground Improvement, Vancouver Geotechnical Society, Vancouver,BC, Canada.

Bandini, P., and Sathiskumar, S. (2009). “Effects of silt content and voidratio on the saturated hydraulic conductivity and compressibility ofsand-silt mixtures.” J. Geotech. Geoenviron. Eng., 10.1061/(ASCE)GT.1943-5606.0000177, 1976–1980.

Bong, T., and Stuedlein, A. W. (2017). “Spatial variability of CPT param-eters and silty fines in liquefiable beach sands.” J. Geotech. Geoenv.Eng., in press.

Camp, W. M., Mayne, P. W., and Rollins, K. M. (2008). “Cone penetrationtesting before, during, and after blast-induced liquefaction.” Geotech-nical earthquake engineering soil dynamics IV, ASCE, Reston, VA.

Cox, B. R., Stokoe, K. H., and Rathje, E. M. (2009). “An in situ test methodfor evaluating the coupled pore pressure generation and nonlinear shearmodulus behavior of liquefiable soils.” Geotech. Test. J., 32(1), 11–21.

Dobry, R., Ladd, R. S., Yokel, F. Y., Chung, R. M., and Powell, D. (1982).“Prediction of pore water pressure buildup and liquefaction of sandsduring earthquakes by the cyclic strain method.” U.S. Dept. of Com-merce, National Bureau of Standards, Washington, DC, 150.

Dowding, C. H., and Duplaine, H. (2004). State of the art in blast densi-fication or explosive compaction, Vol. 2. Magnan, ed., Presses del’ENPC/LCPC, Paris, 505–514.

Dowding, C. H., and Hryciw, R. D. (1986). “A laboratory study of blastdensification of saturated sand.” J. Geotech. Eng., 10.1061/(ASCE)0733-9410(1986)112:2(187), 187–199.

Fellenius, B. H., and Siegel, T. C. (2008). “Pile design considerations in aliquefaction event.” J. Geotech. Geoenviron. Eng., 10.1061/(ASCE)1090-0241(2008)134:9(1412), 1412–1416.

Gianella, T. N. (2015). “Ground improvement and liquefaction mitigationusing driven timber piles.” M.S. thesis, Oregon State, Univ., Corvallis,OR.

Gianella, T. N., Stuedlein, A. W., and Canivan, G. J. (2015). “Densificationof liquefiable soils using driven timber piles.” 6th Int. Conf. on Earth-quake Geotechnical Engineering, Christchurch, New Zealand, 9.

Gohl, W. B., Howie, J. A., and Rea, C. E. (2001). “Use of controlleddetonation of explosives for liquefaction testing.” Proc., 4th Int. Conf.on Recent Advances in Geotechnical Earthquake Engineering and SoilDynamics, Univ. of Missouri-Rolla, Rolla, MO.

Gohl, W. B., Martin, T., and Elliott, R. J. (2010). “Explosive compaction ofgranular soils and in-situ liquefaction testing using sequential detona-tion of explosives.” Ground improvement technologies and case histor-ies, C. F. Leugn, J. Chu, and R. F. Shen, eds., Research PublishingService, Singapore, 809.

Gueguin, M., de Buhan, P., and Hassen, G. (2013). “A homogenizationapproach for evaluating the longitudinal shear stiffness of reinforcedsoils: Column versus cross trench configuration.” Int. J. Numer. Anal.Methods Geomech., 37(18), 3150–3172.

Hryciw, R. D. (1986). “A study of the physical and chemical aspects of blastdensification of sand.” Ph.D. thesis, Northwestern Univ., Evanston, IL,229.

Ishihara, K., Tatsuoka, F., and Yasuda, S. (1975). “Undrained deformationand liquefaction of sand under cyclic stresses.” Soils Found., 15(1),29–44.

Ishihara, K., and Yoshimine, M. (1992). “Evaluations of settlements in sanddeposits following liquefaction during earthquakes.” Soils Found.,32(1), 173–188.

Kayen, R., and Mitchell, J. (1997). “Assessment of liquefaction potentialduring earthquakes by arias intensity.” J. Geotech. Geoenviron. Eng.,10.1061/(ASCE)1090-0241(1997)123:12(1162), 1162–1174.

Kramer, S. L. (1996). Geotechnical earthquake engineering, Prentice Hall,Upper Saddle River, NJ, 653.

Lee, K. L., and Albaisa, A. (1974). “Earthquake induced settlements insaturated sands.” J. Geotech. Eng. Div., 100(4), 387–406.

Mahvelati, S., Coe, J. T., Stuedlein, A. W., Asabere, P., and Gianella, T. N.(2016). “Time-rate variation of shear wave velocity (site stiffness) fol-lowing blast-induced liquefaction.” GSP No. 278, ASCE, Reston, VA.

Narin van Court, W. A., and Mitchell, J. K. (1994). “Soil improvement byblasting.” J. Explos. Eng., 12(3), 34–41.

© ASCE 04017047-12 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2017, 143(9): -1--1

Dow

nloa

ded

from

asc

elib

rary

.org

by

OR

EG

ON

ST

AT

E U

NIV

ER

SIT

Y o

n 05

/15/

17. C

opyr

ight

ASC

E. F

or p

erso

nal u

se o

nly;

all

righ

ts r

eser

ved.

Page 13: Performance of Driven Displacement Pile–Improved Ground in Controlled Blasting …timberpilingcouncil.com/wp-content/uploads/2017/08/... · 2017-08-07 · Performance of Driven

NRC (National Research Council). (1985). “Liquefaction of soils duringearthquakes.” Rep. No. CETS-EE-001, National Academy Press,Washington, DC.

Olgun, C. G., and Martin, J. R. (2008). “Numerical modeling of the seismicresponse of columnar reinforced ground.” Geotechnical earthquakeengineering soil dynamics IV, ASCE, Reston, VA.

Rathje, E. M., Abrahamson, N. A., and Bray, J. D. (1998). “Simplified fre-quency content estimates of earthquake ground motions.” J. Geotech.Geoenv. Eng., 124(2), 150–159.

Rayamajhi, D., et al. (2014). “Numerical study of shear stress distributionfor discrete columns in liquefiable soils.” J. Geotech. Geoenviron. Eng.,10.1061/(ASCE)GT.1943-5606.0000970, 04013034.

Rayamajhi, D., et al. (2015). “Dynamic centrifuge tests to evaluate reinforc-ing mechanisms of soil-cement columns in liquefiable sand.” J.Geotech. Geoenviron. Eng., 10.1061/(ASCE)GT.1943-5606.0001298,04015015.

Richart, F. E., Hall, J. R., and Woods, R. D., (1970). Vibrations of soils andfoundations, Prentice-Hall, Inc., Englewood Cliffs, NJ, 414.

Rollins, K. M., Anderson, J., McCain, A., and Goughnour, R. (2004).“Vertical composite drains for mitigating liquefaction hazard.” 13thInt. Offshore and Polar Engineering Conf., ISOPE, Mountain View,CA, 498–505.

Rollins, K. M., Gerber, T. M., Lane, J. D., and Ashford, S. A. (2005).“Lateral resistance of a full-scale pile group in liquefied sand.” J. Geo-tech. Geoenviron. Eng., 10.1061/(ASCE)1090-0241(2005)131:1(115),115–125.

Rollins, K. M., Hales, L. J., Ashford, S. A., and Camp, W. M. (2006). “P-ycurves for large diameter shafts in liquefied sand from blast liquefactiontests.” Seismic performance and simulation of pile foundations, ASCE,Reston, VA, 11–23.

Rollins, K. M., and Strand, S. R. (2006). “Downdrag forces due to lique-faction surrounding a pile.” Proc., 8th National Conf. on EarthquakeEngineering, Earthquake Engineering Research Institute, Oakland,CA, 10.

Schaefer, V. R., Abramson, L. W., Drumheller, J. C., Hussin, J. D., andSharp, K. D. (1997). “Ground improvement, ground reinforcement,

ground treatment.” Geotechnical Special Publication No. 69, ASCE,Reston, VA.

Seed, H. B. (1979). “Soil liquefaction and cyclic mobility evaluation forlevel ground during earthquakes.” J. Geotech. Eng. Div., 105(2),201–255.

Seed, H. B., and Idriss, I. M. (1971). “Simplified procedure for evaluatingsoil liquefaction potential.” J. Geotech. Eng. Div., 97(9), 1249–1273.

Seed, H. B., Martin, P. P., and Lysmer, J. (1975). “The generation and dis-sipation of pore water pressures during soil liquefaction.” EERC 75-26,Univ. of California, Berkeley, CA.

SHRP2 (Second Strategic Highway Research Program). (2015). “Geotech-nical solutions for soil improvement, rapid embankment construction,and stabilization of the pavement working platform.” ⟨http://www.geotechtools.org/⟩ (Nov. 17, 2015).

Stuedlein, A. W., Gianella, T. N., and Canivan, G. (2016). “Densification ofgranular soils using conventional and drained timber displacementpiles.” J. Geotech. Geoenviron. Eng., 10.1061/(ASCE)GT.1943-5606.0001554, 04016075.

Tokimatsu, K., and Seed, H. B. (1987). “Evaluation in settlements of sandsdue to earthquake shaking.” J. Geotech. Eng., 10.1061/(ASCE)0733-9410(1987)113:8(861), 861–878.

Wang, R., and Brandenberg, S. (2013). “Beam on nonlinear Winkler foun-dation and modified neutral plane solution for calculating downdragsettlement.” J. Geotech. Geoenviron. Eng., 10.1061/(ASCE)GT.1943-5606.0000888, 1433–1442.

Weaver, T. J., Ashford, S. A., and Rollins, K. M. (2005). “Lateral resistanceof a 0.6 m drilled shaft in liquefied sand.” J. Geotech. Geoenviron. Eng.,10.1061/(ASCE)1090-0241(2005)131:1(94), 94–102.

Wiss, J. F. (1981). “Construction vibrations: State-of-the-art.” J. Geotech.Eng. Div., 107, 167–181.

Zhang, J., Andrus, R., and Juang, C. (2005). “Normalized shear modulusand material damping ratio relationships.” J. Geotech. Geoenviron.Eng., 10.1061/(ASCE)1090-0241(2005)131:4(453), 453–464.

Zhang, J. M., Shamoto, Y., and Tokimatsu, K. (1997). “Moving critical andphase transformation stress state lines of saturated sand during un-drained cyclic shear.” Soils Found., 37(2), 51–59.

© ASCE 04017047-13 J. Geotech. Geoenviron. Eng.

J. Geotech. Geoenviron. Eng., 2017, 143(9): -1--1

Dow

nloa

ded

from

asc

elib

rary

.org

by

OR

EG

ON

ST

AT

E U

NIV

ER

SIT

Y o

n 05

/15/

17. C

opyr

ight

ASC

E. F

or p

erso

nal u

se o

nly;

all

righ

ts r

eser

ved.


Recommended