Date post: | 12-Feb-2017 |
Category: |
Documents |
Upload: | charl-eksteen |
View: | 65 times |
Download: | 0 times |
CHARL EKSTEEN
LEADING HAND BOILERMAKER
PERSONAL ACHIEVEMENTS
BOKONI PLATINUM MINES
SURFACE ORE STORAGE FACILITY
ORE HANDLING SYSTEM UPGRADE DECEMBER 2015
After being addressed by the SHE department and management to improve the current ore
handling system, with reference to previous success on all my projects, I accepted the challenge
and proceeded with a positive and safe mind set due to the fact that I enjoy challenges. During
this period I was acting as senior foreman/general engineering supervisor and I could utilize this
opportunity to proceed with the planning and presentation, until I were back on the floor.
SCOPE OF WORK
Planning, upgrading of current system, estimating, technical details and drafting of new
drawings, ordering of material from selected suppliers, fabricating, oversee installing
phase and commissioning of the new system. This includes refurbishing of the 6 mᶾ two
stage feeder pan. This were done as per MHSA and company procedure consisting of:
Investigating of the area together with the chief safety officer to identify all
hazards and risks
Drafting of an issue based risk assessment whereby all hazards and risks were
identified and control measures were put in place to eliminate or minimize the
concern
Ongoing hazard identification and risk assessments were done and controlled. This
data were captured and sent to the safety department on a daily basis
The feeder pan had to be disassembled and dye penetrant tested for cracks. Fortunately it
passed the test and we proceeded with the assembling as follows:
Replacement of all fasteners with electro galvanised swage fast high grip bolts.
Where it was impossible to insert the swage dolly we used electro galvanised GR
8.8 bolts complete with “sham lock” washers and “Cleve lock” nuts.
Replacement of all hard wearing body plates (liners) with 16 thick VRN 500 hard
wearing plates as per OEM specification, complete with electro galvanised, de-
embrittled Allen cap bolts, “sham lock” washers and “Cleve lock” nuts. The liner
plates were cut and countersunk drilled to reference drawings drafted by myself.
RESOURCES
No reference drawings were available. The new design were drafted by me, designed and
drawn, thereafter scrutinised and reviewed by a professional team consisting of:
Engineering manager
Structural engineer
Project and designing engineering consultant
Civil engineer
Engineering specialist
Section engineer
After revising the design only two amendments were done on the civil section
REPORTING STRUCTURE
Production manager
Engineering manager
Section engineer
Foreman
Constant liaising with the planned maintenance officer, estimator and senior
accountant to stay within financial margins and creating of planned maintenance
orders for future reference
AIM
To implement a cost saving initiative by inviting different suppliers to tender on this
project in order to compare costs
Utilizing existing resources and employees, also provide on the job training
Ensuring constant communication and strategic planning
Ensure to stay one step ahead, this will be positive towards the deadline
Allow enough window period for the commissioning phase, not to affect the concentrator
production schedule
Fabrication to be done neat, accurate, ergonomic and above average quality
FINANCIAL FACTORS (estimated to nearest value)
Allocated – R 1 600 000.00
Tender A – R 900 000.00 excluding installation
Tender B – R 820 000.00 excluding installation
Tender C – R 1 450 000.00 including installation, rigging to be done by the
company
Total estimation from myself – R 900 000.00 completing the whole project
Sub factors leading to such a huge saving
Utilised material that were already on site – minimum material were
obtained
Negotiating a good hourly rate with the mobile hydraulic crane supplier.
As it were December I suggest we hire the crane at a descent rate which
will generate income for his company, or he could let the crane stand in his
crane yard without generating income. As one of our sites also required a
mobile crane this period, the costs were split up between the two cost
centres
Body liner plates were cut and drilled to size which were a huge time and
cost saving as no extra labour or oxy-acetylene equipment were necessary
All consumables such as MIG wire, oxygen, acetylene, high tensile
fasteners and lock nuts and correct primer and final painting were
obtained from the company’s stock ledger or existing on site.
No unnecessary labour were utilized and overtime were kept to a
minimum through proper planning
Learner platers were given the opportunity to gain priceless experience
As mentioned earlier I allowed enough time to stay within the allowable
margin given by the company
The final bottom line added up to just over R 1 000 000.00, which still gave us a saving of R
600 000.00. However I were not awarded any kind of prize, the satisfaction that the project were
successful with no injury or time lost, made it priceless.
PREVIOUS MAJOR PROJECTS OR PROCEDURES MANAGED BY ME OR BEING INVOLVED
April 2007 - ore loading station facility underground to surface on the east compartment.
Managed, fabricate and install a new complete measuring flask
December 2007 - ore loading station facility underground to surface on the west
compartment. Managed, fabricate and install a new complete measuring flask
April 2008 - ore loading station facility underground to surface on the east compartment.
Managed, fabricate and install a new complete control chute
September 2008 - ore loading station facility underground to surface on the west
compartment. Managed, fabricate and install a new complete control chute
December 2008 - rock winder replacement of the gearbox. I assisted in the planning and
installation and the consulting were done by Coilmech which is part of ABB nowadays
January 2009 - rock winder replacement of drum bushes, I assisted with installation
April 2009 – man winder replacement of drum bushes, I assisted with installation and the
consulting were done by Coilmech which is part of ABB nowadays
September 2009 – headgear feeder pan. Planned, managed and installed a new feeder
supplied by Vipro. All existing support steel work were replaced
February 2010 – waste ore storage silo. Managed, fabricate and install a new complete
emergency side chute
October 2011 – run-off-mine (ROM) conveyer system. Managed, fabricate and install a
new complete ore handling system
December 2012 – water handling main pump station underground. I assisted in the
planning and installation of a new pump system. This project included designing of new
pump and motor support structures
April 2013 – rock winder. I assisted in the planning and installation of new groove plates
(wrapper plates) on the drum shell. This significantly increased the life span of the winder
steel rope after experiencing a lot of bad coiling. The consulting was done by ABB
February 2014 – compressed air plant. I assisted with the planning, installation and
commissioning on a water treatment system on both the open and closed circuit systems.
The purification system were designed and supplied by WESU eco-friendly treatment
August 2014 - ore loading station facility underground to surface on the east
compartment. Managed, fabricate and install a new complete control chute after
experiencing a massive mud rush and damaged by blasting. This were done in a record
time
December 2014 - man winder. I assisted in the planning and installation of new groove
plates (wrapper plates) on the drum shell. This significantly increased the life span of the
winder steel rope after experiencing a lot of bad coiling. The consulting was done by ABB
February 2015 - ore loading station facility underground to surface on the west
compartment. Managed, fabricate and install a new complete measuring flask, upgraded
landing facility to ensure better access for safe maintenance purposes
July 2015 - ore loading station facility underground to surface on the east compartment.
Managed, fabricate and install a new complete measuring flask, upgraded landing facility
to ensure better access for safe maintenance purposes
I was also involved with huge breakdowns on the compressors. This happened on various
occasions and every breakdown had to be rectified in a record time not to interfere with
production. Breakdowns normally resulted due to bad water causing damage to the
intercoolers, as we do struggle with very low quality of water. We are currently preparing a
presentation which involved various water engineers. The current purification system works
well on the open circuit but we still experience challenges on the closed circuit even by using
chemicals.
Kindly view pictures below as I proceeded with the 510 silo project.