+ All Categories
Home > Education > PertGanttchart

PertGanttchart

Date post: 12-Jul-2015
Category:
Upload: learnt
View: 262 times
Download: 0 times
Share this document with a friend
41
Can you imagine starting a long car trip to an unfamiliar destination without a map or navigation system? You're pretty sure you have to make some turns here and there, but you have no idea when or where, or how long it will take to get there . You may arrive eventually, but you run the risk of getting lost, and feeling frustrated, along the way .
Transcript
Page 1: PertGanttchart

Can you imagine starting a long car trip toan unfamiliar destination without a map ornavigation system?

You're pretty sure you have to make someturns here and there, but you have no ideawhen or where, or how long it will take to getthere.

You may arrive eventually, but you runthe risk of getting lost, and feeling frustrated,along the way.

Page 2: PertGanttchart

Essentially, driving without any idea ofhow you're going to get there is the same asworking on a project without a schedule.

No matter the size or scope of yourproject, the schedule is a key part of projectmanagement.

The schedule tells you when each activityshould be done, what has already beencompleted, and the sequence in which thingsneed to be finished.

Page 3: PertGanttchart

Luckily, drivers have fairly accurate tools theycan use. Scheduling, on the other hand, is not anexact process. It's part estimation, part prediction,and part 'educated guessing.‘ Because of theuncertainty involved, the schedule is reviewedregularly, and it is often revised while the project isin progress.

It continues to develop as the project movesforward, changes arise, risks come and go, and newrisks are identified. The schedule essentiallytransforms the project from a vision to a time-basedplan.

Page 4: PertGanttchart

Project Schedule also help you do the following:

They provide a basis for you to monitor and controlproject activities

They help you determine how best to allocate resourcesso you can achieve the project goal

They help you assess how time delays will impact theproject

You can figure out where excess resources are availableto allocate to other projects

They provide a basis to help you track project progress

Page 5: PertGanttchart

Personal and project calendars – Understandingworking days, shifts, and resource availability iscritical to completing a project schedule.

Description of project scope – From this, you candetermine key start and end dates, majorassumptions behind the plan, and key constraintsand restrictions. You can also include stakeholderexpectations, which will often determine projectmilestones.

Page 6: PertGanttchart

Project risks – You need to understand this to makesure there's enough extra time to deal withidentified risks – and with unidentified risks (risksare identified with thorough Risk Analysis).

Lists of activities and resource requirements –It'simportant to determine if there are otherconstraints to consider when developing theschedule. Understanding the resource capabilitiesand experience you have available – as well ascompany holidays and staff vacations – will affectthe schedule.

Page 7: PertGanttchart

Schedule Network Analysis – This is a graphicrepresentation of the project's activities, the time ittakes to complete them, and the sequence in whichthey must be done.

Project management software is typically used tocreate these analyses – Gantt charts and PERTCharts are common formats.

Page 8: PertGanttchart

Critical Path Analysis – This is the, and

calculating the 'best line' – or critical path – to takeso that you'll complete the project in the minimumamount of time.

The method calculates the earliest and latestpossible start and finish times for project activities,and it estimates the dependencies among them tocreate a schedule of critical activities and dates.

Page 9: PertGanttchart

Schedule Compression – This tool helps shorten thetotal duration of a project by decreasing the timeallotted for certain activities. It's done so that youcan meet time constraints, and still keep the originalscope of the project. You can use two methods here:

Crashing – This is where you assign more resourcesto an activity, thus decreasing the time it takes tocomplete it.

This is based on the assumption that the timeyou save will offset the added resource costs.

Page 10: PertGanttchart

Fast-Tracking – This involves rearranging activities toallow more parallel work. This means that thingsyou would normally do one after another are nowdone at the same time.

However, do bear in mind that this approachincreases the risk that you'll miss things, or fail toaddress changes.

Page 11: PertGanttchart

These activities need to be completed in asequence, with each stage being more-or-less completed before the next stage canbegin. These are 'sequential' activities.

Other activities are not dependent oncompletion of any other tasks. You can dothese at any time before or after a particularstage is reached. These are non-dependentor 'parallel' tasks.

Page 12: PertGanttchart

Step 1. List all activities in the planFor each activity, show the earliest

start date, estimated length of time itwill take, and whether it is parallel orsequential.

If tasks are sequential, showwhich stage they depend on.

Page 13: PertGanttchart

Task Earliest start Length TypeDependent

on...

A. High level analysis Week 0 1 week Sequential

B. Selection of hardware platform Week 1 1 day Sequential A

C. Installation and commissioning of hardware

Week 1.2 2 weeks Parallel B

D. Detailed analysis of core modules Week 1 2 weeks Sequential A

E. Detailed analysis of supporting modules

Week 3 2 weeks Sequential D

F. Programming of core modules Week 3 2 weeks Sequential D

G. Programming of supporting modules Week 5 3 weeks Sequential E

Page 14: PertGanttchart

Task Earliest start Length TypeDependent

on...

H. Quality assurance of core modules Week 5 1 week Sequential F

I. Quality assurance of supporting modules Week 8 1 week Sequential G

J. Core module training Week 6 1 day Parallel C,H

K. Development and QA of accounting reporting Week 5 1 week Parallel E

L. Development and QA of management reporting

Week 5 1 week Parallel E

M. Development of Management Information System

Week 6 1 week Sequential L

N. Detailed training Week 9 1 week Sequential I, J, K, M

Page 15: PertGanttchart

Critical Path Analysis are presented using circle and arrow diagrams. In these,circles show events within the project, such as the start and finish of tasks.

The number shown in the left hand half of the circle allows you to identify eachone easily. Circles are sometimes known as nodes.

An arrow running between two event circles shows the activity needed tocomplete that task.

A description of the task is written underneath the arrow. The length of the taskis shown above it. By convention, all arrows run left to right. Arrows are alsosometimes called arcs.

Page 16: PertGanttchart

This shows the start event (circle 1), and thecompletion of the 'High Level Analysis' task(circle 2).

The arrow between them shows the activity ofcarrying out the High Level Analysis. This activityshould take 1 week.

Page 17: PertGanttchart

Here the activities of 'Select Hardware' and 'Core Module Analysis' cannot bestarted until 'High Level Analysis' has been completed. This diagram also bringsout a number of other important points:

Within Critical Path Analysis, we refer to activities by the numbers in the circlesat each end. For example, the task 'Core Module Analysis' would be calledactivity 2 to 3. 'Select Hardware' would be activity 2 to 9.

Page 18: PertGanttchart

Activities are not drawn to scale. In the diagram above, activitiesare 1 week long, 2 weeks long, and 1 day long. Arrows in this caseare all the same length.

In the example above, you can see a second number in the top,right hand quadrant of each circle. This shows the earliest starttime for the following activity. It is conventional to start at 0. Hereunits are whole weeks.

Page 19: PertGanttchart

Here activity 6 to 7 cannot start until theother four activities (11 to 6, 5 to 6, 4 to 6,and 8 to 6) have been completed.

Page 20: PertGanttchart
Page 21: PertGanttchart

The program (or project) evaluation and

review technique, commonly abbreviated

PERT, is a statistical tool, used in project

management, which was designed to

analyze and represent the tasks involved in

completing a given project.

First developed by the United States Navy

in the 1950s, it is commonly used in

conjunction with the critical path method

(CPM).

Page 22: PertGanttchart

The program (or project) evaluation and

review technique, commonly abbreviated

PERT, is a statistical tool, used in project

management, which was designed to

analyze and represent the tasks involved in

completing a given project.

First developed by the United States Navy

in the 1950s, it is commonly used in

conjunction with the critical path method

(CPM).

Page 23: PertGanttchart

ActivityPredecess

or

Time estimatesExpected

timeOpt. (O) Normal (M) Pess. (P)

A — 2 4 6 4.00

B — 3 5 9 5.33

C A 4 5 7 5.17

D A 4 6 10 6.33

E B, C 4 5 7 5.17

F D 3 4 8 4.50

G E 3 5 8 5.17

Page 24: PertGanttchart
Page 25: PertGanttchart
Page 26: PertGanttchart

A node like this one (from Microsoft Visio) can be used

to display the activity name, duration, ES, EF, LS, LF, and

slack.

Page 27: PertGanttchart
Page 28: PertGanttchart
Page 29: PertGanttchart
Page 30: PertGanttchart

A tools use to determine

critical activities for a project.

It can be used to improve a

project schedule and evaluate

progress.

Page 31: PertGanttchart

In PERT Chart, the longest

path is referred to as the critical

path, it is defined as the path

that will cause the whole

project fall behind if even one

day’s delay is encountered on

it.

Page 32: PertGanttchart

It is essential that the systems

analyst carefully monitor the

activities on the critical path so as

to keep the entire project on time

or even shorten the project length

if warranted.

Page 33: PertGanttchart

It is the leeway to fall behind

somewhat on critical paths.

Page 34: PertGanttchart

ActivityPredecess

or

Time estimatesExpected

timeOpt. (O) Normal (M) Pess. (P)

A — 2 4 6 4.00

B — 3 5 9 5.33

C A 4 5 7 5.17

D A 4 6 10 6.33

E B, C 4 5 7 5.17

F D 3 4 8 4.50

G E 3 5 8 5.17

Page 35: PertGanttchart
Page 36: PertGanttchart
Page 37: PertGanttchart
Page 38: PertGanttchart
Page 39: PertGanttchart

Activity Predecessor Duration

A. Conduct Interviews None 3

B. Administer Questionnaires A 4

C. Read Company Reports None 4

D. Analyze Data Flow B,C 8

E. Introduce Prototype B,C 5

F. Observe Reaction to Prototype E 3

G. Perform Cost/ Benefit Analysis D 3

H. Prepare Proposal G 2

I. Present Proposal H 2

Page 40: PertGanttchart

10

20

40

5030 8060 70

A,3

C,4

B,4

D,8

E,5 F,3

G,3 H,2 I,2

Page 41: PertGanttchart

Determining Paths:There are 4 Paths10-20-30-50-60-70-8010-20-30-40-60-70-8010-30-50-60-70-8010-30-40-60-70-80

10-20-30-50-60-70-80 is the longest path with takes 22 days which is the critical path, while others are set to be slack paths