+ All Categories
Home > Documents > Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08...

Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08...

Date post: 04-Jan-2016
Category:
Upload: arline-booker
View: 214 times
Download: 2 times
Share this document with a friend
31
Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009
Transcript
Page 1: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Petals SAP Point Of Sale System

Third Project PresentationM.Tech Team SE 15 (Saturday) Team 08

17-Jan-2009

Page 2: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Presentation Overview Project Background Requirement Overview Development Strategy Technical Challenges / Resolution Live Demo Project Progress – Plan Vs Actual Management Problem / Mitigation Strategy Acceptance Process Lesson Learnt Q & A

Page 3: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Presentation Overview Project Background Requirement Overview Development Strategy Technical Challenges / Resolution Live Demo Project Progress – Plan Vs Actual Management Problem / Mitigation Strategy Acceptance Process Lesson Learnt Q & A

Page 4: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Project Background The OBTECH Asia pacific Pte ltd, Singapore is an

accounting application solution provider and a SAP global partner.

Its clients use a POS system that’s provided by a 3rd party vendor and has many complaints, issues.

The vendor is not ready to accommodate change requests and also not ready to provide source code for doing enhancements.

As a result the company intends to develop a new POS system that shall have the basic POS system functionality and can accommodate future Singapore customer’s requirements.

The project objective is to “develop a client based sales system for retail sales that will integrate with the SAP business one accounting system.”

Page 5: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Project Team

No Name Role

1 David Tan Project Owner

2 Rama Project Manager

3 Ajish QA Manager

4 Wu Xue Song System Architect

5 Zang Yan Technical Lead

6 Zhang Xi Programmer 1

7 Bensam Programmer 2

8 Zhao Zu Qiu Programmer 3

Project Manager(PM)

QA Manager(QM)

Technical Lead(TL)

Programmer 1/2/3(SE)

System Architect(SArch)

Page 6: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Presentation Overview Project Background Requirement Overview Development Strategy Technical Challenges / Resolution Live Demo Project Progress – Plan Vs Actual Management Problem / Mitigation Strategy Acceptance Process Lesson Learnt Q & A

Page 7: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Requirement Overview

SAP B1 HQ

Customer Master Data Inventory Master Data Payment Methods Price List Special Prices Shipping Methods Currency Exchange Rate Tax

FTP

STORE MANAGER POS FRONT

Point of Sale Cash Register Payment Suspend / Recall Peripherals

Stock Reconciliation Item Requisition Day Start User Maintenance Generate Reports Item Exchange Sales Return Refund Cash Register Amend Transaction Maintain Store Data

MASTER DATA CREATION

OUTLET

Day End Transaction Posting

Page 8: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Use Case Modeling : POS

Page 9: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Use Case Modeling : SMS

Page 10: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Presentation Overview Project Background Requirement Overview Development Strategy Technical Challenges / Resolution Live Demo Project Progress – Plan Vs Actual Management Problem / Mitigation Strategy Acceptance Process Lesson Learnt Q & A

Page 11: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Development Strategy

Rational Unified Process OO Language - .NET C# VS.NET 2008 SQL Server 2005 Google Code (svn)

Page 12: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Technical Reports High Level Design

Deployment Diagram

Page 13: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Technical ReportsHigh Level Design

Component Diagram – SPOS Subsystem

Page 14: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Presentation Overview Project Background Requirement Overview Development Strategy Technical Challenges / Resolution Live Demo Project Progress – Plan Vs Actual Management Problem / Mitigation Strategy Acceptance Process Lesson Learnt Q & A

Page 15: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Technical Challenges and Resolutions

Three layers architecture design - complicated than client/server - build on top of .NET framework

(WCF)

UI design with good usability - existing POS systems as reference

(ShengSiong supermarket) - build up UI prototype

Page 16: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Technical Challenges and Resolutions

Development and debugging of client and server in parallel - Predefined WCF service contract and

DTOs. - use a test client program to unit test

server end methods.

Page 17: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Presentation Overview Project Background Requirement Overview Development Strategy Technical Challenges / Resolution Live Demo Project Progress – Plan Vs Actual Management Problem / Mitigation Strategy Acceptance Process Lesson Learnt Q & A

Page 18: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Presentation Overview Project Background Requirement Overview Development Strategy Technical Challenges / Resolution Live Demo Project Progress – Plan Vs Actual Management Problem / Mitigation Strategy Acceptance Process Lesson Learnt Q & A

Page 19: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Project Work Effort by Phase

Page 20: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Project Work Effort by Resource

Page 21: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Overall Project Progress

Page 22: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Project Progress from Last Audit

Page 23: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Presentation Overview Project Background Requirement Overview Development Strategy Technical Challenges / Resolution Live Demo Project Progress – Plan Vs Actual Management Problem / Mitigation Strategy Acceptance Process Lesson Learnt Q & A

Page 24: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Management Problem& Mitigation Strategy

Team member’s tight schedule Team have to allocate time for exam,

assignment and daytime work. Short Weekly meetings Focused separate small-group discussions

when needed Offline Discussions conducted using yahoo

online chat, emails, telephone

Page 25: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Management Problem& Mitigation Strategy

Aggressive Project Schedule Detail task breakdown at implementation

phase using Excel sheet Closely monitor schedule De-scope DTS server and DTS client

module Redistribution of work

Page 26: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Presentation Overview Project Background Requirement Overview Development Strategy Technical Challenges / Resolution Live Demo Project Progress – Plan Vs Actual Management Problem / Mitigation Strategy Acceptance Process Lesson Learnt Q & A

Page 27: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Acceptance Process Project team did a POS client demo to

OBTech Project team delivered the source code and

documentation for ObTech developer for further work

OBTech will continue on the DTS-client and DTS-server module development

OBTech will perform UAT testing after DTS module integrated with POS client.

Page 28: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Presentation Overview Project Background Requirement Overview Development Strategy Technical Challenges / Resolution Live Demo Project Progress – Plan Vs Actual Management Problem / Mitigation Strategy Acceptance Process Lesson Learnt Q & A

Page 29: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Lesson Learnt

Use google code as CMS -simple, efficient

o Hold yahoo online conference effective way to communicate among

team members

o Refine the process of reviewing document.

review – revise - verify

Page 30: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Lesson Learnt

Should have used a CR tracing system.

efficient

o Make use of .NET WCFo a good framework that separates

the presentation layer and data access layer.

Page 31: Petals SAP Point Of Sale System Third Project Presentation M.Tech Team SE 15 (Saturday) Team 08 17-Jan-2009.

Presentation Overview Project Background Requirement Overview Development Strategy Technical Challenges / Resolution Live Demo Project Progress – Plan Vs Actual Management Problem / Mitigation Strategy Lesson Learnt Q & A


Recommended