+ All Categories
Home > Documents > PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal...

PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal...

Date post: 08-Jul-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
32
A Sustainable Energy Company PETRA ENERGY BHD SYNERGISING PARTNERSHIPS
Transcript
Page 1: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

A Sustainable Energy Company

PETRA ENERGY BHD

SYNERGISING PARTNERSHIPS

Page 2: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Disclaimer

2

This presentation may change from time to time and may not contain all material information about the Company.

These statements are not guarantees of future performance and undue reliance should not be placed on them. Such forward-looking statements necessarily involve known and unknown risks and uncertainties, which may cause actual performance and financial results in future periods to differ materially from any projections of future performance or result expressed or implied by such forward-looking statements.

Although forward-looking statements contained in this presentation are based upon what management of the Company believes are reasonable assumptions, there can be no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. The Company undertakes no obligation to update forward-looking statements if circumstances or management’s estimates or opinions should change except as required by applicable securities laws.

Under any circumstances, this presentation is strictly prohibited from being distributed without the consent of the Company.

Page 3: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Preface

3

2015The oil price crash

impacted all companies

across the value chain

and PETRA was not

spared from this storm.

2013We began a turnaround initiative with the

aim of getting the house in order and

growing the business, this saw the

Company register significant improvement

in fiscal performance and saw PETRA

move up the value chain to become the

third Malaysian Company to be awarded

the RSC Contract (Risk Service Contract) by

PETRONAS taking the Company into the

development & production segment,

which turned out to be one of the most

successful RSC projects in Malaysia.

2018Began a Group-wide

transformation programme

that cut across all segments

within the Group with the

aim of resetting our cost,

this augured well for PETRA

and helped the Company

emerge stronger from the

storm as reflected in the

Group’s balance sheet as at

1H2019

NowSignificantly improved our

operational

efficiency/margins, reduced

our borrowings, and remain

in a negative net gearing

position

GENERAL GUIDELINE ON DIVIDEND✓ Payout based on profitability and Company’s solvency for the next 1-year

Page 4: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

OverviewAbout us

Industry outlook

Company outlook

Financial Highlights

Transformation & roadmap

Moving forward

4

Page 5: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

About us

5

Page 6: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Core businesses

Marginal field RSC – KBM Cluster

▪ Development & Production of petroleum from Kapal, Banang & Merantismall fields offshore Terengganu

▪ The only sustainable and successful RSC in Malaysia

▪ More than RM16 million barrels of oil achieved as at 11 Nov 2018

DEVELOPMENT & PRODUCTION

Integrated Brownfield Maintenance & Engineering

▪ Topside Major Maintenance/Hook-up Construction & Commissioning

▪ Project Management, Procurement & Logistics

▪ Engineering, Operations & Maintenance

▪ Equipment, Packaging & Manufacturing

SERVICES SEGMENT

MARINE ASSETS SEGMENT

Marine Offshore Support▪ 4 workboats

▪ 3 workbarges

▪ 1 AHTS

6

Page 7: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Executive summary

Topside Major Maintenance / Hook up Construction & Commissioning

Development & Production for the Marginal field RSC

❑ Moved up the value chain, third Malaysian company to be awarded the RSC, started as a 30%

investor and today PETRA’s personnel manage 70% of the operations. Can be considered the

most successful RSC in Malaysia.

❑ Kapal and Banang field production in record time, ahead of schedule and below budget

❑ Strong safety performance

❑ All CAPEX has been fully reimbursed

❑ RM1 billion in royalty paid to PETRONAS7

❑ Strong track record and experience spanning 30 years in HUCC/TMM/MCM

❑ ~RM5 billion worth of projects undertaken since 2007 for major clients i.e PETRONAS, SHELL,

EXXON Mobil, Murphy, MMHE

Page 8: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Board of Directors

Dato’ Anthony BujangExecutive Director / Group CEO

Hj. Ahmadi

bin YusoffExecutive Director

Tan Sri Datuk Seri

Panglima Sulong

bin MatjeraieChairman

8

Ng Ing PengNon-Executive Director

Abdul Rahim Abdul

HamidNon-Executive Director

Simon Ong Executive Director

Gian Carlo

MaccagnoNon-Executive Director

Page 9: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Strong leadership team over 130 years of experience

Dato’ Anthony BujangExecutive Director / Group CEO

Tn, Hj. Ahmadi bin YusoffExecutive Director

Simon Ong Executive Director

▪ 25 years of oil & gas experience

▪ 9 years with SHELL, Head of Strategy & Contracts and the Planning & Procurement Head at SHELL Gabon

▪ 25 years experience in Management and Strategy positions spanning across various industries including construction, plantation, trading and electrical

▪ 38 years of oil & gas and broad upstream experience in engineering, Project Management, Maintenance and Upstream Mergers & Acquisitions and asset management for SHELL

▪ Chartered engineer by profession and served as Managing Director Shell Global Vetures Solutions (Malaysia) Sdn Bhd

Subky Bustari CEO, Petra Resources

Khairul Anwar MohamadGroup Chief Financial Officer

▪ 15 years of experience in Strategic Plannng, Finance and Business Development in Construction and oil and gas industries. ▪ 15 years of experience in

corporate strategy, finance andmanagement within variousindustries

▪ Member, Chartered GlobalManagement Accountant

9

▪ 15 years of experience in marine industry

▪ Master Mariner Cert of Competency Class 1, Jabatan Laut Malaysia

Captain Sasitharan CEO, PETRA Marine

Khairul RidzwanHead, Internal Audit & Risk Mgmt

▪ 15 years of exposure in finance and audit with experience in corporate assurance and risk management

▪ Association of Chartered Certified Accountants

Page 10: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Industry outlook

10

Page 11: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Brent price movement

Source: Market Insider 11

▪ Oil prices remained relatively stable in 2019

▪ Saudi Arabia drone attack causing 5.7million boe / day reduction in global supply of oil

▪ War with Iran - oil price could spike to "unimaginably high numbers”, threat of world economic collapse looming

▪ Expect greater market volatility to persist

Page 12: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Malaysian outlook – Offshore FabricationConstruction of offshore structure activity

Source: PETRONAS Outlook 2019

52

8

24

2

1

5

0

2

4

6

8

10

12

14

WHP CPP WHP CPP WHP CPP

2019 2020 2021

41 1 1

15

0

2

4

6

8

10

12

14

WHP CPP WHP CPP WHP CPP

2019 2020 2021

Number of structures: Three-year outlook

Wellhead Platform-WHP & Central Processing Platform-CPP (Topside & Jacket) - Tonnage

Hig

h c

ase

Low

cas

e

Light (<1k MT)

Medium (1k MT - <7.5k MT)

Heavy (7.5k MT - <15k MT)

Super Heavy (>15k MT)

Total metric tonne (MT)

Total metric tonne (MT)

Wellhead Platform-WHP & Central Processing Platform-CPP (Topside & Jacket) – Projected Timeline

Hig

h c

ase

Low

cas

e

2

4

2

13

2

6

1

13

1

6

1

6

1

11

~ 8.7k ~ 47k ~ 18.1k ~ 63k ~ 6.1k ~ 40k ~ 6.2k ~ 26k ~ 7.5k ~ 38k

2018 2019 2020 2021 2018 2019 2020 2021

WHP

CPP

12

Page 13: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Malaysian outlook – HuCC & MCM

Maintenance, Construction & Modification Hook-up, Construction and Commissioning

Source: PETRONAS Outlook 2019

4.93.6

5.4

0

1

2

3

4

5

6

7

8

9

10

2019 2020 2021

No. of Man-hours (Millions): Three-year outlook

17.7 17.6 18.7

0

5

10

15

20

25

2019 2020 2021

No. of Man-hours (Millions): Three-year outlook

Most activities accounted are for Brownfield HUC. HUC activities are expected to remain stable over the next three years, thus no High Case is provided

Activity is expected to remain stable over the next three years, thus no High Case is provided

13

Page 14: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Company outlook

14

Page 15: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Current business activities

Core Business Activity for the

Group

Hook up construction and commissioning (2013 – 2020)

▪ 5 year contract-Pan Mal cluster of jobs▪ Biggest contract to date ▪ Scope of work – HuC and Topside Maintenance for PCSB’s facilities offshore Sabah and Sarawak

waters

iHUC - tender

▪ Participating in iHUC as a continuation from Pan Mal cluster of jobs

Maintenance construction and modification (2017 – 2022 + 1)

▪ 5+1 year contract ▪ Scope of work – Topside major maintenance continuations for PCSB’S facilities offshore Sabah

Services Segment

15

Page 16: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Current business activities

One of the most successful RSC

projects in Malaysia

Kapal, Banang and Meranti

Small field cluster under Risk Service Contract (RSC) with PETRONAS(PETRA owns 30% equity stake)

70% operations managed by PETRA personnel

Contract period 2012 – 2020

PETRA plans to seek to continue its presence in the project.

Development & Production Segment

▪ 1st oil achieved within 5 months after commencement of drilling

▪ In record time, ahead of schedule and development cost below budget

▪ Achieved ~16 million barrels of oil as at Dec 2018

▪ All CAPEX fully reimbursed

▪ Discussion to resolve the ongoing dispute pertaining to a disapproved petroleum costs that affected the share result of an associate has reached final stage – settlement has been agreed subject to conditions to be made

16

Page 17: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Marine assets

Petra Challenger300 men accommodation and work barge

Crane capacity – 124 MT | Year 2004

Petra Endeavour300 men accommodation and work barge

Crane capacity – 68 MT | Year 2007

Petra Orbit189 men workboat

Crane capacity – 23 MT | Year 2008

Petra Galaxy189 men workboat

Crane capacity – 23 MT | Year 2008

KasMarine 1AHTS DP1/FIFI-1

5150BHP / 60MT Bollard Pull | Year 2008

Petra Lyra(formerly known as Otto 3)

300 men accommodation and work barge

Crane capacity – 68 MT | Year 2009

Anis199 men workboat

Crane capacity – 45 MT | Year 2013

Alya199 men workboat

Crane capacity – 45 MT | Year 2014

> 60%Vessel utilization as at June 2019

All vessels have

been fully paid

17

Page 18: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Financial highlights

18

Page 19: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Key financial highlights 1H 2019

RevenueRM249.5m

PATRM15.8m

6% margin

EBITDARM32.9m

13% margin

GP Margin13%

Vessel Utilization

> 60%

19

Page 20: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Improving performance efficiency - Quarterly

624.4 654.8

332.1

460.2

67.5 88.4119.7

191.8

111.9 137.6

56.00%

46.40%

26.90%

43.20%

33.70% 35.20%40.60%

48.80%

> 60% > 60%

2014 2015 2016 2017 Q1 2018 Q2 2018 Q3 2018 Q4 2018 Q1 2019 Q2 2019

Revenue vs Vessel Utilisation (2014 – Current)

Revenue Vessel utilisation

94

63.6

-48.6-49.8

-6.9 -7.9 -13.1

34.0

922.8

34.747.2

-114.2

-46.0

1.0

-15.9-27.0

21.01.7

14.1

15%

10%

-15%-11% -10% -9%

-11%

18%

8%

17%

-20%

-15%

-10%

-5%

0%

5%

10%

15%

20%

-150

-100

-50

0

50

100

150

2014 2015 2016 2017 Q1 2018 Q2 2018 Q3 2018 Q4 2018 Q1 2019 Q2 2019

Gross & Net Profit After Tax (2014 – Current)

Gross Profit Net profit after tax GP Margin

RM

'mil

20

Page 21: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Maintaining low debt / Equity ratio

0.43 0.23 0.00 0.15 0.09 0.07

(0.06)

349.49 341.91

237.71

198.21

123.52 102.04

65.59

2014 2015 2016 2017 2018 Q1 2019 Q2 2019

RM

'mil

Ratio

Borrowings

As at 31 August 2019, total borrowings at

RM31.3m

21

Negative Net Gearing as at 1H2019

Page 22: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Net assets per share vs Share price

1.60 1.70

1.30

1.10 1.04 1.05 1.09

1.73

1.26

0.950.82

0.41

1.07

0.775

-

0.20

0.40

0.60

0.80

1.00

1.20

1.40

1.60

1.80

2.00

2014 2015 2016 2017 2018 Q1 2019 Q2 2019

Net assets per share Share price

PETRA Energy Bhd – stock code 5133Total Issued Shares : 321,750,000Treasury Shares : 807,800Adjusted Capital : 320,942,200Market cap 3.10.19 : 404.4million

Share Priceas at 3/10/2019

RM1.26

Market Capitalizationas at 3/10/2019

RM

404.4m

PE Ratioas at 3/10/2019

10.68times

22

Net asset per share decreased from RM1.10 (2017) to RM1.04 (2018) mainly due to decrease in Retained Earning as a result of Loss in 2017 and 2018

Net asset per share increased from RM1.05 (Q1 2019) to RM1.09 (Q2 2019) mainly due to increase in Retained Earning reflected from Profit recorded in Q2 2019

Page 23: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Dividend

20182015 2016 2017 20192014

2.0

10.0

5.0

2.0

Dividend/share (2014 – 2019)

Year

Sen

23

* No dividend paid in 2017 and 2018 due to Petra incurred losses during these 2 years.

GENERAL GUIDELINE ON DIVIDEND✓ Payout based on

profitability and Company’s solvency for the next 1-year

Page 24: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Dividend

20182015 2016 2017 20192014

1.2%

7.9%

5.3%

2.5%

Dividend yield (2014 – 2019)

Year

Perc

enta

ge

24

* No dividend paid in 2017 and 2018 due to Petra incurred losses during these 2 years.

Page 25: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Balance Sheet (2014 – Current)

FINANCIAL YEAR 2014RM’000

2015RM’000

2016RM’000

2017RM’000

2018RM’000

YTD June 2019RM’000

BALANCE SHEET

Total Liabilities 601,881 559,114 412,650 481,579 315,419 279,404

Total Borrowings 349,490 341,913 237,705 198,206 123,522 65,593

Total assets 1,117,305 1,106,025 830,241 834,635 648,777 629,139

Total Shareholders’ Equity 515,424 546,911 417,591 353,056 333,358 349,735

Dividend/share (sen) 2.0 10.0 5.0 - - 2.0Share price at end of each financial year (RM per share) 1.73 1.26 0.95 0.82 0.41 0.785

Earnings Per Share (sen) 10.80 14.68 (35.58) (14.34) (6.52) 4.93

Net assets/share (RM) 1.60 1.70 1.30 1.10 1.04 1.09

Total cash balances (RM'million) 127.80 213.50 238.70 145.30 94.40 86.04

Net gearing ratio (net D/E) 0.43 0.23 0.00 0.15 0.09 (0.06)25

Page 26: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Profit & Loss (2014 – Current)

FINANCIAL YEAR 2014RM’000

2015RM’000

2016RM’000

2017RM’000

2018RM’000

YTD June 2019RM’000

INCOME STATEMENT

Revenue 624,423 654,789 332,084 460,230 467,424 249,510

EBITDA 74,471 109,477 5,764 9,730 15,634 32,954

PBT/(LBT) 21,780 62,015 (124,483) (46,212) (18,508) 15,829

PAT/(LAT) 34,736 47,214 (114,199) (46,033) (20,919) 15,829

PATAMI / (LATAMI)(attributable to enquiry holders) 34,750 47,214 (114,199) (46,033) (20,919) 15,829

26

Page 27: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Moving forward

27

Page 28: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Opportunities in the pipeline and status

Plan to continue our presence & secure offering in RSC

upon expiry of contract.

Pursuing other small field and late life asset

Bidding for iHUC contract subsequent to expiry of Pan

Malaysia contract

Bidding submission for Solar tender

Bidding for operation & maintenance service

Explore opportunities of underwater IMR

Bidding for a regional onshore decommissioning project

28

Page 29: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Continuous improvement

29

The Group is continuously reviewing & improving operations and

committed to deliver the best quality services to the clients

Current key activities

HSE commitment- Key to business operations within oil and gas industry- PETRA has shown strong HSE track record and achievements

over the years and is now on a journey to move to PROACTIVE state

Investment in a new improved ERP system- To improve monitoring & controls

Robust risk management process

Invested to enhance process planning

Ongoing Transformation journey until 2024

Page 30: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

The roadmap 2019 - 2024

Return

to

black

Start of new era

Re-building

the PETRA brand

2019

- Positive cashflow from Ops

- Cost Reset - Double digit GP

2020

- Positive cash flow from ops for investment

- Potential to increase dividend

- 1 New revenue source

2021

- Cashflow from ops for further investment

- 25% increase in revenue from 2019

- Regional Player

Promote the culture of accountability & ownership, diversity & inclusiveness, care and innovation

Operational Efficiency | motivated and engaged workforce

Building momentum

2022

- Doubling revenue (2019 base)

- Doubling dividend (2019 base)

- Revenue from Renewables

Sustainable

energy

company

2023

- Double digit ROI- Revenue mix 40/40/20- Services, upstream,

renewal- Generative HSSE

culture

Partner of choice

2024

- Double digit ROI- Top Quartile Delivery- Industry benchmark

30

Page 31: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

Summary

31

2015The oil price crash

impacted all companies

across the value chain

and PETRA was not

spared from this storm.

2013We began a turnaround initiative with the

aim of getting the house in order and

growing the business, this saw the

Company register significant improvement

in fiscal performance and saw PETRA

move up the value chain to become the

third Malaysian Company to be awarded

the RSC Contract by PETRONAS taking the

Company into the development &

production segment, which turned out to

be one of the most successful RSC projects

in Malaysia.

2018Began a Group-wide

transformation programme

that cut across all segments

within the Group with the

aim of resetting our cost,

this augured well for PETRA

and helped the Company

emerge stronger from the

storm as reflected in the

Group’s balance sheet as at

1H2019

NowSignificantly improved our

operational

efficiency/margins, reduced

our borrowings, and remain

in a negative net gearing

position

✓ Strong balance sheet✓ Good order book✓ Good cash flow✓ No major CAPEX

GENERAL GUIDELINE ON DIVIDEND✓ Payout based on

profitability and Company’s solvency for the next 1-year

Page 32: PETRA ENERGY BHD · Hook up construction and commissioning (2013 –2020) 5 year contract-Pan Mal cluster of jobs Biggest contract to date Scope of work –HuC and Topside Maintenance

T H A N K Y O U32


Recommended