The public sector and the private sector work well
together, innovate and create significant efficiencies,
but poor public sector preparation and inappropriate
risk transfer lead to unnecessarily expensive and
inflexible contracts. This is the broad theme of the
Treasury's reforms contained in "A new approach to
public private partnerships" and the accompanying
"Standardisation of PF2 Contracts" (SOP2C)
which were issued alongside George Osborne's
Autumn Statement this week.
To the relief of the infrastructure community, Treasury
has not "thrown the baby out with the bathwater" and
has taken much of the learning generated since the
launch of the Private Finance Initiative in 1992 to
form the foundation for what it has rebranded as
"PF2".
In this client alert, we take a closer look at five of the
key themes emerging from the reforms:
■ Improved credit enhancement;
■ A greater role for equity investment;
■ Streamlined procurement;
■ Appropriate risk transfer; and
■ Flexible transparent service provision.
CREDIT ENHANCEMENT
In light of the constrained market for longer term bank
debt, one of the key drivers of the Treasury's reforms
is enhancing the credit rating of PF2 projects with a
view to accessing the broader financial markets.
The Treasury is not convinced by mini perm options,
or structures where bank debt is applied solely to the
construction of the asset. In its view, better assets are
created where the funders' due diligence takes into
account long term maintenance risks and obligations.
For that reason, and to avoid the budgetary uncertainty
of any public sector underpinning of refinancing risk,
the Government continues to support financing
through long term debt.
Whilst some banks can still offer long term finance at
affordable rates due to their funding strategy or
country of origin, they are in the minority, and PF2
has been shaped to take into account discussions with
other players in the financial markets. Along with
Treasury Guarantees and co-lending (implemented by
the Infrastructure (Financial Assistance) Act 2012)
and increased public sector capital contributions
(previously restricted to 30% of total project value), it
is hoped that increasing the proportion of equity
invested in the project company will provide the
BBB+ to A- rating needed to attract capital market
investment.
PF2 – THE BIG REBRAND
02 | PF2 – the big rebrand
EQUITY INVESTMENT
Through additional equity injection (in the form of shares
and sub-debt), PF2 will reshape the familiar 90:10 debt/
equity ratios, to a broader 75/80:25/20 capital structure
for accommodation projects (and perhaps even higher
equity ratios on more complex projects). As the most
expensive financing stream, the government argues that it
can create subscription mechanisms which do not
undermine value for money, although some of the
infrastructure community query whether this will in fact
be the case. As well as the traditional risk capital
provided by project sponsors, government intends to tap
two further tranches of equity investment from the public
sector and from institutional investors:
■ Public sector equity contributions can be up to 30-
49% of the overall equity requirement. Although a
standard shareholders' agreement has yet to be issued,
the guidance states that investment will be made on
the same terms as those agreed by the private sector
for the particular project, and the first draft of SOP2C
(section 5) states that pricing of public sector equity
will be determined competitively through the project
procurement process. Attaching returns to public,
rather than private sector, investment reduces the
overall project costs but creates potential conflicts of
interest between public sector procuring obligations
and the opportunity to invest. In recognition of this, a
central government unit (CGU) will be established
within HM Treasury to make commercial investment
decisions and manage what will become a portfolio of
PF2 investments. CGU is not obliged to invest in
every PF2 project.
■ Equity funding competitions will be introduced at
preferred bidder stage (when negotiation on key
commercial and financial risk is concluded) to attract
institutional investors interested in earning long term
stable returns, rather than maximising returns in the
short term. This tranche will be piloted on live
projects in 2013, and is specifically aimed at reducing
the number and size of secondary market
transactions, which have attracted criticism because
of excessive gains achieved by equity investors.
Treasury also hopes to improve transparency. Public
sector representation on the project company's board of
directors will provide access to the project's financial
performance, as well as more involvement in its strategic
decision making. This has already worked effectively on
projects following the Scottish Government's NPD (Non
Profit Distributing) model and in sector specific models,
such as LIFT. Whilst PF2 proposes no specific cap on
equity returns, profits will be curbed by mechanisms to
share unutilised lifecycle reserves. Some in industry are
concerned that this may have the unintended effect of
inhibiting the potential for creative risk sharing solutions.
Equity involvement provides a "hands on approach" to
transparency, which will be reflected in the government's
wider plans to manage PFI and PF2 liabilities. PFI
liabilities are already publicised in Whole of Government
Accounts. A "control total" for commitments arising
from off-balance sheet PF2 contracts will now be
introduced and further reported in Budget 2013. The
government will also publish an annual report detailing
"full project and financial information on all projects
where government is a shareholder."
PROCUREMENT
As well as enhancing credit conditions, the government
recognises that confidence in an efficient procurement
process will also help to attract new players into the PF2
market.
The Cabinet Office's LEAN review has already identified
the need to train public sector procurers, if time frames
for infrastructure procurement processes are to be
reduced. A new version of the LEAN sourcing
requirements amended to cover PF2 projects is currently
being piloted on the Department for Transport's civilian
search and rescue helicopter service procurement. In
addition, Infrastructure UK and the Major Projects
Authority will run a review of capabilities within
Whitehall to report by Budget 2013. Once skills are
entrenched within central government, there will be a
move towards more centralised procurements - following
the example of Infrastructure Ontario in Canada. The
Education Funding Agency, a unit within the Department
for Education (DfE), which will be responsible for all
procurements connected with the Priority Schools
Building Programme, is the first example of this working
in practice.
The government is keen to go one step further and set up
a single central procurement office to reap the benefits of
repetition and batched procurements, but acknowledges
that the business case for such a structure should be
reviewed further during the IUK and MPA review.
Inevitably, procurement costs are factored into private
sector contract costs. Shorter procurements should mean
cheaper contracts. The time limit for PF2 procurements
will be eighteen months from publication of OJEU to
preferred bidder appointment. Unless an exemption has
been granted, Treasury approval for project funding will
not be given if the project has not been closed within that
timescale. The government reserves a discretion to make
a contribution to failed bid costs and anticipates more
detailed information being provided at OJEU than the
www.dlapiper.com | 03
current norm. This time "guillotine" has been meet with
initial concern from the private sector, but it remains to
be seen the extent to which it will pose a serious
deterrent to bidders.
The message is not simply to work faster. The
government wants to see both the public and the private
sector creating opportunities to discuss solutions for a
project before it has been advertised. The government is
therefore proposing a transparent system for business
case approvals, and a business case approvals tracker (to
be published on the Treasury website Spring 2013), to
allow early planning and innovation.
Any public sector business case must include evaluation
of at least one other contract structure option, as an
alternative to PF2. The government is clear that PF2
must not be considered in a vacuum. Other structures
such as local asset backed vehicles, tax increment finance
structures and joint ventures should also be investigated,
if they are appropriate procurement possibilities.
An Infrastructure Procurement Routemap will be
published in January 2013 to address weaknesses in
appraisal practice.
APPROPRIATE RISK TRANSFER
■ Capex from a general change in law
Work on creating savings in operational PFI contracts
has already identified that transfer of future risks
generally results in the creation of reserves to cover
scenarios which may or may not happen. Previously,
the Treasury therefore issued guidance that PFI
contracts cease to follow SoPC4 provisions requiring
the private sector to underwrite a share of any capital
expenditure arising on a general change in law. PF2
now confirms that the public sector will retain the
entire capital spend risk. Taking out the cost of
setting up and maintaining change in law reserve
accounts will enhance a project's value for money.
■ Site risk
Similarly, the private sector is not in any stronger a
position than the public sector to control risks, such as
contamination of the project site from third party
sources, but historically that risk has been transferred
to it, with resulting contingencies increasing the
contract sum. Under PF2, this risk will remain with
the public sector. Where the project site is owned by
the public sector, it will also warrant ground
condition surveys and title investigations relating to
the site which will reduce the due diligence burden on
bidders.
■ Utilities
Much time has been spent in the past drafting risk
sharing provisions for the volume and price of
utilities used at the project site. Under PF2, volume
risk will be allocated to the public sector, but the
project company retains responsibility for the design
of the building against agreed energy efficiency
standards. A rigorous two year hand over procedure
will test whether utility usage is higher than the
efficiency standards. If so, the project company will
be required to rectify thermal or other deficiencies
within the building, or make a compensatory payment
to cover the public sector loss.
■ Insurance
Risks associated with insurance have also been
revisited. The Government now recommends self-
insurance and provision of a public sector indemnity
for projects with a dispersed asset base and reduced
risk of catastrophic loss. Any indemnity will be
subject to government accounting and FSA regulatory
controls. The new SOP2C guidance gives examples
of where insurance risk should not be transferred to
the private sector. The examples include:
■ not requiring material damage and business
interruption insurance on a street lighting project
(where the project company can simply take the
risk of replacing street lights which are damaged);
■ providing an indemnity, rather than material
damage and BI cover, during the operational
phase of a roads project; and
■ retaining damage risk in sectors where there is a
shallow or inefficient insurance market for
situations where an asset is used in hazardous
conditions.
The government recognises that self-insurance will
raise concerns that senior debt service may not be
covered, or that the public sector could become
responsible for risks that should be the subject of PI
cover. It therefore intends to pilot potential
approaches to self-insurance in future pathfinder
schemes, which submit a business case predicated on
self-insurance.
SOP2C continues to include provisions relating to
insurance premium risk, but the public sector can now
choose its own "nil change" band of between 5 and 30
per cent up and down from the agreed premium
baseline (30% in SOPC4). This is intended to reduce
04 | PF2 – the big rebrand
the level of contingencies currently factored into
unitary payments to cover increased premiums.
FLEXIBLE AND TRANSPARENT SERVICE
PROVISION
Review of existing PFI contracts unearthed a number of
practices that undermined value for money in their long
term service element: either because they precluded
flexibility to reduce or change the scope of service
provision, or because elements of the contract included
inflated pricing.
Recognising that continued responsibility for asset
maintenance enhances design, the government has
retained so-called "hard" services, but excluded
"soft" (eg catering, cleaning and security) services from
the contract structure. They will now be provided
separately through shorter term contracts, to provide the
flexibility to alter service specifications over time. There
will be additional flexibility within the contract structure
to add or remove certain "elective" services (the
examples of periodic redecoration, portable appliance
testing and snow and ice clearance are given - the type of
services which can reasonably be provided from the
maintenance contractor's existing skill set). Elective
services will be provided at a pre-agreed price and can be
added or removed from the project without the need to re
-run the financial model.
PF2 will introduce efficiency reviews to assess service
and efficiency improvements. Efficiency reviews will be
carried out to coincide with the five yearly review of
actual / planned lifecycle expenditure. In line with
regulated businesses such as the water industry, and to
recognise the continuous improvement relic of the
previously more extensive Best Value duty, SOP2C
"recommends" qualitative monitoring obligations to be
measured through customer satisfaction surveys.
Although the mechanism is not clear, seventy-five per
cent of savings realised as a result of an efficiency review
will be paid to the public sector, and twenty-five per cent
to the private sector.
STANDARD DOCUMENTS
SOP2C, like its predecessor "Standardisation of PFI
Contracts", follows a format of explanation of principles,
followed by required/recommended drafting. It remains
to be seen, as PF2 is applied to further sectors, whether
standard project agreements will be issued in the same
way as the DfE has done for the Priority Schools
programme. The benefits of standardisation are also to
be applied to output specifications to ensure
proportionate design commitments.
Consultations on standard form services output
specifications, shareholders' agreement and payment
mechanism have been promised for "soon" after the
Autumn statement.
THE WAY FORWARD
Successful implementation of PF2 will depend on a
prioritised project pipeline. The government has
confirmed that PF2 will be applied to the government's
£1.75bn privately financed Priority Schools programme.
The Government has also marked out projects to improve
parts of the MOD estate as possible candidates for a PF2
structure, as well as Sandwell and West Birmingham
hospital projects and potentially some roads schemes.
However, industry remains sceptical about the speed with
which such identified projects will come to market and
the volume of future projects further down the pipeline.
While the immediate PF2 pipeline is focused on
accommodation projects, the Treasury has confirmed it
will work with departments to ensure all suitable projects
are able to take advantage of PF2.
It will also be interesting to see how PF2 is applied and/
or modified (in particular the government's stated equity
ratio requirements) on schemes that may incorporate
other credit enhancing structures being promoted in the
market, such as the EIB 2020 project bond, Hadrian's
Wall Capital Fund, PEBBLE and CLIP.
Whilst no formal timeline has been published, further
PF2 developments to track are:
■ Consultation on standard form services output spec,
shareholders' agreement and payment mechanism -
"soon" after Autumn statement;
■ Infrastructure Procurement Routemap to be issued for
consultation in January 2013;
■ Updated value for money assessment guidance to be
issued for consultation in Spring 2013;
■ Voluntary code of conduct to improve efficiency and
transparency in operational projects to be issued by
end of March 2013;
■ Pension Fund Platform report in early 2013;
■ Review of procurement capability within Whitehall -
Budget 2013; and
www.dlapiper.com
DLA Piper UK LLP is authorised and regulated by the Solicitors Regulation Authority. DLA Piper SCOTLAND LLP is regulated by the Law Society
of Scotland. Both are part of DLA Piper, a global law firm operating through various separate and distinct legal entities. For further information
please refer to www.dlapiper.com
UK switchboard: +44 (0) 8700 111 111
Copyright ©2012 DLA Piper. All rights reserved. | DEC 12 | Ref: MA/14630771
This publication is intended as a general overview and discussion of the subjects dealt with. It is not intended to be, and should not be used as, a substitute for taking
legal advice in any specific situation. DLA Piper UK LLP and DLA Piper SCOTLAND LLP will accept no responsibility for any actions taken or not taken on the basis of
this publication. If you would like further advice, please speak to your DLA Piper contact on 08700 111 111.
■ Business case approval tracker for PF2 projects to be
published on Treasury Website from Spring 2013.
■ Central unit for managing public sector project equity
to be developed as an arm of HM Treasury
■ Pilot projects for equity funding competitions post
preferred bidder to determine third party equity
■ Insurance pathfinder projects - by authorities who
prepare a business case predicated on self-insurance