NABARD – WDF Seventhipatty & vadavathur watershed Namakkal - District Full implementation phase Watershed Code No:4B1B3b3a1 &4B1B3b3a2. PFA - HEALDS. WATER ABSORPTION TRENCH Total cum : 1440 Total amount :Rs 60746 Work completed : 1050 cum Balance work :390 cum. - PowerPoint PPT Presentation
Popular Tags:
10
NABARD – WDF Seventhipatty & vadavathur watershed Namakkal - District Full implementation phase Watershed Code No:4B1B3b3a1 &4B1B3b3a2 PFA - HEALDS
Transcript
Page 1: PFA - HEALDS

NABARD – WDFSeventhipatty & vadavathur watershed

Namakkal - District

Full implementation phase

Watershed Code No:4B1B3b3a1 &4B1B3b3a2

PFA - HEALDS

Page 2: PFA - HEALDS

WATER ABSORPTION TRENCH Total cum : 1440

Total amount :Rs 60746Work completed : 1050 cum

Balance work :390 cum

WATER ABSORPTION TRENCH (BEFORE) WATER ABSORPTION TRENCH (AFTER)

Page 3: PFA - HEALDS

WATER ABSORPTION TRENCH

WATER ABSORPTION TRENCH (BEFORE) WATER ABSORPTION TRENCH (AFTER)

Page 4: PFA - HEALDS

CONTOUR TRENCH Total cum :1203

Total amount : 50749Contour trench work is completed

CONTOUR TRENCH (BEFORE) CONTOUR TRENCH (AFTER)

Page 5: PFA - HEALDS

CONTOUR TRENCH

CONTOUR TRENCH (BEFORE) CONTOUR TRENCH (AFTER)

Page 6: PFA - HEALDS

STONE GULLY PLUGSTotal Rm : 66

Total amount : 21204Stone Gully plugs work is completed

STONE GULLY PLUGS (BEFORE) STONE GULLY PLUGS (AFTER)

Page 7: PFA - HEALDS

STONE GULLY PLUGS

STONE GULLY PLUGS (BEFORE) STONE GULLY PLUGS (AFTER)

Page 8: PFA - HEALDS

LOOSE BOULDER STRUCTURE

LOOSE BOULDERS STRUCTURE (BEFORE) LOOSE BOULDERS STRUCTURE (AFTER)

Page 9: PFA - HEALDS

LOOSE BOULDER STRUCTURE Total cum : 90

Total amount : 29645Loose boulder structure is completed

LOOSE BOULDER STRUCTURE (BEFORE) LOOSE BOULDER STRUCTURE (AFTER)

Page 10: PFA - HEALDS