+ All Categories

PFI PPI

Date post: 02-Jun-2018
Category:
Upload: k1l2d3
View: 219 times
Download: 0 times
Share this document with a friend

of 24

Transcript
  • 8/10/2019 PFI PPI

    1/24

    PRIVATE FINANCE INITIATIVE /

    PUBLIC PRIVATE PARTNERSHIP:

    A CONTRACTORS PERSPECTIVE

    A paper given to a meetingof the Society of Construction Law

    in London on 15th October 2002

    Martin Lenihan

    December 2002

    www.scl.org.uk

  • 8/10/2019 PFI PPI

    2/24

    1

    PRIVATE FINANCE INITIATIVE /

    PUBLIC PRIVATE PARTNERSHIP:

    A CONTRACTORS PERSPECTIVE

    Martin Lenihan

    This paper looks at the commercial and legal aspects of the private finance

    initiative (PFI) and public private partnership (PPP) which are of particular

    concern to the contractor, and considers how the contractors legal team

    attempts to manage risk when drafting, reviewing and negotiating PFI

    documentation. The main reason for a contractor moving into PFI is the need

    to make better margins and more profit by being different and innovating, incircumstances where there are many (often too many) construction companies

    seeking a limited supply of traditional construction work. All the early PFI

    projects and many of the later ones have been largely contractor driven, rather

    than investor or operator driven. Over time, different trends may emerge.

    PFI/PPP general context

    The first major opportunity for the private sector came in 1981 with what are

    known as the Ryrie Rules.1 These allowed projects to be privately funded so

    long as:

    they provided better value for money than publicly funded alternatives;

    they were not additional to public expenditure (ie there must be an

    equivalent public capital cut); and

    risk was transferred to the private sector.

    In the early days, projects were not known as PFI but by various other

    acronyms, principally BOT (build, own, transfer), BOOT (build, own, operate,

    transfer) and BOO (build, own, operate). Since early projects such as the

    Dartford River Crossing the buzz words have moved on and we are now into

    PFI and the perhaps more politically palatable (and indeed, accurate) term

    PPP. For simplicity, the term PFI is used in this paper.

    Early privately financed opportunities, following Ryrie, included the Channel

    Tunnel and the Dartford-Thurrock crossing (better known as the QEII

    Bridge).2 By about the mid-1990s, it was apparent from a number of earlier

    BOT type projects that PFI could work and was, to some extent, tried and

    tested. This said, however, there were questions as to why success on earlier

    1 So called after Sir William Ryrie, chairman of the committee set up by the NationalEconomic Development Council to review the investment rules for nationalisedindustries and to devise criteria under which private finance might be introduced into the

    public sector.2 The bridge linking the northern sector of the M25 to the southern sector across the River

    Thames: the project had a capital value of some 180m.

  • 8/10/2019 PFI PPI

    3/24

    2

    projects3was not being replicated in other sectors of government, for example

    health and education, all of which have a high spend.

    At about this time, as the PFI process was evolving, one of the most

    distinguishing characteristics of PFI was becoming more discernable, namely

    that the process is all about the purchase ofservices not just assets. It had tobe recognised that rather than merely talking about a 12 month construction

    contract, the participants had to get to grips with agreements which were to

    run for 25-30 years. Problems with transfer of risk, lack of assurance that

    contracts would be honoured by the public sector, excessive transaction costs

    there were still no guidelines or standard documents were real constraints

    on the spread of PFI to other sectors.

    Arguably, the big breakthrough for PFI came with the first Bates Review in

    1997, when Sir Malcolm Bates undertook a review of how PFI was working.4

    His recommendations included the following:

    Stronger central direction which would determine commercial viabilityof projects. This was achieved by setting up the Treasury Taskforce

    with the necessary skills to assist in the selection and driving through of

    projects;

    Legislation to empower public sector bodies to enter into PFI contracts;

    and

    Standardisation of PFI documentation: prior to standardisation, all

    documentation was bespoke with much reinvention of the wheel and

    correspondingly excessive deal costs.

    The Bates Review resulted in a number of major health schemes actually

    being built and coming to fruition.

    It is thought by many that this heralded a new era of sharing of responsibility

    between the public and private sector, rather than the pass the buck approach

    of earlier deals. The new mantra become optimum risk allocation,

    characterised by the new understanding that value for money is maximised

    when risk is placed with the party best able to manage it. Risk and control go

    together; the party to whom risk is allocated must have the freedom to

    determine how to manage it and all risks should be identified, allocated and

    priced at the outset to allow flexibility on the project.

    It now seemed to be generally understood that where there is an interface

    between services being provided by the private sector and the public sector,

    the latter would need to have some limited obligations. For example, in the

    hospital context, the hospital trust would need to sign off clinical adjacencies;

    they would take the risk of occupancy and indeed decide where the hospital

    was to be situated. The government also accepted the risk of project specific

    legislation (for example, if a subsequent government abolished the

    concessions for hospital operations this would be a government risk).

    3 Such as the QEII Bridge and the Tagus Bridge in Portugal, not to mention the M1/A1shadow tolls project.

    4 Sir Malcolm Bates, The Bates Review, June 1997; see www.ogc.gov.uk/pfi.

  • 8/10/2019 PFI PPI

    4/24

    3

    Major legislation followed the Bates Report and greatly assisted the PFI

    process, namely the National Health Service (Private Finance) Act 1997 and

    the Local Government (Contracts) Act 1997.

    Regarding the lack of standardisation of PFI documentation and procedures,

    the position was accurately described by Haydn Cook, Chief Executive ofCalderdale NHS Trust, who said in his case study of the procurement by PFI

    of the Halifax Hospital:

    The Trust negotiated, almost continuously, with Catalyst from

    September 1996 through to July 1998

    Most meetings seemed to involve lawyers and the legal contracts

    seemed to be the basic agenda for almost every meeting. The legal

    contract is a means of reflecting the commercial understanding or so it

    was thought! There were times when it felt like it was an end in itself

    no matter if the hospital did not work, as long as the legal words were

    sound

    The legal negotiations went on ad nauseam, with about thirty drafts of

    the contract being produced (the Trust regularly lost track of which

    revision it was working on) ...

    One meeting, close to financial close, had around twenty people

    present. The lawyers were typically getting 300 an hour. The total

    cost of the time involved must have been in the order of 3,600 an hour,

    or 1 per second ...

    By the last two months, it should be added that everyone was getting

    tired with regular weekend working and long hours that often turned

    into working through the night. Good health and stamina were key

    elements to keeping the negotiators going.5

    This is exactly my experience: one enduring memory I have of a PFI

    negotiation in about 1998, is of the bankers representative producing a tube of

    vitamin C tablets at approximately 3am one Saturday morning near financial

    close on a deal to keep the meeting going to the end.

    In mid-1999 the Treasury Taskforce published the first edition of its Guidance,

    which provides a template for concession contracts (project agreements)

    across all sectors, in most cases setting out the principles for the drafting and

    then providing examples of appropriate clauses. (This has now been

    superseded by the Guidance published by the Office of Government

    Commerce (OGC part of the Treasury).)6 This is already bearing fruit in

    that the National Health Service (NHS) has produced a standard form of

    project agreement, based on the Guidance.7 It remains to be seen whether the

    5 Courtney A Smith,Making Sense of the Private Finance Initiative Developing Public-Private Partnerships, Radcliffe Medical Press, 1999.

    6 Treasury Taskforce Guidance first edition 1999 and OGC Guidance issue 3,Standardisation of PFI Contracts, general revision 2002, OGC/Butterworths, availablefrom www.butterworths.co.uk and see www.ogc.gov.uk/pfi and the PFI network at

    http://pfi.ogc.gov.uk; OGC help desk 0845 0004999.7 NHS Executive Standard Contract (version 2) October 2000, available on

    www.doh.gov.uk/pfi (help desk 01132 545487).

  • 8/10/2019 PFI PPI

    5/24

    4

    transaction costs will be substantially reduced but there is every reason to

    expect that they will.

    Where we are at present

    I believe that PFI does work, principally because the process brings benefits tobothsides of the table: employers are seeking solutions to their requirements,

    allowing innovation to be explored in all sorts of areas creating an

    environment where freedom of ideas can flourish.

    There is complete integration under the project company (which is a corporate

    special purpose vehicle) of everything needed to achieve the required service,

    from designers and contractors, to service provision and maintenance. The

    project company will, therefore, be focussed on being able to provide the

    service efficiently and economically. The project company and employer

    have common goals, and the project company can:

    be more innovative in configuration, design, construction, maintenanceand even the operation of the project;

    create greater efficiencies and synergies between design and operation;

    invest in the quality of the asset, to improve long term maintenance and

    operating costs, to give value for money not cheapest capital cost.

    In the past (under traditional procurement), capital has often been invested

    without a clear commitment to adequate future spending on maintenance,

    leading to poorly maintained assets, high running costs, inefficient service

    provision and premature replacement. In contrast, PFI invests in the future

    because it ensures that assets are maintained properly.

    An upfront decision as to what is required is made, leaving the projectcompany to adopt and deliver a solution. Major capital projects in the past

    have been bedevilled by massive change and variation. PFI is about focusing

    on the right questions, with an emphasis not generally associated with

    traditional construction methods. There is a huge incentive to work towards

    the earliest provision of the service, because only then does payment start to

    flow, and the financial risks of failure on the design and build contractor are

    considerable. This aspect of PFI alone acts to concentrate the minds of design

    and build contractors in a way almost unknown in previous Joint Contracts

    Tribunal (JCT) standard forms of building contract. A big difference between

    PFI and JCT is, invariably, the delivering of a completed product to time for a

    pre-agreed price.

    It may be that the detailed negotiations leading to financial close are one of the

    reasons for the projects success. All parties have the opportunity to fully

    understand what the other parties wish to achieve. The risks are exhaustively

    researched and methods of controlling them determined in advance. The

    design is well progressed and most, if not all, planning issues have been

    resolved. Principal subcontractors have been selected and have bought in to

    the key issues. To my mind, the key feature to understand about the PFI

    process is that it is all about the delivery of aserviceor productof which the

    construction of the facility/hospital/building or whatever is an (important) part.Because of the very different risk:reward profile of PFI projects compared to

  • 8/10/2019 PFI PPI

    6/24

    5

    more traditional methods of procurement and the use of output specifications,

    the participants in PFI must make major mind adjustments and stop thinking

    JCT. Instead, they must adapt to new concepts.

    The future

    The government seems keen to ensure that the lessons learnt through PFI are

    applied to all public sector procurement. Peter Gershorn, the then managing

    director of GEC Marconi, carried out a review of public procurement and

    identified a need for radical change.8 He recommended that the government

    create a central body to ensure consistency of strategy and the promotion of

    best practice across the public sector. A second report was produced by Sir

    Malcolm Bates.9 The result of these reports is that two new governmental

    bodies have been set up.

    Partnership UK will effectively take over where the Treasury Taskforce left

    off. The likelihood is that many different types of public/private co-operationwill develop, some of which we are already seeing, for example in a recent bid

    for the new Meteorological Office building, where the construction costs will

    be directly funded by the government. The OGC will act as a gateway for

    decision making on government procurement (excluding military, health and

    local authority procurement). It is likely to have a significant influence on

    which projects go forward and whether PFI, traditional methods or some

    combination of the two is used. Numerically more projects will be procured

    using PFI methods. Immense potential exists for the export of UK PFI skills

    as other countries begin to copy the UK model.

    I believe that the future of PFI looks bright, despite recent well publiciseddifficulties associated with the process. These difficulties, particularly those

    relating to onerous bid costs, new accounting rules and trade union concerns

    with aspects of PFI, are genuine concerns, but they can be dealt with. The

    disadvantages of the PFI process are greatly outweighed by the advantages.

    Role of the contractors lawyer in PFI transactions

    There is no law of PFI as such but merely many areas of law which have a

    bearing on the various agreements concerned. The essential requirements for

    a lawyer practising in this area include:

    1. A broad experience and understanding not only of construction

    contracts but of a variety of commercial agreements, as well as

    knowledge of a wide range of corporate and general commercial

    documentation (such as service/facilities management agreements and

    their payment and availability regimes, shareholders agreements, joint

    venture agreements, finance documents, property documentation and

    general security documentation);

    8 Peter Gershorn,Review of Civil Procurement in Central Government, April 1999;

    available at www.ogc.gov.uk.9 Sir Malcolm Bates, The Second Review, the results of which were published by the

    Treasury in July 1999; see www.ogc.gov.uk.

  • 8/10/2019 PFI PPI

    7/24

    6

    2. An inclination to wade through sometimes thousands of pages (and

    many, many drafts) of project documentation without losing the will to

    live;

    3. An ability to pick out from this mass of information the key matters and

    issues which have not yet become apparent;

    4. Common sense; and a sense of humour!

    The process of closing a PFI deal can typically take, these days, nine to twelve

    months (and sometimes longer) of continuous work, with a final period of

    three or four months hard work, of which the final six weeks or so will be

    incredibly intense. In my experience, there can be little real doubt that the

    excellent work on standardising PFI documentation to date has resulted in

    significant time and cost savings and standardisation greatly facilitates the

    process of closing deals. Although deals still take a long time to negotiate to a

    close because of project specific considerations (particularly on the larger

    deals), the task is now much less onerous than it used to be. On the subject of

    standardisation of PFI contracts, the new OGC Guidance has just recently

    been made available and is essential reading for those involved or interested in

    the PFI process.10 This updates and improves upon the earlier Treasury

    Taskforce Guidance.

    The diagram appended at the end illustrates the spiders web of parties

    involved in a PFI project. This typical structure gives rise to a mass of legal

    documentation. (On one recent hospital deal I was involved in, there were

    some 144 agreements appearing on the completion protocol: one section of

    one of the major schedules ran to about 6,000 pages on its own!)

    The project agreement

    The first task for the contractors lawyer is to get involved in the project

    agreement negotiations, as it is the project agreement which sets the agenda

    for all the other agreements. Although the contractor is not a party to the

    project agreement, it is crucial that it is drafted in terms satisfactory to the

    contractor, because all the design and build construction risk is either retained

    by the employer, or stepped-down into the various subcontracts (the

    contractor/hard facilities manager/soft facilities manager and equipment

    suppliers are, officially, referred to as the subcontractors, the project

    company being the contractor).

    A project agreement contains numerous provisions and requirements relating

    to the provision of a service. These can look very different when one is

    looking at the construction aspects stepped down into the design and build

    contract. If a particular construction risk is not to be retained by the employer,

    it will be stepped down and taken by the contractor (unless it is an equipment

    or hard or soft facilities management issue). If matters of concern to the

    contractor are not dealt with at all in the project agreement, it is likely that

    they will not be dealt with in the design and build contract. Once negotiations

    on the project agreement are under way, the teams will get involved in looking

    10 See note 6.

  • 8/10/2019 PFI PPI

    8/24

    7

    at various other, related, commercial documentation such as funder/authority

    direct agreements, security documentation etc.

    It remains a truism that the best and most effective way of managing risk in all

    its guises (legal, technical and commercial) is for the contractor to ensure that

    he gets it right to begin with in terms of defining as fully as possible theexact scope of works to be undertaken and to meticulously plan and price to

    do this. This is not rocket science, I agree, but I never cease to be amazed how

    often this basic principle gets overlooked. The source of a disproportionately

    large number of construction disputes can be traced to lack of clarity regarding

    the scope of the work, and a lack of understanding as to exactly who in the

    construction process should be doing what, how, where and when. Because of

    the huge amount of upfront work done in understanding the needs and

    requirements of the employer and the constraints applicable to the project, and

    developing solutions, the PFI process affords the parties a greater opportunity

    of arriving at the best solutions to meet the employers needs.

    What the contractors lawyers look out for

    The NHS Executive standard form project agreement11 illustrates what

    lawyers acting for the contractor particularly look out for. As mentioned, they

    will end up negotiating (to varying degrees of intensity) aspects of the project

    agreement which affect the contractor with a number of teams of lawyers,

    principally those acting for the project company, bank and employer. In

    addition to this, and depending upon the complexity of any given deal, the

    contractors lawyers may also be involved in discussions with lawyers acting

    for other major subcontractors, including the operators lawyers (two lots if

    the operations are split into hard and soft services) and other parties too.

    The NHS standard project agreement (like similar documents used in other

    sectors of industry), contains a wide variety of obligations to cover everything

    that is required for the ultimate provision of a service (including the building

    product), of which the design and construction of the hospital is but one (very

    important!) constituent part. The project agreement deals with all sorts of

    matters from general, normal boiler-plate commercial contract type clauses,

    to matters relating to land issues, construction issues, corporate matters such

    as change in control constraints, intellectual property/confidentiality, taxation,

    employment law12and so on and so forth.

    The employer wants a product that will provide the necessary services (usually

    specified in an output specification) for the concession period (typically 25-30

    years) to a set standard. Provided that the employer actually gets the product

    and service it requires (and subject to meeting the employers minimum

    required technical standards), it will not, usually, be overly concerned whether

    the project company specifies and pays a high capital cost for a high

    specification building from day one (which is going to be virtually

    maintenance free) or whether it specifies a lower specification, lower cost

    11 See note 7.12 Especially relating to the Transfer of Undertakings (Protection of Employment)

    Regulations 1981 (TUPE) or the Governments new retention of employment model.

  • 8/10/2019 PFI PPI

    9/24

    8

    building (requiring less of an initial capital sum but which will have a high

    cost maintenance over the term of the agreement). The philosophy of PFI is

    that that is a decision for the project company. The project company and

    contractor are afforded significant leeway and autonomy and suffer much less

    interference in terms of the detail of how the service is delivered. With the

    transfer of greater risk to the private sector must go a correspondingly greaterdegree of control to enable that risk to be managed.

    The main role of the project companys lawyers will be to get the deal done,

    and generally ensure that all risks and liabilities are identified, and then either

    costed and kept within the project company (unusual) or (more usually) passed

    to another party such as the contractor or the facilities manager. Project

    companies are project specific and generally have little or no resources of their

    own. Their income will rely upon the monthly payments they will receive

    from the employer once the services have commenced. From these monthly

    payments, the project company services its debt, pays the operating contractor,

    builds up contingency reserves for specified matters such as replacement ofplant or equipment, and generally attempts to create a dividend for the

    shareholders. Because the bank will lend money on a limited or non-recourse

    basis (ie the banks usual or only recourse if things go wrong will be to the

    facility asset and revenues generated by it), it will be keen to ensure that no, or

    very little, risk remains with the project company.

    Accordingly, the contractors lawyers, when identifying the risks which are

    unacceptable to their client, must get involved in the project agreement

    negotiations to ensure that any unacceptable risks are either retained by the

    employer, or transferred to a more appropriate party. It is vital to understand

    that, if one is unsuccessful in negotiating out a particular risk within theproject agreement during negotiation with the employers lawyers, it will be

    too late to do anything about that risk when heavy negotiations start on the

    design and build contract.

    It is very important that a good, team-like, working relationship exists, or is

    created, between the lawyers acting for the project company and the

    contractor. The contractors views on the project agreement must be properly

    understood by the project companys lawyers and conveyed fully and fairly to

    the employers lawyers. At appropriate points in the negotiations, the

    contractors lawyers will sit side by side with the project companys lawyers

    in negotiations with the employers lawyers. Even on jobs where thecontractor is wearing many hats (through related companies) and is also a

    shareholder in the project company, the contractors team must not forget that

    it is not the role of the project companys lawyers to act in the contractors

    best interests. In other words, the contractors lawyer must look after his own

    clients interests as nobody else will.

    NHS standard form project agreement summary

    The standard form13is laid out in twelve different parts as follows:

    Part A Preliminary

    13 See note 7.

  • 8/10/2019 PFI PPI

    10/24

    9

    Part B General Provisions

    Part C Land Issues

    Part D Design and Construction

    Part E Quality Assurance

    Part F Information Technology

    Part G ServicesPart H Payment and Financial Matters

    Part I Changes in Law and Variations

    Part J Delay Events Relief andForce Majeure

    Part K Termination

    Part L Miscellaneous.

    In addition to the 69 clauses comprising the operative part of the standard

    form, there are many schedules, the exact number of which differs from deal

    to deal. Key schedules include:

    Schedule 1 Definitions and Interpretation14

    Schedule 2 Completion Documents

    Schedule 7 Land Matters

    Schedule 8 Construction Matters

    Schedule 9 The Programme

    Schedule 10 Review Procedure15

    Schedule 11 Collateral Agreements

    Schedule 12 Outline Commissioning Programme

    Schedule 13 Equipment

    Schedule 15 Independent Tester Contract

    Schedule 21 Insurance Requirements

    Schedule 22 Variations ProceduresSchedule 23 Compensation on Termination

    Schedule 26 Dispute Resolution Procedure.

    Although the contractors team will concentrate on these schedules, they will

    also review and get involved (to varying degrees of intensity) with many of

    the other schedules (usually project specific). This is because of the high

    degree of interfacing which occurs between the various parties and the

    potential for impact on the contractors position. Lawyers acting for parties on

    a PFI transaction get involved to a much greater extent in the detail of

    schedules than was the case in contracts procured under more traditional

    procurement routes This is almost entirely due to the different risk:rewardprofile applying to PFI projects. Moreover, the devil is in the detail.

    It is important to understand what I mean by the different risk:reward profile

    applicable to PFI transactions. When signing a PFI construction contract, in

    practice the contractor is, to all intents and purposes, signing off its final

    account at the same time, in that there is relatively little scope for claims to

    allow upward adjustment of the contractors contract sum. The contractor

    musttherefore understand what he is undertaking to do in terms of scope, and

    price it properly: that is, get it right to begin with.

    14 This is a vital schedule to look at on one recent deal, this schedule alone exceeded 50pages in length.

    15 Dealing with mainly reviewable design data etc.

  • 8/10/2019 PFI PPI

    11/24

    10

    On most PFI jobs, the project company and contractor will only be entitled to

    claim additional money in the event of compensation events, which are

    usually limited to such matters as employer breach, employer change/variation

    and discriminatory or specific changes in law. On some occasions it may be

    possible to justify additional compensation events such as, for example,

    archaeology (a subject treated differently depending upon the project and thecircumstances). Unless the project company receives compensation as defined

    in the project agreement, there will be no equivalent relief flowing down to the

    contractor. A host of drafting devices have been invented by lawyers to

    protect the position of the project company and the interests of the funder.

    The PFI risk profile has resulted in contractors undertaking very significant

    amounts of up front design and related work to ensure that it knows what it is

    supposed to be designing and building, with the aim of achieving clarity of

    scope of works. With this clarity comes greater pricing certainty and less

    scope generally for disputes, as much conflict derives from lack of clarity as to

    scope of obligations and generally who should be doing what, where andwhen. One of the downsides of this is the vastly increased bid costs. These

    arise, not only because of the involvement of lawyers, but also (and more

    importantly) because of the cost of deploying sizeable resources to carry out

    upfront work, all of which is usually done at risk in that these costs (running

    into many millions of pounds on the bigger projects) will not be recoverable if

    financial close is not achieved. This really does tend to concentrate the mind

    of the contractor.

    The costs of playing the PFI game are so high (especially if a deal does not

    reach financial close) that contractors must be very selective in terms of the

    projects they bid for. The public sector should remember that contractors donot possess bottomless pockets in terms of bid costs and that both public and

    private sectors should continue to look for ways to make the PFI process work

    affordably and sensibly for both sides. It should not be forgotten that issues of

    corporate governance and commercial prudence will impose constraints on the

    amount of risk the private sector can reasonably take. From the perspective of

    those contractors who can afford to put at risk very significant upfront bid

    costs, the profit margins available on PFI projects are potentially greater than

    most traditional commercial property development projects, provided that the

    very real risks have been properly evaluated and the project properly managed.

    Experience demonstrates that the line between turning in a reasonable profit

    and a substantial loss is a fine one and ultimately depends on a skilled and

    experienced management team.

    The realities of the PFI process effectively create economic barriers to entry,

    thus discouraging Wide-Boy Construction Limited from simply taking a

    chance, as often happens in commercial property development projects.

    There, the less responsible contractor (who is often not properly resourced and

    who does not invest in training, health and safety, welfare etc, to the same

    degree, or at all, compared with more responsible contractors) too often

    achieves a resultant pricing advantage, which some employers and their

    various advisers are only too happy to exploit. In essence, the risk:reward

    profile of the PFI process rewards those who get it right in terms of good

  • 8/10/2019 PFI PPI

    12/24

    11

    margins and enhanced reputations. If though the contractor gets it wrong, then

    the results can be disastrous and unforgiving.

    NHS standard form project agreement - details

    Above all, when reviewing the NHS standard form,16

    the contractors teamwill concentrate on those clauses and schedules which deal with the regime for

    defining construction requirements (for example Schedule 8 usually contains

    the employers construction requirements and the project

    company/contractors proposals) and other related clauses, such as Clause 5

    (the Project Operations) and Clauses 17-24 (dealing with design and

    construction matters). The employer will be the Trust or Health Authority. In

    Clause 5.2 (General Standards), the contractor should consider whether there

    are any project specific reasons to amend the compliance with

    laws/consents/good industry practice regime (and this is related to Clause 39

    Changes in Law) where, for example, the construction period is unusually

    long.

    The standard form generally assumes, in terms of construction, a single

    facility on a greenfield site, with a 12-18 month construction period. The

    degree of foresight (crystal ball gazing) to be expected of a competent

    contractor in terms of anticipating future changes in law should be considered,

    as this gives rise to very real risk, costing and value for money considerations.

    It is usual to request the employer to be precise as to exactly which NHS

    requirements it expects compliance with (as referred to in Clause 5.2(f)).

    Pinning down exact requirements also contributes to the overall certainty of

    the scope of obligation which is in the interests of all participants.

    Trust data and land issues

    It is essential for the contractors lawyers to ensure that his client will conduct

    a proper due diligence exercise regarding the trust data (having regard to the

    content of Clause 10) as the employer takes little, or no, responsibility for such

    information. I normally seek to ensure that under Clause 14 (Nature of Land

    Interest) sufficient ancillary rights (ie access/ingress/egress to site etc) are

    afforded to the project company (and thus the contractor) and that generally,

    land issues are fully investigated and potential threats and constraints are

    identified, assessed, priced and managed. Related to this is Clause 15 (the

    Site) which places the risk of the condition of the site squarely on theshoulders of the project company. Qualifications or carve-outs may need to

    be considered regarding such issues as areas of the site not capable of

    inspection, past contamination and areas retained by the employer (particularly

    on a multi-phase project).

    In relation to issues arising out of Consents and Planning Approval (Clause

    16), it will be necessary to check these various provisions, particularly those

    relating to the terms of consents and approvals, to make sure the obligations to

    comply are properly understood and allocated.

    16 See note 7.

  • 8/10/2019 PFI PPI

    13/24

    12

    Design, construction and commissioning process

    With regard to the project company/contractors obligations under Clause 17

    `(the Design, Construction and Commissioning Process), much thought will

    go into drafting Schedule 8 (Construction Requirements) and the related

    schedules dealing with reviewable design data, programming etc. It is usual toprovide that where documents are submitted through the review procedure

    (Schedule 10), unless there are any comments to the contrary, they satisfy the

    employers requirements in respect of clinical functionality.

    The employer requirements (output specification) should be clear,

    unambiguous, objective and measurable. With regard to design review

    procedures, it should be clear what is to be reviewed and when and on what

    basis the employer can object: usually only for failing to achieve compliance

    with the output specification or where the design is not in accordance with

    previously submitted designs.

    Programme

    With respect to Clause 19 (Programme and Date for Completion), I normally

    check whether there are any employer damages (see the OGC Guidance on the

    standardisation of PFI contracts for sensible advice17). To the extent that

    programming float has been built into the programme by the contractor, then I

    attempt to ensure that it is made clear that the float belongs to the contractor

    and not anybody else.

    Equipment

    The issue of equipment (Clause 21), should be considered carefully by all

    concerned and I attempt to check who is responsible for what bits of

    equipment. In respect of pre-completion equipment, the contractor should

    generally not be responsible for its provision, as this is normally the function

    of the equipment subcontractor. The contractor will attempt to ensure that the

    provision of the equipment does not interfere with his ability to achieve

    practical completion. The contractor must also keep a close eye on what, if

    any, impact the equipment has on the contractors design in particular

    whether any of the bigger items of equipment have design implications on

    already designed parts of the works. Important design/equipment interfacing

    issues arise which need to be carefully thought through and addressed. Thisrelationship is dynamic and evolves throughout the bid process up to financial

    close and beyond.

    Completion

    Another subject high on the contractors priority list, is the completion regime.

    Completion tests, criteria and sign off procedures must be (a) achievable, (b)

    unambiguous and (c) objective so that it is very clear that an item has passed

    or failed sign off. Completion procedures should allow for sequential testing

    (or shadow testing) with an early warning if any items are unlikely to achieve

    17 See note 6.

  • 8/10/2019 PFI PPI

    14/24

    13

    the completion test criteria. The contractor should insist on completion being

    determined on objective criteria and that it is achieved as quickly and

    efficiently as possible. The cost of any delay to completion incurred by the

    contractor will be horrendous (possibly running at up to 1 million per week,

    which includes but is not limited to liquidated damages).

    Often the objective completion criteria are set out, such that the independent

    tester simply ticks off his list to the effect that the facility exists and has been

    constructed in accordance with the reviewed design, and that (for example) the

    sample of rooms inspected comply with room data sheets.18 Often, the

    completion criteria are not, on the face of it, unduly strict. Hoewever, should

    defects subsequently be found to exist (not picked up when completion is

    certified), the contractor remains very much on the hook and liable for defects,

    insufficiencies etc, in the works, because usually the contractor agrees to be

    responsible for rectifying defects for a period of 12 years. This is a fair and

    balanced approach to determining completion. The contractor is not

    disproportionately penalised in terms of delay related loss and the employerretains its entitlement to have undiscovered defects addressed by the

    contractor.

    Fossils and antiquities

    In relation to fossils and antiquities (Clause 24), if this is considered a real

    likelihood, then consideration should be given to seeking compensation for

    time lost (currently only compensated if there is a variation to the facilities).

    Payment provisions

    The payment provisions (Clause 35 and Schedule 18) should always be

    reviewed for adequacy and consideration should be given to any project

    specific amendments that may be required.

    Insurance matters

    Sufficient time must be allowed for insurance advisers to liaise and advise

    regarding insurance matters (Clause 36 and Schedule 21). One point always

    of interest to a contractor is whether the project company is taking out advance

    loss of profit insurance which, if available, can alleviate the liquidated

    damages burden placed on the contractor in the event of delay (more aboutthis below).

    The ambit of Clause 38 (Information and Audit Access) is very wide and it is

    in both the project companys and the contractors interest to attempt to take

    out commercial confidential documentation from the scope of this provision.

    Delay events

    The wording of Clause 41.11 (Delay Events) is of particular concern to the

    contractor and appears to link the project companys entitlement to a

    compensation event to the award of an extension time. The clause reads: For

    18 Samples, because there may be up to 4,000-4,500 rooms on a large hospital job.

  • 8/10/2019 PFI PPI

    15/24

    14

    the purpose of Clause 41.10, a Compensation Event means any Delay Event

    referred to in Clause 41.3(b) [Breach], (c) [Execution of Non-Project Related

    Works] or (d) [Opening up of Works] for which, in each case, it has been

    agreed or determined pursuant to this clause that the project company is

    entitled to an extension of time. My concern is that this probably means that

    the project company will be entitled to compensation if (and only if) it isawarded an extension of time. This is manifestly unjust. The project

    company (and contractor) might incur disruption losses as a result of an

    employer breach of contract which does not give rise to an extension of time,

    or incur delay related losses on, say, a multi-phased project where such losses

    are not ultimately time critical and do not therefore attract an extension of

    time.

    If this interpretation is correct this clause contravenes the OGC Guidance on

    the subject, the gist of which (fairly in my view) provides that the project

    company should be entitled to compensation in the event of such matters as an

    employer breach of the project agreement (subject to proof ofentitlement/quantum in the normal manner). Paragraph 5.2.1.1 (page 45) of

    the OGC Guidance states In fact, even a delay is not strictly necessary for the

    occurrence of a Compensation Event as cost increases can arise without

    any timetable changes. Although this provision appears in the NHS standard

    form, it has not featured in any of the project agreements that I have reviewed

    on other bids in different industry sectors.

    On a more general note, the contractor is usually able to negotiate extended

    (more realistic) notification and procedural time periods for notifying the

    employer of delays and similar matters which must be notified. A check

    should always be made to ensure that time periods are not unreasonably short.If they are, they will not make much sense or be workable when the contractor

    attempts to step down these provisions in its subcontracts (which, in turn, may

    have to be further stepped down). Issues like this are matters of practicality

    (rather than legal point scoring) and usually there is little difficulty in

    achieving realistic and practical terms with the more experienced PFI advisers.

    Turning to Clause 44.1 (Project Company Event of Default), it is essential for

    the contractor to check that the long stop date allows adequate time to

    complete the works, assuming that the worst has happened, bearing in mind

    that liquidated damages will have to cover the whole period and will include

    loss of revenue stream.

    Intellectual property rights

    The requirement (albeit one of reasonable endeavours) in Clause 51.3, to

    ensure that any intellectual property rights (as described) vest and remain

    vested in the project company throughout the term of the agreement (25-30

    years) is not very realistic. Design consultants, amongst others, will not

    usually agree to vesting provisions in respect of their intellectual property

    rights. The clause refers to any Intellectual Property Rights created,

    brought into existence or acquired during the term of this Agreement as

    having to vest. Can one imagine representatives of Bill Gates at Microsoftagreeing to such a provision?

  • 8/10/2019 PFI PPI

    16/24

    15

    Dispute resolution procedures

    It will be important to review carefully Clause 56 and Schedule 26 (Dispute

    Resolution Procedure) as sometimes (and probably inadvertently) this

    schedule contains material which might give rise to unacceptable no loss type

    legal arguments which could have unintentional adverse implications for thecontractor. More generally, some employers tend to opt for arbitration as the

    ultimate dispute resolution process, not necessarily because they believe in it

    but because of the opportunities for avoiding the more accessible joinder

    provisions available to parties who litigate in the courts.

    Other provisions: finally, one should not forget to consider the commercial

    implications of some of the miscellaneous boilerplate clauses, contained near

    the end of the standard form, as some of these (such as entire agreement,

    Clause 61 and mitigation, Clause 67) do have real commercial implications.

    The design and build contract

    Limits on liability

    Although little or no risk remains with the project company, in the context of

    the design and build contract, that statement must be modified to recognise the

    practice of allowing the contractor to limit, or cap, its overall maximum

    liability for any and all losses to a certain percentage of the contract sum. This

    cap may be subject to limited qualifications or carve outs, usually relating to

    contractor liabilities which benefit from insurance coverage (in which case,

    any insured liability would not normally count towards the overall cap). This

    overall cap will typically have (as a constituent part) one or more sub-caps, themost notable being a limit on the contractors liability in respect of liquidated

    and ascertained damages. For instance, one might see the contractors

    maximum exposure to liquidated damages limited to 20% of the contract sum.

    The issue of the liquidated damages cap has a relationship with the long stop

    date. The funders lawyers will be keen to ensure that the liquidated damages

    cap can be reconciled with the long stop provision such that, in the event of

    delay, the project company is able to satisfy debt service via liquidated

    damages from the contractor.

    As mentioned earlier, it is a commercial fact that because of the high risk

    nature of PFI contracts generally (with severely limited abilities to utiliseclaims upstream), the contractor is, effectively, signing off his final account

    from the moment he signs the PFI construction contract. This reality must be

    understood, managed (and priced) for, by the contractor.

    Project documents

    It may be necessary throughout a design and build contract to expressly

    qualify the relevance of project documents, by utilising drafting devices such

    as insofar as the same relate to the design, construction, of the design

    and build works . Amongst the many obligations to be complied with,

    most design and build contracts require the contractor to observe and complywith the project documents. This term is often defined very widely and

  • 8/10/2019 PFI PPI

    17/24

    16

    sometimes not all of the project documents, as defined, are made available.

    Clearly such documents need to be identified, accessed and assessed.

    Generally, the design and build terms must be reviewed in their entirety with a

    view to deleting or limiting the often excessive use of general indemnity

    provisions (some of which are above and beyond what the projectcompany/employer reasonably need).

    Equivalent project relief

    The contractor should be entitled to a fair and reasonable proportion of any

    equivalent project relief to which the project company becomes entitled under

    the project agreement. Furthermore, and subject to reasonable protection as to

    legal and professional costs, the contractor should be entitled to require the

    project company to enforce rights and obligations regarding matters which

    have, or may have, an adverse effect on the construction contract and/or utilise

    name borrowing procedures to refer any disputes which arise to the agreeddispute resolution process. In terms of obtaining equivalent project relief,

    most PFI design and build contracts contain provisions whereby the project

    company and contractor agree that the latters entitlements upstream (which

    rely on the project company establishing entitlement under the project

    agreement) shall be limited to those benefits which the project company

    derives from the employer: employer derived benefits.

    Such provisions are often detailed and complex and are usually coupled with a

    related clause setting out the regime for pursuit by the contractor of project

    company entitlements under the project agreement. In order to keep the

    project company financially whole (as required by the funder), suchprovisions will mean that if the contractor wishes to pursue a dispute under the

    contract he must fully fund the legal and professional costs of doing so (this is

    where no loss type arguments might arise under the dispute resolution

    provisions in the project agreement). Often the contractor can negotiate that it

    will fund the costs of the project company which are properly and reasonably

    incurred (as well as its own costs).

    Interfacing issues

    The complexity of the PFI process, especially on the bigger, more complicated

    jobs (such as multi-phased large hospitals), gives rise to very complicatedinterfacing issues. Such issues can, as a matter of contractual structure, be

    dealt with entirely within the terms of each individual subcontract between the

    project company and the relevant subcontractor (whereby interfacing issues

    are co-ordinated and dealt with up and down via the project company, which

    is the preference of most construction contractors). Alternatively, such issues

    can be dealt with in a separate interface agreement; or a combination of these

    two approaches is possible. Such agreements deal with a myriad of issues,

    including inter-subcontractor disputes, design review and general co-

    ordination issues.

    In practice, this is a complicated and difficult matter to deal with satisfactorilyfrom everyones perspective. When it occurs which in my experience, is not

  • 8/10/2019 PFI PPI

    18/24

    17

    very often it is one of the more heavily negotiated elements of the design

    and build contract. It is usually preferable from the contractors perspective

    for all interfacing issues to be dealt with through the project company (who

    should have priced for the resource needed to co-ordinate). The project

    company often brings discipline (and sometimes a calming influence) to the

    treatment of inter-subcontractor disputes. The parties will tend to think twiceabout bringing claims against the project company, not wishing to sour

    commercial relations unnecessarily, whereas they may be less inhibited by the

    prospect of launching claims against another subcontractor.

    The active involvement of the project company, acting as it sometimes does as

    a quasi arbitrator if you like, reduces the potential for a free for all.

    Sometimes that can happen quite easily if inter-subcontractor disputes and

    issues are left to be resolved directly between the parties without the active

    involvement of the project company. The project company can be kept whole

    and protected financially because all the individual subcontracts will (or

    should) contain the type of protectionary provisions touched on above.Related interfacing issues concern what effect (if any) an interface agreement

    has on the limits of liability in construction and facilities management

    contracts and security (what if a subcontractor, against whom a large claim

    exists, becomes insolvent?)

    Construction Act avoidance

    In the context of keeping the project company whole, it is frequently a

    requirement for the contractor to enter into an agreement the purpose of which

    is to circumvent the protectionary provisions afforded by the Housing Grants,

    Construction and Regeneration Act 1996. Part II of the Act applies to thedesign and build contract with the project company but not to the project

    agreement between the project company and the employer.

    Such agreements are sometimes labelled loan agreement (or something

    equally misleading), the gist of which is that if, for whatever reason, the

    project company becomes liable to pay monies to the contractor, the latter will

    only receive such monies if and when the project company receive these

    monies from the employer (pay if paid). However, just in case the contractor

    challenges this arrangement, the loan agreement stipulates that at the very

    moment the contractor becomes entitled to receive X from the project

    company, the contractor immediately becomes obliged to make a loan of thatvery same X to the project company. This, in turn, is supplemented by

    further interesting provisions aimed at discouraging any challenge to this

    arrangement by the contractor. Other devices include loans made by sister or

    parent companies and independent guarantees of loans. As far as I can tell,

    nobody really knows whether the loan agreement type device would be upheld

    if tested before the courts: time may tell.

    Performance bonds and parent company guarantees

    The OGC Guidance queries the appropriateness of bonds and parent company

    guarantees in PFI contracts, suggesting that collateral warranties and/or directagreements, as well as the project documents themselves, should provide

  • 8/10/2019 PFI PPI

    19/24

    18

    sufficient comfort and protection for the employer.19 In practice however, a

    parent company guarantee is usually required from the contractor in favour of

    the project company (assignable to the bank by way of security). A bond is

    not usually required and certainly not both a bond and a parent company

    guarantee, in most circumstances. The terms of the bond and parent company

    guarantee will be qualified to contain the usual cluster of provisions normallyrequired by the contractor.

    Direct agreements

    Any direct agreements between the contractor and the fund and employer will

    also contain the usual protectionary provisions required by the contractor. In

    the funder direct agreement, the most heavily negotiated issue often revolves

    around the length of the suspension period by which the contractors right to

    terminate the contract by reason of project company default is suspended

    whilst the funder is afforded a reasonable period of time to decide whether to

    exercise their step in rights, or appoint a receiver, or additional obligor, ornovate the contract. Whilst the concerns of the funder are understandable, so

    too are the concerns of the contractor to be paid monies owed to it and not be

    forced to wait unduly long periods before it can terminate the contract. The

    longer the contractor must remain on site whilst not being paid, the greater its

    exposure to losses which can, quite easily, run into tens of millions of pounds.

    In practice a reasonable compromise is usually achievable.

    It will be essential to ensure that the terms of the funders direct agreement

    and the employer direct agreement are reconciled the funder usually gets

    priority. On a more general level, any warranties the contractor gives to the

    funder or employer via the direct agreement will invariably be expressed asonly applying in circumstances where the project agreement between

    employer and project company is terminated and step in rights are exercised.

    Even then, such warranties should not be greater in extent or duration than

    those imposed upon the contractor by the terms of the design and build

    contract.

    Delays

    Unless the contract says otherwise, the project company (and the contractor on

    a pass through) will be responsible for delays to the project. Exceptions in

    PFI are as follows: compensation events, relief events orforce majeure events.

    Compensation events are those expressly stated to be at the employers risk

    and in respect of which the project company should be compensated. The

    following should be treated as compensation events in all projects: employer

    breach of an obligation (which includes a breach occasioned by third parties

    for whom the employer is responsible, such as teachers or doctors); employer

    changes; and discriminatory or specific changes in law. Experience has shown

    that in certain circumstances, it may be possible to extend this list to problems

    related to planning delays and possibly, also, difficulties encountered with

    archaeological works. Sometimes certain types of ground conditions are

    19 See note 6, section 22.4.

  • 8/10/2019 PFI PPI

    20/24

    19

    included as a compensation event, for example, on hospital projects where the

    contractor has been unable, or given no realistic chance, to check the state of

    the ground (eg for contamination), for instance where an old hospital building

    is to be demolished and rebuilt immediately. If a compensation event occurs,

    and it has an impact on the planned service commencement date, that date may

    need to be postponed. Any long stop date would be similarly pushed back. Ifthe project agreement contains a liquidated damages provision, the project

    companys liability for liquidated damages will also be relieved for the period

    of delay caused by the compensation event. The project company should also

    be relieved of any other liabilities or employer losses in respect of the event.

    Relief events are those which prevent performance by the project company of

    its obligations at any time. The project company bears the financial risk in

    terms of increased costs and reduced revenue but it is given relief from

    termination for failure to provide the full service. In most cases, termination

    should not follow a relief event. They are best managed by the project

    company (although not necessarily in its control). They are usually defined asincluding such incidents as fire, explosion, lightning, storm, tempest, flood,

    bursting or overflowing of water tanks etc. The financial effects of delay

    caused by relief events are borne by the project company (and the contractor)

    so no compensation will be paid by the employer on the occurrence of such a

    delay. If a relief event occurs prior to service commencement, any long stop

    date will usually be extended by a period equal to the relevant delay. If a

    relief event occurs, the contractors liability to the project company in respect

    of liquidated and ascertained damages will continue, even if the project

    companys date is extended under the project agreement (because the

    financing debt must continue to be serviced).

    Force majeureevents are a limited set of events which arise during the life of

    the contract through no fault of either party, which are best managed by the

    contractor (although not in its control) and in respect of which rights of

    termination can arise.

    One very notable difference between the PFI process and traditional JCT

    building contracts is that under, say, JCT 1998,20 upon establishing an

    entitlement to an extension of time for, say, delay caused by a fire or flood

    (Specified Perils) the contractor would be entitled to an extension of time

    under clause 25. The extension would give rise to relief from the liability to

    pay liquidated and ascertained damages to the employer. In contrast, the

    contractor in a PFI construction contract will usually not be relieved from

    liquidated damages because of the fire or storm but will continue to be liable

    to pay liquidated damages to the project company. This liability will be

    abated only in circumstances where an advance loss of profits insurance policy

    kicks in and the proceeds are used to alleviate the contracting losses. This is

    all about keeping the project company whole and satisfying the project

    companys continuing obligation to service its debts to the funder. This

    considerable risk should encourage contractors to focus carefully on a number

    of matters including the viability and reality of their proposed construction

    programmes.

    20 Standard Form of Building Contract, 1998 edition, The Joint Contracts Tribunal Ltd.

  • 8/10/2019 PFI PPI

    21/24

    20

    Changes

    The project agreement should contain a mechanism whereby changes in

    services or variations may be proposed by either party and evaluated and

    approved prior to implementation. Generally, employer changes should be

    limited to changes to the service requirement. If the project company is fullyprotected in the project agreement against the consequences of an employer

    change, including how the change is to be paid for, there should be no

    objection from the project companys financiers.

    As mentioned, discriminatory and specific changes in law usually constitute

    compensation events, the remedies for which benefit the contractor as well as

    the project company. The bigger risk for the contractor relates to general

    changes in the law. The contractor must, to some extent, crystal ball gaze and

    take a view as to likely changes coming into force during the currency of the

    construction works. Such changes might be ascertained by reference to

    published Green and White Papers and proposed changes emerging fromEurope. On a typical hospital project, the contractor might reasonably be

    expected to take the risk of compliance with general changes in law which

    might apply over a period of say, 18 months to 2 years. On some of the

    bigger, more complicated hospital projects, where the construction contract

    period is likely to be in excess of 2 years (sometimes 4 years and over) a

    different (shared) approach to risk allocation may be appropriate. Although a

    contractor might envisage general changes over long construction periods, it is

    often not reasonably possible to foresee the exact nature of any changes and

    therefore, it may be impossible for the project company or contractor to form a

    realistic view as to how to price this risk. Any attempt to price such

    uncertainty would be imprecise, probably excessive and would not representvalue for money.

    The OGC Guidance is helpful and suggests an alternative approach: the

    recognition that it may be more equitable in certain circumstances for the

    employer to share costs which are difficult for the project company (and

    therefore the contractor) to manage.21 One suggestion is that general changes

    in law requiring capital expenditure taking effect during a typical construction

    phase might be at the risk of the project company (and contractor) in terms of

    time and money. On the other hand, on projects which have unusually long

    construction periods, transferring risk of general changes in law for the entire

    construction period (rather than adopting a sharing approach) may, in fact,represent poor value for money and is likely to be difficult to achieve in

    practice.

    Termination

    A project agreement will terminate either on the expiry date (typically after

    25-30 years) or as a result of early termination. Early termination can be

    caused by employer default, project company default, force majeure, corrupt

    gifts and in circumstances of voluntary termination by the employer.22 The

    21 See note 6, section 13.8.22 See note 6, section 20.5.

  • 8/10/2019 PFI PPI

    22/24

    21

    project agreement should deal comprehensively with the consequences of all

    types of termination and in particular, it must address what happens to the

    asset and what termination payments (if any) are payable by the employer. It

    is widely accepted that the level of compensation payable by the employer

    should be determined by such factors as the reasons for the termination, which

    party retains the asset, and whether those assets have any alternative use.

    The objective of compensation on termination for employer default should be

    to ensure that the project company and its financiers are fully compensated

    (that is, no worse off) because of employer default than if the project

    agreement had proceeded as expected. A footnote to the OGC Guidance states

    that the compensation payable should reflect a realistic calculation of an

    anticipated claim for damages, and therefore should be an exclusive remedy of

    the project company leaving no residual claim for damages.23 Usually, the

    drafting of compensation on employer default clauses will involve paying the

    project company an amount equal to the aggregate of the senior debt,

    redundancy payments (for employees of the project company that have beenor will be reasonably incurred as the direct result of termination of the project

    agreement) and amounts payable to the subcontractors under the project

    documents as a direct result of the termination.

    Termination on contractor default should be restricted to acts involving the

    severest of defaults, when all other reasonable alternative options have been

    exhausted. There should be no possibility of unjust enrichment and the

    remedy should be the employers last resort. The events of project company

    default which may lead to termination should be objective, clear and provide

    for reasonable tolerances. Such events of default should be limited to

    breaches which have a material and adverse impact on the performance of theservices.

    The aim with regard to compensation for project company default is to ensure

    that it is dealt with within the project agreement. The level of compensation

    agreed on contractor default termination should represent a balance between

    protecting the employers interests and not imposing unreasonable deductions

    on the project company for its default.

    Land issues

    It is usual for the project company to procure a certificate of title to the landupon which the project is to be built. The due diligence undertaken will result

    in a report which will highlight the nature and extent of interests held by third

    parties which could impact on the contractors ability to perform its

    obligations. In particular, the contractor should look out for unduly onerous

    restrictive covenants, easements or constraints on the site. Do not overlook

    tower cranes and the need for tower crane licences to be negotiated with

    neighbours. If the issue of tower crane licences has not been properly thought

    through (and priced for) before commencement of construction, the contractor

    risks being faced with potential ransom licence fee demands. The same

    worry applies to scaffolding licences, where applicable. The due diligence

    23 See note 6, section 20.1.3.1.

  • 8/10/2019 PFI PPI

    23/24

    22

    exercise should also pick up and disclose any existing section 60 or 61 Control

    of Pollution Act constraints which may apply to the site.24

    Design

    The level of design responsibility in the design and build contract will usuallymirror the equivalent obligation in the project agreement. In the case of the

    NHS standard form, this is set out in Clause 17.2 as follows: The project

    company warrants that it has used and will continue to use the degree of skill

    and care in the design of the Facilities that would reasonably be expected of a

    competent professional designer experienced in carrying out design activities

    of a similar nature, scope and complexity to those comprised in the Works.

    There is some debate as to whether this wording would be sufficient to

    displace the implied term of fitness for purpose.

    Much effort will go into the preparation and negotiation of consultants terms

    of appointment and subcontracts and these must, as far as possible, becompatible with the risk profile of the project agreement and construction

    contract. In terms of administering these contracts, procedures and time

    periods (upstream) should be sensible, otherwise they will not work when

    stepped down into subcontract conditions. This is a fact sometimes

    overlooked in the drafting of project documentation. On a positive note, the

    PFI regime allows much more scope than exists in traditional procurement

    methods for main contractors to develop meaningful long term relationships

    with subcontractors and suppliers. This is done by way of framework

    agreements with key subcontractors and suppliers. Such relationships reduce

    the scope for wasteful conflict and give rise to win:win relationships, which

    means value for money for everyone involved in the process.

    Assignment

    Save for circumstances where the project company can assign or charge the

    benefit of the design and build contract to the funder (or funders agent) in

    connection with the funding of the project, the contractor will be keen to

    prevent any further or other assignment without its express written consent.

    Collateral warranties

    Sometimes (but not always) the contractor is asked to procure collateralwarranties from its subcontractors in favour of various beneficiaries. The

    contractor may well not accept this. In my view, they are (in a PFI context)

    both unnecessary and expensive and are contrary to the value for money

    aspirations of PFI projects. In contrast, however, it is quite normal for direct

    agreements to be provided by the contractors major design consultants in

    favour of the funder and the employer.

    24 Control of Pollution Act 1974.

  • 8/10/2019 PFI PPI

    24/24

    Conclusion

    Does PFI work? In my experience so far, yes it does. The public private

    partnership represents an optimum means of procurement, which invariably

    gets the best out of the private sector. Primarily, this is because the private

    sector takes a stake in the process and is therefore incentivised to make itwork. This, in my experience, rarely happens in traditional cut-throat

    contracting. Innovation by the private sector, accompanied as it usually is

    with a reduction in conflict between the participating parties, gives rise to

    value for money for everyone and real meaning to the concept of partnership.

    The potential to extend the process beyond current limits seems to me an

    exciting prospect with very real chances of success because of its success to

    date. In the real world, economic constraints apply to any governments

    ability to build enough new hospitals and schools to satisfy societys needs

    and demands. PFI/PPP allows more hospitals, schools and other necessary

    infrastructure to be constructed or upgraded (by utilising private finance) thanwould otherwise be the case.

    Despite taking on greater risk when compared to most methods of traditional

    procurement, the contractor has the potential to earn better profit margins if it

    manages to get it right in terms of delivering the product the employer wants

    (an aim the PFI process lends itself to). I believe PFI as a means of

    procurement gives real meaning to the term partnership when used in the

    public private partnership context. When the process goes well (and most

    projects, in my experience, do go well for both sides), a true win:win situation

    arises. The employer generally gets what it wants in terms of a product and

    service with relatively strong certainty of price, time of delivery and quality,giving real meaning to the term value for money. In turn, the contractor gets a

    fair and proportionate return commensurate with the risk:reward profile

    applying to the PFI procurement regime.

    One of the most striking benefits of the PFI process is that as more projects

    come on stream, people up and down the country are witnessing something

    real happening within their communities: the construction of more new

    schools, hospitals and other necessary projects which will be of direct benefit

    to us all in our everyday lives. These projects are, in numerous instances,

    replacing demoralising, crumbling, often Dickensian hospitals, schools and

    other structures. In all likelihood this would not be happening but for PFI.

    Martin Lenihan BA (Hons), LLM (Lond), ACIArb, barrister, is legaladviser to the Skanska Construction Group Limited.

    Martin Lenihan and the Society of Construction Law 2002.

    The views expressed by the author in this paper are his alone, and do not

    necessarily represent the views of the Society of Construction Law or the

    editor, neither of whom can accept any liability in respect of any use to whichthis paper or the information in it may be put.


Recommended