PG&E’s Emerging Technologies Program ET12PGE1381
FIELD ANALYSIS OF COMMERCIAL VARIABLE
REFRIGERANT FLOW HEAT PUMPS
ET Project Number: ET12PGE1381
Product Manager: Peter Biermayer Pacific Gas and Electric Company Prepared By: Harshal Upadhye Electric Power Research Institute 942 Corridor Park Blvd. Knoxville, TN 37932
Issued: December 2, 2014
Copyright, 2014, Pacific Gas and Electric Company. All rights reserved.
i
PG&E’s Emerging Technologies Program ET12PGE1381
ACKNOWLEDGEMENTS
Harshal Upadhye, of Electric Power Research Institute (EPRI), conducted this technology evaluation for Pacific Gas and Electric Company and is published as ‘Field Analysis of Commercial Variable Refrigerant Flow Heat Pumps. EPRI, Palo Alto, CA: 2014. 3002004364. The work was performed under the guidance and management from Chris Li and Keith Forsman of PG&E, which is responsible for this project. It was developed as part of Pacific Gas and Electric Company’s Emerging Technology – Technology Assessments program under internal project number ET12PGE1381. For more information on this project, contact Chris Li at [email protected].
PG&E LEGAL NOTICE
This report was prepared for Pacific Gas and Electric Company for use by its employees and agents. Neither Pacific Gas and Electric Company nor any of its employees and agents:
(1) makes any written or oral warranty, expressed or implied, including, but not limited to those concerning merchantability or fitness for a particular purpose;
(2) assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, process, method, or policy contained herein; or
(3) represents that its use would not infringe any privately owned rights, including, but not limited to, patents, trademarks, or copyrights.
ELECTRIC POWER RESEARCH INSTITUTE, INC. DISCLAIMER OF WARRANTIES AND LIMITATION OF
LIABILITIES THIS DOCUMENT WAS PREPARED BY THE ORGANIZATION(S) NAMED BELOW AS AN ACCOUNT OF WORK SPONSORED OR COSPONSORED BY THE ELECTRIC POWER RESEARCH INSTITUTE, INC. (EPRI). NEITHER EPRI, ANY MEMBER OF EPRI, ANY COSPONSOR, THE ORGANIZATION(S) BELOW, NOR ANY PERSON ACTING ON BEHALF OF ANY OF THEM:
(A) MAKES ANY WARRANTY OR REPRESENTATION WHATSOEVER, EXPRESS OR IMPLIED, (I) WITH RESPECT TO THE USE OF ANY INFORMATION, APPARATUS, METHOD, PROCESS, OR SIMILAR ITEM DISCLOSED IN THIS DOCUMENT, INCLUDING MERCHANTABILITY AND FITNESS FOR A PARTICULAR PURPOSE, OR (II) THAT SUCH USE DOES NOT INFRINGE ON OR INTERFERE WITH PRIVATELY OWNED RIGHTS, INCLUDING ANY PARTY'S INTELLECTUAL PROPERTY, OR (III) THAT THIS DOCUMENT IS SUITABLE TO ANY PARTICULAR USER'S CIRCUMSTANCE; OR
(B) ASSUMES RESPONSIBILITY FOR ANY DAMAGES OR OTHER LIABILITY WHATSOEVER (INCLUDING ANY CONSEQUENTIAL DAMAGES, EVEN IF EPRI OR ANY EPRI REPRESENTATIVE HAS BEEN ADVISED OF THE POSSIBILITY OF SUCH DAMAGES) RESULTING FROM YOUR SELECTION OR USE OF THIS DOCUMENT OR ANY INFORMATION, APPARATUS, METHOD, PROCESS, OR SIMILAR ITEM DISCLOSED IN THIS DOCUMENT.
REFERENCE HEREIN TO ANY SPECIFIC COMMERCIAL PRODUCT, PROCESS, OR SERVICE BY ITS TRADE NAME, TRADEMARK, MANUFACTURER, OR OTHERWISE, DOES NOT NECESSARILY CONSTITUTE OR IMPLY ITS ENDORSEMENT, RECOMMENDATION, OR FAVORING BY EPRI.
THE FOLLOWING ORGANIZATION(S), UNDER CONTRACT TO EPRI, PREPARED THIS REPORT: ELECTRIC POWER RESEARCH INSTITUTE (EPRI)
THIS IS AN EPRI TECHNICAL UPDATE REPORT. A TECHNICAL UPDATE REPORT IS INTENDED AS AN INFORMAL REPORT OF CONTINUING RESEARCH, A MEETING, OR A TOPICAL STUDY. IT IS NOT A FINAL EPRI TECHNICAL REPORT.
THIS IS AN EPRI TECHNICAL UPDATE REPORT. A TECHNICAL UPDATE REPORT IS INTENDED AS AN INFORMAL REPORT OF CONTINUING RESEARCH, A MEETING, OR A TOPICAL STUDY. IT IS NOT A FINAL EPRI TECHNICAL REPORT.
NOTE
For further information about EPRI, call the EPRI Customer Assistance Center at 800.313.3774 or e-mail [email protected].
Electric Power Research Institute, EPRI, and TOGETHER SHAPING THE FUTURE OF ELECTRICITY are registered service marks of the Electric Power Research Institute, Inc.
Copyright © 2014 Electric Power Research Institute, Inc. All rights reserved.
ii
PG&E’s Emerging Technologies Program ET12PGE1381
FIGURES
Figure 1 PG&E Customer Service Office- Auburn, California ........... 7
Figure 2 Birds-eye View of PG&E Auburn Office Building (From
maps.google.com) ........................................................ 8
Figure 3 Basement Plan and Indoor Units ................................... 8
Figure 4 1st Floor Plan and Indoor Units ...................................... 9
Figure 5 2nd Floor Plan and Indoor Unit Locations ......................... 9
Figure 6 3rd Floor Plan and Indoor Unit Locations ....................... 10
Figure 7 Schematic of the Data Acquisition ............................... 14
Figure 8 Cooling Degree Day (CDD) and Heating Degree Day
(HDD) (Base 65°F) ..................................................... 15
Figure 9 Measured Temperature (68-80°F Comfort Zone) ........... 15
Figure 10 Measured Relative Humidity (20-80% Comfort Zone) .... 16
Figure 11 Outdoor Conditions Split in Temperature and Relative
Humidity Bins ............................................................ 17
Figure 12 Outdoor Conditions Split in Temperature and Relative
Humidity Bins (VRF System in Occupied Mode) .............. 17
Figure 13 Load Shape of VRF System (All Year Average; Summer
and Winter) ............................................................... 18
Figure 14 Comparison between PG&E Meter Data and EPRI HVAC
Monitoring Data ......................................................... 20
Figure 15 Recorded Billing Demand and VRF System HVAC
Demand .................................................................... 21
Figure 16 Average Power Draw versus Temperature Bins ............. 22
Figure 17 Indoor Unit Operating Hours in Heating or Cooling
Mode (All 13 Units Combined) ...................................... 24
Figure 18 Operating Hours in Each Mode (Fan, Cooling, Heating
and Mixed) for the VRF System .................................... 25
Figure 19 Indoor Unit 8A and 8B Operating in different Modes
during the Same Time ................................................ 26
Figure 20 Number of Hour’s Indoor Unit 8A and 8B are Operating
in Opposite Mode ....................................................... 26
Figure 21 Operating Mode and Hours for Indoor Unit in Data
Center ...................................................................... 28
Figure 22 Minimum Temperature Recorded for Each Month for
Return Air in the Data Center....................................... 28
Figure 23 Monthly Capacity Delivered for Each Floor .................... 30
iii
PG&E’s Emerging Technologies Program ET12PGE1381
Figure 24 Average EER versus Temperature Bins ......................... 31
Figure 25 Calibrated VRF Systems Modeled Energy Use vs
Metered Energy Use ................................................... 34
Figure 26 Energy Use Intensity for the VRF and PSZ Models
Highlighting the Source of Energy Savings .................... 35
TABLES
Table 1 Summary of VRF Systems Considered for Monitoring ....... 6
Table 2 California Climate Zone (CZ) for Sites Considered ........... 6
Table 3 Outdoor Units ........................................................... 10
Table 4 Indoor Units ............................................................. 11
Table 5 Accuracy of Sensors Used .......................................... 13
Table 6 Comparison of PG&E Billing Data and EPRI VRF System
Monitoring Data ......................................................... 19
Table 7 Maximum Demand from VRF System ........................... 21
CONTENTS
FIELD ANALYSIS OF COMMERCIAL VARIABLE REFRIGERANT FLOW HEAT PUMPS 1
EXECUTIVE SUMMARY ____________________________________________________ 1
INTRODUCTION _________________________________________________________ 3
BACKGROUND __________________________________________________________ 4
ASSESSMENT OBJECTIVES __________________________________________________ 5
TECHNOLOGY/PRODUCT EVALUATION ________________________________________ 5
site selection ......................................................................... 5
Site Details ............................................................................ 7
Emerging Technology/Product ................................................ 10
System Control Scheme ........................................................ 11
Fan Mode ....................................................................... 11 Cooling Mode .................................................................. 12 Heating Mode ................................................................. 12
TECHNICAL APPROACH/TEST METHODOLOGY _________________________________ 12
System Monitoring ............................................................... 12
Equipment Used ................................................................... 12
EVALUATIONS/ANALYSIS _________________________________________________ 14
Weather .............................................................................. 14
iv
PG&E’s Emerging Technologies Program ET12PGE1381
Electrical Characteristics ....................................................... 18
Thermal Characteristics ......................................................... 22
Determining mode of operation of indoor unit ..................... 22 Outdoor unit operating mode ............................................ 23
Operating Hours ................................................................... 23
Capacity Measurements ........................................................ 29
MODELING ____________________________________________________________ 31
Model Development .............................................................. 31
Input Assumptions .......................................................... 32
Envelope ............................................................................. 32
Internal Gains ...................................................................... 32
HVAC - VRF .................................................................... 32
Model Calibration ................................................................. 33
Weather Data ................................................................. 33 Metered Data .................................................................. 33 Calibration Process .......................................................... 33
Packaged Single Zone Model .................................................. 34
Energy Savings .................................................................... 34
DISCUSSIONS AND CONCLUSIONS __________________________________________ 35
RECOMMENDATIONS ____________________________________________________ 37
APPENDICES __________________________________________________________ 38
Monitoring Equipment ........................................................... 38
Obvius AcquiSuite A8810 – Main Data Acquisition Server ..... 38 Obvius Modhopper R9120-5 .............................................. 39 Obvius Flex IO – A8332-8F2D ........................................... 40 Dwyer Series RHP – Humidity/Temperature Transmitter ....... 41 Dwyer Series RH-R – Humidity/Temperature Transmitter ..... 42 ACCU-CT – Split-Core Current Transformer ........................ 43 ELKOR WattsOn .............................................................. 44
Installed mitsubishi equipment .............................................. 45
PURY-P288TSJMU-A ......................................................... 45 PVFY-P18E00A ................................................................ 46 PKFY-P06NAMU-E ............................................................ 47 PKFY-P30NFMU-E ............................................................ 48 PEFY-P36NMAU-E ............................................................ 49 PEFY-P24NMAU-E ............................................................ 50 PEFY-P48NMAU-E ............................................................ 51 PLFY-P08NCMU-E ............................................................ 52 PLFY-P15NCMU-E ............................................................ 53 CMB-P1013NU-GA ........................................................... 54
filters applied to monitored data ............................................ 55
v
PG&E’s Emerging Technologies Program ET12PGE1381
MODELING APPENDIX ........................................................... 61
ZONING ......................................................................... 61
REFERENCES ___________________________________________________________ 62
1
PG&E’s Emerging Technologies Program ET12PGE1381
EXECUTIVE SUMMARY There is a need for detailed measurement of field performance of variable refrigerant flow
heat recovery systems (VRF-HR) to both help characterize actual yearly energy savings
potential, and to provide quality data for use in energy modeling verification. This project
comprised instrumenting and measuring the in-situ performance of such a system in the
Northern California region.
Data representing thermal and electrical characteristics of the VRF system was collected
from the site for a period of 1 year – from June 2013 to May 2014. The electrical
characteristics were used to determine the energy used, load profile, and demand imposed
by the system on the grid.
As a part of this project, the building and the VRF system were modeled by PECI, Inc. The
results from the modeling exercise are presented in this report. The energy model was
developed using AecoSim Energy Simulator (AES), which is a front end for EnergyPlus.
PROJECT GOAL
This report documents the findings from a monitoring exercise on a 13 zone VRF-HR (heat
recovery) system. The project had the following objectives:
To collect operational performance data on an installed VRF-HR system
To collect a data set that is appropriate to provide energy modeling developers with
a validation tool
To model and compare VRF performance to a companion 2008 Title 24 code
compliant HVAC system in the same, or a similar, building
Provide objective analysis and performance characterization of a field installed VRF-
HR system
The data set will also be available for any further analysis or validation of new VRF
models.
PROJECT DESCRIPTION
The selected site for this VRF field monitoring project is a 4-Floor PG&E office building in
Auburn, California which is in California Climate Zone 11.
The VRF system installed at this location is a 24 ton Mitsubishi City Multi 2-pipe VRF system
with heat recovery capabilities (simultaneous heating and cooling operation is possible). The
system has a total of 13 indoor units connected to it.
PROJECT FINDINGS/RESULTS
The objective of this project was to monitor the in-situ performance of a VRF system and
provide performance characterization based on the data recorded. A summary of observed
characteristics is as follows:
2
PG&E’s Emerging Technologies Program ET12PGE1381
1. The monitored ambient conditions show slight variation from the published weather
data for Auburn, California. The variations can be attributed to the limited data set
that is available for the site - single point ambient measurements made only for one
year.
2. Summer load shape shows high demand during peak periods for utilities (coincident
load). The winter load shape shows a high demand imposed outside of the office
hours (early mornings). The trends from the demand data show that during the
winter time, the VRF system maximum demand is during the very early morning
hours (2:00 am to 5:00 am) whereas in summer time the maximum demand is
during the morning startup phase or during hot afternoon hours.
3. The high demand during summer peak hours makes the VRF installation a potential
candidate for a Demand Response program. The significant controls as well as
communications capabilities further necessitate investigation into the DR
possibilities.
4. The high demand during the early morning startup period could be eliminated by
staging the units during the initial ramp-up. This can be done by setting different
occupied / unoccupied time periods for different units.
5. The difference between PG&E billing data and EPRI measurements indicate that the
average energy usage by other loads in the building is 3,865 kWh per month.
6. The outdoor conditions in which a VRF system is operating have significant impact on
the power draw from the system. As expected, at extremes of temperature range,
the power draw is higher (either cooling mode or heating mode) and in the milder
ambient conditions the power draw is lower.
7. The second floor has the least heating or cooling needs. The third floor, due to the
roof, sees higher impact from ambient conditions. The first floor which has a
customer entrance and high ceilings in the customer service area is where most of
the capacity is delivered.
8. Indoor units 8A and 8B which serve third floor open space operated in opposite mode
(one in cooling and other in heating) at the same time for 39 hours during the period
of monitoring. Since the units serve the same space, it appeared that the units were
fighting each other. This can be remedied by grouping units together and forcing
them to operate in a single mode. That way the systems don’t fight each other. This
can also be done for indoor units 4A and 4B as well as 7A and 7B.
9. Indoor unit 2 serves a small data center which also has a backup split system. The
cooling from the backup system was potentially forcing the indoor unit 2 to operate
in heating mode. The data center is usually a cooling load so heating mode operation
of the indoor unit 2 isn’t expected. Through the control scheme, this indoor unit can
be locked in cooling mode or the setback temperature can be reduced significantly so
that the unit doesn’t kick into heating mode.
10. Modeling showed that the EnergyPlus model can predict the energy usage of the
modeled building within ±15% of actual energy use for the VRF system. Comparison
between a modeled baseline and a VRF system showed significant energy savings in
heating mode and fan energy savings.
3
PG&E’s Emerging Technologies Program ET12PGE1381
PROJECT RECOMMENDATIONS
Based on the data analysis and performance characterization, a few recommendations are
made that are applicable to this site but can also be extended across other VRF installations.
The biggest opportunity in terms of energy savings in a VRF technology is the ability to
modulate components as well as change local set points while maintaining occupant comfort
throughout the building. Control over fan speed and tying fan speeds, occupancy and
ventilation air (fresh air) supply together might reduce the load on the system. The control
scheme shared for the purpose of this project indicates that the fan runs when the system
has any indoor unit operating. Thus, in winter months the outdoor unit brings in outside
cold air when there is no need for fresh air (unoccupied mode).
Another energy savings opportunity based on findings of this study is the opportunity for
continuous commissioning. The indoor units fighting each other or the data center indoor
unit operating in heating mode are opportunities to save energy which is wasted if the
system operation is not reviewed. The existing sensors and controls on the system are
capable of determining these issues. If incentives for continuous commissioning are used in
such situations, further energy savings could be realized. Commissioning at time of install
can also be monitored carefully to make sure building characteristics are taken into
consideration. This building for example is a historic building with substantial air leakage
and minimum insulation. The winter operation of this system is heavily dependent on the
type of building and less so on the actual control scheme of the building.
There is an opportunity to investigate demand response potential of this technology
especially since this is a coincident load during summer time. The controls and
communications capability are already included in the product and unlocking the potential
could be the next step to further benefit from this technology.
INTRODUCTION At the heart of the drive towards making buildings highly energy efficient is the need to use
the precise amount of energy required to perform certain tasks, and no more. The historical
norm, with a source of plentiful and inexpensive energy, was to use energetically competing
systems that ultimately balance according to comfort and task execution needs, without
serious regard to energy consumption. The new approach is to understand the overall
exchange of energy on a temporal basis throughout a building, including the exchange with
the outside environment and the needs of the interior building functions. Using that
understanding, you can implement systems that provide for these needs – space
conditioning, lighting, appliances, etc. – treating energy as a valuable and limited resource
that should be expended only as necessary.
Technological improvements in the Heating, Ventilation, and Air Conditioning (HVAC)
industry focus on matching the energy supplied (e.g., cooling or heating) to the load
demanded, and doing so with smooth control and efficient delivery. New technologies like
Variable Refrigerant Flow (VRF) which employ inverter driven technology, variable speed
drives for motors and compressors, on-board diagnostics and inexpensive controls have
made it possible to provide highly efficient and flexible cooling and heating.
4
PG&E’s Emerging Technologies Program ET12PGE1381
In addition to energy efficiency, demand response (DR) for peak load reduction, reducing
facility loading, managing renewable integration, and other uses are important to utilities.
New technologies for adjustment of power used by air conditioners, water heaters and
appliances are being introduced around the country.
Many utility programs base incentive amounts and calculated energy savings on the
marginal difference between rated efficiencies of particular classes of HVAC equipment, such
as packaged rooftop air conditioners and heat pumps. The inherent variability in VRF
equipment lends the equipment to be characterized based on single point fixed operation
mode. This generates questions as to the direct applicability of the rating test as an
accurate representation of actual field performance relative to other unitary equipment. The
interaction of the HVAC system with the building is another important parameter that is not
addressed in laboratory testing.
This report documents the findings from a monitoring exercise on a 13 zone VRF-HR (heat
recovery) system.
BACKGROUND Over the course of the last several years, a VRF rating standard was developed and resulted
in the ANSI/AHRI standard 1230: Performance Rating of Variable Refrigerant Flow (VRF)
Multi-Split Air-Conditioning and Heat Pump Equipment. This standard identifies the
methodology for determining standard cooling, heating and simultaneous cooling & heating
operational efficiency. The intent of the standard was to allow comparison of VRF equipment
performance with that of unitary equipment at similar operating conditions.
Many utility programs base incentive amounts and calculated energy savings on the
marginal difference between rated efficiencies of particular classes of HVAC equipment, such
as packaged rooftop air conditioners & heat pumps. Comparison of VRF to traditional unitary
equipment in this similar manner represents a partial change in approach since two different
classes of HVAC equipment are being compared. The crafters of the 1230 rating standard
attempted to address this by making the testing conditions and methodology as similar to
the unitary standards (ANSI/AHRI 210/240 and 340/360) as possible by allowing for VRF
systems to be operated at manufacturer-determined fixed operating conditions (compressor
& blower fan speeds and expansion valve openings). This leaves a rating standard which
tests equipment at fixed operation, while the same equipment in the field will vary its
operation in accordance with changing load. This creates questions as to the direct
applicability of the rating test as an accurate representation of actual field performance
relative to other unitary equipment.
Much of the potential energy savings attributed to VRF systems may come from the
interaction of the system with the building—such savings would not be captured by a rating
test. Examples of this type of savings are: lower convection losses from refrigerant lines
compared to ductwork, delivery of conditioned air more directly to the occupied space,
rather than to the entire building volume and increased zoning with individual temperature
control.
Simple comparison of rating numbers may turn out to be a valid method for comparing VRF
to unitary systems, but there are currently sufficient questions that require further
understanding. Currently, energy savings derived from VRF use are generally considered
5
PG&E’s Emerging Technologies Program ET12PGE1381
difficult to characterize via any deem-able method and are thus typically modeled via
EnergyPro, Energy Plus, and related building simulation software packages.
Laboratory testing is used for characterization and verification of equipment performance,
but does not address the HVAC system interaction with the building. Field testing will be
used to develop energy and power consumption profiles of the integrated building/HVAC
(VRF-HR) system. Robust field data can then be used to vet and validate VRF modeling
modules, with the aim of producing reliable and repeatable models of energy and power
draw characteristics of buildings using VRF systems.
ASSESSMENT OBJECTIVES There is a need for detailed measurement of field performance of variable refrigerant flow
heat recovery systems (VRF-HR) to both help characterize actual yearly energy savings
potential, and to provide quality data for use in energy modeling verification. This project
will comprise instrumenting and measuring the in-situ performance of such a system with
the following objectives
To collect operational performance data on an installed VRF-HR system in the PG&E
service territory. This would include power and energy draw, ambient air conditions,
delivered zonal capacity and relevant system measures, sufficient to provide an
accurate picture of overall system operation.
To collect a data set that is appropriate to provide energy modeling developers with
a validation tool.
To model and compare VRF performance to a companion traditional HVAC system in
the same or a similar building.
Provide objective analysis and performance characterization of a field installed VRF-
HR system.
The data set will also be available for any further analysis or validation of new VRF
models.
TECHNOLOGY/PRODUCT EVALUATION
SITE SELECTION PG&E provided mechanical and electrical drawings for four PG&E buildings which were
retrofitted with VRF systems. EPRI was encouraged to select a PG&E owned site to keep
administrative tasks to a minimum. The four sites (referred to as Site 1, 2, 3 or 4) under
consideration were –
Site 1, PG&E Auburn Office Building, 1050 High Street, Auburn, California 95603
Site 2, PG&E Eureka Service Center, 2555 Myrtle Avenue, Eureka, California 95501
6
PG&E’s Emerging Technologies Program ET12PGE1381
Site 3, PG&E Martin Service Center, 731 Schwerin Street, Daly City, California,
94014
Site 4, PG&E Redding Ops, 3600 Meadow View Drive, Redding , California 96002
The sites were evaluated based on the following criteria –
1. Installed system size – Each indoor unit connected to the VRF system has to be
monitored for supply and return air temperature and relative humidity. Considering
the instrumentation, complexity and associated costs of measuring these parameters
at each indoor unit systems with minimum indoor units was preferred.
TABLE 1 SUMMARY OF VRF SYSTEMS CONSIDERED FOR MONITORING
Site 1 Site 2 Site 3 Site 4
Total refrigerant circuits 1 1 2 4
Installed Capacity (Tons) 24 24 20,24 18,18,6,8(OA)
Brand Mitsubishi Mitsubishi Mitsubishi Daikin
Heat Recovery / Heat Pump HR HR HR, HR HR,HR, HP,HP
Electrical 208 / 3 / 60 208/3/60 460 / 3 / 60 460 / 3 / 60
Number of Indoor Units 13 21 11, 10 17,15,2,2
2. Site 2, Site 3 and Site 4 have in excess of 20 indoor units for the entire site. Site 3
and Site 4 had multiple separate VRF systems installed (separate refrigerant circuits)
out of which one could be chosen. In order to monitor the entire site, such an
approach of measuring only one refrigerant circuit was not pursued. From an
installed system size perspective Site 1 (Auburn Office Building) seemed to be a
good fit.
3. Climate Zone – The climate in which the system operates is an important
consideration. Table 2 shows the California climate zones (CZ) for the sites
considered.
TABLE 2 CALIFORNIA CLIMATE ZONE (CZ) FOR SITES CONSIDERED
VRF Site Site 1 Site 2 Site 3 Site 4
Climate Zone 11 1 3 11
California CZ 11 (Red Bluff, Auburn) is characterized by distinct cooling and heating days.
Heating requirements dominate the months from November through March whereas June
through September is dominated by cooling requirements. April, May and October can be
considered as shoulder months. A heat pump system installed in this location will be loaded
in both the heating months and the cooling months.
California CZ 1 (Eureka, Klamath) is the coolest climate in California with mostly heating
only requirements. The summers are warm enough to call for cooling on a few days.
California CZ 3 (Oakland, San Francisco) has predominantly heating requirements with a
few days of cooling required. The overall climate is mild which keeps the energy
consumption low.
7
PG&E’s Emerging Technologies Program ET12PGE1381
CZ 11 was considered most demanding of the three CZ’s under consideration. Site 1 which
passed the system size muster is also in the CZ 11.
Based on the two criteria, Site 1 (PG&E Auburn Office Building) was selected. A few other
things were confirmed before a final decision was made on this particular site:
1. Baseline system – A baseline system will not be monitored for this site (the new VRF
systems were already installed when this project started). Instead, billing data prior
to the VRF system being installed will be used. The building did not have any other
efficiency improvement measures. The only change made was replacing the chiller
and boiler combo with a VRF system.
2. Site details – A site visit involving EPRI engineer, PG&E engineers and local HVAC
contractor was completed on March 6th 2013. Purpose of the site visit was to
understand the ‘as built’ system and the site specifics not shown in drawings. Items
investigated were:
a. Ceiling type for wiring purposes
b. Access to indoor and outdoor units and electrical panels
c. Available space or potential locations for mounting monitoring boxes
d. Briefing HVAC contractor on scope of the project
e. Cellular signal strength for data connection to remote EPRI server
f. Generating a picture library which will help in developing monitoring plan
Based on the information gathered during the site visit, site 1, PG&E Auburn Office Building,
was determined to be a good fit for this project.
FIGURE 1 PG&E CUSTOMER SERVICE OFFICE- AUBURN, CALIFORNIA
SITE DETAILS Figure 1 shows the elevation of the PG&E Customer Service Center in Auburn, California.
The selected site is a 4 floor (a basement and three above ground floors) office building with
approximately 8466 square feet of conditioned space. This building has a front (ground
level) customer service center with high ceilings and the remainder of the building space is
8
PG&E’s Emerging Technologies Program ET12PGE1381
designated for cubicles, offices, conference room, kitchen, storage and bathrooms. Figure 2
shows the office building from a bird’s eye view.
FIGURE 2 BIRDS-EYE VIEW OF PG&E AUBURN OFFICE BUILDING (FROM MAPS.GOOGLE.COM)
FIGURE 3 BASEMENT PLAN AND INDOOR UNITS
Figure 3 shows the floor plan for the basement of the building. The basement floor space is
split into storage area and office area, a small data center seen in the right side of the plan
and an unoccupied area to the left side. Two indoor units serve the entire basement, IHP-1
and IHP- 2 (Table 4 ). The hashed area in the floor plan indicated tiled ceilings. The data
center side is the front side of the building facing the street. The orientation is the same for
all the plan views.
9
PG&E’s Emerging Technologies Program ET12PGE1381
FIGURE 4 1ST
FLOOR PLAN AND INDOOR UNITS
Figure 4 shows the first floor plan for the building. The first floor has a front customer
service area (right side area) and behind it is open cubicle space as well as partitioned office
and bathrooms. The first floor is served by indoor units IHP-3, IHP-4A and IHP-4B (Table 4).
FIGURE 5 2ND
FLOOR PLAN AND INDOOR UNIT LOCATIONS
Figure 5 shows the floor plan for the second floor. Second floor has reduced floor space due
to high ceilings from the first floor. The second floor has two offices, an open cubicle area
and a bathroom. The entire second floor is served by either ceiling cassettes or wall mount
units. This floor has no ducted units. IHP-5A, IHP-5B, IHP-6, IHP-7A and IHP-7B serve this
space.
10
PG&E’s Emerging Technologies Program ET12PGE1381
FIGURE 6 3RD
FLOOR PLAN AND INDOOR UNIT LOCATIONS
Figure 6 shows the plan for the third floor of the building. The third floor has three offices, a
large open cubicle space and a bathroom. This space is served by three ducted indoor units
– IHP-8A, IHP-8B and IHP-8C. The original plans included only two indoor units but
complaints from occupants from the office spaces in corner east office and the center office
required addition of the third indoor unit IHP-8C.
EMERGING TECHNOLOGY/PRODUCT The VRF system installed at this location is a 24 ton Mitsubishi City Multi VRF system with
heat recovery capabilities (simultaneous heating and cooling operation is possible). The
system has a total of 13 indoor units connected to it. Of the 13 indoor units, 6 are ducted
units, 2 wall mount units and 5 ceiling cassettes. The system also includes a ventilation
system bringing in fresh air from the outside and feeding on the return air side of one
indoor unit on each floor. The specification sheets for each component in the HVAC system
is attached in the Appendix A. An equipment summary is included in Table 3 (outdoor units)
and Table 4 (indoor units).
TABLE 3 OUTDOOR UNITS
Outdoor Unit Model Number Cooling Capacity (MBH)
Heating Capacity (MBH)
Input Power (kW)
Refrigerant
OHP-1
PURY-
P144TJMU-A 144 160 27.19 R410A
OHP-2
PURY-
P144TJMU-A 144 160 27.19 R410A
11
PG&E’s Emerging Technologies Program ET12PGE1381
TABLE 4 INDOOR UNITS
Indoor Unit
Floor Air Flow (cfm)
Cooling Cap (MBH)
Heating Cap (kW)
Model Number Type
IHP-1 Basement 385 18 5.86 PVFY-P18E00A Vertical AHU
IHP-2 Basement 989 30 - PKFY-P30NFMU-E Wall Mount
IHP-3 1st 1,376 15 5 PEFY-P36NMAU-E Ducted
IHP-4A 1st 635 24 7.9 PEFY-P24NMAU-E Ducted
IHP-4B 1st 635 24 7.9 PEFY-P24NMAU-E Ducted
IHP-5A 2nd
350 6 2 PLFY-P08NCMU-E Cassette
IHP-5B 2nd
350 6 2 PLFY-P08NCMU-E Cassette
IHP-6 2nd
208 6 2 PKFY-P06NAMU-E Wall Mount
IHP-7A 2nd
390 12 2.6 PLFY-P15NCMU-E Cassette
IHP-7B 2nd
390 12 2.6 PLFY-P15NCMU-E Cassette
IHP-8A 3rd
1,342 48 16 PEFY-P48NMAU-E Ducted
IHP-8B 3rd
1,342 48 16 PEFY-P48NMAU-E Ducted
IHP-8C 3rd
1,376 15 5 PEFY-P36NMAU-E Ducted
The branch controller is a Mitsubishi model CMB-P1013NU-GA. The central controller is a
GB-50A which is the controller that implements the system control scheme.
SYSTEM CONTROL SCHEME The system is on a central control which has defined modes of operations for indoor units,
setback and occupied / unoccupied modes. The building is considered occupied in between
6:00 am and 6:00 pm five days of the week. Saturday and Sunday’s are considered
unoccupied. The system is also in unoccupied mode during holidays. The fans are always ON
when the building is in occupied mode.
FAN MODE
In fan mode, the units operate with providing any heating or cooling. The control scheme is
such that whenever the building is occupied, all zones run in fan mode if they are not
providing heating or cooling. This means that the units never actually stop moving air when
the building is occupied. This is done to make sure the fresh air (outdoor air) requirements
are met. The fresh air fan is in the third floor attic space with ductwork from the fan going
to one indoor unit on each floor. The ductwork is from fresh air fan is connected to the
return air side of the indoor units. The air is considered untreated since there is no separate
HVAC system handling the outside air. The fans are set in a fixed speed mode to provide
required airflow rate through each zone. The modulating (multi-speed) capability of the
indoor units is not utilized.
12
PG&E’s Emerging Technologies Program ET12PGE1381
COOLING MODE
In cooling mode the supply air has lower temperature and higher relative humidity than the
return air. The set point in cooling mode is 72°F and can be adjusted ±2°F by the
occupants.
HEATING MODE
In heating mode the supply air has higher temperature and lower relative humidity than the
return air. The set point in heating mode is also 72°F and can be adjusted ±2°F by the
occupants.
The controllers are programmed with a dead band of 1.8°F between heating and cooling
mode. The indoor units cannot be changed from one mode to another by the occupants.
That control rests with the system which determines the operating mode based on the set
point and the dead band. Within the dead band the system operates in fan mode.
TECHNICAL APPROACH/TEST METHODOLOGY
SYSTEM MONITORING The system is monitored for two characteristics – electrical and thermal from the time of
install (approximately end May 2013) for a period of 1 year. Data from numerous channels
monitored is recorded every minute (1 minute resolution data).
The electrical characteristics include power draw (kW), energy consumption (kWh), voltage
(V), current (I) and power factor (PF) at the outdoor units and indoor units. The indoor units
on each floor of the building are connected to a single breaker. The electrical characteristics
at this breaker would be monitored (four in all) in order to keep the instrumentation effort
within reason.
The thermal characteristics will include temperature (T) and relative humidity (RH)
measurements at various points in the building. The T and RH are made at supply air and
return air of each of the 13 indoor units. The ambient (outside) T and RH will also be
measured close to the outdoor unit with precautions taken to keep the sensor away from
the exhaust air stream of the outdoor units. Based on the T and RH measurement and the
air flow measurements from the test and balance report (already provided) capacity
measurements for each indoor unit will be made. For the non-ducted units, the air flow will
be assumed to be the rated air flow from the manufacturer.
EQUIPMENT USED Power meter – Elkor WattsOn – Revenue Grade
Current Transformers (CT) – Continental Controls (100, 20 and 5 amps) – Revenue Grade
Temperature and Relative Humidity - Dwyer (2 different models)
Communications – Obvius products
13
PG&E’s Emerging Technologies Program ET12PGE1381
- AcquiSuite – data acquisition server
- FlexIO – universal input / output module
- ModHopper – wireless Modbus transceiver
- Cell Modem – Airlink 3G
Specifications of all the monitoring equipment used are provided in the Appendices. The
accuracy of the sensors used is shown in Table 5.
TABLE 5 ACCURACY OF SENSORS USED
Instrument Accuracy
Dwyer RHP-2D11 RTD Temperature ±0.3°C @ 25°C
Dwyer RHP-2D11/2R11 RH ±2% 10-90% RH @ 25°C
Dwyer RHT-R016 Temperature ±2% @ 10-90%
Dwyer RHT-R016 RH ±2% @ 10-90%
Elkor WattsOn <0.2% @ 25°C
Accu-CT ±0.75%
Miscellaneous hardware includes NEMA 4X boxes, power supplies, fuses and power strips. A
schematic of data acquisition setup is shown in Figure 7. The AcquiSuite is the main on-site
data acquisition server and the entire site has only one AcquiSuite. The AcquiSuite collects
data from all the sensors (minute resolution) and stores it on its onboard memory. Data
from the AcquiSuite memory is uploaded to EPRI server every eight hours using a 3G cell
connection. Numerous fail safe software procedures are programmed into the AcquiSuite to
avoid any data loss.
The ModHopper is a wireless transceiver that can communicate with the AcquiSuite and with
other ModHoppers. The data is gathered from all the sensors attached to a FlexIO and
handed over to the ModHopper to transmit data wirelessly to the AcquiSuite. Numerous
ModHoppers, FlexIO’s and sensors can be connected to the system. For sake of simplicity
only one such ModHopper is shown. The site will have at least five ModHoppers (one for
each floor and one at the outdoor unit) that will talk to the AcquiSuite and amongst each
other to transmit the data.
14
PG&E’s Emerging Technologies Program ET12PGE1381
FIGURE 7 SCHEMATIC OF THE DATA ACQUISITION
EVALUATIONS/ANALYSIS The monitored data, collected for 1 year, from June 2013 to May 2014, is analyzed in this
section. The charts show the data from January to December for ease of reading. It must be
noted that January through May data is actually from year 2014 whereas June through
December data is from year 2013.
WEATHER The site lies in California Climate Zone 11 (CZ11). CZ11 is in northern California region
south of mountainous Shasta Region, east of Coastal Range and west of Sierra Cascades
according to Pacific Energy Center’s Guide to ‘California Climate Zones and Bioclimatic
Design’
http://www.pge.com/includes/docs/pdfs/about/edusafety/training/pec/toolbox/arch/climate
/california_climate_zones_01-16.pdf accessed 07/19/2014)
Auburn, per the design guide, is expected to have 3095 Heating Degree Days (HDD) and
1292 Cooling Degree Days (CDD). The HDD and CDD are determined by summing up the
average temperature per day below or above 65°F (base temperature). Figure 8 shows the
HDD and CDD’s calculated based on the monitored outdoor temperature at the site. The
numbers based on the actual site measurements show that the HDD’s were 2447.5 and
CDD’s were 1971.7.
Figure 9 shows the average, minimum and maximum outdoor temperature for each month
and also highlights the comfort zone between 68°F and 80°F. Figure 10 shows the average
outdoor relative humidity measured at 4 am and 4pm for each month.
Figure 8, Figure 9 and Figure 10 are included to compare the monitored data with trends
from the design guide. The monitored data shows slight variation from the data presented
in the guide. The variations can be attributed to the limited data set that is available for site
15
PG&E’s Emerging Technologies Program ET12PGE1381
- single point measurement made only for one year. The design guide data is compiled
based on significantly large data set and is representative for the entire area than just one
point measurement made at the site.
FIGURE 8 COOLING DEGREE DAY (CDD) AND HEATING DEGREE DAY (HDD) (BASE 65°F)
FIGURE 9 MEASURED TEMPERATURE (68-80°F COMFORT ZONE)
16
PG&E’s Emerging Technologies Program ET12PGE1381
FIGURE 10 MEASURED RELATIVE HUMIDITY (20-80% COMFORT ZONE)
Figure 11 shows entire outdoor temperature and relative humidity data set split out in
temperature and relative humidity bins. The numbers in the square indicate number of
hours the outdoor conditions were in a particular bin. For example, the outdoor conditions
were in the range of 72.5°F and 77.5°F and relative humidity of 32.5% and 37.5% for
115.3 hours. This chart is a graphical representation of the outdoor conditions experienced
by the VRF system. The comfort zone designated in the design guide is also superimposed
on the chart – the total number of hours in the comfort zone is 1872.5. Figure 12 shows the
same chart but the data is filtered for actual office hours (system occupied mode) which are
defined as Monday through Friday 6:00am to 6:00pm. The hours in comfort zone are
reduced to 823.4.
It must be noted that although these hours are in comfort zone, it doesn’t mean the HVAC
system is not operating. There are internal building loads that will necessitate HVAC system
operating.
17
PG&E’s Emerging Technologies Program ET12PGE1381
FIGURE 11 OUTDOOR CONDITIONS SPLIT IN TEMPERATURE AND RELATIVE HUMIDITY BINS
FIGURE 12 OUTDOOR CONDITIONS SPLIT IN TEMPERATURE AND RELATIVE HUMIDITY BINS (VRF SYSTEM IN OCCUPIED
MODE)
18
PG&E’s Emerging Technologies Program ET12PGE1381
ELECTRICAL CHARACTERISTICS As a potential energy efficient technology, the system electrical characteristics (energy and
demand) are of great interest. This section presents the analysis of monitored and recorded
electrical data for the site. Billing data provided by PG&E is also analyzed.
PG&E’s ‘Electrical Schedule A-10 Medium General Demand-Metered Service’
(http://www.pge.com/tariffs/tm2/pdf/ELEC_SCHEDS_A-10.pdf accessed 07/16/2014) is
used as a reference for defining various times of the year like summer and winter.
Load shape of the VRF system is shown in Figure 13. The load shape in this document is
defined as the average power draw (kW) during the hour for the entire system. By definition
the load shape does not include the maximum demand imposed by the system but just the
hourly average. The load shape is further split out in terms of a summer shape and winter
shape. Summer is defined time between as May 1st and October 31st. Summer load shapes
shows high demand during peak periods for utilities. Winter is defined as time between
November 1st and April 30th. The winter load shape shows a high demand imposed outside
of the office hours (early mornings). This indicates that the temperature in the zones is
dropping below the setback temperature on the controllers which in turn drives the VRF
system in heating mode. Although demand response is not a topic of research for this
project, the high demand during peak hours during summer period makes this type of an
installation a potential candidate for DR programs.
Further analysis on the indoor temperatures is provided in the Thermal Characteristics sub-
section of this chapter.
FIGURE 13 LOAD SHAPE OF VRF SYSTEM (ALL YEAR AVERAGE; SUMMER AND WINTER)
Billing data for the building was made available by PG&E for the purpose of this analysis.
The tabulated data is presented in Table 6. The meter reading date does not exactly align
19
PG&E’s Emerging Technologies Program ET12PGE1381
with month end dates. For example when month of January 2014 is considered, the actual
readings are from 12/25/2013 to 1/26/2014. The time period between the two dates is
considered as month of January since majority of the time is in month of January. The EPRI
data is also filtered to make sure the data presented corresponds to PG&E billing dates. The
PG&E billing data is for the entire building – it covers more than just the VRF system. It
includes lighting loads, a small data center, computers in the building and other plug loads.
The EPRI monitoring data captures all the energy used by the VRF system only. Figure 14
shows the energy data in a chart format. The summer months from May to October show
higher energy usage than the winter months. Figure 15 shows the demand data in chart
format.
Month Reading Date PG&E Meter EPRI Monitoring (VRF)
Energy (kWh) Demand (kW) Energy (kWh) Demand (kW)
Jan 1/26/2014 6,996 29 2,761 23.3
Feb 2/25/2014 6,859 29 2,742 25.1
Mar 3/26/2014 6,418 26 2,489 19.3
Apr 4/27/2014 6,567 27 2,666 22.3
May 5/27/2014 6,661 27 2,790 18.6
Jun 6/25/2013 7,353 29 3,319 20.9
Jul 7/25/2013 8,614 31 4,844 22.7
Aug 8/25/2013 7,766 28 4,236 18.7
Sep 9/24/2013 6,879 28 3,339 20.3
Oct 10/23/2013 5,896 24 2,220 14.1
Nov 11/22/2013 6,155 25 2,068 20.2
Dec 12/25/2013 7,434 36 3,740 20.2
TABLE 6 COMPARISON OF PG&E BILLING DATA AND EPRI VRF SYSTEM MONITORING DATA
20
PG&E’s Emerging Technologies Program ET12PGE1381
FIGURE 14 COMPARISON BETWEEN PG&E METER DATA AND EPRI HVAC MONITORING DATA
The difference between billing data and EPRI measurements indicate the energy usage by
other loads in the building. Based on the data the other loads average 3,865 kWh per
month. The average other loads during summer time (May through October) is 3,737 kWh
and during winter time (November through April) is 3,994 kWh. The difference in average
energy usage, although minor (~6.7%), may be due to use of portable heaters that are
used in certain offices. One such portable heater was seen during site visit and the occupant
of the office said she used it very often during heating season to keep her office warm.
The total energy usage of the building is 83,598 kWh for the year under consideration which
equates to 9.9 kWh/sq foot/year site energy use intensity (EUI). The total VRF energy use
for the entire year is 37,253 kWh which comes out to 4.4kWh/sq foot /year EUI. Figure 15
shows the billing demand created by the entire building during each billing cycle and the
corresponding VRF system maximum demand imposed during the same billing cycle. The
billing demand is defined as the maximum average kW for 15 minute block during the billing
cycle. The blocks are defined as 2:00 to 2:15, 2:15 to 2:30 and so on. From the billing data
provided it wasn’t clear at what date and time the maximum demand created by the
building. For the VRF system, since all the data is monitored, the exact 15 minute period for
the highest demand during each billing cycle can be deduced. From the data obtained from
PG&E it is not possible to determine if PG&E demand was recorded at the same time as VRF
systems maximum demand. Since the VRF system is the biggest building load, it is a safe
assumption that the times do correspond to the maximum billing demand as well.
21
PG&E’s Emerging Technologies Program ET12PGE1381
FIGURE 15 RECORDED BILLING DEMAND AND VRF SYSTEM HVAC DEMAND
TABLE 7 MAXIMUM DEMAND FROM VRF SYSTEM
Month Season Max VRF
Demand Date
Time Frame PG&E Meter
Demand (kW)
EPRI Monitoring (VRF) Demand
(kW) From To
Jan Winter 1/13/2014 3:45 am 4:00 am 29 23.3
Feb Winter 2/4/2014 4:00 am 4:15 am 29 25.1
Mar Winter 3/3/2014 4:30 am 4:45 am 26 19.3
Apr Winter 3/31/2014 2:45 am 3:00 am 27 22.3
May Summer 4/28/2014 3:30 am 3:45 am 27 18.6
Jun Summer 6/7/2013 5:00 pm 5:15 pm 29 20.9
Jul Summer 7/1/2013 3:15 pm 3:30 pm 31 22.7
Aug Summer 8/7/2013 6:15 am 6:30 am 28 18.7
Sep Summer 9/16/2013 6:00 am 6:15 am 28 20.3
Oct Summer 9/25/2013 4:00 pm 4:15 pm 24 14.1
Nov Winter 11/4/2013 3:45 am 4:00 am 25 20.2
Dec Winter 12/7/2013 3:45 am 4:00 am 36 20.2
22
PG&E’s Emerging Technologies Program ET12PGE1381
The trends from the demand data show that during the winter time, the VRF system
maximum demand is during the very early morning hours (2:00 am to 5:00 am) whereas in
summer hours the maximum demand is during the morning startup phase (6:00 am to 8:00
am) or during hot afternoon hours (12:00 pm – 6:00pm). The month of May 2014 falls
under the summer season but the maximum demand was measured during early morning
hours, a trend found in winter months. Further investigation revealed that the day of the
maximum demand 04/28/2014 had the lowest overnight temperatures (44°F) for that
billing period which forced the system to run in heating mode thus showing characteristics
like a winter month.
THERMAL CHARACTERISTICS The outdoor conditions in which a VRF system is operating has significant impact on the
power draw from the system. The full year data is filtered to include only weekdays and
working hours. The trend in power draw with respect to the outdoor temperature is as
expected. At the extremes of temperature range, the power draw is higher (either cooling
mode or heating mode) and in the milder ambient conditions the power draw is lower.
FIGURE 16 AVERAGE POWER DRAW VERSUS TEMPERATURE BINS
DETERMINING MODE OF OPERATION OF INDOOR UNIT
The mode of operation of each individual indoor unit is determined by the difference
between the return air temperature and supply air temperature of the same indoor unit.
There are three different modes of operation – auto fan, cooling and heating. The
temperature difference for determining the operating mode is set at 15°F. If the
temperature difference between return air and supply air is greater than 15°F then the unit
is assumed to be in cooling mode. If the temperature difference is less than -15°F then the
23
PG&E’s Emerging Technologies Program ET12PGE1381
unit is assumed to be in heating mode. For the temperatures in between the unit is in fan
mode.
OUTDOOR UNIT OPERATING MODE
The outdoor unit can be operating in heating only mode, cooling only mode or mixed mode
depending on the total load on system.
In heating only mode all the indoor units are operating in either heating mode or some in
heating and some in fan mode. None of the units are in cooling mode.
In cooling only operating mode the indoor units are operating in either cooling mode or
some in cooling and some in fan mode. None of the units are in heating mode.
In mixed mode a combination of indoor units operating in heating, cooling and fan mode is
observed. The mixed mode operation is also known as the heat recovery mode where
energy from one zone (a warm zone) is transferred to another (a cold zone) whenever
possible.
OPERATING HOURS The indoor unit operating hours for the entire building are shown in Figure 17. These are
cumulative operating hours that 13 units have run for each month. For example, in July
combined operating hours were in cooling mode were 2,127 which makes sense due to the
hot weather in that month.
24
PG&E’s Emerging Technologies Program ET12PGE1381
FIGURE 17 INDOOR UNIT OPERATING HOURS IN HEATING OR COOLING MODE (ALL 13 UNITS COMBINED)
The operating hours in each mode for various temperature bins is shown in Figure 18. The
figure shows that as the ambient temperature increases the cooling mode operation
increases (which makes sense due to the building getting hotter) and vice-versa. The mixed
mode operation is mostly during the 55°F to 70°F temperature range.
25
PG&E’s Emerging Technologies Program ET12PGE1381
FIGURE 18 OPERATING HOURS IN EACH MODE (FAN, COOLING, HEATING AND MIXED) FOR THE VRF SYSTEM
When considering operating modes and hours of the indoor units, one important
consideration is to make sure indoor units operating in large open spaces are not fighting
each other, i.e. for units serving the same common space, one is running in heating mode
while the other is running in cooling mode. Figure 19 shows indoor units 8A and 8B showing
such behavior. These units serve the open space on third floor and during certain hours
showed signs of operating in opposite modes. Figure 20 shows the number of hours the
indoor units 8A and 8B are operating in opposite mode during the same time. There are lot
of hours in January and February where the units are running in opposite modes. All other
indoor units were compared against each other as well but none of them showed such
behavior
26
PG&E’s Emerging Technologies Program ET12PGE1381
FIGURE 19 INDOOR UNIT 8A AND 8B OPERATING IN DIFFERENT MODES DURING THE SAME TIME
FIGURE 20 NUMBER OF HOUR’S INDOOR UNIT 8A AND 8B ARE OPERATING IN OPPOSITE MODE
The data center is also a unique zone where operating mode is of interest. The data center
has another smaller independent split system installed as a backup and there seems to be
evidence of influence from the split system on the operation of the VRF indoor unit. The
27
PG&E’s Emerging Technologies Program ET12PGE1381
data center indoor unit runs in heating mode for quite some time which is counter-intuitive
considering that data center is usually a cooling load.
To understand the operation of the indoor unit in the data center, return air temperature at
the indoor unit was reviewed. The minimum return air temperature for the indoor unit in the
data center is shown in Figure 22. The temperatures do not indicate very cold temperatures
where there is need for heating to be provided.
28
PG&E’s Emerging Technologies Program ET12PGE1381
FIGURE 21 OPERATING MODE AND HOURS FOR INDOOR UNIT IN DATA CENTER
FIGURE 22 MINIMUM TEMPERATURE RECORDED FOR EACH MONTH FOR RETURN AIR IN THE DATA CENTER
29
PG&E’s Emerging Technologies Program ET12PGE1381
CAPACITY MEASUREMENTS Capacity is measured for each indoor unit by using the air enthalpy method. The capacity of
each indoor unit is the product of mass flow rate of air (lb/hr) and the change in enthalpy
across the indoor unit (BTU/lb).
The airflow rate for each individual indoor is obtained from the test and balance (TAB) report provided by PG&E.
The TAB report provides airflow rates in CFM for each of the ducted units installed in the building. For ductless
units (wall mount or cassette) published airflow from the manufacturer at the medium fan speed setting are used.
The airflow is measured in CFM (cubic feet per minute) and then converted into mass flow rate of pounds per hour.
This mass flow rate is assumed to be constant throughout the data monitoring period.
Enthalpy measurements are derived from the dry bulb temperature and relative humidity (RH) measurement taken at
return and supply air of each indoor unit. The enthalpy is calculated based on perfect gas relationships for dry and
moist air elaborated in 2009 ASHRAE Handbook – Fundamentals, chapter 1 Psychrometrics.
h = enthalpy of moist air
t= dry bulb temperature
W=humidity ratio
Humidity ratio is not measured by the installed instrumentation but the relative humidity
(RH) is. Saturation pressure over liquid water (pws) at a given temperature (between 32F
and 392F) is given by –
Where C8 thru C13 are constants, T is absolute temperature.
C8=-1.044 039 7 E+04
C9=-1.129 465 0 E+01
C10=-2.702 235 5 E-02
C11=1.289 036 0 E-05
C12=-2.478 068 1 E-09
C13=6.545 967 3 E+00
Based on pws, pw the partial water vapor pressure of a moist air sample can be calculated
Humidity ratio W is calculated by
Where p is atmospheric pressure assumed to be 14.695 psia.
Field capacity measurements are difficult. The calculations made in this report give an
estimate of the capacity delivered. For accurate capacity measurement significant additional
instrumentation and resources would be required.
30
PG&E’s Emerging Technologies Program ET12PGE1381
Figure 23 shows the total capacity (heating and cooling) delivered by the VRF system
broken down by each floor. The data shows that the second floor has relatively less heating
or cooling needs. The area of second floor is the least due to the high ceiling for the first
floor. The third floor due the roof sees higher impact from ambient conditions. The first floor
which has a customer entrance and high ceilings in the customer service area is where most
of the capacity is delivered.
FIGURE 23 MONTHLY CAPACITY DELIVERED FOR EACH FLOOR
Energy efficiency ratio (EER) can be defined as the ratio of energy output (BTU of cooling or
heating) from the VRF system to the electrical input energy (kWh) during the same period.
The EER of the VRF system is strongly correlated to the ambient temperature conditions.
Figure 24 shows the EER and outdoor temperature correlation for the entire duration of the
test. The data is filtered to include only when the system is in occupied mode. This is done
to avoid skewing the data due to system being in standby mode where no heating or cooling
capacity is delivered. Such situations are encountered when the system is in unoccupied
mode (outside of working hours).
31
PG&E’s Emerging Technologies Program ET12PGE1381
FIGURE 24 AVERAGE EER VERSUS TEMPERATURE BINS
The EER trend is as expected with EER dropping at the extremes (low ambient or high
ambient conditions).
MODELING The objective of modeling exercise is to calibrate a VRF simulation in EnergyPlus and to
calculate the energy savings associated with a VRF system installation a the PG&E facility in
Auburn. As of June 2014, one full year of VRF sub-metered data was available. To calculate
energy savings, PECI created baseline and proposed whole building energy simulations. The
proposed model was constructed per the Auburn Office Building design with a VRF system.
This was also calibrated to the sub-metered VRF energy data. The baseline model included a
code compliant packaged single zone gas fired rooftop unit HVAC system. This memo
describes model development, calibration, and the resulting energy savings.
MODEL DEVELOPMENT The energy model is developed using AecoSim Energy Simulator (AES), which is a
comprehensive front end for EnergyPlus that allows the user to define all model input
parameters, run simulations, and analyze results. AES build 08.11.09.46 was used for this
project, which uses EnergyPlus version 7.2 as the simulation engine.
32
PG&E’s Emerging Technologies Program ET12PGE1381
INPUT ASSUMPTIONS
As built drawings dated November, 18th 2011 that document the HVAC replacement were
used as the basis for most of the model input assumptions including model geometry and
HVAC system assumptions. These plans however are not comprehensive because they were
only for the HVAC replacement. Supplemental information was provided by site staff and
EPRI staff who had previously been on location.
ENVELOPE Envelope assumptions are based on conversations with site staff, as built drawings and
images from google maps. Exterior walls are assumed to be brick veneer walls with batt
insulation in the wall cavity and gypsum board finish. A flat membrane roof is modeled with
wood decking and insulation. Windows are assumed to be clear and single pane. Based on
the age of construction, presence of single pane windows and conversation with PG&E staff,
the building was modeled with relatively a high infiltration rate.
INTERNAL GAINS Internal gains were input based on data reported from EPRI staff that had been onsite and
counted the number and types of lights, significant plug loads and occupants. ASHRAE
Fundamentals was used to determine reasonable assumptions for nominal power draw of
office equipment found onsite. Equipment power density and lighting power density were
broken out on a per floor basis.
A small data closet is situated in the basement of the site. The IT load of this data closet
was unknown. It was estimated at 1.5 kW. This value was based on the available VRF
cooling capacity of the site and from a photo of the data closet.
Domestic hot water was assumed to be provided by a natural gas tank water heater located
in the basement. The system is assumed to have a flow rate of 4 gallons per occupant per
day during working days.
HVAC - VRF
The HVAC system was modeled as defined on the as built drawings with two exceptions. The
drawings show that the building is served by Mitsubishi Lossnay Energy Recovery Ventilator.
However, PG&E staff revealed that this ERV was not actually installed and in its place is
actually a dedicated outside air system with no space conditioning or heat recovery
capability. The other exception is that IHP3 is shown to have 1,376 CFM of supply air and 15
MBH of cooling capacity. This comes out to 1,100 CFM/ton, which is very high. Additionally,
based on the initial model, this seemed to be an inadequate amount of cooling capacity.
Therefore an assumption was made that the plans were incorrect and this unit actually had
a cooling capacity of 45 MBH and a heating capacity of 45 MBG. This equates to 367
CFM/ton which is more aligned with how all other indoor units at this site are designed and
also agrees better with industry standard practice.
The Mitsubishi VRF Heat Recovery system was simulated using the VRF module in AES.
Outdoor unit capacity, indoor unit capacity and supply air flow rates were hardcoded based
on the as built plans. For ceiling and wall cassette type indoor units, fan power could be
taken directly from the unit specification sheet. For ducted indoor units, a range of possible
static pressure requirements was investigated and the fine-tuned using the sub-metered
33
PG&E’s Emerging Technologies Program ET12PGE1381
data. This exercise resulted in a static pressure assumption of six tenths of an inch of water
for ducted units. The default VRF performance curves in AES were used for this exercise
because they are based on a Mitsubishi unit of the same line as the one installed at the
Auburn site.
The HVAC was assumed to have typical office operation, with occupied mode defined as
Monday – Friday 6:00 am – 6:00 pm.
MODEL CALIBRATION The Auburn building was calibrated to sub-metered data provided by the monitoring
exercise of this project. When the model was calibrated, only 11 months of data was
available so the model was only calibrated to the available 11 months of data. The model
was calibrated on a monthly basis using HVAC energy as the calibration target.
WEATHER DATA
National Oceanic and Atmospheric Administration (NOAA) weather data was used from the
Auburn Municipal airport site. Weather data used was from June 1st 2013 to May 31st 2014.
This weather data contains drybulb temperature, relative humidity, wind speed, wind
direction and barometric pressure. Other parameters not specified in by the NOAA Auburn
weather station but still needed for the simulation were taken from a Sacramento TMY3
weather file.
METERED DATA
Metered data of the HVAC system was provided by EPRI. This building is sub-metered per
floor for indoor units and per unit for outdoor units. The provided data was reported at one
minute intervals; however it was aggregated for per month for the purposes of the model
calibration.
CALIBRATION PROCESS
While the target calibration was for HVAC energy the model was calibrated on both fan
energy and outdoor unit energy. This approach provides a more robust model calibration
and allows for easier analysis of modeled results. Critical parameters impacting the
calibration of the indoor units were the fan static pressure, fan efficiency and motor
efficiency. Critical parameters impacting the calibration of the outdoor units were the
infiltration, and temperature setpoints.
The goal of the calibration was to achieve modeled energy use within 15% of the metered
data. As shown in Figure 25, this was achieved for all months except March which was at
23.5% of the metered energy use.
34
PG&E’s Emerging Technologies Program ET12PGE1381
FIGURE 25 CALIBRATED VRF SYSTEMS MODELED ENERGY USE VS METERED ENERGY USE
The red line shows the average temperature for the month as a departure from the
balance temperature f or the space.
PACKAGED SINGLE ZONE MODEL A packaged single zone (PSZ) HVAC system with gas heat was modeled as the baseline
scenario for this building. This model was created to comply with 2008 Title 24. Zoning
was maintained the same as in the building design and in the VRF model. Set points and
schedules were also kept constant between the VRF model and the PSZ model.
The PSZ model consists of 12 SEER 13 units that do not have economizers. The capacity
and airflow rates of these units were auto sized by AES.
ENERGY SAVINGS Energy use for the PSZ model was compared to the energy use for the VRF model. The VRF
model used significantly less energy. The resultant HVAC savings are 126 kWh/ton and 52
therms/ton, which is equal to 51% of the PSZ HVAC energy use. To help demonstrate the
source of these savings, Figure 26 outlines the energy use intensity for the VRF and PSZ
models.
35
PG&E’s Emerging Technologies Program ET12PGE1381
FIGURE 26 ENERGY USE INTENSITY FOR THE VRF AND PSZ MODELS HIGHLIGHTING THE SOURCE OF ENERGY SAVINGS
As Figure 26 shows, the majority of the savings for this project come from heating. The
packaged single zone model uses an 80% efficient forced air finance, whereas the VRF
system is able to take advantage of its heat pump heating and thus achieve significant
savings. Additionally, there are considerable fan savings. These fan savings arise because
with a VRF system the static pressure requirement is significantly less because of the
reduced ductwork. Also the indoor unit fans are able to cycle with heating and cooling load
because ventilation air is decoupled from the VRF supply fan operation.
DISCUSSIONS AND CONCLUSIONS This report provides analysis of a field installed VRF-HR system in Auburn, California. The
data gathered is grouped into two main types – electrical and thermal. The data set
collected can be used for further model validation purposes.
The monitoring and analysis of the VRF-HR system shows that the operating characteristics
were in line with the expectations based on understanding of HVAC systems. Summary of
the findings and discussion is presented in a numbered list -
1. The monitored ambient conditions shows slight variation from the published weather
data for Auburn, California. The variations can be attributed to the limited data set
that is available for site - single point ambient measurements made only for one
year.
2. Summer load shape shows high demand during peak periods for utilities (12:00 pm
to 6:00 pm). The winter load shape shows a high demand imposed outside of the
office hours (early mornings). The trends from the demand data show that during
the winter time, the VRF system maximum demand is during the very early morning
hours (2:00 am to 5:00 am) whereas in summer hours the maximum demand is
during the morning startup phase or during hot afternoon hours.
36
PG&E’s Emerging Technologies Program ET12PGE1381
3. The high demand during summer peak hours makes the VRF installation a potential
candidate for Demand Response program. The significant controls as well as
communications capabilities further necessitate investigation into the DR
possibilities.
4. The high demand during the early morning startup period could be eliminated by
staging the units during the initial ramp-up. This can be done by setting different
occupied / unoccupied times for different units.
5. The difference between PG&E billing data and EPRI measurements indicate that the
average energy usage by other loads in the building is 3,865 kWh per month.
6. The outdoor conditions in which a VRF system is operating has significant impact on
the power draw from the system. As expected, at extremes of temperature range,
the power draw is higher (either cooling mode or heating mode) and in the milder
ambient conditions the power draw is lower.
7. The second floor has the least heating or cooling needs. The third floor due the roof
sees higher impact from ambient conditions. The first floor which has a customer
entrance and high ceilings in the customer service area is where most of the capacity
is delivered.
8. Indoor units 8A and 8B which serve third floor open space operated in opposite mode
(one in cooling and other in heating) at the same time for 39 hours during the period
of monitoring. Since the units serve the same space, it appeared that the units were
fighting each other. This can be remedied by grouping units together and forcing
them to operate in a single mode. That way the systems don’t fight each other. This
can also be done for indoor units 4A and 4B as well as 7A and 7B.
9. Indoor unit 2 serves a small data center which also has a backup split system. The
cooling from backup system was potentially forcing the indoor unit 2 to operate in
heating mode. Data center is usually a cooling load and heating mode operation of
the indoor unit 2 operating in heating mode isn’t expected. Through the control
scheme this indoor unit can be locked in cooling mode or the setback temperature
can be reduced significantly so that the unit doesn’t kick into heating mode.
10. Modeling showed that the EnergyPlus model can predict the energy usage of the
modeled building within ±15% of actual energy use for the VRF system. Comparison
between a modeled baseline and a VRF system showed significant energy savings in
heating mode and fan energy savings.
The VRF system shows overall energy savings based on modeling results, but more energy
savings can be realized by following recommendations deduced from data analysis.
37
PG&E’s Emerging Technologies Program ET12PGE1381
RECOMMENDATIONS The biggest opportunity in terms of energy savings in a VRF technology is the ability to
modulate components as well as change local set points while maintaining occupant comfort
throughout the building. A slightly liberal policy for the local controllers might result in
added energy savings (this has potential disadvantages as well – thermostat fights are a
possibility). This can be reduced by providing occupants training on how to use and interact
with the system.
Another energy savings opportunity based on findings of this study is the opportunity for
continuous commissioning. The indoor units fighting each other or the data center indoor
unit running in heating mode are opportunities to save energy which are wasted if the
system operation is not reviewed. The existing sensors and controls on the system are
capable of determining this issues. If there is an incentive for reviewing information and
data gathered on the system, further energy savings could be realized. Commissioning at
time of install can also be monitored carefully to make sure building characteristics are
taken into consideration. This building for example is an historic building with substantial air
leakage and minimum insulation. The winter operation of this system is heavily dependent
on the type of building and less so on the actual control scheme of the building.
Outdoor air fan presents another opportunity for energy savings. The control scheme shared
for the purpose of this project indicates that the fan runs when the system has any indoor
unit operating. This, in winter months can mean that the outdoor air brings in outside cold
air when there is no need for fresh air (unoccupied mode). This could not be verified
through the data collected.
There is an opportunity to investigate demand response potential of this technology
especially since this is a coincident load. The controls and communications capability are
already included in the product and unlocking the potential could be the next step to further
benefit from this technology.
38
PG&E’s Emerging Technologies Program ET12PGE1381
APPENDICES
MONITORING EQUIPMENT
OBVIUS ACQUISUITE A8810 – MAIN DATA ACQUISITION SERVER
39
PG&E’s Emerging Technologies Program ET12PGE1381
OBVIUS MODHOPPER R9120-5
40
PG&E’s Emerging Technologies Program ET12PGE1381
OBVIUS FLEX IO – A8332-8F2D
41
PG&E’s Emerging Technologies Program ET12PGE1381
DWYER SERIES RHP – HUMIDITY/TEMPERATURE TRANSMITTER
42
PG&E’s Emerging Technologies Program ET12PGE1381
DWYER SERIES RH-R – HUMIDITY/TEMPERATURE TRANSMITTER
43
PG&E’s Emerging Technologies Program ET12PGE1381
ACCU-CT – SPLIT-CORE CURRENT TRANSFORMER
44
PG&E’s Emerging Technologies Program ET12PGE1381
ELKOR WATTSON
45
PG&E’s Emerging Technologies Program ET12PGE1381
INSTALLED MITSUBISHI EQUIPMENT
PURY-P288TSJMU-A
46
PG&E’s Emerging Technologies Program ET12PGE1381
PVFY-P18E00A
47
PG&E’s Emerging Technologies Program ET12PGE1381
PKFY-P06NAMU-E
48
PG&E’s Emerging Technologies Program ET12PGE1381
PKFY-P30NFMU-E
49
PG&E’s Emerging Technologies Program ET12PGE1381
PEFY-P36NMAU-E
50
PG&E’s Emerging Technologies Program ET12PGE1381
PEFY-P24NMAU-E
51
PG&E’s Emerging Technologies Program ET12PGE1381
PEFY-P48NMAU-E
52
PG&E’s Emerging Technologies Program ET12PGE1381
PLFY-P08NCMU-E
53
PG&E’s Emerging Technologies Program ET12PGE1381
PLFY-P15NCMU-E
54
PG&E’s Emerging Technologies Program ET12PGE1381
CMB-P1013NU-GA
55
PG&E’s Emerging Technologies Program ET12PGE1381
FILTERS APPLIED TO MONITORED DATA
Figure 8 Cooling Degree Day (CDD) and Heating Degree Day (HDD) (Base
65°F)
Description: Sum of HDD and sum of CDD for each Local Time Month. For pane Sum of HDD:
Color shows details about Local Time Month. For pane Sum of CDD: Color shows sum of CDD.
Local Time Month has 12 members on this sheet
Members: August; July; June; May; September; ...
Sum of HDD ranges from 5.0 to 551.3 on this sheet.
The formula is IF (65-([Outdoor Air T]))<0 THEN 0 ELSE ((65-[Outdoor Air T])/(24*60)) END
Sum of CDD ranges from -520.8 to -2.2 on this sheet.
The formula is IF (65-([Outdoor Air T]))>0 THEN 0 ELSE ((65-[Outdoor Air T])/(24*60)) END
Figure 11 Outdoor Conditions Split in Temperature and Relative Humidity
Bins
Description: Sum of Number of Records Hours (color) broken down by Outdoor T vs. Outdoor
RH. The data is filtered on LocalTime (MY), which excludes May 2013 and June 2014. The
view is filtered on Exclusions (Outdoor RH,Outdoor T), which keeps 203 members.
Outdoor RH has 19 members on this sheet
Members: 15; 20; 25; 30; 35; ...
Outdoor T has 18 members on this sheet
Members: 70; 75; 80; 85; 90; ...
LocalTime (MY) has 12 members on this sheet
Members: August 2013; July 2013; June 2013; October 2013; September 2013; ...
Figure 12 Outdoor Conditions Split in Temperature and Relative Humidity
Bins (VRF System in Occupied Mode)
Description: Sum of Number of Records Hours (color) broken down by Outdoor T vs. Outdoor
RH. The data is filtered on LocalTime (MY), LocalTime Weekday and LocalTime Hour. The
LocalTime (MY) filter excludes May 2013 and June 2014. The LocalTime Weekday filter keeps
Monday, Tuesday, Wednesday, Thursday and Friday. The LocalTime Hour filter keeps 13 of 24
members. The view is filtered on Exclusions (Outdoor RH,Outdoor T), which keeps 203
members.
Filters: Exclusions (Outdoor RH,Outdoor T), Month, Year of LocalTime, Weekday of
LocalTime, Hour of LocalTime
Outdoor RH has 19 members on this sheet
Members: 25; 30; 35; 40; 45; ...
56
PG&E’s Emerging Technologies Program ET12PGE1381
Outdoor T has 18 members on this sheet
Members: 65; 70; 75; 80; 85; ...
LocalTime Hour has 13 members on this sheet
Members: 10; 6; 7; 8; 9; ...
LocalTime (MY) has 12 members on this sheet
Members: August 2013; July 2013; June 2013; October 2013; September 2013; ...
LocalTime Weekday has 5 members on this sheet
Members: Friday; Monday; Thursday; Tuesday; Wednesday
Figure 13 Load Shape of VRF System (All Year Average; Summer and
Winter)
All Year Average
The trend of average of Total Power for LocalTime Hour. The data is filtered on LocalTime
Weekday, which keeps Monday, Tuesday, Wednesday, Thursday and Friday.
Average of Total Power ranges from 0.58 to 11.13 on this sheet.
The formula is [Total Indoor Power]+[Total Outdoor Power]
Summer
The trend of average of Total Power for LocalTime Hour. The data is filtered on LocalTime
Weekday and LocalTime Month. The LocalTime Weekday filter keeps Monday, Tuesday,
Wednesday, Thursday and Friday. The LocalTime Month filter keeps 6 of 12 members.
LocalTime Month has 6 members on this sheet
Members: August; July; June; May; September; ...
LocalTime Weekday has 5 members on this sheet
Members: Friday; Monday; Thursday; Tuesday; Wednesday
Average of Total Power ranges from 0.81 to 11.52 on this sheet.
The formula is [Total Indoor Power]+[Total Outdoor Power]
Winter
The trend of average of Total Power for LocalTime Hour. The data is filtered on LocalTime
Weekday and LocalTime Month. The LocalTime Weekday filter keeps Monday, Tuesday,
Wednesday, Thursday and Friday. The LocalTime Month filter keeps 6 of 12 members.
LocalTime Month has 6 members on this sheet
Members: April; February; January; March; November; ...
LocalTime Weekday has 5 members on this sheet
Members: Friday; Monday; Thursday; Tuesday; Wednesday
Average of Total Power ranges from 0.32 to 11.18 on this sheet.
The formula is [Total Indoor Power]+[Total Outdoor Power]
57
PG&E’s Emerging Technologies Program ET12PGE1381
Figure 14 Comparison between PG&E Meter Data and EPRI HVAC
Monitoring Data
Description: EPRI HVAC (kWh) and PG&E Meter (kWh) for each MONTH. Color shows
details about EPRI HVAC (kWh) and PG&E Meter (kWh).
Measure Names has 2 members on this sheet
Members: EPRI HVAC (kWh); PG&E Meter (kWh)
MONTH has 12 members on this sheet
Members: Apr; Dec; Jan; May; Nov; ...
Figure 15 Recorded Billing Demand and VRF System HVAC Demand
Description: HVAC Demand and Billing Demand for each MONTH. Color shows details about
HVAC Demand and Billing Demand.
Measure Names has 2 members on this sheet
Members: Billing Demand; HVAC Demand
Measure Names is sorted manually.
MONTH has 12 members on this sheet
Members: Apr; Dec; Jan; May; Nov; ...
Figure 16 Average Power Draw versus Temperature Bins
Description: Average of Total Power for each Outdoor T. The data is filtered on LocalTime
Hour and LocalTime Weekday. The LocalTime Hour filter keeps 15 of 24 members. The
LocalTime Weekday filter keeps Monday, Tuesday, Wednesday, Thursday and Friday. The
view is filtered on Outdoor T, which excludes Null.
Outdoor T has 18 members on this sheet
Members: 50; 55; 60; 65; 70; ...
LocalTime Hour has 15 members on this sheet
Members: 6; 7; 8; 9; ...
LocalTime Weekday has 5 members on this sheet
Members: Friday; Monday; Thursday; Tuesday; Wednesday Average of Total Power ranges from 4.50 to 26.69 on this sheet.
The formula is [Total Indoor Power]+[Total Outdoor Power]
Figure 17 Indoor Unit Operating Hours in Heating or Cooling Mode (All 13
Units Combined)
Description: Sum of HOURS IN HEATING MODE and sum of HOURS IN COOLING MODE
for each LocalTime Month. For pane Sum of HOURS IN HEATING MODE: Color shows
details about LocalTime Month. For pane Sum of HOURS IN COOLING MODE: Color shows
sum of HOURS IN COOLING MODE. The data is filtered on EXACT ONE YEAR, which
keeps 12 months.
58
PG&E’s Emerging Technologies Program ET12PGE1381
LocalTime Month has 12 members on this sheet
Members: August; July; June; October; September; ...
Sum of HOURS IN HEATING MODE ranges from 1 to 1,491 on this sheet.
The formula is
([HM1]+[HM2]+[HM3]+[HM4A]+[HM4B]+[HM5A]+[HM5B]+[HM6]+[HM7A]+[HM7B]+[H
M8A]+[HM8B]+[HM8C])
Sum of HOURS IN COOLING MODE ranges from -2,127 to -17 on this sheet.
The formula is
([CM1]+[CM2]+[CM3]+[CM4A]+[CM4B]+[CM5A]+[CM5B]+[CM6]+[CM7A]+[CM7B]+[C
M8A]+[CM8B]+[CM8C])
EXACT ONE YEAR has 12 members on this sheet
Members: August 2013; July 2013; June 2013; October 2013; September 2013; ...
Delta T has the value 15.
Figure 18 Operating Hours in Each Mode (Fan, Cooling, Heating and
Mixed) for the VRF System
Description: Sum of Number of Hours for each Outdoor Air T (bin). Color shows details about
FAN HEAT COOL MIXED. The marks are labeled by sum of Number of Hours. The data is
filtered on LocalTime Weekday, LocalTime Hour and LocalTime (MY). The LocalTime
Weekday filter keeps Monday, Tuesday, Wednesday, Thursday and Friday. The LocalTime Hour
filter keeps 12 members. The LocalTime (MY) filter excludes May 2013 and June 2014. The
view is filtered on Outdoor Air T (bin), which excludes Null.
Outdoor Air T (bin) has 18 members on this sheet
Members: 65; 70; 75; 80; 85; ...
LocalTime Hour has 12 members on this sheet
Members: 10; 6; 7; 8; 9; ...
LocalTime (MY) has 12 members on this sheet
Members: August 2013; July 2013; June 2013; October 2013; September 2013; ...
There are 4 members on this sheet
Members: COOLING; FAN; HEATING; MIXED
The formula is IF([UNITS IN COOLING MODE]=0 AND [UNITS IN HEATING MODE]=0)
THEN "FAN" ELSEIF([UNITS IN COOLING MODE]0) THEN "MIXED" ELSEIF([UNITS IN
COOLING MODE]=0 AND [UNITS IN HEATING MODE]>0) THEN "HEATING" ELSEIF
([UNITS IN COOLING MODE]
LocalTime Weekday has 5 members on this sheet
Members: Friday; Monday; Thursday; Tuesday; Wednesday
The formula is [Number of Records]/60
Delta T has the value 15.
59
PG&E’s Emerging Technologies Program ET12PGE1381
Figure 20 Number of Hour’s Indoor Unit 8A and 8B are Operating in
Opposite Mode
Description: Sum of 8A 8B FIGHTING for each LocalTime Month. The data is filtered on
EXACT ONE YEAR, which keeps 12 members.
LocalTime Month has 12 members on this sheet
Members: August; July; June; October; September; ...
Sum of 8A 8B FIGHTING ranges from 0.00 to 14.52 on this sheet.
The formula is IF [MODE 8A]=0 THEN 0 ELSE(IF [MODE 8B]=0 THEN 0 ELSEIF[MODE
8A]!=[MODE 8B] THEN (1/60) END) END
EXACT ONE YEAR has 12 members on this sheet
Members: August 2013; July 2013; June 2013; October 2013; September 2013; ...
Delta T has the value 15.
Figure 21 Operating Mode and Hours for Indoor Unit in Data Center
Description: Sum of HM2 and sum of CM2 for each LocalTime Month. Details are shown for
LocalTime Month. For pane Sum of CM2: Color shows sum of CM2. The data is filtered on
EXACT ONE YEAR, which keeps 12 members.
LocalTime Month has 12 members on this sheet
Members: August; July; June; October; September; ...
Sum of CM2 ranges from -67.92 to 0.00 on this sheet.
The formula is IF [MODE 2]=1 then -(1/60) else 0 end
Sum of HM2 ranges from 0.00 to 50.92 on this sheet.
The formula is IF [MODE 2]=-1 then (1/60) else 0 end
EXACT ONE YEAR has 12 members on this sheet
Members: August 2013; July 2013; June 2013; October 2013; September 2013; ...
Delta T has the value 15.
Figure 22 Minimum Temperature Recorded for Each Month for Return Air
in the Data Center
Description: The trend of minimum of Indoor 2 Return Air T for LocalTime Month.
LocalTime Month has 12 members on this sheet
Members: August; July; June; May; September; ...
Minimum of Indoor 2 Return Air T ranges from 66 to 69 on this sheet.
Figure 23 Monthly Capacity Delivered for Each Floor
60
PG&E’s Emerging Technologies Program ET12PGE1381
Description: Basement, First Floor, Second Floor and Third Floor for each LocalTime Month.
Color shows details about Basement, First Floor, Second Floor and Third Floor
Measure Names has 4 members on this sheet
Members: Basement, First Floor, Second Floor and Third Floor
Measure Names is sorted manually.
LocalTime Month has 12 members on this sheet
Members: August; July; June; May; September; ...
Figure 24 Average EER versus Temperature Bins
Description: Average of EER for each Outdoor T. Color shows average of EER. The marks
are labeled by average of EER. The data is filtered on Exclusions (Outdoor RH,Outdoor T),
LocalTime Hour and LocalTime Weekday. The Exclusions (Outdoor RH,Outdoor T) filter
keeps 203 members. The LocalTime Hour filter keeps 12 members. The LocalTime Weekday
filter keeps Monday, Tuesday, Wednesday, Thursday and Friday.
Outdoor T has 18 members on this sheet
Members: 50; 55; 60; 65; 70;...
LocalTime Hour has 12 members on this sheet
Members: 10; 6; 7; 8; 9; ...
LocalTime Weekday has 5 members on this sheet
Members: Friday; Monday; Thursday; Tuesday; Wednesday
Average of EER ranges from 12 to 27 on this sheet.
The formula is [Total Capacity]/ ([Total Outdoor Power]*1000)
Parameters:
Delta T has the value 15.
CFM 4B has the value 630.
CFM 5A has the value 320.
CFM 5B has the value 320.
CFM 6 has the value 225.
CFM 7A has the value 350.
CFM 7B has the value 350.
CFM 8B has the value 820.
CFM 8A has the value 885.
CFM 4A has the value 640.
CFM 8C has the value 800.
CFM 2 has the value 777.
CFM 3 has the value 660.
CFM 1 has the value 580.
61
PG&E’s Emerging Technologies Program ET12PGE1381
MODELING APPENDIX
ZONING
62
PG&E’s Emerging Technologies Program ET12PGE1381
REFERENCES
http://www.pge.com/includes/docs/pdfs/about/edusafety/training/pec/toolbox/arch/climate
/california_climate_zones_01-16.pdf (accessed 07/19/2014)
http://www.pge.com/tariffs/tm2/pdf/ELEC_SCHEDS_A-10.pdf (accessed 07/16/2014)
ANSI/AHRI Standard 1230 ‘2010 Standard for Performance Rating of Variable Refrigerant
Flow (VRF) Multi-Split Air-conditioning and Heat Pump Equipment’ Air-Conditioning, Heating,
and Refrigeration Institute, Arlington, Virginia.
ASHRAE Handbook 2009, Fundamentals, American Society of Heating, Refrigerating and Air-
Conditioning Engineers, Inc., Atlanta Georgia.