Date post: | 14-Apr-2018 |
Category: |
Documents |
Upload: | jun-gwan-park |
View: | 220 times |
Download: | 0 times |
7/27/2019 PGU_TrbneAeratingRunnerTech.pdf
http://slidepdf.com/reader/full/pgutrbneaeratingrunnertechpdf 1/7www.powergenu.com
Turbine Aerating Runner
Technology
7/27/2019 PGU_TrbneAeratingRunnerTech.pdf
http://slidepdf.com/reader/full/pgutrbneaeratingrunnertechpdf 2/72 www.powergenu.com
Educational ObjectivesOn completion of this course, students will:
IntroductionIn recent years, environmental and water quality issues
have become signicant considerations in the operation and
upgrade of many hydropower stations and river systems.
The aeration of water passing through a hydraulic turbine
is rapidly becoming accepted as one eective method of
enhancing dissolved oxygen (DO) levels downstream of
hydropower projects. When coordinated with turbine
refurbishment or re-powering projects, the modications
required to enable aeration of the turbine discharge may be
accomplished in a cost eective manner.
As part of the ongoing hydro modern ization pro-
gram for their Catawba-Wateree Project, Duke Power
elected to upgrade hydraulic turbines at several of their
hydropower stations with various turbine aeration op-
tions. This course will consider the upgrade of Unit 3 at
Duke Power’s Wateree Hydro Station to include turbine
aeration capability as an example of the Turbine Aerating
Runner Technology.
There are a number of dierent options for introducing
air into the turbine discharge. The options are basically dis-
tinguished by the level of DO increase that may be expected,
the exibility of this aeration, the cost for implementation,
and the eect on hydraulic turbine performance. Dissolved
oxygen enhancement at the Wateree Project was accom-
plished by utilizing a new Francis type runner designed to
allow the natural aspiration of atmospheric air from the
trailing edge of the runner vanes.
This proprietary concept was rst proven through ex-
perimentation with a replacement Francis runner, manufac-
tured by Voith Hydro, which was installed by the Tennessee
Valley Authority (TVA) at Norris Dam.1, 2 The runner
installed by Duke Power at the Wateree Hydro Station wasdesigned and manufactured by Voith Hydro after mutual
evaluation of the project goals, the status of the technol-
ogy and the available options. This runner represents the
second generation of this technology and is the rst com-mercial application of the “aerating runner” design. Initial
testing of the Wateree 3 runner has shown excellent perfor-
mance, exibility, and strong DO enhancement capabilities
throughout the entire operating range.
Takingadvantageofopportunities
Typically, the upgrade of a turbine unit includes the
replacement of the existing turbine runner with a
new runner of an improved hydraulic design as well as
refurbishment and design improvement of the other
existing main turbine and/or generator components.
This provides a perfect opportunity to implement the
modifications required for adding turbine aeration ca-
pability on selected generating units in a cost-effective
manner. Duke Power has already implemented turbine
modifications which added “hub venting” capability at
several other hydropower stations (Reference 3). The
hub venting concept was chosen where the maximum de-
sired increase in DO was in the 2 to 3 mg/ l range and the
modifications could be implemented at a relatively smal l
incremental cost. Also, because the in itial focus was on
improving tailrace DO levels during low flow periods,
this fit the capabilities of hub venting well. Hub vent-
ing is most effective during operation of the hydraulic
turbine operating at partial load.
From results of the ongoing Duke Power DO testing
program, the aeration needs were determined to be dif-
ferent at Wateree. Based on historical data, a maximum
DO increase in excess of 3 mg/l would be desirable during
certain low DO periods. The peaking power demand for
Wateree also required the exibility to operate across as
much of the power range as possible. This presented moresignicant economic and technical challenges at Wateree
than for the projects where hub venting was selected and
implemented.
Turbine Aerating Runner Technology
1. Be provided an overview of one method
being used for the enhancement of dissolved
oxygen levels in reservoir water releases.
2. Learn about a variety of designs for aeration.
3. Learn a number of dierent options for
introducing air into the turbine discharge.
4. Understand the benets of the runner discharge
methodology and the aeration methodology.
7/27/2019 PGU_TrbneAeratingRunnerTech.pdf
http://slidepdf.com/reader/full/pgutrbneaeratingrunnertechpdf 3/7www.powergenu.com 3
SelectingandevaluatingtheoptionsDO enhancement by any method cannot be without cost,
but the costs of some DO enhancement alternatives can ex-
tend far beyond the initial investment. The selection of any
DO enhancement system must consider not only upfront
capital costs, but also associated operation and maintenance
costs, performance degradation impacts on revenue, system
eectiveness for multiple units, site specic DO uptakedesired, and site specic hydrology, among others.
In recent years Voith’s joint R&D eorts with their part-
ners have successfully developed a variety of designs for aera-
tion, including hub aeration, distributed aeration (through
the runner) and peripheral or discharge ring aeration.
There are at least four (4) options to consider to achieve
DO enhancement, as follows:
• Vacuum Breaker Aeration
• Hub Venting DO Enhancement Design (Central Aeration)
• Aerating Runner Design (Distributed System)
• Forebay Oxygen Injection System
Vacuum breaker aeration
Most of the hydropower stations on the Catawba-Wateree
have turbines with settings from 7 feet to as much as 15 feet
above tailwater. Manually operated valves exist to break the
draft tube vacuum, which allows the water to be cleared
from around the turbine runner. This permits the units to
be operated as synchronous condensers with very little pow-
er consumption. These valves also can be opened while the
turbines are generating, and air is admitted to the turbine
discharge thereby boosting its DO level. Modications can
be made to increase the air capacity through these valves.
The advantages of this design are that the modications
can usually be implemented without disassembly of the
turbine and at the lowest relative capital cost of the options
considered. The disadvantages are that the eectiveness
varies from station to station and that generally only modest
increases in DO can be realized. Testing results by Duke
Power have shown that at some locations this method can
approach the eectiveness of the hub venting design, but it
cannot achieve higher levels of DO uptake.
Hub venting DO enhancement design
For this design, modications to the turbine are imple-
mented which may allow large quantities of air to be drawn
through passageways in the turbine head cover and directed
to the runner nose cone. Air then travels to the turbine dis-
charge where turbulence in the runner vortex is relied upon
to distribute the air.
The advantages of this option are that larger quantities
of air are added to the turbine discharge than with the simi-
lar vacuum breaker aeration scheme, and the incrementaladditional cost of the modication is still relatively low. The
required turbine modications are not especially complex
and have been successfully completed on various projects by
most of the major turbine vendors. These DO enhancement
systems can be turned on or o as desired and do not have
a signicant eect on performance when not admitting air.
Testing of the units at other Duke Power hydropower sta-
tions has demonstrated that this option is most eective at
increasing DO levels during part load turbine operation and
has lesser enhancement capability as power increases. For
Wateree, it was not expected that the desired levels of DOcould be achieved with this option.
Aerating runner design
This design is similar to the hub-venting concept by using
modications to the turbine that are implemented to allow
large quantities of air to be drawn through passageways in the
turbine head cover. Instead of being directed to the runner
nose cone the air is distributed to the turbine runner, where
it exits from each the trailing edge of each vane. This is de-
signed to provide smaller air bubbles (i.e., higher surface area
for oxygen transfer) and to provide more thorough mixing atall operation levels. Therefore, higher levels of DO uptake are
achieved with less air being admitted than with the hub vent-
ing concept. This lower concentration of air in the draft tube
translates to higher hydraulic performance. Based on model
and prototype testing performed jointly by TVA and Voith
with the Norris turbines, there was reasonable assurance for
Wateree that higher levels of DO uptake could be achieved
with this technology without an unacceptable sacrice in
turbine performance throughout the operating range.
Forebay oxygen injection system
The design of this system uses submerged oxygen dispersion
manifolds in the hydropower station forebays, which are fed
from liquid oxygen storage tanks. This option was employed
at Buzzard Roost Hydro Station due to the diculty in draft-
ing air into the Kaplan turbine design. The advantage of this
system is that it provides an alternative when vacuum breaker
aeration is not sucient and turbine aeration is not viable.
There are however several clear disadvantages to this
option. The initial capital cost of installing this system at
Wateree could exceed the incremental capital cost of an
aerating runner due to the required embedment of the dis-
charge piping. There would also be ongoing annual O&M
cost for purchasing the liquid oxygen. Additional mainte-
nance of the forebay hoses and injection equipment must be
factored into the O&M cost as well.
Evaluation conclusion
From the evaluation performed for Wateree, it was readily
apparent that forebay oxygen injection would be too costly
to be competitive at this site and vacuum breaker venting
would not likely meet the targeted DO uptake. In the nalanalysis, although the aerating runner at Wateree requires
an initial ly greater capital investment than hub venting, the
long term benets for both DO uptake and exibility of op-
7/27/2019 PGU_TrbneAeratingRunnerTech.pdf
http://slidepdf.com/reader/full/pgutrbneaeratingrunnertechpdf 4/7
Figure 1 – Aerating Runner Distributor Section
Figure 2 – Aerating Runner
as Viewed from Below
Figure 3 – Relative Efciency and % Airow vs. Power
100%
85%
80%
R
e l a t i v e E f c i e n c y
A i r F l o w
a s a % o
f F l o w ( W a t e r )
75%
0
MW
Index Test Results from Wateree Aeration Testing
1 2 3 4
90%
95%
20%
10%
5%
0%
15%
3 Pipes
2 Pipes
1 Pipe
No Air
4 www.powergenu.com
eration provide sucient cumulative benets to make the
aerating runner the clear economic choice. Of particular
importance is the increased generation capability during
critical periods of the year, when ambient DO may be low
and peaking energy values may be high.
The aerating runner solution
At the time of the Wateree Project, the aerating runnerdesign was very new to the hydropower industry, with only
the second generation going to Wateree. Tests of the rst
generation distributed aeration system employed at Norris
Dam have shown that the runner discharge methodology
is more benecial than the aeration methodology for the
following reasons:
• Provides air over a range of turbine dis-
charges with lower impact to performance
than all other methods evaluated;
• Provides air in small bubbles which are distributed
over a wide area of draft tube inow;• Provides air in a manner which leads to
a high absorption eciency; and
• Requires smaller amounts of air and therefore preserves
more of the operating characteristic of the turbine.
To obtain the airow required to achieve a 3mg/l uptake
in DO, the Wateree blades were fabricated with hollow sec-
tions serving as the distribution path for air.
A cross section of the aerating runner for Wateree is
shown in Figure 1 above. The air enters the turbine through
pipes installed in the existing turbine guide bearing hous-
ing, where valves are located to control the air ow into the
cavity between the head cover and the rotating runner. A
third seal has been added to the head cover and runner to
isolate the air from thrust relief. Holes in the runner crown
allow the air to travel to the specially designed hollow runner buckets. The cavity within the bucket leads to the
discharge edge of the bucket, where specially designed air
distribution nozzles are used to distribute the air into the
water as a desired cloud of ne bubbles. The technology
embodied in the aerating turbine components is protected
by U.S. Patents 4789051 and 5823740 and is also the subject
of several patents pending.
Figure 2 shows the aerating run-
ner as viewed from below. Easily
visible are the nozzles that distrib-
ute the air to the water. Achieving the required air ow to meet the
greater than 3 mg/ l DO uptake
meant the losses for air ow had to
be minimized in all areas of the dis-
tribution system. This was an area
where the Norris Dam solutions fell below expectations;
therefore, this received very high attention in the second
generation design. The results obtained during testing at
Wateree conrmed the design goal was met; air ow was
in fact controlled by the external valves, rather than the
runner passageways choking o the ow and thus limiting the ultimate DO uptake potential. In summary, the primary
design enhancements incorporated at Wateree were air ow
distribution and reductions in air ow losses.
MakingthegradeatWateree–eldtestresultsThe aerating runner at Wateree was tested in two phases.
During the rst phase of testing, conducted in January 1999,
the machine was index tested with no air admission to estab-
lish a baseline for the unit performance and output charac-
teristics. Following the baseline test, the unit performance
characteristics were measured for several dierent air ow
rates. The results of this testing are shown in Figure 3. Several
observations can be made from Figure 3. For example, when
operating with up to 3 air valves open the turbine eciency
dropped no more than 5% from the baseline at BOP, and the
maximum power output dropped less than 3%. It was deter-
mined later in the testing that 3 open valves actually allowed
more air to be admitted than was needed to meet a 3 mg/l
uptake. The measured airow for the various valve congu-
rations is included on Figure 3. For the aerating runner, the
amount of airow at various turbine load settings from 50%
to 100% was largest at the lower water ow rates, dropping
slightly as the wicket gate setting was increased, when calcu-
7/27/2019 PGU_TrbneAeratingRunnerTech.pdf
http://slidepdf.com/reader/full/pgutrbneaeratingrunnertechpdf 5/7
Figure 4 – DO Uptake vs. Power
5.00
2.00
1.00
D O U p t a k e m g / l
0.00
9.00
Output MW
DO Uptake At Different Air Flows As A % Of Available Opening For Air Flow
11.00 13.00 15.00 17.00 19.00
3.00
4.00
50% Opening
100% Opening for Air Flow
33% Opening
16% Opening
66% Opening
www.powergenu.com 5
lated as a percentage of ow in SCFM. It should be noted that
the actual air volume under the runner depends on the local
pressures and will dier from site to site.
Phase 2 testing measured DO uptake in the tailrace down-
stream of the plant for various air admission settings. This test
was conducted in July 1999. The DO tests were run over sev-
eral days for several air ow conditions. The airow, turbine
relative ow, and generator output power were correlated withthe data from the Phase 1 testing. Baseline DO measurements
were recorded at the beginning and end of testing each day.
The baseline readings were taken after at least 30 minutes of
operating the Unit 3 turbine near best eciency with no air
admission. No other units were operating during the initial
Unit 3 DO tests (some multi-unit mixing tests are described
later). The results of the DO test are shown in Figure 4.
Figure 4 shows that with two air valves open (i.e., 33%
of the available opening), the DO uptake measured in the
tailrace was observed to reach a maximum of 3.5 mg/l when
the turbine is operating at part load. This characteristic is
also similar for hub aerating runners and is based on the
increased turbulence and vortex below the runner providing
enhanced mixing of the admitted air into the water ow.
When the turbine was brought up to best eciency, the DO
uptake dropped to 2.5 mg/l. This DO uptake then remained
constant up to full load. As further shown in Figure 4 the
desired 3 mg/l DO uptake was exceeded at all operating
conditions with just 3 of the available 6 supply pipes open.
As additional air pipes were opened up to the total of 6, the
DO uptake stabilized as the physics of the oxygen transfer
dynamics became saturated.
Completesystembenets
It is important to not only increase the DO levels in the
tailrace, but to use representative DO measurements in
evaluating tailrace aeration. From the raw data, it was
observed that for diering wicket gate positions that the
diering rotation of the draft tube swirl could tend to aect
the direction of the discharge ow and slightly bias the DOreadings at the three monitoring locations across the tail-
race. Therefore, the readings from all three monitors were
allowed to stabilize for each gate position and the readings
were then averaged to get a representative DO uptake. Fig-
ure 5 (above) tracks the averaged DO uptake at the tailrace
monitoring stations (50 yards from the powerhouse) with
four open air valves (~66% of the available opening). Ad-
ditionally, Figure 5 shows the DO uptake present when the
ow from a second adjacent unit, not having enhancement
capability, is mixed with the aerated output of Unit 3 (two
unit mixing occurs from 3:00 to 4:00 pm on the graph). The
mixed ow shows a greater combined DO than the arithme-tic average of the separate DO readings from the two units.
Thus, incremental air volumes above the volume absorbed in
the aerating unit had a benecial eect on the tailrace DO
when the ow from Unit 3 was mixed with other unit dis-
charges. This ability to improve mixed ows may enable the
station to operate aerated and non-aerated units together and
still provide adequate DO enhancement in the tailrace.
Conclusions
These tests have shown that the aerating runner system at
Wateree can eectively enhance tailrace dissolved oxygen
levels while simultaneously retaining much of the generation
capacity and exibility that is so valuable to the hydropower
owner. Although long-term, water quality improvements
in the Catawba-Wateree basin will require the continued
cooperation of water users and regulators, the new aerating
runner at Wateree hydropower stands ready to do its part.
References:1Hopping, P., March, P., Brice, T., Cybularz, J., Update on Development
of Auto-Venting Turbine Technology,” Proceedings, Waterpower
’97, pp. 2020-2027.
2March, P. A. , Brice, T.A. , Mobley, M.A. , and Cybularz, J.M.,“Turbines for Solving the DO Dilemma,” Hydro Review, March1992.
3Ganey, S. R., Jablonski, T. A. ,and Kirejczyk, J. ,”Using HydroTurbines To Enhance Dissolved Oxygen Levels,” Hydro
Review, August 1999, pp. 10-14.
Acknowledgements:
This course is based on the presentation entitled “Using HydroTurbine Aerating Runner Technology to Enhance DissolvedOxygen Levels” as presented at HydroVision International 2000.The authors for this paper are acknowledged as J. C. Sigmon,Duke Engineering & Services, Inc., G.D. Lewis, Duke Power,G.A. Snyder, Voith Hydro, Inc., and J.R. Beyer, Voith Hydro, Inc.Portions of the original paper have been modied for this course.
Figure 5 – DO Uptake vs. Time5
2
0
D O U p t a k e m g / l
1 1 : 4
5 A M
1 1 : 2
5 A M
1 2 : 0
5 P M
1 2 : 2
5 P M
1 2 : 4
5 P M
1 : 0
5 P M
1 : 2
5 P M
1 : 4
5 P M
2 : 0
5 P M
2 : 2
5 P M
2 : 4
5 P M
3 : 0
5 P M
3 : 2
5 P M
3 : 4
5 P M
4 : 0
5 P M
4 : 2
5 P M
5 : 0
5 P M
5 : 2
5 P M
5 : 4
5 P M
4 : 4
5 P M
Time of Day
1
3
4Avg DO mg/l 50 Yards Downstream
7/27/2019 PGU_TrbneAeratingRunnerTech.pdf
http://slidepdf.com/reader/full/pgutrbneaeratingrunnertechpdf 6/76 www.powergenu.com
Questions
OnlineCompletionUse this page to review the questions and choose your answers. Return to www.powergenu.com and sign in. If you have not previously purchased the program
select it from the “Online Courses” listing and complete the online purchase. Once purchased the exam will be added to your User History page where a Take
Exam link will be provided. Click on the “Take Exam” link, complete all the program questions and submit your answers. An immediate grade report will be
provided and upon receiving a passing grade (70%) your “Certicate of Completion” will be provided immediately for viewing and/or printing. Certicates of
Completion can be viewed and/or printed anytime in the future by returning to www.powergenu.com, sign in and return to your User History Page.
1. Name two signicant considerations
that have become important in theupgrade of a hydropower plant:
1. environmental issues
2. economic issues
3. time schedule
4. water quality issues
a. 1 & 2
b. 2 & 3
c. 1 & 4
d. 3 & 4
e. All of the Above
2. There are a number of dierent
options for introducing air into
the turbine discharge. The options
are distinguished by two of the
following:
1. the level of DO increase that
may be expected
2. type of method used
for air injection
3. the cost for implementation
4. ease of maintenance for
DO injection system
a. 1 & 3
b. 1 & 4
c. 2 & 4
d. 2 & 3
e. All of the Above
3. Implementing the modications
required for adding turbine
aeration capability on selected gen-
erating units is not cost-eective
to include when replacing an
existing turbine runner.
a. True
b. False
4. The hub venting concept was
chosen where the maximum desired
increase in DO was in the __ to
__ mg/l range and the modica-
tions could be implemented at a
relatively small incremental cost.
a. 1 to 3
b. 2 to 4
c. 2 to 3
d. 1 to 4
5. Hub venting is most eective
during operation of the hydraulic
turbine operating at partial load.
a. True
b. False
6. The selection of any DO enhance-
ment system must consider not only
upfront capital costs, but also:
1. Associated operation
and maintenance costs
2. Performance degradation
impacts on revenue
3. System eectiveness
for multiple units
4. Site specic DO uptake desired
5. Site specic hydrology,
among others.
a. 1 & 2
b. 2 & 5
c. 1 & 4
d. 3 & 4
e. All of the Above
7. In recent years, Voith’s joint R&D
eorts with their partners have
successfully developed a variety of
designs for aeration, including:
a. hub aeration
b. distributed aeration (through
the discharge ring)
c. perpendicula r aeration
d. head cover aeration
8. There are at least four (4) options
to consider to achieve DO enhance-
ment, as follows:
1. Vacuum Breaker Aeration
2. Hub Venting DO Enhancement
Design (Central Aeration)
3. Aerating Runner Design
(Distributed System)
4. Tailrace Oxygen
Injection System
a. True
b. False
9. The advantages of the Vacuum
Breaker Aeration design are that
the modications can usually be
implemented without disassembly
of the turbine and at the lowest
relative capital cost of the options
considered. The disadvantages
are that the eectiveness varies
from station to station and that
generally only modest increases
in DO can be realized.
a. True
b. False
7/27/2019 PGU_TrbneAeratingRunnerTech.pdf
http://slidepdf.com/reader/full/pgutrbneaeratingrunnertechpdf 7/7www.powergenu.com 7
Questions
OnlineCompletionUse this page to review the questions and choose your answers. Return to www.powergenu.com and sign in. If you have not previously purchased the program
select it from the “Online Courses” listing and complete the online purchase. Once purchased the exam will be added to your User History page where a Take
Exam link will be provided. Click on the “Take Exam” link, complete all the program questions and submit your answers. An immediate grade report will be
provided and upon receiving a passing grade (70%) your “Certicate of Completion” will be provided immediately for viewing and/or printing. Certicates of
Completion can be viewed and/or printed anytime in the future by returning to www.powergenu.com, sign in and return to your User History Page.
10. One advantage of the Hub Venting
DO Enhancement Design is that
smaller quantities of air are added
to the turbine discharge than with
the similar vacuum breaker aeration
scheme, but the incremental
additional cost of the modication
is relatively high. These DO en-
hancement systems can be turned
on or o as desired and do not have
a signicant eect on performance
when not admitting air. This option
is most eective at increasing DO
levels during full load turbine
operation and has lesser enhance-
ment capability at partial loading.
a. True
b. False
11. There are several disadvantages
to the Forebay Oxygen Injection
System:
1. The initial capital cost
of installing this system
2. Ongoing annual O&M cost for
purchasing the liquid oxygen
3. Additional maintenance
of the draft tube hoses
and injection equipment
4. Impact to sh passage
a. 1 & 4
b. 2 & 3
c. 1 & 2
d. 3 & 4
e. All of the Above
12. The runner discharge methodol-
ogy is more benecial than
the aeration methodology
for the following reasons:
a. Provides air over a range of
turbine discharges with lower
impact to performance than
all other methods evaluated
b. Provides air in large bubbles
which are distributed over a
wide area of draft tube inow
c. Provides air in a manner which leads
to a high absorption concentration
d. Requires smaller amounts
of air, but large amounts
of oxygen, and therefore
preserves more of the operating
characteristic of the turbine
13. In the Waterlee, testing determined
that __ open valves actually allowed
more air to be admitted than was
needed to meet a 3 mg/l uptake.
a. 2
b. 3
c. 4
d. 5
14. For the aerating runner, the
amount of airow at various
turbine load settings from 50% to
100% was largest at the ____ ____
water ow rates, dropping slightly
as the wicket gate setting was
____ __ __, when calculated as a
percentage of ow in SCFM.
a. lower/decreased
b. higher/increased
c. lower/increased
d. higher/decreased
15. It is important to not only
increase the DO levels in the
tailrace, but to use representa-
tive DO measurements in
evaluating tailrace aeration.
a. True
b. False