This document is not a sworn English translation. Consequently, in case of discrepancy or divergence between the English and Spanish DGPCPP versions, the

Spanish document will prevail.

PHASE 1. DOCUMENT GOVERNING THE PRE-COMMERCIAL PUBLIC PROCUREMENT (DGPCPP-PCPP)

III. DOCUMENT GOVERNING THE PRE- COMMERCIAL

PUBLIC PROCUREMENT (DGPCPP)

I. INTRODUCTION

II. PPI PMC PCPP

Initiative to support the entrepreneurial ecosystem DESAL+

LIVING LAB and carry out the public procurement process

of pre-commercial technological solutions in desalination,

with the aim of attracting highly innovative ideas/projects,

with high projection in the international market, to be

applied in CG.

Facilitate the development and testing of solutions

proposed by innovative startups, open to any natural or legal person, public or private, that end up in a solution

close to the market. Risks and benefits will be shared with

the contracting body.

Company fully owned by Cabildo de Gran Canaria and attached

to Consejería de Desarrollo Económico, Soberanía Energética,

Clima y Conocimiento (Department for Economic Development Energy Sovereignty, Climate and Knowledge)

Leads a comprehensive, investigational Programme of R&D&i

activities linked to the exploitation of the marine resources of the

islands within the framework of a Collaboration Agreement with the

Spanish Ministry of Sciences, Innovation and Universities

Public limited company fully owned by the Public Administration of

the Autonomous Community of the Canary Islands.

This entity has the powers required to launch the Pre-commercial

Public Procurement procedures ("PCPP”) that the DESAL+ Startups

Programme needs.

SPEGC

ITC

PUBLIC PROCUREMENT OF A GOOD OR SERVICE THAT

DOES NOT EXIST AT THE TIME OF PURCHASE, BUT CAN BE

DEVELOPED WITHIN A REASONABLE PERIOD OF TIME. REQUIRES THE DEVELOPMENT

OF NEW OR IMPROVED TECHNOLOGY IN ORDER TO

MEET THE REQUIREMENTS DEMANDED BY THE

PURCHASER.

PUBLIC PROCUREMENT OF

INNOVATIVE

TECHNOLOGY(PPIT)

THE PRE- COMMERCIAL PUBLIC PROCUREMENT IS A PROCEDURA

ESTABLISHED TO HIRE R&D SERVICES WHERE THE PUBLIC

PROCURER DOES NOT RESERVE THE RESULTS OR OUTCOME OF

THE R&D FOR ITS EXCLUSIVE USE OR FULLY PAYS THE COSTS OF THE SERVICES HIRED, BUT THE

PUBLIC PROCURER SHARES THE RISKS AND BENEFITS OF THE R&D

WITH THE WINNERS OF THE CONTRACT

PRE-COMMERCIAL PUBLIC

PROCUREMENT (PCP)

INNOVATION ASSOCIATION

(IA)

DEVELOPMENT OF INNOVATIVE PRODUCTS, SERVICES OR

WORKS AND THE SUBSEQUENT PURCHASE OF THE RESULTING

SUPPLIES, SERVICES OR WORKS,

PROVIDED THAT THEY CORRESPOND TO THE

PERFORMANCE LEVELS AND MAXIMUM COSTS AGREED

BETWEEN THE CONTRACTING AUTHORITIES AND THE

PARTICIPANTS

PUBLIC PROCUREMENT OF INNOVATION. TYPES

There are major differences between the types of Public Procurement of Innovation. (PPI)

1 IDEA

2 TECHNOLOGY CONCEPT FORMULATED

3 EXPERIMENTAL PROOF OF CONCEPT

4 TECHNOLOGY VALIDATED IN LAB

5 TECH VALIDATED IN RELEVANT ENVIROMENT

6 TECH DEMOS IN RELEVANT ENVIROMENT

7 PROTOYPE DEMOST OPERATIONAL

ENVIROMENT

8 COMMERCIAL PROTOTYPE

9 COMMERCIAL PRODUCT

INVESTIGATION

DEVELOPMENT

INNOVATION

CategoryTECHNOLOGY READINESS

LEVELS (TRLS)Pre-comercial public

procurement

R&D Services

Excluded LCSP

State Aid Framework (DPI)

Ends in Prototype or

Preseries

Work, Supply or Service

Regulated LSCP

Different award procedures

Unlimited deployment

R&D Phase

Acquisition phase result

LSCP Award Procedure

Mandatory deployment

PUBLIC PROCUREMENT OF INNOVATIVE TECHNOLOGY

INNOVATION

ASSOCIATION

There are big legal differences

between the types of innovative

public procurement

The state of art (output TRL) and final objetive ( input TRL) determines the type of PPI

PUBLIC PROCUREMENT OF INNOVATION. TRL

SEARCH FOR IDEAS. PMC

Tender. PCPP

Feasibility solutions.

Solution design

R&D Services contracts

Demo Solution - Prototype

THREE – PHASES PROCEDURE:1.FEASIBILITY STUDY

2.PROOF OF CONCEPT.DESIGN3. PRE-COMPETITIVE PROTOTYPE

PROJECTS MAY RECEIVEEXTERNAL FINANCING

INTELLECTUAL PROPERTY RIGHTS MANAGEMENT

SE DESARROLLARA

UN PROTOTIPO

COMPETITIVOProjectResult

Companies developing all phases of PCP with their proposed solution will execute studies,

design, equipment procurement, pilot and controlled demo-scale installation.

Tender budget 450.000€

(Tax excluded)

20/11/2020 NOV 2021

PMC TENDERPHASE I PHASE IIIPHASE II

FEASIBILITY PILOT DEMO

3 month from Project launch

10 month from Project

launch

PCP: Public procurement solutions with HIGH MARKET PROJECTION IN DESALINATION (FROM

TRL4) – scaling in phases over a period of 12 months up to TRL 6-7.

12 month form Project

launch

FINANCIACION Y HORIZONTE TEMPORAL

RESEARCHING

SOLUTIONS TO FUTURE

PUBLIC DEMANDS

PCP enable the

technological

capability of

Companies

R&D SERVICES CONTRACT

Excluded from Law 9/2017 of 8 November, on

Public Sector Contracts, transposing into Spanish

law the Directives of the European Parliament

and of the Council 2014/23/EU and 2014/24/EU

of 26 February 2014 (hereinafter, LCSP), as

regulated in its Article 8.

Not subject to the Community Procurement

Directive (D/18/2004), nor to the WTO

government procurement agreements.

PUBLIC PROCUREMENT

OF R&D RESULTS

Buyer and companies

share the benefits

resulting from the

research of solutions to

problems proposed by

the public purchaser.

Precommercial

public

procurement

(PCP)

INTRUMENTTYPE OF

CONTRACTWAY OF CONTRACTING PURPOSE

Precommercial Public Procurement

The PCP clearly regulates the final IPR in the

envisaged feasibility and pilot phases. The

proposer must be prepared to grant the

contracting authority a free and unlimited

licence to the pre-existing IPR.

Royalties

Precommercial public procurement(PCP). Industrial property rights

THE PRE- COMMERCIAL PUBLIC PROCUREMENT IS A PROCEDURE ESTABLISHED TO HIRE R&D SERVICES WHERE THE PUBLIC PROCURER DOES NOT RESERVE THE RESULTS OR OUTCOME OF THE R&D FOR ITS EXCLUSIVE USE OR FULLY PAYS THE COSTS OF THE SERVICES HIRED, BUT THE PUBLIC PROCURER SHARES THE RISKS AND BENEFITS OF THE R&D WITH THE WINNERS OF THE CONTRACT

Telematically and within the time limit indicated in the invitation to tender

PLACSP e-tendering services: https://contrataciondelestado.es/w

ps/portal/plataforma

It should be noted that the PLACSP

uses Spanish mainland time.

Presentation:

Tender

Consultations

and comunications:

Writing at least 10 calendar

days before the deadline for

submission of tenders, to the

following address: [email protected]

The answers will be published in

the 'questions and answers' section of the PLACSP.

In case of incidents, ITC may send

notifications to the addresses

provided by the tenderers in ANNEX I.

All the documents linked to this procurement procedure must be submitted in Spanish, except

for any documents for which the terms and conditions specifically establish the possibility to

submit them in English

Purpose:“R&D SERVICE FOR THE ASSESSMENT OF THE FEASIBILITY,

DESIGN, DEVELOPMENT AND VALIDATION OF A PILOT

SEAWATER DESALINATION SOLUTION WITH THE POTENTIAL

TO REACH THE THRESHOLD OF 1.5kWh/m3 OF

DESALINATEDWATER”

Desalación emergente: New

desalination processes or

technologies

AWARD PROCEDURE

Public Concurrence

Varius Selection Criteria

Best value for money

TYPE IPP PCP

Excluded from application Law 9/2017

Contract of a private legal nature. It is

governed by a regulatory document -

specifications

PREVALENCE

Regulatory document

(Spanish v.) in case of

discrepancies with other

contract documents

CPV

73100000-3 Research and experimental

development services

73300000-5 Design and execution of

research and development

42912340-7- Desalination apparatus.

MAINS ASPECTS OF THE DOCUMENT

MAINS ASPECTS OF THE DOCUMENT

LOCATION

BUDGET

FUNDING

Subvention granted by Cabildo de Gran Canaria to ITC, in order to develop a comprehensive,experimental programme of R+D+i linked to the exploitation of the islands' marine resources, inaccordance with the financial report submitted, which amounts to a total sum of SIX HUNDREDTHOUSAND EUROS (€600,000.00), within the framework of the Collaboration Agreement entered intobetween Cabildo de Gran Canaria and the Spanish Ministry of Sciences, Innovation and Universities,currently known as the Ministry of Science and Innovation.

450.0000€ (taxes excluded)

DELIVERY DEADLINE 12 MONTHS ENDING 29 DICIEMBRE 2022 AT THE LATESTS

Phase 1. At the successful tenderer's facilities

Phase 2 y 3. The pilot solution resulting from this purchase of R&D services will be installed and tested

at the facilities of ITC where the DESAL+ LIVING LAB is located, at Playa de Pozo Izquierdo s/n (SantaLucía, Gran Canaria, Las Palmas - Spain).

The Phase 3 May be completed at an alternative location within the island of Gran Canaria,

provided that it is advisable based on the technical conditions, at the discretion of the projectmanager.

3 Phases with the possibility of multiple awardees in each phase.

The phases are eliminatory

Maximum number of successful tenderers for each phase and maximum bid amount

per tender :

Maximum tender budget for each phase and maximum amount tendered per

successful tender.

2 years - not counting possible extensions of the deadline

Price to be broken down for each Phase According to Annex II Model

The maximum tender amount per successful tenderer may not be exceeded. It would

imply exclusion from the process

phaseSuccesfultenderers

Maximum amount per succesful tenderer

IGIC

Maximum tendereramount per succesful

tenderer1 3 40.000,00 € 2.800,00 € 42.800,00 €

2 2 130.000,00 € 9.100,00 € 139.100,00 €

3 2 35.000,00 € 2.450,00 € 37.450,00 €

total 205.000,00 € 14.350,00 € 219.350,00 €

• 368.852,46€ Direct Costs

• 11.065,57€ Indirect Costs

• 47.950,82€ General Expenses

• 22.131,15€ Industrial Profit

Tender budgets and prices

450.000€ + 31.500€

MAINS ASPECTS OF THE DOCUMENT

ENVELOPE 1

ENVELOPE 2

NON AUTOMATICALLY QUANTIFIABLE

8 CRITERION

75 POINTS

AUTOMATICALLY

QUANTIFIABLE

2 CRITERION

25 POINTS

ADMINISTRATIVE DOC TECHNICAL DOC ECONOMIC DOC

ESPD Document (Appendix I)

Responsible DeclarationTechnical proposal(aprox 40

pages long)

Economic offer and future

royalties returns. APPENDIX II

y III

AWARD CRITERIA

ENVELOPE 2 – 75 POINTS

PROJECT PROPOSAL

PRELIMINARY DESIGN OF THE PLANT

INNOVATIVE CONTENTS OF THE SOLUTION

TESTING PLAN

APLICAB TECH

PROPOSAL OF HEAD OF PROJECTS

HUMAN AND TECHNICAL RESOURCES

OPERATIONAL PLAN

15

15

10

10

10

5

5

5

NON-AUTOMATICALLY QUANTIFIABLE

CRITERIA

TOTAL: 75

AWARD CRITERIA

ENVELOPE 3 – 25 POINTS

% Percentage applicable to prospective sales

The % should be above 2%

ECONOMIC OFFER

15

10

AUTOMATICALLY

QUANTIFIABLE CRITERIA

TOTAL: 25

AWARD CRITERIA

CRITERIA IN CASE OF TIE: Score of each solution in each non-quantifiable award criterion in order of importancein score and according to the order of appearance in the score scale. In the event of a tie, a draw will be made

by lot.

CREDITWORTHINESSAND FINANCIAL RELIABILITY

TECHNICAL AND PROFESIONAL STANDING

Yearly turnover during any of the last five years of at least 0.7 times lower the estimated value of the contract per successful tenderer (€14,500.00).

Main services or works carried out in the last 5 years, including amount, dates and the recipient, public or private, of the same. Minimum amount of services 70% estimated contract value per successful tenderer.

CV /resume of the individuals proposed to hold the following roles: Head of Project( ≤10 years) Researcher - Engineer/technician responsible for the design

and development of the prototype(≤5 years) Researcher - Engineer/technician responsible for the follow-up,

data collection and documentation of the results/outcome(≤5 years)

The Deed of incorporationNon-Spanish companies from EU Member must prove their capacity to exercise rights by providing a certificate or affidavit stating that they are registered with any of the registries set

out in Annex I of the General Regulation of the Spanish Public Administration Contract Act (LCAP)

Statement of Compliance:

Indicating the availability of the technical means required for the

implementation of the project set out in the TSP-PCPC Indicating the part of the contract that the business or professional

is intended to outsource/subcontract

Five Percent (5%) of the award amount of the appropriate contract phase, excluding any indirect taxes

CREDITWORTHINESS

GUARANTEE

CAPACITY

SUCCESFUL TENDERERS- CAPACITY- CREDITWORTHINES& GUARANTEE

In the case that the contractor fails to provide any service within the appropriate term due to any cause attributable

to the contractor :

- ITC may choose to terminate this contract, resulting in the loss of the guarantee, or to impose a daily penalty

(applicable on every calendar day) at a rate of €0.60 per each amount of €1,000 of the award amount established for that specific phase of the contract.

In the case that the successful tenderer fails to properly provide the services that are the subject matter of the

contract

- ITC may opt to terminate the contract and keep the guarantee or to impose an economic fine in proportion to the

seriousness of the non-compliance.

In the case that any penalties due to the non-compliance with the contract reaches a multiple of the 5% of the

contract price, excluding the VAT (IGIC), the contracting body will be entitled to terminate the contract or to agree

on the continuation of the contract subject to the imposition of new penalties.

In case of default

- ITC will not have the obligation to notify the contractor in advance about such default.

Non Compliance and penalties

NON COMPLIANCE AND PENALTIES

I. Under ITC convenience. Motivating through report the new scope:

Increase pilot scale

Increase scope of planned experimental plan

Intensify experimental work in some of the phases

Modification of the place where phase III will be carriedout in another location different from Pozo Izquierdo.

II. The amount of activities to be carried out will be proposed by the companies participating in the

corresponding phase.

III. In no case may the amount of the modifications exceed the budget indicated by the contracting body

for the execution of the corresponding phase or, cumulatively, exceed 50% of the total initial price.

CONDITIONS

CONTRACT AMENDMENTS

I. The economic value of an offer (in euros), excluding VAT (IGIC) may be considered

as abnormally low in the case that the value is lower by a 25% (twenty-five percent)

than the maximum bid budget per awardee of each phase established in clause 9

herein.

II. In the case that a proposal is considered disproportionate, the relevant tenderer will

be notified to justify the value of the offer and specify the conditions of such offer

within a term of at the latest five (5) working days from such notice.

III. In the case that the contracting body finds that a tender is not feasible because it

includes abnormally low values, such tender will be rejected.

ABNORMALLY LOW OFFERS

ABNORMALLY LOW OFFERS

ABNORMALLY LOW OFFERS

INDUSTRIAL PROPERTY RIGHTS (IPR)

III. PLIEGO CONTRATACION ADMINISTRATIVO

01 RESULTS PROPERTY

It will belong to the contractor,

but they must indicate that the

product obtained is the result of

collaboration with ITC in the

Desal+ Startups R&D programme.

02

04 06

03

05 07SUBSCRIBES

Contractors may grant sub-licences

(exclusive or otherwise) of the

products developed, subject to

prior authorisation by the

contracting authority under the

conditions set out in section e) IPR.

The contracting authority shall have

a free licence for use.

FURTHER DEVELOPMENT AND FUTURE INVENTIONS

Transfer contract between the

parties. Independent exploitation

of the improvements may not be

carried out until execution of the

exploitation document.

CO-DEVELOPMENT WITH THIRD PARTIES

Contractors may enter into

co-development agreements

with third parties with

agreement between the

parties on the monetary value

of the revenues

APPLICATION MANAGEMENT AND MAINTENANCE

Responsibility of the contractor.

Any new results must be reported

by the contractor to the

contracting authority, especially

those of commercial potential.

PUBLICATION RESULTS

Must be approved by

both parties

PREVIOUS KNOWLEDGEDoc sobre 2 – 4 d):

Responsible Declaration Technologies

and/or know-how

Declaration of responsibility for third party

licences

Declaration of responsibility for the acquisition

of prior knowledge possessed by third parties

Responsible Declaration of the extension

of third-party licences to the contracting

authorities free of charge

This document is not a sworn English translation.

Consequently, in case of discrepancy or divergence between the English

and Spanish DGPCPP versions, the Spanish document will prevail.

THANK YOU!