NetPlan – A Practitioner’s Experience
HASTUS International User Group
September 2012
Phillip Boyle & AssociatesPhillip Boyle & Associates
1. Introduction
2. Our NetPlan Experience
3. Project Focus – Invicta intermodal Scheduling Project
2September 2012
4. NetPlan Solutions to Implementable Outcomes
Phillip Boyle & Associates
Phillip Boyle & Associates has worldwide experience in use of Hastusand NetPlan to produce successful operating outcomes
3September 2012
Phillip Boyle & AssociatesPhillip Boyle & Associates
1. Introduction
2. Our NetPlan Experience
3. Project Focus – Invicta intermodal Scheduling Project
4
4. NetPlan Solutions to Implementable Outcomes
September 2012
Phillip Boyle & Associates
Phillip Boyle & Associates has used NetPlan extensively for planning studies and for service implementation projects
5
Service Location Project Type
Ipswich, QLD Implementation/Service Change Major improvement in connectivity/service quality and improved efficiency
Caboolture, QLD Implementation/Service Change Major improvement in connectivity/service quality and improved efficiency
Park Ridge, QLD Implementation/Service Change Major improvement in connectivity/service quality and improved efficiency
Western Sydney Competitive Tendering In progress
Croydon, Vic Implementation/Network Change
Major improvement in connectivity/service quality and improved efficiency
Doncaster, Vic Competitive Tendering In progress
Cranbourne, Vic Implementation/Service Change Major improvement in connectivity/service quality and improved efficiency
Bendigo, Vic Implementation/Service Change In progress
Latrobe Valley, Vic Implementation/Network Change
Major improvement in connectivity/service quality and improved efficiency
Canberra, ACT Network Change/Planning Study In progress
Las Vegas, NV Competitive Tendering Improved gold-line timetable
Outcome
September 2012
Phillip Boyle & Associates
Westside Bus, Ipswich (Queensland)
6
Service Area
• 18 bus routes, 70 peak vehicles (incl. schools)• Heavy rail service to downtown Brisbane
requiring strong intermodal connectivity at five stations
• Several routes serving common corridors
Project Approach
• Complete re-write of all timetables, on a revised network
• Provide an implementable solution, complete with driver paddles and period rosters
• Work with the bus company on behalf of the state (Translink)
Outcomes
• Major improvement in connectivity & timetable quality
• Improved operating efficiencies• Increased patronage
September 2012
Phillip Boyle & Associates
Westside Bus, Ipswich (Queensland) – NetPlan Schematic
7September 2012
Phillip Boyle & Associates
ACTION Buses (Canberra)
8
Service Area
• 80 bus routes, approx 350 peak buses• Bus is the only mode• Network serves downtown plus four
additional regional centres• Trunk services supported by feeder routes
Project Approach
• Support network planning to identify resource impacts of potential network changes
• Run NetPlan for both existing and proposed networks to allow valid comparison
• Use NetPlan solutions as basis for more detailed scheduling tasks
Outcomes
• Allowing strong support of evidenced-based planning process
• Identifying potential for improved timetable quality
• Ongoing project
September 2012
Phillip Boyle & Associates
Caboolture (Queensland)
9
Service Area
• 6 bus routes, 8 peak buses• Heavy rail service to downtown Brisbane
requiring strong intermodal connectivity at five stations
Project Approach
• Complete re-write of all timetables, for an existing network
• Provide an implementable solution, complete with driver paddles and period rosters
• Work with the bus company on behalf of the state (Translink)
Outcomes
• Major improvement in connectivity & timetable quality
• Improved operating efficiencies (8% more service for 2% more cost)
• Strong patronage increases
September 2012
Phillip Boyle & AssociatesPhillip Boyle & Associates
1. Introduction
2. Our NetPlan Experience
3. Project Focus – Invicta intermodal Scheduling Project
10
4. NetPlan Solutions to Implementable Outcomes
September 2012
Phillip Boyle & Associates
The Invicta bus network covers a substantial part of eastern Melbourne, operating 21 routes with an additional 80 dedicated school services
11
Existing Route Network - Invicta
September 2012
Phillip Boyle & Associates
The network has a range of complexities that require sophisticated scheduling approaches
A few challenges:
Strong connectivity required with the heavy rail system
A range of different route types, and sometimes vehicle types
Some routes offer demand-responsive or flex-route configurations
A number of dedicated school runs are operated and integrated (scheduling-wise) with the regular route services
12September 2012
Phillip Boyle & AssociatesPhillip Boyle & Associates
1. Introduction
2. Our NetPlan Experience
3. Project Focus – Invicta intermodal Scheduling Project
13
4. NetPlan Solutions to Implementable Outcomes
Project process
September 2012
Phillip Boyle & Associates
The project focus was to provide timetable and connectivity enhancements as part of a service change implementation
The key project objectives were:
Generate substantial service quality improvements
Improve the understanding of connection requirements through additional research (Monash ITS – recommended the NetPlan SQI as the most appropriate indicator of relative timetable quality)
Provide network improvements
Ensure the final solution is of sufficient operating robustness to be implemented
Provide a completed operating solution
14September 2012
Phillip Boyle & Associates
The network was defined in NetPlan, with the heavy rail system fixed (for connectivity)
15September 2012
Phillip Boyle & Associates
Many instances of common route corridors were also considered
16September 2012
Phillip Boyle & Associates
Over 70 meet builders were defined, both intermodal and bus-to-bus
17September 2012
Phillip Boyle & Associates
Of particular note was the need to, in some instances, build the whole-of-day timetable based on travelling past the school at morning/afternoon bell times, but keeping an all-day clockface
18September 2012
Bell times modeled by defining a ‘route’
Phillip Boyle & Associates
To understand how to weight/prioritize the meet builders, we undertook a system-wide on-board survey, using an advanced iPad data collection system, tracking the number of passengers transferring at key locations
19September 2012
Phillip Boyle & Associates
Our approach modeled alternatives to find the ‘sweet spot’ in the tradeoff between efficiency and timetable quality/intermodal connectivity
20September 2012
Off-Peak SQI Comparison
Existing Off-Peak
Phillip Boyle & Associates
In the end a complete set of all day timetables, blocks and runs were developed from the NetPlan solutions
21September 2012
Phillip Boyle & AssociatesPhillip Boyle & Associates
1. Introduction
2. Our NetPlan Experience
3. Project Focus – Invicta intermodal Scheduling Project
22
4. NetPlan Solutions to Implementable Outcomes
Coordination Improvements Summary
September 2012
Phillip Boyle & Associates
The NetPlan Service Quality Index indicated significant improvements to timetable quality, and these were supported by a detailed comparison of the timetables…..
23September 2012
Why use the SQI?
Allows an objective comparison of different options or solutions
Enables better understanding of the tradeoff between cost and quality Recommended by Monash ITS research as the best method for evaluating timetable
quality
The SQI for the off-peak indicated a doubling of timetable quality but needed less vehicles
Phillip Boyle & Associates
On weekdays, there are 19% more scheduled connections within 12 minutes.
24September 2012
Phillip Boyle & Associates
In particular, there has been a significant increase in scheduled connections of 3 to 8 minutes
25September 2012
Phillip Boyle & Associates
On weekends, there are 42% more scheduled connections < 12 minutes.
26September 2012
Phillip Boyle & Associates
As a result, there are 50% fewer scheduled connections of greater than 20 minutes on weekends.
27September 2012
Phillip Boyle & AssociatesPhillip Boyle & Associates
1. Introduction
2. Our NetPlan Experience
3. Project Focus – Invicta intermodal Scheduling Project
28
4. NetPlan Solutions to Implementable Outcomes
Patronage impacts after 12 months
September 2012
Phillip Boyle & Associates
Overall patronage from May 2011 to May 2012 has increased by over 15 percent on the eight routes surveyed
29September 2012
Route May 2011 May 2012 Change
664 1,498 1,586 6%
671 192 165 -14%
672 167 236 41%
675 92 131 42%
676 98 100 2%
677 171 154 -10%
691 1,192 1,280 7%
693 1,263 1,715 36%
Overall 4,673 5,367 15%
Source – PBA surveys conducted in May 2011 & May 2012
Phillip Boyle & AssociatesPhillip Boyle & Associates
1. Introduction
2. Our NetPlan Experience
3. Project Focus – Invicta intermodal Scheduling Project
30
4. NetPlan Solutions to Implementable Outcomes
Changes in connectivity patterns
September 2012
Phillip Boyle & Associates
The survey results show a signifcant increase in passengers transferring between buses and trains, well above general patronage level increases
31
Existing Proposed
Total Bus Patronage 4,673 5,367 694 (+15%)
Total Connecting Passengers 849 1,278 429 (+51%)
Total Connecting Passengers as % of bus Patronage 18% 24%
Change
Invicta Phase 1Summary of Weekday Patronage Changes
Source – PBA surveys conducted in May 2011 & May 2012
September 2012
Phillip Boyle & Associates
Both on a per-route basis, with almost every route showing increases in the percentage of connecting passengers…..
32September 2012
Source – PBA surveys conducted in May 2011 & May 2012
Phillip Boyle & Associates
….and by time of day, where only evening services show any reduction
33September 2012
Source – PBA surveys conducted in May 2011 & May 2012
Phillip Boyle & AssociatesPhillip Boyle & Associates
1. Introduction
2. Our NetPlan Experience
3. Project Focus – Invicta intermodal Scheduling Project
34
4. NetPlan Solutions to Implementable Outcomes
On-time running improvements
September 2012
Phillip Boyle & Associates
Finally, service reliability has also improved, with on-time running increasing overall from 73% to 81% across all routes, and some routes showing substantial levels of improvement
35September 2012
Source – PBA surveys conducted in May 2011 & May 2012
Phillip Boyle & AssociatesPhillip Boyle & Associates
1. Introduction
2. Our NetPlan Experience
3. Project Focus – Invicta intermodal Scheduling Project
36
4. NetPlan Solutions to Implementable Outcomes
September 2012