PHS - MAINTENANCE BUILDING SEISMIC STRENGTHENING PROGRAM/ MEASURE E BOND PROGRAM INVESTIGATION, ANALYSIS, AND PRELIMINARY CONCEPT October 24, 2007 R. P. Gallagher Associates Structural Engineers
Transcript

PHS - MAINTENANCE BUILDINGSEISMIC STRENGTHENING PROGRAM/

MEASURE E BOND PROGRAM

INVESTIGATION, ANALYSIS, AND PRELIMINARY

CONCEPT

October 24, 2007

R. P. Gallagher AssociatesStructural Engineers

SITE PLAN

(E) WORKSHOP

(E) STORAGE(E) TRAILER

(E) TRANSFORMER(E) TRAILER

PIEDMONT MIDDLE SCHOOL

STRUCTURAL

STRUCTURES DO NOT MEET ASCE 31

WOOD BUILDING AND TRAILERS WILL LIKELY

FALL OFF SUPPORTS

PREFAB UNLIKELY TO COLLAPSE, BUT MAY BE DAMAGED

MEZZANINES DO NOT MEET CODE

MANY NONSTRUCTURAL HAZARDS

CONTINUED OPERATIONS SEVERELY IMPAIRED OR PREVENTED AFTER EARTHQUAKE

ESSENTIAL IN PREPAREDNESS AND RECOVERY OPERATION

PATH OF TRAVEL NON COMPLIANT

NO ACCESSIBLE ROUTE

LACK OF CODE COMPLIANT DIRECTIONAL SIGNAGE

STAIRS ARE NON COMPLIANT

NO RAMP FOR WHEELCHAIR ACCESS

NO ACCESSIBLE PARKING

ADA / ACCESSIBILITY

EXTERIOR SIDES OF EXIT DOORS DO NOT HAVE HANDRAILS OR LANDINGS

LACK OF PROPER EXHAUST SYSTEMS

LACK OF OSHA COMPLIANCE

NO FIRE ALARM

UNSAFE STORAGE

FIRE & LIFE SAFETY

VARIOUS OPTIONS:

REPAIR EXISTING BUILDINGS

REMOVE WOOD FRAME BUILDINGS AND TRAILERS, REPLACE WITH NEW BUILDINGS

REPLACE ALL BUILDINGS

EXISTING

NEW

1. NEW WORKSHOP/ UPGRADED METAL BUILDING

PROJECT COST: $ 1 – 1.8 Million

OUTCOMES:

More functional

5 Standard parking spaces

Meets ASCE 41

2,000 sf

2,000 sf

EXISTING

NEW

2. NEW WORKSHOP/ STORAGE/ OFFICES

PROJECT COST: $ 2.7 Million

OUTCOMES:

4000 sf new building

Code compliant

5 truck parking spaces plus 3 standard parking spaces

Efficient layout

4,000 sf

PHS – MAINTENANCE BUILDING

PRISCILLA MECKLEY – ARCHULETA

MIKE WASSERMANN

JOHN NELSON

RON GALLAGHER

* For more information, visit http://www.pusdbond.orgR. P. Gallagher Associates