+ All Categories
Home > Documents > Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang...

Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang...

Date post: 05-Aug-2020
Category:
Upload: others
View: 0 times
Download: 0 times
Share this document with a friend
43
Phu Kham Operations, November 2013 David Reid, General Manager
Transcript
Page 1: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Phu Kham Operations, November 2013

David Reid, General Manager

Page 2: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Safety performance – zero harm objective

1.82

00.20.40.60.811.21.41.61.82

0

1

2

3

4

No

v-1

2

De

c-1

2

Jan

-13

Feb

-13

Mar

-13

Ap

r-1

3

May

-13

Jun

-13

Jul-

13

Au

g-1

3

Sep

-13

Oct

-13

TR

IFR

Nu

mb

er

of

Inju

ries

Total Reportable Injuries & Frequency Rate Last 12 Months

TRI Occurances 12 Mth TRIFR YTD TRIFR TRI Target

0

0.05

0.1

0.15

0.2

0.25

0.3

0.35

0

1

2

3

4

5

6

No

v-1

2

De

c-1

2

Jan

-13

Feb

-13

Mar

-13

Ap

r-1

3

May

-13

Jun

-13

Jul-

13

Au

g-1

3

Sep

-13

Oct

-13

LT

IFR

Nu

mb

er

of

Inju

riie

s

Month

Lost Time Injuries & Frequency Rate Last 12 Months

LTI Occurances 12 Mth LTIFR YTD LTIFR LTI Target

-0.10

0.00

0.10

0.20

0.30

0.40

0.50

0.60

0

1

2

3

4

5

6

No

v-1

2

De

c-1

2

Jan

-13

Feb

-13

Mar

-13

Ap

r-1

3

May

-13

Jun

-13

Jul-

13

Au

g-1

3

Sep

-13

Oct

-13

RT

IFR

Nu

mb

er

of

Inju

ries

Month

Restricted Work Injuries & Frequency Rate Last 12 Months

RWI Occurances 12 Mth RWIFR YTD RWIFR RWI Target

Page 3: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Established operation with competitive

cash costs

2013 production expected to be 62,000t

to 65,000t copper at an average C1 cash

costi of approx. US$1.35/lb; total cash

costs (incl. royalty, sustaining capital and

lease and finance charges) US$2.14/lb

for 9 months to 30 Sep 2013

Production expected to rise to between

65,000t and 70,000t copper in 2014 and

over 70,000t in 2015

2016 onwards: production rates to

increase progressively to a peak of

approximately 90,000t in 2018 and 2019

Phu Kham Operation – Outlook Summary

i: C1 direct operating costs, based on payable copper in concentrate produced, after precious metal

credits. Assumes DecH2013 prices of US$1300/oz gold and US$20/oz silver.

Data shown on a 100% equity basis.

Page 4: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Commenced production 2008: 12Mtpa

nominal capacity exceeded

Process plant expanded in 2012 to

16Mtpa nominal: processing rates

exceeding design on transitional ores

Increased Recovery Project completed

2013 ahead of schedule and under

budget: recovery performance exceeding

design for ore types processed

Potential for further mine and mill

optimisation

2013 Ore Reserve estimate confirmed

10-year mine life

Phu Kham district exploration upside

Phu Kham Operation – Overview

Data shown on a 100% equity basis.

Page 5: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Phu Kham: progressive upgrades

2nd regrind mill six additional cleaner cells

2nd filter

3rd transformer

2nd ball mill

Increased flotation capacity

16Mtpa Upgrade Project

Increased Recovery Project

Page 6: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Mill processing rate to increase from

12Mtpa by 33% to a design capacity of

16Mtpa on primary ore

Commissioned in the SepQtr2012; quick

ramp-up; record throughput achieved in

December 2012 demonstrating high

throughput rates at 21Mtpa, running at

18Mtpa rates in 2013

Timed to offset a decline in head grades as

deeper primary ore is mined and processed

Grinding and flotation capacity increased by

50%; collectively deliver 2% absolute

improvement in copper recovery

Capital cost within the US$95M budget

Phu Kham: Upgrade Project

Data shown on a 100% equity basis.

Page 7: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Increased recovery achieved through less

selective rougher flotation together with

increased regrind, cleaner flotation and

concentrate handling capacity

Project completed April 2013, several

months ahead of schedule and under

budget

Utilises existing plant technology: low

technical risk, rapid payback

Metallurgical recovery performance to

date is exceeding design model

expectations for copper and gold based

on ore types processed

Phu Kham: Increased Recovery Project

Data shown on a 100% equity basis.

Page 8: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Expecting an average 6% absolute

increase in copper and gold recovery

Actual recovery rates achieved will

depend upon ore type (S:Cu ratio) and

production strategy including grind size

vs throughput rate trade-off; moderate

positive correlation with copper grade

S:Cu ratio expected to decline (11-13) as

the proportion of primary ore increases

Minor increase in unit processing costs

due to power and grinding media

required for the second regrind mill….

…increased metal production is expected

to reduce C1 cash cost by more than 5%;

capital cost under budget by $10m

Increased Recovery Project

0

10

20

30

40

50

60

70

80

90

0 10 20 30 40

Co

pp

er

reco

very

(%

)

Sulphur : copper ratio

0

10

20

30

40

50

60

70

80

90

0.3 0.4 0.5 0.6 0.7

Co

pp

er r

eco

ver

(%)

Copper grade (%)

Charts show actual daily performance data from July 2013 onwards.

Page 9: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Crusher bottleneck at 18 to 18.5Mtpa

on softer ore, examining options to

improve

SAG mill capacity ~20Mtpa

Original plant design required a

pebble crusher in order to maintain

nameplate throughput on primary ore

Evaluating options to improve in-pit

ore fragmentation (mine to mill

studies) and improving crusher

operating time to allow optimal SAG

mill operation

Opportunity to circumvent crusher by

providing crushed ore from satellite

pits – KTL & LCT potential – and low-

grade stockpiles

Throughput optimisation

Data shown on a 100% equity basis.

Page 10: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Geotechnical instability detected in the

interim pit west wall in December 2012

Revised mine schedule necessitated

lower grade transitional ore to be

prioritised thereby delaying access to

higher grade ore in the pit floor

Average copper head grade for

2013/2014 is expected to range from

0.45% to 0.50%

Interim wall slope angle being reduced;

no change to final pit wall design

The interim west wall failure was mined

out from January to October 2013, new

walls established

Open-pit

Page 11: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Revised life of mine plan developed;

copper production to progressively

increase to a peak of around 90,000t in

2018 and 2019

Ore processing rate of 18Mtpa expected to

be sustained

Phu Kham open pit mine life remains 10

years (from start of 2013) at a copper price

of US$3.00/lb

Potential for mineralisation from satellite

deposits close to Phu Kham and near

Phonsavan to augment mill feed and/or

extend mine life

Revise mine plan: October 2013

Data shown on a 100% equity basis.

Page 12: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Material movements of approx. 50Mtpa from

2014 to 2016 then reducing; additional mine

shovel and drill required in 2014; LOM strip

ratio of 1.2:1

Low-grade stockpile strategy developed

reducing effective strip ratio in high material

movement years

Truck fleet scheduled to increase from Q1

2016 by six trucks as haulage distances

increase with open-pit depth

Accounting standard amended for 2013:

deferred waste mining costs now limited to

waste mining relating to future mining areas

Approximately US$23.3M (or 8.1Mt) of waste

stripping for 2013 is expected to be capitalised

Material movements and strip ratios

Mining pit stages

Mining areas (red) in 2014 Data shown on a 100% equity basis.

Page 13: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Progressive TSF wall lifts have

historically been a significant

component of sustaining capital at

Phu Kham

Implementation of floating discharge

of tailings and continuous discharge

of decant water in 2012 has led to a

revised TSF construction schedule

Annual sustaining costs for 2013 –

2015 are expected to reduce

significantly but will vary depending

upon requirements for

accommodating waste as a

construction material

Tailings Storage Facility

Data shown on a 100% equity basis.

Page 14: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

0.31

0.28

0.26 0.22

0.32

0.08

0.08

0.07 0.09 Labour

Fuel

Process power

Grinding media

Maintenance, mill liners andother spares

Explosives

Reagents

Tyres

Other

Total on-site operating costs: US$1.71/lb (before credits)

Site costs for the 9 months to 30 Sep 2013

Page 15: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Current production fleet comprises:

48 CAT777D 100t trucks

2 PC3000 & 2 RH90 face shovels

2 PC2000 excavators

Reconciliation: ore processed to Ore

Reserve; project to late 2012:

-6% contained copper

+4% contained gold

+24% contained silver

-5% ore tonnes

Low LOM strip ratio: 1.2:1 based at a

US$3.00/lb copper price

Mining costs: US$2.50/t – US$3.00/t,

average $2.60/t

Mine and ore body performance

Tonnes/month

0

500,000

1,000,000

1,500,000

2,000,000

2,500,000

3,000,000

3,500,000

4,000,000

Ap

r-0

8

No

v-0

8

Jun

-09

Jan

-10

Au

g-1

0

Mar

-11

Oct

-11

May

-12

Dec

-12

Jul-

13

Total material mined

Ore mined

Extreme

rainfall

events

Page 16: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Design process plant capacity of

16Mtpa has been exceeded on

softer transitional ores, site uses a

blending regime (S:Cu, hardness)

End Sep 2013 YTD average

processing rate of 2,244t/hr versus

design 2,000t/hr

Ball mill Bond work index range

10-17 kWh/t

Primary grind: P80 of ~90μm

Regrind: P80 of ~30μm

Processing cost: averaging

US$6.50/t

Process plant performance: ore milled

Tonnes/month Tonnes/hr

0

500

1,000

1,500

2,000

2,500

3,000

0

200,000

400,000

600,000

800,000

1,000,000

1,200,000

1,400,000

1,600,000

1,800,000

2,000,000

Ap

r-0

8

No

v-0

8

Jun

-09

Jan

-10

Au

g-1

0

Mar

-11

Oct

-11

May

-12

Dec

-12

Jul-

13

Ore milled

Mill throughput rate (t/hr)

Data shown on a 100% equity basis.

Page 17: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Process plant performance: Cu recovery

Cu Recovery Cu Grade Scheduled ore head grades have

declined as primary ores are mined

and processed

Recoveries reflect the mix of ore

types processed

Transitional ores; metallurgical

complexity limits recovery rates

Higher recoveries achieved on

primary ore types

Current LOM average ore split:

~15% transitional, ~85% primary

0.0%

0.1%

0.2%

0.3%

0.4%

0.5%

0.6%

0.7%

0.8%

0.9%

1.0%

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

Ap

r-0

8

Oct

-08

Ap

r-0

9

Oct

-09

Ap

r-1

0

Oct

-10

Ap

r-1

1

Oct

-11

Ap

r-1

2

Oct

-12

Ap

r-1

3

Oct

-13

Copper recovery

Copper head grade

Page 18: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Typical Phu Kham concentrate

specification:

22% - 25% copper

5g/t - 8g/t gold

30g/t - 100g/t silver

<0.5% arsenic

Variability in output during steady-

state production largely reflects

head grade

Process plant performance: output

Tonnes

0

5,000

10,000

15,000

20,000

25,000

30,000

35,000

Ap

r-0

8

Oct

-08

Ap

r-0

9

Oct

-09

Ap

r-1

0

Oct

-10

Ap

r-1

1

Oct

-11

Ap

r-1

2

Oct

-12

Ap

r-1

3

Oct

-13

Conc produced

Page 19: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Concentrate marketing

Well positioned to supply custom smelters

in Southeast Asia

Copper-gold concentrate trucked to

Sriracha Harbour in Thailand or Vung Ang

in Vietnam for export; haulage cost

~US$95/t (Sriracha) ~US$87/t (Vung Ang)

Approximately 83% of planned sales to the

end of 2014 are under a mix of long term

and spot sales agreements with

internationally recognised traders and

smelters

Majority of current and next 3 years

production committed to contracts

Between 50% and 90% of the copper price

exposure hedged based on provisional

invoice pricing

Phu Kham to

Sriracha Harbour

~1,000km

Phu Kham to

Vung Ang

~630km

Page 20: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

On track to meet 2013 production of 62,000-

65,000t copper in concentrate at an average

C1 cash cost will approximate to the upper end

of guidance (US$1.35/lb)

Revised life of mine plan developed; copper

production to progressively increase to a peak

of around 90,000t in 2018 and 2019

Major capital phase now concluded: benefits

flowing from the expansion and increased

recovery projects together with lower scheduled

sustaining capital is expected to enhance cash

flow

Exploration upside in the Phu Kham district

provides the potential for additional sources of

mill feed

Phu Kham Outlook

Data shown on a 100% equity basis.

Page 21: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Ban Houayxai Operations, November 2013

Dr Jon Gaunt, General Manager

Page 22: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Safety performance – zero harm objective

Ban Houayxai Lag Indicator 12 Month Trends

12 Months from October 2012 to September 2013:

• LTIFR = 0.76

• TRIFR = 4.20

• AIFR = 8.78

Page 23: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Open pit mining operation feeding a

conventional 4Mtpa CIL / gravity gold plant

First gold-silver doré poured 1 May 2012;

commercial production from 1 June 2012

2013 production expected to be 110,000oz

gold at an average C1 cash costi of

US$600-US$650/oz after silver credits; total

cash cost (incl. royalty, sustaining capital

and lease and finance charges) US$863/oz

for 9 months to 30 Sep 2013

Mine life of over 10 years based on 2013

Ore Reserves estimate

Ban Houayxai Gold-Silver Operation

i: C1 direct operating costs, based on payable copper in concentrate produced, after precious metal

credits. Assumes DecH2013 silver price of US$20/oz.

Data shown on a 100% equity basis.

Page 24: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Ban Houayxai Gold-Silver Operation

Admin. Office Process Plant

Open Pit

Waste dump

To accommodation

camp

Page 25: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Production fleet comprises:

7 CAT777D 100t trucks

2 PC1250 from late November

Changing the PC2000 for a PC1250

Good contained metal reconciliation

between ore processed and the Ore

Reserve block model project to date:

-3% contained gold

-3% contained silver

+7% ore tonnes

Mining cost ~US$3.25/t - US$3.75/t

Zone of high-grade gold-silver

mineralisation extends beneath the

current open-pit design; potential target

for underground mining

Mine and ore body performance

Tonnes/month

0

200,000

400,000

600,000

800,000

1,000,000

1,200,000

Total material mined

Ore mined

Page 26: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Open pit current mining

Page 27: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

LOM strip ratio of ~1.7:1 based

on the 2013 Ore Reserve

Over the first six years of

mining the strip ratio is

expected to be approximately

1:1 rising to over 2:1 in the last

year of mine life commensurate

with a cut-back to access

deeper ore

Low-grade stockpiling strategy:

currently defined open pit

depleted after 7 years: low

grade stocks processed

thereafter

Minimal deferred mining costs

Open pit stages and strip ratios

Page 28: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

166

58

92

34 116

34

94

17

147 Labour

Fuel

Process power

Grinding media

Maintenance, mill liners and otherspares

Explosives

Reagents

Tyres

Other

Total on-site operating costs US758/oz gold (before credits)

Site costs for the 9 months to 30 Sep 2013

Page 29: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Design capacity of 4Mtpa; can be

exceeded on softer ores

Record processing rate achieved

in September quarter 2013:

equivalent to annualised rate of

4.9Mt

Focus on milling has delivered

15% improvement in mill

throughput for oxide and

transition ores against design

Processing cost ~US$9.00/t –

US$9.50/t

Minimal sustaining capital until

2016/17 when next TSF lift is

scheduled

Process plant performance: ore milled

Tonnes/month Tonnes/hr

0

100

200

300

400

500

600

700

0

50,000

100,000

150,000

200,000

250,000

300,000

350,000

400,000

450,000

Ore milled

Mill throughput rate (t/hr)

Data shown on a 100% equity basis.

Page 30: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Process plant performance: recovery rates

Recovery rates vary according to

ore type and grade

Recoveries of +90% for gold and

+70% for silver on oxide; c.85% for

gold and c.60% for silver on

transitional ore; gold recovery

75%-80% for harder primary ore

Project identified to evaluate

improved recovery on primary ore

Silver grade increasing with the

proportion of transitional and

primary ore; oxide ore is partly

silver depleted

2013/14 production predominantly

transitional ore types (60%)

0.0

0.2

0.4

0.6

0.8

1.0

1.2

1.4

0%

20%

40%

60%

80%

100%

Gold recovery

Gold head grade

0.0

2.0

4.0

6.0

8.0

10.0

0%

10%

20%

30%

40%

50%

60%

70%

Silver recovery

Silver head grade

Page 31: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Production profile reflects

increasing silver grades as the

proportion of transitional and

primary ores processed

increases

March 2013 production impacted

by SAG mill reline

Post-March soft oxide ore has

progressively been displaced by

harder transitional ore

Mine to mill program is delivering

mill throughput improvements to

offsets the change to harder ores

to maintain gold output

Process plant performance: output

Ounces/month

0

10,000

20,000

30,000

40,000

50,000

60,000

Gold in doré

Silver in doré

Data shown on a 100% equity basis.

SAG mill

reline

Page 32: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Additional information

Page 33: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

PanAust’s assets in Laos are held

by the Lao-registered entity Phu Bia

Mining Ltd (PanAust 90%)

2,600km2 Contract Area held under

a Mineral Exploration and

Production Agreement (“MEPA”):

sets out approvals process for

project development, operating

framework and fiscal regime – mine

development fast track

30-year tenure refreshed with each

new mine development

PanAust’s operations in Laos

Page 34: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Corporate tax rate of 25%

Royalty payment is based on metal prices - net smelter return royalty i.e.

off-site costs (transport, shipping, TC/RC’s etc) are deductable :

Copper:

• Up to US$3,000/t – 3%

• From US$3,000/t to US$4,000/t – 4%

• From US$4,000/t to US$5,000/t – 5%

• Above US$5,000/t – 6%

Gold

• Up to US$450/oz – 3%

• From US$450/oz to US$500/oz – 4%

• From US$500/oz to US$600/oz – 5%

• Above US$600/oz – 6%

Silver

• Royalty rate % is set by the gold rate

Fiscal regime

Page 35: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Mining cost 80

Deduct deferred mining costs (14)

Inventory adjustments (6)

Processing 87

General and Administration 24

Total mine site operating costs 171

Transport, Handling and Marketing 31

Concentrate treatment and refining 20

Total off-site operating costs 51

Precious metal credit (79)

Total direct operating costs (C1 cash cost) 144

Royalty 22

Sustaining capital (includes TSF) 33

Lease principal and interest charges 16

Total cash costs 214

Average copper price received (after realised hedging) 339

Phu Kham production costs; YTD Sep2013

Note: costs are based on payable copper in concentrate produced

US¢/lb copper

Page 36: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Mining 275

Deduct deferred mining costs -

Inventory adjustments (60)

Processing 398

General and Administration 145

Total mine site operating costs 758

Total off-site operating costs (freight, refining) 11

Silver credit (124)

Total Direct Operating Costs (C1 cash cost) 644

Royalty 96

Sustaining capital (includes TSF) 76

Lease principal and interest charges 48

Total cash costs 863

Average realised gold price (after hedging) 1,406

Ban Houayxai production costs; YTD Sep2013

US¢/oz gold

Page 37: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Ban Houayxai Process flow sheet

Page 38: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

PanAust’s commitment to sustainable development is a key consideration in

the way the Company undertakes its business activities and incorporates a

strong emphasis on delivering sustainable benefits to the communities within

the vicinity of its operations.

Further information on PanAust’s sustainability programs can be viewed at the

Company’s website www.panaust.com.au

Sustainability Report 2012: PanAust uses the reporting requirements of the

Global Reporting Initiative (GRI) G3, and reports to an A+ Application Level.

To achieve this rating the report has undergone external verification prior to

publication.

PanAust’s Sustainability Report and GRI index are available on PanAust’s

website at www.panaust.com.au/reports The 2012 Assurance Statement

provided by the external agency (ERM-Siam, Co Ltd) is incorporated into the

report.

Strong commitment to sustainable development

Page 39: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

March 2013: PanAust received the 2013 Sustainability Leadership Award at the Asia Mining

Congress in Singapore in recognition of PanAust’s program to create and support business

opportunities within the villages closest to the Company’s mining operations in Laos

Previously at the Asia Mining Congress, PanAust received awards for “Best Community

Development Initiative” in the Southeast Asia category for:

2011 – The positive contribution that PanAust’s Technical Trades program had made to

local communities and the greater Lao economy

2010 – PanAust’s Livelihood Improvement Programme designed to assist sustainable

development of the local communities

December 2011: PanAust received the Government of Lao PDR Labour Order Class 1

Award for the “best development in a rural area” for the Company’s outstanding contribution

to rural socio-economic development and poverty eradication

December 2011: PanAust received the Ethical Investor magazine 11th Sustainability Award

within the social and community category in recognition of the Company’s Livelihood

Improvement Program that is designed to assist the sustainable development of the

communities around the Phu Kham Copper-Gold Operation in Laos

Award winning sustainability performance

Page 40: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

PanAust provides a total of US$450,000

annually to the Community Development

Funds supporting the communities around

Phu Kham, Ban Houayxai and Phonsavan

Funding and support for: agriculture,

healthcare, infrastructure, and microfinance

and small business development

Phu Kham purchases almost 50% of its fresh

produce for the accommodation camp kitchen

from local communities

PanAust to partner with the Asian

Development Bank in a US$46.6M clean

water project to deliver clean water and better

sanitation facilities to residents of 11 towns in

Laos; PanAust will contribute a US$6M grant

over six years

Sustainable Development

Classroom sessions – market gardening and fish

farming

Around 50% of food requirements for the Phu Kham

camp is sourced locally

Page 41: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Approximately 3,370 employees; ~85% are

Lao nationals

Up-skilling of the Lao workforce; PanAust

has developed scholarship and

apprenticeship programs in conjunction with

colleges, universities and polytechnics in

Laos and Thailand

PanAust received the 2011 award for Best

Community Development Initiative at the Asia

Mining Congress in Singapore in recognition

of the positive contribution that PanAust’s

Technical Trades Training program is making

to local communities and the greater Lao

economy

Laos: employment and training

Page 42: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

Full provision for estimated closure costs is

recognised in PanAust accounts and

amortised over the life of the operation

US$53M provision as at 31 December 2012

Estimate is updated annually

Land rehabilitation

Page 43: Phu Kham Operations, November 2013 · 2013-11-04 · Sriracha Harbour ~1,000km Phu Kham to Vung Ang On track to meet 2013 production of 62,000-65,000t copper in concentrate at an

This presentation has been prepared by the management of PanAust Limited (the 'Company') for the benefit of brokers, analysts and

investors and not as specific advice to any particular party or person.

The information is based on publicly available information, internally developed data and other sources. No independent verification of

those sources has been undertaken and where any opinion is expressed in this document it is based on the assumptions and limitations

mentioned herein and is an expression of present opinion only. No warranties or representations can be made as to the origin, validity,

accuracy, completeness, currency or reliability of the information. The Company disclaims and excludes all liability (to the extent

permitted by law), for losses, claims, damages, demands, costs and expenses of whatever nature arising in any way out of or in

connection with the information, its accuracy, completeness or by reason of reliance by any person on any of it.

Where the Company expresses or implies an expectation or belief as to the success of future exploration and the economic viability of

future projects, such expectation or belief is based on management’s current predictions, assumptions and projections. However, such

forecasts are subject to risks, uncertainties and other factors which could cause actual results to differ materially from future results

expressed, projected or implied by such forecasts. Such risks include, but are not limited to, exploration success, gold and copper price

volatility, changes to the current mineral resource estimates, changes to assumptions for capital and operating costs as well as political

and operational risks and governmental regulation outcomes. For more detail of risks and other factors, refer to the Company's other

Australian Securities Exchange announcements and filings. The Company does not have any obligation to advise any person if it

becomes aware of any inaccuracy in, or omission from, any forecast or to update such forecast.

Important notice


Recommended