+ All Categories
Home > Documents > Pile Foundation FINAL

Pile Foundation FINAL

Date post: 08-Nov-2015
Category:
Upload: shobha
View: 100 times
Download: 12 times
Share this document with a friend
Description:
PILE FOUNDATION PROCESS AND ITS COMPONENTS.
Popular Tags:
38
PILE Foundations
Transcript
  • PILE Foundations

  • BORED PILE FOUNDATION

  • Step of Bored Pile Cycle time of each

    step

    ( hour)

    1. Set up location of

    Bored Pile

    0.3

    2. Inserting Casing 2

    3. Drilling 8

    4. Removing slime

    1

    5. KODEN Test

    1

    6. Inserting Steel

    Cage

    2

    7. Inserting Tremie

    Pipe

    1

    8. Pouring the

    concrete

    2

    9. Remove casing 1.5

    Total Cycle Time 18.8

    Bored Pile Procedure :

    1. Set up the Location of Bored

    Pile

    2. Insert Casing

    3. Drilling

    4. Removing Slime

    5. KODEN-Test

    6. Insert of Steel Cage

    7. Insert Tremie Pipe

    8. Pouring the Concrete

    9. Removing Casing

    10. Covering of Expose

    Concrete with a Pile Cap

  • BORED PILE FOUNDATION

    Total Station instrument are used to survey each pile point.

  • BORED PILE FOUNDATION

    Insert casing

    casing must be stand vertical

    by checking verticality of casing when insert casing

  • BORED PILE FOUNDATION

    use Vibrodriver or Vibrohamer to insert casing

  • BORED PILE FOUNDATION

    Drilling

    Drilling Machine :

    weight : 130tons

    BG - 40 drilling depth : 49m

    diameter : 3m

    weight : 96tons

    BG - 28 drilling depth : 39m

    diameter : 2.5m

    weight : 91tons

    SD - 515 drilling depth : 36m

    diameter : 2.5m

    BG - 40

    BG - 28

    SD - 515

  • BORED PILE FOUNDATION

    Removing slime

    when finish drilling , we use Mechanical pump equipment to remove slime .

  • BORED PILE FOUNDATION

    5. KODEN Test

    KODEN test utilizes the principle of ultrasonic wave travel from sensor to the wall of drilled hole and reflect to the sensor through the Bentonite slurry.

    Equipment KODEN equipment consists of two parts, recorder unit and winch unit .

    Recorder Unit Winch Unit

  • BORED PILE FOUNDATION

    Recorder unit controls the operation and record the test result. On the other hand, winch unit lowers the probe (sensor) down the hole for ultrasonic reflection .

    Testing Procedure

    1. Remove any obstacle around the hole area in order that the test equipment can access to the hole .

    2. Place the winch unit over the top of drilled hole or on the steel casing. Position the sensor (probe) at the center of the hole .

    3. Lower the sensor into Bentonite slurry. Hold the sensor at depth approximately 1 to 1.5m .

    4. Restore the sensor to the starting position and perform the test.

  • BORED PILE FOUNDATION

    Test Result

    Test results are presented in graphical plot and show characteristics

    below :

    1. Profile along two perpendicular axes.

    2. Average verticality of the hole.

    3. Location or depth where abnormality

    Occurs such as reduction in diameter,

    or collapsed wall of the hole.

    4. Depth of drilled hole.

  • BORED PILE FOUNDATION

    Insert of steel cage

  • BORED PILE FOUNDATION

    Insert Tremie

    Type of tremie pipe :

    We have 3 types of tremie : 1m, 2m and 3m

    Length

  • BORED PILE FOUNDATION

    How to insert tremie pipe :

    1. Use mobile crane to hang the hopper

    2. Then connect each tremie pipe

    3. After that put it into the bored pile

    hole

    until bottom

    When we pour concrete, we have to bury

    the tremie pipe into concrete as below :

    Diameter of Bored

    Pile

    Buried Length of

    Tremie

    1000 3 to 3.5m

    1800 2 to 2.5m

  • BORED PILE FOUNDATION

    Pouring the concrete

    Quality of Concrete :

    Max. size of Aggregate : 2.5cm Workability : 55cm ( Flow )

  • BORED PILE FOUNDATION

    Strength of concrete :

    Design strength : fck =300kg/cm ( 28days cure concrete )

    Material Strength

    Calculation of fck ( Mpa ) Strength of mix ( Mpa )

    Target Strength 21 > fck fck + 7

    ( Standard specifications of concrete ) 21 fck 35 fck + 8.5

    Strength of mix ( Target Strength )

    So, for Actual Concrete

    Strength : 400kg/cm

    fck 300kg/cm = 29.42 Mpa

    Strength of mix

    29.42 Mpa + 8.5 Mpa = 37.92 Mpa = 389

    kg/cm

    Apply : 400 kg/cm

  • BORED PILE FOUNDATION

    Remove casing

  • CASE STUDY - BORED PILE FOUNDATION IN METRO

  • CASE STUDY - BORED PILE FOUNDATION IN METRO

    Current METRO piling work at Ashram

  • CASE STUDY - BORED PILE FOUNDATION IN METRO

    Reinforcement Cage for Pile cap

  • CASE STUDY - BORED PILE FOUNDATION IN METRO

  • CASE STUDY - BORED PILE FOUNDATION IN METRO

  • CASE STUDY - BORED PILE FOUNDATION IN METRO

  • CASE STUDY - BORED PILE FOUNDATION IN METRO

  • CASE STUDY - BORED PILE FOUNDATION IN METRO

  • CASE STUDY - BORED PILE FOUNDATION IN METRO

  • CASE STUDY - BORED PILE FOUNDATION IN METRO

  • CASE STUDY - BORED PILE FOUNDATION IN METRO

  • CASE STUDY - BORED PILE FOUNDATION IN METRO

  • DIAPHRAGM WALLS

    Diaphragm Walls are particularly well suited to large open sites with deep

    excavations;

    they are most commonly built as cast in situ walls and have installed

    thicknesses ranging from 500mm to 1500mm.

    Cast in situ diaphragm walls are constructed as a series of primary and

    secondary panels varying in length from 2.8m to 7.5m to accommodate the

    geometry of the wall.

    Although shallower walls

    probably account for the

    majority of diaphragm walls

    installed;

    wall depths over 25 meters

    are almost the exclusive

    preserve of the system.

  • DIAPHRAGM WALLS

    Construction Sequence of

    Diaphragm wall

    Fixing of Alignment

    Stage-2: Guide wall Construction

    Stage-3: Trenching

    Stage-4: Trench Cleaning

    Stage-5: Stop ends fixing

    Stage-6: Reinforcement Cage

    lowering

    Stage-7: Placing of Concrete

    Stage-8: Withdrawal of Stop ends

  • DIAPHRAGM WALLS

    Where are wall pre-cast diaphragm walls used?

    Diaphragm Walls provide a very stiff, strong and cost effective solution for the construction of permanent retaining walls and shaft walls. This method of wall construction delivers far fewer construction joints than

    alternative systems such as bored pile or sheet pile walls.

    Applications for diaphragm walls include: retaining walls for deep basement excavations, cut-off barriers, retaining walls for cut and cover tunnels, quay walls and shaft walls.

  • DIAPHRAGM WALLS

  • CASE STUDY - DIAPHRAGM WALLS IN METRO

    Level of the bentonite slurry should be maintained

    preferably at least 1.5m above the ground water level

    to avoid problem of instability.

    Density and Viscosity of supporting fluid

    Loss of shear strength with time

    Suction effect during trenching

    Specification of Bentonite (as per IS:2911-Part1:Sec2

    Liquid limit : 300 to 450 % (in accordance with IS:2720-

    part V)

    Sand content : Less than 7 %

    Density: 1.12

    Marsh viscosity : About 37 second, tested by Marsh

    cone

    Swelling index: Swelling index at least 2 times of dry

    volume.

    pH value : Less than 11.5

    Tests and compliance values for support fluid prepared

    from bentonite (as per IS9556-1980)

  • CASE STUDY - DIAPHRAGM WALLS IN METRO

  • CASE STUDY - DIAPHRAGM WALLS IN METRO

  • THANK YOU


Recommended