Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 1 of 39
PTT Public Company Limited
Document No.
RP-50-2004.02-3700-01
Piping Site Survey Report
GSP7 Interconnecting pipeline Project
D3 ISSUED FOR ITB WPS SND MKP 17 MAR 21
D2 ISSUED FOR ITB WPS SND SOJ 15 MAR 21
D1 ISSUED FOR ITB WPS SND SOJ 13 MAR 21
REV. DESCRIPTION Prepared by Checked
by Approved by
Quality reviewed by
Issued date
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 2 of 39
1.0 PROPOSE
1.The purpose of site survey are verifying and confirm pipe routing for GSP7 Interconnecting area. 2.To conceptual design for pipe routes which was sketched by visual
2.0 DEFINITIONS
OWNER PTT, PTT Public Company Limited Project No. 2004.02 Subject. Piping Site Survey Report for GSP7 Interconnecting pipeline Project (GSP7 ICP) Referent Drawing: Pipe route study for interconnecting area DWG No. 56-0-2004.02-3700-001 to 012
3.0 RESULT
All pipe route sketches are show in detail page.
4.0 CONCLUSION
This is Preliminary Study and Recommendation for CONTRACTOR to consider in conjunction with EFT, IEAT and other area owner requirement, permit to work, etc. CONTRACTOR shall coordinate with all related organization to finalize all pipe routing, pipe rack, structural steel, concrete and foundation design during detailed engineering.”
5.0 OTHER
N/A
6.0 ATTACHMENT
N/A
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 3 of 39
GSP7 Interconnecting for GSP Area
LINE COLOR:
3701-P-07001-28-D3138-N (Feed gas)
3706-P-05018-24-D6138-N (Sales gas)
3703-P-02002-18-D3138-N (Ethane)
3705-P-04017-10-D3134-N (LPG)
3705-P-02012-8-D3134-N (Propane)
3705-P-06013-4-D1134-N (NGL) JET A-1-16 (For future)
JET A-1-1 (For future)
New Support / Structure New Support / Structure (By BIG)
AREA: A AREA: B
AREA: C
AREA: D
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 4 of 39
GSP7 Interconnecting for Pipeline Area
PTT GSP7
AREA: E
AREA: F
AREA: G
AREA: H
EFT Pipe rack
EFT Pipe rack
Rayong Pipeline
สทร
AREA: F
AREA: H
AR
EA
: G
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 5 of 39
AREA: A • Install Line No. 3706-P-05018-24-D6138-N (SALES GAS)
• Tie in No. 2004.02-3700-051-02-1, 2004.02-3700-051-02-2, 2004.02-3700-051-02-3
• Install new layer pipe rack
2004.02
3700-051
02-1
2004.02
3700-051
02-2
2004.02
3700-051
02-3
Install new layer on pipe rack
METERING FOR SALES GAS
(3706-Y-001, R)
2004.02
3700-051
02-1
2004.02
3700-051
02-2
2004.02
3700-051
02-3
PIG Station
METERING SKID AND PIG RECEIVER AREA FOR SALE GAS
1
1
LOOKING: SOUTH
LOOKING: PLAN
N
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 6 of 39
AREA: A (Cont.)
• Install Line No. 3701-P-07001-28-D3138-N (FEED GAS)
• Tie in No. 2004.02-3700-051-01-1, 2004.02-3700-051-01-2, 2004.02-3700-051-01-3
• Install new pipe bridge and new layer pipe rack
Install new pipe bridge
2004.02
3700-051
01-1
2004.02
3700-051
01-2
2004.02
3700-051
01-3
Install new layer on pipe rack
PIG RECEIVER AREA FOR FEED GAS
2
2
3
LOOKING: NORTH
LOOKING: SOUTH-EAST
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 7 of 39
AREA: B • Install Line No. 3701-P-07001-28-D3138-N (Feed gas)
• Install Line No. 3706-P-05018-24-D6138-N (Sales gas)
• Install Line No. 3703-P-02002-18-D3138-N (Ethane)
• Install Line No. 3705-P-04017-10-D3134-N (LPG)
• Install Line No. 3705-P-02012-8-D3134-N (Propane)
• Install Line No. 3705-P-06013-4-D1134-N (NGL) • Install new pipe rack
Install new pipe rack
Install new layer on pipe rack
Structure bracing shall modify for new pipe
2004.02
3700-051
02-4
7
4
LOOKING: SOUTH
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 8 of 39
AREA: B (Cont.) Install Line No. 3701-P-07001-28-D3138-N (Feed gas) Install Line No. 3706-P-05018-24-D6138-N (Sales gas) Install Line No. 3703-P-02002-18-D3138-N (Ethane) Install Line No. 3705-P-04017-10-D3134-N (LPG) Install Line No. 3705-P-02012-8-D3134-N (Propane) Install Line No. 3705-P-06013-4-D1134-N (NGL) Install new pipe rack
Install new pipe rack
Install new layer on pipe rack
-To be verify underground before detail design -Consider re-routing u-ditch -Excavation soil & concrete -To provide concrete wall
Install new layer on pipe rack
2004.02
3700-051
02-4
LOOKING: PLAN
4
7
5
N
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 9 of 39
AREA: C
• Install Line No. 3703-P-02002-18-D3138-N (Ethane)
• Install Line No. 3705-P-04017-10-D3134-N (LPG)
• Install Line No. 3705-P-02012-8-D3134-N (Propane)
• Install Line No. 3705-P-06013-4-D1134-N (NGL) • Install new pipe rack and pipe bridge
- Install new pipe rack and pipe bridge (EL same as existing pipe bridge) - To provide future access way
METERING SKID AND PIG RECEIVER AREA FOR ETHANE, PROPANE, LNG AND NGL
Install new layer on pipe rack (H = 2 m)
2004.02
3700-051
03-1 to 3
2004.02
3700-051 04-1 to 5
2004.02
3700-051 05-1 to 3
2004.02
3700-051 06-1 to 5
5
5
LOOKING: WEST
LOOKING: WEST
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 10 of 39
AREA:D
• Add new layer of existing pipe rack.
• 3706-P-05018-24-D6138-N (Sales gas)
• 3701-P-07001-28-D3138-N (Feed gas)
Add New layer of existing pipe rack
To used existing pipe bridge
Add New pipe bridge
Concern Existing Transformer station
Add New layer of existing pipe rack
1
LOOKING: NORTH
6
6
3
7
LOOKING: SOUTH
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 11 of 39
AREA:D (Cont.) • Add new layer of existing pipe rack.
• 3706-P-05018-24-D6138-N (Sales gas)
• 3703-P-02002-18-D3138-N (Ethane)
• 3705-P-06013-4-D1134-N (NGL)
• 3705-P-02012-8-D3134-N (Propane) • 3705-P-04017-10-D3134-N (LPG)
• 3701-P-07001-28-D3138-N (Feed gas)
Add New layer of existing pipe rack
To use existing pipe rack
7
4
LOOKING: SOUTH-WEST
LOOKING: NORTH
8
8
9
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 12 of 39
AREA:D (Cont.)
Add New layer of existing pipe rack
9
10
LOOKING: NORTH-WEST
LOOKING: NORTH-WEST
10
11
9
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 13 of 39
AREA:D (Cont.)
Add New layer of existing pipe rack
Add New layer of existing pipe rack
LOOKING: SOUTH
LOOKING: NORTH
11
12
12
13
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 14 of 39
AREA:D (Cont.)
Add New layer of existing pipe rack
13 14
LOOKING: SOUTH
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 15 of 39
AREA: E
3701-P-07001-28-D3138-N (Feed gas)
3706-P-05018-24-D6138-N (Sales gas)
3703-P-02002-18-D3138-N (Ethane)
3705-P-04017-10-D3134-N (LPG)
3705-P-02012-8-D3134-N (Propane)
3705-P-06013-4-D1134-N (NGL) JET A-1-16 (For future)
PIPE BRIDGE PTT-09
USE EXISTING PIPE BRIDGE
LOOKING: EAST
Add New layer of existing pipe rack
14
15
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 16 of 39
AREA: E (Cont.)
PIPE BRIDGE PTT-07
PIPE BRIDGE PTT-08
USE EXISTING PIPE BRIDGE
USE EXISTING PIPE BRIDGE
15
16
LOOKING: NORTH-EAST
LOOKING: SOUTH-EAST
Add New layer of existing pipe rack
16 17
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 17 of 39
AREA: E (Cont.)
USE EXISTING PIPE BRIDGE
USE EXISTING PIPE BRIDGE
PIPE BRIDGE PTT-07
PIPE BRIDGE PTT-06
PIPE BRIDGE PTT-05
Add new layer of pipe rack
17
18
LOOKING: NORTH
LOOKING: SOUTH- EAST
18
19
16
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 18 of 39
AREA: E (Cont.)
PIPE BRIDGE PTT-05
PIPE BRIDGE PTT-04
PIPE BRIDGE PTT-05
USE EXISTING PIPE BRIDGE
USE EXISTING PIPE BRIDGE
LOOKING: EAST
19
20
21
20
LOOKING: NORTH
19
USE EXISTING PIPE RACK
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 19 of 39
AREA: E (Cont.)
PIPE BRIDGE PTT-03 USE EXISTING PIPE BRIDGE
USE EXISTING PIPE RACK
USE EXISTING PIPE RACK
LOOKING: SOUTH
LOOKING: NORTH
21
22
22
23
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 20 of 39
AREA: E (Cont.)
USE EXISTING PIPE RACK
USE EXISTING PIPE RACK
BOX CULVERT PTT-CX-1
23
24
24
25
LOOKING: SOUTH
LOOKING: NORTH-EAST
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 21 of 39
AREA: E (Cont.)
New Pipe bridge PD-GSP7-BX-7
USE EXISTING PIPE BRIDGE
PIPE BRIDGE PTT-02
PIPE BRIDGE PTT-02
BOX CULVERT PTT-CX-1
PIPE BRIDGE PTT-BX-3
USE EXISTING PIPE BRIDGE
25
26
26
LOOKING: NORTH
LOOKING: WEST
27
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 22 of 39
AREA: F
3701-P-07001-28-D3138-N (Feed gas)
3706-P-05018-24-D6138-N (Sales gas)
3703-P-02002-18-D3138-N (Ethane)
3705-P-04017-10-D3134-N (LPG)
3705-P-02012-8-D3134-N (Propane)
3705-P-06013-4-D1134-N (NGL)
JET A-1-10 (For future)
Limit IEAT property
New Pipe Bridge PD-GSP7-BX-6
27
LOOKING: EAST
LOOKING: WEST
28
28
29
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 23 of 39
AREA: F (Cont.)
NEW PIPE BRIDGE I1-GSP7-BX-5
29
30
LOOKING: WEST
LOOKING: NORTH-WEST
Add new layer of existing pipe rack
29
30
28
New Pipe Bridge PD-GSP7-BX-6
31
NEW PIPE BRIDGE I1-GSP7-BX-5
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 24 of 39
AREA: F (Cont.)
NEW PIPE BRIDGE I2-GSP-BX-4
31
32
32
33
LOOKING: EAST
LOOKING: EAST
Add new layer of existing pipe rack
Add new layer of existing pipe rack
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 25 of 39
AREA: F (Cont.)
NEW PIPE BRIDGE I2-GSP7-BX-3
NEW PIPE BRIDGE I2-GSP-BX-4
NEW PIPE RACK
LOOKING: EAST
33
34
34 35
LOOKING: EAST
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 26 of 39
AREA: F (Cont.)
NEW PIPE RACK
NEW PIPE BRIDGE I2-GSP7-BX-2
LOOKING: EAST
35
36
36
37
LOOKING: NORTH
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 27 of 39
AREA: F (Cont.)
PIPE BRIDGE I2-BX-4
37
38
LOOKING: EAST
NEW PIPE RACK
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 28 of 39
AREA: G
3701-P-07001-28-D3138-N (Feed gas)
3706-P-05018-24-D6138-N (Sales gas)
3703-P-02002-18-D3138-N (Ethane)
3705-P-04017-10-D3134-N (LPG)
3705-P-02012-8-D3134-N (Propane)
3705-P-06013-4-D1134-N (NGL)
JET A-1-10 (For future)
PIPE BRIDGE I2-BX-4
LOOKING: NORTH-WEST
38
39 Add new layer of pipe rack
37
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 29 of 39
AREA: G (Cont.)
C
PIPE BRIDGE I7-BX-1
PIPE BRIDGE I7-BX-2
LOOKING: NORTH-WEST
39
40
40
41
LOOKING: SOUTH-WEST
Add new layer of pipe rack
Add new layer of pipe bridge
Add new layer of pipe bridge
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 30 of 39
AREA: G (Cont.)
PIPE BRIDGE I7-BX-3
PIPE BRIDGE I7-BX-4
LOOKING: SOUTH
41
42
42
43
LOOKING: NORTH-WEST
Add new layer of pipe bridge
Add new layer of pipe rack
Add new layer of pipe bridge
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 31 of 39
AREA: G (Cont.)
PIPE BRIDGE I8-BX-12
LOOKING: WEST
43
44
44 45
LOOKING: WEST
Add new layer of pipe rack
Add new layer of pipe rack Add new layer of pipe rack
Add new layer of pipe bridge
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 32 of 39
AREA: G (Cont.)
PIPE BRIDGE I8-BX-16
LOOKING: SOUTH
46
47
Add new layer of pipe bridge
Add 2 layer of pipe rack
PIPE BRIDGE I8-BX-13
45
46
LOOKING: SOUTH-WEST
Add new layer of pipe bridge
Add new layer of pipe rack
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 33 of 39
AREA: G (Cont.)
LOOKING: SOUTH
47
48
Add 2 layer of pipe rack
PIPE BRIDGE I8-BX-19
LOOKING: SOUTH
Add 2 layer of pipe rack
Add new layer of pipe bridge 48
49
50
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 34 of 39
AREA: G (Cont.)
PIPE BRIDGE I8-BX-20
50 51
LOOKING: SOUTH
Add 2 layer of pipe rack
Add new layer of pipe bridge
52
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 35 of 39
AREA: G (Cont.)
PIPE BRIDGE I8-BX-21
LOOKING: NORTH
51
53
Add new layer of pipe bridge
Add new layer of pipe rack
52
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 36 of 39
AREA: G (Cont.)
53
54
LOOKING: SOUTH
Add new layer of pipe rack
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 37 of 39
AREA: H
• Install Line No. 3706-P-07001-28-D3138-N (Sales gas)
• Install Line No. 3706-P-05018-24-D6138-N (Sales gas)
• Install Line No. 3703-P-02002-18-D3138-N (Ethane)
• Install Line No. 3705-P-04017-10-D3134-N (LPG)
• Install Line No. 3705-P-02012-8-D3134-N (Propane)
• Install Line No. 3705-P-06013-4-D1134-N (NGL
• Pipe rack to be provided by BIG
• Pipe rack to be provided by GSP7 Project
54
LOOKING: PLAN
N
Pipe rack to be provided by BIG
55
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 38 of 39
AREA: H (Cont.)
55
56
LOOKING: PLAN
N
Pipe rack to be provided by BIG
Piping Site Survey Report
Doc No : RP-50-2004.02-3700-01
Rev : D3
Page : 39 of 39
AREA: H (Cont.)
56 57
LOOKING: PLAN
N
METERING STATION
Pipe rack to be provided by BIG
Pipe rack to be provided by GSP7 project
New pipe bridge
2004.02
3700-054
01-1 to 3
2004.02
3700-054
02-1 to 3
2004.02
3700-054
03-1 to 3
2004.02
3700-054
04-1 to 5
2004.02
3700-054
05-1 to 5
2004.02
3700-054
06-1 to 5
Pipe rack to be provided by GSP7 Interconnecting pipeline
New pipe bridge
Pipe rack to be provided by GSP7 Interconnecting pipeline