TIER 1 PROJECT AND BRIDGE STANDARDS, 2009 MUTCD, 2011 VIRGINIA SUPPLEMENT TO AMENDED BY CONTRACT PROVISIONS AND THE COMPLETE ELECTRONIC PDF VERSION OF THE PLAN ASSEMBLY. THE MUTCD, 2011 VIRGINIA WORK AREA PROTECTION MANUAL AND AS DEPARTMENT'S 2016 ROAD AND BRIDGE SPECIFICATIONS, 2016 ROAD COUNTY LINE DHV V (MPH) REVISED STATE LINE CITY,TOWN OR VILLAGE RIGHT OF WAY LINE FENCE LINE UNFENCED PROPERTY LINE FENCED PROPERTY LINE WATER LINE SANITARY SEWER LINE GAS LINE ELECTRIC UNDERGROUND CABLE TRAVELED WAY GUARD RAIL RETAINING WALL RAILROADS BASE OR SURVEY LINE LEVEE OR EMBANKMENT BRIDGES CULVERTS DROP INLET POWER POLES TELEPHONE OR TELEGRAPH POLES TELEPHONE OR TELEGRAPH LINES HEDGE TREES HEAVY WOODS GROUND ELEVATION GRADE ELEVATION CONVENTIONAL SIGNS 30 30+ 50 DATUM LINE DATUM LINE 173 175 T/Tg E 6" W 8" S 4" G P L P L DEPARTMENT OF TRANSPORTATION PLAN AND PROFILE OF PROPOSED STATE HIGHWAY Fr: To: SCALE FUNCTIONAL CLASSIFICATION AND TRAFFIC DATA D (%) (design hour) T (%) (design hour) WHERE OTHERWISE NOTED. THE ORIGINAL APPROVED TITLE SHEET(S), INCLUDING ORIGINAL SIGNATURES, ARE FILED IN THE VDOT CENTRAL OFFICE PLAN LIBRARY. ANY MISUSE OF ELECTRONIC FILES, INCLUDING SCANNED SIGNATURES, IS ILLEGAL AND ENFORCED TO THE FULL EXTENT OF THE LAW. ALL CURVES ARE TO BE SUPERELEVATED, TRANSITIONED AND WIDENED IN ACCORDANCE WITH STANDARD TC-5.11U, EXCEPT DESIGN FEATURES RELATING TO CONSTRUCTION OR TO REGULATION AND CONTROL OF TRAFFIC MAY BE SUBJECT TO CHANGE AS DEEMED NECESSARY BY THE DEPARTMENT. THIS PROJECT IS TO BE CONSTRUCTED IN ACCORDANCE WITH THE FOR SECTION NUMBERS) (SEE TABULATION BELOW 674-029-358 SIGNATURES AND THE OFFICIAL PLAN ASSEMBLY IN ELECTRONIC AS AWARDED, HAS BEEN SEALED AND SIGNED USING DIGITAL FORMAT IS STORED IN THE VDOT CENTRAL OFFICE PLAN LIBRARY, INCLUDING ALL SUBSEQUENT REVISIONS, WILL BE THE OFFICIAL CONSTRUCTION PLANS. FOR INFORMATION RELATIVE TO ELECTRONIC FILES AND LAYERED PLANS, SEE THE GENERAL NOTES. THE COMPLETE ELECTRONIC PDF VERSION OF THE PLAN ASSEMBLY 0 100 200 GEOPAK Computer Identification No. 110433 DESIGN PACKAGE (GEOPAK). THIS PROJECT WAS DEVELOPED UTILIZING THE DEPARTMENT'S ENGINEERING R i ce a nd A ss o c i a t e s ( 703 ) 968 - 3200 R i ce a nd A ss o c i a t e s ( 703 ) 968 - 3200 674 SECTION 110499 N/A 0.168 0.175 Prelim. Engr. STATE PROJECT NO. SECTION EQUALITIES FEET LENGTH INCLUDING FEDERAL AID PROJECT NO. FEET FEET MILES MILES LENGTH EXCLUDING TYPE PROJECT DESCRIPTION BRIDGE(S) BRIDGE(S) TYPE CODE UPC NO. BRIDGE NO. 0674- 029- 358 PLAN P-101 ADT (2015) ADT (2043) - - Br i a n G r a h a m ( V o l k e r t ) ( 703 ) 642 - 8100 885.00 925.00 * DESIGN SPEEDS. HORIZONTAL AND VERTICAL CURVE * SEE PLAN AND PROFILE SHEETS FOR FAIRFAX COUNTY Project Lengths are based on Hunter Mill Road (Route 674) Construction Baseline. 3 4 1 APPROVED FOR CONSTRUCTION DISTRICT PLANNING AND INVESTMENT MANAGER FOR CONSTRUCTION DISTRICT PLANNING AND INVESTMENT MANAGER DISTRICT PROJECT DEVELOPMENT ENGINEER DISTRICT PROJECT DEVELOPMENT ENGINEER SURV E Y E D BY ,DATE DE SI GN BY SUBSURF ACE UTI L I TY BY ,DATE STATE FEDERAL AID STATE PROJECT PROJECT ROUTE VA. PROJECT SHEET NO. V I R G I N I A S I C S E M P E R T Y R A N N I S SHEET NO. COMMONWEALTH OF VIRGINIA Copyright 2020, Commonwealth of Virginia FOR INDEX OF SHEETS SEE SHEET 1B d11049901.dgn Plotted By: brenda.duong 9:16:14 AM 6/26/2020 1 PRO J E CT M ANAGE R DATE DATE DATE RECOMMENDED FOR APPROVAL DATE APPROVED FOR RIGHT OF WAY ACQUISITION DATE DATE RECOMMENDED FOR APPROVAL FOR RIGHT OF WAY ACQUISITION DISTRICT ENGINEER/ADMINISTRATOR DISTRICT ENGINEER/ADMINISTRATOR OVER COLVIN RUN HUNTER MILL ROAD (ROUTE 674) BRIDGE REPLACEMENT TO: 0.087 MILES NORTH OF COLVIN RUN FROM: 0.098 MILES SOUTH OF COLVIN RUN From: 0.098 Mi. South of Colvin Run To: 0.087 Mi. North of Colvin Run THESE PLANS ARE UNFINISHED AND UNAPPROVED AND ARE NOT TO BE USED FOR ANY TYPE OF CONSTRUCTION OR THE ACQUISITION OF RIGHT OF WAY. P. H. PLANS 0.098 MILES SOUTH OF COLVIN RUN 0.087 MILES NORTH OF COLVIN RUN S t a . 102 + 00 . 00 S t a . 111 + 25 . 00 V i ce n t e S . V a l eza , J r ., P . E . ( 703 ) 259 - 3256 ( NOVA ) R ou t e 606 T o ll R o a d T o D u ll e s A cce ss R t e . 674 H un t e r M ill R o a d B-643 Rte. 674 Bridge over Colvin Run Bridge - - 110433 N/A 40.00 0.010 S t a . 1 06 + 85 . 00 S t a . 1 06 + 45 . 0 0 B - 643 101 105 1 1 0 11,000 8,000 - Fairfax County Population 1,081,726 (2010 Census) CONFORMING TO S&B-IIM-70.9 NOTE: THESE PLANS WERE DESIGNED FOR A SMALL BRIDGE REPLACEMENT PROJECT FHWA 534 DATA 44010 (NFO) 0674-029-358 STP-BR09(295) STP-BR09(295) STP-BR09(295) PROJ. 0674-029-358, P-101 Co l v i n Run Co l v i n Run S t r e a m C o l v i n Ru n DESCRIPTION REFERENCE POT. Sta. 106+65.00 Rte. 674
Transcript
  • TIER 1 PROJECT

    AND BRIDGE STANDARDS, 2009 MUTCD, 2011 VIRGINIA SUPPLEMENT TO

    AMENDED BY CONTRACT PROVISIONS AND THE COMPLETE ELECTRONIC

    PDF VERSION OF THE PLAN ASSEMBLY.

    THE MUTCD, 2011 VIRGINIA WORK AREA PROTECTION MANUAL AND AS

    DEPARTMENT'S 2016 ROAD AND BRIDGE SPECIFICATIONS, 2016 ROAD

    COUNTY LINE

    DHV

    V (MPH)

    REVISED

    STATE LINE

    CITY,TOWN OR VILLAGERIGHT OF WAY LINEFENCE LINEUNFENCED PROPERTY LINEFENCED PROPERTY LINEWATER LINESANITARY SEWER LINEGAS LINEELECTRIC UNDERGROUND CABLETRAVELED WAYGUARD RAILRETAINING WALLRAILROADSBASE OR SURVEY LINE

    LEVEE OR EMBANKMENTBRIDGESCULVERTSDROP INLETPOWER POLESTELEPHONE OR TELEGRAPH POLESTELEPHONE OR TELEGRAPH LINESHEDGETREESHEAVY WOODSGROUND ELEVATIONGRADE ELEVATION

    CONVENTIONAL SIGNS

    30

    30

    +50

    DATUM LINE

    DATUM LINE

    173

    175

    T/Tg

    E

    6" W

    8" S

    4" G

    PLPL

    DEPARTMENT OF TRANSPORTATION

    PLAN AND PROFILE OF PROPOSED

    STATE HIGHWAY

    Fr:

    To:

    SCALE

    FUNCTIONAL CLASSIFICATION AND TRAFFIC DATA

    D (%) (design hour)

    T (%) (design hour)

    WHERE OTHERWISE NOTED.

    THE ORIGINAL APPROVED TITLE SHEET(S), INCLUDING ORIGINAL

    SIGNATURES, ARE FILED IN THE VDOT CENTRAL OFFICE PLAN LIBRARY.

    ANY MISUSE OF ELECTRONIC FILES, INCLUDING SCANNED SIGNATURES,

    IS ILLEGAL AND ENFORCED TO THE FULL EXTENT OF THE LAW.

    ALL CURVES ARE TO BE SUPERELEVATED, TRANSITIONED AND

    WIDENED IN ACCORDANCE WITH STANDARD TC-5.11U, EXCEPT

    DESIGN FEATURES RELATING TO CONSTRUCTION OR TO REGULATION

    AND CONTROL OF TRAFFIC MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT.

    THIS PROJECT IS TO BE CONSTRUCTED IN ACCORDANCE WITH THE

    FOR SECTION NUMBERS)

    (SEE TABULATION BELOW

    674-029-358

    Cell Revised 6/10/16

    SIGNATURES AND THE OFFICIAL PLAN ASSEMBLY IN ELECTRONIC

    AS AWARDED, HAS BEEN SEALED AND SIGNED USING DIGITAL

    FORMAT IS STORED IN THE VDOT CENTRAL OFFICE PLAN LIBRARY,

    INCLUDING ALL SUBSEQUENT REVISIONS, WILL BE THE OFFICIAL

    CONSTRUCTION PLANS. FOR INFORMATION RELATIVE TO ELECTRONIC

    FILES AND LAYERED PLANS, SEE THE GENERAL NOTES.

    THE COMPLETE ELECTRONIC PDF VERSION OF THE PLAN ASSEMBLY

    0 100 200

    GEOPAK Computer Identification No. 110433

    DESIGN PACKAGE (GEOPAK).

    THIS PROJECT WAS DEVELOPED UTILIZING THE DEPARTMENT'S ENGINEERINGRic

    e and

    Associates (7

    03) 968-3

    200

    Ric

    e and

    Associates (7

    03) 968-3

    200

    674

    SECTION

    110499 N/A 0.1680.175 Prelim. Engr.

    STATE

    PROJECT

    NO.

    SECTIONEQUALITIES

    FEET

    LENGTH INCLUDINGFEDERAL AID

    PROJECT NO.FEET FEETMILES MILES

    LENGTH EXCLUDINGTYPE

    PROJECTDESCRIPTIONBRIDGE(S) BRIDGE(S)

    TYPE

    CODE

    UPC

    NO.

    BRIDGE

    NO.

    067

    4-029-358

    PLAN

    P-101

    ADT (2015)

    ADT (2043)

    -

    -

    Bria

    n

    Graha

    m (V

    olkert) (7

    03) 642-8

    100

    885.00925.00

    *

    DESIGN SPEEDS.

    HORIZONTAL AND VERTICAL CURVE

    * SEE PLAN AND PROFILE SHEETS FOR

    FAIRFAX COUNTY

    Project Lengths are based on Hunter Mill Road (Route 674) Construction Baseline.

    3 4

    1

    APPROVED FOR CONSTRUCTION

    DISTRICT PLANNING AND INVESTMENT MANAGER

    FOR CONSTRUCTION

    DISTRICT PLANNING AND INVESTMENT MANAGER

    DISTRICT PROJECT DEVELOPMENT ENGINEER

    DISTRICT PROJECT DEVELOPMENT ENGINEER

    SU

    RV

    EY

    ED

    BY,

    DA

    TE

    DE

    SIG

    N

    BY

    SU

    BS

    UR

    FA

    CE

    UTILIT

    Y

    BY,

    DA

    TE

    STATEFEDERAL AID STATE

    PROJECT PROJECTROUTE

    VA.

    PROJECT SHEET NO.

    VIRGINIA

    SIC SEMPER TYRANNIS

    SHEET

    NO.

    COMMONWEALTH OF VIRGINIA

    Copyright 2020, Commonwealth of Virginia

    FOR INDEX OF SHEETS SEE SHEET 1B

    d11049901.dgn

    Plotted By: brenda.duong

    9:16:14 AM

    6/26/2020

    1P

    ROJE

    CT

    MA

    NA

    GE

    R

    DATE

    DATE

    DATE

    RECOMMENDED FOR APPROVAL

    DATE

    APPROVED FOR RIGHT OF WAY ACQUISITION

    DATE

    DATE

    RECOMMENDED FOR APPROVAL

    FOR RIGHT OF WAY ACQUISITION

    DISTRICT ENGINEER/ADMINISTRATOR

    DISTRICT ENGINEER/ADMINISTRATOR

    OVER COLVIN RUN

    HUNTER MILL ROAD (ROUTE 674) BRIDGE REPLACEMENT

    TO: 0.087 MILES NORTH OF COLVIN RUN

    FROM: 0.098 MILES SOUTH OF COLVIN RUN

    From: 0.098 Mi. South of Colvin Run

    To: 0.087 Mi. North of Colvin Run

    THESE PLANS ARE UNFINISHED

    AND UNAPPROVED AND ARE NOT

    TO BE USED FOR ANY TYPE

    OF CONSTRUCTION OR THE

    ACQUISITION OF RIGHT OF WAY.

    P. H. PLANS

    0.098 MILES SOUTH OF COLVIN RUN

    0.087 MILES NORTH OF COLVIN RUN

    Sta. 102

    +00.0

    0

    Sta. 111+2

    5.0

    0

    Vic

    ente S. V

    aleza, Jr., P.E. (7

    03)2

    59-3

    256 (N

    OV

    A)

    Route 606

    Toll RoadTo Dulles Acc

    ess

    Rte. 674

    Hunter Mill Road

    B-643 Rte. 674 Bridge over Colvin RunBridge- -110433 N/A 40.00 0.010

    Sta. 106+8

    5.0

    0

    Sta. 106+4

    5.0

    0

    B-643

    101

    105

    110

    11,000

    8,000

    -

    Fairfax County Population 1,081,726 (2010 Census)

    CONFORMING TO S&B-IIM-70.9

    NOTE: THESE PLANS WERE DESIGNED FOR A SMALL BRIDGE REPLACEMENT PROJECT

    FHWA 534 DATA 44010 (NFO) 0674-029-358

    STP-BR09(295)

    STP-BR09(295)

    STP-BR09(295)

    PROJ. 0674-029-358, P-101

    Colvin Run

    Colvin Run

    Stream

    Colvin Run

    DESCRIPTION REFERENCE

    POT. Sta. 106+65.00 Rte. 674

  • 1A

    1A

    THESE PLANS ARE UNFINISHED

    AND UNAPPROVED AND ARE NOT

    TO BE USED FOR ANY TYPE

    OF CONSTRUCTION OR THE

    ACQUISITION OF RIGHT OF WAY.

    P. H. PLANS

    SCALE

    0 0.5M 1M

    ST

    A.

    111+25.0

    0

    ST

    A.

    102

    +00.0

    0

    LOCATION MAPFAIRFAX COUNTY

    P101

    0674-029-358

    PROPOSED PROJECT

    2010 Census

    Population 1,081,726

    Fairfax County

    VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    d11049901a.dgn

    Plotted By: brenda.duong9:16:27 AM

    6/26/2020

    PROJECT SHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    674

    0674-029-358

    Brian Graham P.E. (703) 642-8100 (Volkert, Inc.)

    NO

    VA

    DIS

    TRIC

    T

    DE

    SIG

    N

    UNIT

    (703) 259-3256 (NOVA) Vicente S. Valeza, Jr., P.E.

    VDOT

    VDOT

    P101, B643

    0674-029-358

  • 1B

    1B

    THESE PLANS ARE UNFINISHED

    AND UNAPPROVED AND ARE NOT

    TO BE USED FOR ANY TYPE

    OF CONSTRUCTION OR THE

    ACQUISITION OF RIGHT OF WAY.

    P. H. PLANS

    TITLE SHEET

    TYPICAL SECTIONS

    DESCRIPTIONSHEET NO.

    1A

    4, 4A

    2A

    GENERAL NOTES

    STATIONS

    EROSION AND SEDIMENT CONTROL PLAN

    1

    PLAN AND PROFILE SHEETS HUNTER MILL RD. 100+00.00 to 107+25.00

    PLAN AND PROFILE SHEETS HUNTER MILL RD.

    INDEX OF SHEETS

    1B INDEX OF SHEETS

    SIGNING AND PAVEMENT MARKING PLANS

    1G - 1G(1)

    3, 3A, 3A(1)

    107+25.00 to 111+49.32

    SWPPP2C - 2C(3)

    2D - 2E(1)

    GEOMETRIC LAYOUT / CONSTRUCTION ALIGNMENT DATA SHEET

    TOTAL CROSS SECTION SHEETS 13 (SEE CROSS SECTION SHEET NUMBER 1 FOR INDEX OF SHEETS)

    1F SURVEY ALIGNMENT DATA SHEET

    MAINTENANCE OF TRAFFIC PLAN1K - 1K(4)

    2*

    * NOT INCLUDED IN THIS SUBMISSION

    LOCATION MAP

    5(1) - 5(2)

    6(1) - 6(3) BRIDGE PLANS

    VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    d11049901b.dgn

    Plotted By: brenda.duong9:17:35 AM

    6/26/2020

    PROJECT SHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    674

    0674-029-358

    Brian Graham P.E. (703) 642-8100 (Volkert, Inc.)

    NO

    VA

    DIS

    TRIC

    T

    DE

    SIG

    N

    UNIT

    (703) 259-3256 (NOVA) Vicente S. Valeza, Jr., P.E.

    VDOT

    VDOT

    P101, B643

    0674-029-358

  • 1F

    1F

    THESE PLANS ARE UNFINISHED

    AND UNAPPROVED AND ARE NOT

    TO BE USED FOR ANY TYPE

    OF CONSTRUCTION OR THE

    ACQUISITION OF RIGHT OF WAY.

    P. H. PLANS

    VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    d11049901f.dgn

    Plotted By: brenda.duong9:17:40 AM

    6/26/2020

    PROJECT SHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    674

    0674-029-358

    Brian Graham P.E. (703) 642-8100 (Volkert, Inc.)

    NO

    VA

    DIS

    TRIC

    T

    DE

    SIG

    N

    UNIT

    (703) 259-3256 (NOVA) Vicente S. Valeza, Jr., P.E.

    VDOT

    VDOT

    P101, B643

    0674-029-358

    ==========================================================================================

    Point 107 N 7,037,778.8580 E 11,822,564.9100 Station 119+20.26 Iron Rod w/Cap

    N 48° 43' 25" E Distance 195.89'

    Point 106 N 7,037,649.6290 E 11,822,417.6900 Station 117+24.37 Iron Rod w/Cap

    N 48° 05' 07" E Distance 429.99'

    Point 105 N 7,037,362.3880 E 11,822,097.7200 Station 112+94.38 Iron Rod w/Cap

    N 36° 51' 22" E Distance 338.56'

    Point 104 N 7,037,091.4910 E 11,821,894.6500 Station 109+55.82 Iron Rod w/Cap

    N 88° 58' 24" E Distance 335.61'

    Point 103 N 7,037,085.4770 E 11,821,559.0900 Station 106+20.21 Iron Rod w/Cap

    N 60° 51' 22" E Distance 323.70'

    Point 102 N 7,036,927.8330 E 11,821,276.3700 Station 102+96.51 Iron Rod w/Cap

    N 34° 21' 39" E Distance 296.51'

    Point 101 N 7,036,683.0640 E 11,821,109.0190 Station 100+00.00 Iron Rod w/Cap

    ==========================================================================================

    Survey Alignment (Stream Traverse)

    Colvin Run

    Asphalt

    Asphalt029-1115

    MON

    16.5'

    15.3'

    33.5'

    Grass

    Bonnet Bolt)

    (Chix 'X' On

    Fire Hydrant

    Hunter Mill Road

    Nail

    P. K.

    Nail

    P. K.

    To Toll Road Cameron

    To Baron

    Of Pavement.

    Approximately 15.4' From Edge

    East Side Of Hunter Mill Road

    The Station On The Left Or

    Approximately 0.9 Miles To

    South On Hunter Mill Road

    And Hunter Mill, Proceed

    Intersection Of Baron Cameron

    To Reach The Monument From

    Ground And Stamped 029-1115.

    Concrete Flush With The

    A Standard Disc Set In

    Virginia Department of Transportation Horizontal Control

    VDOT Project Coordinates (2014)

    Coordinates (2014) to NAD 83 - U. S. Survey Feet

    * Reverse this Procedure to convert VDOT Project

    Project Information

    VA State Plane Coordinates : NAD 83- U. S. Survey Feet

    ( Located above left )

    Zones) by the Project Specific Combined Scale Factor.

    * Multiply the Easting And Northing Values (For Both

    Project Coordinates, use the following formula :

    To convert Virginia State Plane Coordinates to VDOT

    W

    N

    DETAILED SKETCH (Not to Scale)

    Control Station I. D. : 029-1115 Date : 1997 (Established) 3-8-2017 (Superseded - VDOT)

    East (X) : 11821982.59 ft.

    North (Y) : 703594.35 ft.

    Elevation : 255.473 ft.

    Factor: 1. 000039802

    Project Specific Combined Scale

    Latitude : 38° 57' 50.35797"

    Longitude : 77° 18' 32.97737"

    Geoid Separation (N) :

    Ellipsoid Height (h) :

    Horizontal Datum : NAD 83 Year : 2017

    Vertical Datum : NAVD88 Geoid : 12B

    Azimuth to Station : is ° ' "

    Control Based On: Static GPS Observation

    NGS Opus Project Solution

    East (X) : 11821512.07 ft.

    North (Y) : 7036314.29 ft.

    Ortho. Elevation (H) : 255.47 ft.

    Zone : North

    Project Number : 0674-029-340, P101,R201, B643

    Route : 674 City/County : Fairfax

    Originally Established By : Rice & Associates

    LD-200 (REV. 10/2014)

    LD-200 (REV. 10/2014)

    Cha

    mberlain

    Drive

    Hunter Mill Road

    Asphalt

    Run

    To Colvin

    To Baron Cameron

    Asphalt SidewalkConc. Sidewalk

    Fence

    Wood.

    Nail

    P. K Nail

    P. K

    #W163

    Guy PoleNail)

    (P. K.

    21.2'

    40.3'

    39.3'

    029-1116

    MON

    Crest Of A Hill.

    Hunter Mill Road Near The

    The Right Or West Side Of

    0.6 Miles To The Station On

    South On Hunter Mill Road

    Hunter Mill Road, Proceed

    Of Baron Cameron And

    Monument From Intersection

    029-1116. To Reach The

    Ground And Stamped

    Concrete Flush With The

    A Standard Disc Set In

    Virginia Department of Transportation Horizontal Control

    VDOT Project Coordinates (2014)

    Coordinates (2014) to NAD 83 - U. S. Survey Feet

    * Reverse this Procedure to convert VDOT Project

    Project Information

    VA State Plane Coordinates : NAD 83- U. S. Survey Feet

    ( Located above left )

    Zones) by the Project Specific Combined Scale Factor.

    * Multiply the Easting And Northing Values (For Both

    Project Coordinates, use the following formula :

    To convert Virginia State Plane Coordinates to VDOT

    W

    N

    DETAILED SKETCH (Not to Scale)

    Control Station I. D. : 029-1116 Date : 1997 (Established) 3-8-2017 (Superseded - VDOT)

    East (X) : 11821576.03 ft.

    North (Y) : 7038356.44 ft.

    Elevation : 304.53 ft.

    Factor: 1. 000039802

    Project Specific Combined Scale

    Latitude : 38° 58' 07.82517"

    Longitude : 77° 18' 37.83510"

    Geoid Separation (N) :

    Ellipsoid Height (h) :

    Horizontal Datum : NAD 83 Year : 2017

    Vertical Datum : NAVD 88 Geoid : 12B

    Azimuth to Station : is ° ' "

    Control Based On: Static GPS Observation

    NGS Opus Project Solution

    East (X) : 11821105.53 ft.

    North (Y) : 7038076.31 ft.

    Ortho. Elevation (H) : 304.53 ft.

    Zone : North

    Project Number : 0674-029-340, P101,R201, B643

    Route : 674 City/County : Fairfax

    Originally Established By : Rice & Associates

    LD-200 (REV. 10/2014)

    LD-200 (REV. 10/2014)

  • 1G

    1G

    ROADWAY ENGINEER

    Springfield, Virginia

    Volkert, Inc.

    THESE PLANS ARE UNFINISHED

    AND UNAPPROVED AND ARE NOT

    TO BE USED FOR ANY TYPE

    OF CONSTRUCTION OR THE

    ACQUISITION OF RIGHT OF WAY.

    P. H. PLANS

    0

    SCALE

    50' 100'

    POT30+00.00

    PC30+62.14

    PT30+90.39

    31

    POT31+35.86

    D

    1

    2

    3

    D

    D

    POC 105+74.23 HUNTER MILL ROAD (ROUTE 674)

    = 88°58'56"

    POT 10+00.00 TRAIL 1

    POC 105+74.23 HUNTER MILL ROAD (ROUTE 674)

    = 89° 54'32"

    POT 20+00.00 TRAIL 2

    POC 108+29.92 HUNTER MILL ROAD (ROUTE 674)

    2

    3

    = 90°00'00.00"

    POT 30+00.00 ENTRANCE 3

    CONSTRUCTION ALIGNMENT DATA SHEET

    1

    PO

    T10

    0+0

    0.0

    0

    100

    101

    PC10

    1+28.3

    9

    102

    103

    PT10

    3+0

    4.6

    8

    104

    105

    PC10

    5+16.5

    5

    106

    107

    PT10

    7+9

    6.0

    7

    108

    PC10

    8+7

    4.6

    4

    109

    PR

    C10

    9+8

    8.8

    7

    110

    PT110+3

    5.9

    7

    111

    PO

    T111+49.3

    2

    POT10+00.00

    PC10+31.56

    PT10+46.49

    POT10+57.24

    POT20+00.00PC20+05.15

    PRC20+20.18

    PT20+47.83

    POT20+63.85

    1 2

    5 6 7

    3

    Curve HUNTERMILLROA_3

    PI = 102+16.95

    T = 88.55'

    L = 176.29'

    R = 750.00'

    101+28.39PC =

    PT = 103+04.68

    Curve HUNTERMILLROA_6

    PI = 106+57.23

    T = 140.68'

    L = 279.52'

    R = 1,000.00'

    105+16.55PC =

    PT = 107+96.07

    Curve HUNTERMILLROA_9

    PI = 109+32.06

    T = 57.42'

    L = 114.23'

    R = 450.00'

    108+74.64PC =

    PRC =109+88.87

    Curve TRAIL_1_3

    PI = 10+39.07

    T = 7.51'

    L = 14.93'

    R = 55.00'

    10+31.56PC =

    PT = 10+46.49

    Curve TRAIL_2_3

    PI = 20+12.90

    T = 7.75'

    L = 15.04'

    R = 25.00'

    20+05.15PC =

    PRC =20+20.18

    Curve TRAIL_2_4

    PI = 20+34.17

    T = 13.98'

    L = 27.65'

    R = 75.00'

    20+20.18PRC =

    PT = 20+47.83

    PI = 30+76.58

    T = 14.44'

    L = 28.25'

    R = 55.00'

    30+62.14PC =

    PT = 30+90.39

    8

    Curve ENTRANCE3_3

    PI = 110+12.44

    T = 23.57'

    L = 47.10'

    R = 450.00'

    109+88.87PRC =

    PT = 110+35.97

    4

    Curve HUNTERMILLRO_10

    VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    d11049901g(00).dgn

    Plotted By: brenda.duong9:17:57 AM

    6/26/2020

    PROJECT SHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    674

    0674-029-358

    Brian Graham P.E. (703) 642-8100 (Volkert, Inc.)

    NO

    VA

    DIS

    TRIC

    T

    DE

    SIG

    N

    UNIT

    (703) 259-3256 (NOVA) Vicente S. Valeza, Jr., P.E.

    VDOT

    VDOT

    P101, B643

    0674-029-358

  • ROADWAY ENGINEER

    Springfield, Virginia

    Volkert, Inc.

    THESE PLANS ARE UNFINISHED

    AND UNAPPROVED AND ARE NOT

    TO BE USED FOR ANY TYPE

    OF CONSTRUCTION OR THE

    ACQUISITION OF RIGHT OF WAY.

    P. H. PLANS

    2

    1

    3

    1G(1)

    1G(1)

    CONSTRUCTION ALIGNMENT DATA SHEET

    5

    6

    7

    TRAIL 1

    CONSTRUCTION BASELINE

    TRAIL 2

    CONSTRUCTION BASELINE

    HUNTER MILL ROAD (ROUTE 674)

    CONSTRUCTION BASELINE

    Ending chain HUNTERMILLROAD description

    ===============================================================================

    Point 15 N 7,037,652.8935 E 11,821,746.9993 Sta 111+49.32

    Course from PT HUNTERMILLRO_10 to 15 N 11° 25' 39.65" W Dist 113.3462

    Chord Bear = N 8° 25' 44.64" W

    Ahead = N 11° 25' 39.65" W

    Back = N 5° 25' 49.63" W

    C.C. N 7,037,452.6354 E 11,821,328.3777

    P.T. Station 110+35.97 N 7,037,541.7943 E 11,821,769.4567

    P.C. Station 109+88.87 N 7,037,495.2222 E 11,821,776.3580

    Mid. Ord. = 0.6161

    Long Chord = 47.0806

    External = 0.6170

    Radius = 450.0000

    Length = 47.1021

    Tangent = 23.5726

    Degree = 12° 43' 56.62"

    Delta = 5° 59' 50.01" (LT)

    P.I. Station 110+12.44 N 7,037,518.6890 E 11,821,774.1271

    Curve HUNTERMILLRO_10

    *----------*

    Curve Data

    Chord Bear = N 12° 42' 09.62" W

    Ahead = N 5° 25' 49.63" W

    Back = N 19° 58' 29.61" W

    C.C. N 7,037,537.8091 E 11,822,224.3383

    P.T. Station 109+88.87 N 7,037,495.2222 E 11,821,776.3580

    P.C. Station 108+74.64 N 7,037,384.0853 E 11,821,801.4092

    Mid. Ord. = 3.6198

    Long Chord = 113.9253

    External = 3.6492

    Radius = 450.0000

    Length = 114.2318

    Tangent = 57.4246

    Degree = 12° 43' 56.62"

    Delta = 14° 32' 39.98" (RT)

    P.I. Station 109+32.06 N 7,037,438.0554 E 11,821,781.7925

    Curve HUNTERMILLROA_9

    *----------*

    Curve Data

    Course from PT HUNTERMILLROA_6 to PC HUNTERMILLROA_9 N 19° 58' 29.61" W Dist 78.5644

    Chord Bear = N 11° 58' 02.03" W

    Ahead = N 19° 58' 29.61" W

    Back = N 3° 57' 34.45" W

    C.C. N 7,036,968.6389 E 11,820,888.4050

    P.T. Station 107+96.07 N 7,037,310.2472 E 11,821,828.2474

    P.C. Station 105+16.55 N 7,037,037.6914 E 11,821,886.0181

    Mid. Ord. = 9.7505

    Long Chord = 278.6110

    External = 9.8466

    Radius = 1,000.0000

    Length = 279.5201

    Tangent = 140.6772

    Degree = 5° 43' 46.48"

    Delta = 16° 00' 55.16" (LT)

    P.I. Station 106+57.23 N 7,037,178.0328 E 11,821,876.3039

    Curve HUNTERMILLROA_6

    *----------*

    Curve Data

    Course from PT HUNTERMILLROA_3 to PC HUNTERMILLROA_6 N 3° 57' 34.45" W Dist 211.8743

    Chord Bear = N 10° 41' 35.53" W

    Ahead = N 3° 57' 34.45" W

    Back = N 17° 25' 36.60" W

    C.C. N 7,036,878.1123 E 11,822,648.8583

    P.T. Station 103+04.68 N 7,036,826.3229 E 11,821,900.6485

    P.C. Station 101+28.39 N 7,036,653.4965 E 11,821,933.2832

    Mid. Ord. = 5.1735

    Long Chord = 175.8805

    External = 5.2094

    Radius = 750.0000

    Length = 176.2861

    Tangent = 88.5511

    Degree = 7° 38' 21.97"

    Delta = 13° 28' 02.14" (RT)

    P.I. Station 102+16.95 N 7,036,737.9832 E 11,821,906.7632

    Curve HUNTERMILLROA_3

    *----------*

    Curve Data

    Course from HUNTERMILLROAD1 to PC HUNTERMILLROA_3 N 17° 25' 36.60" W Dist 128.3942

    Point HUNTERMILLROAD1 N 7,036,530.9956 E 11,821,971.7356 Sta 100+00.00

    ===============================================================================

    Feature: - 25 Scale Baselines

    Beginning chain HUNTERMILLROAD description

    4

    Ending chain TRAIL_1 description

    ===============================================================================

    Point 17 N 7,037,084.0622 E 11,821,824.5833 Sta 10+57.24

    Course from PT TRAIL_1_3 to 17 S 68° 13' 00.00" W Dist 10.7471

    Chord Bear = S 75° 59' 33.40" W

    Ahead = S 68° 13' 00.00" W

    Back = S 83° 46' 06.79" W

    C.C. N 7,037,036.9778 E 11,821,854.9734

    P.T. Station 10+46.49 N 7,037,088.0504 E 11,821,834.5630

    P.C. Station 10+31.56 N 7,037,091.6528 E 11,821,849.0034

    Mid. Ord. = 0.5057

    Long Chord = 14.8830

    External = 0.5104

    Radius = 55.0000

    Length = 14.9287

    Tangent = 7.5105

    Degree = 104° 10' 26.92"

    Delta = 15° 33' 06.79" (LT)

    P.I. Station 10+39.07 N 7,037,090.8376 E 11,821,841.5373

    Curve TRAIL_1_3

    *----------*

    Curve Data

    Course from 16 to PC TRAIL_1_3 S 83° 46' 06.79" W Dist 31.5624

    Point 16 N 7,037,095.0787 E 11,821,880.3793 Sta 10+00.00

    ===============================================================================

    Feature: - 25 Scale Baselines

    Beginning chain TRAIL_1 description

    Ending chain TRAIL_2 description

    ===============================================================================

    Point 19 N 7,037,120.7001 E 11,821,937.9546 Sta 20+63.85

    Course from PT TRAIL_2_4 to 19 N 70° 25' 55.42" E Dist 16.0184

    Chord Bear = N 59° 52' 12.73" E

    Ahead = N 70° 25' 55.42" E

    Back = N 49° 18' 30.03" E

    C.C. N 7,037,044.6667 E 11,821,947.9807

    P.T. Station 20+47.83 N 7,037,115.3351 E 11,821,922.8614

    P.C. Station 20+20.18 N 7,037,101.5339 E 11,821,899.0816

    Mid. Ord. = 1.2707

    Long Chord = 27.4946

    External = 1.2926

    Radius = 75.0000

    Length = 27.6509

    Tangent = 13.9842

    Degree = 76° 23' 39.74"

    Delta = 21° 07' 25.40" (RT)

    P.I. Station 20+34.17 N 7,037,110.6515 E 11,821,909.6848

    Curve TRAIL_2_4

    *----------*

    Curve Data

    Chord Bear = N 66° 32' 18.41" E

    Ahead = N 49° 18' 30.03" E

    Back = N 83° 46' 06.79" E

    C.C. N 7,037,120.4897 E 11,821,882.7819

    P.T. Station 20+20.18 N 7,037,101.5339 E 11,821,899.0816

    P.C. Station 20+05.15 N 7,037,095.6374 E 11,821,885.4955

    Mid. Ord. = 1.1219

    Long Chord = 14.8105

    External = 1.1746

    Radius = 25.0000

    Length = 15.0361

    Tangent = 7.7532

    Degree = 229° 10' 59.22"

    Delta = 34° 27' 36.77" (LT)

    P.I. Station 20+12.90 N 7,037,096.4790 E 11,821,893.2029

    Curve TRAIL_2_3

    *----------*

    Curve Data

    Course from 18 to PC TRAIL_2_3 N 83° 46' 06.80" E Dist 5.1466

    Point 18 N 7,037,095.0787 E 11,821,880.3793 Sta 20+00.00

    ===============================================================================

    Feature: - 25 Scale Baselines

    Beginning chain TRAIL_2 description

    Ending chain ENTRANCE3 description

    ===============================================================================

    Point ENTRANCE35 N 7,037,325.7386 E 11,821,685.6082 Sta 31+35.86

    Course from PT ENTRANCE3_3 to ENTRANCE35 N 80° 32' 48.26" W Dist 45.4737

    Chord Bear = S 84° 44' 21.06" W

    Ahead = N 80° 32' 48.26" W

    Back = S 70° 01' 30.39" W

    C.C. N 7,037,372.5229 E 11,821,739.4977

    P.T. Station 30+90.39 N 7,037,318.2698 E 11,821,730.4643

    P.C. Station 30+62.14 N 7,037,320.8316 E 11,821,758.2861

    Mid. Ord. = 1.8037

    Long Chord = 27.9395

    External = 1.8649

    Radius = 55.0000

    Length = 28.2490

    Tangent = 14.4434

    Degree = 104° 10' 26.92"

    Delta = 29° 25' 41.35" (RT)

    P.I. Station 30+76.58 N 7,037,315.8976 E 11,821,744.7116

    Curve ENTRANCE3_3

    *----------*

    Curve Data

    Course from ENTRANCE31 to PC ENTRANCE3_3 S 70° 01' 30.39" W Dist 62.1369

    Point ENTRANCE31 N 7,037,342.0581 E 11,821,816.6850 Sta 30+00.00

    ===============================================================================

    Feature: - 25 Scale Baselines

    Beginning chain ENTRANCE3 description

    8

    ENTRANCE 3

    CONSTRUCTION BASELINE

    VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    d11049901g(01).dgn

    Plotted By: brenda.duong9:18:04 AM

    6/26/2020

    PROJECT SHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    674

    0674-029-358

    Brian Graham P.E. (703) 642-8100 (Volkert, Inc.)

    NO

    VA

    DIS

    TRIC

    T

    DE

    SIG

    N

    UNIT

    (703) 259-3256 (NOVA) Vicente S. Valeza, Jr., P.E.

    VDOT

    VDOT

    P101, B643

    0674-029-358

  • VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    d11049901k(00).dgn

    Plotted By: brenda.duong9:18:08 AM

    6/26/2020

    PROJECT SHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    674

    0674-029-358

    Brian Graham P.E. (703) 642-8100 (Volkert, Inc.)

    NO

    VA

    DIS

    TRIC

    T

    DE

    SIG

    N

    UNIT

    (703) 259-3256 (NOVA) Vicente S. Valeza, Jr., P.E.

    VDOT

    VDOT

    P101, B643

    0674-029-358TRAFFIC MANAGEMENT PLAN NOTES

    advance and contractor shall provide adequate access during construction.

    Property owners and businesses affected as result of proposed construction zones shall be notified in3.

    Notification

    Public Communications and Outreach Strategies

    Temporary Traffic Control Plans Notes

    Sequence of ConstructionTemporary Traffic Control Plans Notes Cont'd

    TRAFFIC ENGINEER

    Springfield, Virginia

    Volkert, Inc.

    1K

    1K

    en-route traveler information. The Traffic Operations Center will contact the VDOT District Public Affairs Manager.

    work ensuring proper, timely and accurate communication to the media and general public which is critical in providing

    one (1) month in advance of the start of construction and weekly updates by noon on Thursday for the following weeks

    Project information will be given to the VDOT Traffic Operations Center (Northern Regional Operations - NRO) at least 1.

    Schools Superintendent concerning all detours and road closures of any nature.

    The Contractor shall coordinate with the Fairfax County Sheriff's Office, Department of Fire and Rescue, and the County 2.

    g) Fairfax County Sheriff's Office - (703) 246-3227

    f) District Work Zone Safety Coordinator: Kwame Acquah - (XXX) XXX-XXXX

    e) District Traffic Engineer: Ivan Horodyskyj - (703) 259-2330

    d) Area Construction Engineer: Chandraratne B. Basnayake - (XXX) XXX-XXXX

    c) Construction Project Managers: To Be Determined

    b) Project Inspector: To Be Determined

    a) Transportation Operations Center: (703) 877-3449

    Contractor to call:

    Process of notification of incident to be followed is:5.

    guardrails for the northbound lane east of Rte. 240.

    Grade and construct shoulders, aggregate base and intermediate courses at full depth pavement section including the7.

    Demolish the northbound Rte. 240 at Lickinghole Creek bridge. 6.

    the bridge segment from 11' to 10', and access to private driveway entrances throughtout Phase I construction.

    Maintain the existing traffic using portable traffic signals and dynamic electronic board, lane width transition at 5.

    Adjust and relocate traffic signals and signs location as deemed necessary.

    from the private driveway at Sta. 102+00 prior to initiating the lane closure operation with traffic control signals.

    Contractor shall ensure adequate sight distances are provided on both northbound and southbound Rte. 240, and 4.

    per TTC-25.2 of 2011 WAPM, Revision 2 (September 1, 2019).

    two-way, two-lane traffic on Rte. 240 at Lickinghole Creek to lane closure operation using traffic control signals

    and barriers, and provide temporary markings as shown on the temporary traffic control plans. Switch the existing

    Close the northbound lane of Rte. 240 between Sta. 99+50 through Sta. 104+75 with group 2 channelizing devices3.

    construction.

    control signals operation. The private driveway at Sta. 102+00 (left) shall remain open for the entire duration of

    left-right arrow for the private driveway at Sta. 102+00 (left) in preparation of the lane closure with traffic

    Close Oak Drive at Sta. 104+75 (right) with barricades and provide the specified dynamic electronic board with 2.

    and maintain erosion and sediment control measures throughout all construction phases.

    TTC-53.0 as shown in the 2011 Virginia Work Area Protection Manual (WAPM), Revision 2 (September 1, 2019). Install

    The contractor shall set the signing for lane closure operation with traffic control signals and trucks detour using 1.

    guardrails for the southbound lane west of Rte. 240.

    Grade and construct shoulders, aggregate base and intermediate courses at full depth pavement section including the7.

    Demolish southbound Rte. 240 at Lickinghole Creek bridge. 6.

    the bridge segment from 11' to 10', and access to private driveway entrances throughtout Phase II contruction.

    Maintain the existing traffic using portable traffic signals and dynamic electronic board, lane width transition at 5.

    Adjust and relocate traffic signals and signs location as deemed necessary.

    from the private driveway at Sta. 102+00 prior to initiating the lane closure operation with traffic control signals.

    Contractor shall ensure adequate sight distances are provided on both northbound and southbound Rte. 240, and 4.

    (September 1, 2019).

    and operate the lane closure operation using traffic control signals per TTC-25.2 of 2011 WAPM, Revision 2

    At the time of closing the southbound lane, divert traffic onto northbound lane on Rte. 240 at Lickinghole Creek 3.

    Rte. 240 between Sta. 99+50 through Sta. 104+81 as shown on the temporary traffic control plans,

    Provide temporary markings for Phase II, relocate the portable traffic signals, and close the southbound lane of 2.

    the traffic switch using flagging operation (TTC-23.2) as shown in 2011 WAPM, Revision 2 (September 1, 2019).

    Place and connect barriers from southbound lane in Phase I to the northbound lane parapet in preparation of 1.

    the guardrails for the proposed northbound lane of Rte. 674.

    Grade and construct roadways, shoulders, aggregate base and intermediate courses at full depth pavement section including 6.

    Access to existing trail for bicyclists and pedestrians shall be maintained at all times throughout construction.5.

    as stop-controlled throughout construction.

    Maintain the existing private driveway entrances at STA. 102+25.64 (right), STA. 102+40.81 (left), and STA. 108+30.16 (left) 4.

    phase of construction.

    and roadways in preparation of next phase of construction. Maintain existing signs and pavement markings throughout this

    Utilize existing two-way, one-lane operation on Rte. 674 at Colvin Run to construct the eastern portion of proposed bridge 3.

    existing guardrails between STA. 105+78.5 and STA. 109+4.5 throughout MOT Phase One (1).

    Install concrete barriers and impact attenuators from STA. 102+93.0 through STA. 105+59.0 as shown on plans, and maintain 2.

    construction phases.

    Manual (WAPM), Revision 2 (September 1, 2019). Install and maintain erosion and sediment control measures throughout all

    The contractor shall set the signing for Phase 1 as shown on plans using TTC-53.0 per 2011 Virginia Work Area Protection 1.

    the guardrails for the proposed southbound lane of Rte. 674.

    Grade and construct roadways, shoulders, aggregate base and intermediate courses at full depth pavement section including 7.

    Demolish the existing Rte. 674 at Colvin Run bridge. 6.

    throughout construction.

    throughtout Phase 2 construction. Access to existing trail for bicyclists and pedestrians shall be maintained at all times

    Maintain the existing traffic using portable traffic signals and DAD system, and access to private driveway entrances 5.

    closure operation with traffic control signals. Adjust and relocate traffic signals and signs location as deemed necessary.

    private driveway entrances at STA. 102+25.64 (right), STA. 102+40.81 (left), and STA. 108+30.16 (left) prior to initiating the lane

    Contractor shall ensure adequate sight distances are provided on both northbound and southbound Rte. 674, and from the 4.

    operation using traffic control signals per TTC-25.2 of 2011 WAPM, Revision 2 (September 1, 2019).

    temporary traffic control plans. Switch the existing two-way, one-lane traffic on Rte. 674 at Colvin Run to lane closure

    concrete barriers, group 2 channelizing devices and impact attentuators, and provide temporary markings as shown on the

    Close the existing Rte. 674 bridge and portion of southbound lanes between Sta. 102+85.92 through Sta. 108+12.0 with 3.

    operation. All private driveway entrances shall remain open for the entire duration of construction.

    STA. 102+40.81 (left), and STA. 108+30.16 (left) in preparation of the lane closure with traffic control signals

    Provide the Driveway Assistance Device (DAD) system for private driveway entrances at STA. 102+25.64 (right), 2.

    2011 Virginia Work Area Protection Manual (WAPM), Revision 2 (September 1, 2019).

    The contractor shall set the signing for lane closure operation with traffic control signals using TTC-53.0 as shown in the 1.

    Construct raised medians and curbs for Rte. 674 between STA. 105+9.4 and STA. 107+79.19.5.

    throughtout Phase 3 contruction.

    Maintain the existing traffic using portable traffic signals and DAD units, and access to private driveway entrances 4.

    (September 1, 2019).

    and operate the lane closure operation using traffic control signals per TTC-25.2 of 2011 WAPM, Revision 2

    At the time of closing the proposed northbound lane, divert traffic onto the newly constructed southbound lane of Rte. 674 3.

    of Rte. 674 at Colvin Run between Sta. 103+2.7 through Sta. 109+10.42 as shown on plans,

    Provide temporary markings for Phase 3, relocate the portable traffic signals, and close the proposed northbound lane 2.

    of the traffic switch using flagging operation (TTC-23.2).

    Relocate concrete barriers and impact attentuators from Phase 2 to Phase 3 configuration shown on plans in preparation 1.

    the scheduled Rte. 674 road closure on Dulles Toll Road (Rte. 267).

    available for use one week in advance of the construction, during the first week of construction, and during

    The contractor shall have in place a minimum of four (4) portable changeable message sign (PCMS) boards4.

    THESE PLANS ARE UNFINISHED

    AND UNAPPROVED AND ARE NOT

    TO BE USED FOR ANY TYPE

    OF CONSTRUCTION OR THE

    ACQUISITION OF RIGHT OF WAY.

    P. H. PLANS

    Phase II: Construct Second Lane Of Bridge (SB) And Shift Traffic To The Newly Constructed Bridge

    Existing Traffic Operation

    Phase I: Construct One-Lane Of New Bridge (NB) To The East Of Existing Bridge While Maintaining

    Phase IV: MIlling/Overlay Operation, Signing And Pavement Marking, And Final Preparation

    Remove all erosion and sediment control and temporary measures at the completion of the project.3.

    Stripe Rte. 674 at Colvin Run as shown on the signing and pavement marking plans.2.

    asphalt surface course.

    Overlay Rte. 674 between Sta. 101+50.0 through Sta. 111+25.0 adjacent to the newly constructed bridge with 1.

    approval.

    necessary. The contractor shall submit the bridge closure and detour request to the Engineer for review and

    Contractor shall perform the bridge closure with detour as shown on sheets 1K(3) and 1K(4) only when deemed11.

    permission of the VDOT Engineer (per section 108.02 of the Road and Bridge Specifications).

    Except as necessary to maintain traffic, work shall not be performed on Sundays and Holidays without the

    Contractor shall perform work in the construction zone from Monday - Saturday from 8:00 A.M. to 5:00 P.M. 10.

    This is in accordance with section 514 of the specification.

    If the signs are not setup as a pay item, they shall be considered incidental to the price of other items.

    adjusting, maintaining, and removing the signs and posts per the Specifications and Standard Details.

    All construction signs shall be the responsibility of the contractor, including furnishing, installing,9.

    least 48 hours prior to the beginning of work.

    Contractor to call Northern Regional Operations (NRO) Traffic Operations Center (TOC): 703-877-3449 at 8.

    Mailboxes shall be reset/available for use each day.

    on plans. Emergency vehicles and postal vehicles must also have access to all properties at all times.

    connections and entrances, minimum width shall be no less than existing conditions unless otherwise shown

    Access and adequate sight distance to and from all properties shall be maintained at all times. For 7.

    applicable notes.

    Area Protection Manual, Revision 2 (September 1, 2019) i.e TTC-23.2, TTC-25.2, TTC-48.2, TTC-53.0 and

    Contractor shall use Typical Traffic Control (TTC) application drawings shown in the 2011 Virginia Work 6.

    Removal of existing pavement markings shall be completed according to Section 512.03 (l).5.

    measured and paid for as regular excavation in accordance with Section 303 of the specifications.

    item, the removal and salvage of existing surfaces and aggregate base and subbase material will be

    utilized for M.O.T. prior to the use of commercial material. When not specified as a separate pay

    construction and which is suitable for M.O.T, as determined by the Engineer, shall be salvaged and

    Existing surface, aggregate base and subbase material that will be demolished or obliterated during 4.

    of work, as directed by the Engineer.

    All warning signs and temporary traffic control devices shall be promptly removed at the completion3.

    for review and approval.

    traffic control plan shall be signed and sealed by a Professional Engineer and submitted to VDOT

    Any major changes in phasing will require approval of the Engineer. Any changes to the temporary2.

    with the current edition of the 2011 Virginia Work Area Protection Manual, Revision 2 (September 1, 2019).

    Work Zone Safety Coordinator to develop and monitor all traffic control devices and ensure compliance

    The Contractor shall be responsible for providing one intermediate level and one basic level designated 1.

    following:

    approved or directed by the Engineer, the Contractor shall plan and execute the work in accordance with the

    2011 Virginia Supplement to 2009 MUTCD Revision 1. The project will have a Type B TMP. Unless otherwise

    2016 Road and Bridge Standards, 2011 Virginia Work Area Protection Manual, Revision 2 (September 1, 2019),

    This project is to be constructed in accordance with the department's 2016 Road and Bridge Specifications,

    Transportation Operations Plan

    Detailed Transportation Operations Plan to be provided at next design submission.

    Phase III: Build Median And Shift Traffic To The Second Lane (SB Lane) Of Newly Constructed Bridge

  • VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    d11049901k(01).dgn

    Plotted By: brenda.duong9:18:25 AM

    6/26/2020

    PROJECT SHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    674

    0674-029-358

    Brian Graham P.E. (703) 642-8100 (Volkert, Inc.)

    NO

    VA

    DIS

    TRIC

    T

    DE

    SIG

    N

    UNIT

    (703) 259-3256 (NOVA) Vicente S. Valeza, Jr., P.E.

    VDOT

    VDOT

    P101, B643

    0674-029-358

    104

    105

    106

    107

    31

    100

    101 10

    2

    103

    104

    105

    106

    107

    108

    109

    110 111

    2' Paved Shoulder

    31

    100

    101 10

    2

    103

    104

    105

    106

    107

    108

    109

    110 111

    31

    100

    101 10

    2

    103

    104

    105

    106

    107

    108

    109

    110 111

    THESE PLANS ARE UNFINISHED

    AND UNAPPROVED AND ARE NOT

    TO BE USED FOR ANY TYPE

    OF CONSTRUCTION OR THE

    ACQUISITION OF RIGHT OF WAY.

    P. H. PLANS

    TRAFFIC ENGINEER

    Springfield, Virginia

    Volkert, Inc.

    0

    SCALE

    50' 100'

    MOT PHASE 1

    MOT PHASE 2

    MOT PHASE 3

    TO STOP

    PREPARED

    BE

    AHEAD

    ROAD

    ONE LANE HERE ONSTOP

    REDAHEAD

    WORK

    ROAD

    15M P H

    15M P H

    48" x 48"

    W20-4

    48" x48"

    W3-4

    24" x30"

    R10-6

    60" x 18"

    W16-VP3

    48" x 48"

    W3-3

    48" x 48"

    W20-1

    30" x 30"

    W13-1P

    30" x 30"

    W13-1P350 FEET

    TEMPORARY TRAFFIC CONTROL PLAN - PHASE SEQUENCE

    350' - 500'

    1 2 3 4 5

    350' - 500'350' - 500'350' - 500'

    1 23

    40' - 180'50' - 100'

    350' - 500'350' - 500'350' - 500'350' - 500'

    1 23

    40' - 180'50' - 100'

    350' - 500'350' - 500'

    350' - 500'

    350' - 500' 3 2 140' - 180'50' - 100'

    and OperationPer Existing Lane Configuration MOT Phase One (1) To Operate

    VA WAPM Revision 2.Control Signals In Accordance With A Two-Lane Roadway Using Traffic TTC-25.2 (Lane Closure Operation on MOT Phase Two (2) to Operate Per

    MOT Phase One (1)Markings To Remain Throughout Existing Signs And Pavement

    Zone Signs Per TTC-25.2Regarding Associated Work Refer To Signs Legend Above

    Zone Signs Per TTC-25.2Regarding Associated Work Refer To Signs Legend Above

    MOT Phase One (1)Markings To Remain Throughout Existing Signs And Pavement

    Zone Signs Per TTC-25.2Regarding Associated Work Refer To Signs Legend Above

    Zone Signs Per TTC-25.2Regarding Associated Work Refer To Signs Legend Above

    Throughout MOT Phase One (1)Existing Guardrails To Remain

    -ControlledExisting Stop

    - ControlledExisting Stop

    (2) OperationMOT Phase Two (DAD) As Part ofAssistance Device Proposed Driveway

    (2) OperationMOT Phase Two (DAD) As Part ofAssistance Device Proposed Driveway

    6 7

    6 7

    6 7

    DAD System)

    (As Part Of

    24" x30"

    R10-11

    DAD System)

    (As Part Of

    36" x42"

    HUNTER MILL RD (

    ROUTE 674)

    HUNTER MILL RD (ROUTE 674)

    CO

    LVIN

    RU

    NC

    OL

    VIN

    RU

    NC

    OL

    VIN

    RU

    N

    CO

    LVIN

    RU

    NC

    OL

    VIN

    RU

    N

    CO

    LVIN

    RU

    N

    50' - 100'40' - 180' 350' - 500'

    350' - 500'

    3

    350' - 500'

    2

    350' - 500'

    1

    LEGEND

    Work Area

    Temporary Traffic Control Signal

    Impact Attenuator

    Concrete Barrier

    Driveway Assistance Device (DAD) System

    6 7

    6 7

    TR

    AIL

    EXIS

    TIN

    G

    TR

    AIL

    EXIS

    TIN

    G

    TR

    AIL

    EXIS

    TIN

    G

    TR

    AIL

    EXIS

    TIN

    GT

    RAIL

    EXIS

    TIN

    GT

    RAIL

    EXIS

    TIN

    G

    ENTRANCE

    AREA 6 DRIVEWAY

    PARK MAINTENANCE

    LAKE FAIRFAX

    ENTRANCE

    AREA 6 DRIVEWAY

    PARK MAINTENANCE

    LAKE FAIRFAX

    ENTRANCE

    AREA 6 DRIVEWAY

    PARK MAINTENANCE

    LAKE FAIRFAX

    HUNTER MILL RD (

    ROUTE 674)

    HUNTER MILL RD (ROUTE 674)

    HUNTER MILL RD (

    ROUTE 674)

    HUNTER MILL RD (ROUTE 674)

    (3) OperationMOT Phase Three (DAD) As Part ofAssistance Device Proposed Driveway

    VA WAPM Revision 2.Control Signals In Accordance With A Two-Lane Roadway Using Traffic TTC-25.2 (Lane Closure Operation on MOT Phase Three (3) to Operate Per

    (3) OperationMOT Phase Three (DAD) As Part ofAssistance Device Proposed Driveway

    BRIDGE B-645

    BRIDGE B-645

    B-645

    BRIDGE

    9

    30" x 30"

    W11-15

    24" x 12"

    W16-7PL

    9 9

    9

    9

    ROAD WORK

    END

    48" x24"

    G20-2(V)

    8

    8

    8

    8

    8

    1

    1

    1

    350' - 500'

    350' - 500'

    1

    1

    8

    45

    8

    6 7

    4 5

    4 5

    6 7

    54

    System

    Driveway Assistance Device (DAD)

    System

    Driveway Assistance Device (DAD)

    (Not Shown)MarkingsPavementTemporaryProposed

    (Not Shown)MarkingsPavementTemporaryProposed

    (Not Shown)MarkingsPavementTemporaryProposed

    (Not Shown)MarkingsPavementTemporaryProposed

    1K(1)

    1K(1)

    TAPER

    TAPER

    TAPER

    TAPER

    BUFFER

    (Not Shown)MarkingsPavementTemporaryProposed

    (Not Shown)MarkingsPavementTemporaryProposed

    BUFFER

    BUFFER

    BUFFER

  • 31

    100

    101 10

    2

    103

    104

    105

    106

    107

    108

    109

    110 111

    1000 F

    TC

    LO

    SE

    DR

    OA

    D

    500 F

    TC

    LO

    SE

    DR

    OA

    D

    R11-2

    R11-2

    500 F

    T

    CL

    OS

    ED

    RO

    AD

    1000 F

    T

    CL

    OS

    ED

    RO

    AD

    BA

    RRIC

    AD

    ES

    TYP

    E III

    BA

    RRIC

    AD

    ES

    TYP

    E III

    RO

    AD

    CLOSE

    D

    HUNTER MILL RD

    (VA-674)

    HUNTER MILL RD (VA-674)

    RO

    AD

    CLOSE

    D

    W20-3

    W20-3

    500'

    W20-3

    500'

    500'500'

    W20-3

    B-645

    BRIDGE

    ENTRANCE

    AREA 6 DRIVEWAY

    PARK MAINTENANCE

    LAKE FAIRFAX

    VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    d11049901k(02).dgn

    Plotted By: brenda.duong9:19:15 AM

    6/26/2020

    PROJECT SHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    674

    0674-029-358

    Brian Graham P.E. (703) 642-8100 (Volkert, Inc.)

    NO

    VA

    DIS

    TRIC

    T

    DE

    SIG

    N

    UNIT

    (703) 259-3256 (NOVA) Vicente S. Valeza, Jr., P.E.

    VDOT

    VDOT

    P101, B643

    0674-029-358

    Wooden Posts (T

    yp. )

    Colvin Run

    Colvin Run

    Stream

    THESE PLANS ARE UNFINISHED

    AND UNAPPROVED AND ARE NOT

    TO BE USED FOR ANY TYPE

    OF CONSTRUCTION OR THE

    ACQUISITION OF RIGHT OF WAY.

    P. H. PLANS

    1K(2)

    TRAFFIC ENGINEER

    Springfield, Virginia

    Volkert, Inc.

    1K(2)

    0

    SCALE

    50' 100'

    BRIDGE CLOSURE

    TEMPORARY TRAFFIC CONTROL PLAN

    NOTES:

    1.

    2.Ground Mounted Sign

    LEGEND

    Type B Warning Light

    Denotes Barrier

    for setting up work area shown on this sheet.

    Area Protection Manual, Revision 2 (September 1, 2019)

    Contractor shall refer to TTC-48.2 in the Virginia Work

    Work Area Protection Manual, Revision 2 (September 1, 2019).

    R11-2 shall be crashworthy as per the Virginia

    BARRICADE

    TYPE III

    R11-2 (MOD)

    TRAILCLOSED

    TRAILCLOSED

    BARRICADE

    TYPE III

    R11-2 (MOD)

  • VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    d11049901k(03).dgn

    Plotted By: brenda.duong9:19:27 AM

    6/26/2020

    PROJECT SHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    674

    0674-029-358

    Brian Graham P.E. (703) 642-8100 (Volkert, Inc.)

    NO

    VA

    DIS

    TRIC

    T

    DE

    SIG

    N

    UNIT

    (703) 259-3256 (NOVA) Vicente S. Valeza, Jr., P.E.

    VDOT

    VDOT

    P101, B643

    0674-029-358

    267

    7

    Colvin Run

    Colvin

    Run

    FairfaxLake

    Anne

    Lake

    Baron

    (Rte.

    606)

    Camero

    nAv

    e

    SunsetHills

    Rd

    (Rte. 675)DullesTollRd

    Rd

    Toll

    Dulles

    Sunrise Valley Dr(Rte. 5320)

    Wiehle

    Ave

    (Rte. 828)

    Hunter

    Mill

    Rd

    674)

    (Rte.

    Crowell Rd(Rte. 675)

    Colvin

    Rd

    Run

    TRAFFIC ENGINEER

    Springfield, Virginia

    Volkert, Inc.

    1K(3)

    1K(3)

    NOT TO SCALE

    DETOUR

    NOTICE

    RTE 674

    FOLLOW

    CLOSED IN

    HUNTER MILL RD

    1.0 MILE

    AHEAD

    DETOUR

    1000 FT

    CLOSED

    ROAD

    500 FT

    CLOSED

    ROAD

    DETOUREND

    CLOSED

    ROAD

    DETOUR

    3

    DETOUR

    674

    NORTH

    12

    DETOUR

    674

    NORTH

    14

    DETOUR

    NORTH

    674

    13

    13

    14 13

    1312 14

    7

    4

    674

    SOUTH

    12

    17

    DETOUR

    674

    SOUTH

    19

    674

    3

    7

    17

    1716

    17

    16

    6

    7

    18

    DETOUR

    NOTICE

    RTE 674

    FOLLOW

    CLOSED IN

    HUNTER MILL RD

    2 MILES

    5

    5 7 18

    17

    with type 3 barricade

    9

    10

    11

    11

    10

    9

    LOCAL TRAFFIC ONLY

    ROAD CLOSED1 MILE AHEAD

    with type 3 barricade

    8

    1

    1

    1

    2

    1

    2

    6

    M3-15

    2

    M3-14

    M3-35

    18

    M3-1

    M3-32

    DETOUR

    674

    SOUTH

    M3-32

    14

    19

    9

    10

    11

    17

    40

    20

    40

    92.5

    92.5

    DETOUR

    TEMPORARY TRAFFIC CONTROL PLAN

    3

    R11-3a8 60 x 30

    M4-8

    24 x 12

    24 x 12

    M4-8

    M1-V2a 36 x 365

    M6-1R

    M1-V2a 36 x 36

    M6-3

    30 x 21

    30 x 21

    M4-8

    M1-V2a

    24 x 12

    M6-3 30 x 21

    13

    NO.

    SIGN

    MAP

    PANELSIZE

    (INCHES) TOTAL

    SF. QUANTITY

    12

    W20-2 48 x 487

    48 x 605

    30 x 15

    30 x 15

    30 x 15

    36 x 36

    W20-3 48 x 48 322

    R11-2 48 x 30 404

    W20-3 48 x 48 322

    M4-8a 24 x 182 24

    M1-V2a 36 x 36

    M4-8

    M1-V2a

    M6-1R

    24 x 12

    36 x 36

    30 x 21

    30 x 15

    4

    PCMS 2 NA

    48 x 60

    48 x 60

    M6-1L

    M1-V2a

    M4-8 30 x 15

    24 x 12

    36 x 36

    30 x 21

    M4-8

    M1-V2a

    M5-2L

    24 x 12

    36 x 36

    30 x 15

    30 x 21

    TOTAL (SF) =

    CONSTRUCTION

    1 WEEK PRIOR

    TO CLOSE CLOSED

    Notes:

    ROAD CLOSED

    PROJECT AREA

    1215

    7

    Exit 13

    1 mile from

    * Approximately 14

    15

    14

    8

    6

    12

    15

    72

    Exit 14

    1 mile from

    * Approximately

    approximate.

    Detour sign locations shown are

    shown in sign no. 1 and 2.

    The PCMS messages to be displayed are

    1.

    2.

    3.

    4.

    Detour Route

    Ground Mounted Sign

    LEGEND

    RT674 AT

    COLVIN

    RUN

    FOLLOW

    DETOUR

    XX/XX/XX

    CONSTRUCTION

    1ST WEEK OF

    TO CLOSE CLOSED

    RT674 AT

    COLVIN

    RUN

    FOLLOW

    DETOUR

    XX/XX/XX

    2

    CLOSURE

    DURING ROAD

    COLVIN

    RUN

    RT674 AT

    RUN

    COLVIN

    RT674 AT

    6

    DETOUR

    674

    NORTH

    M3-1

    M4-8

    M1-V2a

    M6-2R

    16

    15

    (INCHES)QUANTITY

    TOTAL

    SF. PANEL

    SIZE

    NO.

    SIGN

    MAP

    DETOURFOLLOW

    CLOSED IN

    HUNTER MILL RD

    2.5 MILES

    RTE 674

    NOTICE

    PCMS 2 NA

    AHEAD

    CLOSED

    ROAD

    48 x 48 2W20-3

    3

    32

    96

    30 x 21

    36 x 36

    24 x 12

    30 x 15

    55.5

    2

    37

    37

    Traffic Direction

    25

    882

    Exit 14

    Exit 13

    19

    92.5

    week of construction only.

    the construction and during the first

    be installed one week in advance of

    two weeks only. Both PCMS units to

    PCMS sign no. 1 to be installed for

    offline mode when not in use.

    Both of these PCMS units shall be in

    closure and during the road closure.

    weeks in advance of the scheduled road

    PCMS sign no. 2 to be installed two

    THESE PLANS ARE UNFINISHED

    AND UNAPPROVED AND ARE NOT

    TO BE USED FOR ANY TYPE

    OF CONSTRUCTION OR THE

    ACQUISITION OF RIGHT OF WAY.

    P. H. PLANS

    74

    CONSTRUCTION

    2 WEEKS PRIOR

    20

    20

    with type 3 barricade

    20 48 x 30 202CLOSED

    TRAIL(MOD)

    R11-2

  • ROADWAY ENGINEER

    Springfield, Virginia

    Volkert, Inc.

    THESE PLANS ARE UNFINISHED

    AND UNAPPROVED AND ARE NOT

    TO BE USED FOR ANY TYPE

    OF CONSTRUCTION OR THE

    ACQUISITION OF RIGHT OF WAY.

    P. H. PLANS

    2A

    2ATYPICAL SECTIONSNOTE: PAVEMENT WIDTHS VARY AT TAPERS.

    SEE PLAN SHEETS AND CROSS SECTIONS

    FOR PAVEMENT LENGTHS AND WIDTHS.

    1

    2

    3

    TYPE SM-9.5A

    1.5" ASPHALT CONCRETE SURFACE COURSE

    L

    Finished Grade

    Point of

    B

    STATION 102+75.00 TO STATION 102+87.33

    4%

    HUNTER MILL ROAD (RTE. 674)

    BL

    11' 11'

    HUNTER MILL ROAD (RTE. 674)

    Varies Varies

    2'2'

    (See Cross Section)

    Varies

    Finished Grade

    Point of

    Prop. Guardrail, 9' Post

    Varies

    Section)

    (See Cross

    2' to 4'

    Varies

    0' - 11'

    NOT TO SCALE

    1.5:1 1.5:1

    Prop. Guardrail, 9' Post

    2%2%

    11' 11' 2'2'Varies

    Cross Section)

    (See

    1.5:1

    1.5:1

    HUNTER MILL ROAD (RTE. 674)

    STATION 106+45.00 TO STATION 106+85.00

    Varies

    Section)

    (See Cross

    BL

    Finished Grade

    Point of

    HUNTER MILL ROAD (RTE. 674) BRIDGE B-643

    STATION 106+85.00 TO STATION 107+79.20

    STATION 105+09.43 TO STATION 106+45.00

    4'

    Varies

    Prop. Guardrail, 9' Post

    STATION 107+79.20 TO STATION 110+00.00

    STATION 102+87.33 TO STATION 105+09.43

    BL

    Finished Grade

    Point of

    Varies

    Varies Varies

    Varies

    0' - 11'

    PAVEMENT

    EXISTING

    *1.5" MILL

    ** Station 102+00 to Station 102+75 - 1.5" MILL AND OVERLAY TO EXISTING PAVEMENT

    5%

    Varies

    Aggr. 25 or 26

    Asphalt Commercial

    NOT TO SCALE

    Crusher Run Aggr.

    The type of entrance (I , II , III , IV) to be constructed

    will be determined by the existing condition at the

    TYPE IV

    TYPE I

    6" Crusher Run

    Asphalt Conc. Type

    4" Asphalt Conc. Base Course

    BM-25.0

    TYPE III

    Asphalt

    Asphalt Conc. Type

    TYPE II

    Concrete

    Concrete Entrance Pavement

    7" HES

    4" Aggr. Base Mat'l. Ty. 1

    PRIVATE AND COMMERCIAL ENTRANCES

    4" Aggr. Base Mat'l. Ty. 1

    6" Aggr. Base Mat'l. Ty. 1

    No. 21B

    SM-9.5A @ 220 Lbs. per S. Y. SM-9.5A @ 165 Lbs. per S. Y.

    No. 21B

    No. 21B

    time of construction.

    HUNTER MILL ROAD (RTE. 674)

    STATION 110+50.00 TO STATION 111+25.00

    0' to 8'

    Gore Area Varies

    4

    TYPE BM-25.0A

    4" ASPHALT CONCRETE BASE COURSE

    COURSE TYPE IM-19.0A

    2.5" ASPHALT CONCRETE INTERMEDIATE

    (See Cross Section)

    Varies 18'-21'

    (See Cross Section)

    Varies 18'-21'

    TYPE I, SIZE NO. 21B

    8" AGGREGATE BASE MATERIAL,

    See Inset A

    See Inset A

    See Inset A

    2

    1

    3

    INSET A

    4

    11'2' - 4'

    Varies

    Shoulder

    11' 1' - 3'

    Varies

    Shoulder

    4'2'

    1.5:1

    5%

    (See Cross Section)

    Varies

    Prop. St'd. GR-MGS2 or St'd. GR-FOA-5

    STATION 105+90.25 TO STATION 106+45.00

    STATION 106+85.00 TO STATION 107+12.50

    3.5' to 8'

    VA.

    STATE

    ROUTE PROJECT

    VA.

    REVISEDSTATE

    STATE

    ROUTE PROJECTSHEET NO.

    d11049902a.dgn

    Plotted By: brenda.duong9:19:51 AM

    6/26/2020

    PROJECT SHEET NO.

    DESIGN FEATURES RELATING TO CONSTRUCTION

    OR TO REGULATION AND CONTROL OF TRAFFIC

    MAY BE SUBJECT TO CHANGE AS DEEMED

    NECESSARY BY THE DEPARTMENT

    SURVEYED BY, DATE

    DESIGN BY

    SUBSURFACE UTILITY BY, DATE

    PROJECT MANAGER

    674

    0674-029-358

    Brian Graham P.E. (703) 642-8100 (Volkert, Inc.)

    NO

    VA

    DIS

    TRIC

    T

    DE

    SIG

    N

    UNIT

    (703) 259-3256 (NOVA) Vicente S. Valeza, Jr., P.E.

    VDOT

    VDOT

    P101, B643

    0674-029-358

  • ***Denotes information that is to be provided/completed by the contractor.

    Denotes information that is to be provided/completed by the VDOT RLD.

    SECTION I GENERAL INFORMATION

    **

    **

    *

    *

    STORMWATER POLLUTION PREVENTION PLAN (SWPPP) GENERAL INFORMATION SHEET

    **

    Name Position

    **

    Responsibility

    if there is 0.25 inches or more accumulation noted in the rain gage.

    be noted in the log book and the rain gage emptied and replaced. An inspection is required

    event, an observation of the rain gage shall be made and the observation information shall

    additional rainfall until the conclusion of the rainfall event. At the conclusion of the rainfall

    to be noted in the log book. The rain gage is not to be emptied but left to accumulate

    If there is rainfall occurring at the time of the observation, the observation information is

    required if there is 0.25 inches or more accumulation noted in the rain gage.

    shall be noted in the log book and the rain gage emptied and replaced. An inspection is

    If there is no rainfall occurring at the time of the observation, the observation information

    RLD Certify the SWPPP (with date & sig.)

    *

    construction site.

    that may generate a stormwater or non-stormwater discharge directly related to the

    fuels or chemicals, concrete wash out areas, sanitary waste facilities and any other areas

    and vehicle washing, maintenance, storage and fueling areas, storage areas for fertilizers,

    borrow and disposal areas, construction and waste material storage areas, equipment

    appropriate contract documents. Support facilities shall include, but not be limited to,

    provided by the contractor and identified on the record set of plans or in other

    Construction Permit coverage for this land disturbance (construction) activity shall be

    4. The location of on-site support facilities that will be covered under the VPDES

    July 1, 2019 and VDOT's approved Annual ESC and SWM Standards and Specifications.

    Stormwater From Construction Activities (the VPDES Construction Permit) issued

    comply with the requirements of the VPDES General Permit For Discharges Of

    The information contained in the SWPPP General Information sheets is intended to

    ACRONYMS

    Specifications as approved by the DEQ.

    Annual Erosion and Sediment Control and Stormwater Management Standards and

    (construction) activity have been developed in accordance with VDOT's Approved

    10. The ESC and SWM plans (where applicable) for this land disturbance

    Position ResponsibilityVDOT Individuals

    NPDES

    only to Inspection Schedule 1.

    Specifications except for Section 107.16(e) 4.an Inspection Requirements Rain gauge notes apply

    follow (Select Schedule 1 or 2, if schedule #2 is used, void note #14) as defined in 2016 R&B

    13. The ESC and P2 inspections for this land disturbing (construction) activity shall

    Engineer

    Dist. Hyd.

    inspection in accordance with IIM-LD-256

    NPDES coordinator responsible for the oversight

    approval of ESC SWM plan modification(s).

    responsible for the review & the coordination

    District Hydraulic Engineer or designee(s)

    permitted projects):

    responsibility or the environmental matters for the project: (required only for

    incorporated by reference into this SWPPP). These individual(s) has/have overall

    form LD-445H for delegation of authority (form 445H for the project is hereby

    the SWPPP General Information Sheets and Inspection Reports (C-107). Reference

    "delegated authority" to sign all reports required by the construction permit including

    (required for erosion and sediment control). The following individual(s) have

    11. List the RLD and other responsible parties for the land disturbance activity:

    Tidewater, Virginia in the Virginia Chesapeake Bay Preservation Act.

    Preservation Area, or equal to or greater than 2,500 square feet in the area defined as

    disturb an area equal to or greater than 10,000 square feet outside the Chesapeake Bay

    construction plan set (or other such documents) for land disturbance activities that

    The SWPPP General Information sheets are to be completed and included in the

    RLD - Responsible Land Disturber

    R&B - Road and Bridge

    IIM - Instructional and Informational Memorandum

    ESC - Erosion and Sediment Control

    EPA - U.S. Environmental Protection Agency

    DEQ - Department of Environmental Quality

    BMP - Best Management Practice

    CBPA - Chesapeake Bay Preservation Act

    record set of plans (or other such documents)for the land disturbance (construction) activity.

    (construction) activity. The updated/revised sheets shall be maintained with the designated

    to reflect changes that may occur during the construction phase of the land disturbing

    shown on the SWPPP General Information sheets is updated/revised as necessary in order

    The VDOT RLD (as defined in the latest IIM 242) will ensure that the information

    VSMP Authority stating coverage not needed)

    Construction General Permit coverage letter: (List VPDES Permit # or Letter from

    support activities located outside of VDOT right of way or easement in the form of the

    5. Written Evidence of permit coverage shall be provided by the contractor for all

    and maintained with the other SWPPP documents for this land disturbance activity.

    identified on these SWPPP General Information Sheets. The names will be updated

    accordance with IIM-LD-256 on these land disturbance construction activities as

    12. The name of the VDOT individual(s) responsible for the oversight inspection in

    required based on the amount of accumulated rainfall in the gage.

    amount of accumulated rainfall in the gage, if any, and (5) whether or not an inspection is

    (2) the time, (3) whether or not rainfall is occurring at the time of the observation, (4) the

    book shall be maintained to record observation information which shall include (1) the date,

    measurable storm event (i.e., 0.25 inches of rainfall or greater in a 24 hour period). A log

    The rain gage shall be observed daily at " " to determine the occurrence of a

    (List location of rain gage).

    appropriate SWPPP documents for this land disturbance activity:

    be provided by the contractor and identified on the record set of plans or in other

    measurable storm event for the purposes of ESC and Pollution Prevention inspections will

    14. The location of the on-site rain gage that will be used to determine the occurrence of a

    shall notify the municipality with jurisdiction over erosion and sediment control activities.

    responsibility of the contractor is discovered discharging into a MS-4, the contractor

    17. If excessive loading of sediment from a land disturbing activity that is not the

    shall initiate corrective actions no later than 5 business days after the initial investigation.

    of the current Construction General Permit. If corrective action is necessary, the contractor

    in accordance with the permits approved standards and specifications required by Part I.B

    and ensure all erosion and sediment control best management practices are being implemented

    the contractor shall investigate the area of concern at the site within 24 hours of discovery

    local watershed with a sediment TMDL that allocates a WLA to VDOT's MS4, (see note #7)

    expected from the project with an implemented ESC plan) that is discovered within a

    16. If there is an excessive loading of sediment from the project (i.e. more than to be

    VDOT LD-445I: AS&S Approval Form (when applicable)

    VDOT C-107 Part I and Part II. All projects that require a permit or SWPPP.

    VDOT LD-445H: Permitted projects only.

    Water Quality Requirement (when applicable)

    VDOT LD-445F: Emergency work projects (when applicable).

    Non-CBPA with BMP projects that have a water quantity BMP.

    VDOT LD-445D: Permitted projects, CBPA projects and Non-permitted,

    VDOT LD-445C: Projects that require a permit, ESC Plan, or SWPPP.

    VDOT LD-445A: Permitted projects only.

    BMP and ESC projects > 10,000 s.f. but

  • 2C(1)

    ***Denotes information that is to be provided/completed by the contractor.

    Denotes information that is to be provided/completed by the VDOT RLD.

    2C(1)

    SECTION III POST CONSTRUCTION STORMWATER MANAGEMENT

    ACRONYMS

    RLD - Responsible Land Disturber

    R&B - Road and Bridge

    IIM - Instructional and Informational Memorandum

    ESC - Erosion and Sediment Control

    EPA - U.S. Environmental Protection Agency

    DEQ - Department of Environmental Quality

    BMP - Best Management Practice

    CBPA - Chesapeake Bay Preservation Act

    SWM - Stormwater Management

    WLA - Waste Load Allocation

    VESCP - Virginia Erosion and Sediment Control Program

    VSMP - Virginia Stormwater Management Program

    VPDES - Virginia Pollutant Discharge Elimination System

    VDOT - Virginia Department of Transportation

    TMDL - Total Maximum Daily Load

    SWPPP - Stormwater Pollution Prevention Plan

    Section IV.

    identified in the applicable sections of the documents identified in the Note 1 of

    6. A description of interim and permanent stabilization practices for the site are

    SWPPP documents for this land disturbance (construction) activity.

    108.03 of the VDOT R&B Specifications and shall be included with the other

    shall be provided by the contractor in accordance with the current edition of Section

    (e.g., grubbing, excavation, grading, utilities and infrastructure installation, etc.)

    1. The intended sequence and timing of activities that disturb soils at the site

    303.03 of the VDOT R&B Specifications.

    operating conditions are identified in the current edition of Sections 107.16 and

    sediment control measures and other protective measures in good and effective

    8. A description and schedule of procedures to maintain vegetation, erosion and

    installed prior to any grubbing operations or other earth moving activities.

    Perimeter controls such as silt fence, diversion dikes, turbidity curtains, etc. shall be

    12. The areas beyond the project's construction limits are to be protected from siltation.