Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio [email protected]
Transcript
Page 1: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

Planning and Implementing aHabitat Project

Mike Pearson PhD, RPBio

[email protected]

Page 2: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

Gordon’s Brook, Langley,

2001

Page 3: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001
Page 4: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

Understanding the SystemWatershed Scale:

Species present seasonallyExisting habitat values and issuesMajor landformsLand use patternsSpatial arrangements of habitats

Site Scale:Species present seasonallyHydrograph and water qualityExisting habitat valuesSoilsDetailed topographic surveyConnections to other habitats

Page 5: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

Site Selection

Bigger Is Better More Degraded Is Better

Linking Good Habitats isBest

Close to Good Habitatis Better

Page 6: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

Seven Design Principles

1. Take a Broad View

Focusing on one or twospecies will likely resultin an inferior project –even for those species

• Over 50 SAR depend onuse riparian, stream andwetland habitats in theFraser Valley

Brian Klinkenberg

Page 7: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

2. Incorporate Existing Features

Seven Design Principles

Design aroundexisting trees

Dig in existingdepressions

Pile spoil againstexisting slopes

Use ‘Found’ Materials

Page 8: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

3. Harness Natural Processes

Seven Design Principles

Succession – plantpredominantly earlysuccessional ‘pioneer’species.

Erosion/Sedimentation– place obstructionsdirectly in the path offlow power to createcomplex, self-sustaining habitatfeatures

Page 9: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

4. Mimic Natural Landforms

Seven Design Principles

Avoid The Trench-Bench-Berm Approach

Page 10: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

• Vary bank slopes andchannelwidths to mimic naturalpatterns

• Leave riparian area soils ‘roughand loose’

• Most habitat value is in the finedetails scale of metres to tens ofmetres

4. Mimic Natural Landforms

Seven Design Principles

Page 11: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

5. Cluster Features At Several Scales

Seven Design Principles

Page 12: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

6. Create at Disturbance

Seven Design Principles

Page 13: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

7. Embrace the Random

Seven Design Principles

• Conceptual Plans and field fits by skilled practitionersproduce the best projects

Most habitat is formed by random (stochastic) events.Building random events into construction improvesprojects

• Relinquish control of details when possible

Page 14: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

Permits and Notifications1. First Nations

• This is all unceded Sto:lo / Coast Salish Territory.

• There are many archeological and culturally important sites,some mapped, many not.

• Fish habitat is linked to the right to fish.

• Consult with First Nations Bands and Organizations with aninterest in the site.

• People of the River Referrals Office (PRRO) coordinatesreferrals for many bands using a web portal.

Page 15: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

Permits and Notifications

2. Province of BC• Scientific Fish Collection Permit

(for Fish Salvages)

• Water Sustainability Act• Approval or Notification

required for ‘changes to thenature of a stream’ or‘activities or constructionwithin a stream… )

Page 16: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

Permits and Notifications

3. Fisheries and Oceans Canada• Fish Collection Permit (for Fish Salvages)

• Fisheries Act (?)• Submit a notification you should get a letter of advice back.• It doesn’t mean much.• Hopefully this will change

• Species at Risk Act Permit (may involve Environment Canada)• Required for fish salvages and/or habitat changes involving

Critical Habitat of SARA listed species

Page 17: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

Permits and Notifications

4. Local Government• Requirements vary, depending on bylaws• Almost all regulate soil removal and deposition on properties

• Keep them informed. They are the most likely recipients ofconcerned phone calls.

5. BC One Call• 1-800-474-6886

• You would be surprised atwhere some utilities areburied…

Page 18: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

Site Logistics

What goes where when and how long can it stay there?

Page 19: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

Typical Order of Operations

1. Strip sod and topsoil,stockpile separately

2. Rough excavation

Page 20: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

Order of Operations

3. Detailed excavation /landscaping

4. Large woody debrisinstallation

Page 21: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

Order of Operations

5. Riffle construction 6. Streambed substrate placement

Page 22: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

7. Topsoil spreading

Order of Operations

8. Seedingand planting

Page 23: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

Choosing Equipment

200 Track Excavator with Thumb

• Very powerful• Limited reach (10m)• Large bucket

Page 24: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

Choosing Equipment

200 Long Reach Excavator

• Up to 20 m reach

• Smaller bucket

• No thumb

Page 25: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

Choosing Equipment

For tight spots

Limited reach andbucket size

Small Track Excavator (80-100)

Page 26: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

Choosing Equipment

• Transport long logsand large stumpsefficiently

80 Yard End Dump Trucks

Page 27: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001
Page 28: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

March 2002

October 2002

August 2002

November 2004

Gordon’s Brook, Langley

Page 29: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

August 2001 November 2001

September 2002 February 2005

Gordon’s Brook, Langley

Page 30: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

Salish Sucker Density

0

5

10

15

20

25

300.5

1.5

3.0

4.0

5.0

6.0

7.5

8.5

CPUE

Fre

quency

2002 20042007

2010

Page 31: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001
Page 32: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001
Page 33: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001
Page 34: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001
Page 35: Planning and Implementing a Habitat Project - SCCP...Planning and Implementing a Habitat Project Mike Pearson PhD, RPBio mike@pearsonecological.com Gordon’s Brook, Langley, 2001

Thank-You!