Plant Design Integration, General Arrangement Drawings. E. D. Perry. Plant Design Integration. Requirements Allocate space within NCSX Facility - Includes test cell and adjacent areas Maintain 3D model and use it to extract general arrangement drawings Update general arrangement drawings - PowerPoint PPT Presentation
Popular Tags:
9
SC Project Review of NCSX, April 8-10, 2008 SC Project Review of NCSX, April 8-10, 2008 Plant Design Integration, General Arrangement Drawings E. D. Perry
Transcript
Page 1: Plant Design Integration,  General Arrangement Drawings

SC Project Review of NCSX, April 8-10, 2008SC Project Review of NCSX, April 8-10, 2008

Plant Design Integration,

General Arrangement Drawings

E. D. Perry

Page 2: Plant Design Integration,  General Arrangement Drawings

SC Project Review of NCSX, April 8-10, 2008E. D. Perry - page 2

Plant Design Integration

• Requirements• Allocate space within NCSX Facility - Includes test cell and adjacent areas

• Maintain 3D model and use it to extract general arrangement drawings

• Update general arrangement drawings• Distribute to all NCSX WBS Managers monthly

• Interfaces• Include input from

• All WBS elements which have items to install

• Safety personnel

• Operations personnel

• Maintenance/upgrade personnel

Page 3: Plant Design Integration,  General Arrangement Drawings

SC Project Review of NCSX, April 8-10, 2008E. D. Perry - page 3

Plant Design Integration

• Design status• 3D plant model developed over the past 8 years

• Updated general arrangement drawings extracted from the 3D model are being emailed to WBS managers and posted on website

• Brainstorming meetings being held for complex interfaces

• Cost and schedule estimates• To update models during April/May 2008:

• 10 MD designer

• 5 MD engineer

• To maintain model/drawings until CD4 (based on cost of general arrangement drawings for NSTX)• 1.5 MD per month engineer

• 1 MD per month designer

Page 4: Plant Design Integration,  General Arrangement Drawings

SC Project Review of NCSX, April 8-10, 2008E. D. Perry - page 4

General Arrangement Drawings

• NCSX Test Cell Model

Page 5: Plant Design Integration,  General Arrangement Drawings

SC Project Review of NCSX, April 8-10, 2008E. D. Perry - page 5

General Arrangement Drawings

• General Arrangement drawing of NCSX Test Cell above platform

Page 6: Plant Design Integration,  General Arrangement Drawings

SC Project Review of NCSX, April 8-10, 2008E. D. Perry - page 6

General Arrangement Drawings

• General Arrangement drawing of NCSX Test Cell below platform

Page 7: Plant Design Integration,  General Arrangement Drawings

SC Project Review of NCSX, April 8-10, 2008E. D. Perry - page 7

General Arrangement Drawings

• General Arrangement drawing of NCSX Test Cell elevation• Basement / first floor / platform / catwalk around top of machine

Page 8: Plant Design Integration,  General Arrangement Drawings

SC Project Review of NCSX, April 8-10, 2008E. D. Perry - page 8

3D Model of NCSX Platform

• 3D Model of NCSX Platform• Reviewing Life Safety Code requirements

• Reviewing potential equipment interferences with platform legs

• Reviewing placement of each item on/under platform to assure that all items can be installed, maintained and de-installed

Page 9: Plant Design Integration,  General Arrangement Drawings

SC Project Review of NCSX, April 8-10, 2008E. D. Perry - page 9

Integrated Plant Design Related Items

• Review installation plans from all WBS Managers to assure that each piece does not interfere with other installations / maintenance / operations• Review crane coverage and roll-up door sizes with respect to items which

need to be moved into the NCSX Test Cell (NCTC)

• Also review equipment to be used to move material into NCTC

• Establish staging areas for items waiting to be installed

• Coordinate installation of plant services (electric, air, lighting, HVAC etc) with Facilities Division