+ All Categories
Home > Documents > Plotting Date: SECTION C: TRAFFIC...

Plotting Date: SECTION C: TRAFFIC...

Date post: 18-Aug-2020
Category:
Upload: others
View: 1 times
Download: 0 times
Share this document with a friend
8
0 0 <:'! I- SECTION C: TRAFFIC CONTROL Equation: Sta. 204+22.8 Bk = 0+00.0 Ah 16 R 78 W BEGIN P 0248( I 5)225 Sto. 117+93.0 MRM 225.34 + 0.028 Exception: Sta. a 41 9+68.5 to Sta. a 420+69.5 St,. 11c43-1 I 4-200 R 77 W R 76 W STATE OF SOUTH DAKOTA Plotting Date: 1------PR_O_JE_CT ___ ---I SHEET P 0248(15)225 C1 03/25/2020 INDEX OF SHEETS C1 C2-C4 C5-C6 C7-C8 General Layout with Index Estimate with General Notes & Tables Fixed Location Signs & Special Drawings Standard Plates Equation: Sta. a I 205+28.9 Bk Sta. b 0+00.0 Ah R 75 W TOTAL SHEETS CB -------------------1 dentico I Po int s---------__J END P 0248( I 5)225 Equation: Sta. b 629+04.3 Bk = Sto. b 789+ 76.6 Sta.b 775+54.3 Ah MRM 261 . 76 + 0.006 24 19 w > I- 25 .. 30 0 .., N D .., \ D D w w > > .. 32 .. 33 36 31 U) ,._ 32 N N N N .., "' "' R 74 W R 73 W .!!1 [i:
Transcript
Page 1: Plotting Date: SECTION C: TRAFFIC CONTROLapps.sd.gov/HC65C2C/EBS/lettings/electronicplans/07C3...634E0110 Traffic Control Signs 1,352.0 SqFt 634E0120 Traffic Control, Miscellaneous

0 0 <:'!

I-

SECTION C: TRAFFIC CONTROL

Equation: Sta. 204+22.8 Bk = 0+00.0 Ah

16

~

R 78 W

BEGIN P 0248( I 5)225 Sto. 117+93.0 MRM 225.34 + 0.028

Exception: Sta. a 41 9+68.5 to Sta. a 420+69.5 St,. 11c43-1 I 4-200

R 77 W R 76 W

STATE OF SOUTH

DAKOTA

Plotting Date:

1------PR_O_JE_CT ___ ---I SHEET

P 0248(15)225 C1 03/25/2020

INDEX OF SHEETS C1

C2-C4

C5-C6

C7-C8

General Layout with Index

Estimate with General Notes & Tables

Fixed Location Signs & Special Drawings

Standard Plates

Equation: Sta. a I 205+28.9 Bk Sta. b 0+00.0 Ah

R 75 W

TOTAL SHEETS

CB

-------------------1 dentico I Po int s---------__J

END P 0248( I 5)225

Equation: Sta. b 629+04.3 Bk = Sto. b 789+ 76.6 Sta.b 775+54.3 Ah MRM 261 . 76 + 0.006

24 19

w > I-

25 .. 30 0

.., N D ..,

\ D D w w

> > .. 32 ..

33 36 31 U) ,._ 32 N N N N .., "' "' ■

R 74 W R 73 W

.!!1 [i:

Page 2: Plotting Date: SECTION C: TRAFFIC CONTROLapps.sd.gov/HC65C2C/EBS/lettings/electronicplans/07C3...634E0110 Traffic Control Signs 1,352.0 SqFt 634E0120 Traffic Control, Miscellaneous

0 0 <:'!

SECTION C ESTIMATE OF QUANTITIES

BID ITEM ITEM

NUMBER QUANTITY UNIT

633E1200 High Build Waterborne Pavement Marking Pain t, 2,044 Gal White

633E1205 High Build Waterborne Pavement Marking Paint, 928 Gal Yellow

634E0010 Flagging 1,250.0 Hour

634E0020 Pilot Car 675.0 Hour

634E0110 Traffic Control Signs 1,352.0 SqFt

634E0120 Traffic Control , Miscellaneous Lump Sum LS

634E0630 Temporary Pavement Marking 76.8 Mile

TRAFFIC CONTROL

The Contractor shall designate an employee to be responsible for the maintenance of traffic. The Engineer must approve the employee selected. The name and phone number of person(s) shall be provided to the SD Department of Transportation (605-842-0810), SD Highway Patrol (Rapid City State Radio (605-393-8121)), SD Highway Patrol (Chamberlain (605-734-4560)) and Lyman County Sheriff Department (605-869-2267).

All traffic control devices shall be in "like new" condition

SEQUENCE OF OPERATIONS

The Contractor will submit a sequence of operations for approval two weeks prior to the preconstruction meeting.

TRAFFIC CONTROL ALLOTMENTS

For the planning of the traffic control sequencing purposes, the Contractor has been allotted, to be used at his discretion, sufficient signage quantities to develop his work schedule as follows:

2- Lane closures with Flaggers

GENERAL TRAFFIC CONTROL

Existing guide, route , informational logo, regulatory, and warning signs will be temporarily reset and maintained during construction. Removing , relocating, covering , salvaging, and resetting of existing traffic control devices, including delineation, will be the responsibility of the Contractor. Cost for this work will be incidental to the contract unit prices for the various items unless otherwise specified in the plans. Any delineators and signs damaged or lost will be replaced by the Contractor at no cost to the State.

All temporary traffic control sign locations will be set in the field by the Contractor and verified by the Engineer prior to installation .

Portable sign supports will not be located on sidewalks, bicycle facilities , or other areas designated for pedestrian or bicycle traffic.

All construction operations will be conducted in the general direction of traffic movement.

If there is a discrepancy between the traffic control plans, standard plates, and the MUTCD, whichever is more stringent will be used, as determined by the Engineer.

Unless otherwise stated in these plans, work will not be allowed during hours of darkness.

Traffic Control Signs, as shown in the Estimate of Quantities, are estimates. Contractor's operation may require adjustments in quantities, either more or less. Payment will be for those signs actually ordered by the Engineer and used.

Fixed location signing placed more than 4 calendar days prior to the start of construction will be covered or laid down until the time of construction. The covers must be approved by the Engineer prior to installation . The cost of materials, labor, and equipment necessary to complete this work will be incidental to other contract items. No separate payment will be made.

All fixed location signs, sign posts, and breakaway bases will be removed within 7 calendar days following pavement marking .

All haul trucks will be equipped with an additional flashing amber light that is visible from the backside of the haul truck. The costs for the flashing amber lights will be incidental to the various related contract items.

At no time will a vertical drop-off of greater than 3 inches be left overnight adjacent to the traveled way. The Contractor will utilize embankment material to ensure a 3-inch vertical drop-off is not exceeded . The slope of the embankment material will not be steeper than a 4:1 within 30 feet of the traveled way.

Traffic will be maintained on the driving lanes. Use of the shoulder as a driving lane will not be permitted . Any damage to the shoulder due to rerouted traffic or Contractor's equipment will be repaired at no expense to the Department.

The Contractor will furnish , install , maintain , and remove TRUCK CROSSING (W8-6) signs daily. The TRUCK CROSSING signs will be displayed always when haul vehicles are hauling material. When hauling conditions no longer exist, the signs will be covered or removed from view. The exact number and location will be determined during construction. Payment for additional signs will be based on the contract unit price per square foot for "Traffic Control Signs".

A mobile work operation will be allowed provided the rumble strip or rumble stripe grooving, flush sealing , and pavement marking can be completed satisfactorily by a continuously moving work operation. A mobile work operation will require approval by the Engineer.

A shadow vehicle , equipped with flashing amber light and a ROAD MACHINERY AHEAD sign prominently displayed, shall be used in advance of landscaping, clean up, and other mobile work activities. The cost of ROAD MACHINERY AHEAD sign shall be incidental to the contract lump sum price for "Traffic Control , Miscellaneous".

The exact number and location of "Truck Crossing" signs will be determined on construction.

STATE OF SOUTH

DAKOTA

____ P_R_OJ_EC_T ___ ---1 SHEET

P 0248(15)225 C2 Plotting Date: 03/25/2020

TRAFFIC CONTROL FOR ASPHALT CORING

Coring operations shall be completed during daylight hours only. Traffic control for coring operations shall be executed by following the "Special Detail for Mobile Operations for Asphalt Coring" sheet.

BUMP MARKERS

Type 1 Object Markers need to be back-to-back for two-way traffic operations.

Orange bump markers will be placed adjacent to the bump location. The bump marker details are shown in the following drawing. The steel delineator post will be a 1.12 lb/ft flanged channel steel post for ground mounted installation. If the duration is less than 3 days, the Type 1 Object Marker can be installed on temporary supports.

BUMP (W8-1) signs with appropriate ADVISORY SPEED (W13-1 P) plaques will be placed 500 feet in advance of the bump or as approved by the Engineer for adequate sight distance.

BUMP signs shall be used in conjunction with the cold milling transitions at the end of the day. Bump signs shall also be placed at the end of each days paving.

All costs for bump markers, bump signs, and advisory speed plaques will be incidental to the contract unit price per square foot for 'Traffic Control Signs".

b'-D' Minim um

- ---J'-0' Mfn, ---•-ti

4'-0'

~ _l_ . . ·:•··· .. . ·.•· .. . ·:•

RED OR ORANGE FLAG {OPTIONAL)

WOOD SLAT OR

ALUMIN UM POST

TYPE I OBJECT MARKER

STEEL DELI NEAT OR POST

TOTAL SHEETS

CB

.!!1 [i:

Page 3: Plotting Date: SECTION C: TRAFFIC CONTROLapps.sd.gov/HC65C2C/EBS/lettings/electronicplans/07C3...634E0110 Traffic Control Signs 1,352.0 SqFt 634E0120 Traffic Control, Miscellaneous

0 0 <:'!

l

FLAGGING

Operations will be conducted so that the traveling public will not have to wait longer than 15 minutes at the flagger station.

It is required that the flaggers and pilot car operators be able to communicate with one another. If an emergency vehicle needs to pass through the project, the Contractor will be required to expedite traffic movement. All costs associated with this will be incidental to the contract unit price per hour for "Flagging".

TEMPORARY PAVEMENT MARKING

The total length of no passing zone on this project is estimated to be 24.16 miles.

It is estimated that 114 DO NOT PASS (R4-1) and 114 PASS WITH CARE (R4-2) signs will be required to mark the no passing zones, should the Contractor elect to use these signs.

Temporary flexible vertical markers (tabs) will be used to mark dashed centerline, No Passing Zones, and applicable lane lines. Paint will not be allowed for temporary pavement marking on the asphalt concrete wear course or after application of the flush seal.

Covers on the tabs will be sufficiently secured to prevent traffic from dislodging the cover and when removed , the covers will be properly disposed of. The Contractor will remove and properly dispose of the tabs after permanent pavement marking is applied . Method of removal will be nondestructive to the road surface and will be accomplished within one week of completion of the permanent pavement marking.

Any temporary flexible vertical markers (tabs) with covers removed before the flush seal will be replaced prior to application of the flush seal.

Quantities of Temporary Pavement Markings consist of:

1) One pass on top of the leveling lift of Asphalt Concrete (3.5 miles)

2) One pass on top lift of Asphalt Concrete (36.626 miles) 3) One pass on top of the Flush Seal (36.626)

Full reflectivity of all temporary flexible vertical markers (tabs) is required at all times. The Contractor will be required to replace any missing or non­reflective tabs at no additional cost to the State.

If the flush seal is eliminated, the application of the temporary pavement marking on top of the flush seal will be eliminated. No adjustment in the contract unit price for "Temporary Pavement Marking" will be made because of a variation in quantities.

In the absence of a signed lane closure or pilot car operation, FLAGGER (W20-7) symbol signs and flaggers , or a shadow vehicle with rotating yellow lights or strobe lights will be positioned on the shoulder in advance of workers for both directions of traffic during the installation and removal of the temporary flexible vertical markers (tabs). The traffic control device used will be moved intermittently to provide proper warning of the work operation. A ROAD WORK AHEAD (W20-1) sign , a WORKER (W21-1) symbol sign or a BE PREPARED TO STOP (W3-4) sign will be mounted on the rear of the shadow vehicle. The method of traffic control used by the Contractor for this work must be approved by the Engineer.

Prior to nightfall , tabs will be required to mark centerline on segments of roadway where existing centerline markings have been removed and new markings have not been installed.

PERMANENT PAVEMENT MARKING PAINT

All materials will be applied as per manufacturer's recommendations.

The Contractor shall advise the Engineer a minimum of 3 weeks prior to the application of the permanent pavement marking to allow the State to check and mark the location of no passing zones.

The application of permanent pavement marking paint may not begin until 7 calendar days following completion of fog seal and will be completed within 14 days following completion of fog seal; and be completed no more than 21 days following the completion of the asphalt surface treatment.

For each working day the application of permanent pavement marking paint remains uncompleted after the 14 calendar days, the Contractor will be assessed $250 liquidated damages.

This provision applies up to the Contract completion date, as extended. After the completion date, liquidated damages will be assessed in accordance with Section 8.8, until the permanent pavement marking is completed, even though the project may be open to traffic.

The Contractor will be required to inventory and mark, with appropriate colored tabs , the extent and location of the existing word messages, turn arrows, stop bars, railroad crossings , pedestrian crossings, etc. before the markings are obliterated. The Engineer will be provided a copy of the pavement marking inventory.

HIGH BUILD WATERBORNE PAVEMENT MARKING PAINT

All materials will be applied as per manufacturer's recommendations.

This material will consist of a durable high build , low voe, fast drying, waterborne traffic paint with a 100% acrylic polymer (Arkema DT-400, Dow HD-21A, or equivalent). The Contractor will provide certification that the material is one of the following products or an equivalent as approved by the Operations Traffic Engineer:

Diamond Vogel's Waterborne High Build Polymer Marking Paint Ennis-Flint's High Build Polymer Marking Paint

No further testing of this material will be required . Reflective media will consist of glass beads.

I STATE OF I PROJECT I TOTAL 1-------------1 SHEET SHEETS SOUTH I

DAKOTA P 0248(15)225 C3 I C8

Plotting Date: 03/25/2020

RATES OF MATERIALS FOR HIGH BUILD WATERBORNE PAVEMENT MARKING PAINT

Solid 4" line = 27.8 Gals/Mile Glass Beads = 8 Lbs/Gal.

All cost for materials , labor and equipment necessary to furnish and install the pavement markings will be incidental to the contract unit price for the respective High Build Waterborne Pavement Marking Paint items.

ITEMIZED LIST FOR TRAFFIC CONTROL SIGNS

CONVENTIONAL ROAD

SIGN SIGN DESCRIPTION NUMBER SIGN SIZE

SQFT SQFT

CODE PER SIGN

W3-4 BE PREPARED TO STOP 2 48"" X 48"" 16.0 32 .0 W8-1 BUMP 8 48"" X 48"" 16.0 128.0 W8-6 TRUCK CROSSING 2 48"" X 48"" 16.0 32 .0 W8-11 UNEVEN LANES 4 48'" X 48" 16.0 64 .0 W8-17 SHOULDER DROP-OFF (symbol) 36 48"" X 48"" 16.0 576.0 W20-1 ROAD WORK AHEAD 15 48" X 48" 16.0 240.0 W20-4 ONE LANE ROAD AHEAD 5 48" X 48"' 16.0 80.0 W20-7 FLAGGER (symbol) 6 48" X 48" 16.0 96.0 W21-1 WORKERS (symbol) 2 48" X 48" 16.0 32 .0 G20-1 ROAD WORK NEXT 37 MILES 2 36" X 18" 4.5 9.0 G20-2 END ROAD WORK 14 36" X 18" 4.5 63 .0

CONVENTIONAL ROAD 1352.0 TRAFFIC CONTROL SIGNS SQFT

.!!1 [i:

Page 4: Plotting Date: SECTION C: TRAFFIC CONTROLapps.sd.gov/HC65C2C/EBS/lettings/electronicplans/07C3...634E0110 Traffic Control Signs 1,352.0 SqFt 634E0120 Traffic Control, Miscellaneous

UNDIVIDED ROADWAY

0 QI • ) ...I

{[ 0 (.) (.) <:'!

E E E 0 0 E .. ..

30~ 0 .... .... 0 .:: N N .::

ffi 10' a.~ ~ ~ ~[ ! § I- ...I ...I I-

:E ~ ~ :E ~ 3:: 3:: ~

ID • • • • ID a::: a::: :J

□ 11' 11' [ :J

u 12' 12' u - -..._ ----w w

i I-:E

~ □ [ 3:: ~ ...I • • ::, <t. Ii ~ 11'-8" 11'-8"

U)

12' □ 12' I 12' [ 12' J

- I -- -11'-8" 11'-2"

~ ., _.i ;: -' i 0 <.> 0 <.> ...1 E ...1 E a: ~_g ~ _g ~

~ ;,.~;,.~;i

I- >< ~~ ~a::: -...I (/) < w CU z wa::: 2 !:: f2 :!=:

~ C) w

~ I- >-::::iw z z ~a::: 11. u en ::::i

oz ::, ~ w ::::, (/) < < 0 z 0 cU w I- ::c CL 2 ::c wa::: z (/)

20 U) 0 U) !:: 0 z C) :!=: 11.

;~ ::::iw 11. u oz <

CL a::: w I-z (/) i~ 20

··:r ' ...I

30' (.)

.s w N ~ 0 I-

~ :E ~

::c

i 3:: 3::

• ...I • ~ • l 12' 12'

.,, w "' - -~

PERMANENT PAVEMENT MARKING PAINT PAVEMENT MARKING

Typical pavement marking as shown on this sheet will be

applied throughout the entire length of und ivided roadway .

Traffic Control will be incidental to the cost of application . The

striper and advance or trailing warning veh icle will be equipped

with flashing amber lights and advance warning arrow board .

Application rates will be as follows:

Four Lane Roadway Two Lane Roadway

(Rates for one line) (Rates for one line) Solid Yellow Centerline Dashed Yellow Centerline

Rate= 27 .8 Gals./Pass-Mile Rate= 7 Gals./Pass-Mile Dashed White Laneline Solid Yellow Centerline

Rate= 7 Gals./Pass-Mile Rate= 27 .8 Gals ./Pass-Mile Solid White Edgeline Solid White Edgeline

(Not applicable in curb and gutter) Rate= 27 .8 Gals./Pass-Mile

Rate= 27 .8 Gals./Pass-Mile

4" Yellow Skip Centerline (when not adjacent to a 4" Yellow No Passing

Zone) will be placed consistently to the south or east side of centerline .

ESTIMATED QUANTITIES (BASED ON ONE APPLICATION)

PAINT QUANTITY

WHITE 2,044 GALLONS

YELLOW 928 GALLONS

I STATE OF II-____ PR_O_JE_CT ___ --11 SHEET I TOTAL SHEETS

SOUTH I 1-----+----I

DAKOTA P 0248(15)225 I C4 I cs Plotting Date: 03/25/2020

.!!1 [i:

Page 5: Plotting Date: SECTION C: TRAFFIC CONTROLapps.sd.gov/HC65C2C/EBS/lettings/electronicplans/07C3...634E0110 Traffic Control Signs 1,352.0 SqFt 634E0120 Traffic Control, Miscellaneous

0 0 <:'!

A=

z

ROAD WORK NEXT 37 MILES

G20-I 136"XI8"l

B= [t()

ROAD WORK G20·2

(36"Xl8")

C=

Equation: Sta. 204+22.8 Bk = 0+00.0 Ah

~ =,r= ~°\l- 7""TiJ-------->s~ ~ P~--+-~ ~ ~J---~ --d--~ ---+::>,_.:~ t--

R 78 W

BEGIN P 0248( I 5)225

Sta. I I 7+93.0 MRM 225.34 + 0.028

Fixed Location Signs

Excep ion: Sta. a 419+68.

"'

420+69.5 4-200

Equation: Sta. b 62 Sta. b 775+54.3 Ah

0 :::m,=='-<;='"'r------:::---;;;;:---- .....1.F ===i~ :::5l1~ :;;;:::.-r ~ ~ £ =--:-- ----U- _l___j t--

R 75 W Lu > -0:

N N

33 36 "' N

"' "'

STATE OF SOUTH

DAKOTA

Plotting Date:

z

t--

R 73 W

1------P_RO_J_EC_T ___ ---I SHEET

P 0248(15)225 cs 03/25/2020

END P 0248( I 5)225 Sta. b 789+ 76.6

MRM 261. 76 + 0.006

TOTAL SHEETS

CB

.!!1 [i:

Page 6: Plotting Date: SECTION C: TRAFFIC CONTROLapps.sd.gov/HC65C2C/EBS/lettings/electronicplans/07C3...634E0110 Traffic Control Signs 1,352.0 SqFt 634E0120 Traffic Control, Miscellaneous

0 0 <:'!

SPECIAL DETAIL FOR MOBILE OPERATION FOR ASPHALT CORING

Shadow and work vehicles shall display rotating lights or strobe lights.

◊ 11 I

Work Vehicle --- (As Needed)

• • • • (Optional)

Truck Mounted Attenuator (Recommended)

STATE OF SOUTH

DAKOTA

Plotting Date:

1------P_RO_J_EC_T ___ ---I SHEET

P 0248(15)225 C6 03/25/2020

TOTAL SHEETS

C8

.!!1 [i:

Page 7: Plotting Date: SECTION C: TRAFFIC CONTROLapps.sd.gov/HC65C2C/EBS/lettings/electronicplans/07C3...634E0110 Traffic Control Signs 1,352.0 SqFt 634E0120 Traffic Control, Miscellaneous

0 0 <:'!

Posted Spacing of t Speed Advance Warning

Install additional UNEVEN LANES signs at 2 mile intervals throughout the entire length of the uneven area and at affected major intersections, edge of towns, and other sites deemed necessary.

Prior to Work

(M.P.H.l 0 - 30

35 - 40 45 - 50

55 60 - 75

Published Date: 1st Qtr. 2020

s D D 0 T

GUIDES FOR TRAFFIC CONTROL DEVICES UNEVEN ROAD SURFACE

Signs <Feet)

(Al 200 350 500 750

1000

Apr!/ 15, 2015

PLATE NUMBER

634.22

Sheet I of I

Posted Spacing of Spacing of Speed Advance Warning Channelizing

Prior to Signs Devices Work !Feetl (Feetl

(M.P.H.l (Al (Gl 0 - 30 200 25 35 - 40 350 25

45 500 25 50 500 50 55 750 50

60 - 65 I 000 50

_______. F I a g g er

■ Channelizing Dev ice

For low-volume traffic situations with short work zones on straight roadways where the flogger is visible to road users approaching from both directions, a s ingle flogger may be used.

The ROAD WORK AHEAD and the END ROAD WORK signs may be omitted for short duration operations (I hour or lessl.

For tack and / or flush seal operations, when floggers ore not being used, the FRESH OIL sign (W21-2l shall be displayed in advance of the liquid asphalt areas.

Flashing warning lights and / or flags may be used to coll attention to the advance warning signs.

The channeliz ing devices shal I be drums or 42" cones,

STATE OF SOUTH

DAKOTA

Plotting Date:

Warning sign sequence ~ in opposite direction some OS below.

l. ■

0 N

■ ■

>, 0 :i' L I Cl) 0 Co. 3' 0

011-1-0j CD.Q - - C4-

0 4-...J 0

<(

L Cl) I­C 0

PROJECT

P 0248(15)225 03/25/2020

Channelizing devices are not required along the centerline adjacent to work area when pilot cars ore utilized for escorting traffic through the work area,

<Optionoll

ll!IOM 01/0!1 ON3

Channelizing devices and floggers shall be used at intersecting roads to control intersecting road traffic as required.

The buffer space should be extended so that the two-way traffic taper is placed before a horizontal or vertical curve to provide adequate sight distance for the flogger and queue of stopped vehicles.

The length of A may be adjusted to fit field conditions.

Published Date: 1st Qtr. 2020

s D D 0 T

<(

t

GUIDES FOR TRAFFIC CONTROL DEVICES LANE CLOSURE WITH FLAGGER PROVIDED

June 3, 2016

PLATE NUMBER

634.23

Sheet I of I

SHEET

C7

TOTAL SHEETS

C8

.!!1 [i:

Page 8: Plotting Date: SECTION C: TRAFFIC CONTROLapps.sd.gov/HC65C2C/EBS/lettings/electronicplans/07C3...634E0110 Traffic Control Signs 1,352.0 SqFt 634E0120 Traffic Control, Miscellaneous

0 0 <:'!

G' to 12'

E E :J E :J

·c= E

~ C

~ LO ;;.._

RURAL DISTRICT

* E :J E

;;.._ C Walkway ~

LO

URBAN DISTRICT • If the bottom of supplemental plote is

mounted lower than 7 feet above a pedestrian walkway, the supplemental plate should not project more than 4" into the pedestrian facility.

G' to 12'

RURAL DISTRICT WITH SUPPLEMENTAL PLATE

6' Minimum

RURAL DISTRICT 3 DAY MAXIMUM

E :J E

E ,§ :J :J ,f; E E C ::. C ::. ::. LO ;;.._ Sf"

Sign shall be level.

<Not applicable to regulatory signs)

September 22. 2014

Published Date: 1st Otr. 2020

s D D 0 T

CRASHWORTHY SIGN SUPPORTS (Typical Construction Signing)

PLATE NUIIBER

634.85

Sheet I of I

STATE OF SOUTH

DAKOTA

1------P_RO_J_EC_T ___ ---I SHEET

Examples of~ ,/ GO" Chord Line \\/

Clearance Checks /

' ' \

\

\

P 0248(15)225

Plotting Date: 03/25/2020

__ ___ ___ ____ _ r-Anchor Post or Slip Base ,, - .,,,,....- -..... .. .. 1....

/ '

\

\

' I

I ,'

/

- ------ --

,,/"-.__ 120" Diameter ..,,- ,,, !Perimeter of stub height

clearance checks)

PLAN VIEW !Examples of stub height clearance checks)

Top of Anchor Post or Slip Base

Chord Line_/

Ground Line

ELEVATION VIEW GENERAL NOTES:

The top of anchor posts and slip bases SHALL NOT extend above a GO" chord line within a 120" diameter circle around the post with ends 4" above the ground.

At locations where there is curb and gutter adjacent to the breakaway sign support, the stub height shall be a ma x imum of 4" above the ground I ine at the localized area adjacent to the breakaway support stub.

The 4" stub height clearance is not necessary for U-channel lap splices where the support is designed to yield (bend) at the base.

Published Date: 1st Otr. 2020

s D D 0 T

BREAKAWAY SUPPORT STUB CLEARANCE

July I, 2005

PLATE NUIIBER

634.99

Sheet I of I

ca TOTAL

SHEETS

ca

.!!1 [i:


Recommended