Make Dinner
1.0.0Plan Menu
2.0.0Grocery
Shopping
3.0.0Prepare Meal
4.0.0Set Table
5.0.0Serve
6.0.0Clean Up
2.1.0Write
Shopping List
2.2.0Buy Food
2.3.0Buy Drinks
2.2.1Meat
2.2.2Produce
2.2.3Bread
2.3.1Wine
2.3.2Soda
2.4.3Coffee
3.1.0Slice Bread
3.2.0Prepare Salad
3.3.0Prepare Entree
3.2.1Wash
Vegetables
3.2.2Toss Salad
3.3.1Chop
Vegetables
3.3.2Cook Chicken
4.1.0Lay Tablecloth
4.2.0Place Settings
4.2.1Plates
4.2.2Utensils
61.0Store
Leftovers
6.2.0Wash Dishes
61.0Appetizer
6.2.0Salad
6.2.0Entree
6.2.0Dessert
Make Dinner
1.0.0Plan Menu
2.0.0Grocery
Shopping
3.0.0Prepare Meal
4.0.0Set Table
5.0.0Serve
6.0.0Clean Up
2.1.0Write
Shopping List
2.2.0Buy Food
2.3.0Buy Drinks
2.2.1Meat
2.2.2Produce
2.2.3Bread
2.3.1Wine
2.3.2Soda
2.4.3Coffee
3.1.0Slice Bread
3.2.0Prepare Salad
3.3.0Prepare Entree
3.2.1Wash
Vegetables
3.2.2Toss Salad
3.3.1Chop
Vegetables
3.3.2Cook Chicken
4.1.0Lay Tablecloth
4.2.0Place Settings
4.2.1Plates
4.2.2Utensils
61.0Store Leftovers
6.2.0Wash Dishes
61.0Appetizer
6.2.0Salad
6.2.0Entree
6.2.0Dessert
Make Dinner1.0.0Plan Menu 1h
2.0.0Grocery
Shopping (1.75h)
3.0.0Prepare Meal
(3.25h)
4.0.0Set Table
(.75h)
2.1.0Write Shopping
List 1h
2.2.0Buy Food (1h)
2.3.0Buy Drinks
(.75h)
2.2.1Meat .25h
2.2.2Produce .5h
2.2.3Bread .25h
2.3.1Wine .25h
2.3.2Soda.25h
2.4.3Coffee .25h
3.1.0Slice Bread .25h
3.2.0Prepare Salad
(.75h)
3.3.0Prepare
Entrée (2.25h)
3.2.1Wash Veg (.25h)
3.2.2Cut Veg .25h
3.3.1Chop Veg .25h
3.3.2Cook Chick. (2h)
4.1.0Tablecloth .25h
4.2.0Settings (.5h)
4.2.1Plates .25h
4.2.2Utensils .25h
3.2.2Toss Salad .25h
5.0.0Serve
EmilyChrisRobertClaire
Make Dinner
1.0.0Plan Menu 1h
3.0.0Prepare Meal
(3.25h)
2.0.0Grocery Shopping (1.75h)
3.1.0Slice Bread .25h
3.3.0Prepare Entrée (2.25h)
3.2.0Prepare Salad
(.75h)
Ready to Serve
4.0.0Set Table .75h
Begin Project
Critical Path: Longest sequence of a plan must be time for the complete on date. An activity on the critical path cannot be started until its predecessor activity is complete; if it is delayed for a, the entire project will be delayed for a day unless the activity following the delayed activity is completed a day earlier. http://www.businessdictionary.com/definition/critical-path.html#ixzz43HU1vftJ
Make Dinner
Plan Menu Prepare MealGrocery Shopping
Slice Bread
Prepare EntréePrepare Salad
Set Table
Serve Meal Clean Up
Appetizer
Salad Entree Dessert
Begin12:00pm
Ready to Serve6:00pm
Cleanup7:30pm
End8:30pm
Go to Store2:00pm