1 PM report International & UK programmes Overview Reconstructing the schedule The UK Project Management team Progress with major subsystems Substation upgrade Space, staffing and skills Andy Nichols, STFC, UKNF/MICE PSAG, 14-6-11
Transcript
Page 1: PM report International & UK programmes

1

PM reportInternational & UK programmes

• Overview• Reconstructing the schedule• The UK Project Management team• Progress with major subsystems• Substation upgrade• Space, staffing and skills

Andy Nichols, STFC, UKNF/MICE PSAG, 14-6-11

Page 2: PM report International & UK programmes

Overview• Muon beamline reliable, decay solenoid now being cooled in

readiness for July user run• Target development is going very well, re-engineered target

has been formally accepted by ISIS as technical baseline• FC #1 manufacture is progressing, coil winding is complete,

but cold mass supports critical path now, but overall very good progress

• RF cavity production well on schedule, but LBNL effort rightly transferred to spectrometer solenoids

• Spectrometer solenoids – approval of repair plan late – expert controversy over quench protection, but resolved now

• 2MVA substation upgrade – installed and working ahead of schedule

• Diffuser – steady progress, but limited by available effort• PPS - DSA system now formally handed over to ISIS• First (ten) EMR planes delivered by June 13th, installation

planned for July user run – it’s here, assembly started• LH2 R&D system, ready for cooldown with He next week• LH2 absorber #1, delivered last week

2

Page 3: PM report International & UK programmes

Reconstructing the schedule

• The MICE Project Board (MPB) requested that MICE presents a credible top-level project schedule by 28th June

• MICE had a two-day internal schedule review to prepare for this:• List of major sub-systems• Schedules presented• Resource limitations• Risks and difficulties

• Went very well, almost 100% engagement from the project• New plan is under construction, aim to:

• Assimilate all the information by 10th June• Approval by MICE Executive Board by 17th June• Deliver to MPB 18th June

3

Page 4: PM report International & UK programmes

Reconstructing the schedule

• We will be able to present a detailed schedule for Step IV• Steps V & VI will be as accurate as possible, but qualified with

statement that they are subject to the Coupling Magnet uncertainties – still a major project risk

• A hard cut-off point for MICE will be the long ISIS shutdown for moderator change in August 2014

• We will aim to achieve a major constructional and/or scientific goal by then

• Right now, I don’t know what it is...• We hope it can be Step V• The top-level schedule will contain a more detailed breakdown

of each step configuration

4

Page 5: PM report International & UK programmes

STEP IVComponent Date

Spectrometer solenoid #1 + #2 April’12Fibre tracker #1 + #2 ReadyFocus coil #1 July’11*LH2 delivery Dec ‘11Solid absorber ??Liquid absorber ReadyDiffuser June’11Virostek plate ??Substation upgrade June’11EMR installation Dec’11Radiation shutter ??AFC Moving platform #1 July’11

Step IV ready...Q3, 2012

Page 6: PM report International & UK programmes

Organisation and Project Management

• Thanks to the cooperation of several people, we can now put names to our UK Project Management model – see last OsC:• UK Project Manager – Alan Grant• System Engineer – Tim Hayler• Project Associate – Andy Lintern

• Very unfortunately, we’ve lost Willie Spensley (Hall Manager and Principal Contractor)• This is a major blow – provision of a PC is a legal

responsibility for STFC within the CDM framework and Willie has made a huge contribution to MICE

• Andy N, aided by Vishal Francis, will deputise until we have a replacement (not ideal)

• I believe we must have an STFC employee in the post; this is already in progress

6

Page 7: PM report International & UK programmes

Progress with the Major subsystemsSpectrometer solenoid

• US magnet programme is now led by Steve Gourlay at LBNL• He is able to re-direct resources and set local priorities - crucial

• UK is providing the magnet co-ordination partnership• Roy Preece (engineering) has been on LTA in US since April• Mike Courthold (magnetic systems) travelling and reviewing

extensively• Magnet workshop at LBNL mid-May, very useful

• Aimed to collect all available information on spectrometer solenoid recovery

• Clear up active/passive quench protection (QP) discussion• Clarify route to MAP approval

• Mostly done; QP was cleared up yesterday – it can be passive – easier construction, minimal cost, easier for MAP to approve

• It’s now a question of putting it into practice at Wang – Roy is already making a big difference there

7

Page 8: PM report International & UK programmes

8

Definitive 5+1 CCR layout

Page 9: PM report International & UK programmes

Progress with the Major subsystemsCoupling Magnets

• First Coil is complete at Qi-Hian – major milestone• Fabrication of cold mass jacket and helium tubes has started• Cryostat design is complete – another major milestone• 261 manufacturing drawings of high standard have been

issued for review• Formal review probably at SINAP during August• AN has been invited – Jason Tarrant (MICE integration

Engineer will also be involved• Testing of coil likely in US now – Florida State University has

big enough cryostat• Unfortunately cannot predict final RFCC module delivery due

to US/China uncertainties, but we’re slowly getting under the skin

• Have started the complex integration of CC in MICE Hall discussion – the CC has put on weight since the last effort!

9

Page 10: PM report International & UK programmes

10

RFCC module Cryostat Cold-mass

Coil #1 before and after Al banding

Page 11: PM report International & UK programmes

Progress with the Major subsystemsFC module #1

• Recent progress at Tesla has been good:• Coil is wound and of good quality• Manufacture of vessel and turret going well in parallel• Cryo-cooler performance being qualified by physical tests• Installing quench heaters• Potting and welding cover plates

• Things still worry about:• Testing the FC and field mapping at RAL – likely in R9, but need

experts to work out how to do it (proximity of ferromagnetic infrastructure) Magnet also needs independent support structure

• Accurate co-axial setting of cold mass in vessel• Cold mass support design needs to be finalised

• But it’s encouraging news – looks like September delivery

11

Page 12: PM report International & UK programmes

12

Page 13: PM report International & UK programmes

Progress with the Major subsystemsLiquid hydrogen system

• Going well both inside and outside MICE Hall• R&D system almost ready to test with LHe• Have slipped a month or so due to hole in pre-cool circuit• Now need final leak-test of transfer line• Work on roof in final stages• Control system (and UPS) and extract fans has been exercised• No real problems with ISIS/SHE negotiations• Taking opportunity to design/install extensive pipework for

systems two and three

13

Page 14: PM report International & UK programmes

14

Page 15: PM report International & UK programmes

Progress with the Major subsystemsSubstation Upgrade

• Was finished two days ahead of schedule• Formally handed over to MICE on 27th May• All circuits back on 11KV supply now• Went exceptionally well – minimal disruption to project and to

ISIS• Most of the bill got paid in last FY• All credit must go to BPG and JW Morris Ltd• MICE now has a secure power supply for Step VI

15

Page 16: PM report International & UK programmes

Space, Staffing and Skills

• Permission given by the RALEC in March for MICE to use all of R9 – very good news

• NMR magnet is on its way out soon• MICE needs to adapt the place a bit – design work started at

IC• Vital that we use this space for parallel assembly of RF and

magnets while Step IV is data-taking (one year) and before that

• Availability of staff in DL electrical group is becoming a major worry

• 100% application of some posts (design and installation) will be required very soon if we are to deliver:• RF systems• Solenoid controls