+ All Categories
Home > Documents > Pm Session 7

Pm Session 7

Date post: 09-Mar-2016
Category:
Upload: ldragoman
View: 214 times
Download: 0 times
Share this document with a friend
Description:
PM

of 36

Transcript
  • Project Management Session 7Project Management Control

    Project Management Control

    *Preamble

    Project Management Control

    *How do I manage the following:The overall health of the project;Scope;Acquisition of goods and services;Value.

    Project Management Control

    * Project planning: Milestones Schedule; Human resources; Budget; Responsibilities; Contingencies.Ownership: Stakeholder input; Conditions for satisfaction;Stakeholders feel their interest accommodated.

    Project Health

    Project Management Control

    * Expertise: Have expertise; Members understand their responsibilities; Adequate training for team members; Top level support: Project sponsor share responsibility; TOR agreed; Sponsor and management support when required; Communication.Resources:Available HR; Technology available; Task management effective.

    Project Health

    Project Management Control

    * Justifiable case: Project fully costed and budgeted; Also agreed with sponsor; ROI clear and acceptable;Metrics in place and methods to measure; Adequate funding;Specification:Objectives clear; Strategic and business alignment; Enthusiasm;Adequate documentation reports; budget; specs; deviations; delegations.

    Project Health

    Project Management Control

    *How do I manage the following:The overall health of the project;Scope;Acquisition of goods and services;Value.

    Project Management Control

    *Scope Management

    Project Management Control

    *There are three basic causes for change in projects:Planners erred in their initial assessment about how to achieve a given end or erred in their choice of the proper goal for the project;The client/user or project team learns more about the nature of the project deliverable or about the setting in which it is to be used;Change in the environment in which the project is being conducted.Scope Management

    Project Management Control

    *Scope is defined at various levels:Project charter;Breakdown of deliverables, tasks etc (this is were the Work Breakdown Structure is important);The baseline plan and the budget also part of the scope.Underlying the issue of scope management is change control:Formal system of change control;Impact of changes should be motivated;Where it affects scope, client signoff should be sought and relevant documents updated.

    Scope management

    Project Management Control

    *Scope related dilemmas:Scope creep:Changes that are changing the base plan. Inevitable but the project manager needs to keep these changes manageable ;Hope creep:Falling behind schedule, with the hope that one could catch up. The project manager needs to be very careful as this can have severe consequences for the project;Effort creep:Similar to hope creep. Activity that does not produce results;Feature creep:Adding features rather than sticking to the original agreement about deliverables.Scope management

    Project Management Control

    *How do I manage the following:The overall health of the project;Scope;Acquisition of goods and services;Value.

    Project Management Control

    *PMBOK the processes required to acquire goods and services; Procurement schedule (as such) should only be considered after the network diagram and schedule bar chart has been finalized but before the resource histograms and cash flow statements thus what, when before how much and how much when.Procurement

    Project Management Control

    *Procurement

    Project Management Control

    *How do I manage the following:The overall health of the project;Scope;Acquisition of goods and services;Value.

    Project Management Control

    *Context 70% of projects are:Over budgetBehind schedule

    52% of all projects finish at 189% of their initial budget

    And some, after huge investments of time and money, are simply never comple

    Source: The Standish Group

    Project Management Control

    *What is Earned Value?Earned Value is an approach for understanding and assessing what a project is achieving with budgeted money.

    Project Management Control

    *What Do You Need for EVA?

    Project Management Control

    *Managing Without EVAExample you budget 100 hours to assemble bridgePillars and at the end of the period you have achieved the 100 hoursWow we are on budget !

    BudgetActualVariance100 hours @ R 300R 100 hours @ R 300R 0

    Project Management Control

    *Managing Without EVADoes this mean we have achieved 100 hours worth of work ?Actual cost is not an indication of progress, - Only an indicator ofhours/money spent.

    Project Management Control

    *Important TermsBCWS - Budgeted Cost of Work Scheduled: Planned cost of the total amount of work scheduled to be performed by the milestone date;ACWP - Actual Cost of Work Performed: Cost incurred to accomplish the work that has been done to date;BCWP - Budgeted Cost of Work Performed: The planned (not actual) cost to complete the work that has been done.

    Project Management Control

    *Example

    Chart2

    50005000

    1100012000

    1750019000

    2620029000

    3500039000

    4900055000

    37803

    37834

    37865

    37895

    37926

    37956

    BCWP

    BCWS

    EVA Chart

    500050005000

    120001100012500

    190001750019600

    290002620029900

    390003500039900

    550004900056000

    650003780337803

    800003783437834

    900003786537865

    950003789537895

    1000003792637926

    1020003795637956

    Project is:

    13.8% Behind Schedule16.1% Over Cost

    BCWS

    BCWP

    ACWP

    Typical Chart

    90008640

    1800017280

    2700025920

    3600034560

    4500043200

    5400051840

    6300060480

    7200037834

    8100037865

    9000037895

    9900037926

    10800037956

    Projected

    Actual

    Typical Data

    1/1/032/1/033/1/034/1/035/1/036/1/037/1/038/1/039/1/0310/1/0311/1/0312/1/03

    Projected900018000270003600045000540006300072000810009000099000108000

    Actual8640172802592034560432005184060480

    Factor0.96

    ACWP

    1/1/032/1/033/1/034/1/035/1/036/1/037/1/038/1/039/1/0310/1/0311/1/0312/1/03

    BCWP50001100017500262003500049000

    ACWP50001250019600299003990056000

    ACWP

    BCWP

    ACWP

    BCWP

    1/1/032/1/033/1/034/1/035/1/036/1/037/1/038/1/039/1/0310/1/0311/1/0312/1/03

    BCWP50001100017500262003500049000

    BCWS50001200019000290003900055000

    BCWP

    BCWP

    BCWS

    BCWS

    1/1/032/1/033/1/034/1/035/1/036/1/037/1/038/1/039/1/0310/1/0311/1/0312/1/03

    BCWS5000120001900029000390005500065000800009000095000100000102000

    BCWS

    BCWS

    EVA Data

    1/1/032/1/033/1/034/1/035/1/036/1/037/1/038/1/039/1/0310/1/0311/1/0312/1/03

    BCWS5000120001900029000390005500065000800009000095000100000102000

    BCWP50001100017500262003500049000

    ACWP50001250019600299003990056000

    Schedule Variance0-1000-1500-2800-4000-6000

    Sched. Var. %0.0%-8.3%-7.9%-9.7%-10.3%-10.9%

    Schedule Perf. Index1.0000.9170.9210.9030.8970.891

    Cost Variance0-1500-2100-3700-4900-7000

    Cost Var. %0.0%-13.6%-12.0%-14.1%-14.0%-14.3%

    Cost Perf. Index1.0000.8800.8930.8760.8770.875

    EAC 1

    VAC 1

    VAC % 1

    EAC 2

    Project is:

    10.9% Behind Schedule14.3% Over Cost

    Project Management Control

    *ExampleSV - Schedule Variance: (BCWP-BCWS):A comparison of amount of work performed during a given period of time to what was scheduled to be performed.A negative variance means the project is behind schedule

    Project Management Control

    *Example

    Chart4

    500050005000

    120001100012500

    190001750019600

    290002620029900

    390003500039900

    550004900056000

    650003780337803

    800003783437834

    900003786537865

    950003789537895

    1000003792637926

    1020003795637956

    BCWS

    BCWP

    ACWP

    EVA Chart

    500050005000

    120001100012500

    190001750019600

    290002620029900

    390003500039900

    550004900056000

    650003780337803

    800003783437834

    900003786537865

    950003789537895

    1000003792637926

    1020003795637956

    Project is:

    13.8% Behind Schedule16.1% Over Cost

    BCWS

    BCWP

    ACWP

    Typical Chart

    90008640

    1800017280

    2700025920

    3600034560

    4500043200

    5400051840

    6300060480

    7200037834

    8100037865

    9000037895

    9900037926

    10800037956

    Projected

    Actual

    Typical Data

    1/1/032/1/033/1/034/1/035/1/036/1/037/1/038/1/039/1/0310/1/0311/1/0312/1/03

    Projected900018000270003600045000540006300072000810009000099000108000

    Actual8640172802592034560432005184060480

    Factor0.96

    Combined Chart

    1/1/032/1/033/1/034/1/035/1/036/1/037/1/038/1/039/1/0310/1/0311/1/0312/1/03

    BCWS5000120001900029000390005500065000800009000095000100000102000

    BCWP50001100017500262003500049000

    ACWP50001250019600299003990056000

    Combined Chart

    BCWS

    BCWP

    ACWP

    ACWP

    1/1/032/1/033/1/034/1/035/1/036/1/037/1/038/1/039/1/0310/1/0311/1/0312/1/03

    BCWP50001100017500262003500049000

    ACWP50001250019600299003990056000

    ACWP

    BCWP

    ACWP

    BCWP

    1/1/032/1/033/1/034/1/035/1/036/1/037/1/038/1/039/1/0310/1/0311/1/0312/1/03

    BCWP50001100017500262003500049000

    BCWS50001200019000290003900055000

    BCWP

    BCWP

    BCWS

    BCWS

    1/1/032/1/033/1/034/1/035/1/036/1/037/1/038/1/039/1/0310/1/0311/1/0312/1/03

    BCWS5000120001900029000390005500065000800009000095000100000102000

    BCWS

    BCWS

    EVA Data

    1/1/032/1/033/1/034/1/035/1/036/1/037/1/038/1/039/1/0310/1/0311/1/0312/1/03

    BCWS5000120001900029000390005500065000800009000095000100000102000

    BCWP50001100017500262003500049000

    ACWP50001250019600299003990056000

    Schedule Variance0-1000-1500-2800-4000-6000

    Sched. Var. %0.0%-8.3%-7.9%-9.7%-10.3%-10.9%

    Schedule Perf. Index1.0000.9170.9210.9030.8970.891

    Cost Variance0-1500-2100-3700-4900-7000

    Cost Var. %0.0%-13.6%-12.0%-14.1%-14.0%-14.3%

    Cost Perf. Index1.0000.8800.8930.8760.8770.875

    EAC 1

    VAC 1

    VAC % 1

    EAC 2

    Project is:

    10.9% Behind Schedule14.3% Over Cost

    Project Management Control

    *ExampleCV - Cost Variance: (BCWP-ACWP)A comparison of the budgeted cost of work performed with actual cost.A negative variance means the project is over budget.

    Project Management Control

    *ExampleSchedule Variance = BCWP-BCWS:

    $49,000- 55,000SV = - $ 6,000

    Cost Variance = BCWP-ACWP:

    $49,000 56,000CV = - $7,000

    Project Management Control

    *Earned Value?BCWP - Budgeted Cost of Work Performed: The planned (not actual) cost to complete the work that has been done.

    Project Management Control

    *In Simple TermsActual Cost (26)Budget Plan (21)Earned Value (16)Time NowSchedule variance

    Sheet:

    J

    F

    M

    A

    M

    J

    J

    A

    S

    O

    N

    D

    Budget Plan

    Actual Cost

    Earned Value

    Project Management Control

    *In Simple TermsActual Cost (26)Budget Plan (21)Earned Value (16)Time NowCost Variance

    Sheet:

    J

    F

    M

    A

    M

    J

    J

    A

    S

    O

    N

    D

    Budget Plan

    Actual Cost

    Earned Value

    Project Management Control

    *In Simple TermsActual Cost (26)Budget Plan (21)Earned Value (16)Time NowTime variance

    Sheet:

    J

    F

    M

    A

    M

    J

    J

    A

    S

    O

    N

    D

    Budget Plan

    Actual Cost

    Earned Value

    Project Management Control

    *Important MetricsSPI: Schedule Performance Index:SPI=BCWP/BCWSSPI


Recommended