1 PMINEO chapter meeting program June 17, 2015 Project of the Year for 2014 Vita-Mix Germany eShop Presented by Bob Zoller PMP, PMI-ACP, CSM, ITIL [email protected]
Transcript
Page 1: PMINEO_Proj_of_Year_2014_VitaMix_eShop

1

PMINEO chapter meeting programJune 17, 2015

Project of the Year for 2014Vita-Mix Germany eShop

Presented by Bob ZollerPMP, PMI-ACP, CSM, ITIL

[email protected]

Page 2: PMINEO_Proj_of_Year_2014_VitaMix_eShop

2

PMINEO Annual Awards

PMINEO Project Management Excellence Recognizes an individual demonstrating significant

contributions and continual commitment to the Project Management profession

2014 winner: Christy Laird of Progressive and PMINEO programs

PMINEO Project of the Year

Award criteria: Met or exceeded owner or client needs Applied project management techniques in an original way Advanced the technical aspects and image of project

management

Project of the Year for 2014: Vita-Mix Germany eShop Outstanding timeline performance to satisfy a business

need Used a combination of Waterfall and Agile to meet the

schedule

Page 3: PMINEO_Proj_of_Year_2014_VitaMix_eShop

3

Agenda1) Background of Vita-Mix2) Background of Germany eShop3) Project Scope4) Project Team and Partners5) Project Methodology (*)6) Project Timeline 7) Project Tools8) Timeline Reduction (*)9) Project Success Factors & Lessons Learned10) Closing

Vita-Mix presentation agenda

(*) Take-aways for Project Managers:(5) Project Methodology - hybrid(8) Timeline Reduction(--) Overseas project items

Page 4: PMINEO_Proj_of_Year_2014_VitaMix_eShop

4

Agenda1) Background of Vita-Mix2) Background of Germany eShop3) Project Scope4) Project Team and Partners5) Project Methodology (*) 6) Project Timeline 7) Project Tools8) Timeline Reduction (*) 9) Project Success Factors & Lessons Learned10) Closing

who, what, why

(*) Take-aways for Project Managers:(5) Project Methodology - hybrid(8) Timeline Reduction(--) Overseas project items

Page 5: PMINEO_Proj_of_Year_2014_VitaMix_eShop

5

(1) Background of Vita-Mix

Vita-Mix Cleveland-based kitchen products company since 1921 Today: premium blending equipment for home and

business High growth from healthy eating trend, and “foodies” Organization including IT has high growth (new staff) Growing overseas, focus on “Tier 1” countries (high

income)

Marketing Strategy Retail Partners Online with www.vitamix.com, and some country-

specific sites

Country-specific sites Vita-Mix IT capacity sets pace for country site

development

Page 6: PMINEO_Proj_of_Year_2014_VitaMix_eShop

6

(2) Background of Germany eShop

Plan “A” for marketing to Germany, as of Fall of 2013

Continue recruiting retailers through 2013 and 2014 IT: deploy German eShop in later 2014 (after UK,

Ireland)

Management: German eShop in late 2014 is unacceptable

Page 7: PMINEO_Proj_of_Year_2014_VitaMix_eShop

7

(2) Background of Germany eShop

Plan “B” for marketing to Germany, on December 2, 2013

Vita-Mix IT teams remains on UK, Ireland web sites Find IT subcontractor and deploy German eShop in 2014

Q1 Note “Ambiente” trade show in February 2014, so….. Target: deploy temporary eShop by January 31, 2014 Timeline of 2 months is half of typical German eShop

project.

Page 8: PMINEO_Proj_of_Year_2014_VitaMix_eShop

8

(3) Project Scope

Germany eShop, firm scope eShop dedicated to German market Offer (18) items: blenders, accessories, cookbooks

German language products exist, for retail Purchase using shopping cart and credit card Comply with strict German laws for consumer data

privacy Web site content and documents in German Communicate with customers and Vita-Mix systems

Page 9: PMINEO_Proj_of_Year_2014_VitaMix_eShop

9

(3) Project Scope

Sample category

page, from Vitamix.com

Click on a unit to see unit detail

page.

Page 10: PMINEO_Proj_of_Year_2014_VitaMix_eShop

10

(3) Project Scope

Sample unit detail page.

Click on “Add to Cart”: Enter/validate

address Enter/approve

credit card Generate

confirmation email

German marketing: avoid implied warranty.

Page 11: PMINEO_Proj_of_Year_2014_VitaMix_eShop

11

(3) Project Scope

.

Page 12: PMINEO_Proj_of_Year_2014_VitaMix_eShop

12

(4) Project Team and Partners

Return to (5) Methodology, Factors

Page 13: PMINEO_Proj_of_Year_2014_VitaMix_eShop

13

Agenda1) Background of Vita-Mix2) Background of Germany eShop3) Project Scope4) Project Team and Partners5) Project Methodology (*) 6) Project Timeline 7) Project Tools8) Timeline Reduction (*) 9) Project Success Factors & Lessons Learned10) Closing

who, what, why

how and when

(*) Take-aways for Project Managers:(5) Project Methodology - hybrid(8) Timeline Reduction(--) Overseas project items

Page 14: PMINEO_Proj_of_Year_2014_VitaMix_eShop

14

(5) Project Methodology

Choose: Agile, Waterfall, or Hybrid ?

Factors: Limited shared team experience with Agile

Link: (4) Project Team Short timeline (4 week core development time; 9 weeks

total)

Agile Not a good fit for a new process on short timeline Fixed project scope makes re-prioritization unnecessary

Page 15: PMINEO_Proj_of_Year_2014_VitaMix_eShop

15

(5) Project Methodology

Choose: Agile, Waterfall, or Hybrid ?

Waterfall Highly serialized (non-overlapping) phases poor for

timeline Web site requirements not complete until week 5 of 9

weeks

Waterfall style for this project must be heavily overlapped

Page 16: PMINEO_Proj_of_Year_2014_VitaMix_eShop

16

(5) Project Methodology

Choose: Agile, Waterfall, or Hybrid ? Use Hybrid:

This slide shows standardized iteration structure & timing.

Vita-Mix eShop followed this pattern loosely, with variation in timing of subsections.

Return 8 (A) Progressive Elaboration

Page 17: PMINEO_Proj_of_Year_2014_VitaMix_eShop

17

(6) Project Timeline

Note dual critical paths for: (A) Systems, (B) Partner Setup Week start: Dec 2 - Dec 9 - Dec 16 - Dec 23 - Dec 30 - Jan 6 - Jan 13 - Jan 20 - Jan 27 -

Week end: - Dec 6 - Dec 13 - Dec 20 - Dec 27 - Jan 3 - Jan 10 - Jan 17 - Jan 24 - Jan 31

Timeline for SystemsReqmts & Page Layouts Create, Approve Design Site Processing Data privacy; Inventory; shopping cart with pricing, tax

Backoffice Order processing; warehouse; shippingProduct Products Products, categories, pricingContent Translate Translate Load UpdateLegal Site legal notices Wrrty; Privacy; Terms Translate Load

Email templates Order conf; Ship Translate LoadUS Site Integrate US/DE Link to/from US site (repair shops); "imprint" LoadBackoffice Order process Analysis (banking, order coding) Setup Test Load Prod

Shipping Analysis (warehouse; shipping) Setup Test Load ProdTesting Approve, Test Parallel with development Integrate ApproveeShop Platform Setup: Magento, PayOne, Concardis Load Prod Approve Go

Page content Categories, Products, Legal Load Prod Approve GoProcessing Inventory; order; tax; ship; emails Load Prod Approve Go

Timeline for Partner SetupAcquire Vita-Mix tasks Identify Partners Negotiate contracts; make administrative setups Partners Legal work Negotiate contracts with four new vendors New D&B (IT) Ltr of Und Contract (phased payment, penalties)Partners PayOne (credit) Contract (fee issues; admin setup)

Concardis (pay) Contract (banking lag issue; admin setup)DomFact (host) Interim via D&B Contract (Privacy)

Holidays

(A)

(B)

Jan29

Page 18: PMINEO_Proj_of_Year_2014_VitaMix_eShop

18

(6) Project Timeline

Critical Path: (A) Systems work – weeks 1 to 7

Week start: Dec 2 - Dec 9 - Dec 16 - Dec 23 - Dec 30 - Jan 6 - Jan 13 -Week end: - Dec 6 - Dec 13 - Dec 20 - Dec 27 - Jan 3 - Jan 10 - Jan 17

Timeline for SystemsReqmts & Page Layouts Create, Approve Design Site Processing Data privacy; Inventory; shopping cart with pricing, tax

Backoffice Order processing; warehouse; shippingProduct Products Products, categories, pricingContent Translate Translate Load UpdateLegal Site legal notices Wrrty; Privacy; Terms Translate Load

Email templates Order conf; Ship Translate LoadUS Site Integrate US/DE Link to/from US site (repair shops); "imprint" LoadBackoffice Order process Analysis (banking, order coding) Setup Test

Shipping Analysis (warehouse; shipping) Setup TestTesting Approve, Test Parallel with development IntegrateeShop Platform Setup: Magento, PayOne, Concardis Load Prod

Page content Categories, Products, Legal Load ProdProcessing Inventory; order; tax; ship; emails Load Prod

Holidays

Overseas project notes: translation issues; “imprint”; navigation notifications

Page 19: PMINEO_Proj_of_Year_2014_VitaMix_eShop

19

(6) Project Timeline

Critical Path: (B) Partner Setup – weeks 1 to 7

Week start: Dec 2 - Dec 9 - Dec 16 - Dec 23 - Dec 30 - Jan 6 - Jan 13 -Week end: - Dec 6 - Dec 13 - Dec 20 - Dec 27 - Jan 3 - Jan 10 - Jan 17

Timeline for Partner SetupAcquire Vita-Mix tasks Identify Partners Negotiate contracts; make administrative setups Partners Legal work Negotiate contracts with four new vendors New D&B (IT) Ltr of Und Contract (phased payment, penalties)Partners PayOne (credit) Contract (fee issues; admin setup)

Concardis (pay) Contract (banking lag issue; admin setup)DomFact (host) Interim via D&B Cont (Priv)

Holidays

Overseas project note: most vendor paperwork was in German (standard contracts, pricing lists, Service Level agreements).

Page 20: PMINEO_Proj_of_Year_2014_VitaMix_eShop

20

(7) Project Tools

Project documents: Vita-Mix sharepoint site Typical core project documents, in MS-Word, MS-

Excel Schedule.xls; Risk/Issue/Action.xls; Requirements.doc

Technical Development: “Magento” eShop platform WiTopia software for German IP address simulation Bug-tracking: Mantis internet-based tool (D&B standard)

Page 21: PMINEO_Proj_of_Year_2014_VitaMix_eShop

21

(8) Timeline Reduction

Timeline Reduction Methods Used in eShop project

Team used a collection of timeline reduction methods Nothing revolutionary, just a constant focus on timeline Types:

(A) Compress Waterfall Plus Agile(B) Minimize Deliverables(C) Minimize Time Delays

Page 22: PMINEO_Proj_of_Year_2014_VitaMix_eShop

22

(8) Timeline Reduction

(A) Compress Waterfall Plus Agile…

Fast-tracking = compress by overlapped phases (in parallel)

Shortens timeline, increases risk of errors and rework

Agile techniques to reduce risk: Empowered self-organizing teams

Address issues without time for management involvement

Minimal formal expectations, only a weekly status Daily team meetings

Status 8:30-9:00am EST: core Vita-Mix and D&B (IT) Minimal time lost (1 day) if go off-course.

Page 23: PMINEO_Proj_of_Year_2014_VitaMix_eShop

23

(8) Timeline Reduction

(A) Compress Waterfall Plus Agile (continued)…

Progressive Elaboration (hybrid: red, green, blue, yellow) Define requirements overall at high level as

framework Define requirements and develop sections

progressively Link: (5) Methodology: Hybrid

Frequent direct collaboration, light documentation Ex: for requirements session for function “X”

Include all voices and decision-makers in one session

Goal: define and approve requirements in one session

Early and frequent testing and validation Informal validation of IT WIP during daily meeting Perform at least pre-test for each function as

available.

Page 24: PMINEO_Proj_of_Year_2014_VitaMix_eShop

24

(8) Timeline Reduction

(B) Minimize Deliverables…

Focus on “external” or “required” deliverables Minimize “internal” team deliverables

Example: Select team members with needed skills (avoid training)

The Lead BA on the project was web specialist BA work needed on Ordering and Shipping in VMix

systems BA for Order processing, for analysis & accounting

setup BA for Shipping, for analysis and system setup.

Page 25: PMINEO_Proj_of_Year_2014_VitaMix_eShop

25

(8) Timeline Reduction

(B) Minimize Deliverables (continued)…

Examples (continued) Use known/proven tools (avoid learning curve,

integration time) Magento/PayOne/Concardis were proven integrated

tools PayOne chosen over Chase, to avoid technical

integration German law firm as proxy for Vita-Mix (eliminate

translations) German attorney summarized German documents

for US Redlining was done directly in German documents

Use partners with existing relationships (mutual knowledge) Use partners who know each other and ready to start

work.

Page 26: PMINEO_Proj_of_Year_2014_VitaMix_eShop

26

(8) Timeline Reduction

(C) Minimize time delays…

Use backups for critical path resources Martin Bielke (account manager at PayOne) out for

holidays Bielke found backup resource to continue PayOne,

Concardis Use partners with existing relationships (mutual trust)

D&B with Letter of Understanding (with unknown Vita-mix)

Existing relationship of D&B and K&H was incentive for D&B

Relax standards to reduce wait time Vita-Mix marketing allowed use of “pasted” logo file Vita-Mix finance allowed Payone, Concardis (not

Chase).

Page 27: PMINEO_Proj_of_Year_2014_VitaMix_eShop

27

Agenda1) Background of Vita-Mix2) Background of Germany eShop3) Project Scope4) Project Team and Partners5) Project Methodology (*) 6) Project Timeline 7) Project Tools8) Timeline Reduction (*) 9) Project Success Factors & Lessons Learned10) Closing

who, what, why

how and when

conclusion

(*) Take-aways for Project Managers:(5) Project Methodology - hybrid(8) Timeline Reduction(--) Overseas project items

Page 28: PMINEO_Proj_of_Year_2014_VitaMix_eShop

28

(9) Project Success Factors & Lessons Learned

Project Success Factors Clear scope and priority provided focus

Decision criteria usually simple: what is fastest option?

Strong sponsors (IT and marketing) Provided resources: international staff, multiple BA

Resources available as needed, full-time or otherwise All team members were experts in their role Tight timeline forced cooperation and trust and focus Existing Vitamix.com provided scope example

Page 29: PMINEO_Proj_of_Year_2014_VitaMix_eShop

29

(9) Project Success Factors & Lessons Learned

Project Lessons Learned High cost of specialty legal services; minimal budget

planning Get estimates earlier at least as FYI (large legal

expense) Translation (and all project deliverables) should be

validated Allow time for validation

Get internet-based project document site for access by all The Vita-Mix based site required document

coordination Contract negotiation with D&B – ran long; posed a risk

Mitigated by D&B incentives with partnership with K&H

Page 30: PMINEO_Proj_of_Year_2014_VitaMix_eShop

30

(10) Closing

Q&A

Standing Ovation