IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
1 ©2014 Interna;onal Ins;tute for Learning, Inc.
PMP cross-cutting skills have been updated in the PMP Exam Content Outline – June 2015 (PDF of the Examination Content Outline - June 2015 can be found under the Resources Tab).
Learn about why the PMP exam is changing in 2016.
Download the new Exam Content Outline to study cross-cutting skills here:http://www.brainshark.com/pmiorg/2015PMPExamChange
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
2 ©2014 Interna;onal Ins;tute for Learning, Inc.
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes:
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
3
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: Review these learning objec;ves carefully.
The learning content contained within this module is based on these learning objec;ves.
At the end of this module or the end of the course, you should be able to answer quiz or test ques;ons related to these learning objec;ves.
If you are par;cipa;ng in this course for cer;fica;on, you will be beQer prepared to pass a cer;fica;on exam by recalling these learning objec;ves.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
4
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: Project Stakeholder Management includes the processes required to iden;fy all people or organiza;ons impacted by the project, analyzing stakeholder expecta;ons and impact on the project and developing appropriate management strategies for effec;vely engaging stakeholders in project decisions and execu;on.
PMBOK® Guide – FiWh Edi;on, Glossary
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
5
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: The PMBOK® Guide – FiWh Edi;on describes the key benefit of this process as “enabling iden;fica;on of the appropriate focus for stakeholders.”
PMBOK Guide® -‐ FiWh Edi;on, p. 393
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
6
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: The PMBOK® Guide – FiWh Edi;on defines the following for this first Project Stakeholder Management process:
• Inputs
― Project charter ― Procurement documents
― Enterprise environmental factors
― Organiza;onal process assets • Tools & Techniques
― Stakeholder analysis ― Expert judgment ― Mee;ngs
• Outputs
― Stakeholder register
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
7
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: While the project charter’s primary objec;ve is to authorize the project, authorize the project manager, and to authorize the project manager to expend resources on behalf of the project, it may also include some of the key stakeholders involved in the project such as:
• Execu;ves • Clients • Team members
Procuring services, personnel and materials from outside the organiza;on adds a number of new stakeholders to the project. These can include a general contractor, foreman, workers, tradesmen, lawyers, etc.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
8
Iden;fying stakeholders begins with collec;ng informa;on about who the project stakeholders might be and then collec;ng informa;on that will assist with analyzing how stakeholders might impact the project. These stakeholders include decision makers, anyone affected by the project, and others that may have a role to play on your project. Next, it is important to iden;fy the impact or support that could be given by each stakeholder. You will begin to understand how each stakeholder might respond to various s;muli within the project environment.
We will explore a couple classifica;on models that can be used for stakeholder analysis. These modes are the Power/Interest grid and the Salience model. Your instructor may wish to describe other models…;me permihng.
It is important to iden;fy all your stakeholders. Missing a stakeholder means missing poten;al requirements. Therefore you should talk to as many people as possible to insure you iden;fy all the stakeholders.
Other tools you can use to iden;fy stakeholders include brainstorming and networking.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
9 ©2014 Interna;onal Ins;tute for Learning, Inc.
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: • Step 1: Iden/fy poten/al stakeholders and associated informa;on (e.g., role, department, interests, knowledge level, expecta;ons, influence.
• Step 2: Iden/fy poten/al impact or support stakeholders could generate, and classify them to help define an approach strategy.
• Step 3: Assess poten;al stakeholder reac;ons to use in developing a plan for influencing them and elici;ng their support.
The informa;on needs of the various stakeholders should be analyzed to develop a methodical and logical view of their informa;on needs and sources to meet those needs. The analysis should consider methods and technologies suited to the project that will provide the informa;on needed. Care should be taken to avoid was;ng resources on unnecessary informa;on.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
10
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: Iden;fying stakeholders begins with iden;fying individual and groups of stakeholders. Wri;ng stakeholder names or groups on Post-‐It notes is a convenient way to place them on the Power/Interest Grid. You may want to also include the classifica;on from the Stakeholder Engagement Assessment Matrix men;oned in the next sec;on. This kind of analysis facilitates traceability with requirements and deliverables. Understanding who provided a requirement and where they sit on this grid, can help you when a change in scope or a priori;za;on of requirements is ini;ated. It also is useful when planning how to manage stakeholder ahtudes. For instance, if you have a stakeholder in the high power, high concern area who is resistant, you may need to begin building a rela;onship.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
11
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: The intent of the model is to allow the “project manager” to decide upon the rela;ve salience of a stakeholder, which is “the degree to which managers give priority to compe;ng stakeholder’s claims” or expecta;ons.
Salience Model, by Puneet Kuthiala, PMP, published in JustPM Blog, October 8, 2009
Each circle has a unique label: “Power,” “Urgency,” or “Legi;macy.” Power is the ability to impose one’s will, i.e. the ability of the stakeholder to influence the organiza;on; Urgency is the ability to command aQen;on, because of the cri;cality and ;me-‐sensi;vity of the requirements being set for by the stakeholder for the organiza;on; Legi;macy is the “right” one has to be involved – the legi;macy of the rela;onship and ac;ons of the stakeholder with the organiza;on in terms of desirability, properness or appropriateness.
Adapted from hQp://www.12manage.com/methods_stakeholder_mapping.html
Each circle includes four numeric values that represent different salient (the degree to which managers give priority to compe;ng stakeholder’s claims) classifica;ons, and of the four, one is unique to each circle.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
12
Classifica;on 1 indicates a Dormant Stakeholder who has the ability to impose their will, but they have neither the ability to command aQen;on nor “right” to be involved
Classifica;on 2 for a Discre;onary Stakeholder has neither the ability to impose their will nor the ability to command aQen;on, but they do have “right” to be involved
Classifica;on 3 that is for a Demanding Stakeholder does not have ability to impose their will nor the “right” to be involved, but they have ability to command aQen;on
Classifica;on 4 is a Dominant Stakeholder has the ability to impose their will and the “right” to be involved, but the inability to command aQen;on
Classifica;on 5 is for a Dangerous Stakeholder has the ability to impose their will and the ability to command aQen;on, but they have no “right” to be involved.
Classifica;on 6 is a Dependent Stakeholder has the ability to command aQen;on and the “right” to be involved, but an inability to impose their will.
Classifica;on 7 indicates a Defini;ve Stakeholder has all three: the ability to impose their will, the “right” to be involved, and the ability to command aQen;on.
You can have number 8 outside the Venn diagram to indicate a Non‑stakeholder, if needed.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
13 ©2014 Interna;onal Ins;tute for Learning, Inc.
Stakeholder Register-‐A project document including the iden;fica;on, assessment, and classifica;on of project stakeholders The stakeholder register is a living document that lists various pieces of informa;on about stakeholders that will be used during the life of the project to manage the team’s interac;ons with stakeholders. This informa;on includes, but is not limited to:
• Stakeholder names
• Posi;on • Titles and roles • Expecta;ons • Influence • Drivers • How they are classified The register is a tool to aid in gaining support and minimize nega;ve impacts of stakeholders during the life of the project.
The idea behind the stakeholder register is to capture:
• Iden;fica;on informa;on
• Assessment informa;on
• Stakeholder classifica;on
Other fields that you may want to have in a stakeholder register include:
• Stakeholder interest(s) in the project
• Assessment of impact
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
14 ©2014 Interna;onal Ins;tute for Learning, Inc.
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: The PMBOK® Guide – FiWh Edi;on describes the key benefit of this process as providing “a plan to engage stakeholders to support the project’s interests.”
PMBOK Guide® – FiWh Edi;on, p. 399
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
15
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: The PMBOK® Guide – FiWh Edi;on defines the following for this second Project Stakeholder Management process:
• Inputs
― Project management plan ― Stakeholder register ― Enterprise environmental factors
― Organiza;onal process assets • Tools & Techniques
― Expert judgment
― Mee;ngs ― Analy;cal techniques
• Outputs
― Stakeholder management plan ― Project document updates
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
16
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: The project management plan provides much of the informa;on to put the management of stakeholders in context. The project management plan will describe the lifecycle used and this can point to stakeholders that need to be involved. The project management plan will also describe the work to be done and how it will be done. If changes are requested, the project management plan will describe how they are to be processed. Finally, the it defines how communica;ons between stakeholders will be handled.
The stakeholder register was described in the previous process.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
17
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: A stakeholder engagement matrix is used to map stakeholder’s current level of engagement and their desired level of engagement. Informa;on from this matrix is used when planning how to manage stakeholder engagement throughout the project.
Stakeholder Engagement Levels:
Unaware: Unaware of project and poten;al impacts
Resistant: Resistant to the project
Neutral: Not Suppor;ve or Resistant
Suppor2ve: Suppor;ve to the project
Leading: Takes a leadership role to ensure the success of the project
Your organiza;on may have its own classifica;on scheme that you may wish to use.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
18
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: Communica;on with stakeholders begins with understanding the nature of the stakeholder. There are many tools for characterizing the nature of individuals. Myers Briggs Test, DiSC IV, Personalysis, and Social Styles are a few of the more common tools.. Analysis of a stakeholder and his communica;on style can help you deliver informa;on in a way that the stakeholder can best process and accept the informa;on.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
19
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: The Stakeholder Management Plan is part of the progressively elaborated Project Management Plan. The stakeholder management plan provides the necessary background to intelligently engage the project stakeholders. A by-‐product of the process of building the Stakeholder Management Plan may lead to a need to update requirements and the stakeholder register, schedule, budget, etc.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
20
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: The PMBOK® Guide – FiWh Edi;on describes the key benefit of this process is allowing the project manager “to increase support and minimize resistance from stakeholders.”
PMBOK Guide® -‐ FiWh Edi;on, p. 404 Ac;vely managing stakeholder expecta;ons increases the likelihood that the project will stay on track.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
21
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: The PMBOK® Guide – FiWh Edi;on defines the following for this third Project Stakeholder Management process:
• Inputs
― Stakeholder management plan ― Communica;ons management plan ― Change log ― Organiza;onal process assets
• Tools & Techniques
― Communica;on methods ― Interpersonal skills ― Management skills
• Outputs
― Issue log ― Change requests ― Project management plan updates ― Project documents updates ― Organiza;onal process assets updates
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
22
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: The communica;on management plan is an excellent example of where parts of the Project Management Plan become inputs to other subsidiary plans to the plan. The communica;on management plan directs how stakeholders should be communicated with, the informa;on they should be given, the proper level of informa;on, which individuals should receive the informa;on, and how escala;on over issues should take place.
Remember that any changes to the project scope should be communicated to the appropriate stakeholders.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
23
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: The communica;on plan provides informa;on on how stakeholders need to be communicated to. This may include mee;ngs, conference calls, wriQen means, email, collabora;on tools, etc. We will discuss the communica;ons management plan in more detail in a later lesson.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
24
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: Trust, as described in the American Heritage Dic/onary is “confidence in the integrity, ability, character, and truth of a person or thing.”
Trust is the genesis of leadership and is built by every ac;on, every ini;a;ve and every word of the project manager. Albert Schweitzer, the humanitarian, theologian, missionary, organist, and medical doctor, said, “Example is not the main thing in influencing others, it’s the only thing.”
Trust works both ways. If you are in a leadership posi;on, trust will keep you there, or the lack of trust in you will diminish your capabili;es as a leader.
A good moQo is: Trust un;l you have a compelling reason to mistrust.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
25
One of the best ways to think of this model is from the core (inner ring) and a set of rela;onship-‐based skill families (central core). But since it will take the whole module to get there, we wanted to provide a brief preview of it here. Let’s keep the four families of rela;onship skills “anchored” while we look out through the project lifecycle (PLC) layer, which can be “spun” to align with the current PLC phase. In turn, the outer circle can also be “spun” so that each family of skills in some way supports every combina;on of Stakeholder category/PLC phase. However, if we tried to cover all that territory, we would need a two-‐week workshop. So, in our model, we have posi;oned each family of rela;onship skills opposite the major categories for which that family provides the most effec;ve solu;ons. In some cases, there is also a primary PLC phase, e.g., we see the Advocacy family of skills having the most impact with Governing Bodies, especially in the early stages or Concept phase. That does not mean that the skills that we describe as being in the Advocacy family will not be needed for other combina;ons of stakeholder category/PLC phase, but that the par;cular combina;on we have iden;fied will be used to demonstrate the skill, in what we think is the most effec;ve scenario for prac;ce and successful knowledge transfer.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
26 ©2014 Interna;onal Ins;tute for Learning, Inc.
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: Dealing with stakeholders takes good management skills to bring harmony, agreement and coordina;on to bring about the project’s objec;ves.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
27
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: The issue log (or register) can minimize the impact of schedule, cost and resource issues by documen;ng the issue, assessing the impact, and assigning a responsible party to take correc;ve ac;ons.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
28
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: The PMBOK® Guide – FiWh Edi;on describes the key benefit of this process as “efficiently and effec;vely engaging stakeholders as the project evolves.”
PMBOK Guide® -‐ FiWh Edi;on, p. 409
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
29
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: The PMBOK® Guide – FiWh Edi;on defines the following for this fourth Project Stakeholder Management process:
• Inputs
― Project management plan ― Issue log ― Work performance data
― Project documents • Tools & Techniques
― Informa;on management ― Expert judgment ― Mee;ngs
• Outputs
― Work performance informa;on ― Change requests ― Project management plan updates ― Project document updates ― Organiza;onal process assets updates
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
30
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes:
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
31
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes:
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
32
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes:
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
33
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: Expert judgment extends not only to industry and project knowledge, but how to accomplish things in your environment. When most people hear the word “Poli;cs” and par;cularly “Office Poli;cs,” they conjure up nega;ve thoughts of self-‐interest and betrayals. Instead, try to think of organiza;onal poli;cs as using the interpersonal skills you’ve obtained to help achieve the strategic objec;ves of the organiza;on. This is a worthwhile and noble pursuit and will keep you on the right path.
For more informa;on on the topic, see Jeffrey K. Pinto’s book en;tled POWER & POLITICS in Project Management.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
34
Stakeholder mee;ngs are used for: • Informa;on sharing
• Planning/coordina;ng
• Problem solving
• Decision making
• Team building
Prior to a stakeholder mee;ng, an agenda should be provided to all aQendees, especially for virtual mee;ngs. Be sure to include:
• Name of mee;ng
• Loca;on (if virtual…provide all connec;on informa;on)
• Time (zone if necessary), dura;on and date
• Objec;ve to be reached during mee;ng
• Who is aQending
• Content
If the mee;ng is offsite, be sure to provide direc;ons to the mee;ng loca;on. Send and collateral material that is needed, including suppor;ng material for discussion.
If the mee;ng is virtual, have aQendees arrive early to solve connec;on problems and avoid interrup;ons during the mee;ng.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
35 ©2014 Interna;onal Ins;tute for Learning, Inc.
©2014 Interna;onal Ins;tute for Learning, Inc.
Participant’s Notes: Work performance informa;on is derived from the data that is collected throughout the project. While data is just the raw material of informa;on, informa;on, when craWed properly, prevents stakeholders from misinterpre;ng the data. Informa;on about performance is focused on ensuring that stakeholders correctly understand the context and status of the project and can make proper decisions concerning the project.
Frequently, in the execu;on of a project, it is learned that there might have been a beQer procedure for execu;ng a task or dealing with a risk. Feedback from stakeholders and the outcome of lessons learned mee;ngs should be recorded by upda;ng any of the project documents that are impacted.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
36
RESPECT STANDARDS
We inform ourselves about the norms and customs of others and avoid engaging in behaviors they might consider disrespecNul.
This ethics standard goes beyond cultural diversity. It requires that we proac;vely understand the customs of our stakeholders and demonstrate respecwul behavior.
We approach directly those persons with whom we have a conflict or disagreement.
It can be difficult to confront colleagues that we disagree with. Many ;mes people gossip behind coworker’s backs rather than confront a disagreement head on. However, it is more respecwul to work with the person we have a disagreement with to try and resolve the situa;on.
We conduct ourselves in a professional manner, even when it is not reciprocated.
One of the most challenging situa;ons we find ourselves in is when someone is behaving poorly or being cri;cal of our work or our decisions. None the less, we should hold ourselves to a higher standard and demonstrate professional conduct even when others aren’t.
We do not act in an abusive manner toward others.
Related to conduc;ng our selves professionally, we must never behave abusively towards others. This includes not being disrespecwul, openly cri;cal in front of others, or rude.
We do not exercise the power of our exper2se or posi2on to influence the decisions or ac2ons of others in order to benefit personally at their expense.
Slide 54 discusses the various types of power. As project managers we oWen have expert power and to an extent, posi;on power. It is important to exercise that power with integrity rather than to benefit personally.
IIL-‐CERT5
Project Stakeholder Management The Project Management Cer;ficate Program
38 ©2014 Interna;onal Ins;tute for Learning, Inc.