Date post: | 03-Apr-2018 |
Category: |
Documents |
Upload: | nclogesh1981 |
View: | 235 times |
Download: | 0 times |
of 150
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
1/150
Version # Changed By
1.0 Rajesh Thallam
Prepared By: Rajesh Thalla
Prepared On: Dec 14th, 201
Version No.: 1.0For any suggestions to improv
Pleas
mailto:%[email protected]:%[email protected]7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
2/150
Change Details
Initial version
There are multiple spelling mistakes in the notes. This will be fixed in next version of notes
2
this notes, please email to [email protected]
read "HOW TO USE THIS NOTES" tab before you continue
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
3/150
READ QUESTIO
CAREFULLY
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
4/150
S & OPTIONS
! TWICE!!
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
5/150
HOW TO USE THIS NOTES?
1. Before using this notes, please read PMBOK or Rita's or any book to get fair i
2. Before attempting final exam or any mock test, you can use this test for revis
3. In Table of Contents tab, on the left, you will see PMBOK Pg43 which is the m
that process which explains KEY CONCEPTS, INPUTS, TOOLS & TECHNIQUES a4. On each process, there is a HOME button which will bring you back to this p
5. ITTO Consolidated sheet represents ITTO's of all processes in Excel format. T
use variance analysis or which processes have output as Work Performance Me
6. I have referred couple of websites to clear my doubts on confused topics wh
7. Following topics are "not" covered
* Process management framework and types of organization
* Ethics and responsibility
* Interpersonal Skills (Appendix G in PMBOK)
8. Suggested to read PMBOK or this notes Process Group wise in sequence as
SOURCES
1. PMBOK 4th Ed
2. Rita - PMP Exam Prep
3. Andy Crowe - How to pass PMP in First Try
4. Kim Heldman - Book in PMI reads
5. Christopher Scordo - Mock Tests
6. Some topics are copied from Rajesh Nair Notes on PMZilla.com
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
6/150
dea
ion
ain area of this notes. If you click on any process it will take you to details on
d OUTPUTSge
is will help you to analyze. If you want to ask question like which processes
asurements etc.
och are listed in separate tab.
ell as Knowledge Area wise in sequence
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
7/150
Process Group (5)
Knowledge Area (9)
Initiating (2) Planning (20)
.2 Collect Requirements
.3 Define Scope
.4 Create WBS
.5 Define Activities
.6 Sequence Activities
.7 Estimate Activity Resources
.8 Estimate Activity Durations
.9 Develop Schedule
.10 Estimate Costs
.11 Determine Budget
Project Quality Management
(3.12 Plan Quality
.15 Plan Risk Management
.16 Identify Risks
.17 Plan Qualitative Risk Analysis
.18 Plan Quanitative Risk Analysis
.19 Plan Risk Responses
Project Procurement
Mana ement (4.20 Plan Procurements
.1 Develop Project Charter
.2 Identify Stakeholders .14 Plan communications
.1 Develop Project Management
Plan
.13 Develop Human Resource Plan
Project Integration
Management (6)
Project Scope Management
(5)
Project Time Management
(6)
Project Cost Management (3)
Project Human Resource
Management (4)
Project Risk Management (6)
Project Communication
Management (5)
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
8/150
Executing (8) Monitoring & Controlling (10) Closing (2)
.1 Monitor & Control Project Work
.2 Perform Integrated Change
Control
.3 Verify Scope
.2 Perform Quality Assurance .7 Perform Quality Control
.3 Acquire Project Team
.4 Develop Project Team
.5 Manage Project Team
.6 Distribute Information
.7 Manage Stakeholders
Expectations
.8 Conduct procurements .10 Administer Procurements .2 Close procurements
.8 Report Performance
.9 Monitor & Control Risks
.1 Close Project or Phase
.6 Control Costs
.5 Control Schedule
.4 Control Scope
.1 Direct & Manage Project
Execution
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
9/150
Important
Project & Process framework
Professional Responsibility
There is not much detail about this topic in this notes. Please
refer Rita's or PMBOK. Will update shortly
Not covered
Excel formatted ITTO for easy navigationITTO Consolidated
Topics Usually Confused
Mock Up Exam Details
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
10/150
Project
- an endeavour to deliver a unique product or service and
are meant to meet strategic goals
- temporary duration
- undergoes progressive eloboration
- driven by market demands, customer requests, org requirements or
Operations/Ongoing work
- Work that is repetitive and does not have a clearly delineated
beginning and end. This type of work supports ongoing activity and is
usually managed within organizational functions. Its purpose is to
enable an organization to continue operating
- repetitive, required for thrive in business smoothly
e.g. writing expense reports every month, preparing metrics reports,
performance appraisals
If youre building cars on an assembly line, thats a process. If youre
designing and building a prototype of a specific car model, thats a
project
Responsibility of project manager- to meet the objects
- update the project plans with changes
- balance changing demands of project, budgets, scope, schedule
and quality
- balance stakeholders expectations
Sponsor
Typically, a senior executive of the organization or a management
group for which a project is carried out. The sponsor provides
financial resources and is the primary risk taker within the project.
Customer
The person or organization that purchases or uses the product or
service that results from a project.
Organizational culture
The unique nuances of how business is conducted and ways that the
organization operates. The shared values, norms, beliefs,
expectations, policies, procedures, and views of authority that
members of an organization have all make up the organizational
culture. How employees' view authority impacts communication
between the team and the project manager.
HOME
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
11/150
Functional Organizational structure
- org is grouped by areas of specialization within different functional
areas. Authority is with functional managers.
- Advantages - defined roles, simple reporting structures, cohesive
teams
- Disadvantages - lack of communication and colloboration between
functions, slow decision making due to sharing of mgmt role b/w
project mngrs and functional mgrs, high level of bureaucracy,
competetion of resources, limited project scope
Product
Stage Cost and staffing Uncerta
1. Starting the project Low High
2. Organizing and preparing Increases Decrea
3. Carrying out the work Peaks Decrea
4. Closing the project Decreases Low
Product life cycle stages
1.product inception and development
2.product introduction
3.product growth
4.product maturity
Project L
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
12/150
Portfolio
A collection of lower-level portfolios, programs, projects, and ongoing
work. The work is grouped to facilitate centralized and effective
management, aimed at meeting strategic objectives. The projects
and other work types in the portfolio may not be directly related.
Program
A group of related projects and operational work. It is managed in a
coordinated way to achieve benefits and a level of control not
possible when managing the work components individually.
CompetenciesKnowledge based comptency - knowledge on PM areas like
integration, procurement, cost, scope, time, quality, risk, human
resources, communication
Performance based competency - comes with experience and set of
skills to manage project
Personality based competency - leadership, ability to get things done,
Vendors
External organizations that supply goods or services required by a
project. Vendors, also known as sellers, are typically suppliers or
contractors that provide material or services for the company.
Business partners have a special relationship with the organization,
often acquired through a certification process.
Hidden Stakeholders
that may not be immediately apparent. Examples are stakeholders in
the physical, cultural, or political environment; future generations;
and members of the organization not directly involved in the project
but affected by the organization's structure and culture.
Organizational structure
How positions and departments are defined, and what the reporting
structure is in an organization. An organization may use a functional,
projectized, or matrix structure. A matrix structure blends functional
and projectized organizations. For example, a company could create
a dedicated project team comprised of members from each functional
department. The project manager is responsible for the team and its
work and has control of project resources.
Project Management Essentials
Portfolios, programs, projects and sub-projects
Stakeholder categories
Organizational influencers
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
13/150
Projectized Organizational structure
- entire company is organised by projects. The PM has control of
projects. Perssonal are assinged and report to a PM. Team members
only complete the project work and when the project is over, they do
not have a department to go back to.
- Advantages - freq. collaboration, rapid decision making via single
authority, increased organizational focus
- Disadvantages - employees working on many projects at a time, idle
time, relocating employes after proj is completed
ife Cycle
inty Cost of changes
Low
es Increases
es Increases
High
ife Cycle
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
14/150
Sub-project
Smaller portions of an overall project, created to enable easier
management. Sub-projects may be called projects, but they're really
smaller parts of a whole.
- A project may or may not be part of A program, but A
program will always have projects.
- Portfolios are organized around business goals and
Programs are organized around A shared benefit in
managing them together.
Project team
The people responsible for conducting a project. The project
manager is the person who is authorized to manage a project.
Project team members are the people who perform the work of a
project.
Organizational process assets
Project-related documents or data from previous work that can be
used to improve the current project or facilitate project management.
They include the plans, policies, procedures, and guidelines that may
influence a project's success. They also include knowledge assets.
Plans, templates, policies, and "lessons learned" databases can help
the project manager complete tasks quickly and improve quality by
avoiding mistakes made in the past
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
15/150
Matrix Organizational structure
- Team member reports to two bosses, the Project Mgr and the
Functional Mgr
- Share responsibility and authority between the two.
- As compared to functional org, there would be improved Proj Mgr
control over the resources and better horizontal & vertical
dissemination of information.
- Project life cycle can exist independent of product life cycle
- Project life cycle can run concurrently with product life cycle or form
part of product life cycle
- A single product life cycle can consist of many multiple Project life
cycle
- A product life cycle can completed during A single-phase Project
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
16/150
INPUTS
.1 Project Statement of Work
.2 Business Case
.3 Contract
.4 Enterprise Environmental Factors
.5 Organizational Process Assets
TOOLS & TECHNIQUES
.1 Expert Judgment
OUTPUTS
.1 Project Charter
Develop Project Charter
(Initiating)
KEY ASPECTS
* Involves developing a document that formally authorizes a project or phase and documenting initial requirements that satisfy
stakeholders needs and expectations
* Approved project charter formally initiates the project
* PM is assigned as early in the project, preferably while project charter is being developed and prior to start of planning
* Recommended - PM to participate in the development of project charter as it provides PM authority to apply resources to
project activities
* Projects are authorized by external to project such as sponsor, PMO, portfolio steering committee
* Project sponsor is responsible for creating project charter and sponsor funds the project
* Project initiator or sponsor will either create the project charter or delegate to PM. The initiator's signature on the charter
authorizes the project. This triggers the creation of needs analysis, business case or situation that the project will address
* Involves meeting with stakeholders, define high level objectives, constraints, assumptions and risks to assess feasibility of
project within the given constraints
* Project Charter does NOT NEED to change as the project progresses. Any change into project charter should raise question
whether it should continue?
INPUTS
.1 Project Statement of Work
* SoW is description of products or services to be delivered by the project. It references business need (market demand,
tech advance, legal), product description (characteristics of product or service to be delivered), strategic plan (org strategic
goals)
* Internal projects - SoW is prepared by project sponsor/initiator
* External projects - SoW is received from customer/buyer in the form of request for proposal (RFP), request for
information (RFI) or as part of contract
.2 Business Case
* A document that provides details on why project is worth the required investment
* Includes cost-benefit analysis to justify the project
* For external projects, requesting organization/customer/buyer will write the business case
* PM should know why the project was selected and project selections are "not" done by PM.
Refer Project Selection methods
.3 Contract
* When the work is done for external org, contract would be input for seller to write project charter with a view to increase
Project Selection
HOME
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
17/150
TOOLS & TECHNIQUES
.1 Expert Judgment
* Assess the inputs used to develop project charter on technical and management details during the process
OUTPUTS
.1 Project Charter
Input for ---> Develop Project Management Plan;; Collect Requirements;; Define Scope;; Identify
Stakeholders;;
* Project Title/Description
* Project Manager Assigned & Authority Level (who is given authority to lead the project and can PM determine, manage,
and approve changes to budget, schedule, staffing)
* Business Case (why this project is being done? With Justification)* Resources pre-assigned (How many or which resources will be provided)
* Stakeholders (who will affect or affected by the project)
* Stakeholder requirements (req. related to product/project scope)
* Product description/deliverables (end results)
* Measurable project objectives (summary milestone/summary budget)
* Project Approval Requirements (acceptance criteria for project success and who decides success and who signs off the
project)
* High Level project risks
*
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
18/150
PROJECT SELECTION METHODS
* PM is typically "not" involved in project selection. But the process used by company to select the project will influence how
PM will plan and manage the project
* Two categories of project selection methods -
1. Benefit Measurement Methods (Comparative Approach/ Decision Models) - Murder board, peer review, economic models,
scoring methods
2. Constrained Optimization Methods (Mathematical Methods/Calculation Approach) - Linear programming, non-linear
programming, dynamic programming, multi-objective programming
* Economic Models
* Present Value (PV) -A dollar today is worth more than a dollar tomorrow. e.g. If project is expected to produce $300Kin three yrs then the PV is going to be less than $300K. Reason is you wont get your $300K until 3rd yr but if put $300K in
bank today and after 3 yrs you would end up more than $300K. Bigger PV makes project attractive
PV = FV / (1 + r)n FV= future value, r = interest rate, n = # of time periods
* Net Present Value (NPV) - Same as PV except that costs also factor in. E.g. If you constructed building with PV $500K
and total cost was $350K then NPV is $500K - $350K = $150K. Bigger NPV makes project attractive
* Internal Rate of Return (IRR) - Bigger IRR is better
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
19/150
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
20/150
INPUTS
.1 Project Charter
.2 Outputs from planning processes
.3 Enterprise Environmental Factors
.4 Organizational Process Assets
TOOLS & TECHNIQUES
.1 Expert Judgment
OUTPUTS
.1 Project Management Plan
INPUTS
.1 Project Manage
.2 Approved Chang
.3 Organizational P
.4 Enterprise Envir
Develop Project Management Plan
(Planning)
KEY ASPECTS
* Process of documenting the actions necessary to define, prepare, integrate and coordinate all subsidiary plans
* Proj Mgmt Plan (PMP) defines how project is executed, monitored and controlled, and closed. It varies depending on the
application area and complexity of the project.
* PMP is developed through a series of integrated processes until project closure. This results in a PMP that is
progressively elaborated by updates and controlled and approved through the Perform Integrated Change Control process
* It would be approved by * The Project Manager, * The Project Sponsor, * The Functional Manager who are
providing resources for the project. (for the exam we will do much better to think of the Project Management Plan as
always being DETAILED).
* Exam: If the exam asks what to do when a project deviates significantly from established baselines, the correct answer is
likely the one about reviewing the projects risk mgmt process. Deviations from baselines are often due to incomplete
identification of risks and risk management.
* Configuration Management System and Change Control System are part of PMIS i.e. enterprise environmental
factors
* What to do when you encounter a change.
* You always begin dealing with change by consulting the project management plan.*
INPUTS
.1 Project Charter
Input from ---> Develop Project Charter
.2 Outputs from planning processes
* PMP has management plan from every knowledge plan and also following plans
Requirement Management Plan: How to identify, analyze and document the requirements and how req. will be
managed and controlled throughout the project
Change Management Plan: How changes will be managed and controlled, change control procedures, approval levels
for authorizing changes, creation of change control board, org tools to track the changes
Configuration Management Plan: Defines how to manage changes to deliverables and resulting documentation
(version of scope, cost, schedule components) and org tools to used for this effort
Process Improvement Plan: Identify existing processes and may create or improve some processes
.3 Enterprise Environmental Factors
* Govt or industry standards, PMIS, org structure and culture, infrastructure, personnel admin (hire/fire/perf reviews)
.4 Organizational Process Assets
* Standardized guidelines, work instructions, PMP template, change control procedures, project files past projects
KEY ASPECTS
* Process of perfo
* Activities include
* Create project
* Staff, train an
* Obtain, mana
* Implement pla
* Establish and
* Generate proj
* Issue change
* Manage risks
* Manage seller
* Collect and do
* Work performan
* Anothe impor
* This informat*
INPUTS
.1 Project Manag
Input from ---
.2 Approved Cha
Input from ---
* Perform Integ
* Approved cha
policies, procedure
* Approved cha
* They may req
.3 Enterprise En
* Org structure,
scheduling softewa
other online autom
.4 Organizationa
* Standardized
*
HOME HOME
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
21/150
TOOLS & TECHNIQUES
.1 Expert Judgment
* Improve current processes to project needs, develop tech/mgmt details, determine resource and skill levels, level of
configuration mgmt, project documents subjected to formal change control process
OUTPUTS
.1 Project Management Plan
Input for ---> All Executing, Monitoring & Controlling and Closing process groups
* PMP is consolidation of subsidiary management plans and baselines from planning processes
* PMP contains scope, cost, schedule baselines. Scope baseline is Proj scope stmt + WBS + WBS Dictionary
Together these baselines are called Performance Measurement Baseline which are part of PMP and used for keeping
track of them as they change.
* Once a project management plan is baselined, it may only be changed when a change request is generated and approvedthrough Perform Integrated Change Control process
* Performance measurement baseline in PMP is used for eanred value measurements
* The SCOPE mgmt plan, the SCHEDULE mgmt plan, the COST mgmt plan, the CHANGE mgmt plan, and the
CONFIGURATION mgmt plan are created right here.
TOOLS & TECHN
.1 Expert Judgm
* Expertise is pr
* Additional exp
.2 Project Manag
* It can include
Project Manageme
OUTPUTS
.1 Deliverables
* Approved deli
to complete a proc
.2 Work Perform
* Deliverable st
* Your job is to
your team perform.3 Change Reque
* Requests for a
* These can inc
documents)
.4 Project Manag
.5 Project Docum
* Updates to re
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
22/150
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
23/150
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
24/150
TOOLS & TECHNIQUES
.1 Expert Judgment
.2 Project Management Information
System
OUTPUTS
.1 Deliverables
.2 Work Performance Information
.3 Change Requests
.4 Project Management Plan Updates
.5 Project Document Updates
INPUTS
.1 Project Management Plan
.2 Performance Reports
.3 Enterprise Environmental Factors
.4 Organizational Process Assets
TOOLS & TECHN
.1 Expert Judgmen
Monitor & Con
(Monitoring
KEY ASPECTS
* Process of tracking, reviewing and regulating progress to m
* Monitoring is performed throughout the project which inclu
and assessing measurements and trends to effect prcoess im
* Control includes determining corrective or preventive action
actions taken resolved the performance review
* Activities include
* Compare actual performance against PMP
* Assess performance and recommend corrective/preventi
* Identify, track new risks and monitor existing risks
* Provide info to support project status, reporting
* Providing forecasts to update current cost and schedule
* Monitoring implementation of approved changes as they
INPUTS
.1 Project Management Plan
Input from ---> Develop Project Management Plan
.2 Performance Reports
Input from ---> Report Performance
* Performance reports include current status, milestones/m
.3 Enterprise Environmental Factors
* Govt or industry standards, company work authorization
.4 Organizational Process Assets
* Organization communication requirements
* Financial procedures (time reporting, expenditure and dis
* Issue and defect management procedures
* Risk control procedures (risk categories, probability defin
* Process measurement database
* Lessons learned database
Direct & Manage Execution
(Executing)
n the project management plan to achieve project objectives
s
aterials, tools, facilities)
dards
channels
hedule, technical and quality progress
oved changes
onses activities
and implement approved process improvement activities
cess apart from deliverables
tatus of the deliverables and what has been accomplished.
nagement Plan
Change Control
ocess updates change request status as approved or rejected
umented, authorized changes to expand or reduce the scope. They can also modify
schedules
led for implementation by project team
ntive or corrective actions
l administration, stakeholder risk tolerances, PMIS (Automated tool suite such as
anagement system, information collection and distribution system, web interfaces to
ructions
HOME
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
25/150
TOOLS & TECHNIQUES
.1 Expert Judgment
* Project management team provides expertise to interpre
* PM, along with team, determines actions to ensure perfo
OUTPUTS
.1 Change Requests
.2 Project Management Plan Updates
* Management Plans - Schedule, Cost, Scope, Quality
* Baselines - Scope, Schedule, Cost Performance
.3 Project Document Updates
* Forecasts, performance reports, issue log
anagement team using specialized knowledge/training
takeholders, professional and technical associations
ystems (PMIS)
ated systems used together, integrate and disseminate the outputs of the Develop
d verifiable product, result or capability to perform a service that must be produced
costs incurred
need to do more than deliver the results. You also need to keep track of how well
ork performance information output is about
ternal, direct/indirect, optional/legally mandated
reventive actions, defect repairs and updates (changes to fomally controlled
takeholder register, risk register, project logs (assumption/issues etc.)
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
26/150
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
27/150
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
28/150
OUTPUTS
.1 Change Requests
.2 Project Management Plan Updates
.3 Project Document Updates
INPUTS
.1 Project Management Plan
.2 Work Performance Information
.3 Change Requests
.4 Organizational Process Assets
.5 Enterprise Environmental Factors
TOOLS & TECHNIQUES
.1 Expert Judgment
.2 Change Control Meetings
OUTPUTS
.1 Change Reques
.2 Project Manage
.3 Project Docume
Perform Integrated Change Control
(Monitoring & Controlling)
KEY ASPECTS
* Process of reviewing all change requests, approving changes and managing changes to deliverables, o
project documents and project management plan
* Conducted from project inception to completion
* PMP, scope statement, other deliverables are maintained by carefully managing changes (approving/re
approved changes are incorporated into the revised baseline
* Activities include
* Influencing factors that bypass integrated change control so that only approved changes are implem
* Reviewing, analyzing, approving change requests promptly
* Managing the approved changes
* Maintain integrity of baselines by releasing only approved changes
* Review, approve, deny recommended corrective and preventive actions
* Coordinating changes across the project
* Documenting complete impact of change requests
* Corrective and Preventive Actions do not normally effect the Project Baselines, only the performance a
* Project Manager is given authority to approve certain types of change requests. Whenever required, C
INPUTS
.1 Project Management Plan
Input from ---> Develop Project Management Plan
* Contains subsidiary plans and the baselines against which actual will be compared (i.e. planned deli
from actual, a change request need to be submitted and approved and may lead to updated plan)
.2 Work Performance Information
Input from ---> Direct & Manage Project Execution
* Project deliverable status/schedule progress/cost-to-date and when they are deviated from planned
corrective action
.3 Change Requests
Input from ---> Verify Scope;; Control Scope;; Control Costs;; Control Schedule;; Perform
Assurance;; Perform Quality Control;; Manage Team;; Monitor & Control Risks;; Administer
Manage Stakeholder Expectations;; Report Performance;; Plan Procurements;; Conduct Pro
and Manage Project Execution;; Monitor & Control Project Work
* Direct and manage project execution - Project team find an efficient way to implement tasks and so
* Manage and control project work process - Corrective action after analyzing work performance info
ctives defined in PMP
an distributing performance information
wing upon action plans to determine if
forecast, issues, scheduled activities
tolerances, PMIS
aility and impact matrix)
HOME
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
29/150
TOOLS & TECHNIQUES
.1 Expert Judgment
* In addition to project team's expertise, stakeholders may be asked to provide expertise and sit on C
.2 Change control meetings
* Change control board reviews change requests and gives project manager level of authority (high/lo
requests
* Roles & responsibilities of CCB is clearly defined and agreed upon by all stakeholders
* All CCB decisions are documented and communicated to stakeholders for info and follow up
* Control board approves/rejects/on hold changes depending on feasibility of scope and impact to the
* Feasible - When project baseline can be adjusted without affecting projects performance beyond* Within Scope - If change request does not impact project performance baselines
OUTPUTS
.1 Change Request Status Update
* If Change request is not feasible
* Reject the change request and ask for additional info
* Update change control log, change request status
* Change request is feasible and within scope
* Update change control log, change request status, subsidiary plan
* Change request is feasible and out of scope* Update change control log, change request status, project documents, forecast, performance bas
* Change request status - Approved/Rejected/Pending - will be updated in change request log and ap
implemented during Direct & Manage Projet Execution process
.2 Project Management Plan Updates
* When change effects scope of a project, PM Plan must updated to reflect the changes in performan
subsidiary plans
e.g. Cost overrun due to supplier change will require changes to budget plan and procurement plan
* Changes to baseline should show only changes from current time forward. Past performance may n
y monitor and control processes
ectations
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
30/150
Configuration Management
* Configuration management is an overall system of which change control system is a part.
* Configuration mgmt provides tools to control project changes.
Features
* Ensure version control
* Product documentation version control
* Project management documentation version control* Only approved changes are version controlled
Why version control required?
* Prevent version related errors
How configuration management is helps to implement change control process? (Principles)
* Identify characteristics of change
* Controllin chan es - Track current status to either a rove or re ect chan e re uest
Involves Review, Approve and Manage changes to project deliverables, plans and processes
How changes be implemented? (Principles of change control process)
* Prevent the root cause for changes
* Identify method to identify changes early
* Daily status from team
* Meeting with customer or stakeholder
* Online sources for environmental, technical or legal changes
* Look at impact of the change
* Change control logs or issue logs
* Create a change request* Perform Integrated Change Control
i. Asess the impact
* Understand what led to change - customer demand, legislation change or technical defect so o
* Impact of change - Scope, cost, schedule and quality
* Should change go ahead? Benefits increase or decrease for project completion?
ii. Create options - are created based on crashing, fast tracking, reestimating..etc
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
31/150
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
32/150
INPUTS
.1 Project Management Plan
.2 Accepted Deliverables
.3 Organizational Process Assets
TOOLS & TECHNIQUES
.1 Expert Judgment
OUTPUTS
.1 Final Product or Service or Result
Transition
.2 Organizational Process Asset
Updates
Close Project/Phase
(Closing)
KEY CONCEPTS
* Involves finalizing all activities across all of the proj mgmt process groups to formally complete the project or phase
* Since project scope is measured against project mgmt plan, PM will review that document to ensure completion before
project is closed
* This process also establishes procedures to investigate and document the reasons for actions taken if a project is terminated
before completion
* Activities Involved
* Acceptance of deliverables - acceptance criteria laid out as by corporate guidelines
* Transfer of project's products, services, results to the next phase or to production and/or operations
* Administrative closures - Customer sign off, lessons learned (using Expert Judgment technique)
* Assessing project success - Compare actual results with the planned results defined in project mgmt plan
* To answer questions such as Was project delivered on time and budget? Was the quality acceptable? How well project
team performed? How many revisions were there to project?
* Performing audits or project post-mortem
* Written survey
* Closing meetings*INPUTS
.1 Project Management Plan
Input from ---> Develop Project Management Plan
* Compares actual results to the performance baselines outlined in the plan -
* Performance baselines - scope, schedule (whether delivered on time), budget (project expenses within limits) & risks
.2 Accepted Deliverables
Input from ---> Verify Scope
.3 Organizational Process Assets
* Company guidelines for closure, audits, subcomponent validations
* Historical information and lessons learned database (project records and documents, project closure information, info
about the results of previous project selection decisions, performance information, risk management effort)
HOME
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
33/150
TOOLS & TECHNIQUES
.1 Expert Judgment
* Experts ensure project/phase closure is performed as per standards
OUTPUTS
.1 Final Product, Service or Result Transition
* Transition of deliverables - Formal sign off, official transfer of product/service to next body/person, notify relevant
stakeholders
* The final product, service, or result is concerned with obtaining formal acceptance; organizational process assets involves
documenting and archiving formal acceptance.
* Another function of signoff is that it kicks off the beginning of the warranty period (if applicable)
.2 Organizational Process Asset Updates* Project Files - e.g. PM plan, scope/cost/schedule baseline, risk registers, planned risk response actions, project calendars,
risk impact assessment
* Project or Phase Closure documents
* Formal acceptance document, sign offs, transfer phase/project deliverables to Operations
* During project/phase closures, PM reviews prior phase documentation, customer acceptance from verify scope process
and contract (if applicable) to ensure that all project requirements are complete prior to finalizing the closure of the project
* Historical information
* Sign off documents
*
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
34/150
ADDITIONAL NOTES
* Probability of completing the project is highest during closing and risk is lowest. Majority of the work is completed - if not all
of the work - so the probability of not finishing the project is very low.
* Stakeholders have the least amount of influence during the Closing processes, while project managers have the greatest
amount of influence. Costs are significantly lower during this process because the majority of the project work and spending
has already occurred
* Weak matrix organizations tend to experience the least amount of stress during the Closing processes. This is because, the
functional manager assigns all tasks (projectrelated tasks as well) so the team members have a job to return to once the
project is completed and there's no change in reporting structure.
* Projects come to an end for several reasons:* They're completed successfully.
* They're canceled or killed prior to completion.
* They evolve into ongoing operations and no longer exist as projects.
* Four formal types of project endings exist
*Addition: Projects that evolve into ongoing operations are considered projects that end because of addition; in other
words, they become their own ongoing business unit i.e. Operations
* '* Exam:Remember that product verification, which determines whether all of the work of the project was completed correctly
according to the contract or other procurement terms and satisfactory according to stakeholder expectations, is performed
during the Closing processes. Product documentation is verified and accepted during the Verify Scope process. One more note:
when projects end prematurely, the Verify Scope process is where the level of detail concerning the amount of work completed
gets documented.
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
35/150
Understanding Project Scope
* Scope is work required to complete deliverables
* Scope is like boundary around project - inside boundary is "within scope" and outside boundary is "out
* Project scope is based on product scope and is all of the work that needs to be done to make the prod
* Product scope is defined by components, functions and features
* Scope changes always have cost/quality/schedule implications
* Processes uses to manage scope as well as supporting tools/techniques vary by application area and
as part of the project life cycle
* Scope baseline = Approved project scope statement + WBS + WBS dictionary. This base
monitored, verified and controlled throughout the lifecycle of the project
* Exam: The project scope management plan is a planning tool that documents how the project team w
defining project scope, how the work breakdown structure will be developed, how changes to scope wil
and how the work of the project will be verified and accepted. Scope management plan is a subsidiamanagement plan and created during Develop Project Management Plan process.
* Exam: Scope management involves managing both product and project scope
* Exam: Give priority to the customer
* Scope Creep
* Scope creep is what happens when scope changes are not detected early enough or managed
* Refers to how small, slow and often unpredicted changes can "creep" unnoticed or be ignored becau
project scope is not realized
* This happens when you think you know the impact of a change so you go ahead, but it turns out tha
leads to another one, and since you are already making the first change, you go with the next. Then ano
comes up, and another, and another, until its hard to tell what the scope of the project is.
* Causes of scope creep
* Unexpected scope related issues: Changes project requirements or raise its complexity* Perfectionism: Adding extra features than required causes change in scope and may end up costing
and money
* Placating stakeholders
* Misunderstandings: Especially careful to avoid ambiguity or unclear statements.
* Ramblings from Questions
Project Scope Management Processes
* Collect requirements (Planning Process Group)
* Investigate, define, document stakeholders needs and
* Expectations about project and about products features and functions
* Define Scope
* Involves creating project scope statement that defines work required to deliver product and service
( Elaborates on project deliverables, assumptions, constraints for a project (used throughout the pro
* Create WBS
* WBS subdivides each task into smaller, manageable work packages
* Execution stage of project relies heavily on WBS
* Control scope
HOME
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
36/150
Understanding Time Management Processes
* Where does time management processes fall in the planning activities?
1. Define scope documents
2. Plan resources
3. Plan schedule
4. Plan cost
* Triple constraint model can be used to determine what changes need to be made
* Schedule management plan is created during Develop Project Management Plan, which selects a scheduling methodology,
scheduling tool, sets the format and establishes criteria for developing and controlling the project schedule
Which tool to use?
. Depends on complexity of project, unknowns, potential risks, dependencies among the deliverables
Small to medium project
. Decompose all work packages during planning stage.
. Not required on this type of project.
. Use standardized template based on similar projects.
. No external subject matter experts required. Use project manager and team's own expertise.
Medium to large project
. Decompose known, low-risk work packages during planning stage. Leave unknown work packages and those with
preceding . dependencies to be decomposed later.. Use rolling-wave planning on later-occurring work packages.
. Use standardized template based on similar projects.
. Use judgment from external experts to understand unknowns, dependencies, unfamiliar aspects of the project.
* Define Activities
Decomposing the work packages into activities. First you come up with a list of all of the activities that will need to be
completed.
* Sequence Activities
Determining the order the activities need performed in. Next, you figure out which activities need to come before others
and put them in the right order. The main output here is a network diagram, a picture of how activities are related.
* Estimate Activity Resources
Finding out the quantities and types of resources needed for the activities. Estimate the resources youll need to do the job,
and create a list of them...* Estimate Activity Durations
Determining how long the activities will take. ...and then estimate the time it will take to do each activity.
* Develop Schedule
Creating the project schedule. Then you build a schedule from all of the estimates, and the resource and activity
information youve created.
* Control Schedule
Monitoring the schedule and influencing the factors that can lead to schedule changes. Finally, you monitor and control
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
37/150
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
38/150
INPUTS
.1 Scope Baseline
.2 Enterprise Environmental Factors
.3 Organizational Process Assets
TOOLS & TECHNIQUES
.1 Decomposition
.2 Rolling Wave Planning
.3 Templates
.4 Expert Judgment
OUTPUTS
.1 Activity List
.2 Activity Attributes
.3 Milestone List
Define Activities
(Planning)
KEY ASPECTS
* Closely linked to WBS
* It takes work packages defined in WBS and breaks them down to activities so that it is better able to estimate duration,
schedule them and monitor and control their progress
INPUTS
.1 Scope baseline
Input from ---> Define Scope
* consists of project scope statement, WBS and WBS dictionary
* This has following information that helps in defining activities
* Work packages (deliverables) and their activities
* Dependencies and relationships between the packages
* Project assumptions and constraints
.2 Enterprise environmental factors
* PMIS
.3 Organizational process assets
* Formal/Informal activity planning related policies* Lessons learned
TOOLS & TECHNIQUES
.1 Decomposition
* Decompose work packages (defined in WBS) into activities for estimating purposes and list them in activity list
.2 Rolling-wave planning/ progressive elaboration
* Decompose WBS in stages based on information needed or available at the time
* Work packages to be completed in near time are broken into activities, sequenced and added to schedule while work
packages to be completed in future remain temporarily at work package or mile stone level
.3 Templates
* Standard activity list from previous project is often used as a template for new project* Templates can also be used to identify typical schedule milestones
.4 Expert judgment
* Important if you do not have prior experience in handling this kind of project (can be internal or external judgments)
HOME
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
39/150
OUTPUTS
.1 Activity List
Input to ---> Sequence Activities;; Estimate Activity Resources;; Estimate Activity Durations;; Develop
Schedule
* A table that links an activity to work package in WBS and briefly describes work required for the activity
* 2 roles - track activities, describe activities
.2 Activity Attributes
Input to ---> Sequence Activities;; Estimate Activity Resources;; Estimate Activity Durations;; Develop
Schedule* Similar to activity list but with additional attributes than defined in activity list. These attributes depend on nature of the
project and how project manager feels to describe the activities
* Serves two functions - sequencing activities and help team members to carry out the activities
* Attributes used in sequencing activities are - predecessor activities, successor activities, logical relationships, leads and
lags, imposed dates
* Attributes that help team members to carry out activities are resource req., locations, effort, constraints and assumptions
.3 Milestone List
---
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
40/150
INPUTS
.1 Activity List
.2 Activity List Attributes
.3 Milestone List
.4 Project Scope Statement
.5 Organizational Process Assets
TOOLS & TECHNIQUES
.1 Precedence Diagramming Method
.2 Dependency Determination
.3 Apply Leads and lags
.4 Schedule Network Templates
OUTPUTS
.1 Project Schedule Network Diagram
.2 Project Document Updates
Sequencing Activities
(Planning)
KEY ASPECTS
* To identify logical relationship between the activities and develop a realistic schedule
* To represent sequence of activities and their dependencies, you create a project schedule network diagram
* Sequencing activities involves determining the dependencies and relationships between activities and applying leads and lags
* There are two types of Network Diagrams:
*Arrow Diagramming Method (ADM) - Creates diagrams known as activity-on-arrow (AOA). This is because ADM
diagrams use activities shown on arrows and connected by nodes, usually shown as circles. ADMs drawback is that it can only
show finish-to-start (FS) relationships. In order to show relationships between tasks on different node branches, ADM diagrams
use dummy activities.
* Precedence Diagramming Method (PDM) - Refer below
INPUTS
.1 Activity list
Input from ---> Define Activities
.2 Activity attribute list
Input from ---> Define Activities
* Activity attributes may describe necessary sequence of events or defined predecessor/successor relationships
.3 Milestone list
Input from ---> Define Activities
.4 Project scope statement
Input from ---> Define Scope
* Product scope description includes product characteristics that may affect activity sequencing
* This info is already captured on activity list but is generally reviewed from project scope statement for accuracy.5 Organizational Process Assets
* Old schedule network diagrams can be helpful in creating good quality diagrams for the current project
* Description of scheduling methodology used and how dependencies were determined
TOOLS & TECHNIQUES
.1 Precedence diagramming method
* Used in critical path methodology (CPM) for constructing project schedule network diagram
* Also called Activity-On-Node (AON) - used by most PM software packages
* PDM has 4 types of logical relationships or types of dependencies
* Start to start - Activity A must start before activity B can start. E.g. without having begun filming on a documentary
(A), you would be unable to start the editing process (B).
* Start to finish - Activity A must start before activity B can finish. E.g. you can't start running a new operating system
on your computer (B) until you stop using your old system (A). This is not commonly used* Finish to start - Activity A must finish before you can begin activity B. E.g. you would have to put together computer
hardware (A) before programming software (B). This is the most common type of relationship.
* Finish to finish - Activity A must finish before activity B can be completed. E.g., the activity of editing a manuscript
can't be finished (B) until all the text has been written (A)
.2 Dependency Determination
* Types of dependency - mandatory, discretionary, external
* Mandatory Predecessors (hard logic) -
* -
HOME
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
41/150
OUTPUTS
.1 Project Schedule Network Diagrams
Input to ---> Develop Schedule
* Allows to create realistic project schedule and monitor this as work proceeds
.2 Project Document Updates
* Updates to activity list, activity attributes, risk registers based on any new information gathered during the process
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
42/150
INPUTS
.1 Activity List
.2 Activity Attributes
.3 Resource Calendars
.4 Enterprise Environmental Factors
.5 Organizational Process Assets
TOOLS & TECHNIQUES
.1 Expert Judgment
.2 Alternatives analysis
.3 Published Estimating Data
.4 Bottom-up Estimating
.5 Project Management Software
OUTPUTS
.1 Activity Resource Requirements
.2 Resource Breakdown Structure
.3 Project Document Updates
Estimating Activity Resources
(Planning)
KEY ASPECTS
* Determine resources needed to complete project i.e. material, people, equipment and facilities and gathering information
needed to create a realistic schedule and budget
* Types of resources
* Quantity of resources
* Required skill sets
* Project team roles and availability
* Closely coordinated with Estimate Costs Process
INPUTS
.1 Activity list
Input from ---> Define Activities
* Identifies activities which will need resources
.2 Activity attributes
Input from ---> Define Activities
* Contains input for use in estimating resources required for each activity
.3 Resource calendar
Input from ---> Acquire Project Team;; Conduct Procurements
* Human resources, material resources, skill resources calendars
* The process of estimating the type and quantities of material, people, equipment, or supplies required to perform each
activity. Before you can assign resources to your project, you need to know which ones youre authorized to use on yourproject. Thats an input, and its called Resource Calendars.
* Resource Calendars specify WHEN and HOW LONG identified project resource will be available during the project.
.4 Enterprise environmental factors
* Resource availability and skills
TOOLS & TECHNIQUES
.1 Expert judgment
* Any group/person with specialized knowledge in resource planning and estimating can provide such expertise
.2 Alternatives analysis
* Alternate ways to schedule activities - determine best possible use of resources, different size or type of machines,
different tools (hand vs. automated), make-or-buy decisions regarding resource etc.
* Quantify what resources are required
.3 Published estimated data
* Published updated rates and unit costs of resources* This data can give you frame of reference to work from when resources are being quantified
.4 Bottom-up estimating
* When an activity cannot be estimated with a reasonable degree of confidence the work within the activity is decomposed
into more detail. The resource needs are estimated
* Used when project is new and there are no previous estimated data
* More accurate, slower to carry out, more costly
.5 Project management software
*
HOME
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
43/150
OUTPUTS
.1 Activity Resource Requirements
Input to ---> Estimate Activity Durations;; Develop Schedule;; Develop Human Resource Plan;; Plan
Procurements
* Describes types and quantities of resources needed for each project activity
* Contains information - Resource description, number required, resource assumptions, resource availability, resource
dependencies, basis of estimates
* Recording resource assumptions is important as they can help during different stages of a project - Monitoring &
controlling performance, closure* Review assumptions is important to determine whether anything in the project or env changed since the estimates were
made
* Record resource requirements
.2 Resource breakdown structure
* Hierarchical representation of resources required in project
* Visually simple, breaks resources into categories and resource type
* Helps to organize a project schedule and report on utilization information
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
44/150
INPUTS
.1 Activity List
.2 Activity Attributes
.3 Activity Resource Requirements
.4 Resource Calendars
.5 Project Scope Statement
.6 Enterprise Environmental Factors
.7 Organizational Process Assets
TOOLS & TECHNIQUES
.1 Expert Judgment
.2 Analogous Estimating
.3 Parametric Estimating
.4 Three Point Estimates
.5 Reserves Analysis
OUTPUTS
.1 Activity Duration Estimates
.2 Project Document Updates
INPUTS
.1 Activity List
Input from ---> Define Activities
* Activities for which duration will be estimated. Activities within scope should appear on this list
.2 Activity Attributes
Input from ---> Define Activities
* They describe req. or limitations on specific activities, assumptions & constraints on location and timing of activities. These
factors affect duration estimates
.3 Activity Resource Requirements
Input from ---> Estimate Activity Resources
* Resources assigned to the activity and their availability will significantly influence the duration of estimates
.4 Resource CalendarInput from ---> Conduct Procurements, Acquire Project Team
* Resource availability, capabilities and skills make the difference in estimates
.5 Project Scope Statement
Input from ---> Define Scope
*TOOLS & TECHNIQUES
.1 Expert Judgment
* Expert judgment with historical info can provide duration estimate info or recommended max activity durations from prior
similar project
* Also determines whether to combine methods of estimating and how to reconcile differences b/w them
.2 Analogous Estimating
* Also known as top-down estimating
* Uses parameters such as budget, duration, size, weight and complexity from prev project and relies on actual duration of
previous similar projects for estimating duration of current project* Gross value estimating approach, sometimes adjusted for known differences in complexity
* Frequently used to estimate project duration when there is limited info about the project (like in early phases)
* Less costly and less time consuming and less accurate
* Combines expert judgment with historical info from similar projects completed in past
* Applies to entire project or segment of a project and used in conjunction with other estimating methods
.3 Parametric Estimating
* Statistical relationship between historical data and other variables to calculate estimate for activity parameters
* -
Estimating Activity Durations
(Planning)
KEY ASPECTS
* Process of estimating number of work periods (activity duration) required to complete individual activities with estimated
resources
* Uses activity scope of work, resource types, resource quantities and resource calendars
* The inputs for activity duration originate from person or group on the project team who is most familiar with the nature of
work
* Effort = Amount of labor invested in activity. Usually expressed as staff hours, staff days, or staff weeks
Duration = How long an activity is expected to take with the available labor. Usually expressed as workdays or workweeks
* Activity Durations Estimates show calendar time and not just person-hours
HOME
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
45/150
OUTPUTS
.1 Activity Duration Estimates
Input to ---> Develop Schedule;; Identify Risks
* Show how much time is required for each activity
* Does not include lags/leads
* May include range of possible results. E.g: 2 weeks +- 2 days or 15% of probability of exceeding 3 weeks
.2 Project Document Updates
* May require changes to activity attributes or assumptions made in developing activity duration estimate
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
46/150
INPUTS
.1 Activity List
.2 Activity Attributes
.3 Project Schedule Network Diagrams
.4 Activity Resource Requirements
.5 Resource Calendars
.6 Activity Duration Estimates
.7 Project Scope Statement
.8 Organizational Process Assets
.9 Enterprise Environmental Factors
TOOLS & TECHNIQUES
.1 Schedule Network Analysis
.2 Critical Path Method
.3 Critical Chain Method
.4 Resource leveling
.5 What-if Analysis
.6 Applying Leads and Lags
.7 Schedule Compression
.8 Scheduling Tool
INPUTS
.1 Activity List
Input from ---> Define Activities
* List of activities to be performed to complete the project
.2 Activity Attributes
Input from ---> Define Activities
* Details how and when activities need to be performed
.3 Activity Resource Requirements
Input from ---> Estimate Activity Resources
. Describes types and quantities of resources required to complete an activity
.4 Project Scope Statement
Input from ---> Define Scope. Develop project schedule process uses assumptions and constraints listed in scope
schedule
.5 Resource Calendars
Input from ---> Acquire Project Team;; Conduct Procurements
TOOLS & TECHNIQUES
.1 Schedule Network Analysis
* Employs various analytical techniques - CPM, Critical Chain Method, What-If analy
and late start and finish dates for uncompleted portions of project activities
.2 Critical Path Method
* Calculates theoretical Early/Late Start and Finish dates of each activity without reg
* Longest full path linking activities that must be performed in sequence is known a
. Together, estimated durations of activities on this path represent shortest time in
* Critical paths have Zero or negative total float and schedule activities on critical pa* A delay in any one of the critical path activities will cause the entire project to be
.3 Critical Chain Method
* Modifies project schedule to account for limited resources. After critical path is ide
resourced limited schedule result is determined. The resulting schedule often has alter
* This resource constrained critical path is known as critical chain
* This method adds duration buffers - Project buffers added at the end of critical ch
project from slippage. Feeding buffers placed at each point that a chain of dependent t
(Planning)
KEY ASPECTS
* Project schedule co-ordinates activities,
* Helps manager optimize use of resources
* Provides baseline against project progress can be tracked and
* Serves as communication tool
* Project schedule consists of activity identifier, activity description, resources, calenda
(duration bars, data date line, precedence arrows)
HOME
CPM... Click here
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
47/150
Critical Path method
* Critical Path: Longest duration path through a network diagram and determines sh
project
* Near Critical Path: The closer in length near critical path and critical path, more ris
both the critical paths.* Total Float/Slack: Amount of time an activity can be delayed without delaying the
* Free Float/Slack: Amount of time an activity can be delayed without delaying early
Free float = ESsuccessor - ( ESpredecessor + DURATIONpredecessor )
* Project Float/Slack: Amount of time project cen be delayed without delaying exte
customer/management.
*Activities on critical path have ZERO or negative total float
* Three steps
* Forward pass: Determines early start and early finish dates for all activities
* Backward pass: Determines late start and late finish dates for all activities
* Float: Difference between early start & late start or early finish & late finish is defi
Float = LS - ES or Float = LF - EF
*
OUTPUTS
.1 Project Schedule
* can be represented in below formats
* Milestone charts
* Represents only key events of a project
* Milestones are identified during define activity process which produces mileston
* Each milestone has zero duration and called milestone activity
* Detailed information about milestone - activity id, activity description, duration,
* Milestone chart provides quick way to check project progress in term of signific* Audience for this format is management, customer and project manager for mo
* Bar charts | Gantt Charts
* Activity is represented by duration bar
* Schedule information rolled up to level of main deliverables (level 2) in WBS
* Each activity is represented by a horizontal bar and width of bar represents esti
shows how much activity is completed
* A vertical dotted date line represents as of date for the progress reported in the
* -
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
48/150
OUTPUTS
.1 Project Schedule
.2 Schedule Baseline
.3 Schedule Data
.4 Project Document Updates
INPUTS
.1 Project Management Plan
.2 Project Schedule
.3 Work Performance Information
.4 Organizational Process Assets
TOOLS & TECHNIQUES
.1 Performance Reviews
.2 Variance Analysis
.3 Resource Leveling
.4 What-if Scenario Analysis
.5 Applying Leads and Lags
.6 Scheduling Compression
.7 Project Management Software
.8 Scheduling Tools
(Monitoring & Controlling)
KEY ASPECTS
* Determine current status of the project schedule
* Influence the factors that cause changes - being proactive and using preventive me
* Having Monitoring system that alerts project manager whenever a change threaten
* Managing changes by putting them through project's change control system
* Control Schedule is component of Perform Integrated Change Control process
* Important: Not all schedule variances will impact the schedule. For example, a dela
the overall schedule and might not need corrective action. Use caution here, though
task or its duration is increased for some reason, that task can actually become part
tasks will always cause delays to the project completion date and require corrective a
INPUTS
.1 Project Management Plan
Input from ---> Develop Project Management Plan
* Two areas - schedule baseline and schedule management plan
* Schedule baseline contains baseline start and finish dates and provides basis of
performance
* Schedule mgmt plan describes circumstances in which schedule changes are allo
made. After scheduled change requests are approved, they become another input of
.2 Project Schedule
Input from ---> Develop Schedule
* Latest version of schedule for updates, completed activities and started activities
.3 Work Performance InformationInput from ---> Direct and Manage Project Execution
* How much work has been performed?
* Provides actual dates and durations of the activities
* Compare with baseline dates and durations
TOOLS & TECHNIQUES
* To bring performance back in line with schedule and change schedule to match wit
Monitoring performance
.1 Performance Reviews
* Measure and analyze schedule performance i.e. actual start and finish dates, per
* Using schedule network diagrams to assess performance allows to determine wh
* SV/SPI from EVM are used to assess magnitude of schedule variations
* If critical chain scheduling method is used, comparing buffer remaining to the bu
can help determine schedule status.2 Variance Analysis
* SV and SPI assess magnitude of variation from original schedule baseline
* Total float variance is also an essential planning component to evaluate project ti
* Based on variance whether corrective or preventive action needs to be taken
Controlling variance
* Requires adjustments to baseline to reflect current project realities
* Many of the techniques used in developing project schedule are used in controlli
statement while developing project
is, resource leveling to calculate early
ard to resource limitations
critical path
hich a project can be completed
th are called critical activitieselayed.
ntified, resource availability is entered and
d critical path
in protecting target finish date of the
asks not on the critical chain feeds into
r unit, project schedule time frame
HOME
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
49/150
Schedule Variance
Schedule variance = Earned Value - Planned Value
SV = EV - PV
Schedule Performance Index
Schedule variance = Earned Value / Planned ValueSV = EV / PV
OUTPUTS
.1 Work Performance Measurements
* Schedule control activities, like monitoring and measuring performance, may res
proj mgmt plan component. To estimate degree of schedule impact and severity of th
These need to be calculated and communicated to stakeholders
.2 Change Requests
* Review of variance analysis, performance measures results in change requests t
using perform integrated change control process
* Type of change requests are - changes to start/finish dates, activity durations, pr* Preventive actions may include recommended changes to reduce the probability
.3 Project Management Plan Updates
* Schedule management plan: To reflect change in the way schedule is managed
* Schedule baseline: In response to change requests related to scope, activity reso
* Cost baseline: To reflect changes caused by compression or crashing techniques
.4 Project Documents Updates
* Schedule data: New project schedule network diagrams might be developed to d
ortest path it could take to complete the
kier the project is. PM has to manage
project end date or milestones
start date of its successor
nally imposed project completion date by
ned as float
e list an output
whether milestone is mandatory/optional
nt eventsnitoring and reporting purposes
mated activity duration. Shading on bars
chart
Activity name(Float)
ES EF
LFLS
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
50/150
OUTPUTS
.1 Work Performance Measurements
.2 Change Requests
.3 Project Management Plan Updates
.4 Project Document Updates
.5 Organizational Process Asset Updates
asures to avoid schedule slippage
the schedule
to a noncritical path task will not delay
if a delay occurs on a noncritical path
f the critical path. Delays to critical path
tion. Careful watch of the variances in
easuring and reporting schedule
wed and how these changes should be
ontrolling the schedule
as of the indicated data date
actual performance
entage of work unfinished
ether delays effect critical path
ffer needed to protect the delivery date
ime peformance
g variance also
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
51/150
lt in updating schedule baselines or other
e impact, SPI and SV needs to calculated.
schedule baseline which are reviewed
oject milestonesof negative schedule variances
urces or activity durations
isplay approved remaining durations and
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
52/150
Understanding Cost Management
Covered in this column
* Contents of Cost Management Plan
* Types of Costs
Planning Process Group
* Estimates Cost
* Process of forecasting what each project activity will cost based on resources required to complete it
* Determine budget
* Process of adding up estimated costs for each activity or work package to get an estimated budget for entire budget
Monitoring & Controlling Process Group
* Control costs
* Process of keeping actual costs and planned budget in line
* Involves influencing factors that cause cost variances and manage changes to the budget
* Project cost management should consider stakeholder requirements for capturing costs.
* Project cost management is primarily concerned with cost of resources needed to complete project activities
* Ability to influence costs is greatestat the early stages of the project, making early scope definition critical
* The work involved in performing Project Cost Management knowledge area is preceded by generating Cost
Management Plan which part of Develop Project Management Plan
* Cost Management Plan sets out format and establishes criteria for planning, structuring, estimating, budgeting and
controlling project costs
* Cost Management processes and their associated tools and techniques are established during project life cycle
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
53/150
* Cost Management Plan contains
* Level of Accuracy: Rounding of data to a prescribed precision based on scope of the activities and magnitude of the
project and may include amount of contingencies
* Units of Measure: Unit used in measurements is defined for resources (staff hours, days, weeks)
* Organizational Procedure Links: WBS provides framework for cost management plan which allows for consistency
with estimates, budgets and control of costs. The WBS component used for project cost accounting is called control account
which is linked directly to accounting system using unique code identifier
* Control Thresholds: Variance thresholds for monitoring cost performance to indicate amount of variation to be
allowed before action needs to be taken. Expressed as % deviations from baseline plan* Rules of Performance Measurement: Earned Value Management rules are set.
* Define WBS and points at which measurement of control accounts will be performed
* Establish EVM techniques (weighted milestones, fixed formula, % complete)
* Project EAC and other forecasting methodologies
* Reporting formats: frequency and format of cost reports
* Process Descriptions: Descriptions f Estimate, Budget and control costs
* Types of costs
* Direct cost: include dedicated labor, material, supplies, equipment, licenses, fees, training, travel, or professional
service fees
* Indirect cost: Example, if a color printer is shared by several project teams, its difficult to definitively determine what
percentage of costs each should share.*Variable cost: fluctuate and can't be predicted with absolute certainty. For example, travel or transportation costs that
can change depending upon the cost of fuel or certain commodities and types of raw materials.
* Fixed cost: are static throughout the project or have only a small likelihood of fluctuation. Fixed costs are usually for
items such as rents, leases, licenses, salaries, and fixed fees
* Factors affecting costs
* Risks: During early phases, the greatest risk to budget accuracy is usually that the scope, activity, and constraints
arent fully known
* Total Cost of Ownership/Life-Cycle:
* Cost of Quality: Cost that is incurred to achieve required quality
* Marketplace Conditions
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
54/150
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
55/150
INPUTS
.1 Scope Baseline
.2 Project Schedule
.3 Risk Register
.4 Human Resource Plan
.5 Enterprise Environmental Factors
.6 Organizational Process Assets
TOOLS & TECHNIQUES
.1 Expert Judgment
.2 Analogous Estimating
.3 Parametric Estimating
.4 Three-point Estimating (PERT)
.5 Reserve Analysis
.6 Bottom Up Estimating
.7 Cost of Quality
.8 Project Management Estimating
Software
OUTPUTS
.1 Activity Cost Estimates
.2 Basis of Estimates
.3 Project Document Updates
KEY ASPECTS
* Estimating involves developing of approximation of cost needed to complete project activities i.e. costs of resources like
labor, materials, equipments, services, facilities, categories like inflation allowance, contingency costs...
* Estimates are prediction based on information known at that point of time
* Estimates are expressed in units of currency or units of measure (staff hours)
* Accuracy of Estimates:
* Rough order of magnitude estimate ROM: This type of estimate is made during initiating process. Typical range is
+/-50 percent from actual. These are usually top-down estimates made by expert judgment.
* Budget estimate: This type of estimate is made during Planning phase. Typical range is -10 to +25 percent from
actual.
* Definitive estimate: This type is the most accurate estimate. Later during the project estimates will become more
refined, some PMs use the range of-5 to +10 or -/+10.
* Benefits
* Identifies funding requirements
* Establishes cost baseline
INPUTS
.1 Scope Baseline
Input from ---> Create WBS
* Work Breakdown Structure (WBS) - Each work package provides basis for cost estimation. WBS is developed
progressively using rolling-wave planning, and as a result project's cost estimate baseline is also often refined progressively
* WBS Dictionary - this contains work description, milestones, work to be done that are needed to estimate costs likeresource req. and dependencies
* Scope Statement - This document is aimed at stakeholders and while estimating costs it provides product desc,
acceptance criteria, key deliverables, project boundaries, assumptions, constraints. One basic assumption made during
estimation is whete estimates will be limited to direct costs only or includes indirect costs. Common constraints are limited
budget, required delivery dates, available skilled resources etc.
.2 Project Schedule
Input from ---> Develop Schedule
* Contains planned dates for performing schedule activities and info about what resources are needed and for how long
* Helps in estimates costs for staff, material, location, equipment
.3 Human Resource Plan
---
Estimate Costs
(Planning)HOME
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
56/150
TOOLS & TECHNIQUES
.1 Expert Judgment
* Estimates are influenced by variables such as labor rates, material costs, infaltion risk factors etc. Expert judgment guided
by histroical info provides valuable insight about the env and info from prior similar projects
* Also determines whether to combine methods of estimating and how to reconcile differences b/w them
.2 Analogous Estimating
* Also known as top-down estimating
* When you use costs of previous project to forecast costs for current project (when projects are similar)
* Based on parameters such as scope, cost, budget, duration, size, weight, complexity from previous similar project is usedas basis for estimating for current project
* Gross value estimating approach, sometimes adjusted for known differences in complexity
* Frequently estimate project duration when there is limited info about the project (like in early phases)
* Less costly and less time consuming and less accurate
* Combines expert judgment with historical info from similar projects completed in past
* Applies to entire project or segment of a project and used in conjunction with other estimating methods
.3 Parametric Estimating
*OUTPUTS
.1 Activity Cost Estimates
Input to ---> Determine budget;; Plan Procurements;; Identify Risks
* Quantitative valuations of how much costs required for carrying out a project
* Depends on direct costs like material, equipment, labor, services and might include indirect costs* Can be in detail or summarized
.2 Basis of Estimates
Input to ---> Determine Budget
* Detailed explanation of factors on which activity cost estimate is based
* Details like activity scope of work, documents how on what basis cost was estimated, assumptions made, constraints,
range of possible estimates
.3 Project Document Updates
* Like risk registers or any documents impacted because of changes in cost
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
57/150
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
58/150
INPUTS
.1 Activity Cost Estimates
.2 Basis of Estimates
.3 Scope Baseline
.4 Project Schedule
.5 Resource Calendar
.6 Contracts
.7 Organizational Process Assets
TOOLS & TECHNIQUES
.1 Cost Aggregation
.2 Reserves Analysis
.3 Expert Judgment
.4 Historical Relationship
.5 Funding Limit Reconciliation
OUTPUTS
.1 Cost Performance Baseline
.2 Project Funding Requirements
.3 Project Document Updates
Determine Budget
(Planning)
KEY ASPECTS
* Aggregating estimated costs of individual activities or work packages to eastablish authorized cost baseline
* Baseline includes all authorized budgets, excludes management reserves
* Estimated costs of each activity is converted to realistic cost performance
* Larger projects may be divided into multiple Cost Baselines.
INPUTS
.1 Activity Cost Estimates
Input from ---> Estimate Costs
* How much each scheduled activity costs to complete? Includes resource costs like staff, material, equipment
* Aggregate cost estimates for each activity within a work package to obtain cost estimate for work package
.2 Basis of EstimatesInput from ---> Estimate Costs
* Document recorded about how you arrived at the cost estimate? E.g: Any basic assumptions like inclusions or exclusions
of indirect costs
.3 Scope Baseline
Input from ---> Create WBS
* Scope statement identifies budget limitations (mandated by organization or contract or govt policies)
* WBS shows relationship between the project deliverables and components
* WBS dictionary lists work that needs to occur in each component to complete the project
* All these help in estimating budget more accurately
.4 Project Schedule
---
HOME
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
59/150
TOOLS & TECHNIQUES
.1 Cost Aggregation
* Cost aggregate means adding together activity cost estimates for each component in WBS
Activity Estimates -> Work Package Estimates -> Control Account Estimates -> Project Estimates -> Contingency
Reserves -> Cost Baseline -> Mgmt Reserves -> Cost Budget
.2 Reserve Analysis
* Technique to determine realistic reserves
* Contingency Reserves - account of unplanned changes related to risk events that occur in the project i.e. realized risks.
These are part of cost performance baseline and total budget* Management Reserves - Unplanned changes to scope and cost. They are not included in cost performance baseline but
included in total budget. Project manager has to seek approval before accessing these reserves. These are not included as part
of earned value measurement calculations
.3 Expert Judgment
* Expert knowledge about project activities and associated costs can help to develop accurate budget
.4 Historical Relationships
* Based on historical relationships, project managers can use parametric estimating to develop mathematical models for
OUTPUTS
.1 Cost Performance Baseline
Input to ---> Plan Procurements;; Plan Quality;; Develop Project Management Plan
* Authorized time-phased budget at completion developed as a summation of approved budgets by time period
* Displayed in form of S-curve* In EVM, this is also referred as Performance Measurement Baseline
* Key elements - Work package costs, sub-project costs, total costs, contingency reserves and due dates
* Identifies expected cost of all the work, dates when costs apply
.2 Project Funding Requirements
Input to ---> Control Costs
* Periodic funding requirements derived from cost baseline
* Cost Baseline = ( Projected expenditures + Risk Response Cost ) + Contingency reserve (known unknowns)
* Project Funding Requirements/Cost Budget = Cost baseline + Management reserves (unknowns)
* Funding occurs in incremental amounts that are not continuous (appear as steps)
.3 Project Document Updates
* Risk registers, cost estimates, project schedule
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
60/150
7/28/2019 PMP Notes Rajesh Thallam v1.0 (1)
61/150
INPUTS
.1 Project Management Plan
.2 Project Funding Requirements
.3 Work Performance Information
.4 Organizational Process Assets
TOOLS & TECHNIQUES
.1 Earned Vaue Management
.2 Forecasts
.3 To-Complete Performance Index
.4 Performance Reviews
.5 Variance Analysis
.6 Project Management Software
OUTPUTS
.1 Work Performance Information
.2 Budget Forecasts
.3 Change Requests
.4 Organizational Process Asset Updates
.5 Project Management Plan Updates
.6 Project Document Updates
Control Costs
(Monitoring & Controlling)
KEY ASPECTS
* Below are the tasks performed in cost control process
* Influencing factors that affect costs
* Ensuring costs expenditures do not exceed authorized funding, by period and in total
* Monitoring work performance againsts funds expended i.e. Actual work (Earned value) vs cost
* Analyzing discrepancies
* Managing changes
* Preventing unapproved changes from being included in the reported costs or resource usage
* Communicating with stakeholders
* Actual cost performance is compared against cost performance baseline. By looking a comparison, project manager can see
how project is performing and when actions may be needed to bring actual and planned costs back in line.
* Project funding requirements are another input which project manager compares. They are funds that needs to have
available at different times throughout the projects in order to finance the work
* Control Costs is component of Perform Integrated Change Control process
* Control costs to assure that the project budget isn't exceeded (resulting in cost overruns)
* All budget changes should be agreed to and approved by the project sponsor where applicable (the criteria for approvals
INPUTS
.1 Project Management Plan
Input from ---> Develop Project M