+ All Categories
Home > Documents > pmp notes5 goods

pmp notes5 goods

Date post: 02-Jun-2018
Category:
Upload: bkumar1979
View: 215 times
Download: 0 times
Share this document with a friend

of 946

Transcript
  • 8/10/2019 pmp notes5 goods

    1/944

    PMP Project Management Professional

    Spearhead EduOnline Pvt Ltd.

    PROJECT MANAGEMENT

    &

    PMI

  • 8/10/2019 pmp notes5 goods

    2/944

    PMP Project Management Professional

    Spearhead EduOnline Pvt Ltd.

    1. Introduction to PMP

    2. Seven steps in the Journey towards PMP

    3. Introduction to Project

    List of Topics

  • 8/10/2019 pmp notes5 goods

    3/944

    PMP Project Management Professional

    INTRODUCTION TO PMP

    Spearhead EduOnline Pvt Ltd.

  • 8/10/2019 pmp notes5 goods

    4/944

    PMP Project Management Professional

    References

    A Guide to Project Management Body of Knowledge, Fifth Project Management Institute, Pennsylvania

    S. Chandramouli. PMP Certification Excel with Ease. PEARSO

    Publication., Second Edition.

    Jack R. Meredith, Samuel J. Mantel, Jr. Project managemenManagerial Approach. John Wiley & Sons, Fourth Edition, 2

    Spearhead EduOnline Pvt Ltd.

  • 8/10/2019 pmp notes5 goods

    5/944

    PMP Project Management Professional

    Purpose of Training

    Prepare you for the PMP Certification Examination Provide you with the knowledge needed to successfully com

    exam and also to manage the Projects successfully

    Provide practical hints for answering questions correctly

    Spearhead EduOnline Pvt Ltd.

  • 8/10/2019 pmp notes5 goods

    6/944

    PMP Project Management Professional

    PMI History

    Started in 1969 with few Project Managers First Edition of A Guide to PMBOK in 1996

    Second Edition of A Guide to PMBOK in 2000

    Third Edition of A Guide to PMBOK in 2004

    Fourth Edition of A Guide to PMBOK in 2009 Fifth Edition of A Guide to PMBOK in 2012

    Spearhead EduOnline Pvt Ltd.

  • 8/10/2019 pmp notes5 goods

    7/944

    PMP Project Management Professional

    PMI Activities

    REP Program Training orgs/Courses

    Online Communities

    Professional Standards (PMBOK, OPM3,PMCDF)

    Educational Seminars/ Conferences

    Professional Certifications

    Spearhead EduOnline Pvt Ltd.

  • 8/10/2019 pmp notes5 goods

    8/944

    PMP Project Management Professional

    PMP Certification

    PMI provides certification as a Project Management Profess

    PMP means: sufficient project experience, agreed to follow

    ethics, passed PMP exam

    Number of PMPs community is growing very fast.

    Other groups, like the Gartner Group and the Singapore Com

    Society, have their own IT PM Certification programs

    Spearhead EduOnline Pvt Ltd.

  • 8/10/2019 pmp notes5 goods

    9/944

    PMP Project Management Professional

    What Certifications PMI offers?

    Program Management Professional (PgMP)

    Agile Certified Professional (ACP)

    Project Management Professional ( PMP)

    PMI Risk management professional (PMI-RMP) PMI Scheduling Professional ( PMI-SP)

    Certified associate in project Management (CAPM)

    Spearhead EduOnline Pvt Ltd.

  • 8/10/2019 pmp notes5 goods

    10/944

    PMP Project Management Professional

    Advantage PMP

    Demonstrates your seriousness in the profession. Certifies that you have FORMAL knowledge of the methodo

    rather than just relying on hard work and organization skills

    Distinguishes you from other PM candidates.

    Screening tool for companies looking for PM candidates Average PMPs gets paid higher than non-PMPs

    Spearhead EduOnline Pvt Ltd.

    j f i l

  • 8/10/2019 pmp notes5 goods

    11/944

    PMP Project Management Professional

    The PMP Certification Says

    I am:o Able

    o Capable

    o Trained

    o Interested

    o Up-to-date

    The PMP offers external validation beyond experience

    Spearhead EduOnline Pvt Ltd.

    PMP P j M P f i l

  • 8/10/2019 pmp notes5 goods

    12/944

    PMP Project Management Professional

    SEVEN STEPS IN THE JOUR

    TOWARDS PMP

    Spearhead EduOnline Pvt Ltd.

    PMP P j t M t P f i l

  • 8/10/2019 pmp notes5 goods

    13/944

    PMP Project Management Professional

    Spearhead EduOnline Pvt Ltd.

    PMP

    Become a PMI member. Cost 129 US $

    Time span : On line1

    Mandatory training/PM education fo

    35 hours of credits (chapter, university, institute or REP2

    Submit PMP Examination ApplicationCost : 405 US $ Time : Two week

    3

    Receipt of PMP examination eligibility lette

    from PMI (Time : two weeks4

    Prepare for the exam

    Time : 1 to 3 month5

    Contact local Prometric center tofix up examination dat6

    Execute, Succeed & Celebrat

    Time : 4 Hour7

    PMP P j t M t P f i l

  • 8/10/2019 pmp notes5 goods

    14/944

    PMP Project Management Professional

    Step 1-PMI Membership and Benef

    Reconfirm the need to become a PMP If yes, become a PMI member by simple online enrollment

    www.pmi.org

    PMI membership is not mandatory for the PMP certificatio

    recommended. You get monthly magazine - PM Network, a

    research journal and monthly news letter (for a year) + disc

    PMI books

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    15/944

    PMP Project Management Professional

    Step 1-PMI Membership and Benefits

    Membership is annual (129US $ for the initial membership

    $ for renewals)

    Keep the e-receipt for reimbursement purpose

    Also become the member of your nearest local chapter forPMP certification. Add local chapter subscription to the init

    membership enrollment

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    16/944

    PMP Project Management Professional

    Step 2-Mandatory Training/PM Educa

    Mandatory to have 35 hours of formal PMBOK education co

    process groups

    You can attend classroom training or complete 35 hours tro

    learning

    While submitting the application kit for PMP exam, the deta

    training need to be furnished

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    17/944

    PMP Project Management Professional

    Spearhead EduOnline Pvt Ltd.

    Program Management Professional (PgMPSM) Examination Fees

    Examination and Renewal Fees

    Member Nonm

    Computer-based Testing $1,500.00(US)/ 1,250.00 $1,800.00(U

    Paper-based Training $1,200.00(US)/ 1,000.00 $1,500.00(U

    Re-examination Computer-based $500.00(US)/ 420.00 $600.00(U

    Re-examination Paper-based $400.00(US)/ 335.00 $500.00(U

    Multi-rater assessment Retake $400.00(US)/ 335.00 $500.00(U

    Project Management Professional (PMP) Examination Fees

    Member Nonm

    Computer-based Testing $405.00(US)/ 340.00 $555.00(U

    Paper-based Training $250.00(US)/ 205.00 $400.00(U

    Re-examination Computer-based $275.00(US)/ 230.00 $375.00(U

    Re-examination Paper-based $150.00(US)/ 125.00 $300.00(U

    Certified Associate in Project Management (CAPM) Examination FeesMember Nonm

    Initial Certification Fee $225.00(US)/ 185.00 $300.00(U

    Re-examination Fee $150.00(US)/ 125.00 $200.00(U

    Renewal Fees

    Member Nonm

    Certification Renewal Fee $60.00(US) $150.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    18/944

    PMP Project Management Professional

    Step 3-Submit PMP Examination Appli

    Fill up online application for examination registration. Before filli

    application, keep the following details:

    o A detailed split of for the 4500 hours of PM experience project w

    the project, reporting line, brief description and hours split up a

    initiation/planning/execution/monitoring & controlling and clos

    o PMI membership ID

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    19/944

    PMP Project Management Professional

    Application fee is 405 US$ for PMI Member

    Keep the e-receipt for reimbursement purpose

    You can save the information in-between and continue late

    After submission you will get acknowledgement through e

    Spearhead EduOnline Pvt Ltd.

    Step 3-Submit PMP Examination Applic

    Contd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    20/944

    PMP Project Management Professional

    Step 4 Receipt of PMP Examination Elig

    Letter from PMI After submitting the application within a week you get the

    letter through e-mail

    This letter is valid for 12 months to appear for the examina

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    21/944

    PMP Project Management Professional

    Step-5 Prepare for the Exam

    Key step: requires substantial TIME investments from you (Hours)

    Prepare systematically through various references

    Main focus should be on PMBOK with supporting info from

    references

    Map with real life experiences while reading. The questions

    direct. Most questions focus on ability of Project Manager t

    decision in a situation

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    22/944

    PMP Project Management Professional

    How to Prepare for the Exam

    Read the PMBOK (at least thrice) and pay special attention to th

    Buy some PM reference and study books and/or materials, e.g.,

    o PMP Certification Excel with ease by S. Chandramouli

    Take as many practice exams as you can get your hands on (som

    through the internet)

    Take a refresher class

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    23/944

    j g

    Step-6 Contact local Prometric center and f

    examination date When confident for examination, contact the nearest Prometric c

    up appointment for examination (10-15 days)

    For details about the location and other details in India, call: 91-1

    Examination centers are available at the following locations

    o AHMEDABAD, ALLAHABAD, BANGALORE

    o CALCUTTA, CHENNAI, HYDERABAD

    o MUMBAI, NEW DELHI, TRIVANDRUM

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    24/944

    j g

    Step-7 Execute, Succeed and Celebr

    Examination is for four hours, to answer 200 questions

    Out of 200 questions, 25 questions will be for pretest and w

    included in your score

    To pass you must get 106 correct out of 175 score able que

    No negative marks

    The result will be announced soon after the exam (online)

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    25/944

    j g

    Execute, Succeed and Celebrate Co

    You can go back to questions that are giving you trouble so skip o(mark them for Review Later) and answer the ones you know t

    first. Sometimes a subsequent question or answer can jog your m

    ways to review later:

    o Take your best guess and mark for later review (best) or

    o Leave blank and call up unanswered questions later.o You get your score immediately after completing the test.

    o Certification documentation will be sent to you within 3 to 4 weeks

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    26/944

    Tips/Suggestions

    Do all the sample exams that you can find! Shoot to score 90% o

    them.

    STUDY! Allow 40 to 80 hours to read the PMBOK and other stud

    Hint:

    o Form a self-study group and take advantage of the groups synergy t

    tests together.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    27/944

    Tips/Suggestions Contd.

    Remember it is a pass-fail exam. You have to get the passand no one but you ever knows your score! So dont worry

    knowing everything about everything!

    RELAX! Taking the test is stressful! But you have 240 minu

    answer 200 questions. (And an additional 15 minutes at bedemonstration of the testing software is also allocated.) M

    finished the test in two and a half hours so you have plenty

    Spearhead EduOnline Pvt Ltd.

  • 8/10/2019 pmp notes5 goods

    28/944

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    29/944

    INTRODUCTION TO PROJE

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    30/944

    What is a Project

    Spearhead EduOnline Pvt Ltd.

    A temporary endeavor undertaken to create a unique product

    Temporary Has a definite beginning and end, not an

    on-going effort.

    Ceases when objectives have been attained.

    Team disbanded upon completion.

    Unique The product or service is different in

    some way from other products or services.

    Product characteristics are progressively

    elaborated.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    31/944

    Progressive Elaboration

    Progressive elaborationo Developing in steps; and

    o Continuous improvement

    Project scope will be broadly described early in the project an

    explicit and detailed as the project team develops a better andcomplete understanding of the objectives and deliverables.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    32/944

    Project Vs.. Operation

    Spearhead EduOnline Pvt Ltd.

    Oper

    Ong

    Rep

    People Performs

    Limited Resources

    Planned, Executed and

    Controlled

    Common Characteristics

    Project

    Temporary

    Unique

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    33/944

    Projects Vs.. Operational Work

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    34/944

    Projects and Strategic Planning

    Projects are a means of organizing activities that cannot be ad

    within the organizations normal operational limits

    Projects are often utilized as a means of achieving an organiza

    strategic plan, whether the project team is employed by the o

    or is a contracted service provider

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    35/944

    Projects and Strategic PlanningCon

    Strategic considerations

    o A market demand

    o An organization need

    o A customer request

    o A technological advanceo A legal requirement

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    36/944

    Project Management

    Project Management is the application of knowledge, skills, Tools an

    to project activities in order to meet project requirements

    Project Management is accomplished through the application and in

    PM processes of initiation, planning, executing, monitoring and cont

    closing

    The project manager is the person responsible for accomplishing the

    objectives

    Source: A Guide to Project Management Body of Knowledge, fifth Edition, Project Management Institute, Pennsylvania, USA.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    37/944

    Managing a Project

    Includes:o Identifying requirements

    o Establishing clear and achievable objectives.

    o Balancing the competing demands for quality, scope, time an

    o Adapting the specifications, plans, and approach to the differ

    and expectations of the various stakeholders.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    38/944

    Understanding Project Management Envi

    Cultural and social environment. The team needs to understandproject affects people and how people affect the project.

    International and political environment. Some team members

    be familiar with applicable international, national, regional, and

    customs, as well as the political climate that could affect the pro

    Physical environment. If the project will affect its physical surro

    team members should be knowledgeable about the local ecolog

    geography that could affect the project or be affected by the pro

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    39/944

    Enterprise Environmental Factors

    It refers both internal and External environmental factors tor influence Project Success

    These factors may come from any or all of the enterprise ithe Project

    It may have Positive or negative influence on the outcome

    Project They are considered as input to most of the Planning proc

    Example : Infrastructure , Existing human resources , Organiz, structure, Process, Political Climate, Commercial databases.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    40/944

    General Management Knowledge and Sk Financial management and accounting

    Purchasing and procurement Sales and marketing

    Contracts and commercial law

    Manufacturing and distribution

    Logistics and supply chain

    Strategic planning, tactical planning, and operational planning

    Organizational structures, organizational behavior, personnel administrat

    compensation, benefits, and career paths

    Health and safety practices

    Information technology.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    I l Skill (S f kill )

  • 8/10/2019 pmp notes5 goods

    41/944

    Interpersonal Skills (Soft skills)

    Effective communication. The exchange of information

    Influencing the organization. The ability to get things done

    Leadership. Developing a vision and strategy, and motivating people to

    vision and strategy

    Motivation. Energizing people to achieve high levels of performance an

    barriers to change

    Negotiation and conflict management. Conferring with others to come them or to reach an agreement

    Problem solving. The combination of problem definition, alternatives id

    analysis, and decision-making.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    42/944

    Advantages of Using Formal Project Mana

    Better control of financial, physical, and human resources Improved customer relations

    Shorter development times

    Lower costs

    Higher quality and increased reliability

    Higher profit margins Improved productivity

    Better internal coordination

    Higher worker morale

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    43/944

    Benefits of Project Management for t

    Organization

    Identifies problem areas

    Clarifies project goals and project scope

    Quantifies project risk

    Constant monitoring and corrections

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    44/944

    Benefits of PM for the Individual

    Provides future source of company leaders

    Creates high visibility of project results

    Enhances both professional and personal

    growth opportunities

    Builds ones reputation and network Develops portable skills and experience

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    45/944

    A good Project Manager

    Spends time upfront understanding project and getting commitm

    stakeholders

    Communicates with all stakeholders openly and honestly

    Explains and gets agreement from people on what they need to d

    Listens

    Understand scope and objectives and keeps them in mind when decisions

    Builds the team and makes the most of members skills

    Keeps Project Team involved and motivated

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    46/944

    A good Project ManagerContd. Plans thoroughly keeps workload, resources and timescales in balance

    Is accountable for all aspects of the project Makes decisions based on the information available

    Puts the project before any other allegiances

    Is honest with themselves and others

    Uses common sense

    Is prepared to take calculated risks

    Is a good negotiator

    Anticipates, prioritizes and addresses potential and real problems as soo

    become apparent

    Spearhead EduOnline Pvt Ltd.

  • 8/10/2019 pmp notes5 goods

    47/944

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    48/944

    Program

    A Program is a group of Projects managed in a coordinated w

    benefits not available from managing them individually. P

    includes some elements of ongoing operations.

    Source: A Guide to Project Management Body of Knowledge, Fifth Edition, Project Management Institut

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    49/944

    Project Portfolio Management

    A Portfolio refers to a collection of Projects or Programs and other

    grouped together to facilitate effective management of that w

    strategic business Objectives.

    Source: A Guide to Project Management Body of Knowledge, Fifth Edition, Proje

    Institute, Pennsylvania, USA.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Organizational Project

  • 8/10/2019 pmp notes5 goods

    50/944

    Spearhead EduOnline Pvt Ltd.

    Organizational Project

    ManagementPROJECTS PROGRAMS PORTFO

    Scope

    Projects have defined objectives.

    Scope is progressively elaborated

    throughout the project lifecycle.

    Programs have a larger scope

    and provide more significant

    benefits.

    Portfolios h

    organizational

    changes with th

    objectives

    organizat

    Change

    Project managers expect change

    and implement processes to keep

    change managed and controlled .

    Project managers expect change

    from both inside and outside

    the program and are prepared

    to manage it.

    Portfolio ma

    continuously

    changes in the

    internal and

    environm

    Planning

    Project managers progressively

    elaborate high-level information

    into detailed plans throughout the

    project life cycle.

    Program managers develop the

    overall program plan and create

    high-level plans to guide

    detailed planning at the

    component level.

    Portfolio mana

    and maintain

    processe

    communication

    the aggregate

    PMP Project Management Professional

    Organizational Project

  • 8/10/2019 pmp notes5 goods

    51/944

    Spearhead EduOnline Pvt Ltd.

    PROJECTS PROGRAMS P

    Management

    Project managers manage the project

    team to meet the project objectives.

    Program managers manage the

    program staff and the projectmanagers; they provide vision and

    overall leadership.

    Portfolio m

    coordinatestaff, or pro

    that m

    responsib

    Success

    Success is measured by product and

    project quality, timeliness, budget

    compliance and degree of customer

    satisfaction.

    Success is measured by degree to

    which the program satisfies the

    needs and benefits for which it was

    undertaken.

    Success is

    the agg

    perfor

    realizat

    Monitoring

    Project managers monitor and control

    the work of producing the products,

    services or results that the project was

    undertaken to produce.

    Program managers monitor the

    progress of the program component

    to ensure the overall goals,

    schedules, budget and benefits of the

    program will be met .

    Portfoli

    strategic c

    resource a

    results an

    Organizational Project

    Management-Contd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    52/944

    Project Management Office (PMO

    A Project Management Office is an organizational unit to cecoordinate the management of projects under its domain

    PMOs can operate on a continuum, from providing project

    management support functions in the form of training, soft

    standardized policies and procedures, to actual direct mana

    responsibility for achieving the project objectives

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    53/944

    Standard Vs.. Regulation

    A standard is a document established by consensus and ap

    recognized body that provides, for common and repeated u

    guidelines or characteristics for activities or their results, ai

    achievement of the optimum degree of order in a given con

    A regulation is a government-imposed requirement, which

    product, process or service characteristics,

    Spearhead EduOnline Pvt Ltd.

  • 8/10/2019 pmp notes5 goods

    54/944

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    55/944

    Spearhead EduOnline Pvt Ltd.

    END OF THE SESSION

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    56/944

    Spearhead EduOnline Pvt Ltd.

    PROJECT LIFE CYCLE AND

    ORGANIZATION CONTEXT

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    57/944

    List of Topics

    1. Project Lifecycle

    2. Models of Project Lifecycle

    3. What Helps Projects Succeed?

    4. Organizational Influences

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    58/944

    PROJECT LIFECYCLE

    Spearhead EduOnline Pvt Ltd

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    59/944

    Projects cannot be run in Isolation

    Projects must operate in a broad organizational environme

    Project managers need to take a holistic or systems view of

    and understand how it is situated within the larger organiza

    Senior managers must make sure projects continue to sup

    business needs

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    60/944

    Project Life Cycle

    Collection of project phases

    Serves to define the beginning and end of a project

    Helps to define the processes for a specific project product

    Top management is responsible for the periodic review of

    This should be accomplished, at a minimum, at the compl

    each life-cycle phase.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    61/944

    Project Life CycleContd.

    Defines

    o What technical work to do in each phase

    o When the deliverables are to be generated in each phase and

    will be reviewed, verified and validated

    o Who is involved in each phase

    o How to control and approve each phase

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    62/944

    Project Lifecycle Characteristics

    Projects vary in Size and Complexity. All Projects can be mapped to t

    Life Cycle Structure

    1. Starting the Project

    2. Organizing and preparing

    3. Carrying out the Project work , and

    4. Closing the Project

    This generic Life Cycle structure is often referred to when communicupper management or other entities less familiar with the details o

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    63/944

    Project Lifecycle Characteristics-Con

    Cost and staffing levels Risk and uncertainty

    Stakeholders ability to influence

    Cost of changes

    Probability of completing the project

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    64/944

    Why Project Phases?

    Spearhead EduOnline Pvt Ltd.

    To provide appropriate lin

    ongoing operations of per

    organizations for Resource

    requirements, Funds requ

    and common functionaliti

    Purchase, Stores, Adminis

    etc.

    Projects are

    Unique

    Phasingfacilitate

    better

    Management &

    Control

    Projects

    involves

    Uncertainty

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    65/944

    Need for Phases in Project Life Cyc

    Each phase gives a tangible and verifiable work product

    Projects are divided into phases for better management an

    At the end of each phase, stakeholders can

    o Decide if project should continue

    o Detect and correct errors cost effectively

    These points are Phase Exits, Stage Gates or Kill Points

    Spearhead EduOnline Pvt Ltd.

  • 8/10/2019 pmp notes5 goods

    66/944

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    67/944

    Phase to Phase relationship

    There are 3 different types of Phase to Phase relationship

    1. Sequential Relationship

    2. Overlapping Relationship (may increase Risk and result in Rewo

    3. An iterative Relationship (useful in largely undefined , uncertain

    changing environments such as Research)For multiphase Projects more than one relationship can occur during

    Life Cycle

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    68/944

    MODELS OF PROJECT

    LIFECYCLE

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    69/944

    Waterfall Model

    Spearhead EduOnline Pvt Ltd.

    Requirements

    Design

    Coding

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    70/944

    Iterative Model

    Spearhead EduOnline Pvt Ltd.

    Requirements

    Design

    Coding

    Testing

    Requirements

    Design

    Coding

    Testing

    Requirements

    Design

    C

  • 8/10/2019 pmp notes5 goods

    71/944

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    72/944

    WHAT HELPS PROJECT

    SUCCEED?

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Wh t h l P j t S d?

  • 8/10/2019 pmp notes5 goods

    73/944

    What helps Projects Succeed?

    According to the Standish Groups report CHAOS 2001: A Recipe for

    following items help IT projects succeed, in order of importance:

    Spearhead EduOnline Pvt Ltd.

    Executive support

    User involvement

    Experience project manager

    Clear business objectives

    Minimized scope

    Standard software infrastructure

    Firm basic requiremen

    Formal methodology

    Reliable estimates

    PMP Project Management Professional

    Predictive and Adaptive

  • 8/10/2019 pmp notes5 goods

    74/944

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    P j t St k h ld

  • 8/10/2019 pmp notes5 goods

    75/944

    Project Stakeholders

    Project stakeholders are individuals and organizations who areinvolved in the project, or whose interests may be positively o

    affected as a result of project execution or successful project c

    Source: A Guide to Project Management Body of Knowledge, Fifth Edition, Projec

    Institute, Pennsylvania, USA.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    P j t St k h ld C td

  • 8/10/2019 pmp notes5 goods

    76/944

    Project StakeholdersContd.

    Project Manager

    Customer: Individual or Org that will use the project's product Performing organization

    Project team members

    Sponsor

    Shareholders

    Govt./statutory agencies

    Suppliers and contractors

    Media, general public and society at large

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Identif ing Stakeholders

  • 8/10/2019 pmp notes5 goods

    77/944

    Identifying Stakeholders

    It is a Continuous Process and difficult

    Understanding their degree of influence on the Project is c

    An important part of a Project managers responsibility is to

    stakeholder expectations

    Stakeholders are often have very different and Conflicting O

    Project manager occupies the center of interactions betwestakeholders and the Project itself

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Stakeholders

  • 8/10/2019 pmp notes5 goods

    78/944

    Project Stakeholders

    Managing stakeholders expectations is very difficult because sta

    often have very different objectives that may come into conflictFor example, a customer wants to set up a process industry at a clo

    of a city. Even though they satisfy the pollution control norms some

    organization may not be willing to accept the proposal. Public may

    opinion. It is a challenge for the project manager to integrate the ex

    all the stakeholders to a common platform.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Recognize the Importance of Project Stak

  • 8/10/2019 pmp notes5 goods

    79/944

    Recognize the Importance of Project Stak

    Recall that project stakeholders are the people involved in o

    by project activities

    Project managers must take time to identify, understand, a

    relationships with all project stakeholders

    Senior executives are very important stakeholders

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Skills Project Managers Need

  • 8/10/2019 pmp notes5 goods

    80/944

    Skills Project Managers Need

    Communication

    Organizational Budgeting

    Problem solving

    Negotiation and influencing

    Leading Team building

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    81/944

    ORGANIZATIONAL INFLUE

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Organizational Influences

  • 8/10/2019 pmp notes5 goods

    82/944

    Organizational Influences

    On micro level, virtually all organizations are either marketing-

    engineering, or manufacturing-driven. But on a macro level, oare either project- or non-project-driven.

    Not all companies need project management, Ex slow evolving

    (cement, steel)

    Some companies can do with informal project management

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Organizational Influences-Contd

  • 8/10/2019 pmp notes5 goods

    83/944

    Organizational Influences-Contd.

    Organizations can be defined as groups of people who must c

    their activities to meet Organizational objectives.

    Organizational structures are dictated by such factors as tech

    its rate of change, complexity, resource availability, products

    services, completion and decision making requirements.

    There is no such thing as a good and bad organizational struare only appropriate or inappropriate ones.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Forms of Organization

  • 8/10/2019 pmp notes5 goods

    84/944

    Forms of Organization

    Functional

    Projectized

    Matrix

    o Weak

    o Balance

    o Strong

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Functional, Project, & Matrix Organizat

  • 8/10/2019 pmp notes5 goods

    85/944

    , j , g

    Structures

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    PM Framework

  • 8/10/2019 pmp notes5 goods

    86/944

    PM FrameworkWeak Matrix Organization

    Spearhead EduOnline Pvt Ltd.

  • 8/10/2019 pmp notes5 goods

    87/944

    PMP Project Management Professional

    PM Framework - Contd.

  • 8/10/2019 pmp notes5 goods

    88/944

    PM Framework Contd.

    Spearhead EduOnline Pvt Ltd.

    Balanced Matrix Organization

    PMP Project Management Professional

    Functional Organization Potential Adva

  • 8/10/2019 pmp notes5 goods

    89/944

    Functional Organization Potential Adva

    Easier budgeting and cost control are possible

    Clear reporting relationships and good control over person

    Communication channel are vertical and well established

    Highly specialized & drive for technical excellence

    Specialist can be grouped to share knowledge and respons

    Clear career path

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Functional Organization Potential Iss

  • 8/10/2019 pmp notes5 goods

    90/944

    Functional Organization Potential Iss

    No one individual is directly responsible for the total proje

    formal authority; committee solutions)

    Does not provide the project-oriented emphasis necessary

    accomplish project tasks

    Response to customer need is slow

    Hierarchical decision and communication processes Decisions normally favor the strongest functional group

    Multiple projects compete for limited resources and priori

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Matrix Organization Potential Advant

  • 8/10/2019 pmp notes5 goods

    91/944

    g

    The project manager maintains maximum project control (through t

    managers) over resources Policies and procedures can be set up independently for each projec

    PM has the authority to commit company resources

    Rapid responses are possible to changes, conflict resolution, and pro

    technology or schedule)

    A functional organizations exists primarily as support for the project Each person has a home after project completion. People are susc

    motivation and end - item identification

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Matrix Organization

    P t ti l Ad t C td

  • 8/10/2019 pmp notes5 goods

    92/944

    Potential AdvantagesContd. As key people can be shared, the program cost is minimized

    A strong technical base can be developed, and much more time cdevoted to complex problem solving

    Knowledge is available to all projects on an equal basis

    Conflicts are minimized and those requiring hierarchical referralseasily resolved

    There is a better balance among time cost, and performance

    Authority and responsibility are shared Stress is distributed among the team (and the functional manage

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Matrix Organization Potential Issue

  • 8/10/2019 pmp notes5 goods

    93/944

    g

    Multidimensional information and work flow

    Dual reporting leading to difficulty in monitoring and contr

    Potential for continuous conflict and conflict resolution

    Each project organization operated independently. Care muthat duplication of efforts does not occur

    Employees and managers are more susceptible to role ambin traditional form

    More effort and time are needed initially to define policy aprocedure, compared to traditional form

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project-Based Organization Potential Adv

  • 8/10/2019 pmp notes5 goods

    94/944

    j g

    Provides complete line authority over project

    A focal point is developed for out of company customer rel

    Strong communication channel

    Flexibility in determining schedule, cost and performance

    Interface management becomes easier as unit size is reduc

    Personnel demonstrate loyalty to the project

    Participants work directly for the PM. Unprofitable product

    easily identified and can be eliminated.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project-Based Organization Potential I

  • 8/10/2019 pmp notes5 goods

    95/944

    j g

    Inefficient usage of resources

    A tendency to retain personnel on a project long after they

    Technology suffers because, without strong functional grouof future to improve companys capabilities for new prograhampered

    Control of functional (i.e. organizational) specialties requirecoordination

    Lack of career continuity and opportunities for project pers

    Spearhead EduOnline Pvt Ltd.

  • 8/10/2019 pmp notes5 goods

    96/944

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    97/944

    Spearhead EduOnline Pvt Ltd.

    END OF THE SESSION

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    98/944

    Spearhead EduOnline Pvt Ltd.

    PM PROCESSES AND

    INTEGRATION MANAGEMEN

    PMP Project Management Professional

    List of Topics

  • 8/10/2019 pmp notes5 goods

    99/944

    Project Management Process

    Process Group Interactions

    Project Integration Management (Knowledge Area)

    Introduction to other Knowledge Areas

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    100/944

    PROJECT MANAGEMEN

    PROCESS

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Major Sections

  • 8/10/2019 pmp notes5 goods

    101/944

    1. Project processes2. Process groups

    3. Process interactions

    4. Customizing process interactions

    5. Mapping of project management processes

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Management Processes

  • 8/10/2019 pmp notes5 goods

    102/944

    Highlights

    Number of processes 47

    Number of Process Groups 5

    Number of knowledge areas 10

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Processes

  • 8/10/2019 pmp notes5 goods

    103/944

    Project are composed of processes

    A process is a series of actions bringing about a result.Project process generally falls into one of two major categories

    Project Management Process

    Describe, Organize and complete the work of the project

    Applicable to most of the projects, most of the time

    Product oriented processes

    Specify and creates the projects product

    Generally referred as Project Life Cycle (PLC)

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Processes

  • 8/10/2019 pmp notes5 goods

    104/944

    Project Management Process and Product oriented Process ov

    interact throughout the Life cycle of the Project

    Product Oriented Process should not be ignored by the Projec

    PMI standardize the Project Management Process

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Management Processes

    Process is a set of interrelated actions and activities performed

    ifi d d t i lt

  • 8/10/2019 pmp notes5 goods

    105/944

    pre-specified product, service or result.

    Each process is characterized by its inputs, Tools and Techniques

    applied and the resulting outputs.

    For a project to be successful, the project team must::

    o Select appropriate processes required to meet the project ob

    o Use a defined approach that can be adopted to meet require

    o

    Comply with requirements to meet stakeholder needs and exand

    o Balance the competing demands of scope, time, cost, quality

    and risk to produce the specified product, service or result.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    PM Process Groups

    Project Management Processes are organized into five process groups

    I iti ti P D fi d th i j t j t h

  • 8/10/2019 pmp notes5 goods

    106/944

    Initiating Processes Defines and authorizes a project or a project phase

    Planning Processes Establish the scope, Refine the objectives, define the

    required to attain the objectives that the project was undertaken to achieveExecuting Processes Complete the work defined in the project manageme

    satisfy the project specifications

    Monitoring and Controlling Processes Track, review and regulate the prog

    performance of the project; Regularly monitor and measure project progre

    changes and initiate changes when required

    Closing Processes Formalizes acceptance of the project or a phase and br

    end to the project

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Process Groups

  • 8/10/2019 pmp notes5 goods

    107/944

    Spearhead EduOnline Pvt Ltd.

    ProcessGroups

    Initiation

    Planning

    ExecutingMonitoring

    andControlling

    Closing

    PMP Project Management Professional

    Knowledge Areas

    Scope

  • 8/10/2019 pmp notes5 goods

    108/944

    Spearhead EduOnline Pvt Ltd.

    IntegrationManagement(6)

    pManagement (6)

    TimeManagement (7)

    Man

    Qual

    Managem

    RiskManagement (6)

    Procurement

    Management (4)

    CommunicationManagement(3)

    StakeholderManagement (4)

    HRManagement(4)

    PMP Project Management Professional

    Project Management Process

    Distribution

  • 8/10/2019 pmp notes5 goods

    109/944

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    110/944

    PROCESS GROUP INTERACT

    Spearhead EduOnline Pvt Ltd.

  • 8/10/2019 pmp notes5 goods

    111/944

    PMP Project Management Professional

    Common Project Management Process Intera

    Contd

  • 8/10/2019 pmp notes5 goods

    112/944

    Contd.

    The application of Project Management Process is both iteratIntegrative

    The integrative nature of Project Management requires the M

    and Control Process Groups to interact with other Process gro

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Overlap of Process Groups

    ExecutingPlanningInitiating Monitoring

  • 8/10/2019 pmp notes5 goods

    113/944

    Spearhead EduOnline Pvt Ltd.

    Source: A Guide to Project Management Body of Knowledge, Fifth Edition, Project Management Institu

    Pennsylvania, USA.

    Executing

    Process

    Group

    Planning

    Process

    Group

    Initiating

    Process

    Group

    TimePhase start

    Monitoring

    And Control

    Process Group

    PMP Project Management Professional

    Overlap of Process Groups

    in Phases

  • 8/10/2019 pmp notes5 goods

    114/944

    Spearhead EduOnline Pvt Ltd.

    Executing Process Executing Process Executin

    Planning

    Process

    Planning

    ProcessPlanning

    Process

    Controlling

    Process

    Initiating

    Process

    Level

    of

    Activity

    Phase Start Time

    PMP Project Management Professional

    PM Processes Interactions

  • 8/10/2019 pmp notes5 goods

    115/944

    Spearhead EduOnline Pvt Ltd.

    Initiating

    Process

    Closing

    Process

    Planning Processes

    Executing Processes

    Monitoring &

    Controlling Processes

    Enter Phase/

    Start Project

    PMP Project Management Professional

    Project Initiating Process

  • 8/10/2019 pmp notes5 goods

    116/944

    Project Initiating Process is about

    Recognizing that a project or phase should begin and comfinancial resources to do so

    Project Phase Initiating Process (Project Phase) involves

    Committing the organization to begin the next phase of th

    Initiating processes may be formal or informal

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Initiating Process Group

  • 8/10/2019 pmp notes5 goods

    117/944

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Planning Process

    Project Planning process involves processes performed to establish the tota

  • 8/10/2019 pmp notes5 goods

    118/944

    Project Planning process involves processes performed to establish the tota

    effort, define and refine the objectives, and develop the course of action re

    those objectives. This process is of major importance because the project involves doing som

    not been done before. It creates project management plan which is a key d

    throughout the life of the project

    As more and more information is gathered on the project, there is a need t

    planning processes and this iterative detailing of the project management p

    rolling wave planning. Highest number of Project Management Processes are with planning.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Planning Process -Contd.

  • 8/10/2019 pmp notes5 goods

    119/944

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Execution Process

    P j E i i l h f d

  • 8/10/2019 pmp notes5 goods

    120/944

    Project Execution process involves those processes performed to co

    work defined in the project management plan to satisfy the specific

    Involves coordinating people and resources as well as integrating an

    the activities of the project in accordance with the project managem

    During project execution, results may require planning updates and

    This includes variance that may affect the project management pla

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Execution Process -Contd.Project Human R

    manageme

    Project Stakeholder management

    13.3

    Manage Stakeholder

    9.2

    Acquire Project T

    Project Hum

    Resource manag

  • 8/10/2019 pmp notes5 goods

    121/944

    Spearhead EduOnline Pvt Ltd.

    The dashed circular arrow indicates that the process is part of the project

    management knowledge area. This knowledge area coordinates and unifies the

    other knowledge area.

    Project Integration management

    4.3

    Direct and Manage

    Project work

    Project Procurement

    management

    12.2

    Conduct Procurements

    Project Quality management

    8.2

    Perform Quality

    Assurance

    g

    EngagementAcquire Project T

    9.3

    Develop Project

    9.4

    Manage Project T

    Project Commu

    managem

    10.2Manage Commun

    PMP Project Management Professional

    Project Monitoring and Control ProcProject Monitoring and control process involves those processes required to track, re

  • 8/10/2019 pmp notes5 goods

    122/944

    Project Monitoring and control process involves those processes required to track, re

    regulate the progress and performance of the project, identify the areas where chan

    are required and make those changes.

    The project performance is observed and measured regularly and consistently to ide

    and take corrective actions

    The Monitoring and controlling process group includes:

    Controlling changes and recommending preventive action in anticipation of poss

    Monitoring the ongoing project activities against the project management plan

    performance baseline, and Influencing the factors that could circumvent integrated change control so only

    changes are implemented.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Monitoring and Control Process-Contd.

    Project Stakeholder

    management

    13.3

    Project Scope

    Management

    Project Cost Management

  • 8/10/2019 pmp notes5 goods

    123/944

    Spearhead EduOnline Pvt Ltd.

    Project Integration

    management

    4.4. Monitor and

    control Project

    Project Stakeholder

    management

    13.4 Control

    Stakeholder

    Management

    Project Procurement

    management12.3 Control

    Procurement

    Manage Stakeholder

    Engagement5.5 Validate Scope

    5.5 Control Scope

    Project Communicatio

    management

    10.35

    Control Communications

    Project Risk

    management

    11.6 Control Risks

    10.2

    Manage Communications

    Project Quality managem

    8.3 Control Quality

    4.5 Perform

    Integrated Change

    control

    The dashed circular arrow indicates that the process is part of the project integration management knowledge are

    coordinates and unifies the processes from other knowledge area.

    PMP Project Management Professional

    Project Closing ProcessProject Closing process involves those processes required to finalize all activities

    project management groups to formally complete the project, phase or contract

    Thi ifi h h d fi d l d i hi ll

  • 8/10/2019 pmp notes5 goods

    124/944

    This process group verifies that the defined processes are completed within all t

    groups to close the project or a phase and formally establishes that the project o

    complete.

    At project or phase closure, the following may occur

    Obtain acceptance by the customer or sponsor

    Conduct postproject or phase-end review

    Record impacts of tailoring to any process

    Document lessons learned Apply appropriate updates to organizational process assets

    Archive all relevant project documents

    Close out procurements.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Closing Process -Contd.

  • 8/10/2019 pmp notes5 goods

    125/944

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    126/944

    PROJECT INTEGRATIONMANAGEMENT (KNOWLED

    AREA)

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    PROJECT INTEGRATION MANAGE

  • 8/10/2019 pmp notes5 goods

    127/944

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Integration Management (PI

  • 8/10/2019 pmp notes5 goods

    128/944

    Is crucial to project completion

    Includes processes and activities that are PRIMARILY INTEG

    o Identifies, defines, combines, unifies, and coordinates the va

    processes and project management activities within the Pro

    Management Process Groups

    Use of decision making to meet/exceed stakeholder expec Facilitates coordination of the project and the operations

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Integration Management

  • 8/10/2019 pmp notes5 goods

    129/944

    Spearhead EduOnline Pvt Ltd.

    Project Integration Management describes t

    required to ensure that the various element

    project are properly coordinated. It includes

    consolidation, articulation, project integrativ

    making trade-offs among competing objectiv

    alternatives to meet the stakeholders expec

    Project Integration management entails maninterdependencies amongst the knowledge a

    PMP Project Management Professional

    Project Integration Management -Con

  • 8/10/2019 pmp notes5 goods

    130/944

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Integration ManagementProject Integration Management Overview

  • 8/10/2019 pmp notes5 goods

    131/944

    Spearhead EduOnline Pvt Ltd.

    4.1 Development Project Charter

    Inputs Project Statement of work

    Business case

    Agreements

    Enterprise environmental

    factors

    Tools and Techniques

    Expert judgment Facilitation techniques

    Outputs Project charter

    4.2 Development Project Management

    Plan

    Inputs Project Charter

    Outputs from other processes

    Enterprise environmental

    factors

    Organizational process assets

    Tools and Techniques Expert judgment

    Facilitation techniques

    Outputs Project Management Plan

    4.3 Direct and M

    In

    Project manag

    Approved chan

    Enterprise env

    Organizational

    Tools and

    Expert judgme

    Project manag

    system

    Meetings

    Ou

    Deliverables

    Work performa

    Change reques

    Project manag

    Updates projec

    PMP Project Management Professional

    Project Integration ManagementProject Integration Management Overview

  • 8/10/2019 pmp notes5 goods

    132/944

    Spearhead EduOnline Pvt Ltd.

    4.4 Monitor and Control Project Work

    Inputs Project Management Plan

    Schedule forecast

    Cost forecast

    Validated changes

    Work performance information

    Enterprise environmental factors

    Organizational process assets

    Tools and Techniques

    Expert judgment

    Analytical techniques

    Project management information

    systems Meetings

    Outputs

    Change requests

    Work performance reports

    Project management plan updates

    Project documents updates

    4.5 Perform Integrated Control

    Inputs Project Management Plan

    Work performance reports

    Change requests

    Enterprise environmental factors

    Organizational process assets

    Tools and Techniques Expert judgment

    Meetings

    Change control toolsOutputs

    Final product, service or result

    transition

    Organizational process assets

    updates

    4.6 Close P

    In Project Man

    Acceptable d

    Organization

    Tools a

    Expert Judgme

    Analytical tech

    Meetings

    Ou

    Final, product,

    transition

    Organizationa

    updates

    PMP Project Management Professional

    Things to know in Integration Manage

    Project manager as integrator Project Charter has

  • 8/10/2019 pmp notes5 goods

    133/944

    Project manager as integrator

    Project planning methodology, Project

    plan Project management information

    system

    Work authorization, change control,managing change

    Integrated change control

    Corrective action, Preventive action,defect repair

    Project Charter haso Project Purpose or just

    o Measurable project obsuccess criteria

    o High level requirement

    o High level project desc

    o High level risks

    o Summary milestone sc

    o

    Summary budgeto Project approval requir

    o Assigned PM

    o Sponsor details

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Management Plan

    Project Management Plan includes

  • 8/10/2019 pmp notes5 goods

    134/944

    j g

    Selected Project life cycle and the processes that will be applied tcycle

    Tools and Techniques selected to accomplish the processes

    Management of dependencies, interactions, outputs and inputs

    Methodology of work execution

    Change management plan

    Configuration management plan

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Management PlanContd

  • 8/10/2019 pmp notes5 goods

    135/944

    How integrity of performance management baselines will be ma

    Techniques of stakeholder communication

    How to manage open issues and pending decisions

    Project baselines (cost, schedule, scope)

    Subsidiary plans (scope, requirements management, schedule, cprocess improvement plan, HR, communication, risk and procur

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Develop Project Charter

  • 8/10/2019 pmp notes5 goods

    136/944

    Spearhead EduOnline Pvt Ltd.

    Inputs

    Project statement of work

    Business Case

    Agreements

    Enterprise environmental factors

    Organizational process assets

    Tools & Techniques

    Expert judgment

    Facilitation Techniques

    Outpu Project Charter

    PMP Project Management Professional

    Project Charter Template

    Project Charter

    Project Name:

    Date:

    P i t f C t t

  • 8/10/2019 pmp notes5 goods

    137/944

    Spearhead EduOnline Pvt Ltd.

    Point of Contact:

    Organization Strategic Goals Project Objectives

    Milestone Name Milestone Date

    Summary of Scope Statement

    Project Resource Details

    Project Manager assigned and authority level.

    Resources pre-assigned.

    Project Assumptions

    Project Constraints/High level Risks

    Summary Budget

    PMP Project Management Professional

    Planning Process Group

    Planning Process develop Project Management Plan and the Project documents

    h P j

  • 8/10/2019 pmp notes5 goods

    138/944

    to carry out the Project.

    The Progressive detailing of the Project Management Plan is called Rolling wav The planning process helps gather information from many sources with each ha

    of completeness and confidence.

    These processes also identify, define and mature the projects scope, project cos

    the project activities that occur within the project.

    As new project information is discovered, additional dependencies, requiremen

    opportunities, assumptions and constraints will be identified or resolved. It is an iterative process. While planning the project the project team should inv

    appropriate stake holders.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Initiating Develop Project Cha

    PROJECT INTEGRATION MANAGEM

  • 8/10/2019 pmp notes5 goods

    139/944

    Spearhead EduOnline Pvt Ltd.

    Planning Develop Project Managem

    Executing Direct and Manage Proje

    Monitoring and Controlling Monitor and Control Proj

    Monitoring and Controlling Perform Integrated Chang

    Closing Close Project or Ph

    PMP Project Management Professional

    Develop Project Management Plan

  • 8/10/2019 pmp notes5 goods

    140/944

    Spearhead EduOnline Pvt Ltd.

    Inputs

    Project Charter

    Outputs from other processes

    Enterprise environmental factors

    Organizational process assets

    Tools & Techniques

    Expert judgment

    Facilitation Techniques

    Outputs

    Project Management Pla

  • 8/10/2019 pmp notes5 goods

    141/944

    PMP Project Management Professional

    Develop Project Management Plan

    Activities performed for creating a Project Management Plan

  • 8/10/2019 pmp notes5 goods

    142/944

    The project management processes selected by the project management te

    The level of implementation of each selected process

    The descriptions of the Tools and Techniques to be used for accomplishing t

    How the selected processes will be used to manage the specific project, inc

    dependencies and interactions among those processes, and the essential in

    outputs

    How work will be executed to accomplish the project objectives How changes will be monitored and controlled

    How configuration management will be performed

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Develop Project Management Plan-Co

    Activities performed for creating a Project Management Plan

  • 8/10/2019 pmp notes5 goods

    143/944

    How integrity of the performance measurement baselines

    maintained and used

    The need and Techniques for communication among stakeh

    The selected project life cycle and the associated project ph

    Key management reviews for content, extent, and timing to

    addressing open issues and pending decisions

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Executing process Group

    Process performed to Complete the work defined in the Project Manto satisfy the Project specifications

  • 8/10/2019 pmp notes5 goods

    144/944

    to satisfy the Project specifications.

    It involves coordinating people and resources , as well as integratingperforming the activities of the Project in accordance with the ProjeManagement Plan.

    During Project execution the results may require planning updates alining.

    A large portion of the projects Budget will be expended in perform

    executing Process Group Process.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Initiating Develop Project Cha

    PROJECT INTEGRATION MANAGEM

  • 8/10/2019 pmp notes5 goods

    145/944

    Spearhead EduOnline Pvt Ltd.

    Planning Develop Project Managem

    Executing Direct and Manage Proje

    Monitoring and Controlling Monitor and Control Proj

    Monitoring and Controlling Perform Integrated Chang

    Closing Close Project or Ph

    PMP Project Management Professional

    Direct and Manage Project Work

    This process requires the project manager and project team to

    lti l ti t t th j t t l t

  • 8/10/2019 pmp notes5 goods

    146/944

    multiple actions to execute the project management plan to ac

    work defined in the project scope statement. Some of the actions include:

    o Perform activities to accomplish project objectives

    o Expend effort and spend funds to accomplish the project object

    o Staff, train, and manage the project team members assigned to

    o Obtain quotations, bids, offers, or proposals as appropriate

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Direct and Manage Project Work -Co

    o Select sellers by choosing from among potential sellers

    o Obtain manage and use resources including materials Tools

  • 8/10/2019 pmp notes5 goods

    147/944

    o Obtain, manage and use resources including materials, Tools

    and facilitieso Implement the planned methods and standards

    o Create, control, verify and validate project deliverables

    o Manage risks and implement risk response activities

    o Manage Sellers

    o Adapt approved changes into the projects scope, plans and e

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Direct and Manage Project Work

    o Establish and manage project communication channels, both external and internal to t

    o Collect project data and report cost, schedule, technical and quality progress and statu

  • 8/10/2019 pmp notes5 goods

    148/944

    o Collect project data and report cost, schedule, technical and quality progress and statu

    facilitate forecasting

    o Collect and document lessons learned and implement approved process improvement

    The project manager, along with the project management team and the proj

    the performance of the planned project objectives, and manage the various

    organizational interfaces in the project

    Deliverables are produced as outputs from the processes performed to acco

    project work planned and scheduled in the project management plan

    This process also includes implementation of approved corrective, preventiv

    approved defect repair requests.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Management Information Sys

    PMIS consists of Tools and Techniques to gather, integrate a

    di i t th t t f j t t

  • 8/10/2019 pmp notes5 goods

    149/944

    disseminate the outputs of project management processes

    Used to support all aspects of the project from initiating to

    Can include both manual and automated systems.

    Is integral part of Communication Management Plan.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Direct and Manage Project Work

    Tools & Techniques

    Expert judgment

  • 8/10/2019 pmp notes5 goods

    150/944

    Spearhead EduOnline Pvt Ltd.

    Inputs

    Project Management Plan

    Approved change requests

    Enterprise environmental factors

    Organizational process assets

    Expert judgment

    Project Management

    Information systems

    Meetings

    Outputs

    Deliverables

    Work Performance Dat

    Change Requests

    Project Management P Project documents upd

    PMP Project Management Professional

    Monitoring and Controlling Process G

    Process required to track , review and regulate the Progress a

    performance of the Project

  • 8/10/2019 pmp notes5 goods

    151/944

    performance of the Project

    Identify any areas in which Changes to the Plan are required.

    The Key Benefit of this Process Group is that the Project Perfo

    observed and measured regularly and consistently to identify

    variances from the Project Management Plan.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Initiating Develop Project Ch

    PROJECT INTEGRATION MANAGEM

  • 8/10/2019 pmp notes5 goods

    152/944

    Spearhead EduOnline Pvt Ltd.

    Planning Develop Project Manage

    Executing Direct and Manage Proj

    Monitoring and Controlling Monitor and Control Pro

    Monitoring and Controlling Perform Integrated Chan

    Closing Close Project or Ph

    PMP Project Management Professional

    Monitor and Control Project Work

    It is performed to monitor project processes associated with initplanning, executing and closing. Corrective or preventive actions

    l h j f

  • 8/10/2019 pmp notes5 goods

    153/944

    control the project performance.

    Monitoring is an aspect of project management performed throuproject.

    Monitoring includes collecting, measuring, and disseminating peinformation, and assessing measurements and trends to effect p

    improvements.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Monitor and Control Project Work -Co

    Monitor and Control Project Work is concerned with:

    o Comparing actual project performance against the project management plan

  • 8/10/2019 pmp notes5 goods

    154/944

    p g p j p g p j g p

    o Assessing performance to determine whether any corrective or preventive aindicated and recommending those actions as necessary

    o Analyzing, tracking, and monitoring project risks to make sure the risks are id

    status is reported and appropriate risk response plans are being executed

    o Maintaining an accurate, timely information base concerning the projects p

    associated documentation through project completion

    o Providing information to support status reporting, progress measurement, ao Providing forecasts to update current cost and current schedule information

    o Monitoring implementation of approved changes when and as they occur

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Monitor and Control Project Work

    Tools & Techniques

    Expert judgment

    Analytical Techniques

  • 8/10/2019 pmp notes5 goods

    155/944

    Spearhead EduOnline Pvt Ltd.

    Inputs

    Project Management Plan

    Schedule forecasts

    Cost forecasts

    Validated changes

    Work performance information

    Enterprise environmental factors Organizational process assets

    Project Management

    Information systems Meetings

    Outputs

    Change Requests

    Work Performance repo

    Project Management Pla

    Project documents upda

    PMP Project Management Professional

    PROJECT INTEGRATION MANAGEM

    Initiating Develop Project Ch

  • 8/10/2019 pmp notes5 goods

    156/944

    Spearhead EduOnline Pvt Ltd.

    Initiating Develop Project Ch

    Planning Develop Project Manage

    Executing Direct and Manage Pro

    Monitoring and Controlling Monitor and Control Pro

    Monitoring and Controlling Perform Integrated ChanClosing Close Project or P

    PMP Project Management Professional

    Perform Integrated Change Contro

    Perform Integrated Change Control is the process of reviewing al

    requests; approving changes and managing changes to deliverab

  • 8/10/2019 pmp notes5 goods

    157/944

    q ; pp g g g g g

    organizational process assets, project documents, and the projecmanagement plan; and communicating their disposition. Perform

    Change Control is the process of reviewing all change requests; a

    changes and managing changes to deliverables, organizational pr

    project documents, and the project management plan; and comm

    their disposition. It reviews all requests for changes or modificatidocuments, deliverables, baselines, or the project management

    approves or rejects the changes.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Perform Integrated Change Control -C

    Tools & Techniques

    Expert judgment

  • 8/10/2019 pmp notes5 goods

    158/944

    Spearhead EduOnline Pvt Ltd.

    Inputs

    Project Management Plan

    Work performance reports

    Change requests

    Enterprise environmental factors Organizational process assets

    Expert judgment

    Meetings Change Control Tools

    Outputs

    Approved Change Reques

    Change Log

    Project Management Plan

    updates Project documents updat

    PMP Project Management Professional

    Perform Integrated Change Control F

  • 8/10/2019 pmp notes5 goods

    159/944

    Spearhead EduOnline Pvt Ltd.

    Different

    Process

    Perform

    Integrated

    Change

    Control

    Direct and

    Manage

    Project Work

    Change

    Request

    Approved

    Change

    Request

    Implem

    Cha

    Requ

    PMP Project Management Professional

    Perform Integrated Change Contro

    This process is performed from project inception through It includes the following change management activities:

  • 8/10/2019 pmp notes5 goods

    160/944

    o Identifying that a change needs to occur or has occurredo Influencing the factors that circumvent integrated change co

    only approved changes are implemented

    o Reviewing and approving requested changes

    o Managing the approved changes when and as they occur, by

    the flow of requested changes

    Spearhead EduOnline Pvt Ltd.

  • 8/10/2019 pmp notes5 goods

    161/944

    PMP Project Management Professional

    Perform Integrated Change Contro

    A Configuration Management System with integrated Change Control provide a s

    effective and efficient way to centrally manage approved Changes and baselines

  • 8/10/2019 pmp notes5 goods

    162/944

    Configuration Control is focused on the specification of both the deliverables anChange Control is focused on identifying , documenting and Controlling Changes

    and the Project Baseline.

    Some of the Configuration management activities included in the integrated Cha

    Process are

    1. Configuration identification2. Configuration Status accounting

    3. Configuration Verification and Audit

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Change Control Process

    Change analysis

    performed

    Change request

    submitted

  • 8/10/2019 pmp notes5 goods

    163/944

    Spearhead EduOnline Pvt Ltd.

    Project manager

    or review board

    makes decision

    Recommendationsforwarded

    Cha

    incorNo further action

    Approved

    R

    Not Approved

    T

    Communicate status

    PMP Project Management Professional

    Steps to be Followed if a Change is Request

    Customer1. Evaluate and Assess the change how is the change going to impact t

    2 Discuss with team members about the best way to handle the change

  • 8/10/2019 pmp notes5 goods

    164/944

    2. Discuss with team members about the best way to handle the change

    to crash, fast track etc.)? Also, try to determine what would be the im

    change e.g. change in scope, schedule, cost, quality etc.

    3. Inform customer about the implication of the changes.

    4. If customer still wants the changes, discuss with the management, sp

    stakeholders.

    5. Based on their inputs, if the change is warranted, a change control wiformally opened, necessary approvals received and then the team can

    required changes.

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Change Control System

    There are about 15 questions referring to Change Control S

    exam so, this topic should be studied carefully.

  • 8/10/2019 pmp notes5 goods

    165/944

    Change control system is a collection of formal (note: not indocumented procedures that defines how project perform

    monitored and evaluated.

    Includes the a) paperwork, b) tracking systems, c) processe

    approval levels needed for authorizing change. In many cases, the Change Control System of the performin

    organization can be adopted as is for use by the project.

    Spearhead EduOnline Pvt Ltd.

  • 8/10/2019 pmp notes5 goods

    166/944

    PMP Project Management Professional

    Closing Process Group

    Consists of those processes performed to finalize all activities across all Pr

    Management Process groups to formally complete the Project or Phase or

    Obligations

  • 8/10/2019 pmp notes5 goods

    167/944

    Obligations

    1. Obtain acceptance by the Customer or Sponsor

    2. Conduct Post Project or Phase end Review

    3. Record impacts of tailoring

    4. Document Lessons Learnt

    5. Archive all Project documents6. Close out Procurements

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    PROJECT INTEGRATION MANAGEM

    Initiating Develop Project Cha

  • 8/10/2019 pmp notes5 goods

    168/944

    Spearhead EduOnline Pvt Ltd.

    Planning Develop Project Managem

    Executing Direct and Manage Proje

    Monitoring and Controlling Monitor and Control Proj

    Monitoring and Controlling Perform Integrated Chang

    Closing Close Project or Pha

    PMP Project Management Professional

    Close Project or Phase

    Includes finalizing all activities completed across all Project ManaProcess Groups to formally close the project or project phase, ancompleted or cancelled project

  • 8/10/2019 pmp notes5 goods

    169/944

    completed or cancelled project

    It establishes the procedures to coordinate and interact to formaacceptance of those deliverables by the customer or sponsor, aninvestigate and document the reasons for actions taken if a projeterminated before completion.

    Procedures adopted are:

    o Administrative closure procedureo Contract closure procedure

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Close Project or Phase -Contd.

    Tools & Techniques

    Expert judgment

  • 8/10/2019 pmp notes5 goods

    170/944

    Spearhead EduOnline Pvt Ltd.

    Inputs

    Project Management Plan

    Accepted deliverables

    Organizational process assets

    p j g

    Analytical Techniques Meetings

    Outputs

    Final product, service or re

    transition

    Organization process asset

    PMP Project Management Professional

  • 8/10/2019 pmp notes5 goods

    171/944

    INTRODUCTION TO OTHKNOWLEDGE AREAS

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Scope Management

    Project Scope Management includes the processes required to ensu

    project includes all the work and only the work required to complet

  • 8/10/2019 pmp notes5 goods

    172/944

    successfully. Project scope management involves

    Constantly checking to ensure that all work gets completed

    Saying No to work not within project scope and preventing extra

    plating

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Scope Management (PSM) Processes

    Plan scope

    management

    Process of defining how project scope will be defined, validated a

    Project Scope Management -Contd

  • 8/10/2019 pmp notes5 goods

    173/944

    Spearhead EduOnline Pvt Ltd.

    g

    Collect

    Requirements

    Defining and documenting stakeholders needs to meet the proje

    Define Scope Developing detailed project scope statement as the basis of future

    Create Work

    Breakdown

    Structure (WBS)

    Sub-dividing major project deliverables and project work into sma

    components

    Verify Scope Formalizing acceptance of completed project delivera

    Control Scope Controlling changes to project scope

    PMP Project Management Professional

    Things to know in Scope Manageme

    Project scope Vs. Product scope

    Group creativity, group decision making ,Workshops are some Te

  • 8/10/2019 pmp notes5 goods

    174/944

    stakeholder requirements gathering Project selection methods Benefit measurement methods, con

    optimization methods

    Initiating a project Project selection, history collection, documescope analysis, resource identification, estimation, formal decisio

    stakeholders on the charter etc. Project Constraints, scope statement, scope management plan

    Spearhead EduOnline Pvt Ltd.

  • 8/10/2019 pmp notes5 goods

    175/944

    PMP Project Management Professional

    Sample WBS1.0

    Value Management

    System Project

    1.1

    Node Assessment

    1.2

    Standards Development1.3

    Systems Engineering

  • 8/10/2019 pmp notes5 goods

    176/944

    Spearhead EduOnline Pvt Ltd.

    1.1.2

    Requirements

    Determination

    1.1.3

    Alternatives

    Development

    1.1.1

    Control System Audit

    1.1.4

    System Requirement

    Development

    1.1.1.1

    Components

    Identification

    1.1.1.2Components Analysis

    1.1.2.1

    Gap

    Assessments

    1.1.2.2Requirements Charges

    identification

    1.1.3.1

    Alternatives

    identification

    1.1.3.2Alternatives

    Analysis

    The WBS is illustrative only. It is not intended to represent the full project scope of any specific project, nor to

    way to organize a WBS on this type of project.

    PMP Project Management Professional

    Project Time ManagementProject Time Management describes the processes required to ensure timely completion

    Project Time Management (PTM) Processes

    Plan schedule management Process of establishing the policies, procedure and documen

    developing, managing, executing and controlling the pro

  • 8/10/2019 pmp notes5 goods

    177/944

    Spearhead EduOnline Pvt Ltd.

    Define Activities Identify specific schedule activities that should be performed

    deliverables

    Sequence Activities Identifying and documenting dependencies among sche

    Estimate Activity Resource Estimate the type and no. of resources required to perform

    Estimate Activity duration Estimating the duration / period to complete individual s

    Develop Schedule Analyzing activity sequences, durations, resource requirem

    constraints to create project schedule

    Control Schedule Controlling changes to the project schedul

    PMP Project Management Professional

    Things to know in Time Management -C

    Scheduling Tools and their benefits Milestone charts, flowchart

    charts, network diagram and charts

  • 8/10/2019 pmp notes5 goods

    178/944

    Methods to draw network diagrams

    Schedule development Precedence diagramming methods

    Dependencies, Leads and Lags

    Estimating, resource calendars

    Estimating methods CPM (Critical Path Method), PERT (Program

    and Review Technique) Monte Carlo simulation (iterative)

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Critical path, LAG, FLOAT

    Analogous estimation use of parameters such as durationfrom a similar project as a basis for estimating

    Things to know in Time Manageme

  • 8/10/2019 pmp notes5 goods

    179/944

    p j g

    Parametric estimating, 3 point estimation

    Shortening schedule duration compression, resource levescenario analysis

    Re-estimating, crashing, fast tracking

    Schedule compression (crashing, fast tracking)

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Scheduling Overview

  • 8/10/2019 pmp notes5 goods

    180/944

    Spearhead EduOnline Pvt Ltd.

    PMP Project Management Professional

    Project Cost ManagementProject Cost Management describes the processes required to ens

    project gets completed within the approved budge

    Project Cost Management (PCM) Processes

  • 8/10/2019 pmp notes5 goods

    181/944

    Spearhead EduOnline Pvt Ltd.

    Plan Cost management Process of establishing the policies, procedure and documplanning, developing, managing, executing and controlling

    cost.

    Estimate Costs Developing an approximation of the costs of resources re

    complete the project

    Determine Budget Aggregating the estimated costs of individual activities

    packages to establish cost baseline

    Control Costs Influencing the factors that create cost variances and co

    changes to the project budget

    PMP Project Management Professional

    Things to know in Cost Managemen

    Control account WBS component used for project cost accoun

    Cost risk, resource planning, cost management plan

    Reserve analysis, cost of quality

  • 8/10/2019 pmp notes5 goods

    182/944

    Cost estimating analogous estimating, bottom-up estimating, estimating, computerized estimating Tools, 3 point estimation (moptimistic, pessimistic)

    Earned value analysis (EVA), net present value (NPV


Recommended