+ All Categories
Home > Education > PMP Series - PV, EV, and AC

PMP Series - PV, EV, and AC

Date post: 15-Jul-2015
Category:
Upload: tution-central
View: 39 times
Download: 2 times
Share this document with a friend
Popular Tags:
13
Follow us on Facebook for daily updates https://www.facebook.com/pages/TutionCentral Free study materials available at: http://tutioncentral.com/study-materials Free Practice tests at: http://tutioncentral.com/practice-tests Tutioncentral.com For all information's on Banking/CAIIB/JAIIB/MBA-finance/Probationary Officer / RRB/ CAT/ Verbal/Logical/Puzzles/Interview Questions/Free Practice Exams/Model Papers/Sample Papers and Many more… Visit us http://tutioncentral.com For free study materials & Practice exams PMP Preparation Series- Project Cost Management Planned Value (PV) Earned Value (EV) Actual Cost (AC) 1
Transcript
Page 1: PMP Series - PV, EV, and AC

Follow us on Facebook for daily updates https://www.facebook.com/pages/TutionCentral

Free study materials available at:http://tutioncentral.com/study-materials

Free Practice tests at:http://tutioncentral.com/practice-tests

Free study materials available at:http://tutioncentral.com/study-materials

Free Practice tests at:http://tutioncentral.com/practice-tests

Tutioncentral.com

For all information's on Banking/CAIIB/JAIIB/MBA-finance/Probationary Officer / RRB/ CAT/ Verbal/Logical/Puzzles/Interview Questions/Free Practice Exams/Model

Papers/Sample Papers and Many more…

Visit us http://tutioncentral.comFor free study materials & Practice exams

PMP Preparation Series-

Project Cost Management

Planned Value (PV)Earned Value (EV) Actual Cost (AC)

1

Page 2: PMP Series - PV, EV, and AC

Follow us on Facebook for daily updates https://www.facebook.com/pages/TutionCentral

Free study materials available at:http://tutioncentral.com/study-materials

Free Practice tests at:http://tutioncentral.com/practice-tests

Everything related to Career www.tutioncentral.com

Job

Inte

rvie

w P

rep

arat

ion

-R

ese

arch

yo

ur

com

pan

y

www. Tutioncentral.com Topics Covered• Planned Value(PV)

• Formula to calculate the Planned Value(PV)

• A mathematical Example of Planned Value(PV)

• Earned Value (EV)

• Formula to calculate the Earned Value(EV)

• A mathematical Example of Earned Value(EV)

• Actual Cost(AC)

• Formula to calculate the Actual Cost (AC)

• A mathematical Example of Actual Cost (AC)

• Conclusion

2

Page 3: PMP Series - PV, EV, and AC

Follow us on Facebook for daily updates https://www.facebook.com/pages/TutionCentral

Free study materials available at:http://tutioncentral.com/study-materials

Free Practice tests at:http://tutioncentral.com/practice-tests

Everything related to Career www.tutioncentral.com

Job

Inte

rvie

w P

rep

arat

ion

-R

ese

arch

yo

ur

com

pan

y

www. Tutioncentral.com Planned Value (PV)• As per the PMBOK Guide “Planned Value (PV) is the authorized budget

assigned to work to be accomplished for an activity or WBS component.

• Total planned value for the project is also known as Budget at Completion (BAC)

• The Planned Value is the approved value of the work to be completed in a given time period; in other words, it is the money that you should have spent as per the schedule.

• Planned Value is also referred to as the Budgeted Cost of Work Scheduled (BCWS).

3

Page 4: PMP Series - PV, EV, and AC

Follow us on Facebook for daily updates https://www.facebook.com/pages/TutionCentral

Free study materials available at:http://tutioncentral.com/study-materials

Free Practice tests at:http://tutioncentral.com/practice-tests

Everything related to Career www.tutioncentral.com

Job

Inte

rvie

w P

rep

arat

ion

-R

ese

arch

yo

ur

com

pan

y

www. Tutioncentral.com Formula to calculate the Planned Value (PV)

Planned Value =

(Planned % Complete) X Budget at Completion (BAC)

4

Page 5: PMP Series - PV, EV, and AC

Follow us on Facebook for daily updates https://www.facebook.com/pages/TutionCentral

Free study materials available at:http://tutioncentral.com/study-materials

Free Practice tests at:http://tutioncentral.com/practice-tests

Everything related to Career www.tutioncentral.com

Job

Inte

rvie

w P

rep

arat

ion

-R

ese

arch

yo

ur

com

pan

y

www. Tutioncentral.com A mathematical example (PV)

You have a project to be completed in 12 months and the total cost of the project is $100,000 USD. Six months have passed and the schedule says that 50% of the work should be completed. What is the Planned Value (PV)?GivenProject duration: 12 months Project Cost (BAC): $100,000 USDTime elapsed: 6 months Percent complete: 50% (as per the schedule)The definition of Planned Value says that the Planned Value is the value of the work that should have been completed so far (as per the schedule).• In this case we should have completed 50% of the total work.Hence,Planned Value = 50% of value of the total work= 50% of BAC, = 50% of $100,000 = $50,000Therefore, the Planned Value (PV) is $50,000 USD.

5

Page 6: PMP Series - PV, EV, and AC

Follow us on Facebook for daily updates https://www.facebook.com/pages/TutionCentral

Free study materials available at:http://tutioncentral.com/study-materials

Free Practice tests at:http://tutioncentral.com/practice-tests

Everything related to Career www.tutioncentral.com

Job

Inte

rvie

w P

rep

arat

ion

-R

ese

arch

yo

ur

com

pan

y

www. Tutioncentral.com Earned Value (EV)

• As per the PMBOK Guide “Earned Value (EV) is the value of work performed expressed in terms of the approved budget assigned to that work for an activity or WBS Component.”

• In other words, the Earned Value is the value of the work actually completed to date, or you can say that if the project is terminated today, the Earned Value will show you the value that it has produced.

• Earned Value is also known as the Budgeted Cost of Work Performed (BCWP).

• Most important element

6

Page 7: PMP Series - PV, EV, and AC

Follow us on Facebook for daily updates https://www.facebook.com/pages/TutionCentral

Free study materials available at:http://tutioncentral.com/study-materials

Free Practice tests at:http://tutioncentral.com/practice-tests

Everything related to Career www.tutioncentral.com

Job

Inte

rvie

w P

rep

arat

ion

-R

ese

arch

yo

ur

com

pan

y

www. Tutioncentral.com Formula to calculate the (EV)

Earned Value =

% of completed work X Budget at Completion (BAC)

7

Page 8: PMP Series - PV, EV, and AC

Follow us on Facebook for daily updates https://www.facebook.com/pages/TutionCentral

Free study materials available at:http://tutioncentral.com/study-materials

Free Practice tests at:http://tutioncentral.com/practice-tests

Everything related to Career www.tutioncentral.com

Job

Inte

rvie

w P

rep

arat

ion

-R

ese

arch

yo

ur

com

pan

y

www. Tutioncentral.com A mathematical example (EV)You have a project to be completed in 12 months and the total cost of the project is $100,000 USD. Six months have passed and $60,000 USD has been spent, but on closer review you find that only 40% of the work is completed so far. What is the Earned Value (EV)?

• In the above question, you can clearly see that only 40% of the work is actually completed, and the definition of Earned Value says that it is the value of the project that has been earned.

• Hence, Earned Value = 40% of value of total work= 40% of BAC = 40% of $100,000= 0.4 X $100,000 = $40,000

• Therefore, the Earned Value (EV) is $40,000 USD.

8

Page 9: PMP Series - PV, EV, and AC

Follow us on Facebook for daily updates https://www.facebook.com/pages/TutionCentral

Free study materials available at:http://tutioncentral.com/study-materials

Free Practice tests at:http://tutioncentral.com/practice-tests

Everything related to Career www.tutioncentral.com

Job

Inte

rvie

w P

rep

arat

ion

-R

ese

arch

yo

ur

com

pan

y

www. Tutioncentral.com Actual Cost (AC)

• As per the PMBOK Guide “Actual Cost (AC) is the total cost actually incurred in accomplishing work performed for an activity or WBS component.”

• The Actual Cost is the total cost incurred for the actual work completed to date; or simply put, it is the amount of money you have spent to date.

• The Actual Cost is also known as the Actual Cost of Work Performed (ACWP).

9

Page 10: PMP Series - PV, EV, and AC

Follow us on Facebook for daily updates https://www.facebook.com/pages/TutionCentral

Free study materials available at:http://tutioncentral.com/study-materials

Free Practice tests at:http://tutioncentral.com/practice-tests

Everything related to Career www.tutioncentral.com

Job

Inte

rvie

w P

rep

arat

ion

-R

ese

arch

yo

ur

com

pan

y

www. Tutioncentral.com Formula to calculate (AC)

• There is no special formula to calculate the Actual Cost.

• It is an amount that has been spent and can be found very easily in the question.

10

Page 11: PMP Series - PV, EV, and AC

Follow us on Facebook for daily updates https://www.facebook.com/pages/TutionCentral

Free study materials available at:http://tutioncentral.com/study-materials

Free Practice tests at:http://tutioncentral.com/practice-tests

Everything related to Career www.tutioncentral.com

Job

Inte

rvie

w P

rep

arat

ion

-R

ese

arch

yo

ur

com

pan

y

www. Tutioncentral.com A mathematical Example (AC)

You have a project to be completed in 12 months and the total cost of the project is $100,000 USD. Six months have passed and $60,000 USD has been spent, but on closer review you find that only 40% of the work is completed so far. What is the Actual Cost (AC)?

• As per the definition of Actual Cost, it is the amount of money that you have been spent so far. And in our question, you have spent $60,000 USD on the project so far.

• Hence, The Actual Cost is $60,000 USD.

11

Page 12: PMP Series - PV, EV, and AC

Follow us on Facebook for daily updates https://www.facebook.com/pages/TutionCentral

Free study materials available at:http://tutioncentral.com/study-materials

Free Practice tests at:http://tutioncentral.com/practice-tests

Everything related to Career www.tutioncentral.com

Job

Inte

rvie

w P

rep

arat

ion

-R

ese

arch

yo

ur

com

pan

y

www. Tutioncentral.com Conclusion

• Planned Value is the money that you should have spent as per the schedule.

• Earned Value is the value of the work actually completed to date.

• Actual Cost is the amount spent on the project to date

12

Page 13: PMP Series - PV, EV, and AC

Follow us on Facebook for daily updates https://www.facebook.com/pages/TutionCentral

Free study materials available at:http://tutioncentral.com/study-materials

Free Practice tests at:http://tutioncentral.com/practice-tests

Everything related to Career www.tutioncentral.com

Job

Inte

rvie

w P

rep

arat

ion

-R

ese

arch

yo

ur

com

pan

y

www. Tutioncentral.com Thanks &

All the Best for a great Career

Tutioncentral.com

For all information's on Banking/CAIIB/JAIIB/MBA-finance/Probationary Officer / RRB/ CAT/ Verbal/Logical/Puzzles/Interview Questions/Free Practice Exams/Model Papers/Sample Papers and Many more…

Visit us http://tutioncentral.comFor free study materials & Practice exams

13

Visit Tutioncentral.com forAll everything related to Banking Career

- Banking Terms & Study Materials- JAIIB- CAIIB- NCFM Certifications- PO Exams- Bank Interview Questions & Answers- Vast collection of Study Materials on Banking Topics- Latest news in Banking Sector and many more


Recommended