+ All Categories
Home > Documents > PMP_How to make a WBS

PMP_How to make a WBS

Date post: 27-Nov-2015
Category:
Upload: kok-khek-hun
View: 42 times
Download: 0 times
Share this document with a friend
Description:
How to make a WBS
Popular Tags:
75
Work Breakdown Structure
Transcript
Page 1: PMP_How to make a WBS

Work Breakdown Structure

Page 2: PMP_How to make a WBS

The purpose of the work breakdown structure (WBS) is to sub-divide the scope of work into

manageable work packages which can be estimated, planned and assigned to a responsible

person or department for completion.

Page 3: PMP_How to make a WBS

The WBS was originally developed in the 1960's as part of the drive towards improved project

definition and it soon became the backbone of the planning and control system.

Page 4: PMP_How to make a WBS

The WBS is an excellent tool for quantifying the scope of work as a list of work packages and is an

essential tool for ensuring the estimate or quotation includes the complete scope of work.

Page 5: PMP_How to make a WBS

The WBS can also be considered as a hierarchical form of mind map which helps to break

complexity down into simple manageable components.

Page 6: PMP_How to make a WBS

Turner defines the WBS as: "…….a cascade of deliverables, in which the overall product or

objective of the project is broken into sub-products, assemblages and components. "

Page 7: PMP_How to make a WBS

The first step towards mastering the WBS technique is to fully understand the structured methodology for

sub-dividing the scope of work. The main components of the WBS are:

• Structure• Methods of sub-division• Numbering or coding system• Level of detail• Number of WBS levels• Roll-up• Integrating the WBS/OBS to assign responsibility.

Page 8: PMP_How to make a WBS

The WBS Structure

There are two methods of presenting the WBS:

1. Graphically in boxes2. Text indents.

Page 9: PMP_How to make a WBS

The WBS is a hierarchical structure which is best presented by a graphical sub-division of the scope of work in boxes. This logical sub-division of all

the work elements is easy to understand and assimilate, thus helping the project participants to quantify their responsibility and gain their

commitment and support.

Page 10: PMP_How to make a WBS

House Project WBS Sub-Divided into Boxes

Page 11: PMP_How to make a WBS

Although boxes are an excellent means of presentation it is a cumbersome document to develop

and edit on the computer. Boxes lend themselves more to graphic software than planning software and the printout for a large project would look best from a large flat bed printer rather than sticking A4 or A3

sheets together.

Page 12: PMP_How to make a WBS

The other method of presentation shows the scope of work as text indents, where each level is tabbed to represent its level in the hierarchy. If you are using

planning software you will have to setup this structure anyway as you input the project data.

Page 13: PMP_How to make a WBS

WBS Horizontal Presentation (a simple rotation)

Page 14: PMP_How to make a WBS

• 1.0.0 House Project1.1.0 Civil

1. 1. I Foundations1. 1. 2 Walls and roof

1.2.0 Plumbing1.2.1 Piping1.2.2 Sewerage

1.3.0 Electrical1.3.1 Wiring1.3.2 Appliances

Page 15: PMP_How to make a WBS

Method of Sub-Division

Page 16: PMP_How to make a WBS

Designing the WBS requires a delicate balance to address the different needs of the various disciplines and project locations. There is not necessarily a right or wrong structure because what may be an excellent fit for one discipline may be an awkward burden for

another.

Page 17: PMP_How to make a WBS

As you will see there are many methods of sub-dividing the scope of work, your imagination is the only limiting factor. The best method is the one that works for you and you may use more than one

method as the project progresses.

Page 18: PMP_How to make a WBS

Except for the project life-cycle al I the other breakdown structures (in the text) are simply a sub-division of the scope of work, there are no

logical relationships between the work packages - that will come later in the CPM.

Page 19: PMP_How to make a WBS

Product Breakdown Structure (PBS): This represents a hierarchical view of the physical assemblies,

sub-assemblies, components and parts needed to manufacture the product. Consider the sub-division

of an airplane:

Page 20: PMP_How to make a WBS

Product Breakdown Structure (Airplane)

Page 21: PMP_How to make a WBS

Organization Breakdown Structure (OBS): This represents a hierarchy of the company managing the project. By linking the OBS with the WBS or PBS this will identify who is responsible for performing

the work packages.

Page 22: PMP_How to make a WBS

The OBS could contain any of the following sub-divisions:

• Department or discipline• Contractor or supplier• Project team or person.

Page 23: PMP_How to make a WBS

Organization Breakdown Structure

Page 24: PMP_How to make a WBS

Cost Breakdown Structure (CBS): This represents the financial breakdown of the project into budgets

per work package.

Page 25: PMP_How to make a WBS

Cost Breakdown Structure (by cost center andsupplier)

Page 26: PMP_How to make a WBS

Contract Breakdown Structure also (CBS): This represents the relationships between the client with

the contractor. At the lowest level this could link the purchase orders with the account invoices.

Page 27: PMP_How to make a WBS

Contract Breakdown Structure (by sub-contractor and supplier)

Page 28: PMP_How to make a WBS

Location Breakdown Structure: This represents the physical location of the work and would be

appropriate for a project which has pockets of work dotted all over the place. Consider a power line project where there may be a number of similar

substations.

Page 29: PMP_How to make a WBS

Location Breakdown Structure (power line project)

Page 30: PMP_How to make a WBS

Transport Breakdown Structure: Projects which are characterized by large loads may find that transport and cranage limitations determine their breakdown

structure.

Page 31: PMP_How to make a WBS

Transport Breakdown Structure (with largest units that can be transported by road)

Page 32: PMP_How to make a WBS

System Breakdown Structure: This represents a systems breakdown which may cut across other breakdown structures, but would be useful when

commissioning the product. Consider the following house building project.

Page 33: PMP_How to make a WBS

System Breakdown Structure (House project)

Page 34: PMP_How to make a WBS

Project Life-Cycle Structure: This represents a logical sub-division of the sequence of work into

project phases. This is discussed in the Project Life-Cycle chapter.

Page 35: PMP_How to make a WBS

Project Life-Cycle Structure

Page 36: PMP_How to make a WBS

Each element in the WBS needs to be identified by a short description. Although the length of the

description may be restricted by the size of the box, the meaning should be clear. As these examples have

shown there are many ways of sub-dividing a project, with some methods being more appropriate than others. The best results are generally gained by

using an iterative and heuristic approach which considers a range of sub-divisions until an

appropriate structure is derived.

Page 37: PMP_How to make a WBS

WBS Templates

Page 38: PMP_How to make a WBS

In practice companies that use the WBS, set up a standard WBS proforma or template for their

projects. Instead of starting each project with a blank sheet of paper, consider using a WBS from a

previous project as a template.

Page 39: PMP_How to make a WBS

A standard WBS ensures consistency and completeness as it becomes a planning checklist with

all the components that your particular type of project would contain. Having a structured check list

also reduces the risk of omitting the obvious.

Page 40: PMP_How to make a WBS

Even if the complete WBS cannot be used, there may be portions which are similar and can be copied across. Using proven structures will greatly speed up

the planning process and helps to structure your thinking.

Page 41: PMP_How to make a WBS

The next Figure outlines a WBS where the first level is sub-divided by location, the second level by

discipline and the third level by expense. This format could be used as a standard WBS for the company.

The only changes per project would be to the description rather than the structure. Note: FOB =

free on board a ship, train or road transport.

Page 42: PMP_How to make a WBS

WBS Standard Format or Template (which can be used on similar types of projects)

Page 43: PMP_How to make a WBS

How Many WBS Levels?

Page 44: PMP_How to make a WBS

With each level of the WBS the scope of work is sub-divided into more work packages with a

corresponding increase in the level of detail. For practical purposes three or four levels should be

sufficient to achieve the desired level of planning and control - any more than that and like a Pyramid

the base of the WBS would start to become unwieldy.

Page 45: PMP_How to make a WBS

The number of levels is influenced by:

• level of detail• level of risk• level of control• estimate accuracy• work package value• work package man-hours.

Page 46: PMP_How to make a WBS

If more than three or four levels are required this can be addressed by using sub-projects, where the lowest

level work package of one project constitutes the highest level of another project.

Page 47: PMP_How to make a WBS

This situation is common on projects where a main contractor uses many subcontractors. In this way, the

WBS can effectively increase the number of breakdown levels, with each project manager

focusing on their own scope of work and responsibility.

Page 48: PMP_How to make a WBS

WBS Breakdown by Sub-Projects

Page 49: PMP_How to make a WBS

Project Control: The appropriate level of control relates to the complexity and risks embedded in the

project. Project control is the ability to steer the project to a successful completion. The earned value

technique may suggest an appropriate $ value, duration or work hours for the work packages.

Page 50: PMP_How to make a WBS

WBS (sub-divided by level of risk and uncertainty)

Page 51: PMP_How to make a WBS

Risk and Uncertainty: The WBS structure should reflect the level of risk and uncertainty. Where the

level of risk is high the WBS should be sub-divided further to generate more information and thus reduce

the risk.

Page 52: PMP_How to make a WBS

Estimating

Page 53: PMP_How to make a WBS

If your company wins contracts by competitive bidding it is important to have a system for

generating accurate quotations quickly. The WBS offers a top down sub-division of the work, while

estimating at the work package level, offers a bottom up roll-up of project costs.

Page 54: PMP_How to make a WBS

The Numbering System

• One of the beneficial features of the WBS is its ability to uniquely identify by a number or code all the elements of work in a numerical and logical manner. With a unique number, all work packages can be linked to the project's accounts, the corporate accounts and the client's accounts.

Page 55: PMP_How to make a WBS

The numbering system can be alphabetic, numeric, or alphanumeric (letters and numbers), in most of the

examples here the numbering systems will be numeric. Consider the following example:

Page 56: PMP_How to make a WBS

• Level 0: The first number [ 1.0.0] represents the first work element on the level zero. It is normal practice to have only one item at this level i.e. the total project. The project may have its own unique number, see figures 14 and 15 below.

Page 57: PMP_How to make a WBS

• Level 1: At the first level of sub-division the first work element will be numbered [1.1.0] and the second work element numbered [1.2.0]. Thus the other work elements will be numbered sequentially; [1.3.0], [1.4.0], [1.5.0] etc.

Page 58: PMP_How to make a WBS

• Level 2: These numbers are then further sub-divided at the second level from the first element at the second level into [1.1.1 ], [ 1.1.2], [ 1.1.3], [1.1.4] etc.

Page 59: PMP_How to make a WBS

WBS Sub-Division by Numbering System

Page 60: PMP_How to make a WBS

WBS Numbering System (this example shows how the numbering system can lead to very long work

package numbers)

Page 61: PMP_How to make a WBS

Project Number: Most projects are given a project number and a description to distinguish them from all the other projects the company may be working

on.

Page 62: PMP_How to make a WBS

The project number may come from a number of sources:

• estimate number• quotation number• contract number• invoice number• purchase order number• client's order number

Page 63: PMP_How to make a WBS

Many projects also have a name (marine projects would use the ship's name), or a humorous nickname

to help association. With increased computer graphics a project icon is also a consideration.

Page 64: PMP_How to make a WBS

WBS Roll-up

• The roll-up facility is normally used to roll-up project costs for budget planning and control purposes. By suitably structuring the WBS, budgets can be established per department, per location or per sub-contractor.

Page 65: PMP_How to make a WBS

Roll-Up House Project

Page 66: PMP_How to make a WBS

The WBS roll-up technique lends itself to anything that flows in the project, i.e. man-hours, cubic meters

of concrete thrown, tones of steel erected, bricks laid, drawings completed, square meters of paint etc.

Any of these could be planned, tracked and controlled using the WBS.

Page 67: PMP_How to make a WBS

Consider a Drawing Office project where it would be more appropriate to plan and track man-hours rather than costs. This is because the chief draughtsman can

estimate the time required to complete a drawing from experience, but may not have the data

necessary to estimate the costs involved.

Page 68: PMP_How to make a WBS

Drawing Office Project (where Mh = man-hours)

Page 69: PMP_How to make a WBS

Responsibility

• Assigning responsibility for performing project work is one of the key project management functions. This can be achieved through the interface between the WBS and the organization breakdown structure (OBS). The WBS / OBS links clearly indicates the work packages and the person responsible for carrying out the work, however it is a rather cumbersome presentation as the level of detail increases. For this reason it is best suited to high level links.

Page 70: PMP_How to make a WBS

WBS / OBS Links

Page 71: PMP_How to make a WBS

The WBS/OBS links can also be shown on the schedule bar chart, by either using a responsibility

field (also called a responsibility matrix) or printing the person's name after the activity.

Page 72: PMP_How to make a WBS

Foreign Currency

• Some projects are characterized by international procurement from a number of countries. As these exchange rates are prone to fluctuate, then your risk management analysis will need to determine the extent of your exposure to foreign currency. This can be achieve by structuring the WBS to roll-up a number of foreign currencies and report the total requirement for each.

Page 73: PMP_How to make a WBS

WBS by Foreign Currency

Page 74: PMP_How to make a WBS

The WBS does not indicate when the foreign currency is required, for this you will have to

develop the cash-flow statement through the critical path method (CPM) which is the topic of the

following chapter.

Page 75: PMP_How to make a WBS

Key Points:

• The WBS sub-divides the project into manageable work packages.

• On fixed price contracts the WBS helps to ensure the quotation includes the full scope or work.

• The WBS numbering systems uniquely identifies all the work packages.


Recommended