+ All Categories
Home > Documents > pmw Bombay High Court - Bar & Bench · Bombay High Court pmw ... Senior Advocate with Mr. Gaurish...

pmw Bombay High Court - Bar & Bench · Bombay High Court pmw ... Senior Advocate with Mr. Gaurish...

Date post: 07-Jun-2018
Category:
Upload: vodang
View: 219 times
Download: 0 times
Share this document with a friend
29
Bombay High Court 1 wp-8306.15 pmw IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION WRIT PETITION NO.8306 OF 2015 North Goa District Advocates Association and Ors. … Petitioners Versus The High Court of Bombay and Goa and Ors. … Respondents Mr. Aspi Chinoy, Senior Advocate with Mr. Gaurish Agni, Mr. Omkar Warange, Mr. David Rao and Mr. Abid Ali i/by Mr. Ameya Sudhir Tamhane, for the Petitioners. Mr. D.J. Kambata, Senior Advocate a/w Mr. M.S. Karnik, for the Respondent Nos.1 and 3. Mr. A.N.S. Nadkarni, Senior Advocate (the Advocate General of the State of Goa) a/w Mr. Manish Salkar, AGP for Respondent No.2. Mr. Ashwin D. Bhobe, for Respondent No.4.           CORAM  :  A.S. OKA & A.R. JOSHI, JJ. JUDGMENT RESERVED ON      :  26 th  AUGUST, 2015 JUDGMENT PRONOUNCED ON :  8 th  SEPTEMBER, 2015 JUDGMENT (PER A.S. OKA, J.):-  . There is a District Court of North Goa at Panaji at Goa. There are at present six Courts in  Civil and Criminal  Courts building at Panaji which includes two Courts of the District Judges and four Civil and Criminal Courts. The High Court Administration decided to shift all the four Civil and Criminal Courts from the Civil and Criminal Courts 1 of 29 ::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:04 :::
Transcript

Bombay

Hig

h Court

1 wp-8306.15

pmwIN THE HIGH COURT OF JUDICATURE AT BOMBAY

CIVIL APPELLATE JURISDICTION

WRIT PETITION NO.8306 OF 2015 

North Goa District Advocates Association and Ors. … Petitioners

Versus

The High Court of Bombay and Goa and Ors. … Respondents

Mr. Aspi Chinoy, Senior  Advocate with Mr. Gaurish Agni,  Mr. Omkar Warange,   Mr.   David   Rao   and   Mr.   Abid   Ali   i/by   Mr.   Ameya   Sudhir Tamhane, for the Petitioners.

Mr.   D.J.   Kambata,   Senior   Advocate   a/w   Mr.   M.S.   Karnik,   for   the Respondent Nos.1 and 3.

Mr.  A.N.S.  Nadkarni,  Senior  Advocate   (the  Advocate  General  of   the State of Goa) a/w Mr. Manish Salkar, AGP for Respondent No.2.

Mr. Ashwin D. Bhobe, for Respondent No.4.

          CORAM  :  A.S. OKA & A.R. JOSHI, JJ.

JUDGMENT RESERVED ON       :  26th AUGUST, 2015

JUDGMENT PRONOUNCED ON :  8th SEPTEMBER, 2015

JUDGMENT (PER A.S. OKA, J.):­

   . There  is  a District  Court  of  North Goa at  Panaji  at  Goa. 

There are at present six Courts in  Civil and Criminal  Courts building at 

Panaji which includes two Courts of the District Judges and four Civil 

and Criminal Courts. The High Court Administration decided to shift all 

the four Civil and Criminal Courts from the Civil and Criminal Courts 

1 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:04 :::

Bombay

Hig

h Court

2 wp-8306.15

building at  Panaji   to   the  3rd,  4th  ,  5th   and 6th  floors  of   the building 

known as “Spaces”  (for short “the new building”) at Patto Plaza, Panaji. 

The challenge is to the notice dated 24th  July, 2015 published by the 

learned Principal District and Sessions Judge, North Goa, Panaji Court 

by   which   he   declared   that   all   the   four   Civil   and   Criminal   Courts 

presently housed in the Civil and Criminal Courts building at Panaji will 

start  holding  sittings   in   the  new premises   in   the  new building with 

effect from 10th August, 2015.   The present Petition has been filed by 

the   North   Goa   District   Advocates'   Association,   the   Panjim   Lawyer's 

Forum and two other members of the Bar who are the office bearers of 

the said Associations.  We must note here  that  a  Writ  Petition under 

Article 32 of the Constitution of India was filed by the Petitioners before 

the Apex Court for the same relief.  Under the order dated 10 th August, 

2015,   the said Petition was permitted to be withdrawn by the Apex 

Court with liberty to file a Petition under Article 226 of the Constitution 

of India before this Court at Bombay. Accordingly, the present Petition 

has been filed.  

2.                       The learned   Senior Counsel appearing for the Petitioner  

pointed   out   that   the   existing  Civil   and   Criminal   Courts   building   at 

Panaji  which  houses   the  District  Court   of  North  Goa   is   in   a   sound 

condition.   He   invited   our   attention   to   the   photographs   of   the   said 

2 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:04 :::

Bombay

Hig

h Court

3 wp-8306.15

building placed on record.  He pointed out that there are two Courts of 

the District and Sessions Judge in the said building and four Civil and 

Criminal Courts.  He urged that way back in the year 2009, a large plot 

of land at Merces, Panaji has been already allotted by the Government 

of Goa for construction of a new District Court complex of North Goa 

District   which   can   accommodate   20   Courts.   He   pointed   out   that 

notwithstanding   the   assurances   given   from   time   to   time   regarding 

commencing   and   completing   the   construction  of   new  District  Court 

complex, no steps have been taken by the Government of Goa to even 

commence the construction of the new Court complex.  He pointed out 

the order dated 26th  August, 2009 passed by a Division Bench of this 

Court at Goa in a PIL which directed the State Government to provide a 

plot of land admeasuring about 20,000 square meters at Merces, Panaji 

and accordingly the plot has been allotted. He pointed out that plans of 

the  new District Court complex were ready in the year 2011 and in fact 

in the meeting held between  Hon'ble the Chief Minister of Goa and the 

Hon'ble  Chief Justice of this Court it was agreed that the  construction 

of the District Court complex will be commenced by the end of the year 

2013 and will be completed by the end of 2014. He urged that no steps 

have  been   taken   in   that  behalf.    He pointed  out   that   the   said  new 

building was hurriedly acquired by the Government of Goa in which 

four floors   have been allotted to the Civil and Criminal Courts.   He 

3 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:04 :::

Bombay

Hig

h Court

4 wp-8306.15

pointed   out   that   admittedly   there   exists   a   garbage   dump   in   the 

immediate  proximity  of   the  said new building.    He pointed  out   the 

photographs to show how close the open garbage dump is to the said 

new building.   He urged that the open garbage emits foul odour.   He 

pointed out that the garbage dump has uncovered heaps of composted 

material.     He   pointed   out   that   there   is   no   provision   for   leachate 

collection   which   causes   health   hazard.   He   invited   our   attention   to 

copies of inspection reports of the Goa State Pollution Control Board. 

He also invited our attention to the direction dated 12th January, 2015 

issued by the Goa State Pollution Control Board in respect of the said 

garbage   dump   which   shows   the   extent   of   nuisance   created   by   the 

garbage  dumb.  He  pointed  out   that   there   is  a  public   library   in   the 

vicinity  of   the  said  new building  which cannot  be  used  due  to   foul 

odour emitted by the garbage.   He pointed out that there are various 

public offices in the area of the said new building. He pointed out that 

complaints have been made by the Commissioner of Income Tax, BSNL, 

Officers   of   the   Passport   Office   and   the   Manager   of   LIC   about   the 

nuisance and health hazard created by flies and foul smell.  

3. He  urged   that  he   is   conscious  of   the   limitations  on   the 

power  of   the  Writ  Court   to   interfere  with   the  purely  administrative 

decisions. He pointed out that he is not calling upon this Court to go 

4 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:04 :::

Bombay

Hig

h Court

5 wp-8306.15

into the question of suitability of the premises in the said new building 

for establishing Courts.  He submitted that the very decision of shifting 

the four Civil and Criminal Courts in an area which is known for the 

nuisance created by garbage dump is itself arbitrary for more than one 

reason. He urged that when the existing Courts are properly functioning 

in the existing building and when a new Court complex can be easily 

constructed within a short time on the allotted plot, there was no hurry 

to shift the Civil and Criminal Courts to the new  building.  He pointed 

out that rent of approximately Rs.5 Crores per year will be payable by 

the  Government  of  Goa   in   respect  of   the  premises   in   the   said  new 

building.   He also submitted that on the ground floor of the existing 

Civil and Criminal Court building, there is a storage of muddemal and 

other articles which can be conveniently shifted to the   new building 

instead of shifting the Courts. He urged that the existing six Courts have 

sufficient place in the existing building and more space can be created 

by   shifting   the   old   record   and   muddemal   articles   in   the   premises 

available in the new building.  He urged that when Writ Court exercises 

its    power   to   test   the  administrative  decision  on  the   touch­stone  of 

arbitrariness, there cannot be any difference between an administrative 

decision of   the  High Court  and administrative decision of  any other 

agency and instrumentality  of the State. Lastly, he invited our attention 

to the newspaper reports appearing in February and August, 2015 in 

5 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:04 :::

Bombay

Hig

h Court

6 wp-8306.15

leading newspapers in Goa showing that the garbage dump in the area 

is creating unbearable stink which is causing respiratory problems and 

affecting the health of those who are working in the area.   He urged 

that even going by the stand of the Goa State Pollution Control Board, 

in near future, there is no possibility of the garbage dump at Patto Plaza 

being shifted to another place.  He, therefore, urged that intervention of 

the Writ court is necessary.

4. The learned Advocate General of Goa submitted that the 

four floors which have been made available to the Court in the new 

building are fully air­conditioned. He pointed out that the Government 

of Goa has spent a sum of about Rs.4 Crores on air­conditioning, on 

internal changes and on  providing modern furniture therein.  He urged 

that some of the Judges of this Court including the Hon'ble the Chief 

Justice have inspected the said new building   and have approved the 

same. He invited our attention to the affidavit of Shri Prashant Goyal, 

the Law Secretary, Government of Goa.   He pointed out that all steps 

have been taken by the Government of Goa to commence construction 

of new Court complex for North Goa in Merces, Panaji. He invited our 

attention to the statements made in the said affidavit.   He stated that 

the Government of Goa has entrusted the work of construction of new 

District and Subordinate Court complex at North Goa at Merces to the 

6 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:04 :::

Bombay

Hig

h Court

7 wp-8306.15

Goa State Infrastructure Development Corporation (for short “GSIDC”). 

He urged that after completing all the formalities,   the work order is 

likely to be issued by 15th  January, 2016 and the construction will be 

completed within a period of 24 months from the date of issue of the 

work order.  He invited our attention to the affidavit of Shri Levinson J. 

Martins, the Member Secretary of the Goa Pollution Control Board.  He 

stated that all possible steps have been taken by the Pollution Control 

Board to abate the nuisance created by the garbage dump. He pointed 

out that the Corporation of City of Panaji (for short “CCP”) acquired a 

land  which   is   away   from commercial   establishments   and   residential 

habitation   for   the   purposes   of   setting   up   'Dry   Recyclable   material 

sorting center and composting stations'.  He pointed out that the work 

at the said site commenced in December, 2014 but by order dated 5 th 

March,   2015   the   National   Green   Tribunal   has   granted   an   order   of 

status­quo. He submitted that but for the order of status­quo, the said 

facility would have been operational by now and the use of the plot at 

Patto Plaza as a dumping ground would have been completely stopped. 

He urged that the decision to shift the Courts to the said new building is 

of the year 2013 and the Petitioners were all along aware of the same. 

He urged that the Petition deserves to be dismissed only on the ground 

of gross  delay which is not explained.

7 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:04 :::

Bombay

Hig

h Court

8 wp-8306.15

5. The learned counsel appearing for the CCP relied upon an 

affidavit of Shri Sanjit Rodrigues, the Commissioner of CCP, in which it 

is pointed out that all steps were taken to develop a new site which 

could not be developed due to ad­interim order passed by the National 

Green Tribunal.  He pointed out the steps taken to maintain the site at 

Patto Plaza. 

6. Shri  Khambata,   the   learned Senior  Counsel   representing 

the   High   Court   Administration   invited   our   attention   to   the   present 

status   of existing Court building at Panaji.   He pointed out from the 

documents   annexed   to   the  Petition   that   in   the  year  2013   itself   the 

Petitioners were aware of the decision to shift four Courts to the said 

new building. He pointed out that out of the six Courts in the existing 

building, four Civil and Criminal Courts will be shifted to the said new 

building.  He pointed  out   that  one  Court  of  ad­hoc  District   Judge   is 

situated in another building known as Velho building which is required 

to be vacated.    He stated  that   the said Court  will  be shifted to   the 

existing building.  He stated that there is a possibility that one existing 

Court at Ponda will be shifted to the existing building and probably one 

or two newly appointed Judges will be accommodated in the existing 

building.  He pointed out that the existing building is  very congested as 

well as inconvenient   whereas the four floors in the said new building 

are   fully   air­conditioned   and   the   air   conditioning   will   protect   the 

8 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:04 :::

Bombay

Hig

h Court

9 wp-8306.15

members of the Bar, litigants and Judges from foul odour and alleged 

nuisance.  He urged that the decision to shift four Courts is based on the 

consideration of all the relevant factors and a Writ Court cannot go into 

the issue of the suitability of the premises in the said new building for 

the use as a Court.

7. We have given careful consideration to the submissions. In 

PIL No.6 of 2009, a Division Bench at Goa by order dated 26 th August, 

2009  directed   the  Government   of  Goa   to   allot   a   land  admeasuring 

20,000   square   meters   at   Merces   (for   short   “Merces   land”)   for 

construction of the Court complex to accommodate the District,  Civil 

and Criminal Courts at Panaji.  There is a letter dated 28th March, 2012 

addressed by the learned Principal District and Sessions Judge, North 

Goa to the Principal Chief Engineer of the Public Works Department of 

Government   of   Goa   in   which   it   was   recorded   that   there   was   an 

assurance that the work of construction of new District Court complex 

on Merces land would be completed by 31st  May, 2012. Action Taken 

Report was requested to be submitted by the Principal District Judge. 

Thereafter, there is a continuous correspondence made by the Principal 

District Judge with the Principal Chief Engineer. On 20th October, 2012, 

the Principal District Judge of North Goa, Panaji addressed a letter to 

the Law Secretary of the Government of Goa making a grievance about 

the failure to commence construction on the Merces land.

9 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:04 :::

Bombay

Hig

h Court

10 wp-8306.15

8. A   meeting   was   held   on   21st  March,   2013   between   the 

Hon'ble Chief Minister of Goa and the Hon'ble  Chief Justice in which it 

is   recorded   that   the  plans  of   the  District  Court   complex  have  been 

approved.   Minutes of the meeting annexed to the Petition record that 

the work would be commenced by the end of May 2013 and would be 

completed  by   the  end  of  May,  2014.    Thereafter,   there  were   letters 

addressed by the North Goa District Advocates' Association in the year 

2013   to   the   Hon'ble   the   Chief   Justice   making   various   grievances 

including a grievance that no progress has been made in construction of 

Court  building on Merces   land though  foundation stone was   laid   in 

November,   2009.   As   we   have   noted   above,   even   as   of   today,   the 

construction of the building has not commenced.   The situation which 

has arisen today is mainly due to the gross delay on the part of the 

Government of Goa in the matter of the commencing the construction 

of the Court Complex at Merces.   If construction of the Court complex 

would have been completed as per the assurances given from time to 

time,   the   situation   which   has   arisen   today   would   not   have   arisen. 

Therefore, we propose to issue appropriate directions to ensure that the 

new Court Complex on Merces land becomes functional within the time 

fixed by this Court.  

9. As far as the construction of the building of Merces land is 

10 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:04 :::

Bombay

Hig

h Court

11 wp-8306.15

concerned, we may make useful reference of the law laid down by this 

Court in the decision dated 7th & 13th August, 2015  in the case of New 

Bombay   Advocates   Welfare   Association   and   another   Vs.   State   of  

Maharashtra and others (PIL No.239 of 2010)  wherein this Court has 

held that it is the constitutional obligation of the State to construct the 

Court buildings and to provide all  basic  infrastructure therein to the 

citizens   so   that   the   citizens   are   in   a   position   to   exercise   their 

fundamental right of having access to expeditious  justice. This Court 

has held that financial constraints or administrative constraints  is no 

ground to delay the construction of Court buildings. In the present case, 

the   Government   of   Goa   has   completely   failed   to   perform   its 

constitutional obligation.  

10. It will be necessary to make a reference to statements on 

oath made by Shri  Prashant Goyal,  Law Secretary of  Government of 

Goa in paragraph Nos. 5 to 8, which read thus :­

“5. I say that the Hon'ble High Court of Bombay, at Bombay 

vide letter dated 21/7/2014, conveyed its approval of 

the  Revised  Plans  of   the  construction  of  new District 

and   Subordinate   Courts   Complex   of   North   Goa,   at 

Merces, Tiswadi­Goa to the Principal District & Sessions 

Judge,   North   Goa,   at   Panaji.   I   say   thereafter   the 

Principal District & Sessions Judge forwarded the said 

approval   of   the   Hon'ble   High   Court   of   Bombay,   at 

11 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:04 :::

Bombay

Hig

h Court

12 wp-8306.15

Bombay   to   the   office   of   the   Chief   Architect,   Public 

Works   Department   for   further   necessary   action   on 

05/08/2014. In the meanwhile, the Government of Goa 

has   accorded   approval   and   entrusted   the   work   of 

construction   of   new   District   and   Subordinate   Courts 

Complex of North Goa, at Merces, Tiswadi­Goa to the 

Goa State Infrastructure Development Corporation (for 

short GSIDC).

6. I   say   that  vide   letter  dated  13/3/2015,   the  Principal 

District & Sessions Judge addressed a letter to the Law 

Department, with a request to make a provision of an 

amount  of  Rs.70.00  crores   in   the  Budget.  Vide  order 

dated 11/6/2015, an amount of Rs.1,67,82,000/­ was 

sanctioned   to   GSIDC   towards   the   development   of 

infrastructure facilities, by the Law Department.

7. I say that I have been informed by the GSIDC that M/s. 

Shrikhande Consultants Pvt. Ltd., Vashi, Navi Mumbai, 

have been appointed as Consultants for construction of 

new District and Subordinate Courts Complex of North 

Goa, at Merces, Tiswadi­Goa after following the tender 

process.  I  say that the appointment of  the Consultant 

was   made   on   1/6/2015.   I   say   that   the   Power   Point 

Presentation of the Final Revised Plan has been given to 

the   Hon'ble   Chief   Justice   of   Hon'ble   High   Court   of 

Bombay on 20/08/2015. The Hon'ble Chief Justice has 

given further suggestions and recommendations.    The 

same needs to be incorporated and therefore it is likely 

to cause further delay in the tendering process.

12 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:04 :::

Bombay

Hig

h Court

13 wp-8306.15

8. I   say   that   the   work  of   preparation   of   estimates   and 

preparation of Tender is being carried out by the GSIDC 

and   as   informed   by   GSIDC,   shall   be   completed 

tentatively by 30/10/2015.  I say that as informed by 

GSIDC,   the   scrutiny   and   tendering   of   the   project 

after   obtaining   statutory   approvals   shall   be 

tentatively be done by 30/11/2015. The opening and 

finalization   of   Technical   and   Financial   bids   and 

issuance   of   work   order   shall   be   completed 

tentatively by 15/01/2016.   I  say that  the duration 

for   construction   of   new   District   and   Subordinate 

Courts Complex of North Goa, at Merces,  Tiswadi­

Goa is likely be 24 months from the date of issue of 

the Work Order.”

           (emphasis added)

11. Thus, the assurance is to complete the construction within 

two years from 15th January 2016. We accept the aforesaid statements. 

The   last   assurance   given   by   the   Government   was   to   complete   the 

construction   by   the   end   of   May   2014.   Hence,   not   only   that   the 

construction of the building will have to be completed on or before 15 th 

January 2018, the same will have to be completed in all respects by that 

date so  that   its  effective and actual  use can start   from 16 th  January 

2018. Thus, within this outer limit, all the internal work will have to be 

completed.  We propose   to  direct   the  Government  of  Goa   to   submit 

periodical reports on the progress of construction on Merces land after 

13 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:04 :::

Bombay

Hig

h Court

14 wp-8306.15

every three months along with the photographs. We propose to monitor 

the work to ensure that it is completed within the stipulated time. The 

total  outlay   for   the  construction  of   the  Complex  at  Merces   is  Rs.70 

Crores. We must note that any delay in completion of the construction 

will   put   enormous   burden   on   the   public   exchequer   as   the   rent   of 

approximately   Rs.5   Crores   per   year   is   payable     in   respect   of   the 

premises in the new building.

12.  Now, we come to the challenge to the decision to shift four 

Courts to the new building. There was a representation dated 11th May, 

2013 made by the North Goa District Advocates' Association containing 

several   grievances   including   the   one   of   the   failure   to   commence 

construction on the Merces plot. The opinion of the learned Principal 

District Judge on the said representation was sought by this Court.  By a 

letter dated 11th July, 2013 (Exhibit P­18), the learned Principal District 

Judge submitted the opinion to the Registrar of this Court.  In the said 

letter, the learned Principal District Judge stated that the Hon'ble the 

Chief Minister of Goa in his recent visit to the District Court at Panaji on 

15th  June,   2013   has   given   an   assurance   to   allot   an   area   of 

approximately around 900 square meters on the fourth and fifth floors 

of   the   said  new building  pending   construction  of   the  District  Court 

complex  on  Merces   land.   It   records   that   the  Hon'ble  Chief  Minister 

14 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:04 :::

Bombay

Hig

h Court

15 wp-8306.15

stated that the construction of the new building would be completed in 

three months. The Principal District Judge recorded an opinion that if 

the Government agrees to allot three floors of the said building, the four 

Courts presently working at Panaji can be shifted there and the Court of 

Ad­hoc District Judge which is presently housed at Velho building can 

be shifted to the Civil and Criminal Court building at Panaji. The letter 

records that the owner of the Velho building has written a letter that the 

lease of the Court premises in the said Velho building has expired and 

he does not desire to continue the lease.   There is a letter dated 8 th 

August,   2013   (Exhibit   P­19)   addressed   by   the   North   Goa   District 

Advocates' Association to the Principal District Judge of North Goa in 

which  there   is  a   reference   to   the  proposal  of   the  Hon'ble   the  Chief 

Minister of offering premises in the said new building at Patto Plaza.  In 

the said letter, a grievance is made that the Association has not been 

taken into confidence. The letter is signed by the third Petitioner herein 

in   his   capacity   of   the   President   of   the   said   Advocates'   Association. 

Hence,   it   can   be   said   that   the   Petitioners   were   aware   of   the   said 

suggestion on 8th August, 2013 which came from the Government.

13. At this stage, we must note that on 25th  February, 2013 a 

notice  of  Expression of   Interest   (Exhibit  P­38)  was  published by  the 

Government stating that to accommodate various Government Offices, 

15 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:04 :::

Bombay

Hig

h Court

16 wp-8306.15

the Government of Goa intends to acquire on hire purchase, a suitable 

office space admeasuring 6,000 to 7,000 square meters in a commercial 

zone in and around Panaji, Taleigao and Porvorim for a period of three 

years extendable to six years.   Expression of Interest was invited from 

the owners of the commercial premises. The order dated 18th December, 

2013 (Exhibit P­34) passed by the Government of Goa is annexed to the 

Petition   which shows that a  proposal  was received from M/s. Apex 

Computers and Engineering Services offering the said new building at 

the monthly rent of Rs.60,74,152.57 and in addition the premises on 

the fifth and seventh floor in building Kamat Towers in Patto Plaza were 

also offered. Thereafter, M/s. Apex Computers and Engineering Services 

submitted a revised offer by reducing the rent. The said order records 

that   the   concurrence  was   shown by   the  Finance  Department  of   the 

Government of Goa on 17th June, 2013 and 3rd December, 2013. By the 

said order, the Government accepted the bid submitted by M/s. Apex 

Computers   and   Engineering   Services.   We   have   stated   in   the   earlier 

paragraph that  the  Hon'ble  Chief  Minister   in  his  visit   to  the  District 

Court at Panaji on 15th June, 2013 assured to give two floors of the said 

new building to the Court. On that date, even the concurrence of the 

Finance   Ministry   to   the   proposal   of   M/s.   Apex   Computers   and 

Engineering Services was not received. In fact, the order of the State 

Government   accepting   the  bid  was  passed  on  18th  December,  2013. 

16 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:04 :::

Bombay

Hig

h Court

17 wp-8306.15

Apart from the bid of M/s. Apex Computers  there were two other bids 

received as mentioned in order dated 18th December, 2013. As early as 

on 15th June, 2013 the Hon'ble Chief Minister offered the said premises 

in the new building nearly six months before the decision was taken by 

the Government of Goa to accept the offer in respect of the said new 

building. The Lease was executed on 17th January, 2014 which provided 

that   the   monthly   rent   in   respect   of   the   new   building   will   be 

Rs.42,92,904.80   inclusive  of   taxes  with   annual   increase  of   3.5%.   It 

records   that   the   tenancy commenced with effect   from 1st  November, 

2013 (even before order dated 18th December, 2015 was passed). There 

is another interesting aspect. The order of allotment of the third to sixth 

floors in the said new building to the Civil and Criminal Courts was 

made by the General Administration Department of the Government of 

Goa on 18th November, 2013 (Exhibit P­20) even before the offer was 

accepted  by   the  Government.  The  possession   appears   to  have  been 

handed over  on 27th  November,  2013 by  M/s.  Apex  Computers  and 

Engineering Services (and not by Government of Goa) to the Principal 

District Judge at Goa (see Exhibit P­22). The correspondence made by 

the learned Principal District Judge, North Goa which is annexed to the 

Petition  does  not   state   that   the  possession  was   taken  over  with   the 

express   approval   of   this  Court.  Much   can  be   said   about   the  whole 

process undertaken by the Government of Goa. It is not necessary for us 

17 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:04 :::

Bombay

Hig

h Court

18 wp-8306.15

to deal with this aspect in any further as this action of the Government 

of Goa is not under challenge in this Petition.

14. The said order of allotment dated 18th November 2013 was 

communicated to the Registrar General of this Court by the Principal 

District Judge of North Goa in which it was stated that the steps were 

being taken to take possession of the said premises in the new building. 

The possession appears to have been handed over on 27 th  November, 

2013 by M/s. Apex Computers and Engineering Services to the Principal 

District Judge at Goa. A resolution (Exhibit P­23) was passed on 17 th 

December, 2013 by the second Petitioner strongly objecting to shifting 

of   any   of   the   Courts   at   Panaji   to   the   said   new   building.   On   31st 

December, 2013, the first Petitioner addressed a letter (Exhibit P­24) to 

the Principal District  Judge of  North Goa raising an objection to the 

shifting of   the  Court  premises   to   the  new building.  Similar   letter  of 

protest   was   addressed   by   the   second   Petitioner   Association   to   the 

learned Principal  District   Judge  of  North  Goa  on  3rd  January,  2014. 

Neither in the aforesaid Resolution nor in the said letter, the Petitioners 

have made a grievance that the new building is close to the dumping 

ground of  garbage.   It  appears   that  a  meeting was  convened by   the 

Principal District Judge of North Goa in the chamber on 10 th  January, 

2014 when the President of the first Petitioner was requested to attend 

the   meeting.   It   appears   that   there   was   one   more   meeting   in   the 

18 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:05 :::

Bombay

Hig

h Court

19 wp-8306.15

chamber  of   the   learned  Principal   District   Judge,   North   Goa  on   the 

subject of plans for erecting partitions and modification of the third to 

sixth  floors  of   the said new building.  The plans were approved and 

directions were issued to the Government Architect. On 21st May, 2014, 

the Principal District Judge of North Goa submitted an opinion (Exhibit 

P­36) to this Court that the premises in the new building are suitable for 

housing the four Courts. In the said opinion the learned Judge has not 

stated   that   the   garbage   dump   is   very   close   to   the   new   building. 

Thereafter,  by   letter  dated  15th  June,  2015  the   first  Petitioner  again 

recorded the protest with the learned Principal District Judge of North 

Goa. 

15. Thus, it appears that as of 17th December, 2013 the second 

Petitioner was aware of the decision taken to shift the Courts to the new 

building. As of 31st December, 2013 even the first Petitioner was aware 

of the said decision. Thereafter, steps were taken to carry out internal 

work in the four floors allotted in the new building. As stated earlier, 

the   possession   of   the   four   floors   was   already   handed   over   to   the 

Principal District Judge, North Goa on 27th November, 2013.  It is only 

when the notice was issued by the Principal District Judge on 24 th July, 

2015 of actual shifting of Courts that the Petitioners approached the 

Apex   Court   by   filing   a   Writ   Petition   under   the   Article   32   of   the 

19 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:05 :::

Bombay

Hig

h Court

20 wp-8306.15

Constitution of India. In the meanwhile, necessary internal work was 

carried   out   in   the   premises   in   the   said   new   building.   The   learned 

Advocate General of Goa claims that a sum of Rs.4 Crores was spent on 

the said work.  In the circumstances, there is a great deal of merit in the 

submission made by the learned Advocate General of Goa as well as the 

learned Senior Counsel for the High Court Administration on the issue 

of  delay.  Moreover,   the   four  Courts  will   be   shifted   to   the   said  new 

building only on temporary basis till the new Court complex at Merces 

is ready.

16. The main contention raised in the Petition as regards the 

nuisance and health hazard created by the garbage dump near the new 

building will have to be considered. On this aspect we must consider 

the affidavit of  Shri Levinson J. Martins, the Member Secretary of the 

Goa Pollution Control Board.  In paragraphs 10 and 11 of his affidavit, 

he has stated thus :­

“10. I respectfully state that in so far as the present matter is 

concerned, the Goa State Pollution Control Board has 

already issued directions to the CCP.  I  state that the 

GSPCB is also monitoring the situation continuously, 

so that the odour emanating therefrom is reduced, if 

not completely eliminated. I respectfully state that the 

Patto area has various establishments such as primarily 

Government   offices,   corporate   offices,   Labour   Court, 

20 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:05 :::

Bombay

Hig

h Court

21 wp-8306.15

tourism   complex,   bus   stand,   State   Information 

Commission under the RTI Act,  SBI offices of  various 

professionals such as lawyers etc, apart from State and 

Central   Government   offices   as   also   the   hotels/ 

restaurants   and   other   eateries.   In   this   view   of   the 

matter   the   GSPCB   continuously   monitor's.  I 

respectfully state that the GSPCB would also issue 

directions   to   the   CCP   to   handle   the   garbage 

composting   over   the   weekends   and   over   holidays 

wherein  the Courts  are not   functional  so  that   the 

odour which  is  emanating can be reduced.  I  state 

that this respondent has also issued directions to the 

city corporation to ensure that the odour emanating 

therefrom  is   controlled   if  necessary  by   setting  up 

and   engaging   certain   technology   including   odour 

control   technology which may be available  in  this 

regard. I state that presently the GSPCB has already 

issued directions to the city corporation to cover the 

waste   dump   which   is   laying   at   site   which   is   not 

visible from the adjoining buildings. Covering of the 

waste dump will also reduce the general pollution. 

11. I state that as of now until the alternate facility at Patto 

which is mentioned in the earlier part of the affidavit 

becomes   functional,   it   will   not   be   possible   to   issue 

directions   for   closure  of   the   facility  as   it   is   the  only 

available   facility   and   public   interest   requires   such 

facility to be functional.  I state that the CRZ authorities 

have indeed cleared the project where the other facility 

is bound to come up.  And therefore it would be in the 

21 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:05 :::

Bombay

Hig

h Court

22 wp-8306.15

interest of justice if the matter before the NGT is heard 

at the earliest and the order is vacated so that the plant 

could become operational at the said site.”

                                          (emphasis added)

17. What is stated in the said paragraphs shows that there is an 

issue of the odour emanating from the dumped garbage and therefore, 

the   affidavit   talks   about   taking   measures   to   reduce   the   emanating 

odour.  It also suggests that complete elimination thereof may not be 

easily possible. There is a direction issued to the Corporation of City of 

Panaji to cover the waste dump which is lying on the site so that is not 

visible from the adjoining buildings. The latest photographs produced 

by the Petitioners along with rejoinder show that a huge garbage dump 

is seen very close to the new building. There is an affidavit filed by the 

Commissioner of the Corporation of City of Panaji. Paragraph 8 of the 

said affidavit reads thus :­

“8. I   say   that   the  waste   brought   at   the  Municipal   Solid 

Waste Processing site of Respondent no.4 situated near 

SBI   building,   EDC   Patto,   Panaji,   Goa   presently   is 

between seven to 8 metric tones per day. I say that the 

said waste is treated as aforesaid at Municipal Solid 

Waste Processing site  of  Respondent  no.4 situated 

near SBI building, EDC Patto, Panaji, Goa however 

the same is in excess of the existing infrastructure 

Build at the said site.  I say that the Respondent no.4 

22 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:05 :::

Bombay

Hig

h Court

23 wp-8306.15

therefore   urgently   requires   the   proposed   site   in 

property bearing P.T. Sheet no.56, Chalta no.6 of City 

Survey of Panaji at the earliest to overcome the issues of 

waste processing within the jurisdiction of Respondent 

no.4,   however   the   Respondent   no.4   is   unable   to 

proceed with activities on account of the Order passed 

by National Green Tribunal (Western zone), Pune.”

                                           (emphasis added)

18. Thus,  it   is  an admitted position that the facility at  Patto 

Plaza receives solid wastes of  7 to 8 metric tones every day which is in 

excess of the capacity of the existing infrastructure build at the site.

19. The Petitioners have annexed several complaints made by 

the officers of the Government Departments like the Commissioner of 

Income­Tax, Passport Office as well as public sector undertakings like 

BSNL and LIC regarding the nuisance and health hazard caused due to 

dumping in the Patto Plaza area. The said offices are at Patto Plaza in 

the area of the said new Building. There are large number of newspaper 

reports on which reliance is placed.  The directions were required to be 

issued by   the  Goa  State  Pollution  Control  Board  on  28th  July,  2014 

under Section 5 of the Environment (Protection) Act, 1986 (for short 

“the said Act of 1986”) to the CCP regarding the dumping site. What is 

noted in the said direction are various deficiencies such as foul odour 

23 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:05 :::

Bombay

Hig

h Court

24 wp-8306.15

emanating from the site.  There are puddles of leachate/stagnant water 

in the area. There is no cover provided for the composting material. A 

copy of the   inspection report is also annexed to the said directions. 

Thereafter, there is a further direction issued by the Pollution Control 

Board on 12th January, 2015. It refers to the earlier direction issued on 

28th  July, 2014. It is based on inspection carried out on 23 rd  October, 

2014.  The   contents   of   the  observations  made  during   the   inspection 

carried out on 23rd October, 2014 read thus :­

“1.There   is   a   heap   of   composted   manual   stacked   at   the 

entrance of shed covered with sirpoline.

2. No covering   is  provided   for   the   composted  material 

and birds were observed on the heaps.

3. Slight foul odour was emitted at the site at the time of 

inspection.   A   copy   of   the   inspection   report   dated 

23/10/2014 is enclosed herewith.”

                         (emphasis added)

Thereafter, directions were issued which read thus :

“1. Provide   concrete   platforms   for   stacking   the   composting 

waste behind SBI Building, Patto, Panaji­Goa.

2. To provide drains to collect leachate generated behind SBI 

Building, Patto, Panaji­Goa, which should be connected to a 

leachate collection tank.”

24 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:05 :::

Bombay

Hig

h Court

25 wp-8306.15

20. Thus,   the   issue   raised   by   the   Petitioners   regarding   the 

pollution and nuisance created by the garbage dump and generation of 

foul odour is not without any basis. There is a substance in the said 

grievance. 

21. However, the four Courts will be shifted to the said new 

building only as a temporary arrangement and the same will be brought 

to the proposed new Court complex on Merces land.  Secondly, it is too 

late in the day to interfere with the decision of shifting four Courts for 

temporary period especially considering the finding recorded earlier on 

the aspect of gross delay in approaching the Court.  Thirdly, there is an 

assurance given by the Goa State Pollution Control Board in paragraph 

10 of the affidavit of its Member Secretary to take all necessary steps. 

Moreover, we are informed that all the four floors in the new building 

are air­conditioned. Inconvenience, if any, which is likely to be caused 

to the Members of the Bar and Litigants can be minimized by directing 

the Goa State Pollution Control Board to make frequent site visits and 

to   take   statutory   action   of   issuing   directions   and   ensuring   the 

compliance thereof. Moreover, if construction of the new Court complex 

is not completed within the time specified in the affidavit of the State 

Government, appropriate directions can be always issued in appropriate 

proceedings.  Hence,  we are of   the  view that  no  interference can be 

25 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:05 :::

Bombay

Hig

h Court

26 wp-8306.15

made mainly on the ground of delay and on the ground that the shifting 

of Courts will be on temporary basis only till January 2018. The other 

two factors are the steps assured to be taken by the Pollution Control 

Board and the fact that all the four floors are air­conditioned. 

22. We may record here that High Court Administration will 

have to consider whether  instead of shifting all   the four Courts  it   is 

possible to shift the record and muddemal to the new building so that 

instead  of   four  Courts,  only  one  or   two  Courts   can  be   shifted.  The 

question whether more space can be created in the existing building by 

shifting the muddemal and other articles will have to be considered by 

the High Court Administration.  From the photographs produced by the 

learned counsel for the High Court Administration it appears that the 

condition of the existing building is not at all bad.

23.           We propose to  issue a direction to submit periodical status 

reports on the construction of the Court Complex at Merces. We propose 

to grant liberty to the Petitioners to file a fresh Petition for the same 

relief in the event the Construction is not completed within the time 

stipulated by this Court and in the event the nuisance created by the 

garbage dump is not substantially abated till the expiry of the aforesaid 

period. 

26 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:05 :::

Bombay

Hig

h Court

27 wp-8306.15

24.  Hence, we pass following order:

ORDER

(I) The Petition is rejected with no order as to costs;

(II) We   direct   the   Government   of   Goa   to   complete   the 

Construction of the Court complex at merces in all respects 

till 15th January 2018. The Construction shall be completed 

in such a manner that the actual use of the Building can be 

commenced on 16st January, 2018 ;

(III) The Government of Goa shall submit quarterly reports to 

this Court on the progress made in the construction of the 

Court complex. Photographs shall be submitted along with 

the   report.   The   Government   shall   serve   copies   of   the 

reports to the Petitioners;

(IV) The  Goa  State  Pollution  Control  Board   shall   submit   the 

quarterly reports to this Court on the steps taken by it for 

reducing/preventing the nuisance created by the garbage 

dump. The Pollution Control Board shall serve copies of the 

reports to the Petitioners;

(V) The first of such reports shall  be filed before the end of 

January  2016;

27 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:05 :::

Bombay

Hig

h Court

28 wp-8306.15

(VI) If the Construction of the Court Complex on Merces land is 

not completed on or before 15th  January 2018 and if the 

nuisance caused by the garbage dump continues till then, it 

will   be   open   to   the   Petitioners   to   file   a   fresh   Petition 

seeking appropriate reliefs;

(VII) The  High   Court   Administration   to   consider  whether   the 

muddemal   and   other   record   can   be   shifted   to   the   new 

building  instead of  shifting  total   four  Courts   to   the new 

building so that more space can be created in the existing 

building to accommodate the Courts;

(VIII) For considering the compliance reports, the Petition shall 

be placed for directions on 2nd February 2016.

(A.R. JOSHI, J ) (A.S. OKA, J ) 

28 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:05 :::

Bombay

Hig

h Court

29 wp-8306.15

Mr. Gaurish Agni, Mr. Omkar Warange, Mr. David Rao i/by Mr. Ameya Sudhir Tamhane, for the Petitioners.

Mr. M.S. Karnik, for the Respondent Nos.1 and 3.

25. After   the   Judgment   is   pronounced,   the   learned   counsel 

appearing for the Petitioners invited our attention to the order of the 

Apex   Court   and   submitted   that   the   arrangement   provided   therein 

continued during   the  pendency  of   this  Petition.  He,   therefore,   seeks 

continuation of the same arrangement. The learned counsel appearing 

for the High Court Administration states that this Court may consider 

the prayer   in accordance with law after taking into consideration the 

stand taken by the High Court Administration. None appears for the 

Government of Goa and other parties.  

26. Considering   the  order  of   the  Apex  Court  as  well  as   the 

directions issued by this Court, we direct that the actual sittings of the 

Courts in the new building shall not be commenced for a period of three 

weeks from today.   We make it clear that in the meanwhile the High 

Court Administration is free to consider the aspect which is set out in 

Clause VII of the operative part of the Judgment.

(A.R. JOSHI, J ) (A.S. OKA, J ) 

Certified   to   be   true   and   correct   copy   of   the   original   signed Judgment/order.

29 of 29

::: Uploaded on - 08/09/2015 ::: Downloaded on - 29/07/2016 09:14:05 :::


Recommended