NuElCommitted to Nuclear &xcelenf" Point Beach Nuclear Plant
Operated by Nuclear Management Company, LLC
NRC 2003-0056
June 10, 2003
U.S. Nuclear Regulatory CommissionATTN: Document Control DeskWashington, DC 20555
DOCKET 50-301; LICENSE NO. DPR-27POINT BEACH NUCLEAR PLANT, UNIT 2SUBMITTAL OF THE AUXILIARY FEEDWATER ORIFICE ISSUE REGULATORYCONFERENCE SLIDE PRESENTATION
Ladies/Gentlemen:
On June 6, 2003, a regulatory conference was conducted between representatives of the NuclearManagement Company, LLC (NMC) and members of your Staff to discuss the AuxiliaryFeedwater Orifice Issue at Point Beach Nuclear Plant (PBNP). During the presentation, aquestion was raised regarding the installation date, shown on slide eight, of the "A" motor drivenauxiliary feedwater pump recirculation line orifice. A review perfonned following theconference determined that the date presented was incorrect and should have reflected aNovember 2000 installation date. This error did not impact the risk analysis discussed at theconference.
The attached slide presentation is provided for your use. Based on the error identified above,three slides; eight, twenty, and twenty-one have been corrected. Additionally, slide eight hasbeen clarified to reflect the "A" and "B" designation of the motor driven auxiliary feedwaterpumps.
If you have any questions, please contact Gordon P. Arent at 920/755-6518.
-F ort 6590 Nuclear Road * Two Rivers, Wisconsin 54241
Telephone: 920.755.2321
NRC 2003-0056June 10, 2003
cc: (w/o enclosure)Project Manager, Point Beach Nuclear Plant, NRR, USNRCRegional Administrator, Region 111, USNRCNRC Resident Inspector - Point Beach Nuclear PlantPSCW
Point Beach Nuclear PlantRegulatory Conference Concerning Auxiliary
Feedwater Orifice Issue
June 6, 20031
Agenda
Purpose/Obj ective
Overview
Root Cause Analyses
SignificanceDetermination
Closing Remarks
Mano Nazar
Fred Cayia
Fred Cayia
Mark Reddemann
Mano Nazar
2
i ;; : I i . .
I : - - i:0 AiME i
Purpose
) Provide Overview of Auxiliary FeedwaterSystem Orifice Issue
> Discuss Root Cause Evaluation of the AFWOrifice Issue
> Present Methodology and Conclusion of theNMC/Point Beach SignificanceDetermination Process for AFW OrificeIssue
3
Objective
> Present New Information and ConsiderationsConcerning Issue Significance
> Provide NMC's Position on theCharacterization of the Apparent Violation of10 CFR 50, Appendix B, Criterion III "DesignControl"
4
JDD
::llm::
Overview
5
Overview
Auxiliary Feedwater System
Fire Water Conn(4 total)
OverviewTimeline of AFW System Improvements
Feb. 1981GL 81-14 issued(AFW seismicqualifications)
March 1979
Accident
Sept 1986Added SR EQ level
transmitters for CST(TMI response)
May 1982NRCSER,
NUREG-0737Item ELL1.2,NRC accepts
"safety grade"status of AFWauto initiation
Aug 1984Added AFW
dischargeMOV coutrols
(FMIresponse)
1980
April 1993Installed air line
to allow ISTtesting of AFW
recirculationvalves
1991Added recirc flowinstruments and
larger recirc lines andorifices to increaserecirc flow to 70 &
100 GPM
July 1997Missile
protectedportions of
AFW suctionpiping
July 1997Added AFW
discbarge valvebackup nitrogensupply; installedcable separation
modifications
1990
Note: At time of licensing,AFW was not safety related
July 1981Added AFW supplyline flow indication(TMI response)
1985Added low suction
pressure trip(TMI respone-
W v a3II W. auU June 1988 pressure tripPoint Beach response tIp
Nov 1983 to IEB 88-04 r March 1999Added AFW (review of AFW Nov 1995 Modification to
inoperable alarm minimum flow) Added SW flush assure control(TMI response) identifies need for connection at AFW wire separation
greater recirculation pump suctions for AFW systemflow capability s
March 2003Proper(larger)orifices
installed onall AFW
recirc liues
I
Oct 1970Ul Licensed
Sept2002AFW
recirculationdesignated
safetyI function
Jan 2002
NRCinspection ofModifications/50.59
1970
I ;000: : S : 0: :
- : :: : '
I
Overview
Recirculation Line Orif ce
Discussion:> Orifice Modification Developed in 2000 to Reduce Recirculation
Line Cavitation
> Recirculation Line Orifices- Modification History
_______ _______ _______ ______ Pum p A Pum p B
Motor Driven AFW Pumps (MDAFP) June 2000 June 2000Modification issued
MDAFP Modification Installed November November2000 2000
Unit 1 Unit 2
Turbine Driven Auxiliary Feedwater Pump March 2002 December(TDAFP) Modification Issued 2001
TDAFP Modification Installed October May 20022002
OverviewRecirculation Line Orif ice
Description:
Potential for Fouling of Recirculation Line Coincident withProcedurally-Directed Operator Action to Secure AFW ForwardFlow.
> Identified by NMC Following System Testing of the Motor DrivenAFW Pump
> Orifice Plugging Could Occur When AFW Pumps Were Aligned toService Water Resulting in Potential Common Mode Failure
> Prompt Corrective Actions
* All Four AFW Pumps Declared Out-of-Service Due toPotential Recirculation Orifice Common Mode Failure
* Compensatory Actions Established to Direct Operators toSecure AFW Pumps in the Event Minimum Recirculation FlowCannot be Maintained
9
Root Cause Analyses
10
i = : ,
.... M ., I M ~~ .
- iE I - -- -- --- - --
Root Cause AnalysesUbJ hAFWRecirculation Orifice
> Root Cause-Orifice Issue (RCEOOO 191)
eFailure to Properly Evaluate the Potential forOrifice Plugging Within the Design Process
> Contributing Causes
*Use of Unverified Information and the Omissionof Key Design Information in the SafetyEvaluation for the Orifice Modification
11
Root Cause AnalysesAFWRecirculation Orifice
> Corrective Actions- Complete
* Increased Engineering Management Involvement inApproval and Oversight of Modifications
* Implemented Periodic Review of EngineeringProducts by a Quality Review Team
* Presented Lessons Learned to EngineeringPersonnel Stressing the Use of the Design Process
* Revised Training Materials to Accurately ReflectAFW Recirculation Line Design Functions
* Orifice Redesigned, Tested and Installed on allFour Pumps in March 2003
12
Root Cause Analyses
_~ AFWAir Operated Valve Finding
Missed Opportunitk (RCE 01-069)> The Root Cause Problem Statement Focused on Emergency
Operating Procedure (EOP) Limitations Related to a Loss ofInstrument air event.
> The Root Cause Problem Statement should have Focused on thePotential Loss of Recirculation Flow.
> The Extent of Condition Evaluation would then have InvestigatedConditions in Addition to a Failed Closed AFW AOVrecirculation valve.
> Examples of Possible Loss of Recirculation Failures would haveIncluded:
* Orifice Plugging* Electrical! Control System Failures
Indication Failures
13
I
ijr
Root Cause AnalysesComprehensive AFW Evaluation
> Root Cause-Comprehensive AFW Evaluation (RCE000202)
* Failure to Consider the Integration of AFW SystemDesign and Accident Progression (RC-1)
* Less than Adequate Knowledge of the SafetySignificance of the AFW Recirculation Line inProtecting the Pumps (RC-2)
> Contributing Causes
* Lack of Problem and Issue Ownership (CC- 1)
* Corrective Action Program Weaknesses
* Less than Adequate Engineering / Operations Interface(CC-2)
* Less than Adequate Management of the Inter-Relationship of Documents (CC-3)
14
Root Cause AnalysesComprehensive AFWEvaluation
> Prompt Corrective Actions- Complete* Placed Modifications Developed using "Old Process" on
Installation Hold Pending Accident Progression Review
* Implemented Multi-Discipline Review of ProposedModifications by Management Team
> Interim Corrective Actions- Complete
* Implemented New Fleet Modification Process
* Implemented Design Review Board* Assigned Issue Managers for Significant Station Issues* Conducted Detailed Review of AFW Design and Licensing
Bases (RC-2)* Implemented the Corrective Action Program Improvements
15
Root Cause AnalysesComprehensive AFW Evaluation
Additional Corrective Actions:
> Enhance Understanding of System Design and AccidentProgression (RC-1)
* Upgrade Modification Process and EOP/AOP change process
* Develop and conduct training for Engineering and Operations
> Resolve Remaining Issues from AFW Design and Licensing Bases(RC-2)
> Develop and Conduct Training on AFW Design Bases (RC-2)
> Strengthen the Role of Engineering in the Development/Revisionof Operations Procedures (CC-2)
> Upgrade Electronic Document Management System (CC-3)
> Continue Implementation of Corrective Action ProgramImprovements
16
;?
:::: :E : : f
:
- S 4 l I I R
i I I I i
Signif cance Determination
17
Signif icance DeterminationHistorical Timeline
Sept 2002AFW reclrcAOV open-
functiondesignated
safety related
Key:Recirculation Line OrificeRecirculation Line AOV
A
Nov 2000A&BMDAFW
pump anti-cavitation orifice
Installed
tL
Dec 2001U2 TD AFW pump
anti-cavitation orificemodification issued
May 2002U2 TD AFW pump
anti-cavitationorifice installed
I _- I I I : . 4 - . I : : I M 0 a : fl
2001June 2000
A & B MD AFW pumps'anti-cavitation orificemodMications Issued
Nov 2001*Identification
of recirc Hue AOVissue.
T2002
March 2002Ul TD AFW pump
anti-cavitation orificenodification issued
* Proceduresmodified tomonitor recircAOV position andlow instrument airheader pressurealarm to ensureminimum AFWflow
May/June 2(Instaled safirelated back
N2/air to aAFW recir
AOVs
L March 2003Replacement
Qarger)orifices
instaled On allAFW recrc
Ihles
+ 1 t 2003Oct 2002*UI TD AFW pumpanti-cavitation orificelnstalled
* Potental for orificepluggiug Identifiedwhile testing A MD
W02 AFW pump a fewety weeks laterupii * Procedures modifiedc to rely on forward
flow to ensure min 18flow
2000 4.
l
I
Signif icance DeterminationEvents Affected by Orif ces
Dual Unit Events> Loss of Offsite Power> Loss of Service Water> Loss of Instrument Air (Minor)
> Loss of DC Bus D02
Single Unit> Transient (Minor)> Transient without Heat Sink> Steam / Feed Line Break (Minor)> Loss of Component Cooling Water (Minor)
19
* AS ;;~~~~~~~~~~~~~~~~~~~~~~~~
i .
Significance DeterminationNMC
Orifice Risk Increase- Unit I *
Risk due to orificeplugging > I year
from identiication
Risk due toorifice plugging
mitigated byprocedurechanges
AZ __-- --
Nov 2000A&BMDAFW
2000
*Fraction of yearCDP affected by all3 AFW pumps forUnit 1= 0.06
Sept 2002Recirc AOV open-
function safetb relatedDec 2001
U2 TD AFW pumporifice mod issued
2001June 2000
A & B MD AFW pumps'orifice mods issued Nov 2001
*Identification
2002 March 2002Ul TD AFW pump
anti-cavitation orificemodification issued
of recirc line AOV May/June 2002Issue Installed AOV*Procedures backup N2/airmodified
March 2003New orifices
iustalled on allAFW recirc
lines
V 2003Oct 2002
- Ul TD AFWpump orificeinstalled
* Plugging Identified
* Procedures 20changed
CalculatedBase - -
Risk
I.--
... ,.,.,a ,
I
._________________t
Significance DeterminationNMC
Orifice Risk Increase-Unit
CalculatedBase - - -
Risk
2**
Risk due to orifice ;plugging > 1 year
from identification I
--- - - - - - - - - - - - - - -v
Risk due toorifice plugging
mitigated byprocedure
changes
Wilion 1/
/IA,_ _ _ _ _ _ _ __--
Nov 2000A& B MD AFW
pump orificeinsfd
June 2000A & B MD AFW pumps'
orifice mods issued
Sept 2002Recirc AOV open-
function safety related
Dec 2001U2 TD AFW pumporifice mod issued
2001
Nov 20*Identificatiaof recirc linIssue*Proceduresmodified
**Fraction of yearCDP affected by all3 AFW pumps forUnit 2= 0.472
May 2002U2 TD AFW pump
orifice installed
A
2002 March 2002
Ul TD AFW pumpantiavitation orifice
01 modification issued
e AOVI
May/June 2002Installed AOVbackup N2/air
March 2003New orifices
installed on allAFW recirc
lines
I~~
2003Oct 2002
* Ul TD AFWpump orificeInstalled
* Plugging identified
* Procedureschanged 21
2000
- -
-% I I I f - A ; - 1_ _,_ I Ai _ I '' 1
amioSL
Significance Determination- Event TimelinesEvents
Dual Unit Events
*Loss of Offsite Power, Lossof Instrument Air, Loss ofDC Bus D02, Loss of ServiceWater
Single Unit Events
-Transients without HeatSink
*Transient without Heat Sinkand No Water Treatment
-Small LOCA
-Steam Generator TubeRupture
-Main Steam Line Break(Inside Containment)
-Main Steam Line Break(Outside Containment)
Time to CST Low-Low Level
With Water TreatmentSystem Clearwell
4. 4.
1.6 Hrs
Not Required
2.1 Hrs
5.1 Hrs(0.5" Break Only)
3 Hrs
3.3 Hrs
1.6 Hrs
System Not Available
Not Required
System Not Available
Not Required
9.7 Hrs
12 Hrs
Not Required
Time to InitiateFeed & Bleed(If Required)
4.8 Hrs
Not Required
5.5 Hrs
Not Applicable
Not Applicable
15 Hrs
Not Required
Notes
Normal CST MakeupAvailable
Three break sizes, with andwithout safety injection. Onlysmallest break reaches CSTLow-Low Level
RHR conditions reached onCST inventory at -2.2 hrs-prior to reaching SG levelrequiring feed & bleed.
22
Signif icance DeterminationDiferences for Plugged Orif ice
> AFW Swap-Over Occurs Hours After Reactor Trip
*Decay Heat Lower
*Charging Successful for Feed and Bleed
*Shutdown Cooling Credited
* Steam Generator Depressurization and ServiceWater /Fire Water Addition Possible
*Emergency Response Facilities Staffed
*More Time for Troubleshooting and Recovery
23
Significance DeterminationNRC
9 Preliminary Evaluation of Risk Increase Basedon Phase 2 Analysis
> Assumed AFW Failure Probability of 1.0
> No Credit for:
* Initial Cooling by AFW
* Charging Feed and Bleed
* Transition to Shutdown Cooling
* Service / Fire Water Addition
24
Signif icance Determination
NMC
> Internal Events Evaluated Probabilistic RiskAssessment
* MAAP (Modular Accident Analysis Program)used to Demonstrate Success and DetermineTimeline of Recovery Actions
* Human Reliability Analysis for CreditedRecovery Actions
> Seismic Events Evaluated using Seismic PRA
> Fire Event Analysis in Progress
25
Significance DeterminationNMC Risk Mitigating Factors
Incorporated
> Water Treatment System
* Makeup to Condensate Storage Tank
* Clearwell Tank Makeup to CST
* Recovery Following Restoration of Off-Site Power
> Service/Fire Water through Disabled AFW Pump
> Charging for Feed and Bleed
26
Signif icance DeterminationNMC Risk Mitigating Factors
Incorporated (cont'd)
> Changes to HEPs for Feed and Bleed
> Recovery of SI/ RHR
Incorrect Position
; Operators Starting/Stopping AFW Pumps
to Avoid Failure of 2nd andlor 3 rd Pump
27
Valves Left in
. , 11
m
Significance DeterminationNMC Risk Mlitigating Factors Not
Incorporated
> Available 14,000 Gallons of Water Left in EachCST at Low Low Level
> Increase Charging to Maximum While in Loss ofHeat Sink Procedure
> Likely AFW Pump Survival Time FollowingSwap-Over to Service Water
* Valve Leakage* Packing Leakage
> Alignment of N 2 to Pressurizer PORVs FollowingLoss of IA
28
Signif icance DeterminationLargest Contributors to Risk
Largest Contributors Recovery Credited
Initiator Water Service I Charging ShutdownTreatment Fire Water Feed & Cooling
Bleed
Loss of Offsite Power- x x x xDual and Single Unit
Transient w/o Heat Sink x x x
Loss of DC Bus 2 x x x
Loss of SW x
29
tI
i
o
Significance DeterminationSensitivity Analysis
30
Factor Contribution to CDPReduction (%)
Water Treatment System Impacts 91
Service Water/Fire Water through AFW Pump 48
Feed and Bleed HEP Change 48
Charging for Feed and Bleed 19
SI / RHR Valve Recovery HEP 10
Start / Stop AFWPs 5
Signif icance DeterminationResults
Internal Events> Increase in Internal Events Core Damage
Probability* Unit 1: High White* Unit 2: Mid Yellow
31
Significance DeterminationResults
External Events- Seismic
) Fragility Analysis Performed
> Charging, CST, and Service Water AdditionCredited Following Safe Shutdown Earthquake
> Increase in Seismic Initiated Core DamageProbability
* Unit 1: Green
* Unit 2: Green
32
Signif icance DeterminationResults
Increase in Internal Event and Seismic Initiated CoreDamage Probability>Unit 1: High White
>Unit 2: Mid Yellow
33
:: . .I = -t: 00 0 > D. f.
Significance DeterminationResults
External Events- Fire>Fire PRA Model Not Developed>Development is in Progress>Method Includes:
* Fire Initiation Frequency* Detection Probability* Automatic and Manual Suppression Probability* Identification of Cables and Determination of
Equipment Affected* Credit for Mitigating Factors* Consequences of Unsuppressed Fires
>Completion Targeted in August
34
Summary
> Installation of Inappropriate Orifice Design was RiskSignificant
> NMC Significance Determination Preliminary Results(Internal and Seismic)
* Unit 1: High White* Unit 2: Mid Yellow* Final Results, Including Fire, Targeted in August 2003
> Further AFW System Modifications* Electrical Modifications in Progress* Margin Recover Study
> Engineering Excellence Plan
35
Closing Remarks
> AFW Orifice Issue Self-Identified and Resolved inTimely Manner.
> AFW System Today is more Reliable.> NMC Understands the Importance of the AFW
Orifice Issue.
> NMC Significance Determination PreliminaryResults (Internal and Seismic)
* Unit 1: High White• Unit 2: Mid Yellow
> SDP for Fire Events Remains a Work in Progress.> NMC Concurs with the Characterization of the
Apparent Violation of 10 CFR 50 Appendix B.36