+ All Categories
Home > Documents > Policy and Value: A Case Study of Local Authority Energy Management and Investment

Policy and Value: A Case Study of Local Authority Energy Management and Investment

Date post: 07-Mar-2016
Category:
Upload: paul-price
View: 218 times
Download: 4 times
Share this document with a friend
Description:
A mixed methods study based on an Energy Management Matrix qualitative methodology of assessment studying the current local authority energy management and retrofit investment in contrast with accepted good practice. A focus is the stated policy versus the likely value and coherence of government policy.
160
Policy and Value: A Case Study of Local Authority Energy Management and Retrofit Investment Appraisal Paul Price Dissertation submitted for the award of MSc. Sustainable Development Dublin Institute of Technology October 2012 Volume 1 of 2
Transcript
Page 1: Policy and Value: A Case Study of Local Authority Energy Management and Investment

Policy and Value: A Case Study of

Local Authority Energy Management

and Retrofit Investment Appraisal

Paul Price

Dissertation submitted for the award of

MSc. Sustainable Development

Dublin Institute of Technology

October 2012

Volume 1 of 2

Page 2: Policy and Value: A Case Study of Local Authority Energy Management and Investment

ABSTRACT

Saving energy, reducing carbon emissions and cutting costs through improved

energy management and retrofit investment are significant national and local policy

aims, with the public sector being given an exemplar role. Is implementation of these

policies consistent with good practice in energy management and retrofit investment?

A survey of Dublin City Council (DCC) leisure centres indicated a lack of

essential building energy management metrics and reporting structures, compounded by

very poor data quality from energy suppliers. A document analysis, of a government

grant scheme application process, showed inconsistencies with accepted investment

appraisal criteria. In-depth interviews were then carried out with fourteen informed

respondents in Co. Dublin guided by an 'energy management matrix' (EMM) method of

qualitative assessment, as used by SEAI and the EPA. This research framework also

guided coding and commenting of the transcribed interview data, assisting in its

analysis and interpretation. The indicative results of this exploratory research were that

policy implementation is only weakly consistent with EMM-defined good practice.

Current policy targets appear to lack meaning due to poorly defined baselines,

poor data gathering, an absence of energy reporting and a lack of operational level,

results-driven programmes. A more dominant policy of cost cutting and capital

rationing appears to be undermining value – limiting cost-optimal and robust local

decision-making. Energy accounting was reported as being seriously impeded by poor

billing from energy suppliers. In contrast, but within DCC, the Dublin Fire Brigade

Green Plan, with core principles of behavioural change and carbon saving, has achieved

significant results by linking operational and management commitment with technical

and investment expertise. This research suggests it is a good-practice, robust alternative

model, sustaining local services whilst also saving carbon emissions, energy and money.

Page 3: Policy and Value: A Case Study of Local Authority Energy Management and Investment

Declaration

I certify that this thesis which I now submit for examination for the award of an

MSc. in Sustainable Development is entirely my own work and has not been taken from

the work of others save and to the extent that such work has been cited and

acknowledged within the text of my work.

This thesis was prepared according to the regulations for postgraduate study by

research of the Dublin Institute of Technology and has not been submitted in whole or

in part for an award in any other Institute or University.

The work reported on in this thesis conforms to the principles and requirements of

the Institute's guidelines for ethics in research.

The Institute has permission to keep, to lend or to copy this thesis in whole or in

part, on condition that any such use of the material of the thesis be duly acknowledged.

Signature

______________________________ ______________

Candidate Date

Page 4: Policy and Value: A Case Study of Local Authority Energy Management and Investment

Acknowledgements

I would like to thank my supervisor Dr. Alan Gilmer for his most valuable

guidance and encouragement during the year.

My family, friends and classmates were very helpful, providing support, advice

and comments, I am very grateful. Thanks to Jim Scheer for the much appreciated

suggestions and corrections. Thanks too, to Robert Wyse for the read-through

comments and the solve-the-world summits at the café.

Additionally, I would like to thank all of those who made themselves available for

interview. Particular thanks are due to the staff at Codema, the City of Dublin Energy

Management Agency, for their assistance with my many questions.

Any errors of reporting or interpretation that remain in this work are of course my

own and in no way reflect on the work or views of those who gave their assistance to

this research project.

Dedication

Above all, my thanks go to Lizzie McDonnell, energy management expert and

intrepid wild swimmer, for the unwavering encouragement, diligent editing and all

round effort that made this year of study possible and enjoyable.

Page 5: Policy and Value: A Case Study of Local Authority Energy Management and Investment

i

TABLE OF CONTENTS

CHAPTER 1 INTRODUCTION 1  

1.1 Policy and Governance Context 1  

1.2 Research Context 2  

1.3 Research Question 4  

1.4 Research Framework Methodology, Aim and Objectives 4  

CHAPTER 2 LITERATURE REVIEW 5  

2.1 Sustainability in Energy and Carbon Emissions Policy 5  

2.2 Energy Management 6  

2.2.1 Building Energy Management Capacity 6  

2.2.2 Responsibility for Energy Management 8  

2.2.3 Assessing Quality in Energy Management – The EMM 10  

2.2.4 Energy Management Standards and Indicators 12  

2.2.5 Energy Accounting: Linking Cost, Consumption and Carbon 12  

2.2.6 Energy Performance Certification of Buildings 13  

2.3 Energy Saving and Retrofit Investment Decision-making 14  

2.3.1 Saving Energy: Energy Conservation and Energy Efficiency 14  

2.3.2 Funding Energy Efficiency and Retrofit Measures 15  

2.3.3 Cost optimal Retrofit and Lifecycle Costing 17  

2.3.4 Building retrofit: Active versus Passive Measures, and Co-benefits 19  

2.3.5 Investment Data Quality and Relevance in Appraisal 20  

2.3.6 Investment Appraisal Methods and Considerations 21  

2.3.7 Lifecycle Investment: Global Risks and Local Implications 23  

2.4 Energy Policy and Local Authority Implementation 24  

2.4.1 Energy and Carbon Emission Policies and Targets 24  

2.4.2 National and Local Governance in Ireland 29  

2.4.3 Dublin City Council Energy Usage 30  

2.4.4 Funding Local Authority Retrofit 31  

2.5 The DCC and DFB Green Plan 33  

2.6 Literature Review Conclusion 34  

CHAPTER 3 RESEARCH METHODOLOGY 35  

3.1 Research Methodology Outline 35  

Page 6: Policy and Value: A Case Study of Local Authority Energy Management and Investment

ii

3.2 Research Strategy 35  

3.3 Research Methods 36  

3.3.1 Methodology for Leisure Centre Surveys 36  

3.3.2 Methodology for Document Analysis 38  

3.3.3 Methodology for In-depth Interviews 42  

3.4 Limitations to the Research Strategy and Methods 48  

CHAPTER 4 LEISURE CENTRE SURVEY 49  

4.1 Observations and Findings: Leisure Centre Survey Report 49  

4.2 Leisure Centre Area and Billing Data 52  

4.3 Leisure Centre Energy Data Analysis 53  

CHAPTER 5 DOCUMENT ANALYSIS 56  

5.1 Findings: Analysis of Documents 56  

5.1.1 Description of Application Form 56  

5.1.2 Findings: Application Guide 58  

5.2 Findings: Assess Proposal Data Quality and Relevance 60  

5.3 Analysis: Comparing Appraisal Method Alternatives 61  

CHAPTER 6 IN-DEPTH INTERVIEWS 67  

6.1 Interview Findings: Data Location and Citation Format 67  

6.2 Interview Findings: By Coded EMM category 67  

6.2.1 Energy Policy (EP) 67  

6.2.2 Energy Management Structure (MS) 69  

6.2.3 Implementation and Motivation (IM) 72  

6.2.4 Investment and Cost Analysis (CA) 82  

6.2.5 Monitoring and Targeting (MT) 93  

6.2.6 Data Provided by Energy Suppliers (PD) 98  

6.2.7 Outcomes from Past Policy Implementation (OC) 100  

6.3 Codings: Counts and Average Attainment Levels 107  

CHAPTER 7 DISCUSSION 108  

7.1 Leisure Centre Surveys 108  

7.1.1 Survey Observations Discussion 108  

7.1.2 Data Analysis and DEC Ratings 109  

7.1.3 Survey Conclusions 110  

Page 7: Policy and Value: A Case Study of Local Authority Energy Management and Investment

iii

7.1.4 Limitations of the Leisure Centre Survey 112  

7.2 Document Analysis 112  

7.2.1 Appropriate Investment Appraisal 112  

7.2.2 Timescale, Data Accuracy and Relevance 113  

7.2.3 Comparing Appraisal Methods 115  

7.2.4 Limitations of the Document Analysis 116  

7.3 In-Depth Interviews 117  

7.3.1 Coding Analysis and Interview Limitations 117  

7.3.2 Interview Discussion by EMM Category 118  

8.1 Conclusions and Recommendations 134  

8.1.1 Energy Policy 134  

8.1.2 Management Structure 135  

8.1.3 Implementation and Motivation 135  

8.1.4 Cost Analysis and Investment 136  

8.1.5 Monitoring and Targeting 137  

8.1.6 Provider Data from Energy Suppliers 137  

8.1.7 Outcomes 138  

8.2 Recommendations for further research 139  

REFERENCES 140  

Page 8: Policy and Value: A Case Study of Local Authority Energy Management and Investment

iv

VOLUME 2: APPENDICES

LIST OF APPENDICES

A. Interview Codings and Comments: Method, Sorting and Details

B. Interview Data, Comments and Codings

C. Green Plan: Kilbarrack Fire Station. Initial Results Summary

D. Leisure Centre Report: Cover and Conclusions

E. Spreadsheet Calculator Developed for Assessment and Presentation of Retrofit

Measures. Example for Lighting Retrofit of Ballymun Leisure Centre Car Park

F. Therm Model Views Assessing Fabric Thermal Performance:

Existing and Possible Retrofits of Coolock and Crumlin Swimming Pools

G. Better Energy Workplaces 2012: Document Analysis

H. Alternative SBEM Calculations for Crumlin Swimming Pool by Codema and

Temborias (2012)

I. Spreadsheet used in Comparison of Appraisals

J. Work in Progress Presentation: Methodology and Results

K. Dublin City Council Leisure Centres: Photographs

List of Events Attended to Support the Dissertation Research

Page 9: Policy and Value: A Case Study of Local Authority Energy Management and Investment

v

LIST OF TABLES

Table 2.1 The Energy Management Matrix 11

Table 2.2 Financial and Energy Accounting Attainment Levels 13

Table 2.3 DCC Energy Costs 2010 and 2011 30

Table 3.1 Appraisal Methods, Definitions and Acceptance 41

Table 4.1 Leisure Centre Energy Data, Measured Area and DEC Rating 52

Table 5.1 Collated Sub-Project Descriptions and Data. 58

Table 5.2 Data Used in Appraisal Comparisons. 62

Table 6.1 Attainment Levels for EMM categories and Governance levels 107

LIST OF FIGURES

Figure 2.1 Retrofit Decision-Making: Saving vs. Penalty for Doing Nothing 19

Figure 3.1 Interview Topics Derived from EMM categories. 45

Figure 3.2 Coding Frame for Interview Data Derived from Typical EMM 47

Figure 4.1 Total Energy Usage of DCC Leisure Centres 54

Figure 4.2 Energy Utilisation Index for DCC Leisure Centres 54

Figure 4.3 2010 and 2011 Total Energy Cost versus Energy Cost Index 55

Figure 5.1 Excerpt from BEW Application Showing Sub-Project 1 Details 57

Figure 5.2 Simple Payback in Years for the 16 Projects 62

Figure 5.3 Net Present Values for the 16 Projects 63

Figure 5.4 Profitability Indexes for the 16 Projects 63

Figure 5.5 Profitability Index versus Net Present Value for the 16 projects 64

Figure 5.6 Energy Cost after Retrofit Compared to Present Cost 64

Figure 5.7 Danish Appraisal Method Profitability Index 65

Figure 5.8 Comparison of Rankings by Different Appraisal Methods 66

Page 10: Policy and Value: A Case Study of Local Authority Energy Management and Investment

vi

LIST OF ACRONYMS

BCR Benefit to Cost Ratio

BER Building Energy Rating, an asset based EPC.

BEW Better Energy Workplaces: A government-funded grant scheme

BMS Building Management System

CBA Cost Benefit Analysis

CHP Combined Heat and Power

CIBSE Chartered Institution of Building Services Engineers

CO2 Carbon dioxide

CO2e Carbon dioxide equivalent

Codema City of Dublin Energy Management Agency

DCC Dublin City Council

DEC Display Energy Certificate, an operational EPC

DCF Discounted Cash Flow, accounting for the time value of money

DLRCC Dún Laoghaire Rathdown County Council

DCENR Department of Communications, Energy and Natural Resources

DECLG Department of Environment, Communities and Local Government

ECER Effective Cost of Energy after Retrofit

EMM Energy Management Matrix

EPBD Energy Performance of Buildings Directive 2002/91/EC

EPBD-R Recast Energy Performance of Buildings Directive 2010/31/EU

Page 11: Policy and Value: A Case Study of Local Authority Energy Management and Investment

vii

EPA Environmental Protection Agency

EPC Energy Performance Certificate or Energy Performance Contract

ESCo Energy Saving Company

ESD Energy Services Directive

ETS Emissions Trading Scheme

EU European Union

kW kilowatt, measure of power being used

kWh kilowatt hour, measure of energy used

FCC Fingal County Council

GHG Greenhouse Gas

GPRN Gas Point Reference Number

GWh gigawatt hour

IPMVP International Performance Measurement and Verification Protocol

LCA Life Cycle Analysis

LCC Life Cycle Costing

M&V Measurement and Verification

MPRN Meter Point Reference Number

MS Member State of the European Union

MWh megawatt hour

NEAP Non-domestic Energy Assessment Procedure

NEEAP National Energy Efficiency Action Plan

Page 12: Policy and Value: A Case Study of Local Authority Energy Management and Investment

viii

NPV Net Present Value

O&M Operations and Maintenance

OPW Office of Public Works

pc personal communication

PE Primary Energy

PPP Public Private Partnership

PV Photovoltaic

SBEM Simplified Building Energy Model used for NEAP assessments

SDCC South Dublin County Council

SEAI Sustainable Energy Authority of Ireland

SEAP Sustainable Energy Action Plan

NOTES

1. 'Carbon emissions': The predominant greenhouse gas (GHG) is carbon dioxide.

Often both CO2 and GHGs are described as 'carbon emissions'. Total amounts

of 'carbon emissions' or GHGs emitted are most commonly stated as carbon

dioxide equivalent (CO2e) to include all GHGs.

2. Carbon vs carbon dioxide: The mass of carbon emitted is related to, but not the

same as carbon dioxide emitted. 1 tC = 3.67 tCO2.

3. Power and energy are not the same. Energy use is the capacity to do work,

commonly measured in joules (a very small amount of energy), or in kWh,

MWh etc, for larger amounts. Power is the rate of energy being used at any one

instant in time as measured in W, kW, MW, GW etc.

Page 13: Policy and Value: A Case Study of Local Authority Energy Management and Investment

1

CHAPTER 1 INTRODUCTION

1.1 Policy and Governance Context

Until recently, for large energy users like the public sector, energy costs were

relatively minor compared to other overheads and there were few questions regarding

future availability or the environmental consequences of energy use (Russell, 2010:78).

These factors are now changing rapidly for all energy users, including the public sector

in Ireland that has an energy bill of approximately €500 million every year, of which

local authorities spend more than a fifth (SEAI, 2012d).

National policy, in line with EU directives, sets out clear headline targets: a

legally binding requirement to reduce total carbon emissions by 20% by 2020 relative to

1990 levels and a non-binding aim of decreasing energy use by 20% by 2020 (da Graça

Carvalho, 2012). The National Energy Efficiency Action Plan (NEEAP) stresses the

need for increased energy efficiency in buildings, through good energy management and

extensive retrofit, and directs the public sector to play an exemplar role with a target of

reducing its energy use by 33%. Both Dublin City and South Dublin County Council

have also signed the Covenant of Mayors in 2009 committing them to an overall

reduction of 20% in carbon emissions by 2020.

Over the past five years, energy costs have increased rapidly, there are now

multiple possible suppliers increasing complexity for purchasers, and many doubts are

expressed over the future certain continuity of supply as well as the potential for serious

price shocks ahead. Passing the point of global geologic peak oil production in 2006

(IEA, 2011b) is unlikely to reduce carbon emissions significantly (Verbruggen and Al

Marchohi, 2010), but does means that energy prices are likely to rise rapidly in the

Page 14: Policy and Value: A Case Study of Local Authority Energy Management and Investment

2

medium term (Benes et al., 2012) though large fluctuations are likely, potentially

presenting serious economic problems (de Almeida and Silva, 2009).

The burning of fossil fuels for energy, thereby producing greenhouse gases

contributing to global warming (IPCC, 2007; Metz, 2010:27) has also become a major

concern for many citizens and governments.

Decisions regarding the energy management and retrofit investment of existing

public buildings and social housing are critical in affecting short, medium and long term

costs in money, energy and carbon emissions. Economic, social and environmental

sustainability and security must increasingly be seen in combination if effective policy

is to result in cost-effective and risk-robust decision-making. For all of these reasons,

addressing current and future energy usage in buildings, lighting and water services is

becoming increasingly important to local authorities. Following the financial crisis, the

increasing cost of energy, combined with budgetary constraints, may mean the

difference between maintaining and losing services. This is likely to mean balancing

short-term savings with well-directed investment, to ensure long-term value by making

resilient as well as cost-optimal decisions.

1.2 Research Context

This research examines government commitment to stated energy policy in the

public sector, and the progress being made in fulfilling its exemplary role, by

undertaking a qualitative assessment of energy management and retrofit investment

practices in Dublin local authorities, and those of national funding departments and

agencies as they affect the local authorities.

What are current energy management practices within local authorities and are

they consistent with minimising future operational costs in public buildings and

Page 15: Policy and Value: A Case Study of Local Authority Energy Management and Investment

3

housing, as intended by energy and emissions reduction policies? The only published

research appears to be the 2011 CCMA Local Authority Energy Management Survey

(SEAI, 2011c), a basic questionnaire survey, and Energy Use in the Public Sector

(SEAI, 2012h), both published in Summer 2012, as this research was completed. The

2008 Climate Change Strategy for Dublin City (DCC/Codema, 2008) and the 2010

Dublin City Sustainable Energy Action Plan (DCC/Codema, 2010b) describe past

energy usage and emissions, proposed actions and targets, and future scenarios, but do

not describe existing practices and attitudes to energy management as they relate to

policy implementation. No detailed specific literature on Dublin or Irish local authority

energy management and retrofit planning was found in literature searches.

Literature on good practice for assessing large, private sector, energy users'

energy management performance is readily found (see Section 2.4 and 2.6). A common

method used in Europe and North America is the qualitative assessment based on an

energy management matrix (EMM) approach. A variant of this is EMM auditing used

by the Environmental Protection Agency for Integrated Pollution Prevention Control

energy efficiency auditing, also recommended by SEAI for use in the Large Industry

Energy Network (LIEN) programme (EPA, 2003; Wajer, 2005). As large local

authorities are significant energy users it was deemed appropriate to use this as a

framework in assessing current, local authority energy management practice. An EMM

was therefore the basic framework guiding the methodology and analysis for this

research.

Page 16: Policy and Value: A Case Study of Local Authority Energy Management and Investment

4

1.3 Research Question

The question that this research seeks to address is:

Are national energy saving and carbon emissions reduction policies for the public

sector, and their implementation by local authorities in Dublin, consistent with good

practice in energy management and retrofit investment decision-making?

1.4 Research Framework Methodology, Aim and Objectives

This original, exploratory research made use of the existing, qualitative Energy

Management Matrix auditing technique as a guiding framework for the assessment of

current, local authority level energy management, particularly in regard to public

buildings and social housing.

Following a review of literature, detailing good practice in energy management

and retrofit investment, the research aim was to gather data that would qualitatively

gauge:

• how local authorities are undertaking energy management;

• how retrofit investment in local authority buildings and housing is appraised; and,

• how local authorities are being supported and directed by central government to

meet the energy and emissions targets of stated policies.

Page 17: Policy and Value: A Case Study of Local Authority Energy Management and Investment

5

CHAPTER 2 LITERATURE REVIEW

2.1 Sustainability in Energy and Carbon Emissions Policy

The future of public goods, such as water supply, public lighting and buildings

(leisure centres, libraries and fire stations), and the easing of fuel poverty are reliant on

national and local government decisions prioritising long-term value in the face of

short-term pressures and longer term uncertainty (Lane, 2011; see also local

implications in, Trainer, 1999:52-58). These objectives echo the Our Common Future,

the 'Brundtland Report' of (UN-WCED, 1997), which identified maintaining

intergenerational equity in access to resources and progress toward the elimination of

poverty as key aims of sustainable development. The report also stated the need for

affluent societies and citizens to make choices toward reducing their demands on

ecological supports including energy, to avoid an "interlocking crisis" of economics,

society and the environment, particularly due to global warming, increasing world

population and the end of an era of cheap energy (Para. 27-30).

Today these risks are becoming more apparent, yet only weak policy changes

have been made (IEA, 2011b; IIASA, 2012) and the European and Irish economies

continue to depend on energy inputs from imported fossil fuels with large resultant

greenhouse gas emissions (IEA, 2008; SEAI, 2011b). In spite of the Kyoto agreement

and European emissions regulations, which only address domestic emissions,

effectively no progress had been made at all in reducing global climate emissions,

largely because of a lack of political will to reduce consumption, particularly from

OECD governments and voters (Helm, 2008). Towards a New National Climate Policy

(NESC, 2012), the National Climate Policy Review 2011 (DECLG, 2011:18) and the

Our Sustainable Future (DECLG, 2012b:27) indicate that maintaining the status-quo is

Page 18: Policy and Value: A Case Study of Local Authority Energy Management and Investment

6

not an option. However, these documents generally fail to acknowledge the

increasingly inconvenient evidence of climate change (Anderson and Bows, 2010; New

et al., 2010; Huntingford et al., 2012) thereby degrading the quality and value of

national policy and long-term decision-making in Ireland.

Currently, energy and emissions are effectively only rationed by cost, even though

a sufficiency strategy of carbon budgeting (Alcott, 2008; Brand and Boardman, 2008)

may ultimately be the only effective way to limit total carbon emissions to avoid

dangerous climate change, though time is now running out rapidly (Anderson, 2011;

ICC, 2009).

2.2 Energy Management

Energy management is "the judicious and effective use of energy" requiring a

whole systems viewpoint to optimise and examine all current and planned energy usage

(Capehart et al., 2005:1).

2.2.1 Building Energy Management Capacity

The linkage of costly energy use and resultant carbon emissions with economic

wealth, societal health, energy security, and climate change, given the increasingly high

potential for future shocks, provides a strong impetus for considering future energy

usage carefully (ibid.:3-5). Energy costs rose dramatically in the 1970s and there was a

corresponding increase in energy management, but this fell away in the 1990s and early

2000s such that many organisations now lack capacity to make financially, or

technically, well-informed energy decisions (Fawkes, 2007:41).

With prices rising rapidly in recent years and, generally, likely to continue rising

(Fig 11, Benes et al., 2012), especially relative to public sector funding, energy users

such as local authorities have three possible responses: do nothing; carry out only cost

Page 19: Policy and Value: A Case Study of Local Authority Energy Management and Investment

7

saving proposals; or respond with strategic energy management by aiming to minimise

overall energy cost and exposure to risk during the next decades (Fawkes, 2007:3). As

cost saving, resilience and policy demand, this requires organisational and societal

change to reinvest effort and funding into energy management (Beggs, 2009:3-4), and to

overcome ‘behavioural lock-in’ in energy consumption habits (Maréchal, 2010;

Jackson, 2005:133).

Montier (2009 Ch. 14;) details research indicating that value investors must have

long-term time horizons, but behavioural economics suggests that decision-makers

commonly suffer from serious loss aversion and a bias toward short-term rewards,

discouraging longer term investments that are most likely to produce long term value,

even if otherwise persuasive information is presented. These behaviours apply

particularly with respect to policy decision-making in the face of climate change

(McNall, 2010). In the UK, local authorities believe that the short-term budget cycles

required of them by central government inhibit long-term decision-making (Lorenzoni,

2000:181, cited by Urwin and Jordan, 2008:181) and yet public buildings are likely to

be required indefinitely, mandating long lifecycle criteria in judging retrofit or

replacement (Ruegg and Short, 2007:3.22).

Decision-making is often difficult because of future uncertainty (Hallegatte et al.,

2012:2-9), conflicting objectives, too many or too few proposed alternatives, and

unsupported biases (Eisenführ et al., 2010, Ch. 1). To diminish bias and increase value,

rational decision-making can be used giving a structured process to produce improved

outcomes by breaking down complex problems into component parts (ibid., Ch. 1). No

decision-making method or decision is objectively correct (Triantaphyllou, 1997), but

defining parameters for data quality, key objectives and stakeholder preferences at the

Page 20: Policy and Value: A Case Study of Local Authority Energy Management and Investment

8

start of the process filters out short-term motivations that might otherwise overly effect

unstructured decision making (Eisenführ et al., 2010:2-4).

2.2.2 Responsibility for Energy Management

First and foremost, energy management is an issue that needs to be treated as a

management responsibility (Fawkes, 2007:33). Capehart et al. (2005:1) identify on-

going commitment from upper management in an organisation as the key ingredient in

successful implementation of an energy management program, an assessment agreed

with by Russell (2010:59-63). Any organisation that expects to make actual reductions

in energy waste needs to commit all managers to on-going, results-based organisational

change by setting energy goals and accountabilities (ibid.:52-54).

Frequently cited business research also concludes that successful change

programmes emphasise results, particularly from an on-going succession of short-term

measurable projects. Such programmes involve empirical testing to reveal what works

on-site, combined with frequent reinforcement and a strong management commitment

to monitoring and reporting results (Kaplan and Norton, 1992). In contrast, ‘activity-

based’ ‘quality programmes’ or ‘campaigns of programmatic change’ commonly fail

because they are not judged by verifiable results, they are too large scale and diffuse in

effects, or they are designed by staff specialists or external experts rather than

operating-level managers who can trial and test for results against accurate monitoring

(Schaffer and Thomson, 1992). Enduring organisational change most effectively

evolves at the periphery of organisations (not by ‘top-down’ direction), primarily by

changing behaviour and habits, rather than attitudes or ideas, and is best motivated by

new and clearly identified roles, responsibilities and relationships (Beer et al., 1990).

Page 21: Policy and Value: A Case Study of Local Authority Energy Management and Investment

9

Poor energy policy treats energy management as a series of engineer-driven, fast

payback, capital investment projects, whereas good policy is a continuous management

process of communication involving all employees in deriving value from a mix of

continuous awareness and attention to detail, as with any other financial portfolio,

(Russell, 2010:85-87).

Capehart et al. (2005) describes six critical energy management objectives,

illustrating the need for managers and staff to take responsibility for energy saving.

Four of the key objectives critical to energy management are purely managerial skills

and remain the responsibility of all managers:

• Cultivate good communications on energy management;

• Develop and maintain coherent monitoring and reporting management protocols

to use energy wisely;

• Continuous behavioural improvement to increase returns from energy

investments;

• Develop an interest in and dedication to the energy management program from all

employees.

Two are more technical: the need to improve energy conservation and efficiency, and

reducing impacts of supply interruption (ibid., Ch. 1). Many lessons in good

communication to improve energy efficiency through past marketing efforts are clearly

described in a report by LBNL (2010).

Technical aspects of energy management do require expertise to inform facility

management and decision-making, but it is clear that the responsibility for energy

management lies with management, not with agencies or consultants (Fawkes, 2007:46-

55). To solve energy cost problems, a programme of sustained, ‘continuous energy

Page 22: Policy and Value: A Case Study of Local Authority Energy Management and Investment

10

improvement’ is required, including both behavioural measures and capital projects,

planned so that early, easy stages guarantee savings that can are reinvested in longer

term but high net value investments (Russell, 2010:91).

2.2.3 Assessing Quality in Energy Management – The EMM

Fawkes (2007:42-63) sets out basic activities and enabling tools useful for every

type of organisation, public sector or private sector, large or small, to focus on the

objective of achieving maximum cost, energy and carbon savings. Similarly Russell

(2010) describes assessment of an organisation's energy performance using clearly

managerial categories and questions:

• Organisational Policy: How well does the organisation articulate its energy vision

and goals?

• Management Structure: Is there clear authority and accountability for energy-

related decisions?

• Implementation and motivation: Is energy policy integrated with standard

operating procedures?

• Investment analysis: Are the right criteria used to reach conclusions about energy

and money?

• Monitoring and targeting: Is there a way to measure and react to energy

performance? (ibid.:118)

Typically, these are the headings used in the EMM method, qualitatively

assessing the current performance level in each of these dimensions, often using a zero

up to 4-star scale (see Table 2.1). This tool is used to examine where an organisation is

now and to identify how it needs to progress its energy management abilities.

Widespread use of the EMM for assessment of organisations and industrial sites is

Page 23: Policy and Value: A Case Study of Local Authority Energy Management and Investment

11

noted in references from North America (US-EPA, 2012), Britain (Fig. 3, Carbon Trust,

2011; Fawkes, 2007:56), as well as Ireland (EPA, 2003:16; Wajer, 2005).

Table 2.1 The Energy Management Matrix Collated from Table 5.3, pp.119-120, Russell, 2010

Page 24: Policy and Value: A Case Study of Local Authority Energy Management and Investment

12

2.2.4 Energy Management Standards and Indicators

The new ISO 50001, replacing IS EN 16001, is a worldwide standard for energy

management in use that enables third-party auditing and quality registration of energy

management, establishing energy baselines and Energy Performance Indicators (NSAI,

2012). University College Cork has recently achieved this accreditation (UCC, 2012).

In Ireland, the Sustainable Energy Authority of Ireland (SEA) have developed Energy

MAP, a management action plan for small and medium energy users including local

authorities (SEAI, 2012f).

Quantitative performance indicators are required to enable organisations, local

authorities for example, to compare dispersed buildings of similar type (Moss, 2005,

Ch. 6). Moss notes the need for carbon dioxide emission benchmarks and indices

(CDIs). Capehart et al. (2005:26-29) identify critical performance indicators needed for

on-going analysis of energy use in buildings as total energy cost and consumption, as

well as cost divided by area (Energy Cost Index, ECI) and consumption divided by area

(Energy Utilisation Index, EUI).

2.2.5 Energy Accounting: Linking Cost, Consumption and Carbon

Linking energy costs, energy consumption and carbon emissions is a critical part

of energy monitoring, requiring accurate energy reporting to be coordinated with

financial accounting. Both sets of data can then be jointly subject to analysis thereby

informing policy and management decisions (ibid.:25). Progress toward coordinated

energy accounting can be described in qualitative attainment levels, see Table 2.2, that

complements and further adds to the EMM qualitative assessment of the Monitoring

and Targeting category (ibid., Ch.1). Energy accounting also supports the Investment

Analysis category.

Page 25: Policy and Value: A Case Study of Local Authority Energy Management and Investment

13

Table 2.2 Financial and Energy Accounting Attainment Levels

From Capehart.:25)

Billing data is critical to energy accounting and for establishing baseline energy

use. Fawkes (2007:39-40) notes that in the UK billing by utility companies has been

“atrocious”, with a very low standard that would be unacceptable in any other industry,

and which may be a left over from “take it or leave it” billing from nationalised utilities.

2.2.6 Energy Performance Certification of Buildings

Energy Performance Certificates (EPCs) for buildings have become an effective

reference basis for building energy use and improvements in Europe and worldwide

(Bull et al., 2012; Laustsen, 2008; Yan-ping et al., 2009). Buildings in their design,

fabric and technical equipment can perform at a theoretical level of energy performance,

an 'asset-based' rating. In Ireland, the asset-based EPCs are the Building Energy Rating

(BER) for dwellings and the NBER for non-domestic buildings. Qualified assessors

produce these by inputting a building’s details into modelling software thereby

calculating its energy performance (SEAI, 2012e).

However, a building and its technology are operated by people, often many

people, introducing a multitude of additional variables into the systems operation and

dramatically increasing potential risk of energy waste due to behaviour (Masoso and

Grobler, 2010). To give a building an 'operational' EPC, that will show how an a

occupied building is actually performing in practice, a straightforward method is to sum

Page 26: Policy and Value: A Case Study of Local Authority Energy Management and Investment

14

the total energy inputs for a building for a year, as evidenced by the energy bills,

divided by the measured floor area (SEAI, 2009a:8). In Ireland, the benchmarked

operational EPC is called a Display Energy Certificate, an A (good) to G (bad) rating

system that is renewed annually. Since 2009, all buildings open to the public over 1000

m² in size, including public buildings, are legally required to display this certificate.

Under the revised Energy Performance of Buildings Directive (EPBD-R), this will

apply to all buildings over 250 m² from July 2015 (European Union, 2010).

2.3 Energy Saving and Retrofit Investment Decision-making

2.3.1 Saving Energy: Energy Conservation and Energy Efficiency

To reduce demand, measures need to be taken to save energy, by energy

efficiency or energy conservation, or both (SEAI, 2008). Energy efficiency enables a

result to be achieved with less energy than is currently used, whereas energy

conservation is a reduction in energy usage made simply by the decision to avoid

consuming it (SEAI, 2009b:7). Energy saving usually results in cost saving but if the

saved monies are spent on energy use, through consumption of any kind, a rebound

effect occurs reducing the overall saving, either locally (direct rebound) or more

globally (indirect rebound). As cost, energy use and carbon emissions are strongly

related, similar rebound effects affect each of them. There is great disagreement in the

literature regarding the extent of these effects, some saying they largely cancel out the

efficiency gained (Herring and Sorrell, 2009; Alcott, 2008) and some disagreeing

strongly (Lovins and Lovins, 1997; Ryan and Campbell, 2012:24).

Saving energy can cost less than buying energy, an ‘energy efficiency gap’ that

potentially widens when fuel prices rise rapidly and efficiency costs fall (Lovins and

Lovins, 1997:i). However, there are often serious barriers in organisations, information

Page 27: Policy and Value: A Case Study of Local Authority Energy Management and Investment

15

and markets that prevent investment in improved energy management and capital

projects to limit commitment to future energy usage (Brown, 2001). Allcott and

Greenstone (2012) temper this by finding that the ‘energy efficiency gap’ may not be as

large as engineering-accounting studies suggest. Nonetheless, providing sustainable,

secure energy management structures requires investment and control over both energy

supply and demand Denny and O'Hagan (2011:272).

2.3.2 Funding Energy Efficiency and Retrofit Measures

Financing barriers to funding energy efficiency include: non-availability of funds;

poor information; project scale and development costs; weak risk assessment and

management; and a lack of technical or investment knowledge and capacity (Fig. 1,

IEA, 2011a).

Energy Saving Companies (ESCos) guarantee performance levels and cost

savings in Energy Performance Contracts (EPCs) agreed with energy users. They carry

out retrofit and other measures, and take on the risk of achieving energy savings (SEAI,

2012a). In return they receive payments over the life of the contract and these may be

related to independent measurement and verification (M&V). ESCos can be privately

or publicly run. Local authorities may be wary of transferring risk to private companies,

given their experience of Public Private Partnership (PPP) failures in regeneration work

(Punch, 2009:23-26), outcomes which are not untypical of PPP performance worldwide,

despite their political popularity (Hodge and Greve, 2009). As with PPPs, the public

and private partners to EPCs have divergent goals, so local authorities need expertise to

avoid poor outcomes, due to high transaction costs and knowledge imbalances (Vining

and Boardman, 2008; SEAI, 2012a:18).

Page 28: Policy and Value: A Case Study of Local Authority Energy Management and Investment

16

The logic of rebound and consumption-caused emissions suggests that

governments need to ring-fence revenues from carbon taxes and efficiency savings

toward further spending on carbon-saving efficiency savings, if they are serious about

cutting carbon emissions and sustaining intergenerational equity (Helm, 2008).

Nevertheless, ring-fencing, the reallocation of specific government tax or savings

revenues to specific purposes (also known as Pigouvian taxes, hypothecation or ear-

marking) may not be popular with governments because they typically want flexibility

to spend revenues as they see fit (Spackman, 1997). However, voters can support ring-

fencing more readily if the environmental benefits are made clear (Sælen and

Kallbekken, 2011). Evidence from efficiency programmes in the USA shows that ring-

fencing at least a large percentage of eco-tax revenues and efficiency-related savings to

fund on-going sustainable development measures greatly increases the effect of

interventions (Cowart, 2011).

A portfolio of policies is critical: efficiency labelling and performance standards;

auctions of allowances (as in the EU Emissions Trading Scheme); and a large portion of

carbon tax revenues re-directed back into efficiency measures (Boardman, 2004). With

respect to buildings Cowart (2009) finds that piecemeal approaches make no sense;

whole buildings need system-upgrades rather than making a series of small-scale steps.

Based on actual figures from past programmes, revenue reinvestment programmes that

ring-fence savings toward energy efficiency can save at least seven times more carbon

per consumer unit cost than carbon taxes alone (ibid.). A finance mechanism in line

with this ‘cap and invest’ strategy’ is the ‘revolving fund’ that begins with an initial

investment and requires that returns on the investment go back into the fund to further

investment, as in the Thailand Energy Efficiency Revolving Fund (IEA, 2011a:55-59)

Page 29: Policy and Value: A Case Study of Local Authority Energy Management and Investment

17

and the Revolving Green Fund, ‘invest-to-save’ funding of university energy efficiency

in England (UK Government, 2008:31).

2.3.3 Cost optimal Retrofit and Lifecycle Costing

Though necessary for society and human wellbeing, both new-build and existing

buildings are expensive to build or retrofit, and costly to operate over their lifespan, due

to maintenance and fuel costs (McNicholl and Lewis, 1996; Verbruggen, 2012).

Therefore, when committing to a long-term investment such as new build or retrofit it is

financially and logically prudent to consider ‘whole-life’ costs, benefits and risks. Deep

retrofit of existing buildings is most economically feasible when significant renovation

is undertaken due to major repairs or refitting, typically every 30-40 years (Laustsen,

2008:8). The Department of Finance also state that whole life costs are very important

in costing a design, specifying a 20-50 year study period in the Capital Works

Management Framework (DoF, 2009:55), as demonstrated in a worked example for a

school in Dublin by Kehily and Hore (2012). The EPBD-R directs Member States (MS)

to ensure that major renovations include 'cost optimal level' energy performance

upgrades to building elements or to whole buildings undergoing significant renovation,

with the MS definitions of cost optimal to be submitted and approved by January 2013

(Article 7, European Union, 2010; EU, 2010). 'Cost optimal level' means the lowest

sum total of energy-related investment, maintenance, operating, and disposal costs over

the remaining economic lifecycle of the building or building element as defined by the

MS (Articles 3-5, European Union, 2010; EC-EEE, 2012).

The aim of the EPBD-R is to ensure that investment appraisals of retrofits are

made on the basis of lifecycle costing comparing alternative sets of retrofit measures

(Aggerholm et al., 2011 Section 3). Functional long-lasting buildings are more

Page 30: Policy and Value: A Case Study of Local Authority Energy Management and Investment

18

sustainable if they minimise their total life cycle environmental cost and maximise the

physical and social wellbeing of those who use them (Buys et al., 2011). Life cycle

assessment (LCA) includes all potential environmental effects whereas life cycle

costing (LCC) looks only at the financial costs, but both should include some estimate

of externalities, whether positive or negative (Norris, 2001).

Caplehorn (2012) observes that Whole Life Costing is highly desirable for

sustainability and long-term value but it is frequently not done because it is time

consuming or complex. Certainly, the International Standard for LCC does evince

complication (ISO, 2008). However, in the USA, all federal government departments

and facilities assessing new build or retrofit energy efficiency measures are required to

take decisions based on lifecycle data and appraisal methods to demonstrate long-term

cost-effectiveness and value for money (Capehart et al., 2005:151). Typically, the US

government uses a study period of 25 years (Fuller, 2005). As noted in Section 2.3.6, in

Denmark, a highly simplified LCC is used in building retrofit assessments potentially

enhancing effectiveness of policy through ease of use.

Texts for facility managers discuss Whole Life Costing and financial analysis in

budgeting and procurement to reduce future operating and maintenance costs (Bottom,

2006:212-217; Moss, 2005:118-119). Lifecycle approaches are found to be most

effective in assessing, designing and implementing retrofit actions as part of a rational

decision-making method for retrofit investment (Ardente et al., 2011).

Lifecycle appraisals are good practice and can be applied to all 'energy at risk'

calculations for energy management of future energy use (Russell, 2010: Ch. 6). For all

existing buildings there is a commitment to continue to use energy over the entire

lifecycle of the building. On analysis the current commitment to annual total energy use

can be divided into three parts (Figure 2.1): first, committed energy expenditure that

Page 31: Policy and Value: A Case Study of Local Authority Energy Management and Investment

19

economically cannot be saved; second, ‘energy-at-risk’ which can be economically

saved (comprised of the annualised project costs of all profitable retrofits); and third, an

annual amount comprising either, the savings due to the profitable retrofits and

behavioural measures, or, if the retrofits are not done, the annualised cost of doing

nothing – a penalty often not considered by decision-makers (ibid.:134-136).

Figure 2.1 Retrofit Decision-Making: Saving vs. Penalty for Doing Nothing Redrawn from Figure 6.4, Russell, 2010, with added text referencing Ibid. p.134-136

Investments in energy-smart behavioural practices are highly effective in off-

setting the risks involved in capital retrofit projects (ibid.:87). Where possible, staging

retrofit investments may be the best option in the face of uncertainty (Menassa, 2011), a

finding that may be important for appraisals by capital poor local authorities.

2.3.4 Building retrofit: Active versus Passive Measures, and Co-benefits

Verbruggen et al. (2011) show that the long-term commitment, the

‘irrevocability’ consequent from new build or long-term retrofit decisions should be

accounted for in LCC, a finding in favour of ‘fabric-first’, passive retrofit measures

rather than active technology measures that are at higher risk of premature failure (also

found by Verbeeck and Hens, 2005). Importantly, in a series of papers Little (2011)

shows that some passive measures such as retrofit internal insulation can lead to

Page 32: Policy and Value: A Case Study of Local Authority Energy Management and Investment

20

increased risks of mould and condensation, as well as limited thermal benefit.

Generally, well detailed external insulation entails far less risk producing a more

thermally effective retrofit, in line with the ideal build-up in terms of building physics,

with insulation to the outside of structure, keeping it warmer and dryer (Lstiburek,

2007). Upgrading air tightness or uneven insulation can increase condensation

problems so it is essential to improve ventilation control at the same time (Brown et al.,

2010:8).

The uncosted co-benefits of health and productivity in corporate building retrofits

have been shown to be substantial though they are frequently ignored in assessments

(Yudelson, 2010). Un-costed co-benefits, such as health due to improved comfort

levels should be included in appraisals even if only conservative estimates are made

Ryan and Campbell (2012:26-29). A cost benefit analysis of a large-scale, building

energy efficiency, upgrade programme for dwellings in Ireland, found a Benefit Cost

Ratio (BCR) of 3.0 with energy efficiency making up 57% of the positive return, health

25%, comfort 10% and emissions reductions 8% (Clinch and Healy, 2000).

2.3.5 Investment Data Quality and Relevance in Appraisal

Before an investment appraisal can begin it is critical that the decision-making

costs and benefits data be thoroughly checked for inaccuracies that might affect the

results; the appraisal process is only as good as the data used – good quality data often

takes time and money to obtain (Holmes, 1998:7). A crucial check is to ensure that any

cash flows or savings from the investment are attributable only to the proposed

investment’s commencement (ibid.). Multiple retrofit measures for a building can have

interactive effects if all adopted, so no double counting of savings is allowed in the

investment appraisal (Chidiac et al., 2011). For larger investments it can be advisable

Page 33: Policy and Value: A Case Study of Local Authority Energy Management and Investment

21

to carry out both: a financial assessment, with a sensitivity analysis to look

quantitatively at the effects of possible cost or interest rate changes; and a risk

assessment to examine the robustness of the proposal relative to future uncertainties, be

they an inherent potential for technological failure, or in respect to external effects like

health or ‘deep uncertainties’ like climate change (SEI, 2004; Hallegatte et al., 2012).

It can be difficult to accurately estimate the projected cost or consumption savings

returns on energy efficiency, or verify them after installation, so good baseline data

(adjusted for weather effects) for the building both for the appraisals and after retrofit is

important (Aggerholm et al., 2011:9-10). The process of assessing and confirming

efficiency savings is known as Measurement and Verification (M&V), a critical part of

energy management that may reveal pronounced differences between predicted and

actual energy savings (Fawkes, 2007:56). Behavioural and occupancy rebound effects

can significantly reduce energy savings (Scheer et al., 2012; see also, Hong et al.,

2006).

2.3.6 Investment Appraisal Methods and Considerations

Bandy (2011:140) notes that public sector investments are ‘paid back’ by the

value of public good that they create. To assess investment proposals, appraisal

methods are used to assess the investment quality, to rank them in order of the return

they provide and to give a yes/no answer as to whether they are likely to be profitable

given the input parameters (Holmes, 1998).

Simple payback gives an approximate measure of a project's worth by dividing

the installation cost by the predicted annual savings giving the number of years it would

take for an investment to payback (SEI, 2004:34). Use of simple payback is generally

not advised for assessing energy saving measures because it ignores the time value of

Page 34: Policy and Value: A Case Study of Local Authority Energy Management and Investment

22

money and it also ignores the costs or benefits that accrue after the investment period

(Holmes, 1998:29). Other problems are that its use can build in a bias toward short-

payback riskier projects and many projects that could increase wealth are rejected

(Ibid.). In spite of this Investing in Energy SEI (2004:30-48) discusses both simple

payback and DCF methods but does not state a preference, though remarking that lower

risk, longer life investments should be given a longer time to payback (Ch. 4).

Energy management and investment appraisal references are generally critical of

using the simple payback method of cost analysis and strongly encourage the use of

discounted cash flow (DCF) analyses such as Net Present Value (NPV) or Internal Rate

of Return, IRR (Capehart et al., 2005; Kreith and Goswami, 2007; Holmes, 1998).

NPV is preferred for project appraisal by the EU (EC, 2012b), and the Department of

Finance (DoF, 2009). DCF methods, such as NPV, allow for the time value of money

by including a discount rate, related to the rates at which finance is available and

organisation preferences, and an escalation rate, such as a forecast inflation rate in the

price of energy (Kehily, 2012).

Typically, a positive NPV signifies a worthwhile investment (Koetse et al.:176).

If a building owner is constrained from carrying out positive NPV projects because of

an inability to raise funds (capital rationing) this amounts to market failure (Holmes,

1998:106). Either the market needs better information or the owner is making a

decision that it does not want to take on debt, even if the positive NPV suggests that the

debt can be covered without problem (ibid., Ch. 8).

However, Montier (2009:47-55) notes that DCF methods can also have problems,

by leading to mistaken confidence when it is not possible to accurately predict the

future, and recommends an annualising method of gauging 'earning power’. Russell

(2010:134-136) uses a similar method in annualising the DCF retrofit cost giving an

Page 35: Policy and Value: A Case Study of Local Authority Energy Management and Investment

23

annualised profitability index, that has the advantage of directly comparing current fuel

cost with the effective fuel cost after retrofit.

Benefit to Cost Ratio (BCR) also known as Profitability Index (PI), simply

dividing the benefits by the costs, whether discounted or not, is a method recommended

by financial management texts as giving a measure of the relative amount of return

(Helfert, 2002:264). In cases of capital rationing the aim of an investor is to maximise

the return (NPV) that the available capital can generate, so ranking alternative proposals

by BCR enables decision-makers to choose all the highest BCR proposals with total

investment costs that sum to the available amount of capital (Holmes, 1998:109).

In Denmark, a modified, non-discounted form of BCR is used for its simplicity

(Aggerholm, 2009). In looking at retrofit measures particularly at major renovation,

differing lifetimes are specified for different types of measure – for example, for

insulation forty years and for lighting twenty years. By defining a definite ‘profitability

threshold’, stating that if a measure delivers a profit of more than 33% over its lifetime

then “It is required to implement the measure”, the Danish rules simplify policy and

application (Aggerholm, 2011).

2.3.7 Lifecycle Investment: Global Risks and Local Implications

Unsustainable global trends (Drexhage and Murphy, 2012:19) need to be

considered, even by local decision-makers, if appraising the values of multi-decadal

investments like building retrofit or replacement alternatives in the face of uncertainty

(Bulkeley and Betsill, 2005). Two major concerns for the next three decades, a typical

lifecycle for buildings, are global warming and peak oil. Local decision-making that

accounts for high potential uncertainties through planned local management and

Page 36: Policy and Value: A Case Study of Local Authority Energy Management and Investment

24

resilience policies has been shown to increase the robustness and cost-effectiveness of

infrastructure decisions (Hallegatte et al., 2012:34).

2.4 Energy Policy and Local Authority Implementation

As discussed above in Sections 2.2 and 2.3, good practice in energy management

requires clearly stated policy, management involvement in implementation, energy

accounting and investment appraisal, monitoring and reporting, and on-going

assessment of outcomes (the order of the EMM in Table 1.1). Noting the relationship to

other governance levels, these themes are discussed in this order below as they relate to

local authority energy management and retrofit investment, particularly in Co. Dublin.

2.4.1 Energy and Carbon Emission Policies and Targets

2.4.1.1 European Energy and Climate Policy

Although domestic (not 'total') carbon emissions is one of the three 2020 policy

targets Wood (2010) contends that the emphasis of the European Union has been on

maintaining energy security by securing fossil fuel supplies, increasing renewable

energy, and reducing consumption. This combination led to the EU’s Climate and

Energy Package (EC, 2012a) with the so-called 20:20:20 by 2020 targets (da Graça

Carvalho, 2012): aiming to reduce domestic GHG emissions by 20% from 1990 levels;

to supply 20% of energy needs from renewables; and to reduce energy consumption by

20% by increasing energy efficiency (Nugent, 2010:345).

Already by 2009, it was clear that the non-binding energy efficiency target would

not be met, mainly due to diminishing political will (with Member States distracted by

the Euro crisis) and financial commitment to the required capital investments in

changed circumstances (da Graça Carvalho, 2012:21). The recently approved Energy

Efficiency Directive (EED) will now replace the Energy Services Directive (ESD) but

Page 37: Policy and Value: A Case Study of Local Authority Energy Management and Investment

25

the 20% target has become a 17% target and remains non-binding. The expectation is in

fact of 15% savings by 2020, and only central government, not local authority,

buildings are included in the new 3% annual renovation rate (Euractiv.com, 2012;

Rabitte, 2012). The EED does introduce an obligation of 1.5% of energy sales on

energy suppliers, requiring them to invest that amount in energy efficiency measures for

customers (Rabitte, 2012).

Although they use less energy than water and public lighting, buildings are a

significant cost for local authorities (SEAI, 2011c, p.6;). Improved energy management

and retrofit upgrading of existing buildings have repeatedly been identified by

governments and experts, including those in the EU and Ireland, as cost effective, high

priority measures for reducing carbon emissions and increasing energy efficiency

(DCENR, 2009). However, despite the claimed benefits and strongly stated policies,

achieving actual savings has been slow and the savings obtained are often less than

those targeted as the drive for a new Energy Efficiency Directive has shown (EC,

2012c:1).

2.4.1.2 Energy and Climate Policy in Ireland

Ireland has clear headline policy targets regarding carbon dioxide emissions and

energy use in the public sector, to which local authorities are also bound as stated in the

Climate Policy (DECLG, 2011) and the National Energy Efficiency Action Plan

(DCENR, 2009). The NEEAP describes investing in energy efficiency as imperative

and Government has identified the need for the public sector to lead by example. It has

therefore been given a target of reducing energy use by 33% by 2020 (ibid.:22-28).

Public sector energy use, of about 6,920 GWh in 2007, has in the past only been

calculated as a estimated ‘residual’, the remainder after subtracting industrial,

residential and transport usage from the total national energy supplied (ibid.:49).

Page 38: Policy and Value: A Case Study of Local Authority Energy Management and Investment

26

Dublin has signed The Covenant of Mayors, an international agreement linking

cities committing signatories to reducing their city’s carbon emissions by at least 20%

before 2020 (Codema, 2009). However, none of the targets in any of these documents

are disaggregated in any way among public sector bodies so that differentiated budget

targets are set corresponding to differing potential attainment levels. They also lack

penalties for non-achievement weakening their effectiveness. Only the Climate Policy

has legally enforceable penalties by way of ‘flexible measures’ or carbon credits, credits

that will be needed to enable Ireland to meet the EU target (NESC, 2012:37).

Approximately 20% of non-ETS related emissions in Ireland stem from building-

related emissions, a considerable proportion though less, due to high agricultural and

transport emissions, than the 40% figure found in Europe generally (BPIE, 2011, p.19;).

Irish government departments in these areas are endeavouring to ensure that their

sectors do not have to bear the burden of the emissions reductions that are planned, as

evidenced by recent presentations by their officials (IIEA, 2012)

2.4.1.3 Public Sector – Policies, Programmes and Targets

The exemplar role of the public sector in achieving improved energy efficiency

under the Energy Services Directive is restated in the recently published Energy Use in

the Public Sector (SEAI, 2012h), which provides many details that were previously

unpublished. The policy drivers for energy efficiency are EU legislation (ESD to be

replaced by the EED, and the EPBD-R) and national initiatives including transposing

the directives and energy efficient and green public procurement.

The SEAI’s public sector programme has four key elements: partnership

agreements to engage with top level managers; best practice exchange between public

bodies at all levels and internationally; building new funding and procurement models;

Page 39: Policy and Value: A Case Study of Local Authority Energy Management and Investment

27

and much improved monitoring and reporting. The document urges public sector

bodies to engage with SEAI through basic, full and exemplar energy management

programmes including SEAI’s Energy MAP. Data on public sector energy use has been

poor but this is beginning to change. As from January 2011, all public bodies have to

report their energy performance to SEAI and in their own annual reports.

Regarding the exemplary role assigned to the public service, NGOs have been

critical of central government performance recently and in the past. A recent report

praised the OPW’s Optimising Power@Work energy efficiency campaign and SEAI

schemes, but castigated slow progress in the Departments of Education, Health and

Social Protection (DFOE, 2012). Hernan (2010) compares the lack of binding policy

requirements or sanctions enforcing policy in the Republic of Ireland to the mandatory

participation in the UK Energy Efficiency Scheme applying to the public sector in

Northern Ireland. In this scheme, all participants buy carbon allowances and revenues

are recycled to the participants based on the emissions reductions that they actually

achieve.

In Denmark in the 2000s, the public sector had been directed to “lead the way”

and was, with the household sector, the target for many government policies. However,

a review of Danish energy efficiency policy disappointingly found that in 100 public

buildings (totalling 1 million m2) EUI increased by 10% in electricity use and by 4% for

heating (Togeby et al., 2009:305). Ireland is following a similar policy so this may be a

salutary example worthy of further study.

2.4.1.4 Dublin City Council – Policies and Targets

The 2010 Dublin City Sustainable Energy Action Plan, or SEAP (DCC/Codema,

2010b), published following Dublin City Council’s signing of the Covenant of Mayors

Page 40: Policy and Value: A Case Study of Local Authority Energy Management and Investment

28

in 2009, examined the cost and potential of using 18 measures for reducing carbon

emissions in Dublin City. The net annual investment required was estimated at €200

million. Upgrading boilers has minimal net carbon abatement cost but renewable

energy infrastructure, demolishing older houses and window replacement are very

costly. In the SEAP, the fiscal incentives are to come from national and European grant

programmes. Past behavioural actions noted are the Switch-Off campaign, a Workplace

Travel Plan, and the Minus 3% project (proving that 3% annual energy saving is viable)

though no on-going management targets are mentioned.

Dublin’s per capita carbon emissions from existing buildings are noted as being

25% more than London’s and more than twice Stockholm’s. The Dublin City Climate

Change Strategy sets out the 20% carbon emissions reduction target, the 3% per annum

public sector energy saving target and also states that progress in the twelve named

indicators will be reviewed annually (DCC/Codema, 2008). A full first year review was

published in 2009 (DCC, 2009); however, no further reviews have been published

(DCC, 2012a).

DCC owns 26,500 housing units, some with a history of fuel poverty (RTE,

2011). A Housing Energy Action Plan is mentioned as being currently developed by

the Housing Department and Codema. Although the SEAP refers to a defined 2006

baseline (DCC/Codema, 2010a) and headline targets, the schedule of actions (regarding

buildings, transport and renewable energy) does not itemise the results expected or give

performance indicators to measure verifiable progress, potentially weakening the plan’s

value.

Page 41: Policy and Value: A Case Study of Local Authority Energy Management and Investment

29

2.4.2 National and Local Governance in Ireland

Governance in Ireland is highly centralised with local government having a much

smaller role even though it acts as an agent in delivering many services funded by

central government and has the advantage of closeness to local residents (Lane,

2011:69). A report by Indecon (2005) found that local government is heavily dependent

on central funding and advocated more financial independence. Following the

economic crisis though, both capital and current public spending have been curtailed

and will be very restricted in the near to medium future (Lane, 2011:72-84).

MacCarthaigh (2012) details how cabinet government in Ireland has been

described as having ministerially controlled “silo-like” departments but has also

developed ‘delegated governance’ in assigning responsibilities to agencies of varying

kinds. However, the Irish application of ‘agencification’ has been diverse and

unstructured, producing a complex ‘organisational zoo’ with many agencies, of many

kinds, with varying degrees of accountability to government, or autonomy from it,

(ibid.:131-135), echoing Brundtland’s concerns about the wisdom of devolving

management responsibilities to agencies (Para. 34-35, UN-WCED, 1997). This would

also seem to be potentially at odds with energy management good practice, which

directs managers to lead responsibility for energy saving.

MacCarthaigh and O'Malley (2012:260-263) conclude that reform proposals are

often not implemented or get bogged down in process rather than emphasising results.

They identify a lack of specialist skills across government and an urgent need for

national and local government coordination with far more local input and

empowerment. Performance evaluation and accountability with systemised monitoring

are also viewed as critical to improve governance at all levels. With a quotation from

Machiavelli, Considine and Reidy (2012:102) illustrate the difficulties of overcoming

Page 42: Policy and Value: A Case Study of Local Authority Energy Management and Investment

30

‘path dependency’, resistance to change, in institutions and bureaucracies. They

identify the need for ‘critical junctures’ within institutions so that critical opportunities

for change are realised to break from established patterns that add to policy inertia

ibid.:104). They conclude that ‘critical moments’, like Ireland’s on-going, ‘five part’

interlocking crisis (NESC, 2009), may not necessarily result in such changes occurring,

particularly when judged by past Irish political history.

2.4.3 Dublin City Council Energy Usage

2.4.3.1 DCC Annual Reports 2010 and 2011

In the Annual Report for 2011, Dublin City had Operational Expenses (including

energy) of €279 million although no specific energy cost figures are shown in the

Annual Reports for 2010 and 2011 (DCC, 2012d). Separately, an analysis of council

energy usage is given stating electricity use (72 GWh) but no figures are given for gas

usage, total energy use or carbon emissions (ibid., Appendix 9). Mention is made of

energy performance initiatives, the largest being Ballymun Regeneration work with

savings of 10 GWh. Kilbarrack Fire Station, the world's first carbon-neutral fire station

is noted as saving 633 MWh.

The 2010 and 2011 DCC energy costs (DCC, pc) were as shown in Table 2.3.

The rise of 28% in gas cost from 2010 to 2011, in spite of a warmer year in 2011 than

2010, is particularly notable and is likely to be cause for concern.

Table 2.3 DCC Energy Costs 2010 and 2011

Page 43: Policy and Value: A Case Study of Local Authority Energy Management and Investment

31

(Figures supplied by DCC, personal communication)

Data quality problems were noted in the recent SEAI report (SEAI, 2012h) and

there are some large apparent inconsistencies in the figures given for DCC energy use

by the NEEAP (DCENR, 2009:53)and the DCC SEAP (DCC/Codema, 2010b). The

difference between these figures amounts is more than 30%, indicating possible

uncertainties, casting doubt on the usefulness of the headline policy targets.

DCC leisure centres are part of the Recreation and Amenity Department that had

expenditures or 77.9 million with income of €11.2 million. Both the 2010 and 2011

Annual Reports make special mention of on-going provision required for the three

stand-alone swimming pools at Crumlin, Sean McDermott Street and Coolock (DCC,

2012d:85). The 2011 report notes the reduced income across the leisure centres and the

aim to maintain services.

2.4.4 Funding Local Authority Retrofit

2.4.4.1 Social Housing Retrofit Grant Funding

Investment in local authority energy retrofitting comes in annually provided

grants from the DECLG for social housing retrofit and from DCENR through SEAI, or

other from departments, through grant schemes that can fund public building retrofit.

Curtin (2009) states that about 1.2 million homes require retrofit to reach a C1 BER,

which would take 85 years at the 2009 level of investment. A National Energy Retrofit

Programme is being planned for both domestic and non-domestic sectors to be funded

by the new EED energy supplier obligation and by new market energy service providers

such as ESCos (DCENR, 2010).

Energy retrofits to this local authority owned dwellings are part-funded by the

Social Housing Improvement Programme (SHIP) with funding amounts based on the

Page 44: Policy and Value: A Case Study of Local Authority Energy Management and Investment

32

improvements achieved in BER ratings (DEHLG, 2010; for statistics see DECLG,

2012a). Total SHIP funding for 2012 is €251 million in capital allocations to local

authorities (O'Sullivan, 2012).

Fuel poverty affects close to 20% of Irish households with serious effects on

health and comfort, yet addressing them would have high net benefits for the State and

yet the poverty persists (Scott et al., 2008). Scheer (2012) describes how reallocation of

the current €465 million in energy subsidies could be effectively reallocated, within

current funding, to energy efficiency upgrades with significant benefits for the economy

and subsidised households in fuel poverty. Given the high net real financial benefits

accruing from these long-term investments according to these economic analyses, it

follows that it is either the nature of the problem politically, or the length of the

investment, or both, that inhibits action. Some small pilot ‘area-retrofits’ have been

carried out in fuel poverty affected areas: in Tralee, Co. Kerry and in Dundalk, Co.

Louth, estates of private and public houses were upgraded using SHIP and SEAI

funding (SEAI, 2011a; Ó Dónaill, 2011).

A ‘fabric-first’ approach, insulating and increasing air tightness, is found to be

potentially effective in reducing energy use and carbon emissions in an analysis by

Wyse (2012) of the potential option in upgrading social housing in Co. Wicklow, but

the study notes that this is not common practice in current local authority retrofit

programmes.

2.4.4.2 Better Energy Workplaces: Retrofit Grant Funding

The Better Energy Workplaces scheme, aiming “to deliver a major increase in

pace, scale and depth of sustainable energy investments in upgrading existing buildings

and facilities” (SEAI, 2012c) with a total fund of €7.5 million for part-funding of

Page 45: Policy and Value: A Case Study of Local Authority Energy Management and Investment

33

energy retrofits to private or public sector buildings was announced on 14 March by

DCENR, with applications to SEAI to be received by 30 April and successful applicants

to be informed in June (SEAI). The Application Guide (SEAI, 2012c) was published on

21 March 2012 for public and private sector applicants seeking grant part-funding of

retrofit projects from the 2012 BEW scheme. If approved for funding by SEAI, a non-

commercial public sector application would typically receive the 35% of eligible costs

up to 50% in exceptional circumstances. A particular focus is on applicants involving

third-party ESCo or energy supplier involvement to engender ‘pay as you save’ longer

term funding for projects, thereby increasing the scale of this funding mechanism

(SEAI, 2012a:15).

Ewing et al. (2005:30) critique an earlier SEAI grant scheme for not following

Aarhus Convention provisions in being open to public consultation to learn from

community experience in regard to maximising investment returns or market choice.

2.5 The DCC and DFB Green Plan

Developed and instigated by Fire-Fighter Neil McCabe of Dublin Fire Brigade

(DFB), the Green Plan was instigated in Kilbarrack Fire Station in 2007 and has been

supported by DCC (DCC, 2011). Founded on the four sustainability pillars of The

Natural Step programme, the Plan’s two core principles are behavioural change,

increasing the awareness of energy and water use, and carbon emission reduction,

aiming to trade in the Irish Voluntary Carbon Market by 2011 (McCabe, 2011b). The

plan, focuses on seven areas: energy, water, waste, biodiversity, transport, society and

procurement (DCC, 2010). Numerous verified results are listed by McCabe (2011b).

The flagship project at Kilbarrack Fire Station has involved firefighters in

adopting sustainable responsibility as a new ethos in their work as well as utilising

Page 46: Policy and Value: A Case Study of Local Authority Energy Management and Investment

34

capital investments in water and energy saving technology that have combined to make

very large savings that are being reinvested in further energy saving. Over 85% of

water for fire fighting is now collected from the station’s roof and energy demand has

been cut by more than 80% in two years, paying back the total upgrade investment in

3.3 years and with an on-going saving of over €37,000 per year (McCabe, 2011a).

These are exceptional savings when compared to public building retrofits

elsewhere in Europe where deep retrofit savings of 20-70% are more common (Erhorn-

Kluttig et al., 2004; Ardente et al., 2011).

2.6 Literature Review Conclusion

Comparing the energy management literature to the public sector documents

appears to show inconsistencies. The former stresses linked, consumption and cost

energy accounting and sustained managerial support for operational energy saving

programmes. By contrast, published Dublin annual reports and national policy figures

do not link energy costs with energy consumption in kWh and carbon emissions.

Unlike the European carbon emissions target, national and Dublin energy policy

targets lack staged performance indicators or sanctions that would register progress or

invoke renewed effort. Public sector energy use is not accurately known nationally and

the baseline energy use given for Dublin City Council appears to vary significantly

between documents indicating problems with methodology or data, undermining the

validity of the targets. High per capita carbon emissions, a high level of fuel poverty

and notably high running costs in older swimming pools suggest problems with past,

and perhaps, existing energy policy and implementation.

Page 47: Policy and Value: A Case Study of Local Authority Energy Management and Investment

35

CHAPTER 3 RESEARCH METHODOLOGY

3.1 Research Methodology Outline

Following an overall sequential approach, the research aim was to produce data to

assess whether national energy and emissions policy, in its implementation at local level

in Co. Dublin, is consistent with good practice in energy management and retrofit

investment. The results would potentially be generalisable both to local authorities

nationally and to national energy saving policy with respect to local authorities.

Three individual methods were used within this guiding design:

1. Observation by survey of a specific sub-case: the energy management of DCC

leisure centres with analysis of DECs and identification of energy saving

potential;

2. Documentary analysis of guidance and data sourced from a DCC application for

retrofit funding, later approved by SEAI, with analysis using standard government

and value investment principles;

3. In-depth interviews with informed respondents to extend the research to the

overall local authority approaches to energy management and investment.

3.2 Research Strategy

The focus of this research is specific to the current organisation of energy

management and building retrofit in the Co. Dublin local authorities so it formed a

defined 'case’, initially based on DCC leisure centres, for which a case study research

strategy would be appropriate. A case should be located in a 'natural setting', being

something or somewhere that exists already rather than being generated artificially to

test theories (Denscombe, 2010, Chapter 2;).

Page 48: Policy and Value: A Case Study of Local Authority Energy Management and Investment

36

This study's case is: local authority implementation of national policy on carbon

emissions and energy efficiency, particularly, though not exclusively, relating to public

buildings and social housing. The case study approach is especially valuable in

providing holistic explanations of why particular behaviours, delays or end-results occur

in complex organisational situations – by investigating processes, interrelationships, and

underlying details that contribute to the outcomes (ibid., Chapter 2;).

Multiple methods with multiple data sources are particularly appropriate to

complex problem types, provided the methods follow a logical research procedure

(ibid., Chapter 8;). Creswell and Plano Clark (2011, p.81-86) observe that case study

strategies are often 'mixed method' strategies involving both qualitative and quantitative

research methods. The use of alternative methods provides 'triangulation,' giving a

more complete picture of the subject by obtaining complementary data that may or may

not corroborate the findings (Denscombe, 2010, p.348;).

The overall strategy adopted for this case study research can be depicted in the

notational shorthand of mixed method designs as 'qual/quan ➔ QUAL' (ibid., Table 4.1),

following an explanatory design (ibid., Figure 3.4) such that the initial qualitative and

quantitative research was followed emergently by a deeper phase of qualitative research

interviews exploring the different aspects of policy in practice as viewed by informed

respondents.

3.3 Research Methods

3.3.1 Methodology for Leisure Centre Surveys

Surveys of nineteen Dublin City Council leisure centres were carried out during a

work-placement at the City of Dublin Energy Management Agency (Codema) –

summarised in the DCC Leisure Centres: Display Energy Certificate Advisory Report

Page 49: Policy and Value: A Case Study of Local Authority Energy Management and Investment

37

by Codema for the Culture, Recreation and Amenity Department of DCC submitted in

July 2012 (Price, 2012). The finished report summarised common and building-specific

energy-usage problems and potential solutions.

The 'walk-through surveys' carried out are the most basic level of building energy

audit (Kelsey and Pearson, 2011). This type of on-site, brief building survey aims to

make a simplified, energy-usage description of the building (covering lighting, heating,

ventilation and fabric) and to list basic energy-saving opportunities identified by the

survey including observations and energy-usage comments made by staff. For each

building, a measurement of the building's heated area was made using a laser-measuring

device to take length measurements. Rough site sketches recording the measurements

and, where possible, drawings available on-site, were then used to calculate the heated

floor area of the building. Survey conclusions relevant to the research question are

reported in the Chapter 4. Combining the measured area with energy usage billing data

from the Codema database enabled calculation of a provisional DEC rating using the

SEAI DEC Tool spreadsheet (SEAI, 2012g).

Further analysis (see Section 4.2 and 4.3) tabulated and charted the data, total

energy use and energy utilisation index (EUI), to provide comparisons of the existing

energy use and the extent of the available data for the centres. An additional scatter

chart analysis of the leisure centres on a graph of total energy cost versus energy cost

index (ECI) was made to evaluate this chart type’s usefulness in identifying locations

that might yield the largest energy savings given appropriate energy management.

Page 50: Policy and Value: A Case Study of Local Authority Energy Management and Investment

38

3.3.2 Methodology for Document Analysis

• Documents analysed: SEAI Better Energy Workplaces Guide and an Application

Form as submitted by DCC, 30 April 2012.

The document analysis sought to assess whether a current government retrofit

grant-funding scheme (Better Energy Workplaces 2012) is consistent with accepted

investment principles for data quality and investment appraisal for deep retrofit. The

application form itself and the BEW application guide became a source for research

data. This was examined to give insights into the operation of current government

energy saving policy that aims to encourage wider and deeper investment in building

retrofits, particularly targeting investment innovation though the involvement of ESCos

and energy suppliers (SEAI, 2012b). The analysis involved examining the BEW

Application Guide and a BEW Application Form (referred to hereafter as Guide and

Form) submitted by DCC on 30 April 2012 and approved by SEAI for grant funding on

16 August 2012. As Denscombe (2010, Ch.12) notes, such documents are an

authoritative source of data and analysis that can be used to determine the accuracy of

the figures given, or the presence of bias and errors, thereby providing indicative

assessments of their likely effects.

3.3.2.1 Document Description and Data

The Form's numerical data were tabulated and observations were made about the

form as submitted. Where there were spaces on the form for information, the general

level of detail in these were noted. These findings are in Section 5.5.1.

3.3.2.2 Assessment of Data Quality and Relevance before Appraisal

As the quality and relevance of an investment proposal's data must be assessed

before undertaking financial appraisal (p.28 Holmes, 1998), the Sub-Project data

Page 51: Policy and Value: A Case Study of Local Authority Energy Management and Investment

39

provided was qualitatively assessed using three quality parameters that must be

confirmed, insofar as possible, before any financial appraisal can proceed:

a) Were the annual savings predicted for each Sub-Project "solely attributable to

commencement" of the investment measure (p.8 ibid.);

b) Were the Sub-Projects for a particular building fully independent or is some

double counting of savings possible because the combined savings of the

measures overlap if two or more are installed. Only the ‘incremental’ benefits of

each added measure can be included in a financial appraisal (p.8-9 ibid.)

c) Were the data and assumptions for costing the measures robust enough to

commit to an investment insofar as can be judged from the application form? To

quote Holmes (1998:7): "the investment appraisal process can only be as good

as the data on which any calculations are based."

Taking the Application Form as an example, findings were made indicating where

these parameters may, or may not, have been met or where the assumptions made in

preparing the data appeared to be uncertain.

3.3.2.3 Methodology for Comparison of Alternative Appraisal Methods

The financial appraisal methods mentioned by the guide and used in the

application were identified and any supporting information for lifecycle costing or

discounting methods of appraisal was noted. To inform discussion of alternative

financial appraisal methods, the Form’s sixteen retrofit proposals were used as a

hypothetical basis to inform an examination of appraisal methodologies (for findings

see Section 5.5.3). This comparison was undertaken because no such illustration

comparing the methods was seen in the literature and it might therefore provide findings

Page 52: Policy and Value: A Case Study of Local Authority Energy Management and Investment

40

useful in choosing appraisal methods in regard to ranking or accept/reject decision-

making.

An Excel spreadsheet was made to make these calculations for the various

appraisals, in part based on and checked against the Excel formulas and examples

provided by Kehily (2012). Kehily (pc) confirmed that 15 years would be a reasonable

minimum lifetime over which to compare investments for NPV results so, for

consistency in comparison (Ruegg and Short, 2007:3.22), this was used as a base period

for all appraisals, except for a variable lifecycle method in use in Denmark for retrofit

appraisal. The spreadsheet was made using the total costs and energy savings data as

provided on the Form (using standardised gas and electricity costs to correct Form data

errors) as well as using accepted government figures for nominal discount and inflation

rates as inputs.

Five appraisal methods were compared: Simple payback; Net Present Value

(NPV); Profitability Index (PI), also called Benefit to Cost Ratio (BCR); annualised PI,

giving the effective energy cost after retrofit (Russell, 2010); and the Danish PI method

as described by Aggerholm (2011). The latter, a simple non-DCF method with a clear

acceptance level, weights the study period for individual measures relative to their

likely service life. This was also modelled for the projects to show an alternative

method for retrofit assessment currently in use for building retrofit appraisal elsewhere

in Europe.

Using output from the spreadsheet, this analysis aimed to clearly illustrate the

decision-making differences between alternative appraisal methods. For this

hypothetical comparison, the Form data was found to have inconsistent base energy

costs, so the savings data was normalised using a single cost each for electricity and gas,

and multiplying by the kWh savings given. For the NPV and PI calculations, the

Page 53: Policy and Value: A Case Study of Local Authority Energy Management and Investment

41

lifecycle used was set at fifteen years. The installation costs in the Form were assumed

to be the total cost for the calculation. (Whereas for a lifecycle costing, all discounted

costs over the lifecycle would normally be included, and any resale or residual value of

the measure would count as a benefit.) The nominal discount rate used was 6.7%, the

Government capital investment rate as of 2010 for projects of 5 to 20 years (DPER,

2012). The escalation rate for energy cost increases used was 3.1% (Scheer and

Motherway, 2011:7). This resulted in a real discount rate of 3.5%, compared to the 4%

used by Scheer and Motherway.

Table 3.1 Appraisal Methods, Definitions and Acceptance

The appraisal methods are shown in Table 3.1. As for all appraisals the data must

pass the criteria listed in 3.3.2.2 before the appraisal is done. A comparison chart of the

proposal rankings using different appraisals was then made to facilitate discussion.

3.3.2.4 Limitations of the Document Analysis Methodology

This analysis was limited to assessing the type and comparative usefulness of

investment appraisal that the Guide and Form mention. No conclusions are made about

the DCC data assumptions except where the assumptions appear to be in conflict with

Page 54: Policy and Value: A Case Study of Local Authority Energy Management and Investment

42

investment principles, or with other relevant data found within the application or from

other sources. The Guide and the layout of the Form are the same for all applications so

the descriptive findings are applicable to the BEW 2012 fund. Different applicants

would have filled out the form differently so the analysis of the data given covers just

this case as it informs its grading or appraisals.

The spreadsheet-based comparative analyses for this form are intended to chart

the relative rankings and different acceptance criteria of the alternative appraisal

methods using the Form data as a basis. For the purposes of this illustration, the Form

data was used by hypothetically assuming that all of the (normalised) savings data was

of high quality and met appraisal quality thresholds.

Although sensitivity analyses were carried out using the spreadsheet, with

different discount and escalation rates and different life cycle periods, only one analysis

is illustrated, as the aim is only to compare the results of different appraisal methods to

more clearly illustrate their relative decision-making usefulness.

3.3.3 Methodology for In-depth Interviews

3.3.3.1 Interview Methodology Basis

Interviewing knowledgeable respondents emerged as the most appropriate

method for answering the questions arising from the findings from the initial research

methods. Long-form interviews require large amounts of time in organisation,

transcription and analysis, so the relatively few informants need to be chosen according

to the insights they may have due to the position they hold or their experience

(Denscombe, 2010, p.181;).

Kvale (2007:35-36) sets out seven stages of an interview enquiry, which directed

the sequence of the research method: ‘thematising’ and design, through interviewing

Page 55: Policy and Value: A Case Study of Local Authority Energy Management and Investment

43

and transcription to analysing (based on key topics related to the research question), by

verifying the data by cross-comparison, and finally reporting the data in rigorous and

readable form. The following outline gives a summary of the interview design used and

how these stages of interview enquiry were undertaken.

3.3.3.2 Interviewee Selection

For this research, interviewees with knowledge of local authority energy

management and/or building retrofit were chosen, largely focusing on Dublin City

Council, as this was the origin of the initial data. Concentrating on Dublin City alone

would have given a small range of data given the scope of the research question,

covering only a highly urban, very large local authority with many older buildings.

Extending the interviews to a respondent architect, from adjacent peri-urban authorities

in Dún Laoghaire (DLRCC), a smaller authority with many older buildings, and in

South Dublin (SDCC), also smaller but with many newer buildings and a large amount

of social housing, enabled two reference interviews with county architects giving some

triangulation of data and potentially a larger range of applicability for the research

conclusions.

The interviewees were chosen for their knowledge of the leisure centres, energy

management, buildings, building retrofit, and energy billing and consumption

accounting to give a wide range of expertise to provide data to answer the research

question. Two interviewees were responsible for monitoring grant money to local

authorities, ten interviewees were from the local authorities and one was independent of

government.

Each interview was recorded to an MP3 file using a digital voice recorder and

then transcribed by the author into a text file. The total recorded time for the thirteen

Page 56: Policy and Value: A Case Study of Local Authority Energy Management and Investment

44

interviews was 783 minutes, varying in length from 39 to 94 minutes with an average

interview length of 60 minutes. The respondents interviewed for this dissertation

research were:

• Paul Altman – Architect, Architecture and Building Standards, Department of

Environment, Communities and Local Government.

• Mary Balfe – Finance Office, Dublin City Council

• Patrick Barry – Architect, Irish Green Building Council;

• Jim Beggan – Manager, Leisure Centres; Culture, Recreation and Amenity

Department, Dublin City Council;

• Athena Candy – Senior Staff Officer, Corporate Services, Dublin City Council;

• Sarah Cassidy – Architect, Dún Laoghaire Rathdown County Council

• Matt Carroll – Architect, City Architects, Dublin City Council;

• Eddie Conroy – County Architect, South Dublin County Council;

• Joe Hayden – Energy engineer, City of Dublin Energy Management Agency;

• Cormac Healy – Duty Officer, Poppintree Leisure Centre, Dublin City Council;

• Neil McCabe – Firefighter, Kilbarrack Fire Station, Dublin Fire Brigade

• Colum O'Ruanaidh – Architect, Architecture and Building Standards, Department

of Environment, Communities and Local Government.

• Alan Ryan – Programme manager, Sustainable Energy Authority of Ireland;

• Gerry Wardell – Director, City of Dublin Energy Management Agency.

3.3.3.3 Interview Framework, Topics and Individualised Guides

The informants have extensive knowledge directly relating to the research

question but have greatly differing positions and experience. Therefore the interview

Page 57: Policy and Value: A Case Study of Local Authority Energy Management and Investment

45

design called for a generalised 'interview schedule’ listing the main topics related to the

research question as a basis for individual interview guides and mainly open questions

appropriate to the background of the informant (Gibbs, 2011). More direct, follow-up

questions were included in the guides to confirm specific data or hypotheses relating the

interview topics. For each interview, a slightly revised guide was made but the

underlying topics were the same for each. Such an in-depth approach required longer

interviews (of 40 to 60 minutes in length) to elicit insights and sufficient time to cover

the main areas of interest.

Figure 3.1 Interview Topics Derived from EMM Categories..

The main topics for the interview plan (Figure 3.1) were identified on the basis of

an EMM (Table 2.1) dividing the overall application of energy management into

descriptive categories and assigning a zero to four level of attainment to each.

3.3.3.4 Interview Data

The full interview data, the transcriptions (with codings and comments) are

printed in Volume 2 of the dissertation.

Page 58: Policy and Value: A Case Study of Local Authority Energy Management and Investment

46

3.3.3.5 Commenting and Coding of Interview Data

For analysis, the text transcription for each interview was transferred to a

Microsoft Word document so that ‘document comments’ could be made and

automatically sequentially numbered. Each mark-up comment was made by identifying

a section of a respondent’s response that was relevant to a coding category; the code

was then assigned, and a level of attainment and a level of governance to which the

coding was applied was noted, as guided by the EMM (Table 2.1) and the coding frame

(Figure 3.2) based on it that was used to more clearly identify the topic of a coded

response.

For example, a response containing reference to good energy management

communication between council departments would be assigned an MS3L coding: ‘MS’

indicating the ‘Management Structure’ category; ‘3’ a good level of attainment; and ‘L’

signifying the ‘Local Authority’ level of governance. If comments referred to relations

between levels of governance the higher level was identified in the coding as being the

more relevant one.

For each coding made, an associated comment was also made to justify the coding

and/or to give a brief description of the response to aid in collecting and sorting

findings. The codings rely on the coding process, the range of questions asked and the

way in which respondents chose to answer them.

Page 59: Policy and Value: A Case Study of Local Authority Energy Management and Investment

47

Figure 3.2 Coding Frame for Interview Data derived from Typical EMM..

The coding is used to categorise respondent responses by matching them to the description given.

3.3.3.6 Coding and Coding Analysis of the Interviews

To sort and analyse the codings, each coding and associated comment made in the

Word document for an interview was copied into a line of a worksheet along with the

interview number and comment number. A hierarchical sorting by EMM topic, then by

level of governance, and finally by level of attainment was made. This analysis method

eased the location of similar comments in the whole set of interviews allowing all like-

coded comments to be collated into findings. To sort categories that had large numbers

of codings, a second sort of the codings spreadsheet was made, to give appropriate sub-

categories to further simplify collation of the findings regarding similar topic points

(collating similar or dissimilar responses to the points).

The interview findings are presented as a text summary aiming to accurately

reflect respondent comments within the seven EMM coding category headings. The

brief coding comments served only as a location and sorting mechanism. In

Page 60: Policy and Value: A Case Study of Local Authority Energy Management and Investment

48

summarising the findings, the original response was the guide rather than the coding

comment.

3.4 Limitations to the Research Strategy and Methods

A case study concentrates research on a definite, limited and self-contained area

of policy, programme, occurrence or place (Denscombe, 2010:55). By definition, case

study research has limitations because it provides a limited view of a particular case

(ibid., p.304;). For this dissertation, the researched local authority is primarily Dublin

City with some reference as comparators to two adjacent authorities, South Dublin and

Dún Laoghaire Rathdown, potentially limiting the applicability of research findings to

larger urban local authorities.

‘Walk-through’ level energy audits are time-limited (one to four hours) and the

conclusions reached in surveys partly rely on conversations with leisure centre staff of

varying knowledge of energy management. The data analysis was limited by the quality

and quantity of data available.

The simplified investment appraisal analysis presented was not an in-depth

analysis specifically addressing data or technical issues. It was limited to an overview

of the documents as they were relevant to the research question and in investigating

current practice in retrofit investment appraisal. Alternative methods of appraisal were

investigated as they were recommended by the literature review.

There are limitations to in-depth interview research with expert informants,

particularly the relative lack of knowledge of the interviewer (as detailed by ibid.:193).

Coding of interview data reduces these limitations to some degree but can introduce

additional bias. Each of these potential shortcomings will be individually considered in

discussion in Chapter 7.

Page 61: Policy and Value: A Case Study of Local Authority Energy Management and Investment

49

CHAPTER 4 LEISURE CENTRE SURVEY

4.1 Observations and Findings: Leisure Centre Survey Report

The nineteen surveyed leisure centres form a varied set of buildings that may be

usefully grouped according to age, usage and size. In general, the centres divide into

two age groups: older buildings (three swimming pools, two sports halls, and an all-

weather centre) built in the period 1968 to 1990; and, more modern buildings, mostly

sports and leisure centres built since 1990 and particularly since 2000.

By usage, the surveyed centres may be grouped as follows: seven with swimming

pools (three stand alone swimming pools; three large leisure centres including

swimming pools; and one pool and fitness centre); six combining a sports hall and

leisure centre without a pool; two sports hall and boxing centres; an athletics stadium

and fitness centre; a water sports centre; a rowing centre; and an all weather sports

centre. For survey photographs of the leisure centre exteriors see Appendix K.

By conditioned floor area, the surveyed centres ranged in size from the smallest,

268 m² for the sports field changing rooms at Clontarf, to the largest centre of 4429 m²

for the Ballyfermot Leisure Centre.

The main findings of the surveys are summarised as follows:

• With one exception, no on-site monitoring of any kind was noted at any of the

centres. No automated collection of data from interval metering or sub-metering

is occurring even in large centres with Building Management Systems.

• As far as could be established, manual collection of meter readings is only

occurring at Poppintree Leisure Centre, where the Duty Officer, who has an

interest in energy management and the potential for cost saving, has been noting

Page 62: Policy and Value: A Case Study of Local Authority Energy Management and Investment

50

weekly electricity and gas meter readings since May 2010. These have been

entered in a spreadsheet to log readings and enable monitoring of energy use.

• All energy bills go directly to the Finance Office for payment so the leisure

centre managers are usually unaware of billed current and past energy costs or

consumption. The lack of on-site monitoring means that bills cannot be checked

against past meter readings.

• There are heating and ventilation problems in many of the centres. Windows are

often opened, particularly in gyms to aid ventilation, but were observed

remaining open on cold days when the heating is on.

• During the survey, lights in rooms with many lamps were seen left on when the

room was unoccupied or when daylight levels were more than high enough for

them to be switched off, including large sports halls. The “Switch off

Campaign”, the behavioural energy saving initiative was not evident in the

centres.

• The older swimming pools (Coolock, Crumlin and Sean McDermott Street) all

suffer from very poor building fabric and out-dated ventilation systems with

either only supply air or ineffective dehumidification.

• DCC does not own Coolock Swimming Pool, located on the top of the Northside

Shopping Centre, but DCC pay for its use and its energy usage. It is an

exceptionally poor building with single glazed windows throughout, uninsulated

concrete walls, poor ventilation (no extract air), moisture problems and very

poor air-sealing.

• A predominant view from staff comments was that energy management equates

primarily to on-going maintenance of boilers and HVAC systems by outside

contractors or of lighting replacement by DCC buildings maintenance staff. The

Page 63: Policy and Value: A Case Study of Local Authority Energy Management and Investment

51

interrelationship of the staff and users with the building is not clearly defined as

an important part of leisure centre energy management.

• Crumlin is scheduled for renovation due to a leaking roof having been under

threat of closure. It has poor comfort levels due to un-insulated masonry walls,

very high heat loss due to two large extractor fans, one in each end wall and, as

at Coolock, noticeably cold entrance lobby areas.

• Sean McDermott Street Pool shows similar problems. Severe moisture damage

to the roof, because of poor ventilation, had closed the gallery area.

• The older pools have recently installed new pool covers to reduce evaporative

heat loss during closed periods. Crumlin and Sean McDermott now have new

heat exchangers to heat the pool water more efficiently.

• Most buildings have well insulated distribution pipes, but deteriorating or

missing insulation was seen on some pipes and hot water tanks in older centres.

In Aughrim Street, a hot water tank was found to be entirely unlagged.

• In the large centres, Ballymun, Finglas and Ballyfermot, the plant room is distant

from Reception or the Manager's office and the BMS laptop is not easily

available for daily or weekly timetable matching to the bookings.

• Two leisure centres, Finglas and Ballyfermot have Central Heat and Power

(CHP) units. These were both working during 2010, but the one at Ballyfermot

is not now working because of a failed turbine for which a replacement part is

not available, due to the manufacturer going out of business.

• Ballyfermot Leisure Centre has a design issue in that the swimming pool area is

open to the changing area, which in turn has a weight training gym above it, so

heat and moisture from the pool affect the gym requiring additional ventilation.

Page 64: Policy and Value: A Case Study of Local Authority Energy Management and Investment

52

Energy saving recommendations were made in the survey report’s conclusions

(see Appendix D) covering lighting, area and specific buildings. They were divided

into low, medium and high impact; and low, medium and high cost.

4.2 Leisure Centre Area and Billing Data

The measured and collected data with calculated provisional DEC ratings are

shown in Table 4.1. Grey cells indicate billing data for 2010 that was unavailable as at

June 2012. Glin Road was assigned a G-rating because the oil consumption could not

be accurately estimated. Markiewicz Swimming Pool shares its gas supply meter with

the building above it so the data may well be inaccurate in application to the leisure area

alone. The heated or conditioned area is shown in the table although the unconditioned

area was also measured. In most centres the unconditioned area is mostly plant rooms

and storage, but at Ballymun there is a large underground car park.

Table 4.1 Leisure Centre Energy Data, Measured Area and DEC Rating

Page 65: Policy and Value: A Case Study of Local Authority Energy Management and Investment

53

4.3 Leisure Centre Energy Data Analysis

For each of the 19 centres there is an electricity bill and a bill for thermal energy

(all gas with the exception of Glin Road Sports Centre, which is heated with oil) giving

38 bills in total. By June 2012, 15 of these bills, as shown in Table 4, still remained

unavailable from the energy suppliers for use in energy accounting by Codema and the

Leisure Centres.

Hard copy bills with the consumption figures are available in the DCC Finance

Office but they are logistically very difficult to locate and analyse. Any one building’s

usage would have to found within a long list from the same supplier and the data may

not be easy to collate. There are also different suppliers each with different reporting

formats.

As of September 2012, Codema had billing information for 2011 as well as 2010.

Data remaining absent from the Codema database as of September 2011 included: for

2010, five electricity bills and eight gas bills remained unknown; for 2011, three

electricity bills and four gas bills were missing (Codema, pc).

The incomplete data for energy usage, due to missing bills, is noted by text in

Figures 4.1 and 4.2.

Page 66: Policy and Value: A Case Study of Local Authority Energy Management and Investment

54

Figure 4.1 Total Energy Usage of DCC Leisure Centres

Figure 4.1 shows the total energy use and Figure 4.2 shows the energy use per

square meter (EUI) for the surveyed leisure centres.

Figure 4.2 Energy Utilisation Index for DCC Leisure Centres

Page 67: Policy and Value: A Case Study of Local Authority Energy Management and Investment

55

Figure 4.3 2010 and 2011 Total Energy Cost versus Energy Cost Index.

Arrows in Figure 4.3 indicate change in costs from 2010 to 2011 for individual

named leisure centres. Points for centres with lower energy use are not named and

those missing data are omitted.

Page 68: Policy and Value: A Case Study of Local Authority Energy Management and Investment

56

CHAPTER 5 DOCUMENT ANALYSIS

5.1 Findings: Analysis of Documents

5.1.1 Description of Application Form

The BEW Application Form is in Appendix G.

The Form (DCC, 2012c) details upgrade projects proposed for four buildings with

sixteen separate 'Sub-Projects' (SPs) each individually numbered 1 to 16 (referred to

below as SP1-16). The SPs included: eight for Ballyfermot Library, four for Kevin

Street Library, and two each for Crumlin and Sean McDermott Street Swimming Pools.

The total energy consumption and cost figures for each building are given first, using

2010 figures with the predicted building savings given as the total of each building's SP

savings.

Each building is described separately with a tabled listing of its SPs giving a

description of each retrofit and the predicted electrical or thermal savings in kWh for

each. Each SP is then detailed briefly giving a Project total cost figure (including new

equipment cost and installation cost including labour), the predicted annual savings in

euro and the simple payback in years. None of the boxes available to fill in for the NPV

and IRR of the SP were filled in on this particular application.

An excerpt from the DCC BEW Application is shown in Figure 5.1.

Page 69: Policy and Value: A Case Study of Local Authority Energy Management and Investment

57

Figure 5.1 Excerpt from DCC BEW Application showing Sub-Project 1 details.

Spaces below for ‘Assumptions’, ‘Non-Energy Cost Savings’ and ‘Measurement

and Verification Methodology’ are not shown – only the latter was filled in for the sub-

projects.

Additional space for each SP gave space to enter:

• a description of the basis for energy savings;

• all assumptions and associated values used in calculation;

• non-energy cost savings with assumptions on how they are derived;

• measurement and verification details.

In all cases the description of the M&V details were entered, none involving

International Performance Measurement and Verification Protocol (IPMVP). In no

cases were any details of the assumptions or values used, or any non-energy cost

savings entered.

From the document, SP descriptions (abridged) and their related data are shown in

Table 5.1

Page 70: Policy and Value: A Case Study of Local Authority Energy Management and Investment

58

Table 5.1 Collated Sub-Project Descriptions and Data.

Saving for SP6, in greyed cell, is calculated from the data given.

5.1.2 Findings: Application Guide

A copy of the Application Guide is in Appendix G.

5.1.2.1 Financial Appraisal Method

The Guide (p.7) states that the four criteria for assessment of a BEW application

are: ‘Value for Money’, its benefit in energy, carbon and cost savings relative to its cost

(40); ‘Quality and Delivery’, its demonstration value, replicabilty, and the applicant's

ability to deliver by the deadline (30); ‘Innovation’ in wide application or finance

delivery (15); ‘Jobs Benefit’, the labour-intensity of the project (15). The marks in

brackets are the maximum possible mark that could be allocated during grading by

SEAI. Specifically noted under Value for Money is that:

Page 71: Policy and Value: A Case Study of Local Authority Energy Management and Investment

59

Included in the consideration in this category will be the value of the

investment to the State and the quality of financial appraisal of the

project (SEAI, 2012c)

Following grading, the final approval is also noted as being dependent on:

“project payback timeframes”, the market incentive effects and the applicant sector

(commercial, public sector etc.). Although there are boxes on the form for NPV and

IRR there appears to be no mention of either criterion anywhere in the guide. Neither in

the application nor in the guide is there any standard study period, lifecycle or time

horizon on which to judge an investment for an NPV or IRR calculation.

From the above data it can be concluded that the financial appraisal method being

used in assessment and being encouraged by the BEW funding scheme is simple

payback.

5.1.2.2 Investment Appraisal Data

The SP costs identified by the Guide (p.6) as being eligible for inclusion in the

total cost of the measure for grant consideration are restricted to installation costs due to

labour, materials or specialist assistance. Costs not related to energy performance

improvement and on-going monitoring costs are not eligible.

To verify savings, “projects must include an efficient and effective mechanism for

energy use data collection and/or monitoring of the savings” (p.5). Large and complex

projects are encouraged to have IPMVP monitoring. In the Terms and Conditions,

grantees must comply with their commitment to using the mechanism of monitoring

that they specified in the application form, but no penalty for failing to meet the

predicted savings is specified (p.11).

Page 72: Policy and Value: A Case Study of Local Authority Energy Management and Investment

60

5.2 Findings: Assess Proposal Data Quality and Relevance

These indicative findings reference the principles stated in the methodology

(Section 3.3.2.2).

In SP1, costing €15,000, the existing electric heating is to be removed and

photovoltaic panels are to be installed with a projected saving of €9,868. Two

measures, one removing an electricity demand and one installing an electricity supply

are thereby included in the same SP. The electricity output of the PV panels is not

given but, in SP9, the installation of PV panels costing €5,500 produces an annual

saving of only €208. Therefore, it appears that in SP1 there must be a large saving

ascribed to the removal of electric heating. However, removal of a heating method does

not provide an alternative investment that results in a savings return. For an investment

appraisal, the incremental saving produced by removing the electric heating is zero.

The cost of removing the electric heating should not be part of an energy investment

appraisal, it should be assigned to renovation costs. Given that the payback for SP9 is

stated as 26 years, it seems likely that the payback for the PV panels in SP1 would be

similar and therefore PV in this case should not be associated with the 2-year payback

given.

The calculated thermal savings shown for SPs 3, 6, 7 and 8, whose savings in heat

for the same building would overlap, may account for their mutual influence, but

without a listing of the assumptions that were made in making the estimates it is not

possible to know.

There appear to be no other SPs that are mutually affecting in a way that might

allow double counting or where the projected savings were unlikely to be only from that

particular SP.

Page 73: Policy and Value: A Case Study of Local Authority Energy Management and Investment

61

It is difficult to judge the robustness of the costings and savings from the Form

because all of the boxes for detailing assumptions were left blank giving little

opportunity for checking the assumed data parameters. Calculations for the savings

related to HRV installation at Crumlin made by Temborius (2012) and another SBEM

calculation (see Appendix H) appeared to show markedly lower energy savings than in

the Form, potentially altering the savings data for that case. Similarly the confidence

level for achievement of other projected savings could be questioned but this would

require assumptions to be listed so that they could be checked. The base data for all of

the savings projections was from one year, 2010, a year with 36% fewer 15.5 ºC

Heating Degree Days than 2011 (as calculated from Dublin Airport data, obtained from

BizEE, 2012).

Examining cost and consumption savings provided on the Form for the SPs in

Table 5, there are inconsistencies in the implicit values of gas and electricity in cost per

kWh. It is not clear why this would be the case as there should, presumably, be only

one value assumed for each for a particular building.

5.3 Analysis: Comparing Appraisal Method Alternatives

This Section's results relate to the methodology described in Section 3.3.2.3. As

noted above, there were inconsistencies found in the implicit costs given for gas and

electricity. For this hypothetical comparison of appraisal method alternatives it was

essential to begin with consistent data to give an informative comparison. To enable

this comparison, electricity was given a cost of 17 cent per kWh and gas a cost of 5 cent

per kWh. Table 5.2 shows the full costs, as before, with the annualised savings

normalised using these energy cost figures. This is the data used to make the

comparisons illustrated in this section.

Page 74: Policy and Value: A Case Study of Local Authority Energy Management and Investment

62

Table 5.2 Data used in appraisal comparison.

Annual saving figures normalised by using set cost per kWh for gas and for electricity.

Figure 5.2 shows the simple payback in years for the 16 projects. The shortest

bars appear best in this appraisal as being the projects with the shortest paybacks. In the

Guide and Form no accept/reject level was given, but a line for the 15-year study

period, as used for the other appraisal calculations, is drawn in the chart.

Figure 5.2 Simple Payback in Years for the 16 Projects.

Figure 5.3 shows the NPVs for the measures, yielding a different view of the

appraisal. Marginally negative, unprofitable NPVs, as indicated by grey bars, are found

for SPs 2,4,8,9,11. Four of the SPs, 1,3,13,15, have NPVs greater than €85,000. The

Page 75: Policy and Value: A Case Study of Local Authority Energy Management and Investment

63

two HRVs, SP13 and SP15, are found to have NPVs of €280,000. The remaining five

positive NPV projects have NPVs of less than €20,000.

Figure 5.3 Net Present Values for the 16 Projects.

Figure 5.4 charts the Profitability Index, also called Benefit to Cost ratio (BCR).

PIs of under one (indicating unprofitability) are indicated in grey – the same five of the

projects as for NPV.

Figure 5.4 Profitability Indexes for the 16 projects.

Combining the PI values and NPVs on one scatter chart of the projects gives

Figure 5.5. The base data is the same as that charted in Figures 5.3 and 5.4. This chart

shows that while projects 13 and 15 are forecast to have very high NPVs, project 1

provides a higher return per euro invested. Of the 16 projects, 11 of them can be seen to

have financially marginally positive or marginally negative profitability.

Page 76: Policy and Value: A Case Study of Local Authority Energy Management and Investment

64

Figure 5.5 Profitability Index versus Net Present Value for the 16 projects

Figure 5.6 shows the effective cost of energy after retrofit (ECER) with €1 being

set as the reference present cost (also called the ‘cost to avoid’). Grey bars indicate that

the energy cost after retrofit is effectively more expensive than before retrofit,

indicating rejection of the measure in this appraisal method. Again this method

produces the same accept/reject results as for NPV and PI. As noted previously, this

appraisal is an annualised PI method.

Figure 5.6 Energy cost after Retrofit compared to present cost.

Figure 5.7 shows the project value for money as appraised by the profitability

index method used in Denmark for assessing retrofits. Lifetimes are assigned to each

project based on service lifetimes that are weighted according to the type of measure as

directed in Aggerholm (2011).

Page 77: Policy and Value: A Case Study of Local Authority Energy Management and Investment

65

Figure 5.7 Danish Appraisal Method Profitability Index

Figure 5.8 shows the rankings of the different appraisal methods to gauge

differences between the alternative methods. For each project the ranking given by each

appraisal is shown in the order: Simple payback, NPV, PI, ECER and Danish PI

Method. Tallest bars indicate the best ranking out of 16 given by the particular

appraisal for the 16 projects, and the shorter the bars the lower the rankings.

In terms of ranking measures, PI and ECER are shown to be the same throughout,

as ECER is an annualised PI. The Simple Payback, NPV, PI and ECER methods all

produce very similar rankings of the measures, differing by a maximum of two ranking

places. The Danish method, which uses different study periods for different classes of

measure, produces markedly different rankings, increasing rankings for insulation,

glazing and lighting, and decreasing rankings for fan and electric upgrades (allowing for

earlier technology failure relative to more passive measures).

Measures rejected by a particular appraisal are marked with a diamond below the

relevant bar. The NPV, PI and ECER methods all reject the same projects because they

have the same basis. Simple payback, if given a 15 year maximum as a rejection level,

the study period for the previous methods, rejects one measure that the others do not,

and accepts two projects rejected by NPV, PI and ECER. Given the weighted service

lifetimes assigned, the Danish Method only rejects two measures, those with a PI of less

Page 78: Policy and Value: A Case Study of Local Authority Energy Management and Investment

66

than 1.33, indicating that almost all of the measures are sufficiently profitable that in

Denmark it would be required that they be carried out.

Figure 5.8 Comparison of rankings by different appraisals methods.

Page 79: Policy and Value: A Case Study of Local Authority Energy Management and Investment

67

CHAPTER 6 IN-DEPTH INTERVIEWS

6.1 Interview Findings: Data Location and Citation Format

All of the interview transcripts are located in Volume 2 of the dissertation. Each

transcript is printed as a Word document with the view set to 'Final Showing Markup'

mode thereby showing the sequentially numbered comment boxes that contain the

EMM coding made and a short comment relating to the response identified.

Specific comments are referenced in this chapter’s findings by interview number

and comment number so that they can be readily located in Volume 2. For example, a

response identified in ‘Interview 9’ by ‘Comment 78’ is cited as (9:78). If responses

discussed below in the findings are not part of or immediately adjacent to a numbered

comment, the transcript reference is cited as being between two numbered comments as

in (4:35-36). In some cases clarifications or additional information was sought from

interviewees as personal communication after the interview and allocated the code

(6:pc).

As noted previously the average level of attainment for each category is on a zero

(very poor) to four (very good) indicative scale.

6.2 Interview Findings: By Coded EMM category

6.2.1 Energy Policy (EP)

Very few codings were made (19 in all), evenly split between Europe, National

and Local, were made for this category limiting its findings (see Section 6.3). In part,

this was because few respondents gave clear responses indicating any focus beyond the

headline targets.

Page 80: Policy and Value: A Case Study of Local Authority Energy Management and Investment

68

6.2.1.1 European Level

A lack of clear, long-term European and National targets beyond 2020 and toward

2050 was mentioned (1:14; 10:22). The strongly stated, but not binding, energy-saving

target (2:4) and legally binding emissions targets mandated by the ESD and EPBD

European Directives and agreed to by Ireland was noted (2:10 and also 3:39). Member

States and vested interests appear to have watered down the potential impact of the new

EED that was to have addressed the shortfall in progress toward the energy-saving

target (2:10; 2:6).

6.2.1.2 National Level

At national level, policy objectives are strongly stated, though water and public

lighting are elements currently overlooked by national policy (2:69; see also 9:79).

Water is now beginning to be addressed by SEAI working in coordination with the

CCMA (11:1). The declared policy aim in social housing is to upgrade them to a C1

rating but even before recent cuts in funding the likely outlook was that this would take

15 to 20 years so the target is much more distant now (7:17).

6.2.1.3 Local Level

In local authorities, a lower EMM attainment level of stated energy policy is

indicated by the responses. Noting current funding restrictions, an absence of set

enforced policy targets for local authorities and their departments was reported (3:25;

10:63-64,76). Doubt that the targets can be met, except due to economic recession, was

expressed, for example one respondent said:

Theoretically, we are supposed to be saving 20% by 2020, the public

sector was to save 33%. I do not know how. In a way we have been

saved by the downturn because everything has caved in. (10:74)

Page 81: Policy and Value: A Case Study of Local Authority Energy Management and Investment

69

Local energy action plans do exist though not in every authority (2:14). Dublin’s

Sustainable Energy Action Plan (SEAP) has been published but the DCC Housing

Energy Action Plan remains unpublished despite much work (10:21; 10:20). The

unclear housing policy means that retrofit projects are set up in an ad hoc rather than a

systemised manner by motivated individuals who work to establish individual projects

(10:10).

The seven sustainability themes of the Dublin Fire Brigade Green Plan, each with

results-based, sustainability objectives, are identified by Neil McCabe as critical to its

success, and to its adoption by DFB as their business plan this year (13:4; 13:3). From

now on, all decisions made by DFB will be framed by the Green Plan's themes and

objectives.

6.2.2 Energy Management Structure (MS)

MS codings were made when respondents referred to upper management buy-in,

energy management systems, communication, or responsibility of delegation of energy

matters. For the MS category, 87 scored codings were made with an average attainment

level of 1 and 2 respectively for National and Local levels (see Section 6.3). The mode

value was 1 in each case.

6.2.2.1 European Level

Highly departmentalised systems are evident at every level of governance creating

problems in setting up energy management structures due to ‘silo thinking’ and actions

restricting integrated communication (2:25,27). In Europe, Directorates General for

Climate, Environment, Energy and Agriculture all look at energy and emissions policy

separately and largely communicate with the corresponding departments in Member

States (2:70).

Page 82: Policy and Value: A Case Study of Local Authority Energy Management and Investment

70

6.2.2.2 National to Local Level

In Ireland, Departments and public sector bodies are often isolated from one

another (2:26) with departmentalised, silo thinking (11:27). There are also challenges

for Departments and SEAI in addressing energy management issues in the local

authorities due to the high degree of complexity in intermediate, local authority

administrative structures relating to energy (11:2,11:6). These can be addressed well on

a single-issue basis over time as, for example, in SEAI/CCMA work on water services

currently (11:1). Requirements, such as Display Energy Certificates are not being

complied with; they are not being checked by government agencies so they are not a

priority (8:28). The DECLG are overseeing funded-retrofit works on social housing to

ensure the limited funding (2:42) is well spent (7:11), but frequent meetings take place

between the DECLG and Local Authority architects (3:31; 7:24,25,26,33) that can delay

projects (2:44; 7:37) because negotiations often progress slowly (2:46) by being

“presented in a case by case fashion” (3:31) or by persuasion on a “case by case basis”

(10:43).

The National Procurement Service, which puts out tenders for local authority

energy supply, may lack the power or authority to press suppliers to meet public sector

energy management data requirements (9:87).

6.2.2.3 Local Level – Energy Management Engagement

Local authority energy management structures are at an early stage of

development (9:76; 11:67) and more integrated structures are needed to manage energy

at every level (12:27). Irish cities and counties have highly varied forms of energy

agency that have many different organisational models. There are small 'in-house'

‘agencies’ like the two person one in Co. Kerry (11:7); the not-for-profit Codema in

Page 83: Policy and Value: A Case Study of Local Authority Energy Management and Investment

71

Dublin (that is not an integrated part of DCC) (8:42), and Tipperary agencies; some of

which have closed down due to spending cuts, as in Meath (11:9); and there are some

areas without any energy agency. Across Europe, local energy agencies find it difficult

to establish effectiveness in improving public sector energy management (2:36).

SDCC have engaged with SEAI Energy MAP for four years (9:7) and DLRCC

have had an Energy Team for two years (3:1,5). In each of these counties, the County

Architects have the title of Energy Champion (3:1; 9:1). Though SDCC is now actively

addressing energy and emissions saving, previous efforts and reports have been sporadic

and the results have not been widely disseminated (9:76).

As energy costs have increased, management buy-in to energy concerns has also

begun to increase (8:40, 9:78). Dublin City has shown strong support for the Green

Plan work of Neil McCabe (13:2) but they have yet to engage with Energy MAP on any

scale (8:pc.) and there appears to be limited upper management drive for energy and

emissions savings (5:8,28; 6:41; 10:43; 12:37). DCC is an older and larger organisation

and less easy to change compared to younger authorities like SDCC and DLRCC (8:30).

6.2.2.4 Local Level – Communications, Data and Technical Knowledge

Good communications between and within DCC departments on energy matters

were mentioned (4:24; 6:1), but generally systems for good communication on energy

matters were frequently noted as deficient or lacking (2:24; 3:9; 4:7,11,34; 10:10,18,68;

12:2). Some good examples of energy management were mentioned, as shown by the

accessibility of DCC energy usage data on-line at www.dublinked.ie (6:12). SDCC are

similarly working on energy information transparency with a new website at

www.southdublinenergy.ie (9:66). Lack of technical skills (4:4), lack of time (4:6) or

resources (6:20,24), and limited authority for action (4:6; 6:2) were all cited as

Page 84: Policy and Value: A Case Study of Local Authority Energy Management and Investment

72

management difficulties in delaying or preventing energy-related decision-making. A

reliance on key personnel with a deeper knowledge of energy management issues whose

expertise may be lost to organisations when they move position or retire was mentioned

in DCC (6:7,8,29,40). This was also noted in Irish local authorities generally as a

current problem due to many retirements (11:17). A move to systemise knowledge has

occurred in SDCC in the technical retraining of staff to be able to undertake BERs and

assess retrofit possibilities (9:49).

A breakdown in ‘partnership’ between management, unions and staff within DFB,

initially made communicating the Green Plan very difficult and took three years to

overcome (13:14).

6.2.3 Implementation and Motivation (IM)

IM codings were made when respondents referred to the current degree of

motivation toward achieving the policy objectives and the current level of energy

management commitment. As in the EMM isolated or sporadic results were seen in the

grading as indicating piecemeal approaches, even where positive. For the IM category,

247 scored codings were made with an average attainment level of 2 for both National

and Local levels (see Section 6.3). However, the mode was 1 in each case.

6.2.3.1 European Level

European Union projects continue to support energy-efficiency programmes in

Ireland. The Minus 3% project, led by Codema in Dublin (2:19) tested the potential for

3% annual energy savings and achieved the target in the test year of 2011, reaching 6%

savings (using modelled rather than measured and verified results). Another EU

project, 'Re-Green’, though it is more about energy than other sustainability concerns

such as water and waste, is a current InterReg 4, EU programme that DCC Architects

Page 85: Policy and Value: A Case Study of Local Authority Energy Management and Investment

73

are engaging with currently, primarily with the aim of looking at their housing stock

(10:1,2). The level of deep building retrofit varies around Europe with exemplars being

Germany, which has a large number of external cladding projects, and the Nordic

countries, where there is large-scale use of district heating (2:52). In general, the

implementation of energy management all over Europe and at different governance

levels has had inadequate results:

I would not point the finger at anybody, there are a lot of good people at

local, national and European level, all in a way trying to do something

good but somehow it is not fully connecting. We all have to put up our

hands and say we could do better. (2:61)

6.2.3.2 National Level

Nationally, there are programmes aiming to implement policy such as: the

DECLG funded energy retrofit programme (7:1,3,40), with an aspirational target of

raising all social housing to a C1 BER rating (7:4,5); and the SEAI-administered Better

Energy Workplaces grant scheme, assisting local authorities to meet their 'glide-path’ to

the target from a defined baseline (11:26).

The DECLG programme's annual funding continues to be severely cut with a 58%

cut over the last two years – from €43 million in 2010 to €34 million in 2011, and down

to €18 million this year (7:3). Although limited in scope (7:8,15; 10:27) and only

funding the ‘voids’ (social housing units that become vacant), the DECLG programme

implements a policy of not re-renting F- and G- rated houses (7:29; 10:32). One result

of only doing voids is a lottery effect in that one tenant might get an C-rated dwelling

next to still-occupied G-rated ones for the same rent (7:17). For larger retrofit or new-

build projects, DCC and other local authorities rely on specific negotiated monies or

Page 86: Policy and Value: A Case Study of Local Authority Energy Management and Investment

74

have to bid for funds from Government grant schemes from multiple funding routes

(7:16), rather than budgeting from their own funding as a result of the highly centralised

form of governance in Ireland (10:46, also 2:47).

SEAI have developed Energy MAP to engage the private and public sectors in

their own programmes of energy management change (11:10) and so far about 21 or 22

of the 34 local authorities have engaged with it (11:12). Efforts to involve energy

suppliers (“obligated parties”, see 11:48) are beginning. They are being linked on-line

to local authorities as possible ESCo service providers through “EnergyLink” (11:16)

although this process is at an early stage (2:64; 10:6). The ISO 50001 international

standard of energy management, only currently used by UCC and the Defence Forces, is

seen as an exemplar level that bodies completing Energy MAP can aspire to (11:11).

Energy saving or cost saving, rather than carbon saving, are very much the focus

of current efforts by government (7:30; 1:18; 9:10,73). There are no implemented

carbon commitments as there are in the UK (9:52) despite the latest forecasts showing

that the emissions targets will be missed (2:10,11). An absence of enforced carbon

targets reduces the level of ‘push’ on public sector bodies (1:10; 9:53,54) but energy

costs are becoming a strong driver for savings, due more to the economic downturn than

to policy implementation (9:74). There is some doubt as to whether the EN1 form for

reporting energy consumption is now required by DECLG (5:41).

In Ireland, a past tendency to focus on technological pilot projects can be

identified, often additionally pushed by grants (9:93). A 'fabric-first’ approach, using

passive insulation and air-sealing measures, would be more robust in the long-term

(1:20; 9:94). There have been high achieving, local authority area retrofit projects,

notably in Tralee (7:35; 9:90,91) and Dundalk (10:8), though not on a broad scale

(1:11,12). Kerry County Council are noted as having done very well in having

Page 87: Policy and Value: A Case Study of Local Authority Energy Management and Investment

75

retrofitted most of their vacant stock and are now looking at retrofitting a number of

estates following on from the finished project in Tralee (7:36). Generally, the work in

Tralee has been practically focused on establishing a "virtuous circle”, motivating local

people, creating local employment and implementing behavioural as well as technical

solutions (9:92). In the public sector, the OPW have now installed building monitoring

in many of their buildings (11:21) as well as a ‘bureau-style’ technical service, so that

motivated building managers and users can call for energy saving advice, yielding high

returns in savings at low cost (11:25).

6.2.3.3 Local Level: Organisational Motivation and Change

In local authorities currently, motivation toward energy savings is affected by

poor billing and meter data, making it difficult to confirm usage if unexpectedly high

bills are received (4:12; 6:12).

Codema, as the energy agency for Dublin City, are assembling a Microsoft

Access-based database of all Dublin City energy accounts keyed by unique location

numbers, accessibly storing information from energy bills and surveys of buildings

(8:11,13,20). It is a complex undertaking requiring large amounts of data collection and

checking (8:20,46). Codema's survey audits are continuing and to date these have

proceeded by building type: Fire Stations (13:42), Libraries, Depots, Motor Tax Offices

and Leisure Centres (8:11). They are also surveying buildings for SDCC (9:19) and

Fingal County Council, and the plan is to ultimately survey all council buildings

regardless of size (8:9). Students on work placement have been undertaking these

surveys (8:8) but the aim is to have a graduate engineer for future surveys so that the

DEC ratings produced can be officially certified (8:10). Codema’s aim is to work “from

the ground up” when working with DCC departments on energy projects rather than

from a position of authority (8:43). Codema were described, uncertainly, as a source of

Page 88: Policy and Value: A Case Study of Local Authority Energy Management and Investment

76

energy saving initiatives (6:33) and information (13:34,35,36), but their resources and

scope were described as somewhat limited (9:81; 10:44).

In the manager in overall charge of DCC Leisure Centre,, out of his own personal

interest, has been attending a three-day energy management workshop (4:4-5).

In SDCC, there is a monthly meeting of a committee looking at energy efficiency

(9:20). A register of energy saving opportunities has been produced (9:18), and a heat

map of Tallaght is being used to identify supply and demand for assessment of district

heating potential (9:26). The county has a total housing stock of 9,200 houses and two

areas of social housing, North Clondalkin and West Tallaght, which have been

categorised as suffering from deprivation (9:4). Before the economic crisis of 2007-8,

the SDCC annual capital budget was about €60 million and many new civic buildings

including leisure centres were built. After 2008, with little new work in prospect, the

county's clerks of works were retrained as BER assessors (9:11) looking toward

retrofitting of buildings. Having carried out many BERs and cross-referencing with

published [SEAI] information, it is expected that within about six months there will be a

better understanding of the BER-rating spread of the housing stock (9:34,36). The aim

is to go beyond retrofitting alone, to increase the information circulation and reduce fuel

poverty (9:37).

In Dun Laoghaire, a steep learning curve was noted as being required to track

down consumption and cost for individual properties, using bills and collected meter

numbers (3:4). In the Dublin area, the amount of significant retrofit, other than social

housing void upgrades, has decreased to a low level with only a few projects being

mentioned (2:65; 5:39; 10:3,4,30).

Page 89: Policy and Value: A Case Study of Local Authority Energy Management and Investment

77

6.2.3.4 Local Level: Motivating Behavioural Change

Responses did not indicate that any results-based behavioural change programmes

within departments other than Codema’s Switch-Off Campaign were occurring or

planned. Nevertheless, motivating behavioural change was mentioned by several

respondents as being important in addressing change toward good energy management,

for example:

Who decides what the level of the bill is; it is really the staff (12:14)

In all three authorities, public awareness (9:66,67) and communication with the

residents of retrofit projects was identified as important, both in the retrofit process and

in understanding monitoring or use after retrofit (3:17; 9:37; 10:62). Similarly,

motivating staff to save energy is seen as very important (3:6; 12:4,35; 13:8) and

Codema's Switch-Off Campaign was mentioned (2:20; 3:6; 5:31). However, outside

DFB, implementing behavioural change was reported as being difficult (9:77) or slow

(12:24,25). There have been a number of significant difficulties, particularly a lack of

readily available behavioural or technical advice (4:29,32,35,43; 9:69; 10:81; 11:41;

12:36) but there are no plans to extend the OPW's so-called bureau-style technical

advice service because of cost constraints (11:22). ESCos could provide such a service

in future as part of their contract, if the ESCo funding model becomes more commonly

used (11:41).

One respondent identified self-motivation, obligation and incentives as

alternatives for motivating behavioural change (12:29). Obligation was identified as an

important driver (10:77; 12:6,7) needing firm policy requirements; and the possibility of

financial incentives was mentioned – possibly part of the savings might clearly be

identified as then going toward improving the facility where staff work (12:30).

Page 90: Policy and Value: A Case Study of Local Authority Energy Management and Investment

78

In DFB, after spending two years developing the Green Plan in his spare time

(13:1), Neil McCabe identified community-linked behavioural change as a core,

ethically and morally motivated principle (13:18,45) to be additionally motivated by

intentionally visual projects in the initial phase at Kilbarrack (13:17):

Everyone talks about the technology I have invested in but the reality is

that I did everything else first. When I had the behavioural side changed,

the renewables side of it was as a solution, and not as individual

products (13:45).

McCabe has written extensive guidance documents for DFB advising on behavioural,

technical and procurement management (13:22).

The term ‘energy champion’ was used in different ways by different respondents.

In South Dublin and Dún Laoghaire, interviewees immediately volunteered it as a

particular upper managerial position (3:1; 9:1). The local example of Cormac Healy at

Poppintree (12:15,31) was identified as a possible precedent for establishing each of the

leisure centre managers as a local energy champion (4:5). A view from two respondents

was that, although locally valuable and highly motivated, local energy champions and

projects usually have a very limited overall effect in comparison to improvements made

in wider scale management structures and programmes (2:65; 11:66).

In the locally instigated project at Kilbarrack the firefighters are leading both

organisational and community change (13:3,13) benefiting from Neil McCabe’s Green

Plan work and guidance. One respondent said of McCabe:

He is a great genius in his own way. He has a very clear, simple

understanding of what has to happen. It is an amazing achievement

Page 91: Policy and Value: A Case Study of Local Authority Energy Management and Investment

79

starting with one guy. The way he has brought in older retired guys and

local children; he has an innate understanding of sustainability (9:89)

6.2.3.5 Local Level: Retrofitting

Technical guidance for retrofits is about to be published by the DECLG (1:17;

10:26). Retrofits need to be deep to avoid having to revisit the building (1:16) and are

best achieved on an area basis (1:16) as in the exemplar case of Tralee (7:35; 11:7).

Area retrofit is at very early stage of consideration in Dublin City (10:19). Detailed

technical reports have been made from past projects on how to make savings, like that

for the Minus 3% project (2:16).

Dublin’s council areas differ in their history and building mix: Dublin City and

Dún Laoghaire have older buildings compared to South Dublin and Fingal which

generally have newer civic buildings and housing (9:64).

SDCC are looking at the potential for district heating and CHP in Tallaght

utilising, and potentially linking, the heating and cooling loads of the Civic Offices, the

Square shopping centre, Goodmans food, the hospital and likewise in large data centres,

possibly by means of a council-run ESCo (9:26-27). The facilities manager in the DCC

Civic Offices is making progress toward re-instating rainwater harvesting and installing

photovoltaics (10:67).

In the leisure centres, the ease of access to building controls was stressed. All

main lighting switches are ideally located at reception (12:34) and BMS control laptops

have to be easily accessible to facility managers, so that they are easy to use to match

heating to timetabled room usage – currently they are not easily accessible in some

centres (12:5).

Page 92: Policy and Value: A Case Study of Local Authority Energy Management and Investment

80

A slow pace of retrofit was described in Dublin City (7:37) although deeper

retrofit is designed in where possible (10:45). Given the history of new-build projects,

there is a relative lack of retrofit experience among City Architects (10:47) and a lack of

in-house technical knowledge of retrofit analysis software (10:54). Expert retrofit

analytical advice was sought for retrofit design in pre-crisis years, as on the Glover

Court’s gullwing flats, but is now less likely to be engaged due to cost constraints

(10:60) though it may be needed (10:53). This is also the case in SDCC (9:69).

Piecemeal measures such as drylining of individual units in retrofitting terraces and flats

were identified as normal current practice (7:19,28; 10:52,60), even though the

knowledge that external insulation was a preferable and superior retrofit solution was

clearly stated by respondents (7:19,36-37; 10:29,50).

Lack of funding (10:30-31) and lack of motivation (7:37) were both cited as

reasons for not cladding externally – for example on apartment blocks like the 'gullwing'

apartments and Dolphin's Barn's flats. In Dolphin House flats, there may be a slightly

increased risk of condensation in the un-retrofitted flat neighbouring a flat that is

retrofitted with internal insulation, due to a cooler shared internal wall junction with the

exterior wall (10:53). Glasgow was able to carry out external insulation on a large scale

(7:37-38) despite tenancy-ownership issues. This would not be an issue in Ireland

because local authority apartment buildings are fully owned by the local authorities

simplifying such a potential program of external cladding (7:39). A need to identify

durable, technical solutions for active measures in houses like fans, vents or heat

recovery ventilation was expressed (9:40), with the proviso that they all require regular

maintenance, filter changes and inspection. For social housing though, these could be

combined with the annual boiler and smoke detector inspections (9:39).

Page 93: Policy and Value: A Case Study of Local Authority Energy Management and Investment

81

In DFB the technical experience gained by the Green Plan has included research

into the component parts of technical retrofit measures providing investment data on

facts, prices, carbon emissions, and water and energy reduction. (13:21). A trial of new

technology affecting the DFB fleet has been implemented that is likely to yield savings

of 11% in fuel and 19% in carbon emissions (13:36).

6.2.3.6 Local Level: Management Commitment and Funding Potential

Energy costs are becoming a driver for upper management to buy in to changes

toward energy management (5:36; 9:50,54) as financial resources have reduced.

Generally though, public buildings and housing have been worked on as they are seen

as needing repair, with some energy upgrading, but not with a management or funding

commitment to longer term, deeper or rolling retrofit solutions (2:54). Operational

budget reductions are now restricting implementation of energy measures such as

monitoring and energy usage audits and surveys (4:21; 9:48). However, SEAI are

pushing for more audited measurement and verification in future (11:37). Councils rely

on European and Government funding for their energy programmes such as LEAP, Re-

Green, the Sustainable Energy Community Programme, as they do for supplementary

programme funding generally (9:67).

The economic downturn has led to an even slower rate of building replacement

and retrofit in the local authorities (9:31; 10:83). The need for savings has led to

decreases in energy use but only at about the same rate as energy costs are rising, so the

overall bill has remained much the same (5:33). Grants like those from SEAI can only

provide 'pump-priming' (2:50; 10:36) and application preparation times may be large in

proportion to the small amounts of grant funding available relative to overall council

budgets (11:42).

Page 94: Policy and Value: A Case Study of Local Authority Energy Management and Investment

82

SDCC have found that promised grant funding from SEAI can be very slow to

arrive, delaying implementation of measures (10:55) and grant application and closing

deadlines cause significant implementation difficulties (9:56).

The market for private funding for public retrofit or energy management is at an

early stage of development (10:9; 11:18) because there is a lack of expertise in

investment assessment leading to management uncertainty over the potential gains

(11:64). DCC have been talking with an investment company to establish an energy

investment fund, but as yet no clear timeline has been set for it to proceed (10:40).

Moves toward involving energy suppliers are not yet underway either (10:17).

One respondent described motivation of the public sector toward achieving the

33% energy savings as poor:

They have not really started the road map to actually achieve it. It is just

a figure, there has been no real effort put into how they are going to do

it. (1:10)

6.2.4 Investment and Cost Analysis (CA)

CA codings were made when respondents referred to the current budget

constraints, retrofit planning, grant funding or investment cost analysis methods that

affect the future usage of energy or emissions of carbon dioxide. As in the EMM,

energy cost control concentrating on price alone, on low cost/fast payback requirements,

or using simple payback appraisals, were ranked less highly than cost control and

planning using on-going portfolio and integrated investment appraisals that rely on

rationally-decided, value-driven objectives. Isolated or sporadic results, even if good,

were seen in this grading as indicating piecemeal approaches.

Page 95: Policy and Value: A Case Study of Local Authority Energy Management and Investment

83

For the CA category, 135 scored codings were made with a low average

attainment level of 1 for both National and Local levels (see Section 6.3). The mode

value was 1 in each case.

6.2.4.1 Budget constraints

Public sector budgets in Ireland largely rely on single financial year accounting,

restricting all government bodies to spending only the monies allocated for the current

year (2:57; 11:43). Such constrained grants militate against longer term, deep retrofit

projects (2:58). Larger building and infrastructure projects often have five-year capital

budgets, but there are currently few such projects occurring (3:10; 5:37) and these are

not commonly used for retrofit projects (5:38). Capital budgets are held separate from

current spending and any savings made in a year’s current spending budget must be

spent by the end of the year, they cannot be ring-fenced to provide future capital or

operational spending (10:72). Illustrating this, a DCC community centre was built for

€3.5 million and the capital was found with little difficulty, but the annual operating

cost of €300,000 was much more difficult to agree (10:73).

Local authority accounts are monitored on a quarterly basis, to be scrutinised by

the DECLG, and also now for the IMF (5:32). Current spending is consequently highly

restricted (6:37). For SDCC, this year's current funding from the DECLG was reduced

in August by €1.9 million because of a shortfall in household charge collection, which

will have to be saved out of the remaining operating budget by November (9:60). This

effectively stopped all maintenance operations and reduce the scale of individual

retrofitting. DECLG have told SDCC to cut re-wiring from standard refurbishment

works as a result of the funding cuts (9:61,62).

Page 96: Policy and Value: A Case Study of Local Authority Energy Management and Investment

84

Dublin did have household rates previously until rates were abolished in 1987

(2:49) but a large part of the income for Irish local authorities now comes from rental

and grant monies (7:38). Before the financial crisis revenues from new build site fees

were large (2:49-50). Money was also brought in from selling housing, and in DCC this

was largely spent on housing refurbishment but this revenue source is now closed

(10:38). The financial situation means that very little borrowing is currently occurring

and relatively few capital projects are now in progress (5:40). Local authorities often

have to be creative to obtain funds, bidding in combination with other groups to meet

partnership rules for particular programmes (9:41). Sourcing funding for the authorities

can be complex, flowing from different government departments and through schemes

that change on an annual basis (2:48; 10:14).

In other countries, local authorities have more control over their own budgets, for

example:

In Birmingham [recent winner of the World Green Building Council

award], they have their own budgets that they can allocate; the problem

here is that the local authorities cannot and that is the big problem in

Ireland. The local authorities only have the discretion to bring forward

projects that are then dependent on the approval of the Department of

Environment to carry them through (1:9)

In Dublin City, the energy spend in 2006 was €22 million (Minus 3% project

figures) including water and public lighting (8:1). Within DCC the staff and running

costs for each building are allocated to a 'cost centre' in the accounts (5:3). Department

managers are responsible for their own cost centres, so they have to monitor and control

their own costs including energy costs (5:8) though they may find it difficult for energy

usage in the absence of billed consumption to check the costs incurred (4:10).

Page 97: Policy and Value: A Case Study of Local Authority Energy Management and Investment

85

For the leisure centres, the yearly operating budget is for daily running costs and

if unexpectedly large costs arise they have to be saved within in that budget (4:20). The

budget has become tighter in the recent years so that adding to sinking funds (making

savings from the current year to allow for eventualities next year) is very difficult: “it is

done almost in error rather than in a planned way” (4:20, see also 9:59). A recent large

cost was receiving an unexpected arrears bill for €50,000 from an energy supplier, this

amount then immediately being taken out of the cost centre account for Ballymun

Leisure Centre. Due to the hard copy bill being in the Finance Office and being time-

consuming to locate and read, it has been difficult to substantiate the related

consumption (4:17,46,47; see also 2:35).

Tight departmental annual budgets mean that monies, and technical or investment

appraisal advice, are not available, even for low cost retrofit upgrades which are

sometimes offered by suppliers at low or no initial cost on an ESCo basis with

guaranteed overall savings compared to current energy bills (4:25,26).

6.2.4.2 Retrofit Planning and Funding

Since the 1990s, larger social housing upgrade programmes in Ireland, funded by

Government grant aid, have been carried out by local authorities installing particular

measures in schemes including replacement windows, draught stripping, and attic

insulation (9:28,29). It can be difficult now to identify the houses where this has been

done and efforts are being made to map past retrofits to establish which measures were

installed where (9:30).

Despite the government energy and emission targets, the diminishing budgets

available from the DECLG and from the DCENR through SEAI for retrofitting are

likely to greatly restrict progress toward achieving them (7:21,32). The limited funding

Page 98: Policy and Value: A Case Study of Local Authority Energy Management and Investment

86

available for social housing (7:8,15) means that a programme of large scale retrofit will

not occur in the current budget environment (7:28,29). The DECLG, provide the

funding for social housing energy retrofits and were reported to receive monies from the

DCENR for a third of the carbon savings (10:14).

Like other annually released grant monies the DECLG funding brings time

constraints. In Dún Laoghaire, to retrofit a building for the elderly, health and safety

concerns, contractors and external consultants had to be in place in order to start on site

in July and have the works completed in time for post-works BER assessments to be

submitted in mid-October for the council to draw down the funding (3:32,34). For the

27,000 housing units owned by DCC energy retrofit monies are supplied by the

DECLG:

A lot of the control, management and funding comes from the DECLG

and the Council is more a manager of that. There is an idea that the

Council has total responsibility if the flats are run down. It is as much a

reflection on the Government as it is on the local authority, even more so.

(2:45)

An example is the Dolphin's Barn flats that have had serious damp and mould

problems for years (10:48,49). The flats are now undergoing a rolling program of

piecemeal retrofit of the most seriously affected flats, "probably funded by way of

special pleading to the DECLG”, with a possible regeneration beginning in about three

years time – in 2015 (10:50).

In local authorities, investments in retrofit measures in the highest consumption

accounts, usually Water Services, Public Lighting, and larger buildings, can save very

large amounts of energy – a high Pareto effect that SEAI hopes to help them address in

Page 99: Policy and Value: A Case Study of Local Authority Energy Management and Investment

87

a structured way with Energy MAP training (11:13). This year’s SEAI Better Energy

Workplaces grants are not intended to fund projects that are already financially viable:

If a grant was given on purely financial terms you would not need a

grant, because if this building showed a 20% saving say, and it would

pay for itself in three years, why would you want to grant-aid that? To

give a grant toward that is probably a bad appropriation of public funds

because they should be doing it anyway, you should not need a grant to

do something that is commercially viable. Grants are brought in to

incentivise something that is not happening in the marketplace.

(11:45,46)

In grant application reviews, private sector applicants are vetted as to whether

they really need the money, this is less so in local authorities where budgets are tight

and the money is always needed (11:60). Applications were judged on the basis of

seven criteria including employment provided and new forms of procurement

mechanism (11:61-62). The involvement of energy suppliers or ESCos was encouraged

but very few, or no, local authorities applied in this way, partly because ESCo funding

is considered to be debt on their accounts (11:49). Another aim of the grants is to

encourage retrofits that include multiple project elements and/or involve many sites all

carried out by one applicant (11:52,53). Nonetheless, in grading the applications there

are "a lot of marks for the financial business sense" to ensure that it is a replicable

project (11:61). The annual timeline of grants, funded by Government and the EU, is

very tight. The rules and guidelines for each year's project are usually different,

delaying applications that will then also have to be laboriously evaluated, producing “a

strong administrative burden” (11:44). If approved there are usually only a few months

for applicants to confirm and procure the project. This means that:

Page 100: Policy and Value: A Case Study of Local Authority Energy Management and Investment

88

For the SEAI grants the timeline can be such that the grants are open for

application at the beginning of June and they expect the works to be

completed by the end of September and the verification carried out. So

that timeline is such that you are dependent on grants being available,

but you are supposed to have your ducks lined up in a row beforehand.

A lot of work may have been expended and maybe external consultants

retained to get various things to get the grant, which may not even go

ahead or it may be changed or tweaked, or your project may not be

deemed acceptable. (10:32)

In Dublin Fire Brigade, the Green Plan is now at a stage where the ring-fenced

funding produced by the significant retrofit savings at Kilbarrack, verified by SEAI, are

now funding further retrofit without the need for further grant funding:

It is self-generating. It is money that did not exist and the most

important thing from the ring-fenced saving fund idea is that, say at the

end of this year 2012, we have all the savings from Kilbarrack plus all

the savings from Phibsborough now in the one pot ready to go to the

next fire station. Already that fire station has been chosen as the Fire

Brigade's workshop, the garage in Stanley Street, where we service all

of our vehicles. That fire station/workshop has already undergone part

of its transformation before the year is even finished and I am still not

even asking management for money. (13:10)

By establishing monitored baseline results the DFB intend to go to the private

market for ESCo or PPP funding with a good knowledge of current consumption and

performance (13:26). The technical and investment research carried out by Neil

McCabe, as well as M&V reports, will allow a more informed judgement to obtain the

Page 101: Policy and Value: A Case Study of Local Authority Energy Management and Investment

89

best value from offered investments (10:35). Onerous ISO 14064 auditing has also

been satisfied, allowing carbon credits for the retrofit savings achieved to be sold,

providing further revenue for the retrofit fund (13:43; see also 1:7; 10:66).

6.2.4.3 Retrofit Grant Funding

One of SEAI's aims is to lengthen investment periods to five or ten years, ideally

through the use of ESCos, and avoid funding applications that are just looking for quick

paybacks (11:53). SEAI offered some workshops at the beginning of the BEW scheme

but applicants are not given any particular guidance on the lifecycle to be considered in

calculations (11:56). Life cycle costing concepts were noted as, "only just starting to

come in" so applicants were not using those methods for their applications (see also

11:57). In BEW applications sub-projects submitted were allowed to pass with only the

investment simple payback filled in but applicants were given a few more marks if they

entered a Net Present Value amount (11:55).

At the DECLG, the proposed housing retrofit programs are funded on the basis of

achieving upgraded BER ratings above an F-rating. An improvement in excess of

300kWh/m2.y would receive 90% funding per dwellling up to a maximum of €15,000;

the next band down is above 200 kWh/m2.y; and some funding is available for

improvements of more than 50 kWh/m2.y (7:10; 10:27). BERs are required before and

after the retrofit.

The pre-works BER is used as a basis to assess each measure in an assessment

spreadsheet to give an estimate of the payback before proceeding with works (7:12).

This spreadsheet calculator, made by the DECLG, has been issued to councils for them

to do a cost analysis of measures (7:13). Ideally, a payback of fewer than 15 or at most

20 years is acceptable (7:22). In some cases, not using this design support tool led some

Page 102: Policy and Value: A Case Study of Local Authority Energy Management and Investment

90

councils to invest in measures that did not upgrade the BER rating and failed to obtain

the funding (7:27). Some BER assessments seen have very large 1200 kWh/m2.y

energy use [a G-rating is for houses using over 450 kWh/m2.y] showing the need for

upgrading works (7:27-28).

The DECLG architects offer general advice and guidance toward carrying out the

most cost effective and beneficial measures, so they do not check detailed designs.

They provide an overview, comparing retrofit costs between councils on the basis of

euro/kWh.m2.y improvement, an example shown resulted in retrofit costs of

€31/kWh.m2.y (7:31).

6.2.4.4 Investment Cost Analysis in Local Authorities

While binding targets are not yet in place (2:55), they would force investments to

be made but currently there is no funding to meet them (7:31-32). Local authorities

have generally not done cost analysis of energy related costs because energy has been

seen as a relatively cheap overhead (8:41). However, energy costs have risen rapidly in

recent years (8:37) so that making savings has become important (9:47,68).

In retrofitting public buildings, as at Crumlin Swimming Pool, repairs are

prioritised but energy upgrades are not a main focus (10:5). The economic crisis has

made current investment payback time horizons as short as a couple of years (2:56; see

also 1:4), even though a reasonable time horizon for a building appraisal might be 30

years, with about 15 years for elements such as heating systems (2:77). Deep retrofits

may have longer paybacks but also have significant, wider, ‘public good’ benefits such

as healthier, more comfortable public buildings and publicly owned social housing

(1:5,6).

Page 103: Policy and Value: A Case Study of Local Authority Energy Management and Investment

91

Councils currently see simple payback as the primary appraisal measure as it is

the metric used by DECLG grants (3:25-26; 10:70,71). However, even fast payback /

long service life items, like pumping cavity walls with insulation, are not being

sanctioned now because they require initial investment and organisation (6:34; 10:41).

LCC on longer periods was noted as being potentially complex, which might be off-

putting, but it would be a good start if it became required standard practice in all public

building assessments (1:1,3). The gullwing flats in Dublin are sixty years old so:

You could argue they have paid for themselves so you could demolish

them, but also you could extend their life. Demolishing and rebuilding

would cost €10 million for Glover Court, just as a rough idea, and our €3

million [retrofit] job would have enlarged the flats a little bit as well…

(10:31)

LCA (not LCC) was noted as being too complicated by another respondent (3:26)

and cost saving analysis instead is aimed toward the DECLG guidelines based on

individual measure paybacks and BER targets (3:22,27,28). Lifecycle 'demolish or

retrofit' decisions on older houses and buildings are not being made when considering

the existing stock (10:82) and planning for the long-term uncertainties such as fossil

fuel availability is not being done (10:80, see also 1:15). Budget constraints mean that

life cycle costing on terms of over 20 years is not possible now for local authorities:

You cannot do it. You cannot even plan for the age of the stock over a

longer arc. Anyway we will see how it goes, this is all a function of the

moment; it was not like that before, so we will see. (9:63)

Page 104: Policy and Value: A Case Study of Local Authority Energy Management and Investment

92

6.2.4.5 Investment Co-Benefits and Energy Billing Data

Current cost analyses do not take into account potentially large co-benefits of

retrofit such as health or comfort that could address fuel poverty (3:15; 9:35) though it

is known that there are studies showing significant resultant health savings (1:6,18,19;

10:61,68,79). This could be because it might be "quite a difficult thing to achieve or to

monitor" though it is clear that feedback following a retrofit of elderly social housing

showed that there was a “substantial improvement in peoples comfort conditions that

was an integral part of our work” (3:15-16). Social housing can be very poor in quality,

but the councils have no financial incentive to improve dwellings because it is the

tenants who pay the energy bills and if a dwelling is improved the rent paid does not

increase (10:11).

DCC departments find it difficult to obtain energy data to establish baselines,

against which to judge savings, because energy consumption amounts are not easily

available being only printed on hard copy bills, whereas the costs arrive in digital form

without attached consumption data (4:16,17; 5:16,22). Councils lack expertise in

investment appraisal of retrofits (10:39) and have a limited leeway in budgeting:

The big problem though is that capital budgets are separate from current

spending so that savings in current spending do not end up being

available for capital. It is quite often a problem (10:72)

Due to cost, specialist advice is not being sought in retrofit investment decisions

(10:84) and experimental projects often carry higher risks leading to higher costs (2:76).

Neil McCabe has had no specialist advisors to assist with investment planning (13:19)

for the Green Plan so over three years he carried out detailed technical research to

establish source selection criteria, potential savings and lifecycle costs for possible

Page 105: Policy and Value: A Case Study of Local Authority Energy Management and Investment

93

retrofit measures (13:20) – the resulting information is about to be published as Green

Public Procurement and Investing in Climate Change (13:22).

6.2.5 Monitoring and Targeting (MT)

MT codings were made when responses referred to: any energy saving or carbon

emissions targets (meeting the headline target or any intermediate/departmental targets);

monitoring or metering of buildings; or to data analysis and reporting. For the MT

category, 99 scored codings were made with an average attainment level of 1.5 for both

National and Local levels (see Section 6.3). The mode was 1 in each case. Looking at

targeting alone, 18 codings were made with a mode value of 0.

6.2.5.1 Targets

Delays in achieving energy saving targets in buildings are likely (2:62) as there

will be no strong push until firm figures are available (8:44), and it is likely that Ireland

will in any case have to buy carbon credits in order to meet its legal obligations (2:9).

The overall 33% energy-saving target has yet to be connected with what is happening in

the public sector (11:68). The targets are essentially meaningless because there is a

large amount of uncertainty in the current baseline data due to a lack of reliable

information and different estimating methodologies (2:21,37). This means that it may

not be possible to know when the target has been achieved (9:75). One respondent

stated:

I do not know if they will really be able to hold anyone accountable to the

figures because they are not robust enough at all yet due to so many

uncertainties. Even for the stuff as simple as the actual utility bills there

is so much uncertainty. (8:45)

Page 106: Policy and Value: A Case Study of Local Authority Energy Management and Investment

94

Disaggregation of the overall target figure, so that it is budgeted at each level for

councils, departments or facilities, is at an early stage of consideration (11:65). There is

also a need to keep track of the interdepartmental aspects of reaching the 33% target

(11:27), but no such accounting for variable achievability is currently occurring

(2:29,34,68; 4:38; 6:37; 10:64; 11:64; 12:44) and no mention of annual targets was

made by respondents. It may be best for targets to be set at building and facility level if

they are to be meaningful, so avoiding the segregation problem of separating the target

among departments (2:72).

6.2.5.2 Monitoring and Metering

At national level, SEAI have recently collected 30,000 MPRNs and GPRNs so

there will be a much better estimate of public sector electricity use, but there are still

reporting gaps (11:32). In the recent SEAI/CCMA report, local authority energy use is

divided into Water Services; Public Lighting, and Unallocated, which includes buildings

(8:2).

In Dublin, there have been problems in locating and reading some meters

(6:11,27) and gas meters have been hard to check with Bord Gáis (6:13) but most have

now been captured (6:15). Collating meter numbers and MPRNs over the last two to

three years enabled the council to find meters where bills were being paid in unused

locations and savings have been identified (6:26,31,36). A display screen showing live

meter readings of the Civic Office’s energy and water usage has recently been installed

in the lobby area of the complex (4:40). Automated monitoring of the Civic Offices is

now in place (2:40), but generally very little metering or sub-metering is occurring in

buildings (3:7) and a great deal more needs to be done in verification of savings

(2:29,30). Funding for monitoring is currently lacking (11:38) and would have to be

paid for out of operating revenue funds (4:21). There is often a large gap between the

Page 107: Policy and Value: A Case Study of Local Authority Energy Management and Investment

95

design specification of facilities and the actual performance in practice but often no

allowance is made in budgets for follow-up performance verification:

There is not much connection between capital and current accounts. It

would be much better if there were. So you can get money for capital

investment, but it is hard then to get money from a current account to run

[M&V] on a day-by-day or week-by-week basis. (2:75)

Modelled rather than measured and verified figures are often being used when

reporting savings (2:74; 10:57) and these have built-in uncertainties so IPMVP is

probably needed to increase accuracy in verification (11:38). Agreement has been

reached with the residents of Dolphin House to install energy and condition monitors to

verify performance after retrofit. (10:56). Monitored sub-metering in public buildings

would be ideal but, currently, monitoring of incoming metering will be the easiest to

achieve but there are delays in implementation (11:39). BMS systems are commonly

designed to work with automatic logging systems but these have not been installed and

would cost money to monitor (2:40; 3:38; 9:46; 11:24). One respondent said:

I think we have to somehow start getting into a different world. Even the

BMSs, we cannot read them and we do not know what is going on. We

have to find ways so that there is real monitoring and control. (9:95)

External technical expertise in monitoring has been successful recently in making

savings, such as locating and addressing air loss at the civic offices recently (6:35), and

has been usefully consulted in the past for other projects (10:58).

In the leisure centres there is no automatic monitoring installed (4:30) and

specialist advice would be needed if they were thought to be required (4:21,30). The

only leisure centre meter reading known to be occurring is in Poppintree Leisure Centre,

Page 108: Policy and Value: A Case Study of Local Authority Energy Management and Investment

96

by Cormac Healy, the Duty Officer there (4:5,16; 12:8). There has been a lighting audit

at Ballyfermot Leisure Centre recently with a recommendation not to replace lamps

until required by the light level and then put in LEDs as necessary (4:28).

In DFB, a high quality BMS system with monitoring has been installed in

Phibsborough Fire Station and it was recommended that every fire station should have

one (13:27-28). At Kilbarrack, work was required to get around not installing a BMS,

the cost of which helped to justify the measure in future retrofits (13:27). Flowmeters

are being used at Phibsborough and Kilbarrack to monitor rainwater and wastewater

(13:31). However, there is no national or local system of water metering so there is no

push to do this monitoring other than the ethical push from the Green Plan (13:30). A

two-year project, flow monitoring the pressure and volume water usage of a fire engine

has been carried out, which may well change the way firefighters use water to fight fires

(13:34). A large energy trial, funded by Green Plan savings, is happening across three

DFB locations and is being independently monitored by SEAI using IPMVP standard

M&V (13:25).

6.2.5.3 Housing and Public Lighting

There is a clearly defined target of a C1 rating or a 200 kWh/m².y improvement in

BER set by DECLG although funding only allows upgrading of voids and there is no

deep general retrofit policy (7:7,17). Both pre- and post-works BERs are required to

verify the baseline condition and the retrofitted condition to qualify for grant money

(7:12,17; 3:13,37). In SDCC since 1999, fabric and heating systems have been

upgraded in social housing including, out of 9,200 houses in total: 2,000 cavity wall

insulations; 2,800 heating upgrades; 900 double glazing upgrades from single glazing

(9:11-12). Based on BERs the estimated average energy saving for renters is 37%

(9:25). In Dublin there is some sample information on the social housing stock

Page 109: Policy and Value: A Case Study of Local Authority Energy Management and Investment

97

estimated by Codema based on BER information gained by work done on voids (10:78).

More transparent reporting and accepted comparative indicators of housing energy and

carbon emissions performance would help comparisons domestically and internationally

(9:67).

The Public Lighting electricity supply is unmetered and therefore unmonitored

(8:3; 9:79; 11:28) and existing metering systems are unable to read ‘virtual meters’ that

can now be installed in street lighting (11:30). However, large energy use cuts in Public

Lighting and Water Services as well as buildings are needed if the policy targets are to

be met (2:67).

6.2.5.4 Data Availability, Accounting and Analysis

Many councils nationally lack rigorous energy data reporting or monitoring

(11:15,23,33; also 8:5) and in some cases it may take three or four years before it is

more complete, though a high percentage of it is now available (11:27). Much more

energy data is being required by SEAI from public sector bodies this year so that the

energy in total usage across all fuels will be known and showing whether they are on

track to meet the 33% target (11:34).

DCC corporate services have been collating total energy consumption for the

whole council since 2010, by obtaining figures from the council departments (6:2,32;

8:6). DECLG have said this reporting is no longer required but DCC are continuing to

collect the data (6:4,5); in SDCC it is thought to be still required (9:51-52). The EPA

carbon management tool is in use by DCC to collate data (6:30) but carbon emissions

are not reported in the Annual Report (6:28). There are still gaps and approximations

in the data, in part due to different bill payment centres in addition to the Finance Office

(6:14), and data has to be typed in with reference to paper bills making data collection

Page 110: Policy and Value: A Case Study of Local Authority Energy Management and Investment

98

and processing slow (6:23). Currently there is no cross checking with the Finance

Office of the entered consumption figures against the corresponding individual or

overall cost figures (6:22). Many of the indicators used in reporting councils’ energy

usage have large, in-built uncertainties (9:21).

In the leisure centres there is a strong awareness of energy usage because it adds

up to about 20% of running costs in many cases, and because energy efficiency and the

environment are concerns important to DCC (4:1,2,3). At Poppintree Leisure Centre an

initial baseline of energy usage has been established and comparisons between present

and past readings are now being made (12:21).

At Kilbarrack Fire Station, the Green Plan financial savings have been verified by

DCC and the energy accounting has been stringently audited to comply with ISO 14064

standards (13:43).

6.2.6 Data Provided by Energy Suppliers (PD)

PD codings were made when responses referred to the data quality or the ease of

data availability provided by energy suppliers. For the PD category, 28 scored codings

were made with a low average attainment level of 0.9 (see Section 6.3). The mode

values were evenly counted at 0 and 1.

6.2.6.1 Energy Supplier-Provided Data

DCC energy supplies have been arranged through the National Procurement

Service since about early 2011 (5:1) and there are currently about six energy providers

(6:18) in all, not including Public Lighting which is a large and specialised account

(5:2). Most providers send both soft copy (digital bills) and hard copy bills in to the

Finance Office in different formats and on a variable basis, often monthly (5:1,4). The

Finance Office only looks at the financial costs, including energy bills (5:7-8); Codema

Page 111: Policy and Value: A Case Study of Local Authority Energy Management and Investment

99

and Corporate Services look at consumption to some extent (5:18). Supplier billing is

focused on money so the soft copy data gives a cost and an meter reference but does not

give the associated consumption figures (5:22), which are located on the hard copy

paper bill (5:16) and cannot be easily interrogated, requiring manual processing making

it comparatively useless (5:22; 8:18): “The utilities are not supplying the kind of data

that would be valuable for an energy manager” (2:39; see also 6:18).

A requirement to provide all location, meter reference, cost, and consumption data

in a specified soft copy format from all suppliers would be very helpful but is unlikely

to happen without a change in procurement rules to insist on consistent data as well as

lowest price (5:29). Currently, Energia provides good, though slow, on-line access with

costs, consumption and charts exportable to Excel; Airtricity has limited on-line access,

it did have only cost data but is now improving; and ESB has some on-line management

but data does not seem to be obtainable on-line (8:18).

There is a need for consumption accounting but it is too problematic currently,

given the data difficulties (5:19,28; 8:29). For example (5:26; 4:2,14,17), for the leisure

centres manager to know the energy use for nineteen buildings in the year in that

department, each building’s energy use would have to be located in six or twelve

composite hard copy bills, some of them six inches thick, listing other buildings also,

and there may be five or six different suppliers. It is easier for the managers to try to

obtain the information directly from energy suppliers rather than from the Finance

Office (5:27). In Poppintree, the Duty Officer has arranged access to the centre’s gas

bill by contacting the current supplier (12:10), but getting access to the electricity bill

from a different supplier has been difficult, and as yet unsuccessful, in spite of repeated

emails (12:12).

Page 112: Policy and Value: A Case Study of Local Authority Energy Management and Investment

100

The difficulties with data from providers and changes of suppliers due to new

tenders adds considerable administration time, complexity and costs for the Finance

Office and for department and building managers (5:18,30; 4:8; 8:14; 12:41). It often

takes time to get suppliers to adjust the billing to include required details and then the

suppliers will often change over in a new tender period (5:18) causing continuity of

access problems for facility managers needing continuous on-line access to bills.

(12:40).

Energy users can insist on receiving the data in a set way as specified in

procurement contracts but the complexity of the billing means that training, time, and

therefore costs are involved, both in reading the bills and in analysing them (9:82,83).

In some cases, ‘unpaid bill’ notices have been sent in error by suppliers in cases where

the bills have been paid (9:84) or belated invoices arrive (one for €400,000 in Public

Lighting) due to the supplier’s own accounting mistakes (9:85) amounting to “very

unsatisfactory” service.

Even though every gas or electric meter is numbered individually and each of

these numbers corresponds to a unique meter point reference number there is no on-line

search available linking them (8:23). This causes problems in linking known MPRN or

GPRN billing information to the location and to the meter number because the bill may

have inexact or misleading associated location information (8:22,24,34). Local

authorities are getting the linked meter and meter point reference number data into

databases but it has been and continues to be time consuming (8:24).

6.2.7 Outcomes from Past Policy Implementation (OC)

OC codings were made when responses noted specific outcomes from energy or

retrofit related policy implementation (or lack thereof). The findings are varied because

Page 113: Policy and Value: A Case Study of Local Authority Energy Management and Investment

101

this category accepted specific outcomes of any kind and did not focus on a specific

topic.

For the OC category, 66 scored codings were made with an average attainment

level of 1.2 for National and 1.9 for Local levels (see Section 6.3). The mode was 1 in

each case. For National level there were 5 codings each for the 0 and 1 mode values.

For the Local level there were 10 codings each for the 1,2 and 3 modal values.

For DFB, 12 OC codings were made all with a level of attainment judged as 4 due

to the specific, separate results with a high quality of attainment in described outcomes.

6.2.7.1 National to Local Level – Described Outcomes

Ireland’s Kyoto target was only met because of the financial crisis and recession

(2:11) and overall in Europe energy efficiency to date has only achieved 50% of the

progress required toward the 20% energy saving target (2:11).

In SDCC, efforts at joined-up planning, as at Adamstown, saving carbon

emissions and energy use by situating new developments on the Kildare railway, have

stalled due to the financial crisis (9:6). However, SDCC has strong transport nodes,

aiding sustainability, and very few ‘ghost estates’ in NAMA ownership (9:6).

SEAI now have a highly accessible, data-rich and searchable database of all

existing BERs available on-line, with selectable and downloadable data sets, providing

free and transparent access to data (8:26).

Over the past two decades there have been several important large scale,

government-funded, national programmes of retrofitting social housing, each based on a

specific upgrade: boilers, weather stripping, and double glazing are examples (9:23;29).

These were reported to have often gone very well, especially fitting central heating to

all of DCC’s 27,000 units, so an overcladding or boiler efficiency programme would be

Page 114: Policy and Value: A Case Study of Local Authority Energy Management and Investment

102

possible but would require central government commitment and funding for social

housing retrofit (10:34,35). However, the overall pace of retrofit has been slow and

now it is slower so there are likely to be F and G rated houses for a long time to come

(9:31; 10:33).

No Public Private Partnerships are currently operating and limited piecemeal

assistance is being given in former PPP areas by DECLG where the PPPs failed (7:39).

Fuel poverty is a continuing problem that outweighs sustainability issues in

decision-making (9:32,33). It probably requires policy that aims for a minimum

housing standard simply aimed at eliminating fuel poverty (9:34-35). In Dolphin House

flats, little progress was made for many years in addressing the damp problems, and the

related difficulty in heating (10:48). Coverage on television may have led to the

internal retrofitting of the worst affected units that is now taking place ahead of

regeneration work, perhaps beginning in 2015 (10:52,50). Upgrading social housing

may not result in very large savings in energy use because there can be a large takeback

or rebound effect as residents can better afford increased comfort (2:53).

The outcome of annual budgets for government is very tight time schedules for

grant schemes with tight operating windows and a heavy administrative burden (11:44).

Although policy has been encouraging ESCos as a retrofit financing mechanism, very

few grant scheme applications are engaging with them (11:54).

6.2.7.2 Local Level – Described Outcomes

Overall, annual energy consumption savings (5:10) in DCC are keeping pace with

cost increases so that the total energy budget is approximately stable (5:12) while the

total available budget has fallen by about 5% over the past two years (5:35). The cost of

Page 115: Policy and Value: A Case Study of Local Authority Energy Management and Investment

103

energy is still relatively low and saving it by retrofit may be expensive and difficult so

energy saving has not yet concentrated minds (10:65).

The target of achieving 3% energy savings in the 2011 trial year of the Minus 3%

project was easily achieved with a reduction of 6% (2:17), although it might get harder

to achieve 3% savings after the simpler, easier options are taken up (2:18). Similarly,

SDCC saved €300,000 in their first year of monitoring bills with the help of three one-

day sessions from an SEAI-funded energy advisor and re-tendering on the basis of

increased knowledge (9:9). An energy consultancy firm has identified large savings for

DCC by examining and adjusting electricity tariffs (5:6), in one case saving about

€24,000 on one annual bill. (5:7). A large, 10% reduction in server electricity use was

achieved by the IT department of DCC (8:36). Energy use in the DCC Civic Offices

has been dropping by about 1% per year so although bills are rising they would be

higher if no energy savings had been made (8:35). The Codema database of energy use

is becoming a useful analysis tool in identifying prime locations for energy saving or

large shifts in energy usage (8:33).

Currently, in DCC, 700 units become void each year, mostly flats because houses

do not turn over so often (10:33, 2:31,45). In SDCC, retrofitting of voids is down to

150 houses per year (9:31). SDCC’s own staff have carried out extensive BERs (1,600

to date) aiming to make BER maps of estates to target further measures (9:34). Since

the new Part F of the Building Regulation was introduced, reducing the ventilation

requirement, there has been more condensation in housing than ever before due to moist

air from kitchens and bathrooms not being exhausted so condensation occurs in colder

rooms (9:38).

Even in newer, larger, designed buildings there has often been piecemeal

installation of systems and services, which have not then been tested for performance,

Page 116: Policy and Value: A Case Study of Local Authority Energy Management and Investment

104

or the building managers and staff may not be fully trained in how it works (8:39;

12:33). Newer leisure centres do have designed and built-in potential for energy saving,

particularly if the staff increase their awareness of how to take care of energy use (12:3).

Two years ago the Department of Transport, Tourism and Sport made some money

available in sports capital grants, which DCC bid for: they were unsuccessful in a bid

for the bigger centres, that would have installed a CHP unit in Ballymun; but DCC

secured €150,000 for the smaller pools, renewing pool covers at Sean McDermott and

Crumlin Pools (4:23). Such grants occasionally become available to local authority-

only bids because money that has not been taken up in a particular round of grants is

then re-offered on a more closed basis, rather than inviting a large number of

applications needing processing (4:23).

In SDCC, newer facilities have been completed with many energy saving, or on-

site energy supply features including; CHPs, wood pellet boilers, energy efficient

lighting, and heat exchangers in leisure centres; and ground source heat pumps and

photovoltaics in other buildings (9:22). Last year SDCC were able to show savings of

15% in their buildings; for the first time, this was a verifiable figure using combined

cost and energy data to prove the savings. However, there do continue to be many

opportunities for energy saving where savings can be made through energy efficiency

and Energy MAP (9:28).

6.2.7.3 DCC Green Plan: Described Outcomes

The Green Plan has now become the business plan of DFB, guiding all decisions

in a sustainable direction by asking, “Can we actually sustain a front-line emergency

fire service?” (13:11). After four years, since inception at Kilbarrack, the ring-fenced

saving fund has become self-generating, enabling retrofit of further fire stations in

sequence, each retrofit’s savings adding to the fund to make further savings (13:7,11).

Page 117: Policy and Value: A Case Study of Local Authority Energy Management and Investment

105

Retrofit work is complete at Kilbarrack and Phibsborough and semi-complete in

Donnybrook, Dolphin’s Barn and Tallaght Fire Station (10:39).

Water is seen as equivalent in importance to energy so, at Kilbarrack, all grey

water from the fire station and rainwater collected from its roof is treated and used in

the fire engines to put out fires (13:28). Running costs for water were €5,500 annually

but now almost no water is now being used from the mains, such that the station is 97%

water independent (13:29). At Phibsborough, a 20,000 litre tank has been installed

below ground and all water for fire fighting now comes from the roof (13:33) – each fire

station has the potential to collect 14,000 litres of water every ten days with fire engines

requiring 1,800 litres per fill.

Uniting the Green Plan ‘Transport’ and ‘Waste’ themes, biodiesel made from

cooking oil collected from fish and chip shops across Dublin is being used to reduce fire

engine running costs by €150,000 per year – biofuel from land crop is not acceptable

because it competes with food (13:37).

Overall, it is estimated that DFB will easily achieve the energy saving and carbon

emissions reductions well ahead of the dates set, potentially reaching 90% savings if the

new procurement document leads to the ESCo and private funding arrangements that

are planned (13:39). At Kilbarrack: reductions of 97% in water usage and 85% in

energy use have been achieved; present and retired firefighters have been involved in

creating an allotment and growing vegetables; and wind turbines have been successfully

trialled. In DFB, the Green Plan has now also led to recently completed successful

trials of three phase lighting, recycled frying oil as fuel for the fire engines, and a live

registry, each of which will deliver major savings (13:pc). These have all come about

beginning with the savings made at Kilbarrack and are now at the other stations also.

Page 118: Policy and Value: A Case Study of Local Authority Energy Management and Investment

106

‘Society’ is key theme in the Green Plan, both internally, in each station and in the

Fire Brigade as a whole, and externally, so that stations become hubs of sustainability

for their local community. School children across Dublin are beginning to talk about

how they are hearing about sustainability from their local fire fighters (13:12). At

Kilbarrack, an on-going process of firefighter involvement and technical retrofits has

created a series of socially engaged energy, waste and water saving improvements

(13:9). Overall, the combination of behavioural and technical measures have led to

significant returns and co-benefits:

We are using rainwater and wastewater to put out local fires. Because

we are doing that, the community responds with so many letters and

cards being written to us. They will come up and say: “Are you the

crowd using rainwater to put out those fires”. We will be there doing

that and they will be saying, “That's amazing!” (13:46)

Page 119: Policy and Value: A Case Study of Local Authority Energy Management and Investment

107

6.3 Codings: Counts and Average Attainment Levels

Table 6.1 shows a simple pivot table analysis of the overall attainment level

averages for EMM categories and governance levels, providing an indicative,

comparative assessment of current overall attainment within EMM categories and

governance levels. These values will have low weighting if the number of codings is

low.

Greyed result cells indicate fewer than 10 interview comments were coded for the

cell. Overall averages relate to the adjacent total count of codings. For example the

overall average for Management Structure is 1.5 based on 87 comments, and that for

Local level is 1.6 based on 417 comments.

Table 6.1 Attainment levels for EMM categories and Governance levels.

Page 120: Policy and Value: A Case Study of Local Authority Energy Management and Investment

108

CHAPTER 7 DISCUSSION

7.1 Leisure Centre Surveys

7.1.1 Survey Observations Discussion

The survey revealed behavioural, technical and management issues in the energy

management of the leisure centres relative to best practice in literature.

In the centres, many of the behavioural problems seen are initially caused by

technical building or services design. As was observed frequently, if a building does

not react to ambient conditions then building users attempt to change them by opening

windows for ventilation or switching lights on in the darker conditions. However,

energy wastage soon occurs as a result of such actions as ventilation need is reduced or

daylighting improves. The literature (section 2.2) indicates that it is well worth

assessing the benefits of technical changes, but even if technical solutions are put in

place, good behavioural awareness and energy saving habits will decrease the payback

time and overall cost of retrofit measures. Increased awareness would save energy by

changing habits toward containing rather than permitting wastage, however on the basis

of interview evidence, improved motivation is clearly required.

It is striking that there were thirteen new facilities built between 1995 and 2008,

but no significant retrofit or renewal investment appears to have been made during that

time in the six older buildings. The recent retrofit measures in the older pools were only

made following a successful bid for retrofit grant monies. Another bid for a grant for

the larger centres was turned down, even though it would have been likely to result in

significant savings. Investment logic suggests that a life cycle view of costing has not

been taken in the past given the level of on-going energy costs in some buildings. As

highlighted in the literature (section 2.3.3), there is an on-going cost of doing nothing to

Page 121: Policy and Value: A Case Study of Local Authority Energy Management and Investment

109

an existing building. However, the survey observations, would suggest that such costs

continue to be accepted as a cost of building ownership.

7.1.2 Data Analysis and DEC Ratings

The very high energy use of some centres indicates that there are potentially large

energy savings to be made. As Table 4.1 shows, giving 2010 figures, two of the

centres, Finglas (over 2,947,000 kWh costing €162,000) and Ballyfermot (3,157,000

kWh costing €184,000) use very large amounts of energy. For Ballymun, for which the

gas bill was unavailable, the electrical use alone was over 1,079,000 kWh costing

€141,000. It quite probably uses more than the other two large centres judging by the

electricity bill, its size, and the lack of a CHP unit. The EUI for Finglas was 1500

kWh/m².y and for Ballyfermot it was only about 800 kWh/m².y. The CHP unit or other

factors at Finglas seems to have been less efficient than that at Ballyfermot given that

Finglas is significantly smaller and has a higher EUI.

There are continuing losses that have wasted very large amounts of energy (and

money) in the past and continue to do so unnecessarily. The three older 'stand-alone'

swimming pools all use about 1.5 million kWh per year with EUIs between 1,700 and

2,200 kWh/m².y. These are large amounts, though surprisingly their DEC ratings for

2010 were E1 and Fs rather than Gs, when benchmarked against similar buildings.

Illustrating the current and past level of energy waste, at Crumlin Swimming

Pool, the proposed installation of heat recovery ventilation at a cost of €80,000 (with

BEW grant funding) could save at least 30% in gas usage that currently costs over

€50,000 per year giving an annual saving of €15,000 (Codema, pc). Much more would

be saved with additional insulation and air sealing, which could be pumped into the

cavity walls, raising air temperatures, increasing swimmer comfort and reducing

Page 122: Policy and Value: A Case Study of Local Authority Energy Management and Investment

110

evaporative heat losses from the pool, potentially saving a further 50% of the remaining

pool heating cost.

The scatter chart (Figure 4.3) of the leisure centres showing Total Energy Cost

versus Energy Cost Index (ECI) provides a useful analysis method. Changes in both

axes, from year to year, are immediately apparent and require explanation. For

example, the very large changes in energy use for four of the centres from 2010 to 2011.

There may have been a change of usage pattern, equipment failures, behavioural

changes or billing errors. The absence of data for some buildings and only one or two

annual data points for each centre restricts the current usefulness of the chart. These are

retrospective measures of performance but even this limited evidence of large changes

shows that there is a need for automated ‘live’ monitoring of the energy use of the

centres given the high energy costs in some of them.

The 2010 figures, in Fig. 4.1, 4.2 and 4.3, indicate similar energy performance for

all three older pools, but the 2011 figures are dramatically different with a total cost and

ECIs for Sean McDermott Street and Coolock in 2011 twice that of Crumlin. These

large rises in costs are particularly in need of explanation given that 2011 was a

significantly warmer year than 2010. Finding the reasons for these changes is a critical

part of energy management but a question for the later interviews became whether there

were established mechanisms in DCC to identify these changes in a systematic way.

7.1.3 Survey Conclusions

The continuing difficulty in obtaining energy consumption and cost data for the

leisure centres, more than 18 months after the 2010 year-end, implied some form of

failure in systems to address energy waste and resulting emissions be it at supplier or

council level.

Page 123: Policy and Value: A Case Study of Local Authority Energy Management and Investment

111

It may be that these findings are unsurprising to managers, but as strongly

indicated by the literature (section 2.2), good energy management relies on good data

collection, systemised reporting and analysis expertise that appears to be lacking

currently within the department and in the centres. As mentioned by staff, all energy

bills go to the Finance Office directly to be paid. Even where the facility manager was

interested in energy use and recording meter readings it was being done manually, out

of personal interest and without any advice on how to analyse the data (to weather

correct it for example). The lack of automatically logged, time-interval metering in

large centres is out of step with effective energy management procedures. As evidenced

by the experience in DFB, monitored BMSs are worthwhile for buildings where costs

are high.

The very poor energy efficiency of the older leisure centre buildings is largely due

to poor building fabric and out-dated services, which have been more or less unchanged

for 30 years. This indicates that these are clear candidates for deep retrofit or

replacement to be judged on a reasonable lifecycle, having all been more or less

unchanged in fabric terms for more than thirty years. Coolock is a particularly energy

wasteful building with very high operational costs (see Appendix H). A life cycle

costing would compare the 30-year energy use and rental or lease costs with the

replacement costs.

Repairs are planned at Crumlin Swimming Pool, due to its leaking roof, but

despite this major retrofit the major renovation plans (DCC, pc) do not include an

energy upgrade to the whole building on a cost-optimal, life cycle basis as the EPBD-R

lays out. By observation, it is a rectangular building with ease of access to all sides and

the pool building has wide-cavity masonry walls (survey by DCC shows cavities around

pool area are 300 mm across) that could efficiently and cost-effectively be filled with

Page 124: Policy and Value: A Case Study of Local Authority Energy Management and Investment

112

insulation. For these reasons it would seem an ideal candidate for a 30-year lifecycle

deep retrofit approach.

7.1.4 Limitations of the Leisure Centre Survey

The walk-through energy audits were restricted in time to between one and four

hours and relied on personal observations and conversations with staff. Much of the

time was spent in measuring the floor area, a key input for the DEC calculation. The

plant rooms were seen in all cases but only visual observation of boilers, HVAC and

lighting types was undertaken; no technical examinations were undertaken. These

factors limited the depth and quality of the findings. Nonetheless, the basic audit

revealed many areas that would require more detailed auditing to assess retrofit

potential especially the HVAC systems. The detail revealed by staff depended on which

members of staff were available and their level of knowledge of energy use in the

building.

7.2 Document Analysis

7.2.1 Appropriate Investment Appraisal

The document analysis findings (Sections 5.5.1 and 5.5.2) show that simple

payback, without a specified time limit, is the appraisal method favoured by the BEW

grant scheme. The only mention of other methods are cells provided in the sub-project

listing for NPV and IRR but there is no a stated study period or specified reference data

given, so any NPV or IRR entered would be meaningless for comparative purposes

against other applications. Energy management references describe simple payback as

an inadequate method of investment appraisal (see Section 2.9), particularly unsuited to

financial appraisal of energy upgrade investments for existing buildings. There are

many reasons given as to why simple payback is not an appropriate decision-making

Page 125: Policy and Value: A Case Study of Local Authority Energy Management and Investment

113

tool (itemised by Russell, 2010:130-134) yet the BEW grant scheme encourages its use

by applicants and it seems to be in use by SEAI in the Value for Money grading of

applications.

Although BEW scheme objectives are not focussed on funding projects that are

necessarily financially viable, as such projects should theoretically be undertaken in any

case unless there is market failure (mentioned also in the interviews), the objective of all

investments is increase future wealth by saving relative to some alternative. This could

be other investments or the decision to do nothing. It would seem advisable for

government to use and encourage appraisal methods appropriate to the investment

decisions being made, especially when one specified aim is to encourage public sector

bodies to engage with private investors such as ESCos and energy suppliers. These

investors are unlikely to make long-term decisions for 10 or 15-year investments on the

basis of low quality data or inadequate appraisals. Therefore, public sector bodies will

need to understand both the importance of good input data, based on valid, specified

assumptions, and how to apply appropriate appraisals if they are going to engage

confidently with funding parties to obtain good value for public expenditure on energy.

7.2.2 Timescale, Data Accuracy and Relevance

Accurate data for costs and savings are critical to good quality appraisals, as is the

timescale for assessment. The BEW Application Form appears to encourage the use of

only installation cost and a predicted figure for savings, based on a single year's energy

data, as a basis for a simple payback calculation. As was seen in Section 5.2 there

appears to be some data in the application that does not meet investment appraisal

requirements for savings to be justified as being incrementally based on the proposal.

Also it may be that some of the savings allow double counting though this is difficult to

Page 126: Policy and Value: A Case Study of Local Authority Energy Management and Investment

114

determine on the basis of available information. No assumptions are identified, thus it

is difficult to see how the investments could be graded effectively in 'Value for Money'

terms.

The use of only a single year's data, for 2010 (a cold year), does not give a strong

basis for an estimate of predicted savings. The observation, made during the surveys,

that new pool covers and pool water heat exchangers had been or were being installed in

Crumlin and Sean McDermott Street for example, indicates that savings due to these

measures should have been accounted for to give a more accurate corrected baseline.

As noted in the surveys findings in Chapter 4, the lack of 2011 billing data access at the

time of the application probably restricted the ability of DCC to provide a more current

baseline usage.

Only data that is of high quality should be used in investment appraisal; however,

collecting good quality data is time consuming and often costly (Holmes, 1998:7-8). As

the BEW Guide is dated March 21st, and Application Forms had to be submitted by the

end of April, it is possible that, given the very short timeline, applicants who were not

already prepared for the grant scheme may well not have had sufficient time to check

data to a high standard. Nonetheless, the application was submitted by DCC and

approved by SEAI, indicating that the ‘first-step’ procedure of checking the data

carefully was not one that would cause rejection at any of the assessment stages of a

Sub-Project or Project, or of the application as a whole.

Lifecycle costing or DCF methods would generally require a timescale of between

15 and 30 years, requiring many other costs and adjustments to savings to be included,

potentially greatly altering the appraisal. Such lifecycle and accounting requirements

are the methodology advised by the Department of Finance in the Capital Works

Management Framework (DoF, 2009:55) and by the EPBD-R as informed by EN 15459

Page 127: Policy and Value: A Case Study of Local Authority Energy Management and Investment

115

(Zirngibl and Francois) yet they are not being used in the grants and their use would

seem to be justified.

7.2.3 Comparing Appraisal Methods

The charts presented in Section 5.3 illustrate the differences between appraisal

methods by hypothetically assuming that the data for the 16 sub-projects met

investment quality and relevance requirements, the aim of the comparisons being to

compare different methods of appraisal to inform choice of appraisal methods.

Simple payback does give rankings that are broadly similar to other appraisal

methods but, critically, it gives no indication of the profitability or overall benefit or

loss provided by the investments. The four shortest payback period investments are by

far the best value proposals, as also chosen by the other methods, so it is the ranking of

the more marginal investments where differences become clearer. For example, project

5 appears to have a reasonably short payback of six years yet, as shown in the NPV and

PI charts it is barely profitable and may be unprofitable if the anticipated savings are not

as high as predicted. All of the alternate methods provide more information and give

more definite accept/reject criteria than simple payback.

As noted in Figure 2.1, retrofit appraisals for existing buildings are not yes/no

decisions because the option to keep the building has already been accepted. The

comparisons performed illustrate that simple payback is an inadequate and potentially

misleading appraisal method,

Graphing the projects on a scatter chart of PI versus NPV (Figure 5.5) gives an

effective visual presentation of the projects returns, portraying both value for money

invested and overall financial value of the project.

Page 128: Policy and Value: A Case Study of Local Authority Energy Management and Investment

116

The Danish profitability index appraisal method for retrofitting is straightforward

and simple to understand for policy makers, architects, builders and building owners

alike. As with the other methods, reliable well checked data is required. It gives a

preference to long-lasting, fabric-first passive measures like insulation and windows –

as noted in Section 2.3.4, research shows that this can be financially justified. As the

method does not involve DCF it is also simple to calculate, given good data, and it has a

very straightforward decision-making level, stating simply that, if the PI is above 1.33,

“It is required to proceed with the measure”. It is clear from Figure 5.7 that it is likely

that more retrofits would pass the acceptance threshold using this method.

For all of the appraisals the result would be more meaningful if all lifecycle costs

and benefits were used.

7.2.4 Limitations of the Document Analysis

The document analysis of the SEAI Guide for BEW scheme applicants and DCC

funding Application Form to SEAI is not an in-depth analysis of the scheme itself but is

only aimed at assessing, in light of the declared deep retrofit aim of the funding, the data

quality and appraisal methods that were requested, utilised and approved. The findings

and discussion relies on the relevant investment appraisal literature consulted, and

findings may only apply to this scheme. Nevertheless, the findings provide an insight

into an outcome of energy policy in regard to retrofit investment by a national agency

and a local authority.

Page 129: Policy and Value: A Case Study of Local Authority Energy Management and Investment

117

7.3 In-Depth Interviews

7.3.1 Coding Analysis and Interview Limitations

7.3.1.1 Coding Analysis

The coding analysis in Table 6.1, shows the main purpose and relevance of the

study was to investigate energy management and retrofit investment as implemented in

Dublin, and as they are directed toward achieving the nationally set targets. The

national and local levels, and the main implementation categories therefore had the most

codings.

For the national and local governance levels the codings are very similar for each

category, lying in the EMM attainment range between 1 and 2 with ‘investment and cost

analysis’ at the low end of the range. The data quality provided by energy suppliers was

assessed as being poor at 0.9. The interviewees in the Fire Brigade and the Poppintree

Leisure Centre were exemplar cases skewing the averages in these categories toward

higher values, but providing comparative data for the national and local level indicators.

Table 6.1 indicates some of these weaknesses and some of the strengths within

interviews by stating where the number of responses related to an average or a particular

EMM category and Governance level combination. Questions on supplier-provided

data were only added to the interviews when it became clear that this was a significant

issue (so some respondents were not asked and some would be unaware of it). Except

in confirming the basic targets for energy and emissions saving, energy management

policy was mentioned by only a few respondents.

7.3.1.2 Limitations of the In-Depth Interviews

The coding of interview data aimed to reduce subjectivity limitations in assessing

a large number of responses, by use of a framework derived from literature review. This

Page 130: Policy and Value: A Case Study of Local Authority Energy Management and Investment

118

reduced the influence of the form of the questions or biases of respondents, provided

sufficient codings are made (Gibbs, 2011). Judging the attainment level reached in

energy management categories, as the analysis attempted, does rely on the coder, but the

need for a high level of calibration was considerably lessened by the first-approximation

estimate of attainment essayed by this research. In fact the codings could be likely to

over estimate the attainment level as the grading aimed to be in line with the

respondent’s opinion as well as being scored in regard to the EMM.

The exploratory nature of the research means that more data is needed to fully

triangulate the findings. A further limitation, due to the restricted number of

respondents and the research time available, was that no interviews of top-level

management were undertaken. This would be a recommendation for further research.

Nonetheless, the ultimate implementation of energy saving policy depends on those

closest to where 'coalface' energy-use decisions are made and as such the results should

reflect these actual practices relating to energy management at present.

All of the interviews relate to Co. Dublin, the largest urban centre in Ireland, and

are relatively large councils so there are limitations of scale in applying findings to other

local authorities though the findings regarding funding and governance mechanisms are

widely applicable to other local authorities.

7.3.2 Interview Discussion by EMM Category

7.3.2.1 Energy Policy

Energy policy at national and local level is focused on achieving targets in energy

saving and carbon reduction. Although headline targets were strongly repeated by

respondents, no further detail was evident apart from references to the NEEAP. Policy

Page 131: Policy and Value: A Case Study of Local Authority Energy Management and Investment

119

is in place but it does not seem to be integrated, enforced, systemised, or ‘bought-into’

sufficiently at local level to have been noted in the interviews by respondents.

Respondents noted that the national policy of improving social housing to C1

would take many decades at the current rate of progress. Given the limited funding

support for it, policy with such low levels of implementation would seem to lack

significant merit.

Similarly, at local level, the lack of definite annual or disaggregated objectives or

penalties, diminished the value of energy and climate policy for respondents. No

guiding policy, or funding, was mentioned that would encourage individual, council

departmental actions toward establishing behavioural or other managerial energy

measures. In Dublin, the SEAP is published but does not seem to be guiding the

departments within DCC, no baselines appear to be available for use by departments as

evidenced by respondents. No targets or policy from the NEEAP or the SEAP were

seen to be affecting the leisure centres for example.

In contrast, the Green Plan policy themes seem clear and highly result-oriented

with an initial focus on cost saving, enabling further investment. Most apparent was the

concentration on sustainability in all aspects that has clearly inspired staff and

management to achieve real savings. The policy emphasis on behaviour and carbon

saving, as well as measurable targets and results, was clear from the published reports.

The interviews confirmed this, but also showed that, though impressed, other

respondents remained highly uncertain about how the Green Plan results had been

achieved.

It seems that senior managers and, especially, facility managers elsewhere in DCC

and in other councils could learn from looking more carefully at the Green Plan policy

Page 132: Policy and Value: A Case Study of Local Authority Energy Management and Investment

120

documents. The concentration on operational level results, strongly linked to changing

habits by engaging with core themes of sustainability could inform and improve future

policy in DCC and elsewhere.

7.3.2.2 Management Structure

A strong literature finding was that managers should take responsibility to manage

energy, but it was clear from respondents that management structures in European,

national and local governance, continue to be top-down, complex and highly

departmentalised. The varying structures and management interests reported make it

difficult for effective, systemised and encouraging energy management to take place in

the public sector. There was no clear sense from interview respondents that the

management structure of DCC is deeply engaged implementing policy with energy

management, either in supporting facility staff to save energy or in energy accounting to

monitor and target energy saving. At best such processes are in the early stages of

development.

Unclear communication between and across governance bodies was frequently

mentioned as being problematic. SEAI have to communicate with a wide range of local

authority boards and agencies to create programmes, which delays implementation.

Councils have to go back and forth with the DECLG negotiating over building projects.

Local authorities engage in time-consuming negotiations over larger retrofit schemes

with DECLG. Given the annual funding nature of budgets, a delay of a few months

may well miss the next funding allocation and working window, delaying things further.

As noted by several respondents, councils currently have to go to the DECLG with

proposals and negotiate on a “case by case” basis and then resubmit proposals

repeatedly, awaiting rejection or acceptance without clear information on the decision

thresholds. From the responses given, these management structures appear

Page 133: Policy and Value: A Case Study of Local Authority Energy Management and Investment

121

unnecessarily top-down, complicating instead of delegating local decision-making.

Overall, these findings echoed the ‘organisational zoo’ outlined by literature (see

Section 2.4.3).

This concern extends to city and county energy agencies, which were reported as

having many different organisational models. It was notable that the external agency in

Co. Meath was mentioned as having closed due to spending cuts whereas, in contrast, it

was a small, in-house ‘agency’ in Kerry County Council that was noted by many

respondents as being successful and innovative. This lean, expert, in-house format

might be one that councils elsewhere could adopt, provided they will or can fully

commit to energy management and medium term time horizons for investment. As

noted by the literature, and as in the Green Plan, rather than distancing energy decisions,

good practice in energy management relies on all managers and staff recognising their

roles in supporting and achieving energy saving.

SEAI’s Energy MAP was cited as being helpful by both SDCC and DLRCC, but

DCC has not yet engaged with the Energy MAP process. It is possible that the larger

size or more traditional structure of DCC’s management systems is in some way

restricting this involvement. On-going retirements in the public sector, partly resulting

from the response to the financial crisis mean that there is also a drain of such sources

of expertise that are available, so retraining would seem an important option to take for

councils as shown by the effective example of SDCC’s retraining of staff to carry out

BERs. Architects and leisure centre managers reported that there is no clear in-house

council back-up bureau or energy manager for them to call for immediate advice on

energy management or retrofit investment issues.

By comparison, the Green Plan exemplifies profound organisational change

beginning at the periphery of an organisation (see Section 2.2.2), in this case motivated

Page 134: Policy and Value: A Case Study of Local Authority Energy Management and Investment

122

by an energy champion and supported by staff and management. DCC have supported

FF Neil McCabe in pursuing the Green Plan and it seems clear that that the DFB

management structure has been forward looking, not only in supporting the plan at

Kilbarrack, but also taking it in to change their entire business plan to enhance the long-

term sustainability of the Fire Brigade’s services and operations.

Codema act as advisors on special projects, often EU funded, and influence policy

but is not delegated with authority to independently monitor energy use or costs in

council departments to achieve targets. Codema have been assisting in documenting the

Green Plan work in DFB recently, and an energy agency would seem an ideal advisor to

directly support local and departmental energy champions to achieve results in specific

savings projects by assisting with technical and investment appraisals. However, this

does not seem to be a large part of their role currently. If Neil McCabe is going back to

full-time firefighting, as he said in interview, then it would seem ideal for DCC and

Codema to become more active in continuing his work, with his advice, to provide the

back-up technical and procurement knowledge necessary to systemise continuing

support for the Green Plan for DCC departments and facility managers.

7.3.2.3 Implementation and Motivation

A quoted respondent said that, in spite of policy, implementation had not fully

connected across government, but also observed that everything does connect at the

facility or building where the energy is used. This seems a key point that the Green

Plan addresses directly, by engaging directly with personal reasons for actions and

habits. This may help explain why the top down programmes, worked on by different

governance levels and bodies are more likely to fail, especially when judged by their

costs relative to their success or lack thereof. Although the area retrofits in Dundalk and

Tralee were mentioned as good examples of implementation at scale, there seem to be

Page 135: Policy and Value: A Case Study of Local Authority Energy Management and Investment

123

no plans at national level or in Dublin to replicate them in the near future and only

vague intentions to engage with energy suppliers.

The accepted fact of widespread fuel poverty in publicly owned housing would

seem to confirm an on-going failure in national policy implementation that has

continued for many years. In spite of government advisory reports showing large net

benefits, mentioned in several responses, this is set to continue for many more years

given the even slower rate of retrofit now occurring. The logic of the policy of not re-

renting F- and G-rated houses and retrofitting so slowly is that governments accept that

they will continue to be the landlords of such poor houses into the far future. National

government, the primary source of upgrade funding, is therefore, directly responsible

for the resultant excess future carbon emissions. This is at odds with the stated

emissions policy and was the case even before the financial crisis according to

respondents. This suggests that other considerations must have favoured the on-going

capital rationing with respect to social housing retrofit, amounting to market failure in

investment terms, both before and since the financial crisis.

BER ratings have clearly been effective in benchmarking retrofit improvements,

as noted by respondents regarding pre- and post-works BERs for social housing void

upgrades. Energy performance certification, such as BERs and DECs, resulting from

the EPBD, therefore appear to be an example of how top down government has

succeeded in supporting and enforcing policy through strong regulation. If government

were serious about energy efficiency policy with the public sector as an exemplar it

would seem similarly important that requirements for official DECs to be in place

would be enforced. Also, Energy MAP or ISO 50001 might be required rather than

voluntary and all public bodies would be required to publish and budget for a rolling

retrofit investment programme to identify the ideal first candidates for deep retrofit. As

Page 136: Policy and Value: A Case Study of Local Authority Energy Management and Investment

124

was reported by respondents, these kinds of top-down regulatory moves are not

occurring and are not being funded. As a result, the understanding of respondents was

that energy management and deep retrofit are seen as much less important than cutting

costs or maintaining the status quo.

SEAI’s Energy MAP programme was mentioned as playing a role in motivating

change in energy management practices in SDCC and DLRCC. In DCC, Codema’s

survey audits and reports are communicating building information to departments that

may not have considered their energy use previously and outside experts recently been

examining bills to find savings. The database of information on DCC buildings will

clearly be of great use in DCC energy management in locating facilities where

unexpected changes in energy use occur and identifying potential buildings for further

assessment with a view to retrofitting. It was not clear from interviews how strongly

departments respond to the advice given by Codema.

According to respondents, implementing energy management is most likely to be

motivated by individual managers with a personal interest in energy saving, as in was

noted in Corporate Services or in Poppintree Leisure Centre, or by EU supported, large

scale projects run by the council’s energy agency. In EMM terms these are both seen as

isolated and sporadic approaches rather than continuous localised improvement

throughout an organisation.

Findings regarding behavioural change were well defined. Respondents noted

Codema’s Switch Off campaign as a success, though the achieved savings were

modelled rather than metered and it was difficult to know if its effect was continuing.

Elsewhere though, behavioural change has been difficult to implement and has lacked

support. The contrast with the Green Plan could not be more clear: behavioural change

began at Kilbarrack with collecting batteries, and has continued through constructing

Page 137: Policy and Value: A Case Study of Local Authority Energy Management and Investment

125

their own rainwater harvesting, involving retired firefighters, and now firefighters are

teaching sustainability to school children.

The Green Plan’s core ethos has clearly resonated with firefighters and

management and it seems important that it has mostly been about doing things toward

sustaining work, community and the environment through doing things well, rather than

the focus being on ‘energy efficiency’ and ‘retrofitting programmes’. It has also come

from a trusted, operational-level co-worker not from upper management or outside

agencies, though supported by them. And it has been on-going, encouraged by small

projects with good results, and then larger projects repeating the message of success,

enriching the knowledge base and increasing local self-confidence. These findings echo

business literature and may well provide a template to follow for other council

departments and other local authorities.

7.3.2.4 Cost Analysis and Investment

Responses indicated that the kind of detailed technical and investment expertise

brought to DFB’s individual projects appears to be generally missing from Co. Dublin

councils, in large part because times have changed so radically since 2008. Before then,

large capital projects and new builds were commonplace, and income gained by selling

houses was put into upgrading remaining stock. Now, budgets continue to be cut and

there is a realisation that retrofitting existing buildings has to be done, or whole life cost

calculations have to be carried out to see if a new build would in fact be cheaper over a

30 year lifespan given lower operating and maintenance costs.

However, local authorities act under significant financial constraints due to the

financial situation, annual budgeting and an inability to act independently. Their

decision-making is dependent on a web of grant funding arriving from different

Page 138: Policy and Value: A Case Study of Local Authority Energy Management and Investment

126

departments and grant schemes, which often require time consuming and

administratively burdensome bidding or proposal processes for the DECLG or SEAI

grants. The appraisal findings presented in Chapter 5 would seem to confirm this

analysis. As a respondent noted, local authorities are always in need of money, making

the need for this kind of grant system questionable, especially in view of the severe

constraints imposed by annual budgeting and the rapidly decreasing level of available

funding.

As was clear from interview responses, the separation of capital and current

spending, especially in the current financial environment, combined with single year

accounting, causes significant problems for energy management and retrofit investment.

Installing monitoring equipment, technical or investment guidance, and other such

measures requires monies to be spent from highly restricted current spending. Any

savings made by departments cannot be reserved for future spending nor are they being

ring-fenced to invest in energy saving measures. Interviewees were clear that capital

spending, even for investments with short paybacks, is highly restricted and so life cycle

costing is not possible, limiting the potential for value-focused investment appraisal.

Respondents noted that local authority management is currently motivated far

more strongly by cost cutting policy than by energy saving or carbon emissions

reduction policy. The energy consumption figures are only now establishing a baseline

so it will be even more time before measures can show their worth. Deep retrofit will

require a more holistic, lifecycle approach to energy saving. As seen in the leisure

centre survey and interviews, new buildings were built during the Celtic Tiger period

but older houses and leisure centres were not renewed. Interview responses showed that

significant, lifecycle ‘replace or retrofit’ decisions have been delayed, in favour of

capital spending on new buildings or current spending for on-going maintenance and

Page 139: Policy and Value: A Case Study of Local Authority Energy Management and Investment

127

repair. Now there is little capital spending, and current spending may or may not be

sufficient to cover maintenance and repair, as evidenced by the repair work that will

soon proceed at Crumlin Swimming Pool and the recent cutbacks affecting house

retrofits and building maintenance noted in SDCC. Medium term investment such as

energy auditing, metering, monitoring and analysis, or small retrofit projects, are also

unlikely to proceed because they require monies from current funding.

As it will have to be closed for major renovation, Crumlin Swimming Pool would

seem an ideal building for a long lifecycle, whole building deep retrofit in line with

government and European best practice. However, the existing plans (DCC, pc) only

extend to replacing the leaking roof and internal refitting rather than deep retrofit with

whole building insulation and air sealing. Piecemeal renovations are also on-going in

Dublin flats, which were mentioned as being long overdue for replacement or cladding

(though a regeneration is planned beginning in 2015). It is notable that architects in

DECLG and Dublin councils are fully aware that the solutions being used are neither

optimal in cost nor in building science terms, but they note that they have to make do

with the funding available. For social housing, councils do not receive any benefit from

increased rents after retrofit, creating serious ‘principal-agent problems’ in retrofitting.

As noted by respondents, research suggests that these are highly productive investments

for society with numerous long-term cost, health and energy security benefits

As mentioned by respondents, retrofitting entails significant ventilation and

condensation risks, requiring considerable building science knowledge and analytical

skills, which were noted in interviews as being new to many architects. Much technical

and investment appraisal evidence (acknowledged in interviews) shows that shallow,

piecemeal retrofits may provide poor long term value and carry potential condensation

and ventilation risks. Unfortunately, due to the short time horizons enforced by both

Page 140: Policy and Value: A Case Study of Local Authority Energy Management and Investment

128

annual budgeting and financial circumstances, dominated by demands for short-term

cost saving, these continue to be the dominant type of retrofit undertaken.

Commonly throughout the councils, there appears to be a very limited

understanding of investment analysis that could facilitate retrofit decision-making.

DECLG provide useful technical guidance on retrofitting dwellings (pc) and although

they use simple payback appraisals, the acceptable payback was stated in interview as

being up to a reasonable acceptance level of 15 years. However, to invest in such

medium to long-term energy saving projects will require more funding or different

funding mechanisms. If this means engaging with private ESCos or energy suppliers

then the findings presented here show that local authorities will require a much

increased awareness of investment appraisal and funding streams to ensure that they can

effectively evaluate the proposals made by funding parties.

The literature review showed that whole life costing is part of government

recommended procedures (see Section 2.3.3), but it was found that these are not in use

by councils (or by SEAI or DECLG) in costing projects. Both the literature and many

of the respondents agree that lifecycle costing, even of a simplistic kind, would give an

improved basis for judging long-term decision-making.

Unlike traditional budgetary mechanisms, the Green Plan’s revolving fund

financing model has provided flexibility in project selection and freedom in timing. Its

successful results and the interview data indicate that the artificial division in public

finance between capital and current spending is directly undermining investments in

sustainability and deep retrofit energy saving. The seed-funded and ring-fenced saving,

revolving-fund mechanism also offers an ideal model for current financial

circumstances, allowing early “low hanging fruit” energy upgrades with fast paybacks

and high returns to pay into a local fund that finances further retrofits on the first site

Page 141: Policy and Value: A Case Study of Local Authority Energy Management and Investment

129

and then at other sites as the fund grows. This agrees with the ‘cap and invest’ financial

and ‘sufficiency’ carbon emissions reductions policies (noted in Section 2.3), thereby

avoiding rebound effects by reinvesting in more carbon reduction.

7.3.2.5 Monitoring and Targeting

DCC currently have a target of 33% energy saving by 2020, also stated as 3% per

year. As the target is not disaggregated, it is implied, and was generally understood by

respondents, that this is also the individual target for each department and each facility.

If energy efficiency is the policy objective, it cannot be judged without good energy

data. If the initial reference level for a target, the baseline, is not accurately defined

with reliable and accurate data then no point can be defined at which the target is

reached. This would mean that the target is equally meaningless. This does not mean

that efforts to save energy are valueless, but the 33% energy saving and 20% carbon

saving targets are strongly featured in policy documents when the baseline data to

support them does not yet exist.

Currently, accounting can readily report total council energy costs for gas,

electricity and fuel but this is not so easily done at present for individual council

departments who may not know what their own energy use is currently. Combined with

the great difficulties obtaining energy consumption data, reported by virtually all

respondents, this amounts to very weak energy accounting when judged relative to

Table 2.2. SEAI are now moving to ensure that consumption data is available shortly

but it is not clear that cost information will be strongly or directly linked to it as good

energy accounting demands.

Though respondents reported that kilowatt-hours are the measure preferred by

SEAI and governments, this requires the setting up of energy accounting systems, which

Page 142: Policy and Value: A Case Study of Local Authority Energy Management and Investment

130

are yet to be established and have numerous complications, as was noted by several

interviewees. The Green Plan aim for initial cost savings may well be a key target

metric because it is easier for all involved to understand money. Critically, it is already

highly monitored through standard financial accounting. As confirmed by personal

communication with the DCC Finance Office, energy costs are not currently accounted

for separately in this way, for each specific leisure centre for example. Doing this

would give a baseline energy cost for every centre, potentially with good historic data

also, against which to target improvements.

Examining bills carefully requires knowledge and analysis but can clearly pay

dividends as in the €24,000 saving made by an energy consultant on DCC electric bills.

Energy usage data is not being reported, or accounted for, even in large facilities, in

ways consistent with good energy management practice to enable checking of billing

and supplier-submitted arrears. The three largest leisure centres are significant energy

users but remain unmonitored whereas the OPW were noted as having interval

monitoring with remote logging on much smaller buildings. It would seem prudent to

ensure that monitoring, reporting and analysis are in place for the larger centres.

7.3.2.6 Provider Data

Frequently mentioned by respondents, the unacceptably poor quality of data

provided by energy suppliers is an on-going problem creating serious accounting

problems for the Finance Office in DCC and for facilities and departments bearing

energy costs. As reported, energy bills and arrears claims are difficult if not impossible

to verify, potentially allowing possible billing errors submitted by suppliers to be paid

but not allowing any effective means of checking the billing’s accuracy. The billing

problems appear to echo the “atrocious” UK utility billing practices (see section 2.2.4).

Page 143: Policy and Value: A Case Study of Local Authority Energy Management and Investment

131

As confirmed by the NPS (pc, email), the existing tendering contract allows the

NPS to enforce billing requirements and it would seem possible to insist on a simple

billing format from all energy suppliers providing uniform digital, soft-copy data

containing all relevant identification, cost, consumption, carbon emissions and meter

information on a single line of readily interpretable data (OPW, 2010, see S3.5, S1.2.2

and S2-2.7). The contract states “Tenderers shall supply such information in the

electronic format specified” (ibid.:14). When contacted regarding these findings, the

National Procurement Service (NPS, pc email) commented that building up the client

base of public sector bodies has been a major task and they will only be approaching the

suppliers once the many registration and supply point transferral resolutions have been

carried out and after the requirements of the many public sector bodies have been

ascertained. Energy policy that does not begin with good energy accounting, linking

cost and consumption, is compromised by poor data and will be of limited value. The

billing data problem would seem a straightforward one-off cost to address. As a

condition of tendering and as a supplier obligation this could be regulated for and

immediately enforced by government to support energy policy.

Further data problems noted by respondents were delays and information gaps

when obtaining meter point reference numbers (MPRNs and GPRNs) from the MRSO

when meter numbers were submitted. According to respondents there is no clear reason

why the data is not transparently available on-line.

7.3.2.7 Outcomes

The better outcomes reported in the findings include the on-line database of all

existing BERs made available by SEAI and the two area retrofits of estates in Tralee

and Dundalk. Few other positive outcomes were apparent from interviews though. At

local level, in DCC, the Minus 3% and Switch Off projects coordinated by Codema,

Page 144: Policy and Value: A Case Study of Local Authority Energy Management and Investment

132

were reported as notable successes, as judged by modelled results, as was a 10%

reduction in electricity use achieved by the IT department in the Civic Offices.

SDCC’s verifiable 15% savings using energy data combining cost and consumption

data were notable for being monitored savings from bills rather than modelled results.

SDCC and DLRCC both reported successful outcomes from using Energy MAP

guidance from SEAI in gaining a degree of knowledge and control over billing issues

though problems remain. SDCC and DCC have made efforts to upgrade public lighting

despite the lack of metering on these very large accounts. The plan by SDCC to tender

this account separately would seem a good option to establish its worth more exactly.

Newer public buildings have incorporated energy saving designs but frequently

the services have been installed in ways that do not enable ease of access to controls or

switching to facility managers.

7.3.2.8 Outcomes: DCC and DFB Green Plan

The outcomes reported from the Green Plan were qualitatively and quantitatively

different from other responses. The Plan’s declared aims of core sustainability of the

Dublin’s fire service have been matched by real projects with measured and verified

results at Kilbarrack Fire Station, following an initial grant investment which paid back

within four years. The long list of verified results, from many interrelating projects

supported by behavioural change, indicates a different approach from those generally

advocated in policy. There is a habit changing purpose to the Green Plan and the

firefighters’ achievements that is not clearly set out in government energy efficiency

literature or grant schemes.

The Fire Brigade has a very hierarchical and regimented structure that may well

have assisted the Green Plan after it was accepted but this may also indicate the level of

Page 145: Policy and Value: A Case Study of Local Authority Energy Management and Investment

133

commitment and teamwork that is required to achieve strong results, especially the kind

of early results that feed back to create a continuing impetus to do more. It is evident,

from the interview responses, from a visit to Kilbarrack Fire Station, and the level of

data gathering in research, measurement and verification, that evidence-based and

structured decision-making is part of the fire brigade’s modus operandi. Combined with

a strong purpose in carbon saving and behavioural change these factors have

transformed Kilbarrack from a highly wasteful building with a staff of firefighters with

low morale into the world’s first carbon neutral fire station, greatly increasing morale

and community support. The technical and procurement expertise developed by Neil

McCabe through his own research over several years has undoubtedly been critical to

successful implementation.

DCC have supported the Green Plan’s development and the next stage would

seem to be for individual departments to develop their own version by supporting their

operating staff in working through the Green Plan themes in their facilities or buildings.

Starting very simply, as happened at Kilbarrack where firefighters were surprised by

how many used batteries they could collect from their homes in a short time, was a

small but important first step. It would seem sensible to follow the same pattern by

supporting the most motivated staff to engage in sustainability in these simple and

rewarding ways first. The Green Plan began at one site with high potential savings, by

motivating and encouraging one team, it would seem sensible to start in the same way

again.

Page 146: Policy and Value: A Case Study of Local Authority Energy Management and Investment

134

CHAPTER 8 CONCLUSION

8.1 Conclusions and Recommendations

By using an Energy Management Matrix (EMM) framework of qualitative

assessment to answer the research question (Section 1.3), this research into energy

saving and carbon emissions reduction policy found that implementation at local

authority level in Dublin is only poorly consistent with good practice in energy

management and building retrofit investment. The EMM methodology proved an

effective framework for qualitative assessment of the gathered data. Only poor to

moderate levels of attainment were found in the qualitative EMM categories –

management structures, implementation and motivation, energy accounting and

investment, monitoring and targeting, and outcomes.

These results contrast markedly with those of the five year old DCC Green Plan

that began with a flagship, Dublin Fire Brigade project in Kibarrack Fire Station.

8.1.1 Energy Policy

This study’s findings, from the leisure centre survey, the document analysis and,

most strongly, the in-depth interviews, suggest that current energy and climate policy is

not a strong motivator of practice in local authorities, particularly compared with the

current pressing need for cost savings. As was clear from all respondents, there are

many hard working people in local authorities doing good work, but they are working

toward poorly defined, aspirational policy aims that appear to lack adequate funding or

effective regulatory bite to fulfil the stated intent.

The policy conflict between short term political or financial requirements and the

longer-term positive returns provided by energy and climate measures needs to be

Page 147: Policy and Value: A Case Study of Local Authority Energy Management and Investment

135

explicitly acknowledged and balanced if the targeted outcomes and the many potential

beneficial returns are to be achieved. The Green Plan focus on localised behavioural

change and carbon saving could improve both national and local policy.

8.1.2 Management Structure

Interview respondents noted problems with management buy-in, communications

and energy management knowledge. These were connected with departmentalised

structures and the ease with which energy usage can be ‘somebody else’s problem’.

Energy saving initiatives and programmes still tend to come from interested

departmental managers or energy agencies working on discrete programmes, often

without strong measurement and verification to measure results. The Green Plan results

show that strong management support for operational level staff, focusing on results-

based actions to change energy-usage habits and working practices, can achieve

excellent energy management and retrofit investment results. There may well be special

factors in the DFB success, associated with Neil McCabe and the fire brigade’s

management structure. Nonetheless, it would seem that there is much that local

authorities and national government can learn from the DCC Green Plan in saving costs,

energy and carbon emissions, as well as strengthening the resilience of services and

communities.

8.1.3 Implementation and Motivation

Indicative of weak attainment in EMM assessment, programmes of change to

improve energy saving were reported to be generally sporadic or dispersed, rather than

on-going and concentrated. Respondents noted a general lack of success in behavioural

change efforts and relatively few significant savings. The interview responses also

Page 148: Policy and Value: A Case Study of Local Authority Energy Management and Investment

136

indicated that grant funding approval processes impede deep retrofit outcomes by

limited appraisals, administrative delays and annual budget timetable constraints.

Given the results of this research, a much increased managerial understanding of

their own critical role in energy management is needed to continuously develop,

communicate, and support operational staff in achieving localised energy and carbon

savings.

8.1.4 Cost Analysis and Investment

The findings of this research support the view that neither the financial support

currently available nor the investment guidance from central government is sufficiently

strong to outweigh a past history of inadequate investment and current short-term cost

cutting due to the financial crisis. The leisure centre survey showed that inadequate

retrofit investment has occurred particularly in older buildings, and respondents noted

that this has also been true in social housing.

Both European and Irish government policy spells out a need for life cycle costing

to achieve medium and long-term value in buildings but these approaches are not

evident or possible in current council practice or grant funding schemes. The document

analysis and appraisal comparison undertaken showed that the data quality accepted and

the inferior ‘simple payback’ appraisal method used by SEAI are inconsistent with

investment practice, particularly for retrofit investments of public buildings. Interview

respondents also acknowledged that councils lack investment expertise. These

deficiencies will need to be addressed if local authorities are to engage confidently with

ESCo or energy suppliers in EPC arrangements in future.

The revolving-fund model, as used in the Green Plan, appears to be a relatively

risk free starting point for making savings, enabling a period of behavioural, technical

Page 149: Policy and Value: A Case Study of Local Authority Energy Management and Investment

137

and investment learning and encouraging progress by local ring-fencing of initial gains.

Though probably contingent on emulating the core Green Plan themes for success, this

would seem a pragmatic model for other local authorities and public sector bodies to

emulate, especially in current financial circumstances.

8.1.5 Monitoring and Targeting

Current policy gives headline targets but there is no disaggregation of targets to

council departments, or on an annual basis, nor are there strong ‘drivers’ that would

push achievement – by incentives, regulations or penalties. These factors ensure that

the policy lacks meaning for council managers and staff. Even when required, as DECs

are, compliance is not being enforced and there is little or no money available for

monitoring or reporting measures. Data quality to support the targets is beginning to

improve, but only eight years remain to reach targets that remain broadly undefined.

In the short term, an emphasis on monitoring and targeting energy cost might be

more useful than using energy consumption figures, as figures are more readily

available. Given the very large potential for savings, interval monitoring for the large

energy users like the bigger leisure centres would seem to be urgently required, and

until supplier data improves it would seem essential that all facility managers obtain on-

line access to their own facility bills by contacting their energy supplier directly.

8.1.6 Provider Data from Energy Suppliers

Data quality, as provided by energy suppliers, was reported by respondents to be

very poor indeed and not conducive to good energy accounting. An urgent need to

require energy suppliers to provide high quality, linked energy consumption and cost

digital data was identified. Though all respondents and the NPS were doubtful that this

Page 150: Policy and Value: A Case Study of Local Authority Energy Management and Investment

138

would change in the near future, it would seem to be more a matter of political will,

given that the suppliers already provide all the required data on hard copy bills.

8.1.7 Outcomes

All three methods utilised in this research enquiry showed that energy and carbon

saving outcomes in local authorities, from energy management and retrofit investment

in public buildings and housing, are not consistent with the exemplar public sector role

set out by policy. Some progress has certainly been made in the past four years but it

seems unlikely that current approaches are going to achieve the intended outcomes.

In contrast to the other findings, the DCC Green Plan, in use by Dublin Fire

Brigade, ranked highly in all EMM categories. It is likely that DFB as a whole will

meet the policy targets far earlier than scheduled, at very low cost and with multiple co-

benefits. The management structure and operational priorities of DFB encourage

structured decision-making and energy management but this research, and the published

verification data for the Green Plan, suggests that it is the deep sustainability ethos of

the plan that has focused these capabilities, achieving world-class reductions in carbon

emissions. Firefighters and management have achieved the policy targets without

requiring any further investment monies after the initial grant, by using a revolving

fund, reinvesting savings in further measures to increase sustainability.

In speed and depth, a locally championed plan appears to be outperforming other

national and agency implementation, producing exceptional cost, energy, and carbon

savings as well as conferring sustainability benefits of all kinds for staff, DFB and the

community. This template for success indicates that the most important ‘front line

agencies’ are people themselves, encouraged by their own successes in achieving

sustainable outcomes for their own workplace and their local community.

Page 151: Policy and Value: A Case Study of Local Authority Energy Management and Investment

139

8.2 Recommendations for further research

• Research interviews with city and county managers and councillors would

provide views of upper management and political leadership that would compare

and contrast with this research.

• Given the energy and climate change issues now faced, there is much scope for a

revival in energy management research: especially as to how operational level

local programmes can be best supported by departments and agencies at local

and national levels.

• Examining the investment case for particular sets of buildings, in line with the

new EPBD-R’s cost optimal methodology, would be valuable in showing where

opportunities lie for effective public investment, particularly in identifying the

optimum strategy for rolling retrofit in public buildings and social housing.

Page 152: Policy and Value: A Case Study of Local Authority Energy Management and Investment

140

REFERENCES

Aggerholm, S. (2009) Implementation of the EPBD in Denmark: Status November 2008

P136. Intelligent Energy Europe. Aggerholm, S. (2011) Cost Efficiency Evaluation Methodology Danish Approach

Presentation. European Commission: Expert Workshop Brussels, 16th March 2011.

Aggerholm, S, Erhorn, H, Hitchin, R, Erhorn- Kluttig, H et al. (2011) Cost Optimal Levels for Energy Performance Requirements. Intelligent Energy Europe: Concerted Action.

Alcott, B (2008) The Sufficiency Strategy: Would Rich-World Frugality Lower Environmental Impact? Ecological Economics 64 770-786.

Allcott, H and Greenstone, M (2012) Is There an Energy Efficiency Gap? WP-032. UC Center for Energy and Environmental Economics Working Paper Series. UCE3 1-37.

Anderson, K and Bows, A (2010) Beyond 'Dangerous' Climate Change: Emission Scenarios for a New World. Philosophical Transactions of the Royal Society A: Mathematical, Physical and Engineering Sciences 369 20-44. http://rsta.royalsocietypublishing.org/cgi/doi/10.1098/rsta.2010.0290

Anderson, K (2011) Climate Change: Going Beyond Dangerous – Brutal Numbers and Tenuous Hope. Tyndall Centre, University of Manchester. http://137.205.102.156/Ms%20S%20J%20Pain/20111124/Kevin_Anderson_-_Flash_(Medium)_-_20111124_05.26.31PM.html [Accessed 12 October 2012]

Ardente, F, Beccali, M, Cellura, M and Mistretta, M (2011) Energy and Environmental Benefits in Public Buildings as a Result of Retrofit Actions. Renewable and Sustainable Energy Reviews 15 460-470.

Bandy, G. (2011) Financial Management and Accounting in the Public Sector. (Routledge Masters in Public Management). Routledge.

Beer, M, Russell, A, Spector, B and Eisenstat (1990) Why Change Programs Don't Produce Change. Harvard Business Review 68 1-13.

Beggs, C. (2009) Energy: Management, Supply and Conservation. Elsevier Butterworth-Heinemann. Amsterdam ; London.

Benes, J, Chauvet, M, Kamenik, O, Kumhof, M et al. (2012) The Future of Oil: Geology Versus Technology. 1-33. IMF Working Paper WP/12/109.

BizEE (2012) Degreedays.Net - Custom Degree Day Data. www.degreedays.net [Accessed 22 September 2012]

Boardman, B (2004) Achieving Energy Efficiency Through Product Policy: The Uk Experience. Environmental Science & Policy 7 165-176.

Bottom, C (2006) Financial Management. In Facilities Management. (Ed, Booty, F) Elsevier. Oxford. pp. 183-227.

BPIE (2011) Europe's Buildings Under the Microscope. 1-132. Buildings Performance Institure Europe. http://dl.dropbox.com/u/4399528/BPIE/LR_%20CbC_study.pdf [Accessed 31 July 2012]

Brand, C and Boardman, B (2008) Taming of the Few—The Unequal Distribution of Greenhouse Gas Emissions From Personal Travel in the Uk. Energy Policy 36 224-238.

Brown, M A (2001) Market Failures and Barriers as a Basis for Clean Energy Policies. Energy Policy 29 1197-1207.

Page 153: Policy and Value: A Case Study of Local Authority Energy Management and Investment

141

Brown, P, Burke, M, Morris, G and Webster, P. (2010) The Salford Low-Energy House: Learning From Our Past. University of Salford.

Bulkeley, H and Betsill, M (2005) Rethinking Sustainable Cities: Multilevel Governance and the 'Urban' Politics of Climate Change. Environmental Politics Environmental Politics Environmental Politics 14 42-63. Routledge.

Bull, R, Chang, N and Fleming, P (2012) The Use of Building Energy Certificates to Reduce Energy Consumption in European Public Buildings. Energy and Buildings 50 103-110. http://linkinghub.elsevier.com/retrieve/pii/S0378778812001806

Buys, A, Bendewald, M and Tupper, K. (2011) Life Cycle Cost Analysis: Is it Worth the Effort? (Report): An Article From: ASHRAE Transactions. American Society of Heating, Refrigerating, and Air-Conditioning Engineers, Inc.

Capehart, B L, Turner, W C and Kennedy, W J. (2005) Guide to Energy Management. Fairmont Pr.

Caplehorn, P. (2012) Whole Life Costing: A New Approach. Routledge. Carbon Trust (2011) Energy Management. 1-53. Chidiac, S E, Catania, E J C, Morofsky, E and Foo, S (2011) Effectiveness of Single and

Multiple Energy Retrofit Measures on the Energy Consumption of Office Buildings. Energy 36 5037-5052.

Clinch, J P and Healy, J D (2000) Cost-Benefit Analysis of Domestic Energy Efficiency. Energy Policy 29 113-124.

Codema (2009) Covenant of Mayors. 1. Codema website. http://www.codema.ie/report-article/date/2009/06/23/covenant-of-mayors.html [Accessed 12 September 2012]

Considine, J and Reidy, T (2012) The Department of Finance. In Governing Ireland: From Cabinet Government to Delegated Governance. (Eds, O'Malley, E and Maccarthaigh, M) Institute of Public Administration. Dublin. pp. 88-105.

Cowart, R (2009) Carbon Revenue Recycling, Consumer Costs and Efficiency Solutions: Video. Institute of Irish and European Affairs. http://www.iiea.com/events/richard-cowart-on-emissions-trading-in-the-us-and-eu [Accessed 28 September 2012]

Cowart, R (2011) Cowart: Carbon Caps and Efficiency Resources. World Forum on Energy Regulation IV Athens 2009 (Presentation) 1-14.

Creswell, J and Plano Clark, V L. (2011) Designing and Conducting Mixed Methods Research. Sage Ltd.

Curtin, J. (2009) Greenprint for a National Energy Efficiency Retrofit Programme. Institute of International and European Affairs. Dublin.

da Graça Carvalho, M (2012) EU Energy and Climate Change Strategy. Energy 40 19-22.

DCC (2009) Climate Change Strategy for Dublin City: 2009 – First Year Review:. 1-29. Dublin City Council.

DCC (2010) Sustainability Report 2010. 1-32. Dublin City Council. DCC (2011) Green Plan. 1-2. Dublin City Council.

http://www.dublincity.ie/WaterWasteEnvironment/DublinFireBrigade/Documents/Kilbarrack%20Green%20Plan.pdf [Accessed 28 September 2012]

DCC (2012a) Climate Change Strategy for Dublin City. Dublin City Council website. http://www.dublincity.ie/WATERWASTEENVIRONMENT/SUSTAINABILITY/Pages/TheClimateChangeStrategyForDublinCity2008-2012.aspx [Accessed 15 October 2012]

DCC (2012b) Dublin City Sustainable Energy Action Plan 2010 - 2020. 1-45. DCC (2012c) Better Energy Workplaces Application Form 2012. 1-44. Dublin City

Council application for funding to SEAI.

Page 154: Policy and Value: A Case Study of Local Authority Energy Management and Investment

142

DCC (2012d) Dublin City Council Annual Report and Accounts 2011. 1-134. Dublin City Council,.

DCC/Codema (2008) Climate Change Strategy for Duiblin City. 1-26. Dublin City Council.

DCC/Codema. (2010a) Baseline Emission Inventory for Dublin City Sustainable Action Plan 2010-2020. Dublin City Council / Codema.

DCC/Codema (2010b) Dublin City Sustainable Energy Action Plan 2010 - 2020. 1-148. Dublin City Council.

DCENR (2009) Maximising Ireland’s Energy Efficiency: The National Energy Efficiency Action Plan NEEAP. 1-162. Department of Communications, Energy and Natural Resources.

DCENR (2010) National Energy Retrofit Programme: Consultation Document. Department of Communications, Energy and Natural Resources. Dublin.

de Almeida, P and Silva, P D (2009) The Peak of Oil Production—Timings and Market Recognition. Energy Policy 37 1267-1276.

DECLG (2011) National Climate Policy Review 2011. Department of Environment, Communities and Local Government.

DECLG (2012a) Latest Housing Statistics. Department of Environment, Community, and Local Government. http://www.environ.ie/en/Publications/StatisticsandRegularPublications/HousingStatistics/ [Accessed 27 September 2012]

DECLG (2012b) A Framework for Sustainable Development for Ireland. 1-116. Department of Environment, Community, and Local Government.

DEHLG (2010) Energy Efficiency Programme - Retrofitting. Improving Energy Efficiency in Local Authority Housing Stock. Department of Environment, Heritage and Local Government. http://www.oireachtas.ie/documents/committees30thdail/j-envherlocgov/correspondence/meetingnumber_j79/2010-Circ12.pdf [Accessed 27 September 2012]

Denny, E and O'Hagan, J W (2011) Physical Infrastucture, Energy and the Environment. In The Economy of Ireland: National and Sectoral Policy Issues. (Ed, O'Hagan, J W) Gill & Macmillan Ltd. pp. 262-294.

Denscombe, M. (2010) The Good Research Guide. McGraw-Hill. England. DFOE (2012) Cuts That Don't Hurt! 1-12. Dublin Friends of the Earth,. DoF. (2009) Capital Works Management Framework – Planning and Control of

Capital Costs, Guidance Note 2.2. Department of Finance. Dublin. DPER (2012) Project Discount &Amp; Inflation Rates. 1-2. Department of Public

Expenditure and Reform. Drexhage, J and Murphy, D (2012) Sustainable Development: From Brundtland to Rio

2012. Background Paper. 1-26. High Level Panel on Global Sustainability, United Nations.

EC (2012a) Action Plan for Energy Efficiency (2007-12). 1-4. European Commission. http://europa.eu/legislation_summaries/energy/energy_efficiency/l27064_en.htm

EC (2012b) Guide to Cost-Benefit Analysis of Investment Projects. 1-259. European Commission,.

EC (2012c) Proposal for a Directive of the European Parliament and of the Council on Energy Efficiency and Repealing Directives 2004/8/EC and 2006/32/EC. 1-82.

EC-EEE (2012) Cost Optimal Building Performance Requirements. European Council for an Energy Efficient Economy 1-38.

Page 155: Policy and Value: A Case Study of Local Authority Energy Management and Investment

143

Eisenführ, F, Weber, M and Langer, T. (2010) Rational Decision Making. Springer. London.

EPA (2003) Energy Efficiency Auditing. 1-29. Environmental Protection Agency. http://www.epa.ie/downloads/advice/licensee/EPA_guidance_note_energy_efficiency_auditing.pdf

Erhorn-Kluttig, H, Erhorn, H and Wössner, S (2004) Exemplary Retrofit Concepts in Europe: Energy-Efficient Public Buildings (Results From IEA/EU-Projects). 1-8. BRITA in PuBs.

EU (2010) Directive 2010/31/EU of the European Parliament and of the Council of 19 May 2010 on the Energy Performance of Buildings (Recast). 1-23.,European Union.

Euractiv.Com (2012) Parliament Gives Final Green Light to Energy Efficiency Directive. http://www.euractiv.com/energy-efficiency/european-parliament-gives-final-news-514732 [Accessed 26 September 2012]

European Union (2010) Directive 2010/31/EU of the European Parliament and of the Council of 19 May 2010 on the Energy Performance of Buildings. 1-23. European Union.

Ewing, M, Hough, A and Amajirionwu, M (2005) Environmental Democracy in Ireland Strive Report Series No. 86. 1-62. Environmental Protection Agency.

Fawkes, S. (2007) Outsourcing Energy Management: Saving Energy and Carbon Through Partnering. Gower. Aldershot, UK.

Fuller, S K. (2005) Guidance on Life-Cycle Cost Analysis Required By Executive Order 13123. USA Department of Energy, Federal Energy Management Program. Washington DC.

Gibbs, G R (2011) Coding Part 5: The Code List or Code Hierarchy. University of Hull. http://www.youtube.com/watch?v=DVpkuTdkZvA&feature=plcp [Accessed 27 August 2012]

Hallegatte, S, Shah, A, Lempert, R, Brown, C et al. (2012) Investment Decision Making Under Deep Uncertainty. Policy Research Working Paper 6193. The World Bank.

Helfert, E A. (2002) Techniques of Financial Analysis W/ Financial Genome Passcode Card: A Guide to Value Creation. McGraw-Hill Higher Education.

Helm, D (2008) Climate-Change Policy: Why Has So Little Been Achieved? Oxford Review of Economic Policy 24 211-238. http://oxrep.oxfordjournals.org/cgi/doi/10.1093/oxrep/grn014

Hernan, R E. (2010) Making Energy Efficiency Work for the Public Sector. Report. Irish Environment, Environmental Matters on the Island of Ireland.

Herring, H and Sorrell, S. (2009) Energy Efficiency and Sustainable Consumption: The Rebound Effect (Energy, Climate and the Environment). Palgrave Macmillan.

Hodge, G A and Greve, C (2009) Public–Private Partnerships. Institute of Economic Affairs 1-7.

Holmes, P. (1998) Investment Appraisal. Thomson Business Press. London. Hong, S, Oreszczyn, T and Ridley, I (2006) The Impact of Energy Efficient

Refurbishment on the Space Heating Fuel Consumption in English Dwellings. Energy and Buildings 38 1171-1181.

Huntingford, C, Lowe, J A, Gohar, L K, Bowerman, N H A et al. (2012) The Link Between a Global 2  °C Warming Threshold and Emissions in Years 2020, 2050 and Beyond. Environmental Research Letters 7 014039.

ICC (2009) International Climate Conference: Four Degrees and Beyond. Oxford University / Tyndall Centre. http://www.eci.ox.ac.uk/4degrees/programme.php [Accessed 19 September 2012]

Page 156: Policy and Value: A Case Study of Local Authority Energy Management and Investment

144

IEA (2008) Worldwide Trends in Energy Use and Efficiency. 1-94. IEA (2011a) Policy Pathway. 1-78. International Energy Agency. IEA (2011b) World Energy Outlook – Executive Summary. International, Energy

Agency. IIASA (2012) Global Energy Asessment. 1-118. International Institute for Applied

Systems Analysis,. IIEA (2012) Carbon Day 2012 Conference on Irelandʼs Climate Change Strategy. 1-2.

Institute of International and European Affairs. http://www.iiea.com/event/archive_view?urlKey=carbon-day-conference-on-irelands-climate-change-strategy [Accessed 5 October 2012]

Indecon (2005) Indecon Review of Local Government Financing. 1-352. Indecon Consultants & Inst. of Local Government Studies at University of Birmingham.

IPCC (2007) IPCC 4th Assessment Report Climate Change 2007: Synthesis Report. 1-52.

ISO (2008) ISO 15686 Life-Cycle Costing: Buildings and Constructed Assets. International Organisation for Standardisation 1-51.

Jackson, T (2005) Motivating Sustainable Consumption. Sustainable Development Research Network. 1-170.

Kaplan, R S and Norton, D P (1992) The Balanced Scorecard - Measures That Drive Performance. Harvard Business Review Jan-Feb 1992 71-79.

Kehily, D (2012) Guide to Life Cycle Costing. 1-23. Society of Chartered Surveyors. Kehily, D and Hore, A (2012) Life Cycle Cost Analysis Under Ireland&Apos;S Capital

Works Management Framework. 1-12. Kelsey, J and Pearson, D (2011) Updated Procedures for Commercial Building Energy

Audits. ASHRAE Transactions ML-11-C045 1-9. Koetse, M, De Groot, H and Florax, R A Meta-Regression Analysis of the Investment-

Uncertainty Relationship. In Improving Energy Efficiency Through Technology: Trends, Investment Behaviour and Policy Designimproving Energy Efficiency Through Technology: Trends, Investment Behaviour and Policy Design. (Eds, Koetse, M, De Groot, H and Mulder, P) Edward Elgar. pp. 352.

Kreith, F and Goswami, D Y. (2007) Energy Management and Conservation Handbook (Mechanical and Aerospace Engineering Series). CRC Press.

Kvale, S. (2007) Doing Interviews. SAGE. London. Lane, P R (2011) Role of Government: Rationale and Issues. In The Economy of

Ireland: National and Sectoral Policy Issues. (Ed, O'Hagan, J W) Gill & Macmillan Ltd. pp. 384.

Laustsen, J (2008) Energy Efficiency Requirements in Building Codes, Energy Efficiency Policies for New Buildings. IEA information paper 1-85.

LBNL (2010) Driving Demand for Home Energy Improvements. Lawrence Berkeley National Laboratory. Berkeley, CA, USA. pp.136

Little, J (2011) Joseph Little: Downloads and Lectures. Joseph Little Architects website. http://www.josephlittlearchitects.com/papers.html [Accessed 5 October 2012]

Lorenzoni, I, Jordan, A., O’Riordan, T., Turner, K., Hulme, M. (2000) A Co-Evolutionary Approach to Climate Change Impact Assessment: Part I. Integrating Socio-Economic and Climate Change Scenarios. Global Environmental Change 10 57-68.

Lovins, A B and Lovins, L H (1997) Climate: Making Sense and Making Money. Rocky Mountain Institute.

Page 157: Policy and Value: A Case Study of Local Authority Energy Management and Investment

145

Lstiburek, J (2007) The Perfect Wall. ASHRAE Journal May 2007 1-4. American Society of Heating, Refrigerating and Air-Conditioning Engineers.

MacCarthaigh, M (2012) From Agencification to De-Agencification: The Changing Bureaucratic Model. In Governing Ireland: From Cabinet Government to Delegated Governance. (Eds, O'Malley, E and Maccarthaigh, M) Institute of Public Administration. Dublin. pp. 128-151.

Maccarthaigh, M and O'Malley, E (2012) Conclusions: Reforming Govenment. In Governing Ireland: From Cabinet Government to Delegated Governance. (Eds, O'Malley, E and Maccarthaigh, M) Institute of Public Administration. Dublin. pp. 260-265.

Maréchal, K (2010) Not Irrational But Habitual: The Importance of “Behavioural Lock-In” in Energy Consumption. Ecological Economics 69 1104-1114.

Masoso, O T and Grobler, L J (2010) The Dark Side of Occupants’ Behaviour on Building Energy Use. Energy and Buildings 42 173-177.

McCabe, N (2011a) Green Plan Kilbarrack Fire Station. Briefing for Codema. 1-7. McCabe, N (2011b) Green Plan Kilbarrack Fire Station. 1-40. Dublin County Council. McNall, S (2010) Public Policy and Leadership: "We Have Met the Enemy and He is

Us". In Sustainable Communities Design Handbook: Green Engineering, Architecture, and Technology. (Ed, Clark, W W) A Butterworth-Heinemann Title. pp. 23-44.

Mcnicholl, A and Lewis, O. (1996) Green Design : Sustainable Building for Ireland. Stationery Office. Dublin.

Menassa, C C (2011) Evaluating Sustainable Retrofits in Existing Buildings Under Uncertainty. Energy and Buildings 43 3576-3583.

Metz, B. (2010) Controlling Climate Change. Cambridge University Press. Montier, J. (2009) Value Investing : Tools and Techniques for Intelligent Investment.

Hoboken, N.J.: Wiley ; Chichester : John Wiley [distributor], 2009. Moss, K. (2005) Energy Management in Buildings. Routledge. NESC (2009) Ireland's Five Part Crisis. 1-132. National Economic and Social Council. NESC (2012) Towards a New National Climate Policy: Interim Report of the NESC

Secretariat: Published 1 October 2012. National Economic and Social Council. New, M, Liverman, D, Schroder, H and Anderson, K (2010) Four Degrees and Beyond:

The Potential for a Global Temperature Increase of Four Degrees and Its Implications. Philosophical Transactions of the Royal Society A: Mathematical, Physical and Engineering Sciences 369 6-19. http://rsta.royalsocietypublishing.org/cgi/doi/10.1098/rsta.2010.0303

Norris, G A (2001) Integrating Life Cycle Cost Analysis and LCA. The International Journal of Life Cycle Assessment 6 118-120. Springer. http://www.springerlink.com/index/81611618N0184886.pdf

NSAI (2012) Driving Improved Energy Performance. National Standards Authority of Ireland website. http://www.nsai.ie/Our-Services/Certification/Management-Systems/ISO-50001-Energy-Management.aspx [Accessed 11 October 2012]

Nugent, N. (2010) The Government and Politics of the European Union. Palgrave Macmillan. Basingstoke.

Ó Dónaill, D (2011) Dundalk Area-Based Energy Retrofit Pilot. Institure of Irish and European Affairs website. http://www.iiea.com/ftp/RetrofitConf_PowerPoint/ESB%20Electric%20Ireland%20-%20Déaglán%20Ó%20Dónaill%20-%2023%20Sept%202011.pdf [Accessed 27 September 2012]

Page 158: Policy and Value: A Case Study of Local Authority Energy Management and Investment

146

O'Sullivan, J (2012) Housing Minister Jan O'Sullivan Announces Funding of Over €250 M to LAs From a Total Budget of 691 Million. MerrionStreet.ie Irish Government News Service. http://www.merrionstreet.ie/index.php/2012/03/housing-minister-jan-osullivan-announces-funding-of-over-e250m-to-las-from-a-total-budget-of-e691m/ [Accessed 27 September 2012]

OPW (2010) Electricity Framework Agreement (Public Sector) Ss/0001/10. 1-37. OPW, National Procurement Service.

Price, P. (2012) Dublin City Council, Culture, Recreation and Amenity Department Building Survey. Display Energy Certificate: Advisory Report. Codema/Dublin City Council. Dublin.

Punch, M (2009) The Irish Housing System - Vision, Values, Reality. 1-80. Rabitte, P (2012) Minister Welcomes New EU Energy Efficiency Directive. Teagasc.ie.

http://www.teagasc.ie/energy/news/june_news_2012/MinisterWelcomesNewEUEnergyEfficiencyDirective.pdf [Accessed 27 September 2012]

RTE (2011) Prime Time -3rd May 2011. RTE. http://www.rte.ie/news/2011/0503/blog-3may2011_primetime.html [Accessed 29 September 2012]

Ruegg, R and Short, W (2007) Economics Methods (Chapter 3). In Handbook of Energy Efficiency and Renewable Energy (Mechanical and Aerospace Engineering Series). (Eds, Kreith, F and Goswami, D Y) CRC Press. pp. 24.

Russell, C. (2010) Managing Energy From the Top Down : Connecting Industrial Energy Efficiency to Business Performance. CRC ; Taylor & Francis [distributor]. Boca Raton, Fla. London.

Ryan, L and Campbell, N (2012) Spreading the Net: The Multiple Benefits of Energy Efficiency Improvements. 1-37. International Energy Agency.

Sælen, H and Kallbekken, S (2011) A Choice Experiment on Fuel Taxation and Earmarking in Norway. Ecological Economics 70 2181-2190. http://linkinghub.elsevier.com/retrieve/pii/S0921800911002710

Schaffer, R H and Thomson, H A (1992) Successful Change Programs Begin With Results. Harvard Business Review Jan-Feb 1-11.

Scheer, J (2012) Alleviating Energy Poverty in Ireland –An Efficient Approach for Future Government Expenditure. Masters Thesis, Trinity College Dublin.

Scheer, J, Clancy, M and Ní Hogan, S (2012) Quantification of Energy Savings From Ireland’s Home Energy Saving Scheme: An Ex Post Billing Analysis. Energy Efficiency 1-16. Springer. http://dx.doi.org/10.1007/s12053-012-9164-8

Scheer, J and Motherway, B (2011) Economic Analysis of Residential and Small-Business Energy Efficiency Improvements. 1-32.

Scott, S, Lyons, S, Keane, C, McCarthy, D et al. (2008) Fuel Poverty in Ireland. Working Paper 262. 1-73. Economic and Social Research Institure.

SEAI (2008) Demand Side Management in Ireland - Main Report. 1-77. SEAI (2009a) Methodology for the Production of Display Energy Certificates (Dec).

Sustainable Energy Authority of Ireland 1-37. SEAI (2009b) Energy Efficiency in Ireland. Sustainable Energy Authority of Ireland 1-

66. SEAI (2011a) Tralee Town Council: Mitchels Beherbee Regeneration. Sustainable

Energy Authority Ireland. http://www.seai.ie/News_Events/Energy_Show/Seminars/Willie%20Moynihan.pdf [Accessed 27 September 2012]

SEAI (2011b) Energy in Ireland 1990 – 2010. Sustainable Energy Authority of Ireland. SEAI (2011c) CCMA Local Authority Energy Management Survey 2011. Sustainable

Energy Authority of Ireland

Page 159: Policy and Value: A Case Study of Local Authority Energy Management and Investment

147

SEAI (2012a) A Guide To Energy Performance Contracts and Guarantees. Sustainable Energy Authority of Ireland.

SEAI (2012b) Overview of Better Energy Workplaces 2011 and 2012: Presentation. Sustainable Energy Authority of Ireland. http://www.seai.ie/Grants/Better_Energy_Workplaces/Better%20Energy%20Workplaces.pdf [Accessed 23 September 2012]

SEAI (2012c) Better Energy Workplaces Fund 2012. 1-14. Sustainable Energy Authority of Ireland. http://www.seai.ie/Grants/Better_Energy_Workplaces/Better_Energy_Workplaces_Application_Guide.pdf

SEAI (2012d) Energy Efficiency in the Public Sector:. 1-12. Sustainable Energy Authority of Ireland.

SEAI (2012e) BER Research Tool User Information Guide. 1-38. Sustainable Energy Authority of Ireland.

SEAI (2012f) Energy Map. 1-38. Sustainable Energy Authority of Ireland website. http://www.seai.ie/EnergyMAP/ [Accessed 12 October 2012]

SEAI (2012g) User Guide to the Calculation Tool for Display Energy Certificates (Dec) for Large Public Buildings. 1-33.

SEAI (2012h) Energy Use in the Public Sector. 1-32. Sustainable Energy Authority of Ireland. http://www.seai.ie/Publications/Your_Business_Publications/Energy_Use_in_the_Public_Sector.pdf

SEAI (2012i) Better Energy Workplaces Fund 2012 Webpage. Sustainable Energy Authority of Ireland. http://www.seai.ie/Grants/Better_Energy_Workplaces/ [Accessed 23 September 2012]

SEI (2004) Investing in Energy. Sustainable Energy Ireland. Spackman, M (1997) Hypothecation: A View From the Treasury. In Ecotaxation. (Ed,

O'Riordan, T) Earthscan. London. Temborius, M (2012) Improvement of Building Energy Efficiency in Dublin: Sports and

Leisure Centres: Author's Draft (Personal Communication). BSc. thesis, Hockschule Ostwestfalen-Lipp, University of Applied Science.

Togeby, M, Dyhr-Mikkelsen, K, Larsen, A, Hansen, M J et al. (2009) Danish Energy Efficiency Policy: Revisited and Future Improvements. eceee Summer Study 299-310. European Council for an Energy Efficient Economy.

Trainer, F E (1999) The Significance of the Limits to Growth for the Discussion of Social Policy. International Journal of Sociology and Social Policy 18 1-25. message:%[email protected]%3E

Triantaphyllou, E (1997) A Sensitivity Analysis Approach for Some Deterministic Multi-Criteria Decision Making Methods. Decision Sciences 28 151-194.

UCC (2012) Irish University is World's First to Achieve ISO 50001 Standard University College Cork. http://www.ucc.ie/en/build/energy/ISO50001/ [Accessed 11 October 2012]

UK Government (2008) Strategy for Sustainable Construction. 1-64. Department for Business, Enterprise & Regulatory Reform Construction Sector Unit.

UN-WCED (1997) Our Common Future. Chairman: Brundtland, G H Report to United Nations World Commission on Environment and Climate Change. http://www.un-documents.net/ocf-ov.htm#1.2 [Accessed 14 September 2012]

US-EPA (2012) Assess Your Energy Management Program – (Energy Program Assessment Matrix). US Environmental Protection Agency - Energy Star. [Accessed 26 September 2012]

Page 160: Policy and Value: A Case Study of Local Authority Energy Management and Investment

148

Verbeeck, G and Hens, H (2005) Energy Savings in Retrofitted Dwellings: Economically Viable? Energy and Buildings 37 747-754.

Verbruggen, A (2012) Financial Appraisal of Efficiency Investments: Why the Good May be the Worst Enemy of the Best. Energy Efficiency

Verbruggen, A and Al Marchohi, M (2010) Views on Peak Oil and Its Relation to Climate Change Policy. Energy Policy 38 5572-5581.

Verbruggen, A, Marchohi, M A and Janssens, B (2011) The Anatomy of Investing in Energy Efficient Buildings. Energy and Buildings 43 905-914.

Vining, A R and Boardman, A E (2008) Public-Private Partnerships: Eight Rules for Governments. Public Works Management Policy 13 149-161. Sage.

Wajer, B H (2005) Energy Management Implementation Model and Standards. 1-88. Intelligent Energy – Europe (EIE) EIE/04/246/S07.38678

Wood, S (2010) Europe's Energy Politics. Journal of Contemporary European Studies 18 307-322.

Wyse, R (2012) Assessing the Potential for Reductions in Irish Local Authority Residential Energy Consumption. MSc. Thesis, De Montfort University.

Yan-ping, F, Yong, W and Chang-bin, L (2009) Energy-Efficiency Supervision Systems for Energy Management in Large Public Buildings: Necessary Choice for China. Energy Policy 37 2060-2065.

Yudelson, J. (2010) Greening Existing Buildings. McGraw-Hill. New York. Zirngibl, J and Francois, C Information Paper on EN 15459, Energy Performance of

Buildings- Economic Evaluation Procedure for Energy Systems in Buildings. Intelligent Energy Europe. www.buildup.eu


Recommended