Date post: | 01-Jun-2018 |
Category: |
Documents |
Upload: | nikhil-aggarwal |
View: | 229 times |
Download: | 0 times |
of 65
8/9/2019 POM 16 - MRP
1/65
Upendra Kachru OPERATIONS MANAGEMENT
Material Requirement
Planning
8/9/2019 POM 16 - MRP
2/65
Upendra Kachru OPERATIONS MANAGEMENT
Material Requirements Planning
Materials requirements planning (MRP) is a means fordetermining the number of parts, components, and
materials needed to produce a product
MRP provides time scheduling information specifying
when each of the materials, parts, and components should
be ordered or produced
Dependent demand drives MRP
MRP is a software system
8/9/2019 POM 16 - MRP
3/65
Upendra Kachru OPERATIONS MANAGEMENT
MATERIAL PLANNING
Master Production
Schedule (MPS)
Material
Requirements
Planning (MRP)
Inventory
Status
Records
Product
Structure
Records
Purchasing Manufacturing
(what we plan)
(what we have) (what we require)
(what we need)
8/9/2019 POM 16 - MRP
4/65
Upendra Kachru OPERATIONS MANAGEMENT
Primary Prerequisites
For MRP
1. A Master Production Schedule exists
and can be stated in bill of materials
form;
2. All inventory items are uniquely
identified;
3. A bill of material exists at the time of
planning
4. Inventory records contain data on the
status of every item;5. There is integrity of file data.
8/9/2019 POM 16 - MRP
5/65
Upendra Kachru OPERATIONS MANAGEMENT
Master Data
Material Master
MRP Group - Group common MRP materials together MRP Type - Planning Method.
Planning Time Fence - Restricts Activities
Lot Sizing - Lot Size determination
Storage Cost Indicators - For Optimum Lot sizing Only
Ordering Costs
Assembly Scrap - For Assembly Scrap Only
Procurement Type - Make or Buy Indicator.
Safety Stock
8/9/2019 POM 16 - MRP
6/65
Upendra Kachru OPERATIONS MANAGEMENT
Based on a master production
schedule, a materialrequirements planning system:
Creates schedules identifying the
specific parts and materials
required to produce end items
Determines exact unit numbersneeded
Determines the dates when orders
for those materials should be
released, based on lead times
Material
Requirements
Planning System
8/9/2019 POM 16 - MRP
7/65
Upendra Kachru OPERATIONS MANAGEMENT
Primary MRP Reports
Planned ordersto be released at a future time
Order release noticesto execute the planned orders
Changes in due datesof open orders due to rescheduling
Cancellations or suspensionsof open orders due to
cancellation or suspension of orders on the masterproduction schedule
I nventory status data
8/9/2019 POM 16 - MRP
8/65
Upendra Kachru OPERATIONS MANAGEMENT
Secondary MRP Reports
Planning reports, for example, forecasting inventoryrequirements over a period of time
Performance reportsused to determine agreement
between actual and programmed usage and costs
Exception reportsused to point out seriousdiscrepancies, such as late or overdue orders
8/9/2019 POM 16 - MRP
9/65
Upendra Kachru OPERATIONS MANAGEMENT
Scheduling
Procurement type
Lot-size calculation
Net Requirements Calculation
BOM Explosion: Determinethe valid BOM for explosion
Overview : BOM ExplosionBill of Materials
8/9/2019 POM 16 - MRP
10/65
Upendra Kachru OPERATIONS MANAGEMENT
The bill of materials is a materials list that provides informationuseful to reconstruct the manufacturing process.
It is the master product definition that contains as-designed
information.
The information includes product description:
Materials
Parts
Components
Production sequence
Bill of Materials
A T pical Engineering Bill of Materials
8/9/2019 POM 16 - MRP
11/65
Upendra Kachru OPERATIONS MANAGEMENT
A Typical Engineering Bill of Materials
Level Part- Revision Quantity Description Make/buy
1 16844-23003 B 1 Adapter Make
16844-23004 J 1 Control Unit Buy
16844-23010 C 3 Moisture
Tester
Make
16844-23023 B 2 Enclosure Buy
16844-23024 B 1 Enclosure Buy
16844-23025 D 2 Machine
Screw
Buy
16844-23033 F 3 Cover Buy
16844-23030 AA 4 Precipitatory
Assy.
Make
16844-23040 E 5 Element Buy
16844-23043 E 6 Housing Buy
16844-23048 D 4 Machine Buy
16844-23049 G 3 Precipitator Buy
8/9/2019 POM 16 - MRP
12/65
Upendra Kachru OPERATIONS MANAGEMENT 12
The bill of material file provides
complete information on:
Raw materials in stock
Semi finished component parts in
stock
Finished component parts in stock
Sub-assemblies in stock
Component parts in processSub-assemblies in process
BOM File
8/9/2019 POM 16 - MRP
13/65
Upendra Kachru OPERATIONS MANAGEMENT
Each inventory item is carried as a
separate file
The bill of materials pegs materials i.e.lists components of each assembly and
subassembly linking of individual item
bills which from the product, resulting
in a hierarchical, and pyramid like
structure with different levels.
It Identifies each parent item that
created demand
Bill Of Materials
(BOM) File:
8/9/2019 POM 16 - MRP
14/65
Upendra Kachru OPERATIONS MANAGEMENT
Typical Product Structure
F G
ZNHA
P
B I XR Q X
Q R SX
D
E
Parent
Level 1
Level 2
Level 3
The bill of material file guides the explosion process.
O S i
8/9/2019 POM 16 - MRP
15/65
Upendra Kachru OPERATIONS MANAGEMENT
Planned orderPriority
1
2
Usage
Production
Engineering
BOM Selec t ion ID
Production
BOM
Costing
BOMEngineering
BOM
Used if no valid production
BOM exists
BOM Selection
8/9/2019 POM 16 - MRP
16/65
Upendra Kachru OPERATIONS MANAGEMENT
It is an artificial grouping of items
in bill of materials format, which
expresses the relationship of
multiple product features, variantsand options, where inventory
items are arranged in terms of
product modules each of which
can be planned as a group.
Modular Bill of
Materials
Modular bill kept for each major
subassembly
Simplifies forecasting and planning
8/9/2019 POM 16 - MRP
17/65
Upendra Kachru OPERATIONS MANAGEMENT
4-Cylinder (.40) Bright red (.10) Leather (.20) Grey (.10) Sports coupe (.20)6-Cylinder (.50) White linen (.10) Tweed (.40) Light blue (.10) Two-door (.20)
8-Cylinder (.10) Sulphur yellow (.10) Plush (.40) Rose (.10) Four-door (.30)
Neon orange (.10) Off-white (.20) Station wagon (.30)
Metallic blue (.10) Cool green (.10)
Emerald green (.10) Black (.20)
Jet black (.20) Brown (.10)
Champagne (.20) B/W checked (.10)
X10Automobile
Engines Exterior color Interior Interior color Body(1 of 3) (1 of 8) (1 of 3) (1 of 8) (1 of 4)
Modular BOM
Combinations = 3 x 8 x 3 x 8 x 4 = 2,304 configurations
Combinations = 3 + 8 + 3 + 8 + 4 = 26 modular bills
8/9/2019 POM 16 - MRP
18/65
Upendra Kachru OPERATIONS MANAGEMENT
There are two somewhat different
objectives, in modularization.
To disentangle combination of
optimal product features.
To segregate common from unique,
or peculiar parts.
The first is required to facilitate
forecasting.
The second is aimed at minimizing
inventories in components that are
common to option alternatives
Objectives ofModularization
8/9/2019 POM 16 - MRP
19/65
Upendra Kachru OPERATIONS MANAGEMENT
Net Requirements
Calculation
Net Requirements Calculation
8/9/2019 POM 16 - MRP
20/65
Upendra Kachru OPERATIONS MANAGEMENT
Assumptions1. Individual item lead times are known;
2. Every inventory item goes into and outof stock
3. All of the components of an assembly
are needed at the time of release of
assembly orders;
4. There is discrete disbursement and
usage of component materials
5. Process independence of manufactured
items is ensured.
8/9/2019 POM 16 - MRP
21/65
Upendra Kachru OPERATIONS MANAGEMENT
Net Requirements Calculation
MRP will compare the requirement and supply to get a
shortage gap. A comparison is made betweenstore/warehouse stock and the appropriate receipts and
issue.
1. Determine Available Store/Warehouse Stock
2. Determine Planned Receipts (afterconsidering existing issues andreceipts)
3. Calculate the Shortage Quantity
8/9/2019 POM 16 - MRP
22/65
Upendra Kachru OPERATIONS MANAGEMENT
MRP: Net Requirements Calculation
ShortageShortage
SalesSales OrdersOrders
Planned Ind ReqmtsPlanned Ind Reqmts
Dependent ReqmtsDependent Reqmts
ReservationsReservations
Planned Orders
Production Orders
Purchase Requisitions
Purchase orders
Warehouse Stock
Lot Size
SafetySafety
StockStock
CompareCompare
DemandSupply
Matching Demand and Supply
H th Pl i R W k
8/9/2019 POM 16 - MRP
23/65
Upendra Kachru OPERATIONS MANAGEMENT
How the Planning Run Works
Reorder Point Planning
When Available Stock falls below reorder level, planned orders are
generated in the planning run to order up to reorder level. Safety Stock
requirement is just for information
Available Stock = Plant Stock + Receipts
Forecast Based Planning
System only considers forecast requirements (any other requirements are not
considered). Planned orders are proposed when available stock is less than
forecast requirements.
Available Stock = Plant stock - Safety Stock + Receipts - Forecast Requirements
In the net requirements calculation, a difference is made between
reorder point planning, forecast-based planning, and MRP. In each
procedure, the system calculates available stock differently.
BOM E l i
8/9/2019 POM 16 - MRP
24/65
Upendra Kachru OPERATIONS MANAGEMENT
/dates
Target
Change status
Component selection
Dependent reqmts
quantities and dates
Usage
Lot size
Explosion date
Items relevant to production
BOM Explosion
Usage quantity
BOM E l i S l ti b O d St t
8/9/2019 POM 16 - MRP
25/65
Upendra Kachru OPERATIONS MANAGEMENT
Time
BOM 1 BOM 2 BOM 3
Valid from(relevant to
planning from )
Valid from(relevant to
planning from )
Valid from(relevant to
planning from )
Order 1 Order 2
Order startOrder start
BOM Explosion: Selection by Order Start
Explosion: Using the Order Finish Date
8/9/2019 POM 16 - MRP
26/65
Upendra Kachru OPERATIONS MANAGEMENT
Time
BOM 1 BOM 2 BOM 3
Valid from
(relevant to
planning from )
Valid from(relevant to
planning from )
Valid from
(relevant to
planning from )
Order 1 Order 2
Order finishOrder finish
Explosion: Using the Order Finish Date
Safety Stock
dli S f S k
8/9/2019 POM 16 - MRP
27/65
Upendra Kachru OPERATIONS MANAGEMENT
Reqmt Receipt
Stock
TimeSafety stock
(not available
for planning)
Available
quantity
for planning
Safety s tock : To be set in mater ialmaster
y
Handling Safety Stock
8/9/2019 POM 16 - MRP
28/65
Upendra Kachru OPERATIONS MANAGEMENT
Planning Time Fence
Plan is protected from changes within the planning time fence.
End date of time fence determined from planning date.You can configure system as to how you want the orders to react
within the time fence.
8/9/2019 POM 16 - MRP
29/65
Upendra Kachru OPERATIONS MANAGEMENT
Planning Time Fence
Outside the time fence, system creates order proposal as usual.
When new orders move into the time fence, they may be firmedautomatically depending on how the system is configured.
Firming Types for MRP Planned Materials :
Firming TypesOrders Moving IntoTimeFence
New OrderProposals Creation
New OrderStatus
Type 1 Firmed Outside Time Fence Not Firmed
Type 2 Firmed No Orders Created NA
Type 3 Not Firmed Outside Time Fence Not Firmed
Type 4 Not Firmed No Orders Created NA
L t Si C l l ti d S h d li:
8/9/2019 POM 16 - MRP
30/65
Upendra Kachru OPERATIONS MANAGEMENT
Scheduling
Procurement type
Lot- size calculation
Lot Size Calculations and Scheduling
Overview of Lot- Sizing ProceduresD fi iti i
8/9/2019 POM 16 - MRP
31/65
Upendra Kachru OPERATIONS MANAGEMENT
Static
procedures
Static
procedures
Lot- for-lot order quantity
EOQ
Fixed lot size
Period
procedures
Other
procedures
Optimal Lot sizing
Lot-Lot- sizing proceduressizing procedures
Entered in
Material master
Definition in
Customizing
Determining the Lot Size
8/9/2019 POM 16 - MRP
32/65
Upendra Kachru OPERATIONS MANAGEMENT
Lot Sizing in MRP Programs
Lot-for-lot (L4L) Economic order quantity (EOQ)
Least total cost (LTC)
Least unit cost (LUC)
Which one to use? The one that is least costly!
Optimum Lot- Sizing Procedures
8/9/2019 POM 16 - MRP
33/65
Upendra Kachru OPERATIONS MANAGEMENT
Many deliveries /
High order costs
Minimal stockkeeping/
Minimal storage costs
Few deliveries /
Low order costs
More extensive stockkeeping/Higher storage costs
Optimum Lot Sizing Procedures
Procurement Types
8/9/2019 POM 16 - MRP
34/65
Upendra Kachru OPERATIONS MANAGEMENT
External procurementStockStock transfertransfer
Procurement TypesProcurement Types
In-In- househouse
productionproduction
SubcontractingSubcontracting VendorProductionProduction inin
ownown plantplantProductionProduction inin
anotheranother plantplant
Reservation inReservation in
anotheranother plantplantComponentsComponentsComponents
Procurement typesSpecial procurement types
yp
Backward Scheduling
8/9/2019 POM 16 - MRP
35/65
Upendra Kachru OPERATIONS MANAGEMENT
Planned orderPlanned order
Availability
date
Opening
date
Order start
date
Order finish
date
Tim
Goods receipt
processing timeIn-house production time
Opening period
Schedul ing margin
key (MRP 2)
Lot - s ize dependen t : MRP 2
Lo t- s ize i ndependen t : wo rk schedu li ngMRP 2
Scheduling
8/9/2019 POM 16 - MRP
36/65
Upendra Kachru OPERATIONS MANAGEMENT
Scheduling
The following times are taken into account :
Processing time required by purchasing department (workdays)
Planned delivery time of the material (calendar days)
Goods receipt processing time (workdays)
These times will be used to determine the release date of the
planned order or purchase requisition.
8/9/2019 POM 16 - MRP
37/65
Upendra Kachru OPERATIONS MANAGEMENT
MRP Example
A(2) B(1)
D(5)C(2)
X
C(3)
Item On-Hand Lead Time (Weeks)
X 50 2
A 75 3
B 25 1
C 10 2
D 20 2
Requirements include 95 units (80 firm orders and 15 forecast) of X in
week 10
Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95
LT=2 Scheduled receipts
8/9/2019 POM 16 - MRP
38/65
Upendra Kachru OPERATIONS MANAGEMENT
A(2)
X
p
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20C Gross requirements 45 40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
It takes 2
As foreach X
Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95
LT=2 Scheduled receipts
8/9/2019 POM 16 - MRP
39/65
Upendra Kachru OPERATIONS MANAGEMENT
p
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20C Gross requirements 45 40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
B(1)A(2)
X
It takes 1
B foreach X
Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95
LT=2 Scheduled receipts
8/9/2019 POM 16 - MRP
40/65
Upendra Kachru OPERATIONS MANAGEMENT
A(2) B(1)
X
C(3)
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20C Gross requirements 45 40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
It takes 3
Cs for
each A
Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95
LT=2 Scheduled receipts
8/9/2019 POM 16 - MRP
41/65
Upendra Kachru OPERATIONS MANAGEMENT
A(2) B(1)
C(2)
X
C(3)
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20C Gross requirements 45 40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
It takes 2
Cs for
each B
Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95
LT=2 Scheduled receipts
8/9/2019 POM 16 - MRP
42/65
Upendra Kachru OPERATIONS MANAGEMENT
A(2) B(1)
D(5)
C(2)
X
C(3)
Proj. avail. balance 50 50 50 50 50 50 50 50 50 50
On- Net requirements 45
hand Planned order receipt 45
50 Planner order release 45
A Gross requirements 90
LT=3 Scheduled receipts
Proj. avail. balance 75 75 75 75 75 75 75 75On- Net requirements 15
hand Planned order receipt 15
75 Planner order release 15
B Gross requirements 45
LT=1 Scheduled receipts
Proj. avail. balance 25 25 25 25 25 25 25 25
On- Net requirements 20
hand Planned order receipt 20
25 Planner order release 20C Gross requirements 45 40
LT=2 Scheduled receipts
Proj. avail. balance 10 10 10 10 10
On- Net requirements 35 40
hand Planned order receipt 35 40
10 Planner order release 35 40
D Gross requirements 100
LT=2 Scheduled receipts
Proj. avail. balance 20 20 20 20 20 20 20On- Net requirements 80
hand Planned order receipt 80
20 Planner order release 80
It takes 5 Ds
for each B
MRP Cl d L S t
18-4
8/9/2019 POM 16 - MRP
43/65
Upendra Kachru OPERATIONS MANAGEMENT
MRP - Closed Loop System
Production Planning
Master Production Scheduling
Material Requirements Planning
Capacity Requirements Planning
Realistic?No
Feedback
Execute:
Capacity PlansMaterial Plans
Yes
Feedback
8/9/2019 POM 16 - MRP
44/65
Upendra Kachru OPERATIONS MANAGEMENT
MRP Scheduling Terminology
Gross Requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipt
Planned order release
Forward Scheduling
8/9/2019 POM 16 - MRP
45/65
Upendra Kachru OPERATIONS MANAGEMENT
AvailabilitydateOrder startdate Order finishdate
Time
Goods receipt
processing timeIn-house production time
Today
Planned orderPlanned order
Au tomatic, i f order start date is in th e
past dur ing backward schedul ing
8/9/2019 POM 16 - MRP
46/65
What is ERP?
8/9/2019 POM 16 - MRP
47/65
Upendra Kachru OPERATIONS MANAGEMENT
What is ERP? Enterprise Resource Planning
It attempts to integrate all data and processes of an organization intoa unified system. A typical ERP system will use multiplecomponents of computer software and hardware to achieve theintegration. A key ingredient of most ERP systems is the use of aunified database to store data for the various system modules.
E ol tion of ERP
8/9/2019 POM 16 - MRP
48/65
Upendra Kachru OPERATIONS MANAGEMENT
Evolution of ERP
1960s: software packages with inventory control
1970s: MRP systems
Production schedule with materials management
1980s: MRPII systems
Adds financial accounting system
1990s: MRPII Integrated systems for manufacturing execution
Late 1990s: ERP
Integrated manufacturing with supply chain
2000s: ERP II
ERP Definition
8/9/2019 POM 16 - MRP
49/65
Upendra Kachru OPERATIONS MANAGEMENT
ERP - Definition
ERP is a process of managing all resources and their use in the entire
enterprise in a coordinated manner
ERP is a set of integrated business applications, or modules which carry out
common business functions such as general ledger, accounting, or order
management
Put simply, ERP systems tie together varied processes using data
from across the company. For instance, a typical ERP system
manages functions and activities as different as the bills of materials,
order entry, purchasing, accounts payable, human resources, and
inventory control, to name just a few of the modules.
Problems of Legacy Systems
8/9/2019 POM 16 - MRP
50/65
Upendra Kachru OPERATIONS MANAGEMENT
Problems of Legacy Systems Automates existing processes
Normally not driven by organization strategy and business vision. Develop one application at a time. No integration between applicationsjust
transaction passing.
Decentralized applications.
Are relatively inflexible to accommodate changes in the business environment.
Written in language / platform prevalent at the time of development. Up gradation to latest technology is difficult
Usually not well documented.
Maintenance is a problemlargely because of poor documentation and staffattrition.
What makes ERP different
8/9/2019 POM 16 - MRP
51/65
Upendra Kachru OPERATIONS MANAGEMENT
What makes ERP different
Supports business through optimizing, maintaining,and tracking business functions
Integrated modules
Common definitions
Common database
Update one module, automatically updates others ERP systems reflect a specific way of doing business
Must look at your value chains, rather than functions
Process View of Business
8/9/2019 POM 16 - MRP
52/65
Upendra Kachru OPERATIONS MANAGEMENT
Sales
F
unction
Ac
counting
F
unction
Pu
rchasing
F
unction
Production
F
unction
Logistics
F
unction
Material Order Process
Customer Order Process
The basic ERP Model is based on a process view of the organization. Each of the tasks
may cross functional boundaries
ERP Structure
8/9/2019 POM 16 - MRP
53/65
Upendra Kachru OPERATIONS MANAGEMENT
The foundation of ERP systems is popularly called the Stool. The stool is made up of three
basic elements Market Sales and Distribution, the Product Materials Management and
Production and the Financial Accounting and Control.
8/9/2019 POM 16 - MRP
54/65
Financials
8/9/2019 POM 16 - MRP
55/65
Upendra Kachru OPERATIONS MANAGEMENT
Financials
Financial and management accounting
Internal Controlling and Audit
Financial Supply Chain Management
General Ledger
Financial Reporting Costing
Budgeting
Accounts Payable
Accounts receivables
Human Capital Management
8/9/2019 POM 16 - MRP
56/65
Upendra Kachru OPERATIONS MANAGEMENT
Human Capital Management
Recruiting
Applicant data administration Compensation
Assessment
Development and Training
Personnel development planning
Payroll Benefits administration
Workforce planning
Schedule & shift planning
Time management Travel expense accounting
Marketing & Sales Management
8/9/2019 POM 16 - MRP
57/65
Upendra Kachru OPERATIONS MANAGEMENT
Marketing & Sales Management
Lead tracking
Sales forecasting
Order management
Customer management
Customer service
8/9/2019 POM 16 - MRP
58/65
Example of How ERP Works
8/9/2019 POM 16 - MRP
59/65
Upendra Kachru OPERATIONS MANAGEMENT
Example of How ERP Works
Step 1 : Brazilian retailer orders, via the Internet, 1,000 shoes
from International Shoe Co. A sales rep takes the order, routes it
to ERPs ordering module, ERP checks the retailer credit, price,etc. The order is approved.
Step 2 : Simultaneously ERPs inventory module checks the
stocks and notifies the rep that half the order can be filled
immediately from stock. The other half will be manufacturedand delivered in 5 days directly from the factory in Taiwan.
ERP delivers a single database that contains all data for the software
modules across an entire company. People in different departments all seethe same information and can update it. For example:
Example of How ERP Work
8/9/2019 POM 16 - MRP
60/65
Upendra Kachru OPERATIONS MANAGEMENT
Step 3 : ERPs manufacturing module schedules the production in
Taiwan and instructs the warehouse (in China) to ship the shoes to
Brazil and print up an invoice (in Portuguese).
Step 4 : ERPs human resources module calculates labor
requirements. Due to a shortage, the personnel manager in Taiwan
is instructed to get temporary workers. Step 5 : ERPs material planning module notifies the purchasing
manager about a shortage of purple dye. A purchase order is
automatically issued.
Example of How ERP Work
8/9/2019 POM 16 - MRP
61/65
Upendra Kachru OPERATIONS MANAGEMENT
Example of How ERP Work
Step 6 : The customer logs on via the extranet to thecompanys sneakers division. He can see that 500 shoes were
shipped from the regional warehouse. This is done with ERP
tracing capabilities.
Step 7 : Based on data from ERPs forecasting and financial
modules, the CEO can determine both demand and
profitability per product. The financial module also converts
all foreign money to $U.S., whenever needed
Benefits of ERP
8/9/2019 POM 16 - MRP
62/65
Upendra Kachru OPERATIONS MANAGEMENT
Benefits of ERP
Desire to standardize and improve processes
To improve the level of systems integration
To improve information quality
Common set of data
Help in integrating applications for decision making and
planning
Allow departments to talk to each other
Easy to integrate by using processed built into ERP software
A way to force BPR (reengineering)
Difficulty in implementation
8/9/2019 POM 16 - MRP
63/65
Upendra Kachru OPERATIONS MANAGEMENT
y p
Very difficult
Extremely costly and time intensive
Typical: over $10,000,000 and over a year to implement
Company may implement only certain modules of entire
ERP system
You will need an outside consultant
Common Pitfalls
8/9/2019 POM 16 - MRP
64/65
Upendra Kachru OPERATIONS MANAGEMENT
Do not adequately benchmark current state
Did not plan for major transformation
Did not have executive sponsorship
Did not adequately map out goals and objectives
Highly customized systems to look like old MRP systems
8/9/2019 POM 16 - MRP
65/65
Upendra Kachru OPERATIONS MANAGEMENT
C l i c k t o e d i t c o m p a n y s l o g a n .