+ All Categories
Home > Documents > POM 16 - MRP

POM 16 - MRP

Date post: 01-Jun-2018
Category:
Upload: nikhil-aggarwal
View: 229 times
Download: 0 times
Share this document with a friend

of 65

Transcript
  • 8/9/2019 POM 16 - MRP

    1/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Material Requirement

    Planning

  • 8/9/2019 POM 16 - MRP

    2/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Material Requirements Planning

    Materials requirements planning (MRP) is a means fordetermining the number of parts, components, and

    materials needed to produce a product

    MRP provides time scheduling information specifying

    when each of the materials, parts, and components should

    be ordered or produced

    Dependent demand drives MRP

    MRP is a software system

  • 8/9/2019 POM 16 - MRP

    3/65

    Upendra Kachru OPERATIONS MANAGEMENT

    MATERIAL PLANNING

    Master Production

    Schedule (MPS)

    Material

    Requirements

    Planning (MRP)

    Inventory

    Status

    Records

    Product

    Structure

    Records

    Purchasing Manufacturing

    (what we plan)

    (what we have) (what we require)

    (what we need)

  • 8/9/2019 POM 16 - MRP

    4/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Primary Prerequisites

    For MRP

    1. A Master Production Schedule exists

    and can be stated in bill of materials

    form;

    2. All inventory items are uniquely

    identified;

    3. A bill of material exists at the time of

    planning

    4. Inventory records contain data on the

    status of every item;5. There is integrity of file data.

  • 8/9/2019 POM 16 - MRP

    5/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Master Data

    Material Master

    MRP Group - Group common MRP materials together MRP Type - Planning Method.

    Planning Time Fence - Restricts Activities

    Lot Sizing - Lot Size determination

    Storage Cost Indicators - For Optimum Lot sizing Only

    Ordering Costs

    Assembly Scrap - For Assembly Scrap Only

    Procurement Type - Make or Buy Indicator.

    Safety Stock

  • 8/9/2019 POM 16 - MRP

    6/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Based on a master production

    schedule, a materialrequirements planning system:

    Creates schedules identifying the

    specific parts and materials

    required to produce end items

    Determines exact unit numbersneeded

    Determines the dates when orders

    for those materials should be

    released, based on lead times

    Material

    Requirements

    Planning System

  • 8/9/2019 POM 16 - MRP

    7/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Primary MRP Reports

    Planned ordersto be released at a future time

    Order release noticesto execute the planned orders

    Changes in due datesof open orders due to rescheduling

    Cancellations or suspensionsof open orders due to

    cancellation or suspension of orders on the masterproduction schedule

    I nventory status data

  • 8/9/2019 POM 16 - MRP

    8/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Secondary MRP Reports

    Planning reports, for example, forecasting inventoryrequirements over a period of time

    Performance reportsused to determine agreement

    between actual and programmed usage and costs

    Exception reportsused to point out seriousdiscrepancies, such as late or overdue orders

  • 8/9/2019 POM 16 - MRP

    9/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Scheduling

    Procurement type

    Lot-size calculation

    Net Requirements Calculation

    BOM Explosion: Determinethe valid BOM for explosion

    Overview : BOM ExplosionBill of Materials

  • 8/9/2019 POM 16 - MRP

    10/65

    Upendra Kachru OPERATIONS MANAGEMENT

    The bill of materials is a materials list that provides informationuseful to reconstruct the manufacturing process.

    It is the master product definition that contains as-designed

    information.

    The information includes product description:

    Materials

    Parts

    Components

    Production sequence

    Bill of Materials

    A T pical Engineering Bill of Materials

  • 8/9/2019 POM 16 - MRP

    11/65

    Upendra Kachru OPERATIONS MANAGEMENT

    A Typical Engineering Bill of Materials

    Level Part- Revision Quantity Description Make/buy

    1 16844-23003 B 1 Adapter Make

    16844-23004 J 1 Control Unit Buy

    16844-23010 C 3 Moisture

    Tester

    Make

    16844-23023 B 2 Enclosure Buy

    16844-23024 B 1 Enclosure Buy

    16844-23025 D 2 Machine

    Screw

    Buy

    16844-23033 F 3 Cover Buy

    16844-23030 AA 4 Precipitatory

    Assy.

    Make

    16844-23040 E 5 Element Buy

    16844-23043 E 6 Housing Buy

    16844-23048 D 4 Machine Buy

    16844-23049 G 3 Precipitator Buy

  • 8/9/2019 POM 16 - MRP

    12/65

    Upendra Kachru OPERATIONS MANAGEMENT 12

    The bill of material file provides

    complete information on:

    Raw materials in stock

    Semi finished component parts in

    stock

    Finished component parts in stock

    Sub-assemblies in stock

    Component parts in processSub-assemblies in process

    BOM File

  • 8/9/2019 POM 16 - MRP

    13/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Each inventory item is carried as a

    separate file

    The bill of materials pegs materials i.e.lists components of each assembly and

    subassembly linking of individual item

    bills which from the product, resulting

    in a hierarchical, and pyramid like

    structure with different levels.

    It Identifies each parent item that

    created demand

    Bill Of Materials

    (BOM) File:

  • 8/9/2019 POM 16 - MRP

    14/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Typical Product Structure

    F G

    ZNHA

    P

    B I XR Q X

    Q R SX

    D

    E

    Parent

    Level 1

    Level 2

    Level 3

    The bill of material file guides the explosion process.

    O S i

  • 8/9/2019 POM 16 - MRP

    15/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Planned orderPriority

    1

    2

    Usage

    Production

    Engineering

    BOM Selec t ion ID

    Production

    BOM

    Costing

    BOMEngineering

    BOM

    Used if no valid production

    BOM exists

    BOM Selection

  • 8/9/2019 POM 16 - MRP

    16/65

    Upendra Kachru OPERATIONS MANAGEMENT

    It is an artificial grouping of items

    in bill of materials format, which

    expresses the relationship of

    multiple product features, variantsand options, where inventory

    items are arranged in terms of

    product modules each of which

    can be planned as a group.

    Modular Bill of

    Materials

    Modular bill kept for each major

    subassembly

    Simplifies forecasting and planning

  • 8/9/2019 POM 16 - MRP

    17/65

    Upendra Kachru OPERATIONS MANAGEMENT

    4-Cylinder (.40) Bright red (.10) Leather (.20) Grey (.10) Sports coupe (.20)6-Cylinder (.50) White linen (.10) Tweed (.40) Light blue (.10) Two-door (.20)

    8-Cylinder (.10) Sulphur yellow (.10) Plush (.40) Rose (.10) Four-door (.30)

    Neon orange (.10) Off-white (.20) Station wagon (.30)

    Metallic blue (.10) Cool green (.10)

    Emerald green (.10) Black (.20)

    Jet black (.20) Brown (.10)

    Champagne (.20) B/W checked (.10)

    X10Automobile

    Engines Exterior color Interior Interior color Body(1 of 3) (1 of 8) (1 of 3) (1 of 8) (1 of 4)

    Modular BOM

    Combinations = 3 x 8 x 3 x 8 x 4 = 2,304 configurations

    Combinations = 3 + 8 + 3 + 8 + 4 = 26 modular bills

  • 8/9/2019 POM 16 - MRP

    18/65

    Upendra Kachru OPERATIONS MANAGEMENT

    There are two somewhat different

    objectives, in modularization.

    To disentangle combination of

    optimal product features.

    To segregate common from unique,

    or peculiar parts.

    The first is required to facilitate

    forecasting.

    The second is aimed at minimizing

    inventories in components that are

    common to option alternatives

    Objectives ofModularization

  • 8/9/2019 POM 16 - MRP

    19/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Net Requirements

    Calculation

    Net Requirements Calculation

  • 8/9/2019 POM 16 - MRP

    20/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Assumptions1. Individual item lead times are known;

    2. Every inventory item goes into and outof stock

    3. All of the components of an assembly

    are needed at the time of release of

    assembly orders;

    4. There is discrete disbursement and

    usage of component materials

    5. Process independence of manufactured

    items is ensured.

  • 8/9/2019 POM 16 - MRP

    21/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Net Requirements Calculation

    MRP will compare the requirement and supply to get a

    shortage gap. A comparison is made betweenstore/warehouse stock and the appropriate receipts and

    issue.

    1. Determine Available Store/Warehouse Stock

    2. Determine Planned Receipts (afterconsidering existing issues andreceipts)

    3. Calculate the Shortage Quantity

  • 8/9/2019 POM 16 - MRP

    22/65

    Upendra Kachru OPERATIONS MANAGEMENT

    MRP: Net Requirements Calculation

    ShortageShortage

    SalesSales OrdersOrders

    Planned Ind ReqmtsPlanned Ind Reqmts

    Dependent ReqmtsDependent Reqmts

    ReservationsReservations

    Planned Orders

    Production Orders

    Purchase Requisitions

    Purchase orders

    Warehouse Stock

    Lot Size

    SafetySafety

    StockStock

    CompareCompare

    DemandSupply

    Matching Demand and Supply

    H th Pl i R W k

  • 8/9/2019 POM 16 - MRP

    23/65

    Upendra Kachru OPERATIONS MANAGEMENT

    How the Planning Run Works

    Reorder Point Planning

    When Available Stock falls below reorder level, planned orders are

    generated in the planning run to order up to reorder level. Safety Stock

    requirement is just for information

    Available Stock = Plant Stock + Receipts

    Forecast Based Planning

    System only considers forecast requirements (any other requirements are not

    considered). Planned orders are proposed when available stock is less than

    forecast requirements.

    Available Stock = Plant stock - Safety Stock + Receipts - Forecast Requirements

    In the net requirements calculation, a difference is made between

    reorder point planning, forecast-based planning, and MRP. In each

    procedure, the system calculates available stock differently.

    BOM E l i

  • 8/9/2019 POM 16 - MRP

    24/65

    Upendra Kachru OPERATIONS MANAGEMENT

    /dates

    Target

    Change status

    Component selection

    Dependent reqmts

    quantities and dates

    Usage

    Lot size

    Explosion date

    Items relevant to production

    BOM Explosion

    Usage quantity

    BOM E l i S l ti b O d St t

  • 8/9/2019 POM 16 - MRP

    25/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Time

    BOM 1 BOM 2 BOM 3

    Valid from(relevant to

    planning from )

    Valid from(relevant to

    planning from )

    Valid from(relevant to

    planning from )

    Order 1 Order 2

    Order startOrder start

    BOM Explosion: Selection by Order Start

    Explosion: Using the Order Finish Date

  • 8/9/2019 POM 16 - MRP

    26/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Time

    BOM 1 BOM 2 BOM 3

    Valid from

    (relevant to

    planning from )

    Valid from(relevant to

    planning from )

    Valid from

    (relevant to

    planning from )

    Order 1 Order 2

    Order finishOrder finish

    Explosion: Using the Order Finish Date

    Safety Stock

    dli S f S k

  • 8/9/2019 POM 16 - MRP

    27/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Reqmt Receipt

    Stock

    TimeSafety stock

    (not available

    for planning)

    Available

    quantity

    for planning

    Safety s tock : To be set in mater ialmaster

    y

    Handling Safety Stock

  • 8/9/2019 POM 16 - MRP

    28/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Planning Time Fence

    Plan is protected from changes within the planning time fence.

    End date of time fence determined from planning date.You can configure system as to how you want the orders to react

    within the time fence.

  • 8/9/2019 POM 16 - MRP

    29/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Planning Time Fence

    Outside the time fence, system creates order proposal as usual.

    When new orders move into the time fence, they may be firmedautomatically depending on how the system is configured.

    Firming Types for MRP Planned Materials :

    Firming TypesOrders Moving IntoTimeFence

    New OrderProposals Creation

    New OrderStatus

    Type 1 Firmed Outside Time Fence Not Firmed

    Type 2 Firmed No Orders Created NA

    Type 3 Not Firmed Outside Time Fence Not Firmed

    Type 4 Not Firmed No Orders Created NA

    L t Si C l l ti d S h d li:

  • 8/9/2019 POM 16 - MRP

    30/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Scheduling

    Procurement type

    Lot- size calculation

    Lot Size Calculations and Scheduling

    Overview of Lot- Sizing ProceduresD fi iti i

  • 8/9/2019 POM 16 - MRP

    31/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Static

    procedures

    Static

    procedures

    Lot- for-lot order quantity

    EOQ

    Fixed lot size

    Period

    procedures

    Other

    procedures

    Optimal Lot sizing

    Lot-Lot- sizing proceduressizing procedures

    Entered in

    Material master

    Definition in

    Customizing

    Determining the Lot Size

  • 8/9/2019 POM 16 - MRP

    32/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Lot Sizing in MRP Programs

    Lot-for-lot (L4L) Economic order quantity (EOQ)

    Least total cost (LTC)

    Least unit cost (LUC)

    Which one to use? The one that is least costly!

    Optimum Lot- Sizing Procedures

  • 8/9/2019 POM 16 - MRP

    33/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Many deliveries /

    High order costs

    Minimal stockkeeping/

    Minimal storage costs

    Few deliveries /

    Low order costs

    More extensive stockkeeping/Higher storage costs

    Optimum Lot Sizing Procedures

    Procurement Types

  • 8/9/2019 POM 16 - MRP

    34/65

    Upendra Kachru OPERATIONS MANAGEMENT

    External procurementStockStock transfertransfer

    Procurement TypesProcurement Types

    In-In- househouse

    productionproduction

    SubcontractingSubcontracting VendorProductionProduction inin

    ownown plantplantProductionProduction inin

    anotheranother plantplant

    Reservation inReservation in

    anotheranother plantplantComponentsComponentsComponents

    Procurement typesSpecial procurement types

    yp

    Backward Scheduling

  • 8/9/2019 POM 16 - MRP

    35/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Planned orderPlanned order

    Availability

    date

    Opening

    date

    Order start

    date

    Order finish

    date

    Tim

    Goods receipt

    processing timeIn-house production time

    Opening period

    Schedul ing margin

    key (MRP 2)

    Lot - s ize dependen t : MRP 2

    Lo t- s ize i ndependen t : wo rk schedu li ngMRP 2

    Scheduling

  • 8/9/2019 POM 16 - MRP

    36/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Scheduling

    The following times are taken into account :

    Processing time required by purchasing department (workdays)

    Planned delivery time of the material (calendar days)

    Goods receipt processing time (workdays)

    These times will be used to determine the release date of the

    planned order or purchase requisition.

  • 8/9/2019 POM 16 - MRP

    37/65

    Upendra Kachru OPERATIONS MANAGEMENT

    MRP Example

    A(2) B(1)

    D(5)C(2)

    X

    C(3)

    Item On-Hand Lead Time (Weeks)

    X 50 2

    A 75 3

    B 25 1

    C 10 2

    D 20 2

    Requirements include 95 units (80 firm orders and 15 forecast) of X in

    week 10

    Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95

    LT=2 Scheduled receipts

  • 8/9/2019 POM 16 - MRP

    38/65

    Upendra Kachru OPERATIONS MANAGEMENT

    A(2)

    X

    p

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75On- Net requirements 15

    hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receipts

    Proj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20

    hand Planned order receipt 20

    25 Planner order release 20C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40

    hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    It takes 2

    As foreach X

    Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95

    LT=2 Scheduled receipts

  • 8/9/2019 POM 16 - MRP

    39/65

    Upendra Kachru OPERATIONS MANAGEMENT

    p

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75On- Net requirements 15

    hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receipts

    Proj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20

    hand Planned order receipt 20

    25 Planner order release 20C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40

    hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    B(1)A(2)

    X

    It takes 1

    B foreach X

    Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95

    LT=2 Scheduled receipts

  • 8/9/2019 POM 16 - MRP

    40/65

    Upendra Kachru OPERATIONS MANAGEMENT

    A(2) B(1)

    X

    C(3)

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75On- Net requirements 15

    hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receipts

    Proj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20

    hand Planned order receipt 20

    25 Planner order release 20C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40

    hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    It takes 3

    Cs for

    each A

    Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95

    LT=2 Scheduled receipts

  • 8/9/2019 POM 16 - MRP

    41/65

    Upendra Kachru OPERATIONS MANAGEMENT

    A(2) B(1)

    C(2)

    X

    C(3)

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75On- Net requirements 15

    hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receipts

    Proj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20

    hand Planned order receipt 20

    25 Planner order release 20C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40

    hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    It takes 2

    Cs for

    each B

    Day: 1 2 3 4 5 6 7 8 9 10X Gross requirements 95

    LT=2 Scheduled receipts

  • 8/9/2019 POM 16 - MRP

    42/65

    Upendra Kachru OPERATIONS MANAGEMENT

    A(2) B(1)

    D(5)

    C(2)

    X

    C(3)

    Proj. avail. balance 50 50 50 50 50 50 50 50 50 50

    On- Net requirements 45

    hand Planned order receipt 45

    50 Planner order release 45

    A Gross requirements 90

    LT=3 Scheduled receipts

    Proj. avail. balance 75 75 75 75 75 75 75 75On- Net requirements 15

    hand Planned order receipt 15

    75 Planner order release 15

    B Gross requirements 45

    LT=1 Scheduled receipts

    Proj. avail. balance 25 25 25 25 25 25 25 25

    On- Net requirements 20

    hand Planned order receipt 20

    25 Planner order release 20C Gross requirements 45 40

    LT=2 Scheduled receipts

    Proj. avail. balance 10 10 10 10 10

    On- Net requirements 35 40

    hand Planned order receipt 35 40

    10 Planner order release 35 40

    D Gross requirements 100

    LT=2 Scheduled receipts

    Proj. avail. balance 20 20 20 20 20 20 20On- Net requirements 80

    hand Planned order receipt 80

    20 Planner order release 80

    It takes 5 Ds

    for each B

    MRP Cl d L S t

    18-4

  • 8/9/2019 POM 16 - MRP

    43/65

    Upendra Kachru OPERATIONS MANAGEMENT

    MRP - Closed Loop System

    Production Planning

    Master Production Scheduling

    Material Requirements Planning

    Capacity Requirements Planning

    Realistic?No

    Feedback

    Execute:

    Capacity PlansMaterial Plans

    Yes

    Feedback

  • 8/9/2019 POM 16 - MRP

    44/65

    Upendra Kachru OPERATIONS MANAGEMENT

    MRP Scheduling Terminology

    Gross Requirements

    Scheduled receipts

    Projected available balance

    Net requirements

    Planned order receipt

    Planned order release

    Forward Scheduling

  • 8/9/2019 POM 16 - MRP

    45/65

    Upendra Kachru OPERATIONS MANAGEMENT

    AvailabilitydateOrder startdate Order finishdate

    Time

    Goods receipt

    processing timeIn-house production time

    Today

    Planned orderPlanned order

    Au tomatic, i f order start date is in th e

    past dur ing backward schedul ing

  • 8/9/2019 POM 16 - MRP

    46/65

    What is ERP?

  • 8/9/2019 POM 16 - MRP

    47/65

    Upendra Kachru OPERATIONS MANAGEMENT

    What is ERP? Enterprise Resource Planning

    It attempts to integrate all data and processes of an organization intoa unified system. A typical ERP system will use multiplecomponents of computer software and hardware to achieve theintegration. A key ingredient of most ERP systems is the use of aunified database to store data for the various system modules.

    E ol tion of ERP

  • 8/9/2019 POM 16 - MRP

    48/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Evolution of ERP

    1960s: software packages with inventory control

    1970s: MRP systems

    Production schedule with materials management

    1980s: MRPII systems

    Adds financial accounting system

    1990s: MRPII Integrated systems for manufacturing execution

    Late 1990s: ERP

    Integrated manufacturing with supply chain

    2000s: ERP II

    ERP Definition

  • 8/9/2019 POM 16 - MRP

    49/65

    Upendra Kachru OPERATIONS MANAGEMENT

    ERP - Definition

    ERP is a process of managing all resources and their use in the entire

    enterprise in a coordinated manner

    ERP is a set of integrated business applications, or modules which carry out

    common business functions such as general ledger, accounting, or order

    management

    Put simply, ERP systems tie together varied processes using data

    from across the company. For instance, a typical ERP system

    manages functions and activities as different as the bills of materials,

    order entry, purchasing, accounts payable, human resources, and

    inventory control, to name just a few of the modules.

    Problems of Legacy Systems

  • 8/9/2019 POM 16 - MRP

    50/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Problems of Legacy Systems Automates existing processes

    Normally not driven by organization strategy and business vision. Develop one application at a time. No integration between applicationsjust

    transaction passing.

    Decentralized applications.

    Are relatively inflexible to accommodate changes in the business environment.

    Written in language / platform prevalent at the time of development. Up gradation to latest technology is difficult

    Usually not well documented.

    Maintenance is a problemlargely because of poor documentation and staffattrition.

    What makes ERP different

  • 8/9/2019 POM 16 - MRP

    51/65

    Upendra Kachru OPERATIONS MANAGEMENT

    What makes ERP different

    Supports business through optimizing, maintaining,and tracking business functions

    Integrated modules

    Common definitions

    Common database

    Update one module, automatically updates others ERP systems reflect a specific way of doing business

    Must look at your value chains, rather than functions

    Process View of Business

  • 8/9/2019 POM 16 - MRP

    52/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Sales

    F

    unction

    Ac

    counting

    F

    unction

    Pu

    rchasing

    F

    unction

    Production

    F

    unction

    Logistics

    F

    unction

    Material Order Process

    Customer Order Process

    The basic ERP Model is based on a process view of the organization. Each of the tasks

    may cross functional boundaries

    ERP Structure

  • 8/9/2019 POM 16 - MRP

    53/65

    Upendra Kachru OPERATIONS MANAGEMENT

    The foundation of ERP systems is popularly called the Stool. The stool is made up of three

    basic elements Market Sales and Distribution, the Product Materials Management and

    Production and the Financial Accounting and Control.

  • 8/9/2019 POM 16 - MRP

    54/65

    Financials

  • 8/9/2019 POM 16 - MRP

    55/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Financials

    Financial and management accounting

    Internal Controlling and Audit

    Financial Supply Chain Management

    General Ledger

    Financial Reporting Costing

    Budgeting

    Accounts Payable

    Accounts receivables

    Human Capital Management

  • 8/9/2019 POM 16 - MRP

    56/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Human Capital Management

    Recruiting

    Applicant data administration Compensation

    Assessment

    Development and Training

    Personnel development planning

    Payroll Benefits administration

    Workforce planning

    Schedule & shift planning

    Time management Travel expense accounting

    Marketing & Sales Management

  • 8/9/2019 POM 16 - MRP

    57/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Marketing & Sales Management

    Lead tracking

    Sales forecasting

    Order management

    Customer management

    Customer service

  • 8/9/2019 POM 16 - MRP

    58/65

    Example of How ERP Works

  • 8/9/2019 POM 16 - MRP

    59/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Example of How ERP Works

    Step 1 : Brazilian retailer orders, via the Internet, 1,000 shoes

    from International Shoe Co. A sales rep takes the order, routes it

    to ERPs ordering module, ERP checks the retailer credit, price,etc. The order is approved.

    Step 2 : Simultaneously ERPs inventory module checks the

    stocks and notifies the rep that half the order can be filled

    immediately from stock. The other half will be manufacturedand delivered in 5 days directly from the factory in Taiwan.

    ERP delivers a single database that contains all data for the software

    modules across an entire company. People in different departments all seethe same information and can update it. For example:

    Example of How ERP Work

  • 8/9/2019 POM 16 - MRP

    60/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Step 3 : ERPs manufacturing module schedules the production in

    Taiwan and instructs the warehouse (in China) to ship the shoes to

    Brazil and print up an invoice (in Portuguese).

    Step 4 : ERPs human resources module calculates labor

    requirements. Due to a shortage, the personnel manager in Taiwan

    is instructed to get temporary workers. Step 5 : ERPs material planning module notifies the purchasing

    manager about a shortage of purple dye. A purchase order is

    automatically issued.

    Example of How ERP Work

  • 8/9/2019 POM 16 - MRP

    61/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Example of How ERP Work

    Step 6 : The customer logs on via the extranet to thecompanys sneakers division. He can see that 500 shoes were

    shipped from the regional warehouse. This is done with ERP

    tracing capabilities.

    Step 7 : Based on data from ERPs forecasting and financial

    modules, the CEO can determine both demand and

    profitability per product. The financial module also converts

    all foreign money to $U.S., whenever needed

    Benefits of ERP

  • 8/9/2019 POM 16 - MRP

    62/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Benefits of ERP

    Desire to standardize and improve processes

    To improve the level of systems integration

    To improve information quality

    Common set of data

    Help in integrating applications for decision making and

    planning

    Allow departments to talk to each other

    Easy to integrate by using processed built into ERP software

    A way to force BPR (reengineering)

    Difficulty in implementation

  • 8/9/2019 POM 16 - MRP

    63/65

    Upendra Kachru OPERATIONS MANAGEMENT

    y p

    Very difficult

    Extremely costly and time intensive

    Typical: over $10,000,000 and over a year to implement

    Company may implement only certain modules of entire

    ERP system

    You will need an outside consultant

    Common Pitfalls

  • 8/9/2019 POM 16 - MRP

    64/65

    Upendra Kachru OPERATIONS MANAGEMENT

    Do not adequately benchmark current state

    Did not plan for major transformation

    Did not have executive sponsorship

    Did not adequately map out goals and objectives

    Highly customized systems to look like old MRP systems

  • 8/9/2019 POM 16 - MRP

    65/65

    Upendra Kachru OPERATIONS MANAGEMENT

    C l i c k t o e d i t c o m p a n y s l o g a n .


Recommended